Consulting and Financial Services, Inc v. John H. Friedmann, Sr. ( 2014 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    March 19, 2014 Session
    CONSULTING AND FINANCIAL SERVICES, INC, ET AL. V. JOHN H.
    FRIEDMANN, SR.
    Appeal from the Chancery Court for Sumner County
    No. 2008C205    Tom E. Gray, Chancellor
    No. M2013-01416-COA-R3-CV -          Filed April 24, 2014
    This is the second appeal of this case, arising from the installation of tile
    flooring. In Consulting and Financial Services, Inc. v. Friedmann, No. M2011-00093-
    COA-R3-CV, 
    2012 WL 139062
    1(Tenn. Ct. App. April 19, 2012), we held that the trial
    court’s measure of damages was correct, but remanded for re-calculation of the amount of
    damages. The remand was necessary because the original judgment included damage
    amounts that were based upon tile repairs to certain areas of the home, which repairs were
    not raised by Appellees/homeowners within the one-year warranty period. We did not,
    however, mandate the method by which the trial court could determine the adjusted amount.
    Upon remand, the only evidence presented was from the original contractor, who relied upon
    his original estimate. To arrive at the portions of the original estimate that were for the
    excluded areas, the contractor had his tile subcontractor submit separate estimates for those
    areas. The separate estimates were calculated using the current price-per-square-foot
    applicable at the time of remand, which was less than the price-per-square-foot that was used
    in the original estimate. To arrive at the adjusted damages amount, the trial court simply
    subtracted the separate estimate amounts from the original estimate. Appellant/Contractor
    appeals, arguing, inter alia, that the lower price-per-square-foot applicable at the time of
    remand should apply to the entire judgment, or, in the alternative, that the excluded amounts
    should be calculated using the same price as was used in the original estimate. The “law of
    the case,” based upon our holding in the first appeal, was that the judgment would be
    adjusted to exclude all costs associated with the excluded areas. Although we did not
    mandate that the trial court re-try the issue of damages, we did not preclude that option in our
    first opinion. However, it was implicit in our holding that, if the trial court chose to use the
    original estimate (which it did), then the total costs for the excluded areas would be
    calculated, at the same price used in the original estimate, and subtracted from the original
    estimate. Because the trial court used new estimates for the excluded areas, which were not
    calculated at the same rate as in the original estimate, the adjusted judgment did not remove
    the full amount for repairs to the excluded areas that were contemplated in the original
    estimate. Accordingly, the law of the case was not followed. Vacated and remanded with
    instructions.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court is Vacated
    and Remanded
    J. S TEVEN S TAFFORD, J., delivered the opinion of the Court, in which D AVID R. F ARMER, J.,
    and H OLLY M. K IRBY, J., joined.
    Bruce N. Oldham, Gallatin, Tennessee, for the appellant, John H. Friedmann, Sr.
    Russell E. Edwards and Michael W. Edwards, Hendersonville, Tennessee, for the appellees,
    Consulting and Financial Services, Inc. and Paul G. Crenshaw.
    OPINION
    In Consulting and Financial Services, Inc. v. Friedmann, No. M2011-00093-COA-
    R3-CV, 
    2012 WL 139062
    1(Tenn. Ct. App. April 19, 2012) (“Friedmann I”), the Contractor,
    Appellant John H. Friedmann, Sr., appealed the trial court’s award of $106,103.92 in
    damages, plus $4,252.00 in discretionary costs, to Appellee/homeowners. In Friedmann I,
    we were asked to review the trial court’s finding of liability, and particularly whether the trial
    court failed to apply the standard of performance contained in the contract and whether the
    trial court erred in its calculation of damages. In Friedmann I, we determined that the trial
    court applied an implied warranty of workmanship standard, as first enumerated in Dixon
    v. Mountain City Const. Co., 
    632 S.W.2d 538
    (Tenn.1982), rather than the contractual
    standard. However, after a de novo review of the evidence, we modified the trial court’s
    judgment to hold that the Mr. Friedmann had breached the contractual standard, and
    remanded the case for a determination of the appropriate amount of damages. A full
    recitation of the factual history of the case is set out in Friedmann I. In the interest of
    continuity and judicial economy, we restate the relevant facts here:
    On May 10, 2004, Consulting and Financial Services,
    Inc. (“CFS”) contracted with John H. Friedmann, Sr., a licensed
    general contractor, to construct a home in the Fairvue Plantation
    subdivision in Gallatin, Tennessee. The “Building Contract”
    (“the contract”) provided, among other things, as follows:
    -2-
    1. That the Contractor will construct in a good,
    workmanlike manner, and without delay, a
    dwelling or other specified building in accordance
    with the plan, drawings, and specifications
    attached to and made part of this Contract on the
    following described property. . . .
    8. The Contractor shall correct any work that fails
    to conform with the requirements of the contract
    documents where such failure to conform appears
    during the progress of the work, and shall remedy
    any defects due to faulty materials, equipment or
    workmanship which shall appear within a period
    of one year from the date of the issuance of a Use
    and Occupancy Permit. The provision of this
    article apply [sic] to work done by subcontractors
    as well as work done by direct employees of the
    Contractor. Contractor warrants the fitness and
    habitability of the work, and compliance with all
    codes.
