Brooks Varner v. David M. Marrs And Latitia M. Marrs ( 2001 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT JACKSON
    JUNE 18, 2001 Session
    VARNER CONSTRUCTION COMPANY, INC., and THE ESTATE OF
    BROOKS VARNER v. DAVID M. MARRS AND LATITIA M. MARRS
    An Appeal from the Chancery Court for Shelby County
    No. 90765-2    Floyd Peete, Chancellor
    No. W-2000-01029-COA-R3-CV - Filed April 18, 2002
    This is a construction case. In 1981, the defendant owners hired the plaintiff construction company
    to build a custom home. Over the course of construction, the parties disagreed over many things,
    and their relationship ended in July or August 1983. The construction company sued the owners,
    alleging that the owners had not paid the full amount due under the contract. The owners filed a
    counterclaim, alleging that the construction company owed them for amounts expended in
    completing the project and for estimated amounts to cure remaining defects. The chancellor referred
    the case to a special master who, after taking the case under advisement for a lengthy time, issued
    findings which favored the construction company. The chancellor adopted the findings of the master
    and awarded the construction company damages plus prejudgment interest. The owners now appeal.
    We affirm in part, reverse in part and modify.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment in the Chancery Court is Affirmed in
    Part, Reversed in Part and Modified.
    HOLLY K. LILLARD, J., delivered the opinion of the court, in which ALAN E. HIGHERS, J., and DAVID
    R. FARMER , joined.
    John J. Heflin, III, and Kenneth P. Jones, Memphis, Tennessee, for the appellants, David M. Marrs
    and Latitia M. Marrs.
    J. Frank Hall, Memphis, Tennessee, for the appellees, Varner Construction Company and the Estate
    of Brooks Varner.
    OPINION
    This is a construction case. About twenty years ago, defendants David M. Marrs and Latitia
    Montague Marrs (collectively “Owners”) hired Varner Construction Company (“Contractor”),
    owned by James Varner, to build a custom-designed, concrete, partially-underground residence at
    3191 Airline Road in Eads, Tennessee.1 On November 24, 1981, the parties signed a standard
    Amercan Institute of Architects Contract (“AIA Contract”), which detailed the specifications of the
    residence and set the contract price at $328,000. Over the course of construction, approximately
    twenty-eight change orders were issued relating to a variety of details ranging from ice-makers to
    spiral ducts. The changes resulted in approximately $30,000 more due under the contract.
    All of the work performed on the home took place in 1982 and 1983. It is undisputed that
    the parties disagreed over many things including, but certainly not limited to, the timeliness and
    quality of the Contractor’s work, the Owners’ failure to make progress payments to the Contractor
    in a complete and timely manner, and the Contractor’s failure to pay subcontractors. On
    approximately July 14, 1983, James Varner and David Marrs engaged in a “fist fight,” apparently
    stemming from Mr. Marrs’ belief that Mr. Varner had a romantic interest in Mrs. Marrs. Mr. Marrs
    told Mr. Varner not to come back on the property. Mr. Marrs changed the locks on his residence,
    and the altercation apparently marked the end of James Varner’s work on the job.
    In a letter dated August 22, 1983, the architect on the job, Bill Fuller (“Fuller”),2 wrote a
    letter to the Contractor detailing twenty-two items on the project that needed to be completed:
    On all exterior conc. drill holes missing so as to continue the pattern left by the tie
    rods.
    Caulk over the backer rod at the skylite [sic].
    Clean the skylite [sic] on the east side between the two plastic panels.
    install [sic] cover flanges at the solar system conection [sic] of the PVC and metal
    duct at the roof.
    Tighten the fire place flue head.
    Tighten the ‘c’ anchors that hold the solar panels to the frame.
    Clean the tape marks off the solar panels.
    Install the Kitch. Exhaust fan on the roof.
    Clean and polish all door knobs.
    Touch up paint at the metal hand rails.
    At the upper gtass [sic] between the M. bedroom and the garden clean the white
    paint off of the metalso [sic] as to have a straight line.
    Install the hand sprayer on the sink at the N.W. bathroom.
    Repair the leaks at the downstaires [sic] mech. room at the mech. system and at the
    solar system.
    Anchor and level commode in the S.W. bathroom.
    At the downstairs mech room use wire nuts at the splices of wires for the intercom system.
    Install relief valves at the water tanks and water storage tanks.
    1
    At the time of the contract, the Marrs w ere m arried , but now they are divorced.
    2
    Fuller was also the Own ers’ neighbor on A irline Road .
    -2-
    repair [sic] the steam shower head leak.
    Install the icemaker with pump at the bar.
    Restain the bridge floor.
    Clean all [the] trash from site.
    Complete cabinets.
    Install intercom system in livingroom.
    (“August 22 letter”). In the letter, Fuller stated that “[w]hen the . . . list is complete to my
    satisfaction I shall issue a certificate of substantial completion.” Brooks Varner, James Varner’s
    father who had joined his son in working on the job, testified that he and his subcontractors went
    back to the site four or five times to complete the items on the architect’s list. On September 13,
    1983, however, Mr. Marrs filed a Notice of Completion in the Shelby County Register’s Office in
    which he stated that he, rather than the Contractor, substantially completed the work. Whether the
    Contractor or the Owners should receive credit for completing different parts of the project is the
    subject of much dispute. Over the course of construction, the Owners paid the Contractor at least
    $313,868 and paid the Contractor’s subcontractors at least $19,789.
