R.P. Industries v. United States Aluminum ( 2003 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    MARCH 20, 2003 Session
    R. P. INDUSTRIES, INC. v. UNITED STATES ALUMINUM
    CORPORATION - CAROLINA
    Direct Appeal from the Circuit Court for Davidson County
    No. 00C-347    Carol Soloman, Judge
    No. M2002-00897-COA-R3-CV - Filed October 15, 2003
    This appeal arises from a dispute over an agreement to issue joint checks. The trial court found that
    the parties had an agreement whereby the general contractor was to issue checks jointly payable to
    the sub-contractor and the materials supplier, which the general contractor breached when it issued
    single payee checks. The court awarded the materials supplier $17,500.00. The parties raise two
    issues on appeal. For the following reasons, we affirm in part, reverse in part, and remand.
    Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Circuit Court Affirmed in Part,
    Reversed in Part and Remanded
    ALAN E. HIGHERS, J., delivered the opinion of the court, in which DAVID R. FARMER , J., and HOLLY
    M. KIRBY, J., joined.
    Gregory L. Cashion, Nashville, TN, for Appellant
    Joel T. Galanter, Nashville, TN; Scott A. Frick, Memphis, TN, for Appellee
    OPINION
    Facts and Procedural History
    R.P. Industries (“RPI”) was the general contractor that constructed a car dealership in
    Nashville for Carmax. Asheville Plate Glass (“APG”), a subcontractor on this project, was to furnish
    and install all the glass for the storefront as well as the windows and doors. United States Aluminum
    Corporation- Carolina (“USAC”) supplied materials used on the project to APG.
    USAC requested that APG execute a Joint Check Agreement with RPI. In January of 1999,
    APG gave USAC a joint check agreement purportedly signed by RPI. This agreement provided that
    checks issued by RPI would be payable jointly to APG and USAC.
    On March 16, 1999, USAC sent a letter to RPI seeking RPI’s “cooperation in issuing ‘joint
    checks’ payable to” APG and USAC. Thereafter, on May 3, 1999, RPI transmitted a fax to USAC
    confirming that the joint check had been prepared. The fax also stated that USAC would be paid by
    joint check once RPI received a lien waiver. USAC responded on May 14, 1999 by sending RPI a
    Conditional Waiver and Release Upon Progress Payment which indicated that RPI would issue a
    joint check. Upon receipt of the waiver, RPI forwarded the check to APG with instructions that APG
    was to endorse the check and forward it to USAC. Instead of complying with these instructions,
    APG endorsed the check and placed it in its account.
    APG sent USAC a check in the amount of $6,194.00 on May 15, 1999 and a check in the
    amount of $27,446.42 on May 25, 1999. No one at USAC inquired as to why they did not receive
    a joint check in the amount fo $45,000.00. At the same time RPI issued the $45,000.00 joint check
    to APG and USAC, RPI issued a joint check in the amount of $49,255.00 to APG and Viracon,
    another supplier.1
    After issuing the joint check for $45,000.00, an RPI employee authorized the payments to
    be released directly to APG. RPI paid $17,500.00 solely to APG with four additional payments in
    the amounts of $5,000.00; $5,000.00; $5,000.00; and $2,500.00. At the time RPI issued these direct
    payments to APG, RPI had no knowledge that APG had not paid its suppliers, both USAC and
    Viracon with the two joint checks. USAC continued to supply materials to APG in June and July
    of 1999. It was not until August 10, 1999 that USAC notified RPI that it was owed $31,823.24 on
    the Carmax project. On August 19, 1999, RPI wrote USAC advising them that a joint check in the
    amount of $45,000.00 had been issued and requesting that USAC execute an Affidavit of Forged
    Signature or Missing Endorsement to be given to RPI’s bank.
    On February 4, 2000, USAC filed suit against RPI, seeking payment for materials provided
    by USAC on the Carmax project. USAC claimed that it was entitled to recover from RPI for
    payments it did not receive from APG, pursuant to a joint check agreement between RPI and APG.
    The complaint also named APG, The Bank of Nashville, and Branch Bank & Trust as defendants.2
    RPI filed its answer on April 17, 2000 and later amended this answer on April 9, 2001. In
    its amended answer, RPI alleged that the joint checking agreement was a forgery. The trial court
    entered an agreed order allowing RPI to amend its answer on April 30, 2001.
    1
    To protect its interest, Viracon filed a lien against the Carmax project in the amount of $29,000.00, which
    RP I paid . USAC did no t file a lien on the pro ject.
    2
    These parties, however, are not relevant to this appeal. Prior to trial, the co urt granted a m otion to dismiss
    the Bank of N ashville and B ranch Banking & Trust. The reafter, on M arch 1 2, 20 01, the trial court entered a default
    judgment against A PG for its failure to appear or otherwise respond to USA C’s summons and comp laint as well as its
    failure to resp ond to the no tice of the motio n for default jud gment. On April 5, 2001, the trial court entered an order
    awarding USAC a judgment against APG in the amount of $31,823.24. Apparently, USAC has not attempted to enforce
    this judg ment.