    [The president of CFS,] Paul G. Crenshaw [together with
    CFS, Appellees] . . . and Sherry Steffey, wife of Mr. Crenshaw
    and vice president of CFS, took possession of the residence on
    May 7, 2005. Approximately six months after moving into the
    home, Ms. Steffey noticed cracked tile in the kitchen. She
    notified Mr. Friedmann about the damaged tile; Mr. Friedmann
    came to inspect the tile, but he did not repair it. Subsequently,
    tile in the master bathroom, hallways, and foyer began to crack.
    On August 8, 2008, CFS and Paul G. Crenshaw
    (collectively referred to as [“Appellees”]) filed suit against Mr.
    Friedmann. The complaint alleged that Mr. Friedmann “poorly
    and negligently constructed” the home, which constituted a
    “breach of warranty, breach of contract, and/or unjust
    enrichment.” With respect to the allegations of breach of
    contract and breach of warranty, [Appellees] specifically alleged
    that Mr. Friedmann “failed to construct this dwelling in a
    workmanlike manner, and thus, has breached the warranty
    and/or contract with CFS.” [Appellees] requested damages
    -3-
    equaling the cost of repair, cost of inspections, and attorney’s
    fees.
    A bench trial commenced on July 14, 2010. Mr.
    Crenshaw and Ms. Steffey testified primarily regarding their
    plans for construction of the home, their concerns about the
    cracked tile, their interactions with Mr. Friedmann, and how the
    condition of the tile worsened over time. Three consultants,
    hired by [Appellees], testified regarding their inspections and
    their reports relative to the condition of the tile and the structural
    significance of the cracks. A real estate agent, an engineer, a
    licensed contractor, and tile installation specialist testified on
    behalf of Mr. Friedmann regarding the installation and
    replacement of the tile.
    The trial court entered an Order on October 15, 2010,
    awarding judgment to [Appellees] in the amount of
    $132,565.00; the court found that “the construction of the
    residence at 836 Plantation Way, Gallatin, Sumner County,
    Tennessee, by John H. Friedmann, Sr., failed to meet prevailing
    standards in the Sumner County Community for residential
    construction . . . .” In discussing the amount of the judgment, the
    court stated, in relevant part:
    [Appellees] present evidence of cost to repair to
    be $159,790.00 and [Mr. Friedmann] has one tile
    installer who gives an estimate of $12,432.00 and
    another who makes a quote of $14,750.00. The
    low estimates are to remove existing tile and
    install new tile. To limit the damages to just tile
    work is not just. More problems exist for
    correction than just replace [sic] the tile flooring.
    The estimated scope of work shown on Exhibit 26
    made to the testimony of Gene Hughes is realistic.
    The court awards a judgment in favor of
    [Appellees] for $132,565.00 which is cost of
    material and labor for estimated work at
    $118,362.00 and profit at 12% of $14,203.00
    ($118,362.00 plus $14,203.00 = $132.565 [sic] ).
    -4-
    On November 3, 2010, the trial court entered an Order awarding
    $4,252.00 in discretionary costs to [Appellees].
    On November 15, 2010, Mr. Friedmann filed a Motion to
    Alter or Amend requesting that the court alter the amount of the
    judgment by deducting the amount awarded for retiling the
    basement. The court granted the motion and reduced the
    judgment to $106,103.92.
    Friedmann I, 
    2012 WL 139062
    1, at *1–2. As noted above, in Friedmann I, we first
    determined that the trial court had, in fact, applied the correct measure of damages.
    Specifically, we reasoned:
    Mr. Friedmann argues that, because there has been no reduction
    in the value of the Plaintiffs’ property, they are not entitled to an
    award of damages. He also contends that the repair estimates are
    “inflated” and “grossly disproportionate to any reduction in
    value.”
    Tennessee courts have discussed two methods of
    measuring damages in actions for breach of a construction
    contract—cost of repair and diminution in value. See Wilkes [v.
    Shaw Enterprises, LLC, No. M2006-01014-COA-R3-CV,]
    
    2008 WL 695882
    , at *10 [(Tenn. Ct. App. March 14, 2008)].
    The distinction between the two measures has been summarized
    by our Court thusly:
    As a general rule, the measure of damages is the
    cost of correcting the defects or completing the
    omissions, rather than the difference in value
    between what ought to have been done in the
    performance of the contract and what has been
    done, where the correction or completion would
    not involve unreasonable destruction of the work
    done by the contractor and the cost thereof would
    not be grossly disproportionate to the results to be
    obtained. On the other hand, the courts generally
    adhere to the view that if a builder or contractor
    has not fully performed the terms of the
    construction agreement, but to repair the defects
    -5-
    or omissions would require a substantial tearing
    down and rebuilding of the structure, the measure
    of damages is the difference in value between the
    work if it had been performed in accordance with
    the contract and that which was actually done, or
    (as it sometimes said) the difference between the
    value of the defective structure and that of the
    structure if properly completed.