    In late August 1983, the owners moved into their new house. On January 10, 1984, the
    Contractor filed suit against the Owners, claiming that the Owners still owed money under the
    construction contract. The case was not pursued, however, until 1990, when the Owners answered
    the complaint and asserted their counterclaim for costs incurred in completing the construction of
    their residence. In October 1990, the chancellor entered an order referring the case to a master and
    directing the master to answer twenty-five specific questions pertaining to the parties’ claims. The
    master held hearings on February 5 and 6, 1991, and continued on July 2, 1991.
    For reasons not apparent in the record, the master’s report was not issued until approximately
    seven years later, on April 24, 1998. The report answered all of the chancellor’s inquiries and
    ultimately recommended a finding in favor of the Contractor. The Contractor filed a motion to
    confirm the master’s report, and the Owners filed an objection the report. Following oral argument,
    on April 3, 2000, the chancellor entered a final judgment adopting all of the master’s conclusions,
    including the finding that the Owners owed the Contractor $21,838 on the construction contract and
    $12,000 in prejudgment interest, for a total judgment of $33,838.3 In accordance with the
    recommendation in the master’s report, the trial court dismissed the Owners’ counterclaims. The
    Owners now appeal, challenging the chancellor’s order adopting the findings in the master’s report.
    We review this case in accordance with the concurrent finding rule. Under that rule,
    concurrent findings of the master and the chancellor are conclusive and binding on the appellate
    court, except where the finding under scrutiny is (1) upon an issue not proper to be referred; (2)
    based on an error of law; (3) based on a mixed question of law and fact; or (4) not supported by any
    3
    The judgment is in favor of the estate of Brooks Varner, Jame s Varner’s father, because the original plaintiff,
    Varner Construction Comp any , assign ed its interest in the suit to B rooks V arner, wh o is no w d eceased.
    -3-
    material evidence. See Staggs v. Herff Motor Co., 
    390 S.W.2d 245
    , 251 (Tenn. 1965); Aussenberg
    v. Kramer, 
    944 S.W.2d 367
    , 370 (Tenn. Ct. App. 1996); Shepherd v. Griffin, 
    929 S.W.2d 336
    , 344
    (Tenn. Ct. App. 1995); see also Tenn. Code Ann. § 27-1-113 (2000) (stating that “the court of
    appeals shall not have the right to disturb” a concurrent finding of the master and chancellor). The
    Contractor alleges numerous errors in the master’s report and in the chancellor’s subsequent order.
    We will address each argument in turn.
    The Contractor initially makes the argument that we must vacate the chancellor’s order in
    total, or at least give his findings closer scrutiny, because the record shows that he did not exercise
    his independent judgment in adopting the master’s report. Rather, the Contractor alleges, the
    chancellor simply “rubber-stamped” the report without making any deliberate analysis. See
    Blankenship v. Blankenship, No. 02A01-9603-CH-00051, 1997 Tenn. App. LEXIS 42 (Tenn. Ct.
    App. Jan. 17, 1997). Blankenship involved a complicted boundary dispute. In that case, the
    appellate court vacated the trial court’s judgment adopting the special master’s report because it was
    apparent from the record that the trial judge failed to exercise independent judgment in adopting that
    report. Specifically, at the outset of trial, the trial judge informed the parties that the master would
    determine where the disputed boundary lay, commenting that “that’s the way it’s going to have to
    be, because I can’t make heads or tails out of this.” Id. at *3. After the master had issued his report,
    the trial judge refused to allow the parties to offer further evidence to support their positions, stating
    that “if [the master is] wrong, he’s just wrong and you have a right to appeal it.” Id. at *5. In light
    of that evidence, this Court vacated the trial court’s judgment and remanded with instructions for the
    trial court to reconsider the matter independently and permit the parties to offer additional evidence
    on the location of the boundary. Id. at *7-*8.
    In the case at bar, the Owners contend that the chancellor abdicated his responsibility to
    evaluate independently the circumstances of this case. The Owners rely on a statement in the
    chancellor’s order that “the Special Master has discretion to accept or reject testimony and therefore
    the Special Master was well within his scope of discretion to make the findings set forth in his
    report.” The Owners assert that this statement shows that the trial court impermissibly deferred to
    the findings of the master without exercising independent judgment based on the evidence. The
    Owners argue that such a conclusion is particularly compelling in the instant case, in which the
    master’s decision was not issued until approximately seven years after the submission of evidence.
    While the time for which this case has been pending is indeed excessive, the record contains
    no evidence of prejudice to the parties from the delay. More importantly, unlike Blankenship, the
    chancellor in this case did not preclude evidence offered to rebut the findings of the master. Instead,
    the record shows that the trial court heard oral arguments on the matter and deliberately weighed the
    evidence. As the court in Blankenship recognized, “[a] trial court is entitled to adopt a special
    master’s report in full. T.C.R.P. 53.04(2).” Id. at *5. Under these circumstances, we find no
    evidence to support a finding that the chancellor abdicated his responsibility to exercise independent
    judgment.
