Ruffin Buildling Systems, Inc. v. Larry Gene Varner, an individual ( 2004 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    March 24, 2004 Session
    RUFFIN BUILDING SYSTEMS, INC. v. LARRY GENE VARNER, AN
    INDIVIDUAL, ET AL.
    Appeal from the Chancery Court for Sullivan County
    No. 31384(L) Richard E. Ladd, Chancellor
    FILED MAY 21, 2004
    No. E2003-1677-COA-R3-CV
    Larry Gene Varner and Todd Duncan (“Defendants”) contracted with Joel Frazier d/b/a Timberline
    Construction Company (“Timberline”) for construction of a building on Defendants’ property.
    Timberline then contracted with Ruffin Building Systems, Inc. (“Plaintiff”) for Plaintiff to provide
    certain materials for the construction. Defendants paid Timberline, but Timberline never paid
    Plaintiff. Plaintiff sued Defendants on its materialman’s lien. The Trial Court granted Defendants
    summary judgment holding, inter alia, that Plaintiff did not comply with the notice requirements of
    Tenn. Code Ann. § 66-11-115. Plaintiff appeals. We affirm.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed;
    Case Remanded
    D. MICHAEL SWINEY , J., delivered the opinion of the court, in which HERSCHEL P. FRANKS, P.J.,
    E.S., and BEN H. CANTRELL, SP . J., joined.
    L. Eric Ebbert, Kingsport, Tennessee, for the Appellant, Ruffin Building Systems, Inc.
    O. Taylor Pickard, Jr., Kingsport, Tennessee, for the Appellees, Larry Gene Varner and Todd
    Duncan.
    OPINION
    Background
    The operative facts in this case are undisputed. Defendants contracted with
    Timberline to have Timberline construct a building on property owned by Defendants. Timberline
    then contracted with Plaintiff for Plaintiff to provide certain materials to be used in the building
    project on Defendants’ property. Plaintiff’s and Timberline’s contract provided for payment net 30
    days.
    On December 13, 2000, Plaintiff delivered to Defendants’ property all of the building
    materials required under its contract with Timberline. Defendants made partial payment to
    Timberline pursuant to the agreement between them, but Timberline never paid Plaintiff. Since that
    time, Timberline apparently has filed for bankruptcy. Timberline did not complete the building and
    Defendants hired another company to complete the work. A Notice of Completion was recorded on
    May 18, 2001.
    On March 14, 2001, ninety-one days after its delivery of building materials, Plaintiff
    sent a Notice of Nonpayment to Defendants. Defendants did receive this notice. Plaintiff recorded
    its Notice of Lien on March 16, 2001. Plaintiff then sued Defendants on June 11, 2001 seeking to
    foreclose a materialman’s lien pursuant to Tenn. Code Ann. § 66-11-126(3).
    Plaintiff and Defendants each filed a motion for summary judgment. In its order filed
    April 16, 2003, the Trial Court held, inter alia, that the notice that Plaintiff sent to Defendants on
    March 14, 2001, was timely made and denied both motions for summary judgment. Defendants filed
    a Motion to Reconsider asking the Trial Court to reconsider its ruling on the issue of whether
    Plaintiff gave timely notice under Tenn. Code Ann. § 66-11-115. The Trial Court reconsidered its
    April 16, 2003, order and found, inter alia, that Plaintiff mailed the Notice to Owner on March 14,
    2001, ninety-one days after Plaintiff delivered the materials. The Trial Court entered an order June
    15, 2003, holding, inter alia, that because Plaintiff did not give notice within ninety days of
    Plaintiff’s last delivery of materials, Defendants were entitled to summary judgment as a matter of
    law. Plaintiff appeals to this Court.
