Gulf Insurance Co. v. Construx, Inc. ( 2001 )


Menu:
  •                   IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    September 8, 1999 Session
    GULF INSURANCE CO. v. CONSTRUX, INC., ET AL.
    Appeal from the Chancery Court for Williamson County
    No. 24472    Russ Heldman, Chancellor
    No. M1999-02803-COA-R3-CV - Filed July 26, 2001
    This is an appeal from the grant of Plaintiff’s motion for summary judgment. The case arises from
    a construction contract in which Gulf Insurance Co. provided Construx, Inc. the required payment
    and performance bonds, and in return obtained an indemnity contract with the individual Defendants
    as indemnitors. Additionally, a Settlement Agreement was executed in connection with the
    permanent loan financing and Gulf settled the subcontractor liens with the remaining proceeds of
    the construction loan. After payments were made, Gulf sued for indemnity under the indemnity
    contract for payments made. Construx asserted that the Settlement Agreement barred Plaintiff’s
    claims or, alternatively, Gulf did not act reasonably and in good faith in settling the claims and is not
    entitled to recovery. Summary judgment was granted to Gulf and Construx appealed. For the
    reasons below, we reverse and remand finding that there are genuine issues of fact, making summary
    judgment inappropriate.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Reversed and Remanded
    PATRICIA J. COTTRELL , J., delivered the opinion of the court, in which WILLIAM FRANK CRAWFORD
    and WILLIAM B. CAIN , JJ., joined.
    James Robert Buckner, Alan Daniel Hall, Richard Christopher Rose, Chattanooga, Tennessee, for
    the appellant, Construx, Inc., et al.
    Richard McCallister Smith, Nashville, Tennessee, for the appellee, Gulf Insurance Co.
    OPINION
    This is an appeal from the grant of a motion for summary judgment to Gulf Insurance
    Company and an award of damages in the amount of $42,587.74 and attorney’s fees totaling
    $85,763.44 for a total award of $128,351.18.
    I. Background
    In July 1994, Construx, the general contractor, entered into a contract with Roger Patel, doing
    business as Days Inn Incorporated, to build a Comfort Inn in Franklin, Tennessee. In connection
    with this contract, Construx was required to provide a payment and performance bond to ensure
    performance of the contract and payment to all subcontractors. Gulf Insurance Company, as surety,
    issued a performance bond and a payment bond to Construx, Inc. as principal. Joseph Amszynski
    and Deborah Silverstein executed a General Agreement of Indemnity indemnifying Gulf for claims
    upon the bonds. The bonds were executed on September 7, 1994, and the Indemnity Agreement was
    executed on October 26, 1994.
    The construction project was complete in November of 1995. At the time of completion,
    there was approximately $165,000 remaining on the construction loan. Just prior to completion,
    several subcontractors began filing liens and claims for work and materials supplied but not paid for
    by Construx. In order to obtain the permanent financing on the project, the liens and claims by the
    subcontractors needed to be resolved prior to closing. Therefore, in early 1996, Mr. Patel, Gulf,
    Construx and First Tennessee Bank, the lender, discussed a Settlement Agreement to resolve all liens
    and claims of the subcontractors, closing of the permanent loan and distribution of the remaining
    $165,000.00 left on the construction loan proceeds. All of the negotiations between Gulf and
    Construx pertaining to the Settlement Agreement were made between Gulf’s attorney, Richard
    Smith, and the Defendant, Joseph Amszynski.
    Mr. Amszynski claims that he was induced to enter the Settlement Agreement based on
    representations by Gulf’s attorney that all claims could be settled for $110,000.00 and that attorney’s
    fees would amount to no more than $10,000.00. The parties agree that a Settlement Agreement was
    entered into in early February of 1996, among Mr. Amszynski, Gulf, First Tennessee and Mr. Patel.
    Mr. Patel received, under the agreement, $30,000 of the $165,000 remaining as proceeds from the
    construction loan or contract, and Construx released the rest to Gulf to settle claims and to distribute
    any “savings” after such settlement according to the terms of the agreement. Construx also executed
    a release for claims against Mr. Patel and First Tennessee. Both parties agree that the Settlement
    Agreement provided that if the claims were settled for a total amount less than $135,000,1 “any
    savings” would be divided by payment to the owner, Mr. Patel, of seventy percent (70%) and
    payment to the contractor, Construx, of thirty percent (30%).2
    1
    Actually, one party asserts that the amount stated in the agreement, after revision, was $134,640.65.
    2
    Gulf, however, w ould assert it wa s entitled to Co nstrux’s 30% o f the “savings” p ursuant to another provision
    of the agreem ent if there had b een any “savin gs.”
    2
    After the Settlement Agreement was purportedly3 executed, Mr. Smith requested Construx
    to direct all subcontractor claims to him for settlement negotiations. Construx agreed. Prior to the
    Settlement Agreement, Construx had already provided Gulf records regarding subcontractor claims
    and continued to provide records to facilitate settlements including balance sheets, accounts
    receivable, accounts payable, offsets, credits and back charges.
    Gulf settled all the claims regarding the construction project. During the settlement
    negotiations, Construx protested the payment of various amounts proposed by Gulf. The total of the
    amount paid out by Gulf in settlement of the claims was $177,228.39.
    Gulf filed suit against Construx and the individual guarantors, Mr. Amszynski and Ms.
    Silverstein, seeking recovery of payments Gulf made to subcontractors to settle claims against Gulf’s
    payment bond, which Gulf claimed was $42,587.74.4 The complaint also sought recovery of
    attorneys’ fees and expenses incurred by Gulf as a result of the settlement process and this litigation.
    Defendants answered and asserted that Gulf’s claims were barred by the Settlement Agreement
    between the parties. They also asserted that Gulf had paid excessive, invalid, and disputed
    subcontractor claims.
    Gulf filed a motion for judgment on the pleadings, which was opposed by Defendants. The
    trial court denied the motion, ruling that there were “genuine issues as to the amount, if any, of
    Plaintiff’s claim against Defendants.” Gulf later filed a motion for summary judgment, seeking
    $105,617.06 in damages incurred to that point.
    Defendants responded arguing there were genuine issues of material fact as to whether Gulf’s
    agreements with, and representations to, Defendants regarding the Settlement Agreement barred Gulf
    from recovery. They also asserted that genuine issues of material fact existed regarding the
    reasonableness and good faith in Gulf’s payments to subcontractors.
    After a hearing, the trial court granted Gulf’s motion, awarded Gulf $105,617.06 in damages,
    and directed Gulf to submit evidence regarding its claim for additional expenses. When documents
    supporting those claims were filed, Defendants objected to this “alleged evidence.” Various
    additional filings and objections took place. The trial court granted partial summary judgment on
    the $105,617.06 already awarded and set a hearing on the new expenses. The trial court later entered
    an order awarding Gulf the total amount of its claimed damages, $128,351.18.
    Defendants had filed a motion to alter or amend the original summary judgment ruling, and
    Gulf responded. Four days after the hearing on this motion, Gulf filed a Notice of Filing a document
    3
    W e use the word “purportedly” in this recitation of the facts because, as will be discus sed later in this opinion,
    although both parties claim the existence of an executed agreement, the record before us leaves some question on that
    point.
    4
    The parties appear to agree that Gulf, pursuant to the Settlement Agreement, received $134,640.65 from the
    remaining construction loan p roceeds.
    3
    it contended was the final executed version of the Settlement Agreement. Defendants had originally
    filed the purported Settlement Agreement with their answer and Mr. Amszynski’s affidavit. The two
    documents are not identical.
    II. Summary Judgment
    A trial court’s grant of a motion for summary judgment presents a question of law that we
    review de novo without a presumption of correctness. Finister v. Humbolt Gen. Hosp., Inc., 
    970 S.W.2d 435
    , 437 (Tenn. 1998); Robinson v. Omer, 
    952 S.W.2d 423
    , 426 (Tenn. 1997). We must
    determine whether there is no genuine and material factual issue, thereby entitling movant, Gulf, to
    judgment as a matter of law. In making this determination, we view the evidence in the light most
    favorable to the non-movant and draw all reasonable inferences in the non-movant’s favor, affirming
    the summary judgment only when the facts and inferences permit a reasonable person to reach but
    one conclusion.
    Accordingly, the appellate court must make a fresh determination concerning whether the
    movant has met the requirements of Tenn. R. Civ. P. 56. Hunter v. Brown, 
    955 S.W.2d 49
    , 50-51
    (Tenn. 1997); Mason v. Seaton, 
    942 S.W.2d 470
    , 472 (Tenn. 1997). Summary judgment is only
    appropriate if the pleadings, depositions, answers to interrogatories and admissions on file, together
    with the affidavits, if any, show there is no genuine issue as to any material facts and the moving
    party is entitled to a judgment as a matter of law. Tenn. R. Civ. P. 56.04; Bain v. Wells, 
    936 S.W.2d 618
    , 622 (Tenn. 1997); Carvell v. Bottoms, 
    900 S.W.2d 23
    , 26 (Tenn. 1995); Byrd v. Hall, 
    847 S.W.2d 208
    , 214 (Tenn. 1993).