    -4-
    For the remaining issues, the Owners assert that certain enumerated findings of the master,
    adopted by the chancellor, were not supported by any material evidence. The applicable provisions
    in the parties’ AIA Contract are as follows:
    ARTICLE 2: ARCHITECT
    * * *
    2.2.7   The Architect will be the interpreter of the requirements of the Contract
    Documents and the judge of the performance thereunder by both the Owner and
    Contractor.
    * * *
    2.2.11 The Architect’s decisions in matters relating to artistic effect will be final
    if consistent with the intent of the Contract Documents.
    *   *     *
    2.2.13 The Architect will have authority to reject Work which does not conform
    to the Contract Documents.
    *   *     *
    ARTICLE 13: UNCOVERING AND CORRECTION OF WORK
    13.2    CORRECTION OF WORK
    13.2.1 The Contractor shall promptly correct all Work rejected by the Architect as
    defective or as failing to conform to the Contract Documents whether observed
    before or after Substantial Completion and whether or not fabricated, installed or
    completed. The Contractor shall bear all costs of correcting such rejected Work,
    including compensation for the Architect’s additional services made necessary
    thereby.
    13.2.2 If, within one year after the Date of Substantial Completion of the Work or
    designated portion thereof or within one year after acceptance by the Owner of
    designated equipment or within such longer period of time as may be prescribed by
    law . . . any of the Work is found to be defective or not in accordance with the
    Contract Documents, the Contractor shall correct it promptly after receipt of a written
    notice from the Owner to do so unless the Owner has previously given the Contractor
    a written acceptance of such condition. This obligation shall survive termination of
    the Contract. The Owner shall give such notice promptly after discovery of the
    condition.
    -5-
    The Owners challenge the following findings of the master, asserting that there is no material
    evidence to support each finding:
    QUERY 2:
    What change orders were agreed to and signed by the proper persons?
    FINDING 2:
    The Master finds that the first change order was signed by the architect,
    Fuller[,] the contractor Varner and the owner Marrs. Subsequent change orders were
    signed only by Varner & Marrs. There were two change orders (Ref. Ex. 61 and 62)
    that the architect denied signing. (Trcp. p. 416 line 18 to p. 418 line 20; p. 432 line
    12-p. 434 line 7). However, on the Applications and Certificate for Payment for the
    period 04/20/83 to 05/30/83 the architect’s signature on 06/10/83 was not questioned
    and showed change orders (1022) totaling $27,887.00 (Ref. Ex. 6).
    In addition to this $27,887.00, Marrs agreed to pay for the following changes
    not previously shown in Application and Certificate For Payments (Ref. 6)
    Change Order #27 dated 04/14/83                    $485.00
    (Trcp. p. 244 line 7-11, Ref. Ex. 5)
    Change Order # - dated 05/03/83                    500.00
    (Trcp. p. 240 line 4-10, Ref. Ex. 5)
    Brown Sheet of Paper Change Order                1,828.00
    (Trcp. p. 240 line 12-15, Ref. Ex. 19)
    2,813.00
    Previously approved Change Orders               27,887.00
    TOTAL CHANGE ORDERS                             30,700.00
    *   *     *
    QUERY 5:
    What amount of money was paid by the Defendant to the Plaintiff pursuant
    to the contract?
    FINDING 5:
    The Master finds that the Defendant paid $313,868.00 to the Plaintiff. (Trcp.
    p. 341 line 24 - p. 342 line 2; Ref. Ex. 9)
    -6-
    QUERY 6:
    Were these payments [progress payments to Varner] made when they were
    supposed to be made?
    FINDING 6:
    *    *       *
    Article 9.4.1 requires the architect to certify the application for payment
    within seven days or notify the contractor of reasons for referral to certify. (Ref. Ex.
    3)
    Article 9.5.1 provides that after Architect has certified the application for
    payment, the Owner shall make payments in the manner and within the time
    provided in the Contract Documents. (Ref. Ex. 3)
    Article 5 PROGRESS PAYMENTS in the Standard From [sic] of Agreement
    Between Owner and Contractor (Ref. Ex. 1) provides that payment should be not
    later than ten days following the end of the period covered by the Application For
    Payment (Note: this is the same as the billing date in most instances). The Master
    finds that the following payments were made in excess of the ten day provision:
    Application #3 (6 days late), #4 (1 day late), #5 (22 days late), #6 (3 days late), #8
    (4 days late), #9 (51 days late), #10 (17 days late), #12 (3 days late), #13 (60 days
    late) #14 (20 days late), #17 (still unpaid)
    *       *   *
    QUERY 8:
    Did the Plaintiff perform under the contract what was supposed to be done
    under the contract?
    FINDING 8:
    The Master finds that Bill Fuller, Architect, in his letter of August 22, 1983
    (Ref. Ex. 18) indicated that he would issue a certificate of substantial completion
    upon the completion of the [22 items quoted above] to his satisfaction . . . .
    The Master finds that the owner filed a Notice of Completion on September
    13, 1983 in the Shelby County Register’s Office which was recorded as Instrument
    No. U5 9321, in which the owner states that he rather than the contractor has
    substantially completed the work. (Ref. Ex. 71).
    -7-
    QUERY 9:
    If the Plaintiff did not perform what was supposed to be done, what did the
    Plaintiff do or not do, that was supposed to be done or not done?