    Discussion
    Although not stated exactly as such, Plaintiff raises two issues on appeal: 1) whether
    for purposes of complying with Tenn. Code Ann. § 66-11-115, a materialman’s contract expires on
    the date payment is due rather than upon the last date of delivery of materials; and 2) whether
    Plaintiff timely provided notice to Defendants as required by Tenn. Code Ann. § 66-11-115 by filing
    the complaint and obtaining service on Defendants within ninety days of the completion of the
    project. Defendants raise two additional issues, which we restate as: 1) whether the Trial Court erred
    in refusing to dismiss the case because the oath to the complaint and the attachment bond were
    -2-
    defective and the time to correct these deficiencies expired; and 2) whether the Trial Court erred in
    refusing to grant Defendants summary judgment because no attachment issued after Plaintiff
    corrected the defects in the oath to the complaint and the attachment bond.
    As our Supreme Court has instructed:
    The standards governing an appellate court’s review of a motion for summary
    judgment are well settled. Since our inquiry involves purely a question of law, no
    presumption of correctness attaches to the lower court’s judgment, and our task is
    confined to reviewing the record to determine whether the requirements of Tenn. R.
    Civ. P. 56 have been met. See Hunter v. Brown, 
    955 S.W.2d 49
    , 50-51 (Tenn. 1997);
    Cowden v. Sovran Bank/Central South, 
    816 S.W.2d 741
    , 744 (Tenn. 1991).
    Tennessee Rule of Civil Procedure 56.04 provides that summary judgment is
    appropriate where: (1) there is no genuine issue with regard to the material facts
    relevant to the claim or defense contained in the motion, see Byrd v. Hall, 
    847 S.W.2d 208
    , 210 (Tenn. 1993); and (2) the moving party is entitled to a judgment as
    a matter of law on the undisputed facts. See Anderson v. Standard Register Co., 
    857 S.W.2d 555
    , 559 (Tenn. 1993). The moving party has the burden of proving that its
    motion satisfies these requirements. See Downen v. Allstate Ins. Co., 
    811 S.W.2d 523
    , 524 (Tenn. 1991). When the party seeking summary judgment makes a properly
    supported motion, the burden shifts to the nonmoving party to set forth specific facts
    establishing the existence of disputed, material facts which must be resolved by the
    trier of fact. See Byrd v. Hall, 847 S.W.2d at 215.
    To properly support its motion, the moving party must either affirmatively
    negate an essential element of the non-moving party’s claim or conclusively establish
    an affirmative defense. See McCarley v. West Quality Food Serv., 
    960 S.W.2d 585
    ,
    588 (Tenn. 1998); Robinson v. Omer, 
    952 S.W.2d 423
    , 426 (Tenn. 1997). If the
    moving party fails to negate a claimed basis for the suit, the non-moving party’s
    burden to produce evidence establishing the existence of a genuine issue for trial is
    not triggered and the motion for summary judgment must fail. See McCarley v. West
    Quality Food Serv., 960 S.W.2d at 588; Robinson v. Omer, 952 S.W.2d at 426. If the
    moving party successfully negates a claimed basis for the action, the non-moving
    party may not simply rest upon the pleadings, but must offer proof to establish the
    existence of the essential elements of the claim.
    The standards governing the assessment of evidence in the summary
    judgment context are also well established. Courts must view the evidence in the
    light most favorable to the nonmoving party and must also draw all reasonable
    inferences in the nonmoving party’s favor. See Robinson v. Omer, 952 S.W.2d at
    426; Byrd v. Hall, 847 S.W.2d at 210-11. Courts should grant a summary judgment
    only when both the facts and the inferences to be drawn from the facts permit a
    -3-
    reasonable person to reach only one conclusion. See McCall v. Wilder, 
    913 S.W.2d 150
    , 153 (Tenn. 1995); Carvell v. Bottoms, 
    900 S.W.2d 23
    , 26 (Tenn. 1995).
    Staples v. CBL & Assocs., Inc., 
    15 S.W.3d 83
    , 88-89 (Tenn. 2000) (footnote omitted).