    Consequently, the questions a court must consider in determining whether to grant or deny
    a motion for summary judgment are (1) whether a factual dispute exists; (2) whether that fact is
    material; and (3) whether that fact creates a genuine issue for trial. Byrd v. Hall, 847 S.W.2d at 214.
    “A disputed fact is material it if must be decided in order to resolve the substantive claim or defense
    at which the motion is directed.” Id. at 215. A disputed material fact creates a genuine issue if “a
    reasonable jury could legitimately resolve that fact in favor of one side or the other.” Id. The phrase
    “genuine issue “ refers exclusively to factual issues and not to legal conclusions that could be drawn
    from the facts. Id. at 211.
    Once the moving party documents its assertion that there is no genuine issue of material fact,
    the burden then shifts to the nonmoving party to show the existence of such issue, requiring
    submission to the trier of fact. Id. at 215. The nonmoving party cannot simply rely on its pleadings,
    but rather must set forth, by affidavit or discovery materials, specific facts showing a genuine issue
    of material fact for trial. Id. The evidence offered by the nonmoving party must be taken as true.
    Id. Finally, summary judgment shall be denied if there is “any doubt whether or not a genuine issue
    exists.” Id. at 211.
    A court reviewing summary judgments must view the evidence in the light most favorable
    to the nonmoving party and must also draw all reasonable inferences in the nonmoving party’s favor.
    4
    Robinson v. Omer, 
    952 S.W.2d 423
    , 426 (Tenn. 1997); Mike v. Po Group, Inc., 
    937 S.W.2d 790
    , 792
    (Tenn. 1996). Thus, a summary judgment should be granted only when the undisputed facts
    reasonably support one conclusion - that the moving party is entitled to a judgment as a matter of
    law. McCall v. Wilder, 
    913 S.W.2d 150
    , 153 (Tenn. 1995); Carvell v. Bottoms, 900 S.W.2d at 26.
    In its grant of summary judgment, the trial court held “there are no genuine issues of material
    fact and summary judgment should be entered in favor of the Plaintiff and against Defendants.”
    In this appeal, Defendants, Construx and the individual indemnitors, first argue that summary
    judgment in Gulf’s favor was not warranted because genuine issues of material fact exist as to
    whether Gulf’s claims are barred by the Settlement Agreement and related representations. In this
    regard, Defendants rely on their asserted affirmative defenses of estoppel and accord and satisfaction.
    Defendants also assert that Gulf was not entitled to summary judgment because genuine issues of
    material fact exist as to whether Gulf acted reasonably and in good faith in settling the subcontractor
    claims.5
    III. The Settlement Agreement
    Defendants have defended on the basis of the Settlement Agreement, and Gulf has relied on
    specific provisions of that document in its argument. However, there is a dispute as to which version
    of the Settlement Agreement was executed and in effect between the parties. Both Plaintiff and
    Defendants assert that such an agreement exists, but each relies on a different version.
    At the time the Plaintiff’s motion for summary judgment was decided, there was only one
    version before the court. This first version, the “Construx version” was filed with Construx’s answer
    and an affidavit by Mr. Amszynski identifying it as the agreement signed by the parties. Gulf did
    not challenge this version as the accurate documentation of the parties’ agreement until it filed its
    Notice of Filing while Defendants’ motion to alter or amend the grant of summary judgment was
    pending. That document gave notice of filing the “attached copy of the fully executed Settlement
    Agreement, dated February 8, 1996. Plaintiff would show unto the Court that the document which
    Defendants have relied upon is a draft and not the original executed agreement.” Attached to the
    Notice was the “Gulf version.” Construx responded to the notice by asserting it was too late in the
    proceedings for new evidence to be filed and that there were questions concerning the validity and
    execution of the “Gulf version,” including the authority of the surety to modify the prior version of
    the agreement without authority from the indemnitor.
    After these filings, the trial court denied the motion to alter or amend and made no reference
    to the differing versions of the agreement. Gulf acknowledges that “there is some confusion as to
    the appropriate version of the Settlement Agreement.” It refers to the version it submitted, after the
    motion to alter and amend the judgment granting summary judgment, as “the fully executed version
    relied on by Gulf.” It refers to the version submitted by Defendants along with their answer as the
    5
    In addition, D efendants assert the damages, expenses and fees, awarded by the court were excessive, not
    supporte d by evide nce, and no t demonstra ted to be re asonable and neces sary.
    5
    “unexecuted version relied on by Construx.” Construx maintains the version it filed is the only one
    properly in the record, that the two versions are identical with respect to material issues, and that
    even if they were different, an issue of fact would be created.
    The presence in the record before us of two versions of the Settlement Agreement creates
    issues whose resolution by the trial court is not apparent. Because there are unexplained
    discrepancies in the execution of each of the versions, and because the two versions differ as to
    particular relevant provisions, there are questions as to the actual terms agreed to by the parties.
    As noted above, Gulf asserts that the “Gulf version” is the executed, original Agreement.
    The document was executed, however, on behalf of Construx by the same party who signed for Gulf
    as its Attorney of Record. The attorney’s signature on the line for Construx includes the notation
    “for J. Amszynski per power of attorney.” After searching the voluminous technical record, we have
    discovered a Limited Power of Attorney signed by Mr. Amszynski giving Gulf’s attorney certain
    authority, apparently relating to actions necessary to close the permanent financing on the motel by
    February 1, 1996. The power of attorney is limited to specific actions and expired at 6:00 p.m. on
    February 1, 1996. The Notice of Filing indicates the “Gulf version” of the Settlement Agreement
    was executed on February 8, and the agreement itself states it was executed on that date. There is
    no testimony or other evidence in the record regarding the execution of the “Gulf version.”6
    In fact, its filing was unaccompanied by any affidavit.
    The “Construx version” states it was executed February 1, 1996. That version also raises
    questions about its execution. As filed, the document has two signature pages. Construx’s signature
    block appears on the first, and is signed by Mr. Amszynski as President, not by anyone else using
    a power of attorney or other permission. The other signature block on that page, for Mr. Patel, is
    blank. The second signature page, however, is obviously not sequential to the first. It includes text
    from the body of the agreement above the signature lines and includes signature blocks for all
    parties. It appears to be a photocopy of the signature page that is contained in the “Gulf version”
    because the signatures on the first two signature lines are exactly the same as those in the “Gulf
    version,” (meaning that the second signature page includes a signature block for Construx that is
    signed by the attorney for Construx, “per power of attorney.”) However, the third signature block,
    for the lender, is blank on the “Construx version” and filled in on the “Gulf version.”
    In view of Contrux’s questioning the “Gulf version” as validly executed,7 we have attempted
    to find anything in the record to shed light on which version, if either, all parties actually executed.
    6
    W e do not sugg est any impro priety in the execution of the document, merely confusion based on the record
    before us.
    7
    We ar e aware that b oth versions allow the agre ement to b e signed “in o ne or mo re counterp arts or dup licate
    signature pages” and state, “Any one or more such counterparts or duplicate signature pages may be removed from any
    one or m ore origina l copies of this A greement a nd annexe d to other coun terparts or duplicate signature pages to form
    a completely executed instrument.” Without testimony or other explanation, we are unable to tell which, if either, version
    is the “comp letely executed instrument.”
    6
    No testimony or other evidence was taken on this issue, and the trial court did not rule on the correct
    version. We are unable to do so based on the record before us. This situation creates some
    difficulties with regard to summary judgment because both parties rely on the agreement or specific
    provisions of it for their positions. Neither version contains all of those provisions, and we disagree
    that the versions are identical with respect to terms that are material to the issues before us. We will
    discuss the issues presented by the two versions in the context of the substantive issues.
    IV. Whether the Settlement Agreement Bars Additional Recovery
    Gulf’s complaint sought to enforce the obligations undertaken by Defendants in the
    Agreement of Indemnity. In particular, Gulf alleged it was entitled to reimbursement for payments
    made and expenses incurred in settlement of claims under the payment bond by virtue of the
    following provision of the Indemnity Agreement:
    That the Indemnitor will perform all the conditions of each said bond or obligation,
    and any and all alterations, modifications, renewals, continuations, and extensions
    thereof, and will at all times indemnify and save the Company [Gulf Insurance]
    harmless from and against every claim, demand, liability, loss, cost, charge, counsel
    fee, payable on demand of Surety, whether actually incurred or not, (including fees
    of special counsel whenever by the Company deemed necessary) expense, suit, order
    judgment and adjudication whatsoever, and any and all liability therefore, sustained
    or incurred by the Company by reason of having executed or procured the execution
    of said bonds or obligations, and will place the Company in funds to meet same
    before it shall be required to make payment, and in case the Indemnitor requests the
    Company to join in the prosecution or defense of any legal proceeding, the
    Indemnitor will, on demand of the Company, place it in funds sufficient to defray all
    expenses and all judgments that may be rendered therein.