    FINDING 9:
    J. Varner testified that he did not recall or did not complete the architect’s
    punch list (Trcp. p. 123 line 19- p. 128 line 1).
    B. Varner testified that he personally completed some of the items on the
    punch list and that the subcontractors completed other items. He further testified that
    since Marrs paid the subs their retainage, the subs were not inclined to return to the
    job (Trcp. p. 148 line 3 - p. 152 line 24).
    D. Marrs testified regarding the punch list:
    Expenses allowed by Master-
    Clean skylite [sic]-Lincoln Glass 10/10/83      $392
    (Trcp. p. 266 line 1-21, Ref. Ex. 48)
    Expenses disallowed by Master- (failed to carry burden of proof)
    Install icemaker-Sears 9/24/83
    (Trcp. p. 267 line 11-18, Ref. Ex. 50)
    Clean all trash from site
    (Trcp. p. 268 line 13-18, Ref. Ex. 52)
    Complete Cabinets-estimated cost
    (Trcp. p. 286 line 11-21)
    Install Intercom System
    (system was installed but did not work
    Trcp. p. 282 line 19 - p. 283 line 7)
    Part of punch list & part for Varner
    Himmer (Trcp. p. 271 line 15- p. 276 line 24, Ref. Ex. 56 I.D.)
    *   *     *
    QUERY 14:
    What is the nature, extent and character of any defects in workmanship
    attributable to the Plaintiff?
    -8-
    FINDING 14:
    There was voluminous testimony on defects:
    a) Repair of solar panels (Trcp. p. 250-256);
    b) Replace dirt & sod (Trcp. p. 257-260);
    c) Varner equipment tore up ground (Trcp. p. 258);
    d) Varner equipment tore up driveway (Trcp. p. 262-265);
    e) Repair skylite [sic] leak (Trcp. p. 266);
    f) Icemaker never furnished (Trcp. p. 267);
    g) Roof leak (Trcp. p. 268);
    h) Trash at site (Trcp. p. 268-270);
    i) Failure to pay for door (Trcp. p. 271);
    j) Failure to complete punch list (Trcp. p. 271-276);
    k) Repair intercom system (Trcp. p. 282-283)
    l) Honeycombs in concrete exterior walls (Trcp. p. 45, 93, 130, 279, 402,
    405-407);
    m) Honeycombs in concrete interior walls (Trcp. p. 403-404, 408-409);
    n) Concrete floor (Trcp. p. 283-284, 400-402, 407-408);
    o) Cabinets not stained (Trcp. p. 286);
    p) Concrete around pool (Trcp. p. 410-411).
    The Master disallows these claims [based on the Application and
    Certification for Payment signed by the architect (Application #16) on 6/10/83 (Ref.
    Ex. 6) which indicates that the project was substantially complete and from the
    architect’s punch list (Ref. Ex. 18) which does not show these items; the Defendant
    also did not carry his burden of proving damages] except for those itemized in
    finding 9.
    *    *    *
    QUERY 15 a (Revised):
    If any defects existed in the work after Plaintiffs stopped work, did Plaintiffs
    cure them?
    FINDINGS 15 a:
    Brooks Varner testified that he or the Subcontractors corrected or tried to
    correct the defects noted on the architect’s punch list (Trcp. p. 147-153, Ref. Ex. 18),
    however, the Master finds that no “official” written acceptance was produced by
    either party.
    -9-
    *    *     *
    QUERY 20:
    What amount of money does the Defendant owe the Plaintiff, or in the
    alternative, what amount of money does the Plaintiff owe the Defendant? Give the
    reasons.
    FINDING 20:
    Based on Application #16 of the Application and Certification for Payment
    (Ref. Ex. 6), the Master finds that
    Contract Sum                                       $328,000
    Change orders                                        27,887
    Total                                              $355,887
    Less: Payments (Schedule A)      $313,868
    Payments Allowed (Finding 9)     392
    Payments to Subs (Finding 10) 19,789          334,049
    Total Due Plaintiffs                                $21,838
    *    *     *
    QUERY 22 (Revised):
    When the Defendant moved into the house, what defects, if any, remained?
    FINDING 22:
    The Master finds that the following defects had not been remedied, however
    the Defendant failed to carry his burden of proving damages:
    Clean skylite[sic]-Lincoln Glass 10/10/83
    (Trcp. p. 266 line 1-21, Ref. Ex. 48)
    Install icemaker-Sears 9/24/83
    (Trcp. 267 line 11-18, Ref. Ex. 50)
    Clean all trash from site
    (Trcp. p. 268 line 13-18, Ref. Ex. 52)
    Complete Cabinets-estimated cost
    (Trcp. p. 286 line 11-21)
    Install Intercom System
    (system was installed but did not work
    Trcp. p. 282 line 19 - p. 283 line 7)
    Part of punch list & part for Varner
    -10-
    Himmer (Trcp. p. 271 line 15- p. 276 line 24, Ref. Ex.
    56 I.D.)
    We will address each challenged finding to determine whether there is material evidence to support
    the concurrent finding of the master and the chancellor.