    Both of Plaintiff’s issues deal with whether Plaintiff complied with Tenn. Code Ann.
    § 66-11-115, which provides, in pertinent part:
    Mechanic’s lien - - Notice to owner
    (a) Every journeyman or other person contracted with or employed to work on the
    buildings, fixtures, machinery, or improvements, or to furnish materials for the same,
    whether such journeyman, furnisher, or other person was employed or contracted
    with by the person who originally contracted with the owner of the premises, or by
    an immediate or remote subcontractor acting under contract with the original
    contractor, or any subcontractor, shall have this lien for such work or material;
    provided, that the subcontractor, laborer or materialman satisfies all of the
    requirements set forth in § 66-11-145, if applicable.
    (b) Within ninety (90) days after the demolition and/or building or improvement is
    completed, or the contract of such laborer, mechanic, furnisher, or other person shall
    expire, or such person is discharged, such person shall notify, in writing, the owner
    of the property on which the building is being erected or the improvement is being
    made, or the owner’s agent or attorney, if the owner resides out of the county, that the
    lien is claimed.
    Tenn. Code Ann. § 66-11-115 (2003). To comply with the notice requirement of Tenn. Code Ann.
    § 66-11-115, Plaintiff had to notify Defendants in writing that a lien was claimed within ninety days
    of either the completion of the building, the expiration of Plaintiff’s contract, or Plaintiff’s discharge.
    We begin by addressing whether for purposes of complying with Tenn. Code Ann.
    § 66-11-115 a materialman’s contract expires on the date payment is due or upon the last date of
    delivery of materials. Plaintiff contends it complied with Tenn. Code Ann. § 66-11-115 by providing
    notice within ninety days of the date its contract expired. Plaintiff argues that contrary to the Trial
    Court’s conclusion, Plaintiff’s contract did not expire upon the last date of its delivery of materials.
    Rather, Plaintiff argues that its contract provided for payment net thirty days and, because of this,
    the contract did not expire until the date payment was due thirty days after the delivery of the
    materials. Plaintiff argues that its contract could not expire upon its last delivery of materials
    because Defendants still had uncompleted obligations, i.e., to pay, and that a contract does not expire
    until all obligations are complete or are breached. In support of this argument Plaintiff cites to two
    provisions of the Uniform Commercial Code. Specifically, Plaintiff cites Tenn. Code Ann. § 47-1-
    201, which defines a contract as “the total legal obligation which results from the parties’ agreement
    . . . .” Tenn. Code Ann. § 47-1-201(11) (2003). Plaintiff also cites Tenn. Code Ann. § 47-2-301,
    -4-
    which discusses the obligations of parties to a contract stating “[t]he obligation of the seller is to
    transfer and deliver and that of the buyer is to accept and pay in accordance with the contract.” Tenn.
    Code Ann. § 47-2-301 (2003).
    Plaintiff admits that under Tenn. Code Ann. § 47-2-310, payment is due at the time
    and place at which the buyer receives the goods unless the parties agree otherwise. Tenn. Code Ann.
    § 47-2-310(a) (2003). However, Plaintiff contends that the parties did agree otherwise in this
    situation. However, the parties who agreed otherwise were Timberline and Plaintiff. Defendant was
    not a party to this agreement.
    Plaintiff also argues that if the Legislature intended that the notice had to be provided
    within ninety days of the last date of delivery of materials, it could have specifically stated this rather
    then using the expiration of the contract as the starting date. In support of this contention, Plaintiff
    cites Tenn. Code Ann. § 66-11-145, which states, in pertinent part, “[e]very . . . materialman
    contracted . . . to furnish materials . . . shall provide, within ninety (90) days of the last day of the
    month within which work, services or materials were provided, a notice of nonpayment . . . to the
    owner and contractor . . . .” Tenn. Code Ann. § 66-11-145(a) (2003). Plaintiff argues that since the
    Legislature specifically stated in Tenn. Code Ann. § 66-11-145 that notice shall be provided within
    ninety days of the last day of the month within which materials were provided and did not use the
    same language in Tenn. Code Ann. § 66-11-115, the term “expire” as used in Tenn. Code Ann. § 66-
    11-115 means something other than the last date upon which materials were delivered.