    
    Id. (quoting Edenfield
    v. Woodlawn Manor, Inc., 
    462 S.W.2d 237
    , 241 (Tenn. Ct. App. 1970); see also Mize v. Consulo,
    M2011-00455-COA-R3CV, 
    2011 WL 6152980
    (Tenn. Ct. App.
    Dec. 8, 2011). In sum, “[g]enerally, the measure of damages will
    be the cost [of] repair unless the repairs are not feasible or the
    cost is disproportionate to the [diminution] in value.” GSB
    
    Contractors, 179 S.W.3d at 543
    (quoting Radant v. Earwood,
    No. 02A01-9802-CV-00029, 
    1999 WL 418339
    , at *8 (Tenn. Ct.
    App. June 22, 1999)). Importantly, “[t]he burden is on the
    defendant to show that the cost of repairs is unreasonable when
    compared to the diminution in value due to the defects and
    omissions.” 
    Id. (citing Nutzell
    v. Godwin, 
    1989 WL 76306
    , at
    *1 (Tenn. Ct. App. July 13, 1989)).
    Thus, in order for the award of damages to be other than
    the cost of repair, it was incumbent upon Mr. Friedmann to offer
    proof showing diminution in value. See Nutzell, 
    1989 WL 76306
    , at *1–2 (affirming trial court’s use of cost of repair
    measure where defendant failed to produce evidence of
    diminution in value). The only proof Mr. Friedmann offered in
    this regard was the testimony of Susan Maddox-Reed, a realtor
    hired by [Appellees], who testified that the home was originally
    listed for sale in June 2007 for $1,150,000.000, that the price
    was subsequently reduced to $924,000.00, and that she was
    unable to sell the home. We do not find Ms. Maddox–Reed’s
    testimony to be probative evidence of diminution in value.
    In determining the diminution in value, comment b to the
    Restatement (Second) of Contracts § 347 provides the following
    guidance:
    -6-
    the loss in value caused by the breach is equal to
    the difference between the value that the
    performance would have had if there had been no
    breach and the value of such performance as was
    actually rendered. In principle, this requires a
    determination of the values of those performances
    to the injured party himself and not their values to
    some hypothetical reasonable person or on some
    market.
    Restatement (Second) of Contracts § 347 cmt. b []. Ms.
    Maddox-Reed testified regarding the listing price of the
    property, but she did not give an appraisal or other competent
    evidence of value or diminution in value. Moreover, in ruling
    that the cost of repair was the most appropriate measure of
    damages, the trial court implicitly held that the cost of repair
    was not unreasonable. We find no error in the trial court’s use
    of the cost of repair as the measure of damage in this case.
    Friedmann I, 
    2012 WL 139062
    1, at *6-7 (footnote omitted).
    Having concluded that the trial court used the appropriate measure of damages, we
    then proceeded to address the question of whether the trial court erred in the computation of
    damages. On this issue, we explained:
    The court based its determination of damages on the
    estimate of Gene Hughes, a licensed general contractor who
    testified at trial and submitted a written estimate which was
    made an exhibit to his testimony. Mr. Friedmann first contends
    that the trial court erred in relying on the estimate of Mr. Hughes
    because his testimony regarding repair costs was “excessive”
    and “speculative.” Mr. Friedmann also asserts that Mr. Hughes’
    estimate includes costs for repairs of items that were not
    identified by [Appellees] within the one-year time frame
    outlined in the contract and that the trial court erred in awarding
    damage for such repairs. Specifically, it is Mr. Friedmann’s
    contention that the trial court erroneously awarded damages for
    repair of the deck.
    We first consider Mr. Friedmann’s argument that Mr.
    -7-
    Hughes' testimony was speculative and excessive. The trial court
    stated the following regarding the written estimate and
    testimony of Gene Hughes:
    Gene Hughes testified that he has been a home
    builder for thirty five (35) years in the company of
    Hughes-Edwards Homes. From Exhibit 26 the
    court finds the first paragraph leads to a
    conclusion that the workmanship at 836
    Plantation Way did not meet the workmanship
    standards prevailing in the community. For repairs
    Mr. Hughes estimated costs to repair to be
    $159,790.00. His costs of repair reflected a 35%
    profit margin and thorough work on all aspects of
    repair. . . .
    . . . The estimated scope of work shown on
    Exhibit 26 made to the testimony of Gene Hughes
    is realistic.
    We find nothing in the record to preponderate against the
    trial court’s finding that Mr. Hughes’ estimate is “realistic” and
    “thorough.” Moreover, the trial court did not accept Mr.
    Hughes’ estimate wholesale; rather, the court made
    modifications to the amount of damages awarded by omitting
    damages for repair to the basement of the home and changing
    the profit margin to 12%. We find no error in the trial court’s
    acceptance of Mr. Hughes’ estimate rather than the estimates
    proffered by Mr. Friedmann. Mr. Hughes’ estimate also includes
    costs of repair for the basement, and the trial court included cost
    of repairing the basement in its original order; however, the trial
    court eliminated damages awarded for basement repairs in
    ruling on the motion to alter or amend.
    Mr. Friedmann also contends that [Appellees] did not
    notify him of some items included in the award of damages
    within the time frame outlined in the contract, and that,
    consequently, the award for those items was not available under
    the contract.