    Objection to findings number 2 & 5
    The Owners argue that finding numbers 2 and 5 are erroneous because finding number 2
    specifically charges the Owners with a $1,828 change order (referred to as the “Brown Sheet of
    Paper Change Order”) for the installation of gold mirrors, but finding number 5 fails to give the
    Owners credit for the uncontroverted $1,650 payment for the mirrors made on July 11, 1983. The
    Contractor does not dispute that the Owners should be credited for this payment, so long as the
    corresponding change order is included as a valid cost. Therefore, because the Owners are charged
    for the “Brown Sheet of Paper Change Order” in finding number 2, they should be credited with the
    $1,650 payment in finding number 5. There being no dispute about this credit to the Owners, we
    find that there is no material evidence to support the concurrent finding of the special master and the
    chancellor on this issue, and hold that the Owners should be credited $1,650 for this item.
    Objection to finding number 6
    As to finding number 6, the Owners complain that, although the master found that certain
    progress payments were untimely, he did not indicate whether the failure to pay was justified or
    unjustified. No damages are alleged to have resulted from the delay in payment. Consequently, this
    issue is without merit.
    Objection to findings number 8 & 14
    In the August 22 letter quoted above, Fuller made a list of defects that, in his opinion, needed
    to be remedied by the Contractors before the job would be “substantially complete.” The Owners
    argue that in findings number 8 and 14, the master assumed that the August 22 letter was an
    exhaustive “punch list” of all defects as of the date of the letter, and that all defects omitted from the
    list were either not cured or were not the Contractor’s responsibility. The Owners argue that the
    master’s assumption in this regard was erroneous, and that the disallowance of any expense simply
    because the defect was not listed in the August 22 letter should be reconsidered.
    Contrary to the Owners’ assertion, the record reflects that the master did not specifically
    determine that the August 22 letter was intended to be an exhaustive list of defects, or that the cost
    to remedy defects that were omitted from the list should be automatically disallowed. Rather, the
    master noted that certain defects were or were not on the list, and he considered that fact as probative
    evidence of whether Fuller deemed the curing of that defect as necessary for the “substantial
    completion” of the project. Therefore, if the existence of a defect is disputed, the omission of that
    defect from the August 22 letter would be relevant to show that Fuller did not consider it necessary
    -11-
    to remedy that defect at the time the letter was written. However, if the evidence is undisputed that
    a particular defect existed and that the Contractor was responsible for curing it, the fact that the
    defect was not included in the August 22 letter is irrelevant. At this juncture, then, we find that the
    master’s findings number 8 and 14 were not generally erroneous. We will later address the specifics
    regarding certain items of reimbursement claimed by the Owners.
    Objection to finding number 9
    The Owners assert that there is no material evidence to support the master’s allowance of
    $392 for having the skylight cleaned by Lincoln Glass, and at the same time disallowing five other
    items for which the evidence was substantially similar. In finding number 9, the master disallowed
    the Owners credit for installing an icemaker, cleaning trash from the site, staining the inside of
    cabinets, repairing the intercom system, and for money paid to a subcontractor for making
    miscellaneous repairs. Regarding those items, without elaboration, the master noted that the Owners
    “failed to carry [their] burden of proof with respect to these items.”
    a. Installing an icemaker - $644.09
    It is undisputed that an icemaker was not installed by the Contractor, and that the contract
    specifications provided for an icemaker to be installed. Fuller’s August 22 letter notified the
    Contractor that it needed to “[i]nstall the icemaker with pump at the bar.” Moreover, it is undisputed
    that the Owners purchased an icemaker on approximately September 24, 1983, for $644.09, and the
    Owners’ check for that purchase was entered into the record.
    The Contractor claims that, due to a mistake by the architect, the particular icemaker
    specified in the contract was not available at the time the house was being built. In its brief, the
    Contractor cites the testimony of James Varner to support their claim that “something else” was
    substituted in lieu of the icemaker. However, the testimony to which the Contractor refers pertains
    to a refrigerator, not an icemaker. Furthermore, when questioned about whether his company had
    installed the icemaker, James Varner replied, “I don’t believe that was done.” Thus, we find no
    material evidence to support the master’s finding, adopted by the chancellor, that the icemaker was
    provided to the Owners. Consequently, the $644.09 cost of this item should be credited to the
    Owners.
    b. Cleaning trash from the site - $200
    In the proceedings before the master, the Owners asserted that the Contractor did not clean
    up the site, and the testimony of James Varner was consistent with that assertion. The Owners
    submitted into evidence photographs of the trash and debris that remained outdoors on the project
    site after most of the construction had taken place. The record also includes a check for $200 from
    the Owners to Bobby Smith for cleaning up the site. The Contractor contends that it was unable to
    clean up the site because James Varner was prohibited from entering the property after the “fist
    fight” in July 1983. It is undisputed, however, that Brooks Varner was never prohibited from
    -12-
    entering the property. He testified that, after the incident, he and other employees of the Contractor
    entered the premises to try to resolve the issues raised in the August 22 letter. There is no allegation
    that Brooks Varner, on behalf of the Contractor, was unable to perform the necessary clean up. The
    clean-up task was listed in the August 22 letter as an item that should have been done by the
    Contractor. Under these circumstances, we conclude that there is no material evidence to support
    the disallowance of this item. Thus, the Owners should be credited $200.