    Thus, this lawsuit is based on the Indemnity Agreement, and Gulf’s complaint asserts that,
    under that agreement, Construx and the individual indemnitors are obligated to indemnify and hold
    Gulf harmless from all liability, loss, damages, and fees of attorneys and other expenses resulting
    from Gulf’s issuance of a payment and performance bond in favor of Construx. The complaint
    further alleges that Gulf paid claims and made demands on the indemnitors to be held harmless and
    the indemnitors failed to pay.
    Defendants answered and defended on the basis that Gulf’s claims are barred by the
    Settlement Agreement and representations and agreements made in connection with the Settlement
    Agreement. Defendants assert that all claims between the parties were settled, compromised, or
    otherwise disposed of by the Settlement Agreement. They argue that, in entering into the agreement,
    Construx released any claims it might have against the owner and the lender, agreed to give $30,000
    to the owner out of the remaining construction loan/construction contract proceeds, and agreed to
    turn over the rest to Gulf for settlement of claims and distribution in accordance with the agreement.
    Defendants assert that, absent the Settlement Agreement, Gulf would not have been entitled to the
    7
    proceeds from which to settle claims. Further, Construx agreed to allow Gulf to negotiate directly
    with the claimants and to use its expertise to settle the claims.
    Defendants further asserted that Gulf was estopped from seeking additional payment from
    the indemnitors because Gulf had induced Construx to enter into the Settlement Agreement by
    assurances that Gulf would settle all subcontractor claims for a maximum of $120,000 including
    attorney fees. Defendants submitted an affidavit and deposition testimony of Mr. Amszynski that
    he relied upon Gulf’s representations that it could settle all subcontractor claims for less than
    $110,000 and that related attorney fees would amount to less than $10,000. At the time these
    representations were allegedly made, Gulf had been furnished information from Construx regarding
    the outstanding claims. Mr. Amszynski states that Gulf’s attorney assured him Gulf could “buy
    down” the claims to under $110,000. According to Defendants, they released all claims they may
    have had against the owner and the lender and released most of the remainder of the construction
    loan proceeds to Gulf in reliance upon these representations. This understanding, they assert,
    explains the Settlement Agreement’s disposition of “any savings” if the claims were settled for less
    than the $135,000 left in loan proceeds released to Gulf.
    Construx also relied in part on a letter, written before the Settlement Agreement was
    executed, from the owner’s attorney to Gulf proposing a settlement procedure wherein Gulf would
    settle all subcontractor claims for not more that $110,000 in the aggregate.8 This letter was sent two
    days after that attorney was provided by Gulf with a list of outstanding claims, along with the
    amounts Construx claimed were owed. The total amount claimed by subcontractors was
    $178,142.11, and Construx claimed that only $100,762.24 was actually owed.
    Defendants argue that they released all claims they may have had against the owner, agreed
    to allow Gulf to settle claims using the remaining contract or loan proceeds, and gave up claim to
    most of the those proceeds, agreeing to give the owner $30,000, and receiving only 30% of any
    savings from settlement of the claims for less than $135,000, in reliance upon Gulf’s promise that
    it would settle the claims for less than $120,000, including attorney fees.
    Defendants also asserted that Construx’s release of the remaining proceeds from the
    construction loan, along with other consideration evidenced by the Settlement Agreement,
    constituted an accord and satisfaction of any claims by Gulf against Construx or the individual
    indemnitors. They assert that Construx provided Gulf with the remaining construction loan proceeds
    (a material consideration to which Gulf would not have otherwise been entitled) in exchange for Gulf
    using its expertise to settle all subcontractor claims for a total of $120,000. Both parties, Defendants
    assert, intended this and other consideration to act as an extinction of Construx’s or the individual
    indemnitors’ obligation to reimburse Gulf for subcontractor payments and attorney fees beyond the
    $135,000 given to Gulf for such purposes under the Settlement Agreement. Construx gave up its
    8
    The owner Mr. Patel, apparently had an interest in the amount paid to subcontractors because he ended up
    negotiating a provision in the agreement to provide him the greater portion of any savings between the settlement amount
    and the co nstruction co ntract amou nt (or remain ing loan pro ceeds).
    8
    claim to most of the remaining loan/contract proceeds, and Gulf was provided a pool of money, not
    its own, from which to make payments to claimants. Thus, Defendants assert, the acceptance by
    Gulf of the loan proceeds and execution of the Settlement Agreement constituted an accord and
    satisfaction, barring Gulf from asserting claims against Defendants for further reimbursement.
    In response, Gulf contends that the Settlement Agreement does not expressly limit the
    amounts Gulf could use to settle payment bond claims or attorney fees; that the agreement contains
    no arrangement as described by Defendants; but that the agreement expressly preserves Gulf’s rights
    under its payment bond. Gulf further asserts that the Settlement Agreement does not modify the
    rights and obligations of the parties to the payment bond or the Indemnity Agreement. In essence,
    Gulf relies on specific language of the Settlement Agreement and asserts that “the document speaks
    for itself.”
    Gulf argues that the Settlement Agreement is unambiguous, relying on several provisions
    of the agreement. Gulf insists that the Settlement Agreement itself does not include an agreement
    by Gulf to limit settlement of subcontractor claims and attorney fees to $135,000, but that Gulf
    merely agreed to pay any savings, if the claims were settled for under $135,000, to the owner and
    Construx.9 Gulf also relies on the provision in which Gulf agreed to continue to honor its obligations
    to pay the claims of subcontractors and suppliers under the payment bond. Thirdly, Gulf relies on
    a provision which states, “[t]his Settlement Agreement shall not be deemed to be a waiver of any
    rights, remedies, and/or defenses which the Surety may have under its Payment Bond or otherwise.”
    Finally, Gulf relies on a provision appearing only in the “Gulf version” wherein Construx
    specifically ratifies the Indemnity Agreement.
    Gulf did not dispute the factual allegations of Construx regarding the parties’ intent that the
    Settlement Agreement extinguish all claims under the Indemnity Agreement. Instead, Gulf relied
    on the document and argued that Defendants must rely on parol evidence to create their issue, and
    that parol evidence is not admissible when the parties’ intentions can be found in the contract itself.
    Citing Freeze v. Home Fed. Sav. & Loan Ass’n. of Manchester, 
    623 S.W.2d 109
    , 112 (Tenn. Ct.
    App. 1981) (citations omitted), Gulf argues that Mr. Amszynski’s testimony, as well as the above
    described letter, is parol evidence, which cannot be used “to vary, add to, detract from, or contradict
    the terms of a document, or to modify its legal import.” Similarly, Gulf asserts that Defendants must
    rely on parol evidence to make its estoppel argument because the Settlement Agreement does not
    include any provision expressly limiting the amount which Gulf could incur in payment of
    subcontractor claims. Relying on Womble v. Dortch, 1984 Tenn. App. LEXIS 3268 ( Nov. 1, 1984),
    Gulf asserts that Construx cannot defeat summary judgment by relying on parol evidence where a
    claim predicated on estoppel is grounded upon oral promises made prior to the written contract that
    integrated the parties’ agreement.
    A. The Provisions of the Agreement
    9
    The “G ulf version” wo uld give Co nstrux’s share o f any savings to G ulf.
    9
    The primary dispute is whether the Settlement Agreement bars, or evidences the parties’
    intent that it bar, any additional liability under the Indemnity Agreement. As a general rule, the
    interpretation of a clear and unambiguous contract is a question of law for the court and the court’s
    role is to interpret the contract according to its plain terms. Hardeman County Bank v. Stallings, 
    917 S.W.2d 695
    , 699 (Tenn. Ct. App. 1995) (citing Malone & Hyde Food Serv. v. Parson, 
    642 S.W.2d 157
    , 159 (Tenn. App. 1982)); Estate of Haynes v. Braden, 
    835 S.W.2d 19
    , 21 (Tenn. Ct. App. 1992)
    (citations omitted); Woodmen of the World Life Ins. Soc’y v. Bank of Waynesboro, 
    826 S.W.2d 915
    ,
    918 (Tenn. Ct. App. 1991) (citing 88 C.J.S. Trial § 217 (1955)); Krantz v. Overfelt’s Discount
    Realty, Docket No. 01A01-9311-CH-00501, 
    1994 WL 164091
     at *4 (Tenn. Ct. App. May 4, 1994)
    (no Tenn. R. App. P. 11 application filed) (citing Strickland v. City of Lawrenceberg, 
    611 S.W.2d 832
     (Tenn. App. 1980)). “It is incumbent upon this court to enforce contracts according to their
    plain terms.” Hardeman County Bank v. Stallings, 
    917 S.W.2d 695
    , 699 (Tenn. Ct. App. 1995)
    (citing Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc., 
    521 S.W.2d 578
    , 580 (Tenn.