    -8-
    The trial court awarded damages in accordance with the
    repair estimate of Mr. Hughes.1 We have reviewed Mr. Hughes’
    estimate and note that the estimate includes repair costs for
    problems with the decking, contrary to paragraph 8 of the
    contract. For example, Mr. Hughes lists the “Estimated scope of
    work” to include: removal of tile on both back porches, removal
    of material under the tile, building up slope on porch floors,
    applying water proofing mat on porch floors, and installing new
    tile on porch floors. The portion of the estimate detailing the
    monetary amount for repair does not delineate which line items
    relate to problems with the deck.
    There is undisputed evidence that [Appellees] notified
    Mr. Friedmann regarding the cracked tile within one year of
    their occupancy of the home. However, there was no evidence
    indicating that either Mr. Crenshaw or Ms. Steffey noticed any
    issue with the deck within the one-year time frame outlined in
    the contract. In Bunch v. Cooper, buyers and sellers of a newly
    constructed home entered into a contract that disclaimed “all
    other warranties” and expressly warranted the materials and
    workmanship of the construction for one year. Bunch v.
    Cooper, No. 03A01-9705-CV-00154, 
    1997 WL 600150
    (Tenn.
    1
    The itemized estimate provides as follows:
    Crenshaw estimate: Cost
    Move furniture 1200[sic]
    R & R tile 1st floor 56,616
    2nd floor 15874[sic]
    Lumber 4,000
    Carpenter 14,000
    Electrical 850
    Move cabinet base 1,000
    Granite 4200[sic]
    Trim Material & Labor 2250[sic]
    Paint 1200[sic]
    Protective Material 250
    Dumpster 400
    Misc. 5000[sic]
    Rough clean up 3000[sic]
    Final Clean up 850
    -9-
    Ct. App. Sept. 30, 1997). Buyers discovered water problems
    with their home more than one year after moving in and sued
    sellers for recovery of damages. We held that the buyers could
    not avoid the one-year express warranty and were therefore
    unable to recover for the problems occurring outside of the
    one-year time frame. 
    Id. at *3.
    Likewise, we find that
    [Appellees] in this case should be limited to recovery for the
    cost of repairs they identified and complained of within the
    one-year period outlined in the contract. Therefore, we must
    vacate the judgment and remand the case for the trial court to
    determine the amount of damages not including repair work on
    the deck.
    Friedmann I, 
    2012 WL 139062
    1, at *7–8 (footnote in original).
    Upon remand from this Court, a hearing was held on February 1, 2013. The only
    testimony given at the remand hearing was from Gene Hughes, the original contractor. As
    discussed infra, Mr. Hughes relied upon his original estimate, but had his tile subcontractor
    submit separate bids for the porch and deck areas that were specifically excluded, under
    Friedmann I, from the damages. These separate estimates were calculated at the price
    applicable at the time of remand, which was less than the price-per-square-foot that was used
    to arrive at the original estimate. The trial court simply subtracted the separate estimates
    from the original estimate to arrive at the adjusted judgment. On February 19, 2013, the trial
    court entered its order, stating, in relevant part, that:
    1. The remand hearing is for this Court to determine the
    damages to the [Appellees’] home not including repair work on
    the deck, according to the opinion from the Court of Appeals,
    which the parties agree to mean the deck and screened-in porch.
    2. Gene Hughes rendered an estimate for the total amount of
    repairs needed to be done to the [Appellees’] home and he
    testified as to this at the original trial on behalf of the
    [Appellees]. Mr. Hughes was specifically found by this Court
    to be credible, and the Court relied upon Mr. Hughes’s
    testimony in rendering its judgment against [Mr. Friedmann] in
    the amount of $106,103.92. The amount of damages as opined
    by Mr. Hughes was upheld on appeal, with exception to the
    removal of the decking from his estimate as set forth above.
    -10-
    3. Mr. Hughes testified at the remand hearing as well regarding
    the estimate he prepared for repairs to solely the deck and the
    screened porch, and said repairs total $14,448.00. [Mr.
    Friedmann] did not offer any expert testimony to refute this
    amount.
    4. The Court again finds Mr. Hughes to be credible in his
    testimony and his estimate for repairs to the deck and screened
    porch are found to be reasonable. The Court therefore deducts
    the said $14,448.00 from the original judgment amount of
    $106,103.92; thus leaving a judgment against [Mr. Friedmann]
    in favor of [Appellees] in the amount of $91,655.92.
    On March 21, 2013, Mr. Friedmann filed a motion to alter or amend the foregoing
    judgment, or, in the alternative, for a new trial. Mr. Friedmann’s motion was denied by order
    entered on May 15, 2013. Mr. Friedmann appeals; he raises one issue for review as stated
    in his brief:
    In the prior appeal, the award of damages was vacated, and the
    case was remanded to the trial court to determine the cost of
    repairs that the [Appellees] identified and complained of within
    the one year period outlined in the contract. On remand, the
    [Appellees’] expert testified that he was not asked to review his
    previous estimate used at the prior hearing, he could not
    delineate which portions of the line items listed on his previous
    estimate were applicable to the damages complained of within
    the one year time limit, and that the price per square foot for
    replacement of tile on his new estimate was significantly lower
    than the price used in his earlier estimate. Under these facts, did
    the [Appellees] fail to prove their damages by a preponderance
    of the evidence.