    c. Staining inside of cabinets - $1,300
    The Owners claim that the Contractor was responsible for having the inside of the cabinets
    stained, and attributed an estimated cost of $1,300 to this task. The August 22 letter specifically
    listed “[c]omplete cabinets” as one of the defects to be corrected. However, the Owners submitted
    only the testimony of David Marrs on his estimate for the item, with no indications of the
    specifications for the task or evidence corroborating Marrs’ estimate. The master found that the
    Owners had not carried their burden of proof on this item and, accordingly, disallowed it. We cannot
    conclude that there is no material evidence to support the mater’s conclusion, adopted by the
    chancellor.
    d. Repairing intercom system - $392.70
    It is undisputed that the Contractor had an intercom system installed, and that the intercom
    system did not work properly when the Contractor left the job. The August 22 letter listed “[i]nstall
    intercom system in livingroom” as unfinished business. David Marrs testified that he hired Acme
    Sales Company to repair the intercom, and that he paid them $392.70 for that work. However, the
    record contains no evidence about the reason the system malfunctioned. The Owners did not submit
    any corroborating evidence, such as a canceled check or invoice, regarding the amount paid, to
    whom it was paid, and the service that was performed. Under these circumstances, we find that there
    was material evidence to support the master’s decision to disallow this item for lack of proof.
    e. To Himmer for completing items on punch list - $1,563.36
    This claim is based on two payments made by the Owners to Roy Himmer totalling
    $1,563.36, allegedly for his efforts to complete items that needed to be finished on the house.
    However, the record contains no evidence of what tasks were performed by Himmer, and whether
    those tasks were the responsibility of the Contractor or the Owner. Himmer did not testify, and the
    record includes no bill to show what work Himmer performed. Consequently, we find that there was
    material evidence to support the master’s decision to disallow this item for lack of proof.
    Objection to finding number 14
    In query number 14, the master was asked about the defects in workmanship attributable to
    the Contractor. The master listed sixteen defects that were alleged by the Owners, but he disallowed
    each of those claims “based on the Application and Certification for Payment signed by the architect
    -13-
    (Application #16) on 6/10/83 . . . which indicates that the project was substantially complete and
    from the architect’s punch list . . . which does not show these items; the Defendant also did not carry
    [their] burden of proving damages” with respect to the sixteen items.4 The Owners claim that the
    master erred in disallowing some of these claims, and also in neglecting to mention their claims for
    repairing a heat pump ($743.90) and for waterproofing materials ($54.24).
    a. Undisputed Items
    The evidence is undisputed that the Owners incurred expenses in repairing solar panels,
    repairing the skylight leak, and installing an exterior door. The evidence is also undisputed that these
    items were the responsibility of the Contractor. It appears that the master’s only basis for
    disallowing the Owners their expenses related to curing these defects was the fact that the defects
    were not listed in the August 22 “punch list.” As noted above, the master did not specifically find
    that the August 22 letter was intended to be an exhaustive list of defects. Consequently, where it is
    undisputed that the defect exists and that the expense for remedying the defect is necessary, the
    omission of a defect from the August 22 letter is not relevant. There is no other material evidence
    to support the conclusion of the master and chancellor to disallow these items. Therefore, we must
    reverse with respect to the following: (1) repair of solar panels, $378.87; (2) repair of skylight leak,
    $500.58; and (3) failure to pay for door, $152.97. Accordingly, the Owners should be credited
    $1,032.42 for curing those defects.
    b. Repair roof leak and waterproofing materials - $250.00 and $54.24
    David Marrs testified that he paid Kermit Buck $250 to repair the leak in the roof and paid
    Styro Floral $54.24 for waterproofing material related to that repair. The evidence shows that the
    check to Buck was written on January 8, 1985, and the waterproofing material was purchased in
    November of 1984. According to the contract, if “within one year after the Date of Substantial
    Completion of the work . . . any of the Work is found to be defective or not in accordance with the
    Contract Documents, the Contractor shall correct it promptly after receipt of a written notice from
    the Owner.” The roof leak was not included as an existing defect in the August 22 letter. Further,
    there is no evidence that this defect was found within the year after substantial completion, nor is
    there evidence that the Contractor ever received notice of this defect. Under these circumstances,
    we find that there was material evidence to support the master’s conclusion that the Owners failed
    to sustain their burden on this claim.
    4. Honeycombs in concrete exterior walls - $8,300; honeycombs in concrete interior walls -
    $4,609.
    4
    These include several items previously discussed in this Opinion, such as the icemaker that was not furnished,
    trash on the site, the payments to Himm er for completing the “punch list,” repairing the intercom system, and the
    cabinets that were not stained.
    -14-
    The Owners claim that the Contractor was responsible for curing defective lines, called
    “honeycombs,” in the exterior concrete walls. The evidence is undisputed that the Contractor
    discontinued work on the job without completely repairing those walls, even though it had stated in
    a letter dated April 11, 1983 that it would patch the concrete “at an appropriate time prior to the job
    being considered ‘substantially complete’ and in compliance with the contract.” This defect is not
    listed in the August 22 letter as being important for substantial completion, but Fuller testified before
    the master that some of the honeycombing on the exterior walls was “horrible.” He suggested that
    the best way to cure the defect would be to pour concrete over the existing wall, which he estimated
    would cost approximately $8,300. No formal quote was submitted into evidence.
    With respect to the interior walls, Fuller testified before the master that the walls were
    “obviously defective” because of honeycombing and discoloration, and that it would cost $4,609.00
    to remedy the defects. The Owners submitted no photographs of the inside walls, nor was any
    formal estimate obtained to support their position.