    1975)).
    Both parties have relied on the Settlement Agreement, although they apparently do not agree
    on the terms of such agreement. Both versions contain the following language:
    WHEREAS, there exists several outstanding issues for Construx, Patel, the10 First
    Tennessee Bank and Gulf to resolve: namely, (i) the release of outstanding
    mechanics, materialmen and suppliers’ lien, (ii) the resolution of actions to enforce
    mechanics lien arising out of the construction, (iii) reimbursements claimed by Patel
    for payments made on behalf of Construx under the construction contract, (vi) [sic]
    such other claims or defenses Construx, Patel, First Tennessee Bank and Gulf might
    have under the terms of the Payment Bond, Performance Bond and contract, (vii)
    such other claims as Gulf or Construx may have against Patel and or First Tennessee
    Bank. To insure the proper resolution of the outstanding issues referred to herein and
    without enlarging or expanding Surety’s obligations under the Payment and
    Performance bonds and without waiving the penal sum set forth in the Payment and
    Performance bonds and in order to limit the potential liability of Construx in the
    event Patel is unable to close the East Ridge loan on or before February 1, 1996 since
    the East Ridge commitment to make the loan expires that date, Construx, Patel, First
    Tennessee Bank and Gulf have agreed to enter into this Agreement to resolve the
    issues herein and to disburse the remaining construction loan proceeds presently held
    by First Tennessee Bank;
    WHEREAS, the parties acknowledge that remaining contract proceeds are in the
    amount of $165,000;11
    10
    The “Construx version” includes this “the” and the “Gulf version” does not. Otherwise, the provisions are
    identical, including the misnumbering of items.
    11
    The “Gulf version” reflects this figure, in typewritten form, as $164,640.65.
    10
    NOW, THEREFORE, in consideration of the premises and other good and valuable
    consideration, receipt and sufficiency of which are hereby acknowledged, the parties
    agree as follows:
    1. Patel and First Tennessee Bank agree to accept the project12 and will retain
    $30,000 of remaining contract proceeds to be disbursed directly to Patel upon
    closing.
    2. Construx and the Surety13 agree to accept remaining contract proceeds subject to
    the conditions set forth herein.
    4.14 The Bank hereby agrees to disburse to the Surety the sum of $135,000.0015 of
    remaining contract proceeds subject to the conditions set forth herein.
    The provision of perhaps greatest significance to the issues in this appeal appears as
    paragraph 6 of the “Construx version” and as paragraph 4 of the “Gulf version.” We begin with the
    “Construx version.”
    Gulf will utilize remaining contract proceeds in the amount of $135,000.00 to
    discharge such obligations as it may have pursuant to its Payment Bond to suppliers
    and subcontractors in direct privity of contract with Construx. The Surety will
    continue to honor such obligations as it may have pursuant to its Payment Bond to
    third party suppliers and subcontractors who have direct contractual privity with
    Construx. This Settlement Agreement shall not be deemed to be a waiver of any
    rights, remedies and/or defenses which the Surety may have under its Payment Bond
    or otherwise. This Settlement Agreement shall not be deemed to in any way expand
    Gulf’s obligations and/or liabilities under the Payment Bond. In the event that
    settlement of the aggregate amount of outstanding valid Payment Bond claims is less
    than $135,000.00, then any savings shall be divided between Patel and Construx with
    Patel receiving 70% of the total sums saved.
    In the “Gulf version,” the figure $135,000 has been corrected, by hand, to $134,640.65, and
    the word “Gulf” has been substituted, by typewritten change, for the words “the Surety.” The most
    12
    The “Co nstrux version ” included the phrase “a s is” at this point.
    13
    The “G ulf version” sub stitutes “Gulf” for “th e Surety.”
    14
    The “Construx version” had another provision preceding this one, numbered 3 in that version, which is not
    relevant to the issues under d iscussion. T hat provisio n does no t appear a s paragrap h 3 in the “Gu lf version.”
    15
    On the “Gulf versio n,” the typed $ 135,00 0.00 has b een marke d out, and th e figure $13 4,640.65 has been
    handwritten in its place, and the change is initialed by one party “GR C.” In add ition, in the “Gulf version,” the words
    “First Tenn essee Ba nk and P atel” are sub stituted for the wo rd “Bank .”
    11
    significant difference, however, is the addition in the “Gulf version” of the following sentence at the
    end of the provision: “Construx agrees that any savings due it shall be assigned to and be the
    property of Gulf.”
    In addition, the “Gulf version” includes the following provision, which is absent from the
    “Construx version:” “Construx does hereby ratify and confirm that the terms of any General
    Agreement of Indemnity remain in full force and effect.”
    B. Genuine Issue
    Gulf argues that Defendants’ assertions that the Settlement Agreement foreclosed additional
    claims under the Indemnity Agreement, that Gulf is estopped to assert such claims because
    Defendants were induced to enter into the Settlement Agreement on the understanding the remaining
    loan proceeds would cover all claims and expenses relating to settlement of subcontractor claims,
    and that the Settlement Agreement is an accord and satisfaction because of the same understandings,
    are all based on parol evidence which cannot be considered if the contract is unambiguous. Gulf
    relies on the agreement’s provision that “This Settlement Agreement shall not be deemed to in any
    way expand Gulf’s obligations and/or liabilities under the Payment Bond.” This provision appears
    in both versions of the Settlement Agreement in the record. Gulf also relies on the provision
    appearing only in the “Gulf version” ratifying the Indemnity Agreement.
    When a contract is unambiguous, “[p]arol evidence cannot be received to vary, add to, detract
    from, or contradict the terms of a document, or to modify its legal import.” Krantz v. Overfelt’s
    Discount Realty, 
    1994 WL 164091
     at *4 (citing Freeze v. Home Fed. Sav. & Loan Ass’n of
    Manchester, 623 S.W.2d at 112); Renaissance Fin. Serv., Inc. v. Billbury, Docket No. 03A01-9710-
    CH-00462, 
    1998 WL 430554
     at *4 (Tenn. Ct. App. July 31, 1998) (no Tenn. R. App. P. 11
    application filed). However,
    [p]arol evidence has been held admissible where: (1) the evidence tends to establish
    an independent collateral agreement that does not conflict with the original writing;
    (2) to show an agreement made subsequent to the original document; (3) to show the
    inducement for entering into the written contract; (4) where fraudulent
    representations have occurred; or (5) where plaintiff relies upon the doctrine of
    estoppel. In addition, parol evidence is admissible to uncover and reveal the true
    intentions of the parties in the event of an ambiguity in the contract. However, when
    no ambiguity exists, there is no occasion to entertain parol evidence, or to vary from
    the plain meaning of the contract.
    Krantz v. Overfelt’s Discount Realty, 
    1994 WL 164091
     at *4 (citations omitted).
    12
    As this court has stated:
    The parol evidence rule is a rule of substantive law intended to protect the integrity
    of written contracts. Since the courts should not look beyond a written contract when
    its terms are clear, the parol evidence rule provides that contracting parties cannot use
    extraneous evidence to alter, vary, or qualify the plain meaning of an unambiguous
    written contract.
    The rule appears to be quite all-encompassing. However, the courts have been
    reluctant to apply it mechanically and have now recognized that it has numerous
    exceptions and limitations. Thus, the rule does not prevent using extraneous
    evidence to prove the existence of an agreement made after an earlier written
    agreement, or to prove the existence of an independent or collateral agreement not
    in conflict with a written contract. In each of these circumstances, the courts have
    conceived that the parol evidence is not being used to vary the written contract but
    rather to prove the existence of another, separate contract.
    The courts have also recognized certain circumstances that permit contracting parties
    to vary or circumvent the plain terms of their written contract. Thus, the parol
    evidence rule does not prevent using extraneous evidence to prove that a written
    contract does not correctly embody the parties’ agreement, or to prove estoppel or
    waiver.
    GRW Enterprises, Inc. v. Davis, 
    797 S.W.2d 606
    , 610-11 (Tenn. Ct. App. 1990) (citations omitted).
    In GRW Enterprises, this court determined that testimony regarding the parties’ negotiations
    prior to execution of a written option agreement was admissible to prove “that the final version of
    the written option did not accurately reflect the parties’ agreement and to prove that [the defendant]
    should be estopped from relying” on the expiration date appearing in the written agreement. GRW
    Enterprises, 797 S.W.2d at 613.