    The purpose of assessing damages in a breach of contract action is to “place the
    plaintiff, as nearly as possible, in the same position he would have had if the contract had
    been performed.” Wilhite v. Brownsville Concrete Co., Inc., 
    798 S.W.2d 772
    , 775 (Tenn.
    Ct. App. 1990). A trial court’s determination regarding the proper amount of damages is a
    question of fact. GSB Contractors, Inc. v. Hess, 
    179 S.W.3d 535
    , 541 (Tenn. Ct. App.2005)
    (citing Beaty v. McGraw, 
    15 S.W.3d 819
    , 827 (Tenn. Ct. App.1998)). However, it is well
    settled that the amount of damages may not be exact in cases of breach of contract. As noted
    in 24 Samuel Williston, Treatise on the Law of Contracts § 64:8 (4th ed.):
    -11-
    [D]amages which are considered to be too remote and
    speculative are not recoverable [in a breach of contract case].
    "[W]here actual pecuniary damages are sought, there must be
    evidence of their existence and extent, and some data from
    which they may be computed.”
    The amount of damages must be established with
    reasonable, not absolute, certainty. The exact amount need not
    be shown, since mathematical precision is not required. It is
    sufficient if a reasonable basis for computation of damages is
    afforded, even though the result will only be approximate.
    
    Id. (footnotes omitted)
    (emphasis added).
    Because this case was tried by the court, sitting without a jury, we review the factual
    issue, concerning the proper amount of damages, de novo upon the record with a presumption
    of correctness. Tenn. R. App. P. 13(d). Unless the evidence preponderates against the trial
    court’s findings, we must affirm, absent error of law. 
    Id. In order
    for the evidence to
    preponderate against the trial court’s findings, it must support another finding of fact with
    greater convincing effect. Walker v. Sidney Gilreath & Assocs., 
    40 S.W.3d 66
    , 71 (Tenn.
    Ct. App. 2000). In addition, and as set out in its 
    order, supra
    , the trial court made specific
    findings that both Mr. Hughes’ testimony, and his estimate, were credible. It is well settled
    that when the resolution of the issues in a case depends upon the truthfulness of witnesses,
    the trial judge who has the opportunity to observe the witnesses and their manner and
    demeanor while testifying is in a far better position than this Court to decide those issues. See
    McCaleb v. Saturn Corp., 
    910 S.W.2d 412
    , 415 (Tenn. 1995); Whitaker v. Whitaker, 
    957 S.W.2d 834
    , 837 (Tenn. Ct. App. 1997). The weight, faith, and credit to be given to any
    witness’ testimony lies in the first instance with the trier of fact, and the credibility accorded
    will be given great weight by the appellate court. 
    Whitaker, 957 S.W.2d at 837
    ; see also
    Walton v. Young, 
    950 S.W.2d 956
    , 959 (Tenn. 1997).
    We first noted that, during the remand hearing, an issue arose concerning the scope
    of the trial court’s re-calculation of damages. As set out in full context above, in Friedmann
    I, we held that: (1) there was “no error in the trial court’s acceptance of Mr. Hughes’ estimate
    rather than the estimates proffered by Mr. Friedmann;” (2) the trial court correctly removed
    Mr. Hughes’ estimate for costs of repair for the basement in its ruling on the motion to alter
    or amend because Appellees had not complained of damage to the basement within the one-
    year warranty; (3) the Appellee “should be limited to recovery for the cost of repairs they
    identified and complained of within the one-year period outlined in the contract;” (4) the
    Appellees did not complain of damages to the decks (which, according to the order 
    appealed, supra
    , the parties’ agreed included both the deck and the screened porch) within the one year
    -12-
    warranty; (5) because Mr. Hughes’ estimate included, but did not delineate, those repairs
    associated with the deck and porch, and we could not determine these amounts from Mr.
    Hughes’ estimate, we vacated the judgment and remanded for re-calculation to exclude the
    deck and porch areas.
    As correctly noted in Appellees’ brief, the phrase “law of the case” refers to a legal
    doctrine which generally prohibits reconsideration of issues that have already been decided
    in a prior appeal of the same case. Memphis Publ’g Co. v. Tennessee Petroleum
    Underground Storage Tank Bd., 
    975 S.W.2d 303
    , 306 (Tenn. 1998) (citations omitted).
    Therefore, when an initial appeal results in a remand to the trial
    court, the decision of the appellate court establishes the law of
    the case which generally must be followed upon remand by the
    trial court, and by an appellate court if a second appeal is taken
    from the judgment of the trial court entered after remand. There
    are limited circumstances which may justify reconsideration of
    an issue which [] was decided in a prior appeal: (1) the evidence
    offered at a trial or hearing after remand was substantially
    different from the evidence in the initial proceeding; (2) the
    prior ruling was clearly erroneous and would result in a manifest
    injustice if allowed to stand; or (3) the prior decision is contrary
    to a change in the controlling law which has occurred between
    the first and second appeal.