    Further, Plaintiff argues that Bristol Brick Works v. King Coll., an 1896 case, held that
    the contract in that case did not expire upon the date of last delivery of materials but, rather, that the
    agreement between the parties governed the expiration. Bristol Brick Works v. King Coll., 
    41 S.W. 1069
     (Tenn. Ct. Ch. App. 1896). Thus, Plaintiff contends that Bristol Brick Works is controlling
    precedent. Plaintiff, however, has misconstrued the import of Bristol Brick Works. In that case, the
    Court held that “in cases of contract for continuing the source or supply of material to be ordered by
    a contractor the contract is open, and has not expired until the actual completion of the particular
    work contracted for, or for which the materials are to be supplied.” Id. at 1070. Thus, Bristol Brick
    Works dealt with an open contract for a continuing supply of material. The case at hand, however,
    deals with a one-time delivery of materials, not an ongoing business relationship and, therefore, the
    holding in Bristol Brick Works is not dispositive of this issue in this case.
    While Plaintiff’s arguments are well made, we disagree with Plaintiff’s position. It
    has long been the rule in Tennessee that a materialman may claim a lien for materials incorporated
    in an improvement in real property if the materialman fully complies with the statutory requirements.
    E.g., Andrews Distrib. Co. v. Oak Square at Gatlinburg, Inc., 
    757 S.W.2d 663
    , 665 (Tenn. 1988),
    overruled in part on other grounds by Spence v. Allstate Ins. Co., 
    883 S.W.2d 586
    , 596 n.5 (Tenn.
    1994). “Tennessee generally requires strict compliance with its lien statutes. Strict compliance is
    required because ‘[a] materialman’s lien is altogether statutory, and, when the lawmaking body
    prescribes the terms upon which it may be asserted, it is beyond the power of [courts] to waive its
    provisions or substitute others.’” Vulcan Materials Co. v. Gamble Constr. Co., 
    56 S.W.3d 571
    , 573-
    -5-
    74 (Tenn. Ct. App. 2001) (citations omitted; addition in original). In this case, we hold Plaintiff did
    not comply with the statutory notice requirements of Tenn. Code Ann. § 66-11-115 and, thus, is not
    entitled to a lien under that statute.
    Tennessee Code Annotated § 66-11-115 originally was enacted in the 1800's, long
    before the adoption of the Uniform Commercial Code provisions that Plaintiff cites in support of his
    argument. Although there are no Tennessee cases that directly address the question of when a
    contract to supply materials expires, at common law when one furnished material to a building site,
    payment was due at the time of delivery and everyone agreed that the contract expired at that time.
    See e.g., Andrews Distrib. Co., 757 S.W.2d at 665 (construing Tenn. Code Ann. § 66-11-115 and
    stating “the actual issue is whether plaintiff gave notice to the property owner within ninety days of
    the date the last of the material was furnished.” (emphasis in original)); Bird Bros. v. Southern Sur.
    Co., 
    200 S.W. 978
    , 979 (Tenn. 1918) (dealing with a precursor to Tenn. Code Ann. § 66-11-115 and
    stating: “In the case of a furnisher of material he must serve his notice within 30 days after the last
    material is furnished . . . .”); Cole Mfg. Co. v. Falls, 
    22 S.W. 856
    , 857 (Tenn. 1893) (dealing with
    a precursor to Tenn. Code Ann. § 66-11-115 and stating: “Complainant’s contract with Rempe
    expired on . . . the day on which it furnished the last of the materials it was employed to furnish.”
