Moore Construction Co. v. Story Engineering ( 1998 )


Menu:
  •        IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    FILED
    MOORE CONSTRUCTION COMPANY, )                     July 10, 1998
    INC., and PAUL W. MOORE,     )
    )                 Cecil W. Crowson
    Plaintiffs/Appellants, )                Appellate Court Clerk
    )           Montgomery Circuit
    )           No. C9-31
    VS.                          )
    )
    )           Appeal No.
    STORY ENGINEERING COMPANY,   )           01A01-9606-CV-00267
    INC., and RODDY L. STORY,    )
    )
    Defendants/Appellees.  )
    APPEAL FROM THE CIRCUIT COURT
    FOR MONTGOMERY COUNTY
    AT CLARKSVILLE, TENNESSEE
    THE HONORABLE JAMES E. WALTON, JUDGE
    For Plaintiffs/Appellants:               For Defendants/Appellees:
    Thomas N. Bateman                        John T. Horton
    Robert T. Bateman                        Brewer, Krause, Brooks & Mills
    Bateman, Bateman & Darnell               Nashville, Tennessee
    Clarksville, Tennessee
    AFFIRMED AND REMANDED
    WILLIAM C. KOCH, JR., JUDGE
    OPINION
    This appeal stems from a construction contract to improve the natural gas
    transmission system in the City of Clarksville. After the City awarded the contract,
    an unsuccessful bidder sued the project engineer in the Circuit Court for Montgomery
    County, claiming interference with prospective economic advantage, defamation, and
    disparagement. The trial court granted the project engineer’s motion for summary
    judgment, and the unsuccessful bidder has appealed to this court.            We have
    determined that the summary judgment was appropriate because Tennessee does not
    recognize the tort of interference with prospective economic advantage and because
    the project engineer’s statements concerning the unsuccessful bidder were true.
    I.
    In the early 1990's, the City of Clarksville hired Story Engineering Co., Inc. to
    perform a feasibility study concerning the capacity of its natural gas transmission
    system. Roddy L. Story, the principal of Story Engineering who was to perform the
    work, is a Vanderbilt-trained engineer who had been employed by Nashville Gas
    Company for thirty-two years. Mr. Story had assisted with the design of Clarksville’s
    existing system in the 1950's.
    After Mr. Story reported that Clarksville’s system was no longer adequate to
    meet the expected demand in the case of severe weather, the City retained him as
    project engineer to design the improvements and to prepare the plans and
    specifications and other contract documents for the project. The project Mr. Story
    designed called for the installation of 116,900 linear feet of 12¾-inch O.D. coated
    steel natural gas pipe with fittings, 600 linear feet of 6e-inch O.D. coated steel gas
    pipe, and various regulator stations, bridge crossings, tie-ins, and related
    appurtenances.
    Because the quality of the workmanship on the project was extremely
    important, Mr. Story included in the specifications and contract documents a
    requirement that the successful bidder must have constructed a similar natural gas
    -2-
    transmission pipeline project within three years preceding the date of the Clarksville
    project.1 Moore Construction Company, Inc. was one of the nine companies
    submitting bids on the project. Mr. Story requested Moore Construction Company
    to provide additional information because its original bid did not contain sufficient
    information about its prior jobs or the personnel who would perform the work.
    Moore Construction Company’s supplemental information revealed that the last gas
    pipeline it had constructed was in 1984 in Louisiana.
    After evaluating the bids, Mr. Story informed the City that King Pipeline and
    Utility Company, Inc. had submitted the lowest bid of $3,398,808 and that it had
    recently completed four similar projects. He also informed the City that Moore
    Construction Company had submitted the second lowest bid of $3,432,378 but that
    it had not completed a similar project within the past three years.                          Moore
    Construction Company appeared at a meeting of the Clarksville Utility Committee
    shortly after the bids were opened and requested that it be awarded the contract in
    accordance with the City’s procurement rule that favors local contractors when there
    is less than a five percent difference between their bid and the lowest bid. The
    committee declined to recommend Moore Construction Company because it did not
    meet the specification’s qualifications for performing the work. When the matter
    came before the Clarksville City Council, Mr. Story informed the council members
    that Moore Construction Company was “not qualified to construct the project and that
    the City of Clarksville, Tennessee, and its individual council members . . . would
    expose itself and themselves to liability should it award the contract to [Moore
    1
    The Specifications and Contract Documents stated:
    The Owner will require as minimum qualification for Bidder to have successfully
    completed within the last thirty-six months the installation of a natural gas
    transmission pipeline and regulator station system similar in size and complexity to
    this Project. Bidder must have previous experience in welding on high pressure gas
    lines, hydrostatic pressure testing, and filling of pipelines with high pressure natural
    gas.