    Womble v. Dortch, relied upon by Gulf, is not inapposite. In that case, this court determined
    that parol evidence of an oral agreement which the Plaintiff alleged induced him to enter into a
    written agreement would not be admissible at trial because that evidence directly conflicted with the
    terms of the written agreement. 1984 Tenn. App. LEXIS 3268 at *6. The written agreement stated
    that it could be terminated by either party upon thirty days notice. Id. at *2. The Plaintiff alleged
    he had been promised he would have employment, through the written lease agreement, for at least
    five years. Id. Thus, there was a direct contradiction between the alleged oral promise and the terms
    of the written agreement, and that direct contradiction was determinative. Womble itself relies on
    other authority that indicates that exclusion of parol evidence is not required where such is a aid to
    the meaning of the contract and not at odds with a later integrating written agreement. Id. at *3-6.
    13
    It is well-settled that where the contract is ambiguous, parol evidence is allowed to explain
    the written agreement. Jones v. Brooks, 
    696 S.W.2d 885
    , 886 (Tenn. 1985). In Jones, the court
    allowed parol evidence to explain the intention of the parties as to the meaning of a provision
    requiring one party to assume responsibility of “all known . . . accounts amounting to an amount
    in excess of $13,000.00 as per attached list . . .” Id. The court found that the agreement was
    ambiguous with respect to which party was responsible for known debts which were not included
    on the list. Id. at 886-87. “Being subject to two reasonable interpretations, the language is
    ambiguous,” and parol evidence was properly considered. Id. at 887.
    The parties’ versions of the Settlement Agreement herein both include the provision stating
    the purposes of the settlement, which include “(i) the release of outstanding mechanics, materialmen
    and suppliers’ lien, (ii) the resolution of actions to enforce mechanics lien arising out of the
    construction, . . . (vi) such other claims or defenses Construx, Patel, First Tennessee Bank and Gulf
    might have under the terms of the Payment Bond, Performance Bond and contract.” The agreement
    envisions that the total settlement of claims may be less than the amount given to Gulf to settle such
    claims, making specific provision for the disbursement of such “savings.” On the other hand, the
    agreement is silent as to what happens if the total amount paid in settlement of the claims exceeds
    the amount given to Gulf for the purpose of settlement.
    Gulf asserts that the provision stating, “[t]his Settlement Agreement shall not be deemed to
    in any way expand Gulf’s obligations and/or liabilities under the Payment Bond” precludes any
    interpretation that the Settlement Agreement extinguished its rights to reimbursement from the
    indemnitors. We do not interpret Defendants’ arguments as affecting Gulf’s obligations or liabilities
    under the payment bond. Gulf was always obligated to perform in accordance with that bond, and
    those obligations ran to the subcontractors. In any event, Gulf brought this lawsuit to enforce the
    obligations under the Indemnity Agreement.
    The issue of whether the Settlement Agreement settled Defendants’ obligations under the
    Indemnity Agreement is unaddressed by the “Construx version” of the agreement. That version is
    silent as to any cancellation or affirmance of the Indemnity Agreement. We conclude, reading that
    entire document as a whole, that the “Construx version” of the agreement is subject to two
    reasonable interpretations regarding liability for any settlement amounts and expenses in excess of
    the $135,000 given to Gulf, and, therefore, subject to two reasonable interpretations regarding the
    indemnitors’ continuing liability under the Indemnity Agreement.
    In the trial court and in this court, Gulf has relied on the provision which states, “Construx
    does hereby ratify and confirm that the terms of any General Agreement of Indemnity remain in full
    force and effect.” We do not disagree that such a provision removes some ambiguity regarding
    whether the Indemnity Agreement’s obligations were extinguished by the Settlement Agreement.
    At the time Gulf was relying on this provision in the trial court to support its summary judgment
    motion, however, that provision did not appear in the only version of the Settlement Agreement
    which had been presented to the court. While Gulf attempted to correct this oversight by a late filing
    of its own version of the agreement, that filing creates fact issues of its own. In addition, if the “Gulf
    14
    version” was not the final and fully executed version, about which a factual issue exists, the presence
    of the ratifying provision in the later draft could have implications for the interpretation of its
    absence from the “Construx version.” This discrepancy alone creates issues of fact regarding the
    parties’ intent on a primary issue. The two versions create greater ambiguity as to the terms of the
    agreement as well as to the intent of the parties.
    In addition to the ambiguity issue, Defendants have also asserted the defense of estoppel. The
    principle of estoppel is based on the premise that “one who has orally induced a changed
    performance by the other should not escape payment therefor.” GRW Enterprises, 797 S.W.2d at
    611. In discussing the affirmative defense of estoppel, this court has stated:
    [W]hen one man by his promise induces another to change his situation, repudiation
    of the promise would amount to a fraud. Where one makes a promise which the
    promisor should reasonably expect to induce action or forbearance of a definite and
    substantial character on the part of the promisee, and where such promise does in fact
    induce such action or forbearance, it is binding if injustice can be avoided only by
    enforcement of the promise.
    Stones River Util., Inc. v. Metropolitan Gov’t of Nashville, Davidson County, 
    981 S.W.2d 175
    , 177
    (Tenn. Ct. App. 1998) (quoting Foster & Creighton Co. v. Wilson Contracting, 
    579 S.W.2d 422
    , 427
    (Tenn. Ct. App. 1979)).
    Therefore, we conclude that parol evidence may be considered because the Settlement
    Agreement, or the two versions of the Settlement Agreement, are not unambiguous on the issue of
    whether it settled all claims between the parties. In addition, parol evidence may be considered
    where the issue of estoppel is sufficiently raised.
    In response to the motion for summary judgment, Defendants alleged facts regarding the
    inducement for them to enter into the Settlement Agreement as well as facts regarding the
    interpretation of the agreement. Gulf did not dispute these factual allegations, and provided another
    version of the agreement, creating additional issues of material fact.
    Therefore, Defendants have sufficiently put at issue the breadth and effect of the Settlement
    Agreement and the intent of the parties in executing it. At a minimum, we find that there is a
    material factual dispute as to whether Gulf settled its claims against Defendants by executing the
    Settlement Agreement, or whether Gulf is estopped to assert otherwise, thereby limiting the amount
    of Defendants’ liability for payment of subcontractors claims and attorney fees incurred by Gulf.
    The basic issue which must be resolved before that issue can be addressed is what the parties actually
    agreed to, and there is a genuine factual dispute regarding that material issue also. Therefore,
    summary judgment was inappropriate as a matter of law.
    15
    V. Settlement of Subcontractor Claims
    Defendants contend that Gulf settled claims at inflated rates, to which Construx objected:
    specifically, that Gulf settled claims over Defendants’ protest and in spite of Construx having
    provided records in defense of its position that some subcontractors were not entitled to monies
    requested. In fact, Construx claims that some subcontractors were paid even more than the
    subcontractors claimed were due. In essence, Defendants, in their answer and on appeal, have
    contended that Gulf paid claims that were disputed or invalid and in excess of what claimants were
    entitled to. In making such payments, Defendants assert, Gulf was acting beyond the terms of the
    agreements between the parties and expended its own funds for which it is not entitled to
    reimbursement.
    Specifically, Defendants assert: (1) that Apex was paid $3,700.98 more than claimed by Apex
    and over the contract price for fixtures; (2) Lee Plumbing was paid $10,135.50 more than the
    contract provided for; (3) Northview Glass was paid for bathroom fixtures never furnished by
    Northview because Construx furnished the fixtures and, therefore, was overpaid $13,000 and that
    Gulf was provided documentation of the credit for the fixtures; (4) Ramco Electric was paid $750
    more for work done in the pool area for the owner, and there was no contract between Ramco and
    Construx; (5) Roger Patel was paid $2,000 because he indicated he was unhappy with the towel rack
    he picked out and was paid “to go away;” (6) Carter Heating and Air was paid $3,691.25 in excess
    of the contract price; (7) Grade Technologies was paid $286.25 more than it was due; and (8) Rib
    Roof was paid $19,370.12 more than it was entitled to. Also, Construx asserted that Gulf did not
    take into account back charges and the fact that Rib Roof had delayed the project and cost Construx
    $300 per day in liquidated damages, even though Gulf was made aware of this prior to payment.
    Additionally, Construx asserted the work was defective and Construx was required to repair it. In
    sum, Construx asserts that Gulf was provided with documentation and/or contracts that indicated
    the amounts were wrong, but that Gulf paid the higher amounts anyway.
    Included in Defendants’ evidence is a letter from Gulf’s attorney to the owner’s attorney prior
    to the Settlement Agreement in which Gulf lists outstanding payment bond claims, reflecting the
    amount claimed by each claimant and the amount Construx contended was due. The total requested
    from the claimants was $178,142.11, and Construx estimated the amounts due at $100,762.24. The
    total amount actually paid out in claims was $177,228.39.
