Ronald E. Brown v. Balaton Power, Inc. ( 2003 )


Menu:
  •                     IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    September 5, 2002 Session
    RONALD E. BROWN v. BALATON POWER, INC.
    Appeal from the Chancery Court for Williamson County
    No. 27720  Russ Heldman, Chancellor
    ________________________________
    No. M2001-02770-COA-R3-CV - Filed December 31, 2003
    ________________________________
    This case involves the issue of whether parties contracted for arbitration to be the sole method of
    dispute resolution with regard to contract disputes. We find the intent of the parties unclear due to
    an irreconcilable conflict between two sections of the contract dealing with dispute resolution. We,
    thus, affirm the trial court’s ruling that Plaintiff cannot be compelled to arbitrate.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Affirmed and Remanded
    WILLIAM B. CAIN , J., delivered the opinion of the court, in which PATRICIA J. COTTRELL, J., and
    ELLEN HOBBS LYLE, SP . J., joined.
    A. Russell Willis, William B. Hawkins, Nashville, Tennessee; John W. Elwick, Vancouver, British
    Columbia, for the appellant, Balaton Power, Inc.
    William L. Harbison, L. Webb Campbell, Ryan A. Rafoth, Nashville, Tennessee, for the appellee,
    Ronald E. Brown.
    OPINION
    Balaton Power, Inc. (“Balaton”) is a Canadian power company incorporated and
    headquartered in Vancouver, British Columbia, with a field office located in Boise, Idaho. From
    August of 2000 to February of 2001, Balaton maintained an administrative/marketing office in
    Franklin, Tennessee.1 Balaton hired Ronald E. Brown as the President and CEO of the Franklin
    office and signed an employment contract to that effect on July 27, 2000. The employment contract
    contained an arbitration clause, which is the central issue on appeal.
    1
    The parties agreed that United States Federal law and Tennessee law would govern the arbitration issue
    presented in this appeal.
    On December 5, 2000, Mr. Brown submitted a letter of resignation from his position as
    President and CEO. At that time, Mr. Brown exercised the option in his employment contract to be
    appointed Senior Vice-President of Marketing for Balaton. He continued working in that position
    until February 12, 2001. On that date, Balaton informed Mr. Brown by a letter written by Rodney
    E. Smith, President of Balaton, of his immediate suspension without pay.
    Between February 12, 2001, and April 27, 2001, Balaton investigated several allegations
    against Mr. Brown. In a letter dated April 27, 2001, Balaton terminated the employment agreement
    with Mr. Brown. That letter stated that, while the investigation was ongoing, the “preliminary results
    are such that the company now exercises its right to terminate the Employment Agreement and your
    services for just cause.” The termination was effective as of February 12, 2001. Mr. Brown then
    filed suit against Balaton for breach of the employment agreement alleging that he had been
    wrongfully terminated and deprived of salary, benefits, and stock options.
    The trial court entered an Order directing the parties to submit the cause to a mediator. Mr.
    Brown sought a default judgment, based upon Balaton’s failure to answer the Complaint. Balaton
    responded and filed the Affidavit of the President and Director, Rodney Smith. Their response
    argued that default judgments were unfavored, particularly when the defendant demonstrates a
    meritorious defense to the complaint. Balaton answered the Complaint soon thereafter and argued
    that Mr. Brown failed to state a claim upon which relief could be granted and that the trial court
    lacked jurisdiction over the action as the Employment Agreement mandated arbitration in accordance
    with the laws of British Columbia, Canada. Balaton then filed a Motion to Dismiss arguing that the
    employment agreement stipulated that all disputes were to be arbitrated and, therefore, the trial court
    lacked jurisdiction.
    The trial court entered a scheduling order directing the parties to comply with the court’s
    previous Order of mediation, setting the date for discovery completion, and setting February 6, 2002,
    as the date for trial. The trial court denied the Defendant’s Motion to Dismiss on October 2, 2001,
    that Order stating:
    The Court finds that the Employment Contract in this matter contemplates in Section
    8.1 the filing of a complaint in “a court of competent jurisdiction,” that the Chancery
    Court for Williamson County, Tennessee has jurisdiction over the parties and the
    subject matter of this case, and that there is no requirement that the case be brought
    in British Columbia as urged by the Defendant.
    On October 5, 2001, Balaton filed a Motion to Compel Arbitration, based upon the argument
    that “[m]ediation is not the agreed upon means for the resolution of this dispute and is not likely to
    be successful” and that “[t]he parties to this contract intended for any dispute to be arbitrated
    according to the laws of British Columbia.”
    On October 22, 2001, the trial court heard Balaton’s Motion to Compel Arbitration. The trial
    court denied the Motion to Compel Arbitration, finding that “the inconsistencies between paragraphs
    2
    8.1 and 8.2 of the employment agreement cannot be reconciled.” Balaton also orally requested an
    interlocutory appeal on the issue of whether Mr. Brown can be compelled to arbitrate this dispute.
    On November 20, 2001, Mr. Brown filed a Motion to Dismiss the Appeal with this Court.