    -3-
    Construction Company] . . . instead of following [his] recommendation . . ..” 2
    Thereafter, the City Council awarded the contract to King Pipeline.
    In November 1992, Moore Construction Company and its president filed suit
    against Mr. Story and Story Engineering in the Circuit Court for Montgomery County
    alleging that Mr. Story’s statements to the City Council had defamed and disparaged
    them and had interfered with their prospective economic advantage. They requested
    $300,000 in actual and $600,000 in punitive damages. Mr. Story later moved for
    summary judgment. The trial court granted the motion and dismissed each of Moore
    Construction Company’s claims on the ground that Mr. Story’s statements to the City
    Council concerning Moore Construction Company’s qualifications under the
    project’s specifications were true.
    II.
    Summary judgments enjoy no presumption of correctness on appeal. See City
    of Tullahoma v. Bedford County, 
    938 S.W.2d 408
    , 412 (Tenn. 1997); McClung v.
    Delta Square Ltd. Partnership, 
    937 S.W.2d 891
    , 894 (Tenn. 1996). Accordingly,
    reviewing courts must make a fresh determination concerning whether the
    requirements of Tenn. R. Civ. P. 56 have been satisfied. See Hunter v. Brown, 
    955 S.W.2d 49
    , 50-51 (Tenn. 1997); Mason v. Seaton, 
    942 S.W.2d 470
    , 472 (Tenn. 1997).
    Summary judgments are appropriate only when there are no genuine factual disputes
    with regard to the claim or defense embodied in the motion and when the moving
    party is entitled to a judgment as a matter of law. See Tenn. R. Civ. P. 56.04; Bain
    v. Wells, 
    936 S.W.2d 618
    , 622 (Tenn. 1997); Carvell v. Bottoms, 
    900 S.W.2d 23
    , 26
    (Tenn. 1995).
    Courts reviewing summary judgments must view the evidence in the light most
    favorable to the nonmoving party and must also draw all reasonable inferences in the
    nonmoving party’s favor. See Robinson v. Omer, 
    952 S.W.2d 423
    , 426 (Tenn. 1997);
    2
    The City Council’s resolution awarding the contract to King Pipeline recited that
    There was extended discussion regarding the option of awarding the contract to
    Moore Construction Co., a local contractor and the second low bidder, under the 5%
    provision. Mr. Story stated that in accordance with the bid specifications, it was his
    opinion that Moore Construction Co. was not qualified because this company had not
    completed a project of this magnitude within the past 36 months as specified in the
    bid documents.”
    -4-
    Mike v. Po Group, Inc., 
    937 S.W.2d 790
    , 792 (Tenn. 1996). Thus, a summary
    judgment should be granted only when the undisputed facts reasonably support one
    conclusion -- that the moving party is entitled to a judgment as a matter of law. See
    McCall v. Wilder, 
    913 S.W.2d 150
    , 153 (Tenn. 1995); Carvell v. Bottoms, 900
    S.W.2d at 26. A party may obtain a summary judgment by demonstrating that the
    nonmoving party will be unable to prove an essential element of its case, see Byrd v.
    Hall, 
    847 S.W.2d 208
    , 212-13 (Tenn. 1993), because the inability to prove an
    essential element of a claim necessarily renders all other facts immaterial. See
    Alexander v. Memphis Individual Practice Ass’n, 
    870 S.W.2d 278
    , 280 (Tenn. 1993);
    Strauss v. Wyatt, Tarrant, Combs, Gilbert & Milom, 
    911 S.W.2d 727
    , 729 (Tenn. Ct.
    App. 1995).
    III.
    Moore Construction Company asserts that Mr. Story was not entitled to a
    summary dismissal of his three claims because of material factual disputes that render
    a summary judgment inappropriate. It claims that the record contains disputed facts
    regarding its ability to construct the pipeline according to the project specifications
    and the City Council’s potential liability for awarding the contract to a contractor
    who did not meet the bid requirements. We have determined that these issues, to the
    extent that they are factual, are not material to the disposition of this case and that Mr.
    Story is entitled to a judgment dismissing each of Moore Construction’s claims as a
    matter of law.
    A.
    The status of the tort of intentional interference with prospective economic
    advantage was not settled when Moore Construction Company first filed its
    complaint against Mr. Story. However, the Tennessee Supreme Court put this issue
    to rest in 1997 when it held that this cause of action would not be recognized in
    Tennessee. See Nelson v. Martin, 
    958 S.W.2d 643
    , 646 (Tenn. 1997). The Court’s
    decision applies to cases pending at the time it was handed down, see Alexander v.
    Inman, 
    825 S.W.2d 102
    , 105 (Tenn. Ct. App. 1991) (applying retroactively the
    Tennessee Supreme Court’s abolition of the common-law tort of alienation of
    -5-
    affections). Thus, we affirm the trial court’s dismissal of this claim because it does
    not exist under Tennessee law.