    On the other hand, Gulf contends that the claims were not overpaid and, in opposition to
    Construx’s allegations, asserted that extensive investigations were done on the disputed claims to
    verify contracts, amounts owed, and materials delivered and used at the site. Also, affidavits and
    releases were obtained prior to payment. For example, Gulf asserts that Construx did not take into
    account the following: Apex had a judgment in Cobb County State Court on April 24, 1996 for
    $13,749.75 and provided an accounting of such; Gulf obtained sworn testimony of the amount and
    delivery slips to verify supplies delivered; negotiations settled the claims for $12,471.63. Lee’s
    Plumbing’s original claim included the Apex claim of $3,977.02 and was reduced once the Apex
    claim was settled. The contract submitted by Construx was unsigned and in the amount of $67,000.
    16
    Lee signed the contract for $77,000 and produced pay slips with $77,000 on them in which
    Defendant had signed. Additionally, there was a dispute on a charge order in the amount of $1,200.
    Also, Lee filed a lien in which Defendant was notified by letter of February 28, 1996. Construx did
    nothing in response to this and, therefore, Gulf had to defend with an answer and discovery. In
    response to the Northview Glass claim, the contract did not include toilet accessories which were
    disputed for credit of $13,246. However, Gulf obtained a secured sworn statement, documents and
    interviews to support payment of the claim. Regarding the Ramco claim, Construx did not consider
    a change order for wiring and installation for parking lights and two entrance signs totaling
    $2,538.89. After a thorough investigation, it was determined that the claim of Ramco totaled
    $14,942.48 and was settled for $11,096.70. Next, Rib Roof made a claim for $36,135.96.
    Defendants claim that liquidated damages were not considered in settlement of this claim. However,
    liquidated damages were a claim by the owner against Construx and were settled in the release of
    funds and with the Settlement Agreement. Additionally, the owner was paid because 46 of 51 racks
    had failed in the rooms. Gulf asserts this was a warranty claim due to faulty installation.
    Obviously, there are many factual disputes regarding the amounts actually due a number of
    subcontractors and claimants. The question, for our purposes, is whether any of these disputes are
    material; that is, whether those factual disputes must be decided in order to resolve the substantive
    claim by Gulf or the defense asserted by Defendants. Defendants assert that the surety, Gulf, is not
    entitled to recover from the indemnitors for any claims where no liability existed or where settlement
    was not made reasonably and in good faith.
    Gulf does not dispute that basic statement of the law, merely phrasing it a little differently:
    a surety on a payment bond and Indemnity Agreement may recover from its principal and
    indemnitors if it has acted reasonably and in good faith. Gulf relies on the following provisions of
    the Indemnity Agreement, which Gulf asserts remains in full force and effect, notwithstanding the
    execution of the Settlement Agreement:
    That the Indemnitor . . . will at all times indemnify and save the Company [Gulf]
    harmless from and against every claim, demand, liability, loss, cost, charge, counsel
    fee, payable on demand of Surety, whether actually incurred or not, (including fees
    of special counsel whenever by the Company deemed necessary) expense, suit, order
    judgment and adjudication whatsoever, and any and all liability therefore, sustained
    or incurred by the Company by reason of having executed or procured the execution
    of said bonds or obligations, and will place the Company in funds to meet same
    before it shall be required to make payment, and in case the Indemnitor requests the
    Company to join in the prosecution or defense of any legal proceeding, the
    Indemnitor will, on demand of the Company, place it in funds sufficient to defray all
    expenses and all judgments that may be rendered therein.
    *****
    That the Company [Gulf] shall have the right to pay, settle or compromise any
    expense, claim or charge of the character enumerated in this agreement, and the
    17
    voucher or other evidence of such payment shall be prima facie evidence of the
    propriety thereof and of the indemnitor’s liability therefore to [Gulf].
    Gulf asserts that the law is well-settled that provisions of this nature “are valid, enforceable,
    and not contrary to public policy in Tennessee,” citing Safeco Ins. Co. of America v. Criterion Inv.
    Corp., 
    732 F. Supp. 834
    , 841 (E.D. Tenn. 1989), which in turn relied upon a 1948 opinion of this
    court, National Sur. Corp. v. Buckles, 
    219 S.W.2d 207
     (Tenn. Ct. App. 1948). The relevant
    question, however, is not whether the provision is enforceable, but how it is to be interpreted in such
    enforcement.
    We begin with the language that evidence of payment by Gulf of claims is “prima facie
    evidence of the propriety” of such payment. Prima facie evidence establishes a fact as presumptively
    true unless disproved by evidence to the contrary. BLACK’S LAW DICTIONARY 1190 (6th ed. 1990);
    Tennessee Farmers Mut. Ins. Co. v. Moore, 
    958 S.W.2d 759
    , 765 (Tenn. Ct. App. 1997) (a statute
    making certain evidence prima facie evidence of other facts creates a presumption which can be
    rebutted); Hunter v. Burke, 
    958 S.W.2d 751
    , 755 (Tenn. Ct. App. 1987) (prima facie evidence can
    clearly be rebutted by countervailing proof). Thus, the language of the agreement itself recognizes
    that other proof may be considered to show that a payment was not proper or that the indemnitor is
    not liable for it.
    Although Gulf appears to concede that the proper test is whether the surety acted reasonably
    and in good faith in settlement of claims, it argues for a restrictive and subjective interpretation of
    the term “good faith”16 and disregards the reasonableness requirement. Gulf relies extensively on
    the Safeco case, pointing out the similarity of the language of the Indemnity Agreement at issue in
    Safeco and the one involved in this case.17 Gulf directs us to that portion of the Safeco opinion
    which finds that the surety’s “duty under the Indemnity Agreement which is the basis of this action
    was simply to determine in good faith whether any claim under the bond issued for [the principals]
    should be paid. Furthermore, the Indemnity Agreement made any such good faith determination,
    at least from the indemnitors’ viewpoint, ‘final and conclusive.’” Safeco, 732 F. Supp. at 841. As
    noted above, the language in the agreement herein makes such payment “prima facie evidence of the
    propriety thereof and of the indemnitor’s liability therefore.”
    In Safeco the federal court applied its interpretation of Tennessee law regarding the standard
    to be applied to a surety’s actions in paying claims for which it seeks reimbursement from an
    16
    For example, Gulf argues that allegations of lack of diligence in investigation of claims does not make out a
    claim of bad faith, and that “improper motive is . . . an essential element of bad faith,” again relying on the Safeco
    opinion. Gulf also asserts that the mere possibility that defenses existed to some cla ims is not evide nce of bad faith and
    that settlement o ver the obj ection of the p rincipal is also no t sufficient to establish b ad faith settleme nt.
    17
    W e note, however, that the agreement in Safeco gave the surety “the exclusive right . . . to determine in good
    faith whether any claim . . . shall be paid.” 732 F. Supp. at 836.
    18
    indemnitor. Id. The court ruled after a trial, not on a summary judgment motion, and had the
    following observations about a standard based on good faith:
    What is “good faith” depends, it is obvious, upon the facts and circumstances of each
    case. This standard requires less of an actor than the standard of reasonableness
    under the circumstances which is central to the law of negligence. See e.g. Tennessee
    Code Annotated § 47-1-201 (19): “‘Good faith’ means honesty in fact in the conduct
    or transaction concerned.”
    Id. (citations omitted).
    Generally, there are two recognized defenses an indemnitor can raise when a surety seeks
    reimbursement for claims settled over the principal’s protest: (1) that the surety did not settle in good
    faith or (2) that the surety did not act in a reasonable and prudent manner. John Hinchey, Surety’s
    Performance Over Protest of Principal: Considerations and Risks, 22 Tort & Ins. L.J. 133, 148
    (1986). Jurisdictions vary in whether only the lack of good faith defense is available or whether the
    surety is also held to a reasonableness standard. Id.