    -2-
    USAC filed a motion for summary judgment on September 6, 2001, asserting that it was
    entitled to summary judgment because RPI had breached a joint checking agreement and that there
    were no genuine issues of material fact. Subsequently, RPI filed a motion for summary judgment.
    There is no record of a ruling on either of these motions.
    The trial was held on February 26, 2002 and the final order entered on March 20, 2002. The
    court found that the joint check agreement between RPI and APG was forged and was thus invalid.
    However, the court found that the parties subsequently entered into an agreement to issue joint
    checks. The court further found that RPI violated this agreement “by not sending three checks
    totaling Seventeen Thousand Five Hundred 00/100 Dollars ($17,500.00).”3 Stated another way, the
    court found that RPI violated the agreement by issuing these checks solely to APG. The court also
    found that RPI did not have an obligation to ensure that APG “did not commit a felony by cashing
    the checks without the express permission of United States Aluminum Corporation or the signature
    of both parties.” Instead, RPI’s only duty was to issue joint checks. The court awarded USAC
    $17,500.00.
    RPI filed its notice of appeal on April 12, 2002. On April 18, 2002, USAC filed a Motion
    to Alter or Amend Judgment and for Discretionary Costs, seeking prejudgment interests and costs.
    Thereafter, on May 21, 2002, the judge issued an amended order awarding USAC prejudgment
    interest and discretionary costs. RPI filed its second notice of appeal on June 18, 2002. This Court
    granted RPI’s motion to consolidate on July 1, 2002. The parties raise the following issues for our
    review.
    Issues
    I.        Whether the trial court erred in finding that there was an agreement between
    the parties to issue joint checks.
    II.       Whether the trial court erred in finding that RPI is only liable for $17,500.00,
    instead of $33,114.79 which is the full outstanding balance on the account,
    for its breach of the agreement to issue joint checks.
    Standard of Review
    The findings of fact made by a trial court are given a presumption of correctness that will not
    be overturned unless the evidence preponderates against those findings. See TENN. R. APP . P. 13(d);
    see also Bank/First Citizens v. Citizens and Assoc., 
    82 S.W.3d 259
    , 262 (Tenn. 2002). A trial
    court’s ruling on a matter of law, however, will be reviewed “‘under a pure de novo standard . . .
    according no deference to the conclusions of law made by the lower court[].’” Bank/First 
    Citizens, 82 S.W.3d at 727
    (quoting Southern Constructors, Inc. v. Loudon County Bd. of Educ., 
    58 S.W.3d 706
    , 710 (Tenn. 2001)).
    3
    While the trial court’s order dated March 2 0, 20 02 states that there were three (3 ) checks in the total amount
    of $1 7,50 0.00 , the reco rd reveals that the re were four (4) checks in the total am ount o f $17 ,500 .00.
    -3-
    Law and Analysis
    RPI first argues that it never entered into a joint check agreement with any party in this case.
    Specifically, RPI asserts that the trial court erred in finding that USAC’s March 16, 1999 letter
    constituted an agreement to issue joint checks. RPI asserts that the letter was a unilateral act by
    USAC and that RPI never communicated with USAC in response to the letter. RPI further argues
    that there was no mutual assent, no offer, no acceptance and no consideration and that without these
    elements there can be no contract.
    In response, USAC argues that even if the original joint check agreement was a forgery and
    thus invalid, that the parties subsequently reached an agreement to issue joint checks. USAC asserts
    that the March 16, 1999 letter indicated that USAC expected to receive payment by joint check and
    that RPI, through is May 3, 1999 facsimile, agreed to issue a joint check upon receipt of a partial lien
    waiver signed by USAC. USAC asserts that it gave consideration in the form of continuing to
    supply all material to the job and by executing the lien waiver. USAC asserts that RPI breached this
    agreement by “failing to properly complete the payee designation of the check.” USAC also asserts
    that RPI’s failure to properly execute the $45,000.00 check as a joint check and the “subsequent
    disregard of this agreement by issuing three additional checks totaling $17,500.00 made payable
    solely to [APG]” caused USAC to be underpaid on the project. As a result, USAC asks this Court
    to hold RPI liable in the amount of $33,114.79, which represents USAC’s unpaid balance on the
    project.
    A contract is simply an agreement, based upon adequate consideration, “to do or not do a
    particular thing.” Johnson v. The Central National Insurance Company of Omaha, Nebraska, 
    356 S.W.2d 277
    , 281 (Tenn. 1962) (citations omitted). A contract may be either express or implied,
    written or oral and “must result from a meeting of the minds of the parties in mutual assent to the
    terms, must be based upon sufficient consideration, . . . and sufficiently definite to be enforced.” 
    Id. at 281 (citing
    American Lead Pencil Co. v. Nashville, Chattanooga & St. Louis Ry. Co., 
    134 S.W. 613
    ( Tenn. 1910)).
    Within the framework of the above contract principals, we now turn to the documents at
    issue. The March 16, 1999 letter provides in pertinent part as follows:
    Gentlemen:
    We are material suppliers on the above job furnishing commercial aluminum
    storefronts, sections & entrances to your sub-contractor, Asheville Plate Glass. It has
    been our experience in the last six months that 15% to 20% of pre-arranged joint
    check payment agreements are inadvertently paid solely to sub-contractor.