    The evidence submitted to the master on this is disputed regarding the appropriate remedy
    for honeycombs; there was testimony that pouring concrete over the wall would be best, and other
    testimony that patching the walls would be the most appropriate remedy. The record contains no
    evidence of the cost of patching. Moreover, despite Fuller’s testimony on the severity of the
    honeycombing, the defects were not listed in his August 22 letter. Under these circumstances, there
    is material evidence to support the conclusion of the master and the chancellor that the Owners failed
    to carry the burden of proof on these items.
    5. Repair defects in concrete floor - $32,544.25
    David Marrs testified that the concrete floors were to be scored after pouring, forming two
    foot squares resembling a checkerboard across the room. When the floor was colored and waxed,
    it was to look like marble or some other type of inlaid floor. Both Marrs and Fuller testified that the
    job was defective because the Contractor allowed the concrete to harden too much prior to the
    scoring, and as a result the workers chipped the floor rather than cutting smooth, even lines. They
    attempted to patch the floor, but the patching allegedly caused discoloring and damaged flooring.
    Fuller estimated that the cost to repair this defect would be $32,544.25, because a whole new layer
    of floor would need to be poured and rescored.
    At the hearing before the master, no photographs were submitted to illustrate how the floors
    were defective, and there was no formal estimate from a contractor who would perform such a task.
    As with the walls, Fuller did not list this large-ticket item in his August 22 letter, and therefore at
    that time must not have found the defect to have been critical to achieving substantial completion.
    That omission is inconsistent with his later testimony that the floors needed a complete overhaul.
    Under these circumstances, we find that there is material evidence to support the disallowance of this
    claim for repair.
    6. Repairing heat pump - $743.90
    -15-
    The Owners claim that they paid Diamond Services $743.90 between January and May of
    1985 to repair the heat pump in the house. David Marrs testified that he paid a total of $716.91 for
    this purpose, and there is some discrepancy between the testimony and the documentary evidence.
    From the record, it appears that this expense was incurred after the one-year period, and the
    Contractor received no notice of this defect prior to one year after substantial completion. Moreover,
    this defect was not among those listed in the August 22 letter. Consequently, we find that there is
    material evidence to support the conclusion of the master and the chancellor that the Owners failed
    to sustain their burden of proof on this claim.
    In sum, the assessment of the total amount due to the Contractor in this case is modified to
    the following:
    Contract Sum                                                                  $328,000.00
    Change Orders                                                                   30,700.005
    Total                                                                          358,700.00
    Less: Payments (Application No. 16)      $313,868.00
    Payments allowed to Owners
    Cleaning of Skylight (Finding 9) 392.00
    Gold Mirror                     1,650.00
    Icemaker                          644.09
    Clean up trash                    200.00
    Repair solar panels               378.87
    Repair skylight leak              500.58
    Door                              152.97
    Payments to Subs (Finding 10) 19,789.00                            337,575.51
    Total Due Contractor                                                            $21,124.49
    As a final matter, both parties dispute the chancellor’s award of prejudgment interest.
    Generally, the appellate court will not overturn a trial court’s finding of prejudgment interest unless
    the trial court has abused its discretion. Alexandar v. Inman, 
    974 S.W.2d 689
    , 698 (Tenn. 1998).
    The chancellor awarded the Contractor a flat amount of $12,000 in prejudgment interest,
    “taking into consideration the fact that the case has been pending for approximately 17 years and that
    the Special Master had the matter under advisement for 7 years. The Court feels that the defendants
    should not be taxed with interest during the entire period the suit was pending.”
    The Contractor argues that the chancellor erred in limiting the prejudgment interest to
    $12,000, because the AIA Contract provides specifically that “[p]ayments due and unpaid under the
    Contract Documents, shall bear interest from the date payment is due . . . .” AIA Contract ¶7.8.
    5
    This total amount of chan ge orders is consistent with the master’s finding number 2. Apparently, the change
    order am oun t was mistaken ly listed as $27 ,887 in the m aster’s fin ding num ber 2 0.
    -16-
    Instead, the Contractor claims, the trial court should have awarded prejudgment interest from the
    date the payments were due, approximately seventeen years prior, which would amount to
    approximately $39,000 in this case. Where prejudgment interest is provided for in a contract, the
    Contractor argues, that provision must be enforced without weighing any equitable considerations.
    Because the contract in this case included a provision regarding interest due on unpaid debts, the
    Contractor urges this Court to find that the provision requires an award of prejudgment interest
    “from the date payment [was] due.” AIA Contract ¶7.8.
    The Owners argue on appeal that the chancellor erred in awarding any amount of
    prejudgment interest. They argue that the contractual provision cited by the Owners is not
    applicable, and that Tennessee Code Annotated § 47-14-123 governs the award of prejudgment
    interest in this case. That statute provides in pertinent part:
    Prejudgment interest . . . may be awarded by courts or juries in accordance with the
    principles of equity at any rate not in excess of a maximum effective rate of ten
    percent (10%) per annum . . . . In addition, contracts may expressly provide for the
    imposition of the same or a different rate of interest to be paid after breach or default
    within the limits set by § 47-14-103.