    The Safeco court recognized that Central Towers Apartments, Inc. v. Martin, 
    61 Tenn. App. 244
    , 
    453 S.W.2d 789
     (Tenn. Ct. App. 1969), could be interpreted as requiring the application of a
    reasonableness standard in addition to a finding of good faith. 732 F. Supp. at 842. In Central
    Towers, the surety sought reimbursement for attorney fees and expenses incurred by it in defending
    a lawsuit by the owner of a construction project. The lawsuit was brought against the contractor,
    surety, architect, subcontractors, and an equipment manufacturer, and the contractor was already
    defending the action. Central Towers, 61 Tenn. App. at 247-48, 453 S.W.2d at 791. The Indemnity
    Agreement in that case provided that indemnitors would hold the surety harmless from any and all
    claims, liability, cost, charge, counsel fee, and expense. Id. at 61 Tenn. App. at 253-54, 453 S.W.2d
    at 793. It further provided, “liability hereunder shall extend to any and all disbursements made by
    the Surety in good faith under the belief it was liable for the amount so disbursed, or that it was
    necessary or expedient to make such disbursements, whether such liability, necessity or expediency
    existed or not.” Id. at 61 Tenn. App. at 254, 453 S.W.2d at 793-94. This court determined that no
    conflict of interest existed between the contractor and the surety in the lawsuit brought by the owner
    and determined the issue to be “when, or under what circumstances, an indemnified surety may incur
    attorney’s fees and litigation expense at the cost of the contractor indemnitor when the Indemnity
    Agreement gives the surety the right to incur such expenses.” Id. at 61 Tenn. App. at 263, 453
    S.W.2d at 798. In answer to that question, this court stated:
    . . . the liability of the principal for the attorney fees and expenses thus incurred by
    the surety depends upon whether, under all the facts of the case, it was reasonably
    necessary for the surety to so act in its own defense, and whether the surety acted in
    good faith toward the principal . . .
    19
    and it is necessary in each case for the court to look to the evidence to determine the
    question of good faith and reasonable necessity of the action on the part of the surety
    in creating these expenses which it seeks to recover of the principal.
    Id. at 61 Tenn. App. at 267, 453 S.W.2d at 799. In addition, the court listed a number of factors
    bearing on the reasonable necessity and good faith of the surety in hiring its own counsel. Because
    there had been a full trial of the issues, the court was able to apply the factors it deemed relevant to
    the facts developed in the record. Although Central Towers involved a claim for litigation expenses,
    we think its reasoning applies to a request for reimbursement for amounts paid in settlement as well
    as for expenses incurred in settlement or litigation where the Indemnity Agreement gives the right
    to make such settlements or incur such expenses.18
    Although the standard to be applied was not a debated issue in Feld Truck Leasing v. ABC
    Transnational Transp., 
    681 S.W.2d 554
    , 556, (Tenn. Ct. App. 1984) in that case, this court found,
    under an express agreement, that the indemnitee was entitled to reimbursement for settlements where
    the indemnitor left the claims to be handled by the indemnitee, making the payments not “voluntary,”
    and where “the trial court expressly found that the settlements made . . . were reasonable.” (emphasis
    added).
    We agree with the parties that Tennessee law requires that, in order for a surety to recover
    under an indemnity agreement, the surety must act both reasonably and in good faith. Feld Truck
    Leasing, 681 S.W.2d at 555-56; Central Towers, 61 Tenn. App. at 267, 453 S.W.2d at 799-800.
    However, we are not convinced that the reasonableness requirement adds a higher standard than the
    good faith requirement as good faith has been interpreted in a contractual or commercial context.
    Even without the reasonableness requirement, the requirement that the surety act in good faith in
    settling claims under its contractual ability to do so involves consideration of a broader range of
    factors than Gulf would have us use.
    An indemnity agreement is subject to the general law of contracts, and every contract
    contains an implied obligation of good faith and fair dealing in its performance and enforcement.
    2 PERILLO AND BENDER , CORBIN ON CONTRACTS § 5.27 at 139 (rev. ed. 1995). Thus,
    [t]here is no doubt that, in performance of its duty to indemnify the insured, the
    insurer is bound to exercise “good faith” and to act fairly in the interest of the
    insured. Such an undertaking is said to be “implied,” it is certainly required of an
    indemnitor by the law, whether it is “implied in fact” or not. This is especially
    18
    The Safeco court also determined that the Central Towe rs holding appeared to apply only to a situation in
    which the prin cipal is coo perating to k eep the sure ty from expo sure to risk on the bond . Safeco, 732 F. Supp. at 842.
    That court found that Defe ndants in Safeco had failed to d eal with the claim ants under the bond after the surety’s
    repeate d requests that it do so. “It is precisely this failur e of Criterion to comm unicate with the b roker’s surety bond
    claimants which made the plaintiff’s conduct reasonable.” Id. Obviously, in the case before us, C onstrux co ntinued to
    provide Gulf with record s and docume ntation and to voice its objection to the particulars of specific settlements.
    20
    applicable to an insurer who has promised to defend suits and who has reserved the
    power to “settle” claims asserted against the insured.
    3 ARTHUR L. CORBIN , CORBIN ON CONTRACTS § 572A at 355 (1960).
    In defining good faith, courts have sometimes applied the Uniform Commercial Code’s
    definition to transactions not covered by the UCC. Specifically, UCC § 1-201(19) defines good faith
    subjectively as “honesty in fact in the conduct or transaction concerned.”19 PETER A. ALCES, THE
    LAW OF SURETYSHIP AND GUARANTY ¶ 3.01[2][a][i] (1997). However, as has been explained,
    The Second Restatement of Contracts defines good faith in essentially the same terms
    as the UCC. One portion of the comment to Restatement of Contracts § 205 explains
    that “[g]ood faith performance or enforcement of a contract emphasizes faithfulness
    to an agreed common purpose and consistency with the justified expectations of the
    other party; it excludes a variety of types of conduct characterized as involving ‘bad
    faith’ because they violate community standards of decency, fairness or
    reasonableness.” The invocation of community standards of reasonableness suggests
    good faith necessarily incorporates an objective, almost tortlike measure, not
    withstanding the ostensibly subjective (“honesty in fact”) language of the Article 1
    definition. And the Restatement of Contracts comment confirms that a
    reasonableness analysis is appropriate.
    Id. ¶ 3.01[2][a][ii].
    Our Supreme Court adopted a similar approach in defining the scope of the good faith
    requirement for acceleration of a debt when the creditor deems itself insecure. Interpreting the
    UCC’s provision that the power to so accelerate payments must be construed as giving the creditor
    “the power to do so only if he in good faith believes that the prospect of payment . . . is impaired,”
    the Court stated:
    The good faith requirement is independent of particular privileges and duties that
    arise under the code or under the contracts. It imposes “an honest intention to abstain
    from taking any unconscious advantage of another, even through the forms and
    technicalities of the law.”
    Lane v. John Deere Co., 
    767 S.W.2d 138
    , 139, 140 (Tenn. 1989) (citations omitted). The Court
    listed a number of circumstances which could be relevant to a determination of good faith in the
    transaction involved, Id. at 140-41, and concluded that the record contained sufficient material
    evidence to support the jury’s verdict that the creditor did not act in good faith in accelerating
    payment. Id. at 142.
    19
    For example, in Safeco the court foun d relevant t he statutory definitio n of good faith found in T ennessee’s
    adoptio n of the Unifo rm Com mercial Co de, Ten n. Code A nn. § 47-1 -201(19 ).
    21
    The Court held that because the creditor must act out of an honest belief that the other party’s
    ability to perform has deteriorated and must not use the acceleration clause as an instrument of
    abuse, “[a]ny evidence that the belief was not rational or that the party accelerating the debt took
    unconscientious advantage of the other or resorted to this severe remedy for other reasons is
    material.” Id. at 142.
    The Supreme Court has addressed the meaning of good faith in another commercial context,
    and “accepted that bad faith can be defined as a knowing or reckless disregard of a customer’s
    rights.” Glazer v. First Am. Nat. Bank, 
    930 S.W.2d 546
    , 549 (Tenn. 1996). In that case, a bank’s
    customer sued the bank for, among other things, refusing to provide records regarding forged checks
    payable to him. In discussing the appropriate definition of good faith, the Court stated:
    [W]e first note that [the bank] is correct that 47-1-201(19) does make a party’s “good
    faith” dependent upon its “honesty,” and that this Court, in McConnico, supra, did
    equate “bad faith”with “dishonesty.” This does not end the inquiry, however, for the
    word “honesty,” which is not defined in the code, is susceptible to more than one
    definition. For example, Webster’s defines “honesty” as “freedom from subterfuge
    or duplicity,” a definition that supports the bank’s argument. Webster’s Third
    International Dictionary 1086 (G.C. Merriam Co. 1976). However, Webster’s also
    defines the term as “fairness and straightforwardness of conduct,” Id., which tends
    to support Dr. Glazer’s argument. Moreover, several courts have concluded that the
    term “bad faith” encompasses a wider range of actions than outright deception or
    untruthfulness. Shearson Lehman Bros., Inc. v. Wasatch Bank, 
    788 F. Supp. 1184
    ,
    1196 (D. Utah 1992); Kraftsman Container Corp. v. United Counties Trust Co., 169
    N.J.Super. 488, 
    404 A.2d 1288
    , 1293 (1979); Taylor v. Citizens Bank of Albany, 
    290 Ky. 149
    , 
    160 S.W.2d 639
    , 641 (1942). Taking into consideration the various
    meanings of the word “honesty,” and the conclusions of other courts, we accept the
    definition proffered by Dr. Glazer [a knowing or reckless disregard of a customer’s
    rights.]