    Memphis 
    Publ’g, 975 S.W.2d at 306
    (citations omitted). In Friedmann I, we vacated the
    original judgment and remanded for re-calculation of damages, excluding repairs to the porch
    and deck. We did not, as Appellees contend, limit the trial court’s ability to entertain
    additional, or different, evidence on this question. This is a point that the trial court
    understood and noted in its statement from the bench that: “the court did not intend to stop
    any testimony on the remand or any testimony put forward by [either party] relative to the
    damages issue.” However, we did not, as Appellant contends, mandate that the trial court try
    the issue of damages “from scratch,” nor did we require the damages for the excluded porch
    and deck to be determined in any particular way. Although we did not take issue with Mr.
    Hughes’ original testimony, or his original estimate, we could not determine what portions
    of the estimate were for work to the excluded areas, so as to adjust the judgment to exclude
    those costs.
    At the remand hearing, Mr. Hughes was the only witness. As set out above, the trial
    court made a specific finding that Mr. Hughes’ testimony at the remand hearing was credible,
    and we give great weight to findings concerning a witness’ credibility. Whitaker, 957 S.W.2d
    -13-
    at 837. In relevant part, Mr. Hughes testified as follows:
    Q. Mr. Hughes, did I understand that when you were asked . .
    . to prepare this new estimate that you did not go back and look
    at your old estimate, you just came up with a new one–
    A. That’s correct.
    *                                *                        *
    Q. So you don’t dispute that–and I can show you the estimate
    you had at the trial before [i.e., the original estimate], for
    instance, had $4 per square foot for tile as opposed to [$]3. Is
    that because the market rates have changed . . . .
    A. I didn’t go back and look at the other. I didn’t–typically we
    do [$]3. I don’t know why we did that [i.e., original estimate]
    [at] [$]4.
    *                                *                              *
    Q. And what is the reason that you’re now testifying to what
    works out to about $13 a square foot for the tile on the decks?
    Is it just because you’re using a different–
    A. What is $13?
    Q. Well, looking back at your . . . new estimate, you’ve got
    demo tile at $2 a square foot, correct?
    A. That’s correct.
    Q. The tile labor is $8 a square foot?
    A. That’s correct.
    Q. And then tile at $3 a square foot, so that’s–
    A. $13 a square foot.
    Q. $13 a square foot, versus [$]22 a square foot. You had [$]18
    plus [$]4–well, actually, it’s more than that because . . . you had
    some charges for grout, Ditra mat, and things like that.
    A. Setting materials, stuff like that.
    *                                  *                         *
    Q. Okay. But do [you] agree that your earlier estimate [i.e., the
    original estimate] was charging exactly the same amount per
    square foot for the decks as it was for the living room and other
    areas of the house, correct?
    -14-
    A. Based on [this] bid, yes.
    *                                         *                         *
    Q. And you have not gone back then and attempted to allocate
    out of your earlier estimate how much of that earlier estimate
    would have been for the main part of the house as opposed to
    the decks?
    A. No, I did not. This [i.e., the new estimates for the porch and
    deck areas] is strictly a–you asked me to bid it and that’s what
    I came up with as separate. I didn’t go back and refer to
    anything or extract anything [from the original bid].
    In addition, from Mr. Hughes’ testimony, it appears that there were additional costs
    associated with the excluded areas that appeared in the original estimate, but which were not
    excluded from the new estimates:
    Q. Lumber, $4,000 [in the original bid], how much of that
    lumber was strictly for the tile on the main floor?
    A. I don’t recall.
    Q. Okay. Carpentry, [$]14,000 [in the original bid], how much
    of that was strictly for carpentry work for the tile on the main
    floor?
    A. I don’t recall. That’s—majority of it was for the tile on the
    first floor . . . . The majority of it is the first floor.
    Q. Okay. Well, some of it would have been for correcting the
    slope on the porch [Mr. Hughes had previously testified that the
    slope of the porch was not correct, causing water to pool]?
    A. That’s correct.
    *                                     *                     *
    Q. But you can’t tell us today how much of this original bid was
    actually for lumber and carpentry on this part that had to be re-
    tiled on the main floor, not including the porches?
    *                                     *                         *
    A. I don’t know. I don’t have that broken down [].
    -15-
    In his brief, Mr. Friedmann argues, inter alia, that the damages in this case should
    have been calculated by taking the square footage of the main area of the house, which does
    not include the excluded deck and porch, and multiplying this area by $13 per square foot:
    It is not appropriate for the [Appellees] to use one price per
    square foot when evaluating the repair costs at trial and use a
    different amount when it benefits the [Appellees] to do so on
    remand. The award of $91,655.92 awarded by this Court on
    remand represents an average of $56.50 per square foot for the
    1,622 square feet of tile . . . . The amount awarded to the
    [Appellees] on remand for tile replacement, not including the
    decks, should not exceed $13 per square foot based on the
    current estimate, which would equal $21,086 (1,622 x $13 =
    $21,085).