    As this may subject all parties to unnecessary liability, we ask your cooperation in
    issuing “joint checks” payable to Asheville Plate Glass and United States Aluminum
    Corporation/Carolina. Your assistance would be appreciated.
    -4-
    We thank you and wish you well on favorable completion of this job.
    Sincerely,
    UNITED STATES ALUMINUM CORPORATION/CAROLINA
    The May 3, 1999 facsimile provides in pertinent part as follows:
    A joint check with Asheville Plate Glass Co., 276 Haywood Road, Asheville, NC has
    been prepared by us. Please fully complete and execute the attached partial lien
    waiver and return by fax to the undersigned to FAX #(615) 595-2476. Upon receipt
    of same we will forward your joint check to Asheville Plate Glass by regular mail to
    be endorsed and sent on to you. Should you have any questions, please do not
    hesitate to contact me at (615) 595-2422.
    We find that USAC’s March 16, 1999 letter in and of itself was insufficient to support a
    finding of a joint check agreement. The letter made a vague reference to “pre-arranged joint check
    payment agreements” and simply expressed USAC’s desire for RPI’s “cooperation in issuing ‘joint
    checks.’” We do find, however, that the parties did have an agreement to issue a joint check in the
    amount of $45,000.00. In its May 3, 1999 facsimile, RPI stated that upon receipt of a partial lien
    waiver, a joint check would be issued to APG to be forwarded to USAC. As consideration, USAC
    sent RPI a partial lien waiver that covered a “progress payment for labor, services, equipment or
    material furnished to Asheville Plate Glass through April 30, 1999 only and [did] not cover any
    retention or items furnished after said date.” In its facsimile, RPI offered to execute and forward a
    joint check if USAC executed a partial lien waiver, which it did. We find that there was an offer,
    acceptance, consideration and mutual assent and thus a valid agreement.
    We do not find, however, that there was sufficient evidence to support a finding of an
    ongoing joint check agreement that encompassed the four (4) additional payments in the amount of
    $17,500.00. The May 3, 1999 facsimile and the May 14, 1999 partial lien waiver referenced a joint
    check in the amount of $45,000.00. There are no documents in the record that support an agreement
    to issue joint checks thereafter. We find no evidence of offer, acceptance, consideration, or mutual
    assent sufficient to find that there was an ongoing agreement to issue joint checks. Thus, RPI had
    no duty to issue the four (4) additional payments in the total amount of $17,500.00 in the form of
    joint checks. RPI’s only duty was to issue a joint check in the amount of $45,000.00.
    On April 30, 1999, RPI executed a check in the amount of $45,000.00 payable to
    “ASHEVILLE PLATE GLASS/ US ALUMINUM JTLY.” APG endorsed the check and Branch
    Bank & Trust and the Bank of Nashville issued payment on the check. The Banks subsequently filed
    motions to dismiss, which the trial court granted. In its brief, USAC claims that in ruling on the
    Banks’ motions to dismiss, the trial court held that the payee designation on the check was
    ambiguous and that the check was payable alternatively to APG or USAC. The order cited by USAC
    in their brief contains no such ruling. The order merely states that the Banks’ motions to dismiss are
    well taken and should be granted. The slash mark or virgule which separated the names of the
    -5-
    payees on the check is used “to separate alternatives.” American Heritage Dictionary. See also
    T.C.A. § 47-3-110(d). The abbreviation “JTLY” appears, in retrospect, to mean “jointly” but there
    apparently was a question raised in the trial court about this terminology. Thus we remand for a
    determination as to RPI’s liability, if any, regarding the issuance of the $45,000.00 check.
    USAC argues in the alternative that if it is found that there was not an express contract, then
    there was an agreement implied in fact to issue joint checks. Specifically, USAC argues that RPI
    accepted USAC’s materials for the Carmax project with the express understanding that USAC
    expected to be paid in the form of joint checks. Our finding that there was an express agreement to
    issue a joint check in the amount of $45,000.00 renders any discussion of this point moot. USAC
    advances no argument that it should be entitled to the $17,500.00 due to a contract implied in fact.
    USAC also argues in the alternative that RPI should be estopped from denying its
    representation that a joint check would be issued. This argument, however, was not raised in the trial
    court and as such we will not considered on appeal. See Lawrence v. Stanford, 
    655 S.W.2d 927
    , 929
    (Tenn. 1983) (holding that issues not properly raised at trial cannot be raised for the first time on
    appeal).
    Conclusion
    Accordingly, we affirm in part, reverse in part and remand. We affirm the trial court’s
    finding that there was an agreement between the parties to issue a joint check in the amount of
    $45,000.00, reverse the trial court’s award of $17,500.00 in damages, and remand for proceedings
    consistent with this opinion. Costs on appeal are assessed equally against the Appellant, R.P.
    Industries, Inc., and its surety, as well as Appellee United States Aluminum Corporation-Carolina,
    for which execution may issue if necessary.
    ___________________________________
    ALAN E. HIGHERS, JUDGE
    -6-