    As this Court stated in Jo Ann Forman, Inc. v. National Council on Comp. Ins., Inc.:
    The legislature is presumed to know the interpretation which courts make of
    its enactments; the fact that the legislature has not expressed disapproval of a judicial
    construction of a statute is persuasive evidence of legislative adoption of the judicial
    construction, especially where the law is amended in other particulars, or where the
    statute is reenacted without change in the part construed.
    Jo Ann Forman, Inc. v. National Council on Comp. Ins., Inc., 
    13 S.W.3d 365
    , 373 (Tenn. Ct. App.
    1999) (quoting Hamby v. McDaniel, 
    559 S.W.2d 774
    , 776 (Tenn. 1977) (citations omitted)).
    Tennessee Code Annotated § 66-11-115 has been revised by our Legislature several times since it
    originally was enacted. As the Legislature is presumed to know the common law interpretation that
    expiration of a contract to supply materials, for purposes of Tenn. Code Ann. § 66-11-115, meant
    expiration upon the last date of delivery of materials, and the Legislature has not amended or revised
    the statute to read otherwise, we can only conclude that the Legislature intended for the term
    “expire”, as used in this statute, to mean upon the last date of delivery of materials.
    We hold that for purposes of complying with Tenn. Code Ann. § 66-11-115, a
    materialman’s contract expires on the last date of delivery of materials rather than on the date
    payment is due. To hold otherwise would result in the potential for continuing liability of an owner
    as the materialman unilaterally could postpone the time for payment or keep extending such time
    indefinitely without the owner’s knowledge. Plaintiff’s brief states “[p]arties can negotiate the
    expiration of the contract to occur after the date of last delivery of the materials.” However, our
    Legislature provided for a specific time period in which mechanic’s liens must be filed and perfected
    and for a specific time period in which to notify the owner of the property. Most certainly, our
    -6-
    Legislature did not intend for these specific time periods to be circumvented by agreements between
    contractors and subcontractors that could result in liability for owners, subsequent purchasers,
    mortgagees, etc. who would be without notice of such agreements. While the Legislature’s adoption
    of the notice of completion after improvements provision contained in Tenn. Code Ann. § 66-11-
    143(a) does provide some protection to a property owner, under Plaintiff’s interpretation, it would
    not prevent a materialman from unilaterally extending its materialman’s lien rights under Tenn. Code
    Ann. § 66-11-115 to some indefinite date short of the deadline created by the filing of a notice of
    completion. More importantly, and as already discussed, the dispositive question is what was the
    Legislature’s intent when it enacted Tenn. Code Ann. § 66-11-115. We believe the clear Legislative
    intent was that the contract “shall expire” on the day of the materialman’s last delivery of material
    to the site, a date certain.
    We turn now to the issue of whether Plaintiff provided timely notice to Defendants
    as required by Tenn. Code Ann. § 66-11-115 by filing the complaint and obtaining service on
    Defendants within ninety days of the completion of the project. Plaintiff admitted during oral
    argument before this Court that this issue and argument were not raised below. As this issue was
    not raised in the Trial Court, it is not properly before us on appeal. We, therefore, decline to address
    this issue or to grant Plaintiff any relief relative to this issue.
    Our determination of Plaintiff’s issues renders Defendants’ issues moot. We,
    therefore, need not address the two additional issues raised by Defendants.
    As there is no genuine issue with regard to the material facts relevant to Defendants’
    defense that Plaintiff failed to provide timely notice pursuant to Tenn. Code Ann. § 66-11-115, and
    as Defendants are entitled to a judgment as a matter of law on the undisputed facts, we affirm the
    grant of summary judgment to Defendants.
    Conclusion
    The judgment of the Trial Court is affirmed, and this cause is remanded to the Trial
    Court for collection of the costs below. The costs on appeal are assessed against the Appellant,
    Ruffin Building Systems, Inc., and its surety.
    ___________________________________
    D. MICHAEL SWINEY, JUDGE
    -7-