Sumner Co. Bd of Ed. v. Mansker Farms ( 2002 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    JULY 10, 2002 Session
    SUMNER COUNTY BOARD OF EDUCATION v. MANSKER FARMS,
    LLC
    Direct Appeal from the Chancery Court for Sumner County
    No. 99C-274; The Honorable Tom E. Gray, Chancellor
    No. M2001-01888-COA-R3-CV - Filed January 23, 2003
    This is a dispute over an option contract. Mansker Farms, a land developer, offered the Sumner
    County School Board an option on land in its development to build a school. A dispute arose over
    whether a condition precedent existed in the contract and whether the nonfulfillment of this
    condition prevented the School Board from exercising the option. The trial court found that no valid
    contract existed because there was no meeting of the minds between Mansker Farms, who gave the
    option, and the Sumner County Board of Education, who attempted to exercise the option. For the
    following reasons, we affirm the ruling of the trial court.
    Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Chancery Court Affirmed
    ALAN E. HIGHERS, J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S.,
    and HOLLY KIRBY LILLARD, J., joined.
    John R. Phillips, Jr., Gallatin, TN, for Appellant
    Joe H. Thompson, Gallatin, TN, for Appellee
    OPINION
    Facts and Procedural History
    In October, 1995, the Appellee, Mansker Farms, LLC (“Mansker Farms”) purchased
    approximately 500 acres of land in Hendersonville, Tennessee for a residential development.
    Mansker Farms was approved by the Hendersonville Regional Planning Commission (“the HRPC”)
    to proceed with development only on a portion of the property known as Phase I. In September,
    1995, Mansker Farms’ chief manager, Mack McClung (“Mr. McClung”) contacted the Appellant,
    the Sumner County Board of Education (“the Board”). Mr. McClung offered the Board four lots in
    the development upon which to build an elementary school in exchange for $186,000.00-- the cost
    to increase the sewer capacity for the development. Contract negotiations ensued between Mansker
    Farms and the Board, including the exchange of several faxed copies of a proposed option contract
    between the parties. The negotiations proved fruitless when in late 1996, the Board turned down
    Mansker Farms’ offer.
    In 1997, Mansker Farms attempted to gain approval from the HRPC to begin development
    of the remainder of the property. At a meeting of the HRPC where Mansker Farms had
    unsuccessfully proposed a master development plan, Mansker Farms was told by the Ms. Baldwin,
    the Hendersonville city planning director, that the inclusion of a school in the development could
    help attain approval for the plan. Mansker Farms again contacted the Board and offered land in the
    development for an elementary school. In April 1998, negotiations broke off between Mansker
    Farms and the Board. In the summer of 1998, however, negotiations resumed when the Board
    expressed interest in building a middle school in the development. During these on-again-off-again
    negotiations, Mr. McClung and Leah Dennen, an attorney working for the Board, passed draft copies
    of an option contract back and forth as the agreement between the parties took shape. These draft
    copies contained various changes, including handwritten changes made to the language of the
    agreement by the parties.
    On August 19, 1998, Mr. McClung forwarded an executed option contract to the Board. On
    October 21, 1998, the Board returned an almost identical option contract to Mr. McClung. The
    option contract stated that, if exercised, the cost to the Board for approximately 20 acres of Mansker
    Farms would be $50,000.00 for the sewer line installation to the property. Mansker Farms made a
    rezoning request to the City of Hendersonville (“the City”) which included the school and which
    asked for higher density zoning so that Mansker Farms could build town homes. In March, 1999,
    the Board sent two letters informing Mansker Farms that it wished to exercise its option. Mansker
    Farms did not reply to the letters. On April 13, 1999, the City rejected Mansker Farms’ rezoning
    request. Mansker Farms then refused to sell the property to the Board.
    On September 29, 1999, the Board filed a complaint for declaratory judgment and specific
    performance against Mansker Farms in the Chancery Court of Sumner County. The complaint
    requested that the trial court order Mansker Farms to sell the property to the Board under the option
    contract. On November 19, 1999, Mansker Farms filed an answer alleging that its duty to perform
    under the option contract never arose because the condition precedent of obtaining higher density
    zoning did not occur.
    On May 21 and 22, 2001, a trial was held. On July 11, 2001, the trial court entered an order
    dismissing the Board’s complaint. The trial court found that there was no meeting of the minds, and
    thus not a valid contract. The trial court found that each side of this dispute attributed a different
    meaning to Paragraph 5(d) of the contract. Mansker Farms read Paragraph 5(d) to mean that having
    their property rezoned was a condition precedent to conveying the land to the Board. The Board,
    however, read Paragraph 5(d) as applying only to the 20 acres in consideration for building the
    school and was not contingent on anything. The trial court held that because Paragraph 5(d) was
    “capable of being understood in two or more possible senses,” it was ambiguous and that “[w]hen
    -2-
    a contract term is ambiguous, there is no meeting of the minds.” The Board filed a timely notice of
    appeal and presents the following issues for our review:
    I.      Whether the trial court erred by determining that the option contract is
    ambiguous.