    Thus, Mr. Friedmann assigns error to the fact that Mr. Hughes’ new estimate on the
    porch and deck areas was calculated at a rate of $13 per square foot and not at the original
    rate he used for his estimate in the first trial. Accordingly, Mr. Friedmann contends that the
    amount excluded (from porch and deck areas) was less than it should have been based upon
    the different cost-per-square-foot amounts used by Mr. Hughes in his original estimate and
    in his estimate for just the porch and deck areas, or alternatively, that the price per square
    foot for tile replacement in those areas included in the damages (i.e., the approximately 1,622
    square feet inside the house) should be calculated at no more than $13 per square foot.
    While the trial court was not under mandate to rely upon Mr. Hughes’ original
    estimate in amending the judgment to exclude the porch and deck areas, having chosen to do
    so, it seems axiomatic that in order to remove the excluded costs from the original estimate,
    not only would the trial court need to identify those portions of the original estimate
    chargeable to the excluded areas (including any extraneous items over-and-above the costs
    of demolition, tile, and labor–items such as Ditra board, lumber, electrical, paint, and the
    like), but it would also need to apply the same price-per-square-foot to the excluded areas as
    was used in the original estimate. In this way, the court would have been within the “law of
    the case,” because Appellees’ judgment would have been reduced by the full amount for the
    excluded areas that were included in Mr. Hughes’ original estimate as contemplated in
    Friedmann I.
    However, had the trial court included, in the order appealed, its reasoning for
    reducing the judgment at a lower price-per-square foot than was used in the original estimate,
    we would perhaps have sufficient guidance to decide the case on the merits. Tennessee Rule
    of Civil Procedure 52.01 provides, in relevant part, that: “In all actions tried upon the facts
    -16-
    without a jury, the court shall find the facts specially and shall state separately its conclusions
    of law and direct the entry of the appropriate judgment.” This Court has previously held that
    the General Assembly’s decision to require findings of fact and conclusions of law is “not
    a mere technicality.” In re K.H., No. W2008-01144-COA-R3-PT, 
    2009 WL 1362314
    , at *8
    (Tenn. Ct. App. May 15, 2009). Instead, the requirement serves the important purpose of
    “facilitat[ing] appellate review and promot[ing] the just and speedy resolution of appeals.”
    Id.; White v. Moody, 
    171 S.W.3d 187
    , 191 (Tenn. Ct. App.2004); Bruce v. Bruce, 
    801 S.W.2d 102
    , 104 (Tenn. Ct. App.1990). “Without such findings and conclusions, this court
    is left to wonder on what basis the court reached its ultimate decision.” In re K.H., 
    2009 WL 1362314
    , at *8 (quoting In re M.E. W., No. M2003-01739-COA-R3-PT, 
    2004 WL 865840
    ,
    at *19 (Tenn. Ct. App. April 21, 2004)). Without findings of fact, we cannot discern the basis
    for the trial court's decision, “and we are unable to afford appropriate deference to the trial
    court's decision.” In re Connor S.L., No. W2012-00587-COA-R3-JV, 
    2012 WL 5462839
    ,
    at *4 (Tenn. Ct. App. Nov. 8, 2012). Generally, the appropriate remedy when a trial court
    fails to make appropriate findings of fact and conclusions of law is to “vacate the trial court’s
    judgment and remand the cause to the trial court for written findings of fact and conclusions
    of law.” Lake v. Haynes, No. W2010-00294-COA-R3-CV, 
    2011 WL 2361563
    , at *1 (Tenn.
    Ct. App. June 9, 2011). However, this Court has indicated that we may “soldier on” with our
    review despite the trial court’s failure to make sufficient findings of fact and conclusions of
    law, in certain limited circumstances:
    On occasion, when a trial judge fails to make findings of fact
    and conclusions of law, the appellate court “may ‘soldier on’
    when the case involves only a clear legal issue, or when the
    court’s decision is ‘readily ascertainable.’” Hanson v. J.C.
    Hobbs Co., Inc., No. W2011-02523-COA-R3-CV, 
    2012 WL 5873582
    , at *10 (Tenn. Ct. App. Nov. 21, 2012) (quoting
    Simpson v. Fowler, No. W2011-02112-COA-R3-CV, 
    2012 WL 3675321
    , at *4 (Tenn. Ct. App. Aug. 28, 2012)).
    Pandey v. Shrivastava, No. W2012-00059-COA-R3-CV, 
    2013 WL 657799
    , at *5 (Tenn.
    Ct. App. Feb.22, 2013). Unfortunately, this is not one of those cases. Without some
    explanation to justify the use of one price-per-square foot in the original estimate, and a
    different price-per-square-foot in the new estimates for the deck and porch, it appears on its
    face that this method of calculation results in a windfall to the Appellees. In its 
    order, supra
    ,
    the trial court notes that “[Mr. Friedmann] did not offer any expert testimony to refute this
    amount [i.e., the new estimates for the deck and porch].” In the first instance, it was not
    incumbent upon Mr. Friedmann to do so as the burden of proof rested with Appellees to
    prove damages. As noted in 17B C.J.S. Contracts § 947: “In an action to recover damages
    for a breach of contract, it is incumbent on the plaintiff to prove the breach complained of
    -17-
    and his or her right to recover therefor. A plaintiff also has the burden of proving that
    damages arose from the breach, were caused by the breach, and the extent of those damages”
    (footnotes omitted); see also Cole v. Clifton, 
    833 S.W.2d 75
    , 77 (Tenn. Ct. App. 1992).