    B.
    Moore Construction Company asserts that its defamation claim should not have
    been summarily dismissed because the facts, taken in their most favorable light,
    demonstrate that Mr. Story’s statements were false or falsely implied the existence
    of other derogatory facts. Based on the uncontroverted evidence concerning Mr.
    Story’s statements to the City Council, we have determined that Mr. Story’s
    statements were true as a matter of law. Therefore, the trial court correctly summarily
    dismissed this claim because Moore Construction Company failed to demonstrate that
    it would be able to prove an essential element of its defamation claim at trial.
    The basis of a defamation action, whether it be libel or slander, is that the
    defamatory statement has injured a person’s character or reputation. See Quality Auto
    Parts Co. v. Bluff City Buick Co., 
    876 S.W.2d 818
    , 820 (Tenn. 1994). The Tennessee
    Supreme Court, adopting Restatement (Second) of Torts § 580B (1977), defined the
    tort as follows:
    One who publishes a false and defamatory communication
    concerning a private person, or concerning a public official
    or public figure in relation to a purely private matter not
    affecting his conduct, fitness or role in his public capacity,
    is subject to liability, if, but only if, he
    (a) knows that the statement is false and that it defames the
    other,
    (b) acts in reckless disregard of these matters, or
    (c) acts negligently in failing to ascertain them.
    Press, Inc. v. Verran, 
    569 S.W.2d 435
    , 442 (Tenn. 1978). Under this formulation,
    statements that are factually true cannot provide a basis for a defamation action. See
    Stones River Motors, Inc. v. Mid-South Publishing Co., 
    651 S.W.2d 713
    , 719 (Tenn.
    Ct. App. 1983).
    Mr. Story’s statements that Moore Construction Company did not satisfy the
    qualifications for bidding on this project were based on information that Moore
    Construction Company itself provided. There is no dispute that Moore Construction
    Company had not undertaken to build a natural gas transmission pipeline during the
    thirty-six months prior to bidding on this project. Mr. Story’s appraisal of whether
    -6-
    Moore Construction Company qualified as a bidder on this project cast no reflection
    on the company’s competence as a contractor, but rather reflected the undisputed fact
    that the company did not satisfy the prior experience requirement in the specifications
    for this project.
    Moore Construction also asserts that Mr. Story’s warning about the City
    Council’s exposure to liability is false and defamatory. This statement, which is little
    more than an expression of legal opinion by a lay person, is also correct. Local
    governmental officials are not immune from suit for willful or wanton acts or acts
    amounting to gross negligence. See Tenn. Code Ann. § 29-20-201(b)(2) (Supp.
    1997). Because it was undisputed that Moore Construction Company did not meet
    the qualifications to bid, Mr. Story’s caution about the consequences of awarding a
    contract to construct a natural gas pipeline to a contractor who did not meet the
    qualifications to bid was neither inappropriate nor defamatory.
    C.
    Moore Construction Company’s final claim is for disparagement. Even though
    Tennessee courts have not specifically recognized this tort, it is among the classes of
    torts recognized in the Restatement (Second) of Torts § 623(A) (1977) which
    provides:
    One who publishes a false statement harmful to the
    interests of another is subject to liability for pecuniary loss
    resulting to the other if
    (a) he intends for publication of the statement to result in
    harm to interests of the other having a pecuniary value, or
    either recognizes or should recognize that it is likely to do
    so, and
    (b) he knows that the statement is false or acts in reckless
    disregard of its truth or falsity.
    This case does not provide an appropriate vehicle for explicitly recognizing
    disparagement as a separate tort because Moore Construction Company has been
    unable to demonstrate that it will be able to prove an essential ingredient of the cause
    of action.
    Like a claim for defamation, a claim for disparagement must be based on a
    false statement. We have already determined that Mr. Story’s statements concerning
    -7-
    Moore Construction Company’s inability to qualify as a bidder under the project’s
    specifications and his caution of the possible consequences of awarding the bid to a
    non-responsive bidder were true and correct. Accordingly, these statements, as a
    matter of law, cannot support a cause of action for disparagement.
    IV.
    We affirm the summary judgment and remand the case to the trial court for
    whatever further proceedings may be required. We tax the costs of this appeal,
    jointly and severally, to Moore Construction Company and Paul W. Moore and their
    surety for which execution, if necessary, may issue.
    ______________________________
    WILLIAM C. KOCH, JR., JUDGE
    CONCUR:
    __________________________________
    HENRY F. TODD, PRESIDING JUDGE
    MIDDLE SECTION
    __________________________________
    SAMUEL L. LEWIS, JUDGE
    -8-