    2.      Whether, assuming that the option contract is ambiguous, the Board’s
    interpretation should prevail.
    Standard of Review
    The standard of review for a non-jury case is de novo upon the record. See Kendrick v.
    Shoemake, No. E2000-01318-SC-R11-CV, 2002 Tenn. Lexis 489, at * 6-7 (Tenn. 2002). The
    findings of fact made by a trial court are given a presumption of correctness that will not be
    overturned unless the evidence preponderates against those findings. See Tenn. R. App. P. 13(d);
    see also Bank/First Citizens v. Citizens and Assoc., 
    82 S.W.3d 259
    , 262 (Tenn. 2002) (citing Bogan
    v. Bogan, 
    60 S.W.3d 721
    , 727 (Tenn. 2001)). A trial court’s ruling on a matter of law, however, will
    be reviewed “’under a pure de novo standard . . . according no deference to the conclusions of law
    made by the lower court[].’” Bank/First Citizens, 82 S.W.3d at 727 (quoting Southern Constructors,
    Inc. v. Loudon County Bd. of Educ., 
    58 S.W.3d 706
    , 710 (Tenn. 2001)). The interpretation of a
    written agreement is a question of law, and, therefore, will be reviewed de novo with no presumption
    of correctness given to the trial court’s findings of law. Union Planters Nat’l Bank v. American
    Home Assurance Co., 
    865 S.W.2d 907
    , 912 (Tenn. Ct. App. 1993).
    Law and Analysis
    There is no dispute between the parties as to whether or not they properly executed an option
    contract. The dispute arises in the interpretation of their agreement, and specifically as to whether
    Paragraph 5 Section (d) created a condition precedent which the nonfulfillment of prevents the Board
    from exercising the option. The option contract begins by naming the parties, stating the
    consideration, describing the land on which the option is being given (“parcel IV-4 of the Mansker
    Farms Development Plan”), and giving a five year time frame in which the option must be exercised.
    The contract continues with a sentence that reads “[s]ubject to the following terms and conditions”
    followed by eight numbered paragraphs. Paragraph 5, and more specifically Section (d) of Paragraph
    5, is the crux of the present dispute. It reads in pertinent part:
    It is further understood between the parties that the exercise of the option is
    subject to the following:
    (d) Approval of zoning and changes necessary from the City of
    Hendersonville or other governmental authority for the construction of the public
    school and related facilities including the proposed site plan and rezoning as
    hereinabove recited. School system agrees to support and/or assist Seller with said
    change.
    -3-
    Before we look at the specifics of the clause, we must determine its effect. If it is a condition
    precedent, it will affect the Board’s ability to exercise the option, but if it is not, any discussion about
    Paragraph 5(d)’s meaning is pointless. The creation of a condition precedent as well as its effect
    has been summed up as follows:
    A contractual duty subject to a condition precedent is not required to be
    performed until the condition occurs or its nonoccurrence is excused. Covington v.
    Robinson, 
    723 S.W.2d 643
    , 645 (Tenn. Ct. App. 1986); Strickland v. City of
    Lawrenceburg, 
    611 S.W.2d 832
    , 837 (Tenn. Ct. App. 1980); Restatement (Second)
    of Contracts § 225(1) (1981). The existence of a condition precedent depends upon
    the parties' intention, which courts may discern from the contractual language and the
    circumstances surrounding the contract's execution. Miller v. Resha, 
    820 S.W.2d 357
    ,
    360 (Tenn. 1991); Harlan v. Hardaway, 
    796 S.W.2d 953
    , 957-58 (Tenn. Ct. App.
    1990) . . . . No special language is needed to create a condition precedent. The nature
    of the agreement and its surrounding circumstances may sufficiently manifest the
    parties' intention to make a contractual obligation conditional. Harlan v. Hardaway,
    796 S.W.2d at 957-58; Restatement (Second) of Contracts § 226 cmt. a (1981).
    However, the presence of a condition is usually signaled by a conditional word or
    phrase such as "if," "provided that," "when," "after," "as soon as," "on condition that,"
    and "subject to." Harlan v. Hardaway, 796 S.W.2d at 958; Restatement (Second) of
    Contracts § 226 cmt. a; 3A Corbin on Contracts § 639.
    Holland v. Holland, No. M1999-02791-COA-R3-CV, 2001 Tenn. App. LEXIS 409, at *10-12
    (Tenn. Ct. App. June 1, 2001).