    Tenn. Code Ann. § 47-14-123 (2001). Under that statute, the Owners argue, prejudgment interest
    should be awarded “in accordance with the principles of equity,” and the equities in this case weigh
    in favor of disallowing any interest because the Contractor’s right of recovery was disputed on
    reasonable grounds. See Alexander, 974 S.W.2d at 698 (stating that prejudgment interest is more
    likely to be equitable if plaintiff’s right of recovery is not disputed on reasonable grounds).
    This Court has held that the equitable considerations referred to in Tennessee Code
    Annotated § 47-14-123 are applicable in a construction dispute, even where the contract involved
    contains a provision regarding interest accrual on unpaid debts arising out of the contract. Southwest
    Progressive Enters., Inc. v. Shri-Hari Hospitality, LLC, No. 01-A-01-9810-CH-00542, 1999 Tenn.
    App. LEXIS 603 (Tenn. Ct. App. Sept. 1, 1999). In Southwest Progressive Enters., the plaintiff
    contractor sued the owner/developer of a hotel project for amounts due on a contract in which it had
    agreed to texturize the walls in eighty-five (85) rooms of the hotel. The contract between the parties
    “provided that payments due and unpaid under the contract would accrue interest at the rate of 10%
    per year.” Id. at *2. The trial court found in favor of the contractor and awarded prejudgment
    interest. On appeal, the owner argued that the trial court erred in awarding prejudgment interest
    because the obligation to award such interest never arose under the specific terms of the contract.
    In rejecting the owner’s argument, the appellate court noted that “[i]t has long been the law in
    Tennessee that courts may award pre-judgment interest in accordance with the principles of equity.”
    Id. at *4. The Court noted that the owner’s contractual argument did “not address the equitable
    purpose of awarding prejudgment interest, which is ‘to fully compensate a plaintiff for the loss of
    use of the funds to which he or she was legally entitled.’” Id. at *5 (quoting Mitchell v. Mitchell,
    
    876 S.W.2d 830
    , 832 (Tenn. 1994)). The appellate court concluded that it would have been
    inequitable to reward the owner for refusing to pay by allowing it free use of the contractor’s money.
    -17-
    In this case, we find that the chancellor was entitled to weigh the equities in determining the
    appropriate amount of prejudgment interest. The provision in the contract regarding interest applies
    to “[p]ayments due and unpaid under the Contract Documents.” AIA Contract ¶ 7.8. The amounts
    “due and unpaid” were the subject of much dispute. We have recognized that a trial court has the
    power to award prejudgment interest “in accordance with the principles of equity.” Southwest
    Progressive Enters., 1999 Tenn. App. LEXIS 603, at *4. On this basis, we find that the chancellor
    did not err in refusing to hold the Owners liable for prejudgment interest at a rate of 10% for the
    entire duration of this controversy.
    We also reject the Owners’ argument that the chancellor should not have awarded any
    prejudgment interest. The Owners claim that prejudgment interest was inappropriate in this case
    because their obligations were disputed on reasonable grounds. While the fact that an obligation is
    reasonably disputable is a factor in determining whether prejudgment interest is warranted, a court
    is not bound to deny prejudgment interest in such cases. See Myint v. Allstate Ins. Co., 
    970 S.W.2d 920
    , 928 n.7 (Tenn. 1998) (overruling those cases which hold that prejudgment interest is not
    allowable when an obligation is disputed on reasonable grounds). Rather, the court has
    “considerable deference in the prejudgment interest decision.” Id. at 927. Trial courts are guided
    by several principles in determining an appropriate amount of prejudgment interest. A court must
    consider principles of equity, and it must also bear in mind that the purpose of making such an award
    “is to fully compensate a plaintiff for the loss of the use of funds to which he or she was legally
    entitled, not to penalize a defendant for wrongdoing.” Id. Also, prejudgment interest should be
    granted “when the amount of the obligation is certain,” and where “the amount is not disputed on
    reasonable grounds.” Id.
    The chancellor in this case found that the equities weighed in favor of awarding prejudgment
    interest, but he also concluded that the extraordinary duration of these proceedings required that such
    interest be limited. It was within the equitable power of the chancellor to consider the unusual
    duration of this litigation as a factor in reducing the prejudgment interest so as to prevent unjust
    punishment to the Owners. See Foster & Creighton Co. v. Wilson Contracting Co., 
    579 S.W.2d 422
    , 428-29 (Tenn. Ct. App. 1978) (affirming trial court’s disallowance of prejudgment interest
    against defendant when case endured twenty (20) years and claim was one for unliquidated
    damages). Because the amount of the damages award has not been greatly modified on appeal, we
    affirm the award of prejudgment interest in the amount of $12,000.
    Accordingly, we affirm in part, reverse in part, and modify. The cause is remanded to the
    trial court for further proceedings consistent with this Opinion. Costs are to be taxed equally to the
    appellants, David M. Marrs and Latitia M. Marrs, and their sureties, and appellees, Varner
    Construction Company and The Estate of Brooks Varner, for which execution may issue if
    necessary.
    -18-
    ___________________________________
    HOLLY K. LILLARD, JUDGE
    -19-
    

Document Info

Docket Number: 2000-01029-COA-R3-CV

Filed Date: 6/18/2001

Precedential Status: Precedential

Modified Date: 4/17/2021