    However, Mr. Friedmann did, by Mr. Hughes’ own testimony on cross-examination,
    establish that the calculations for the deck and porch in the original estimate and the
    calculations for that work in the new estimates were not calculated at the same price-per-
    square-foot. In addition, Mr. Hughes’ testimony establishes that not all of the extraneous
    costs of repair to the excluded areas, which costs were included in the original estimate, were
    included in the new estimates for these areas. In this regard, Mr. Hughes’ testimony was not
    uncontested. From our review of the entire record, and in the absence of any Rule 52.01
    explanation for the use of different prices-per-square-foot between the two estimates, we
    conclude that the evidence preponderates against the trial court’s calculation for the deck and
    porch repairs.
    In addition, Mr. Friedmann also argues that some items listed in Mr. Hughes’ original
    estimate for repairs to the kitchen area should not be allowed as part of the damages amount.
    Specifically, he cites the $1,000 estimate to move a cabinet base, and the $4,200 estimate for
    granite. In Friedmann I, we concluded that the Appellees “should be limited to recovery for
    the cost of repairs they identified and complained of within the one-year period outlined in
    the contract.” This, too, is the law of the case. Because we must remand this case for further
    proceedings, the trial court may also, in its discretion, hear further proof concerning these
    disputed items to determine: (1) whether the Appellees complained of these items/areas
    within the one-year warranty period; (2) if so, whether they may recover damages; and (3)
    the amount of such damages. Neither our holding in Friedmann I, nor our holding here
    would preclude the trial court’s ability to allow the parties to argue these matters.2
    We vacate on the ground that Friedmann I required (as the law of the case) that
    Appellees not be awarded damages for any portion of the original estimate for areas they did
    not complain about within the one-year warranty. So, although we stated in Friedmann I
    that the trial court’s acceptance of Mr. Hughes’ original estimate was reasonable, we
    2
    Our holding herein, however, should not be interpreted as precluding the Appellees
    from arguing that Mr. Friedmann’s argument on these issues is waived by either his failure to raise
    these issues at trial and/or the failure to raise these issues in the first appeal. See Tenn. R. App. P.
    13(b) (“Review generally will extend only to those issues presented for review.”); see also Simpson v.
    Frontier Community Credit Union, 
    810 S.W.2d 147
    , 153 (Tenn.1991) (“[I]ssues not raised in the
    trial court cannot be raised for the first time on appeal.”). We are unable to determine from the
    record on appeal whether these issues were timely and properly raised by Mr. Friedmann. If Mr.
    Friedmann failed to raise these issues at trial or in his first appeal, he may, nevertheless, be precluded
    from arguing these issues on remand.
    -18-
    anticipated that those portions for the porch and deck would be removed from that estimate
    upon remand at the same rate that they were originally calculated, and that all extraneous
    costs for these areas (e.g., repairing the sub-floor, profit and overhead, moving furniture,
    painting, etc.) would also be removed from the original estimate at the same rate at which
    these items were originally calculated. From Mr. Hughes’ testimony, this was not done.
    Consequently, the trial court erred because it did not adhere to the law of the case. However,
    in Friedmann I, we did not go so far as to mandate that the trial court use Mr. Hughes’
    original estimate upon remand. Because it is clear that Mr. Friedmann did not get the benefit
    of having all of the costs of the excluded areas removed from the original estimate, and
    because the trial court did not explain (under Tennessee Rule of Civil Procedure 52.01) its
    reasons for allowing the excluded areas to be calculated at a lower price-per-square-foot, we
    conclude that the law of the case was not followed on remand. Consequently, we vacate
    again with these general directions. Upon remand, the court: (1) may arrive at the same
    judgment by using Mr. Hughes’ separate calculations; however, if it does so, it must explain
    its reasons for allowing the calculations to made using two different prices-per-square-foot;
    (2) may use Mr. Hughes’ original estimate, and instruct the parties to remove ALL costs for
    the excluded areas from the original estimate, using the same price-per-square-foot used in
    the original estimate; or (3) may allow the parties to re-try the issue of damages. In each of
    these scenarios, Friedmann I dictates that the basement area, the porch, the deck, and any
    items not complained of within the one year warranty should be determined and then
    excluded from the judgment. In providing these parameters, we do not wish to precisely
    dictate the method the trial court may use to calculate damages in this case. If, upon remand,
    the trial court determines that an option, other than those enumerated herein, is warranted or
    will serve the parties better, it is not precluded from applying that option so long as it does
    not interfere with the law of the case as outlined herein, and in Friedmann I.
    For the foregoing reasons we vacate the order of the trial court and remand for such
    further proceedings as may be necessary and are consistent with this Opinion. Costs of the
    appeal are assessed one-half to the Appellant, John H. Friedmann, Sr., and his surety, and one
    half to Appellees, Consulting & Financial Services, Inc. and Paul Crenshaw, for all of which
    execution may issue if necessary.
    _________________________________
    J. STEVEN STAFFORD, JUDGE
    -19-