    The Board contended at trial and at oral argument that Section 5 was its “political clause”
    meant to allow it to gracefully exit deals that fell through and, thus, was not intended to benefit
    Mansker Farms. Mansker Farms, on the other hand, contends that because the “subject to” language
    is contained at both the beginning of the section of numbered paragraphs and at the beginning of
    Paragraph 5, a condition precedent exists which must be fulfilled before the Board can exercise its
    option. In light of the above statement of law, and our review of the record, we agree with Mansker
    Farms that the numbered paragraphs created condition precedents to the exercise of the option by
    the Board.
    Having determined that the ability of the Board to exercise the option contract depended on
    the conditions outlined in the numbered paragraphs, we turn to the Board’s contention that the
    disputed provision, Section (d) of Paragraph 5, is not ambiguous. The trial court determined that this
    section was ambiguous because it could be reasonably interpreted in two different ways. The trial
    court found no valid contract existed because the required meeting of the minds did not take place.
    After a de novo review of the entire record in this case, we reach the same conclusion that the trial
    court reached.
    -4-
    The formation of a contract “‘must result from a meeting of the minds of the parties in mutual
    assent to the terms . . . .’” Doe v. HCA Health Services of Tennessee, Inc., d/b/a HCA Donelson
    Hospital, 
    46 S.W.3d 191
    , 196 (Tenn. 2001) (citations omitted). In the construction of a contract, the
    intention of the parties at the time the agreement is executed governs. Planters Gin Company v.
    Federal Compress & Warehouse Company, Inc., et al, 
    78 S.W.3d 885
    , 890 (Tenn. 2002). The
    parties are presumed to have expressed their intentions in the language of the agreement. Id. When
    this expression of intent is “clear and unambiguous, the literal meaning of the language controls the
    outcome.” Id. Terms of the contract that “may be susceptible to more than one reasonable
    interpretation . . . render[] the terms of the contract ambiguous.” Id. This court has similarly defined
    ambiguity as it relates to a contract provision as “doubt or uncertainty arising from the possibility
    of the same language being fairly understood in more ways than one.” Inscoe v. Kemper, No.
    M1999-00741-COA-R3-CV, 2000 Tenn. App. LEXIS 736, at *8 (Tenn. Ct. App. Nov. 6, 2000)
    (citing Hillis v. Powers, 
    875 S.W.2d 273
    , 276 (Tenn. Ct. App. 1993)). There is no “meeting of the
    minds” when a contract term is ambiguous, and thus no enforceable contract. Id. (citing Jamestowne
    On Signal, Inc. v. First Federal Savings & Loan Ass’n, 
    807 S.W.2d 559
    , 564 (Tenn. Ct. App. 1990)
    (further citations omitted)).
    The testimony at trial detailed a series of negotiations between Mansker Farms and the Board.
    These negotiations took place over a period of several years and involved several different proposals
    for a school location on the Mansker Farms development. Witnesses for Mansker Farms testified
    that the negotiations that led to the agreement in dispute were brought about because of its need for
    zoning approval, and that they made clear that it was essentially a school-for-zoning deal. The
    Board’s witnesses testified they were not aware of this condition. During the course of negotiations
    between the parties, Mr. McClung added the language in dispute to the end of Paragraph 5 (d) in his
    handwriting on a contract proposal sent to him by Ms. Dennen. This language was reviewed by the
    Board and was incorporated into the signed option contract. The Board’s witnesses testified that they
    were unaware of Mr. McClung’s interpretation of that language while witnesses for Mansker Farms
    testified that the Board was aware of the condition it was putting on the exercise of the option. This
    lack of a “meeting of the minds” on this provision where both sides were revising and adding
    language to the contract provision, each with their own interpretation, created an ambiguous
    provision.
    We find that the language of section 5(d), specifically the parts reading “including the
    proposed site plan and rezoning as hereinabove recited” and “[s]chool system agrees to support
    and/or assist Seller with said change,” to be capable of two different but reasonable interpretations.
    On the one hand, the Board’s position that the zoning referred to was only that for the school and
    not for the entire Mansker Farms development is a reasonable interpretation. On the other hand, the
    word “rezoning” and the phrase “[s]chool system agrees to support and/or assist Seller with said
    change” can be reasonably interpreted as referring to the entire Mansker Farms property and the idea
    that Mansker Farms was conditioning its gift to the School on the “said change.” Thus, as evidenced
    by the ambiguity of this provision, there was no “meeting of the minds” between Mansker Farms and
    the Board. As stated above, when there is no “meeting of the minds” there can be no enforceable
    contract. Thus, we affirm the judgment of the trial court.
    -5-
    Conclusion
    Because there is not a valid contract, all other issues are moot. We affirm the judgment of
    the trial court. Costs are taxed to the Appellant, Sumner County Board of Education, and its surety,
    for which execution may issue, if necessary.
    ___________________________________
    ALAN E. HIGHERS, JUDGE
    -6-