    Id. at 549-50.
    Good faith, or the lack thereof, as well as reasonableness, should be determined in the context
    of the specific factual situation involved. “What is good faith depends, it is obvious, upon the facts
    and circumstances of each case.” Safeco, 732 F. Supp. at 841; see also Lane v. John Deere Co., 767
    S.W.2d at 142 (any evidence tending to show an other than good faith basis for the action is
    material); Central Towers, 61 Tenn. App. at 267, 453 S.W.2d at 799 (court must look to all the facts
    of the case to determine whether it was reasonably necessary for the surety to so act in its own
    defense, and whether the surety acted in good faith toward the principal).
    Similarly, as a general rule, “[t]he question of reasonableness is a factual question to be
    determined by the trier of fact and, if there is a dispute, summary judgment would not be proper.”
    Educational Serv. Placement, Inc. v. Watts, 
    789 S.W.2d 902
    , 904-05 (Tenn. Ct. App. 1989)
    22
    (deciding whether buyer made reasonable efforts to obtain financing). For example, this court has
    previously recognized that the reasonableness of a plaintiff's reliance on an alleged misrepresentation
    is generally a question of fact inappropriate for summary judgment. City State Bank v. Dean Witter
    Reynolds, Inc., 
    948 S.W.2d 729
    , 737 (Tenn. Ct. App. 1996). Also, “the reasonableness of the
    plaintiff’s actions in making the demand is a factual determination for the trial court to make at trial,
    not on summary judgment.” Frye v. Postal Employees Credit Union, 
    713 S.W.2d 324
    , 326-27
    (Tenn. Ct. App. 1986).
    This is not to say that summary judgment is never available when the question of good faith
    or reasonableness is a determinative issue. However, summary judgment is warranted only when,
    taking the evidence of the non-moving party as true, viewing that evidence in the light most
    favorable to the non-moving party, and drawing all reasonable inference therefrom in favor of the
    non-movant, there is no genuine issue of material fact. If there is any doubt whether a genuine issue
    exists, summary judgment must be denied.
    Defendants presented deposition and affidavit testimony as to the reasons the overpayments
    were unreasonable and to show that Gulf knew this information prior to payment of the claims.
    Specifically, Mr. Amszynski indicated that Gulf did not take into account the setoff, credits, back
    charges, contract terms, etc., included in all of the documentation supplied to Gulf prior to payment.
    Moreover, he contended Gulf knew of actual defenses, not just possible defenses prior to payment
    of claims. There are specific instances disputed as to the amount owed the subcontractor and
    specific instances when Gulf paid an amount beyond the amount requested by the subcontractor.
    Defendants assert they provided evidence
    that Gulf paid the subcontractors for extra work performed for the owner, not
    Construx; paid the subcontractors for materials that were actually furnished by
    Construx; paid the subcontractors whatever the subcontractors claimed was due and
    owing despite the clear terms of their contracts and invoice payments; paid the
    subcontractors for items furnished at a higher price quoted to the surety than was
    originally quoted to Construx; paid the subcontractors for defective work; and in one
    case (Apex Supply) even paid a subcontractor more than even the subcontractor
    claimed was due and owing.
    While Gulf has responses to these claims, Defendants’ submissions set forth specific facts
    needed to survive a motion for summary judgment, are not merely conclusory allegations, and are
    not just legal conclusions. Whether Gulf’s actions were reasonable under the circumstances is a
    question of fact for determination after trial, not for summary judgment.
    Gulf correctly argues that Defendants have the burden of establishing that Gulf did not act
    in good faith in settling the claims. Gulf also cites to evidence it presented regarding the
    extensiveness of the investigation of subcontractor claims it undertook and to the facts briefly set out
    23
    above regarding each of the claims.20 The reasonableness of the investigation is one factor relevant
    to the question of whether Gulf acted in good faith. Stated another way, the surety has a duty to
    reasonably investigate the claim, counterclaim and all possible defenses and act in good faith in
    settling a claim. United States of America for the use of the Trustees of the Elec. Workers Local
    Pension Fund v. D Bar D Enter., Inc., 
    772 F. Supp. 1167
    , 1170 (D. Nev. 1991) (citations omitted).
    However, because Defendants have provided evidence to create factual disputes regarding the
    claims and the investigation, we cannot say that no reasonable mind could find that Gulf’s
    investigation was unreasonable. And, the thoroughness of the investigation is not the only relevant
    factor.
    Gulf also argues that the “self-serving statements” of Mr. Amszynski regarding the validity
    of the claims “ignores the subcontractors’ and suppliers’ positions, documentation, [and]
    representations of their own personnel.” We think Defendants’ factual allegations dispute, rather
    than ignore, Gulf’s evidence. Gulf also argues that conclusory allegations of bad faith are
    insufficient to defeat a surety’s motion for summary judgment to enforce an indemnity agreement.
    The specific statements regarding various subcontractor claims are not conclusory allegations. The
    question is whether, taking those allegations as true, those facts sufficiently raise a triable issue of
    the reasonableness and good faith of the settlement payments.
    Finally, Gulf argues that its payment of the claims using its own money (above the $135,000
    given it by the Settlement Agreement) is evidence of its good faith and the reasonableness of the
    settlements. “Gulf had sufficient internal and external incentives against settling the subcontractors’
    claims against Construx in bad faith. It would not make sense for Gulf to settle claims in excess of
    a dollar amount in which it felt it was validly exposed to liability.” Such a defense is not sufficient
    to cut off examination of other facts and circumstances relevant to the issues of good faith and
    reasonableness. “Of course a party’s assertion that he acted out of a good faith belief is not the only
    relevant evidence.” Lane v. John Deere Co., 767 S.W.2d at 140.
    Gulf also states that Construx was required by the Indemnity Agreement to post sufficient
    collateral with Gulf if Construx wished to prevent the settlement of claims and that Construx did not
    post such collateral. The Indemnity Agreement provides “in case the indemnitor requests the
    Company to join in the prosecution or defense of any legal proceeding, the indemnitor will, on
    demand of the Company, place it in funds sufficient to defray all expenses and all judgments that
    may be rendered therein.” There is no evidence in the record before us to show whether a demand
    was made for additional collateral or whether Construx posted such collateral.
    And, in any event, Defendants have presented evidence that, by entering into the Settlement
    Agreement, they gave Gulf the $135,000 in remaining contract proceeds to use to settle the
    20
    Again, Gulf relies on Safeco, where in the federal court adopted a standard from Texas law. “‘[N]either lack
    of diligence nor negligence is the equivalent of bad faith; an d improp er motive . . . is an essential elem ent of bad fa ith.’
    Engbrock v. Federal Insurance Company, 
    370 F.2d 784
    , 787 (5th Cir. 19 67) (citation s omitted) (a pplying T exas law).”
    Safeco, 732 F. Supp. at 841.
    24
    subcontractor claims. Without the Settlement Agreement, Construx would have been entitled to the
    proceeds. Defendants also contend they agreed to allow Gulf to negotiate and settle the
    subcontractor claims and agreed to have the claimants deal directly with Gulf. Again, Defendants’
    position is that, absent the Settlement Agreement, Construx would have dealt with the subcontractors
    prior to the surety’s involvement. Defendants specifically allege that Gulf informed Construx that
    if Construx would release all claims it had to the remaining loan proceeds, Gulf would use the loan
    proceeds as a fund out of which to pay all subcontractor claims as well as Gulf’s attorney fees, and
    that Gulf represented that the loan proceeds were more than enough to fully satisfy subcontractor
    claims and attorney fees. Thus, there is a dispute as to whether Gulf requested collateral from
    Defendants and received it.
    In light of the evidence in the record as to whether Gulf acted reasonably and in good faith
    in settlement of the claims and the expenses incurred therein, summary judgment is not appropriate,
    and the trial court’s grant of judgment is reversed.
    VI.
    We do not find it necessary to determine whether the alleged damages are adequately
    supported by the record in light of the fact that we find the motion for summary judgment
    inappropriate at this juncture. All of the damages, including attorney fees, awarded in accordance
    with the motion for summary judgment stemmed from the Indemnity Agreement and are, therefore,
    still in dispute.
    VII.
    For the reasons set forth herein, we find that the trial court’s grant of summary judgment was
    improper. Therefore, we reverse the order granting summary judgment to Gulf and remand this
    cause to the trial court for further actions consistent with this opinion. Costs of this appeal are taxed
    to the Plaintiff, Gulf, for which execution may issue, if necessary.
    ____________________________________
    PATRICIA J. COTTRELL, JUDGE
    25