    Balaton responded by filing its Motion for Clarification on November 21, 2001, seeking a
    determination as to whether it should proceed with the appeal under Tennessee Rule of Appellate
    Procedure 3 or 9. This Court denied the Motion to Dismiss the Appeal on January 7, 2002, and
    clarified that the appeal was allowed under Rule 3 by Tennessee Code Annotated section 29-5-319.
    This Court stayed all proceedings in the trial court, including discovery, during the pendency of the
    appeal.
    On appeal, Balaton argued that the parties anticipated arbitration to be the method by which
    disputes arising from the employment agreement would be resolved and that the question of whether
    arbitration is the proper method should be determined by applying the law of the Tennessee Uniform
    Arbitration Act, section 29-5-301 to 320 of the Tennessee Code, and the Federal Arbitration Act, 9
    U.S.C. § 2. Mr. Brown, on the other hand, argued that, due to the conflicting language in the
    Employment Agreement that was drafted by Balaton, the trial court correctly held that Brown could
    not be compelled to arbitrate the dispute. He also argued that Balaton waived its right to arbitrate
    the dispute as a result of its actions which were inconsistent with an intent to arbitrate.
    I. The Employment Agreement
    The employment contract at issue herein contains an arbitration clause, construction of which
    is the primary issue on appeal. The pertinent section at issue states:
    8.      Governing Law
    8.1     This agreement shall be governed by and construed in accordance with the
    laws of the Province of British Columbia, Canada or in such jurisdiction
    wherein the Company’s Registered Head Office is located if the Company
    decides to relocate said Registered Head Office and any action or proceeding
    in respect of it or alleging a breach of it will be commenced and maintained
    only in a court of appropriate jurisdiction.
    8.2     Any dispute, controversy or claim arising out of or relating to this agreement
    or the breach of it shall be settled by arbitration in accordance with the laws
    of the Province of British Columbia, Canada or other appropriate jurisdiction
    per 8.1 above and, unless the parties agree to refer the same to a single
    arbitrator, shall be referred to two arbitrators, one to be chosen by each of the
    parties and the arbitrators shall, before entering on the reference, appoint an
    umpire.
    There is no question that, if the parties made an agreement to arbitrate, that agreement must
    3
    be enforced by this Court. The issue is, however, whether the above cited paragraphs, together, show
    that the parties intended arbitration to be the sole required method of contract resolution.
    Because the contract in this case is one that involves interstate commerce, the
    [Federal Arbitration Act] applies to ensure that the arbitration agreement between the
    parties is enforced according to its terms. . . .
    The purpose of the FAA is “to ensure the enforceability, according to their
    terms, of private agreements to arbitrate.” Mastrobuono v. Shearson Lehman Hutton,
    Inc., 
    514 U.S. 52
    , 57, 
    131 L. Ed. 2d 76
    , 
    115 S. Ct. 1212
    (1995); Volt Info. Sciences,
    
    Inc., 489 U.S. at 476
    , 
    109 S. Ct. 1248
    . However, parties cannot be forced to arbitrate
    claims that they did not agree to arbitrate. As the United States Supreme Court has
    stated,
    Arbitration under the [FAA] is a matter of consent, not coercion, and
    parties are generally free to structure their arbitration agreements as
    they see fit. Just as they may limit by contract the issues which they
    will arbitrate, so too may they specify by contract the rules under
    which that arbitration will be conducted.
    Volt Info. Sciences, 
    Inc., 489 U.S. at 479
    , 109 S.Ct.1248 (citations omitted).
    The FAA’s “proarbitration policy does not operate without regard to the
    wishes of the contracting parties.” 
    Mastrobuono, 514 U.S. at 57
    , 
    115 S. Ct. 1212
    .
    Because “arbitration is a matter of contract[,] . . . a party cannot be required to submit
    to arbitration any dispute which he has not agreed so to submit.” AT&T Techs., Inc.
    v. Communications Workers of Am., 
    475 U.S. 643
    , 648, 
    89 L. Ed. 2d 648
    , 
    106 S. Ct. 1415
    (1986). When parties agree to arbitration, the FAA ensures enforcement of that
    agreement by withdrawing “the power of the states to require a judicial forum for the
    resolution of claims which the contracting parties agreed to resolve by arbitration.”
    Southland 
    Corp., 465 U.S. at 10
    , 
    104 S. Ct. 852
    . However, consistent with the FAA,
    parties may agree that only certain issues will be submitted to arbitration or that they
    will not arbitrate at all. Cf. Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth,
    Inc., 
    473 U.S. 614
    , 628, 
    87 L. Ed. 2d 444
    , 
    105 S. Ct. 3346
    (1985).
    Therefore, the question essentially becomes “what the contract has to say
    about the arbitrability of petitioner’s claim . . . .” 
    Mastrobuono, 514 U.S. at 58
    .
    Frizzell Const. Co., Inc. v. Gatlinburg, L.L.C., 
    9 S.W.3d 79
    , 83-4 (Tenn.1999).
    The question of whether parties intended the contract to require arbitration is clearly one to
    be decided by the court.
    The first principle gleaned from the Trilogy is that “arbitration is a matter of
    contract and a party cannot be required to submit to arbitration any dispute which he
    4
    has not agreed so to submit.” Warrior & 
    Gulf, supra, at 582
    ; American Mfg. 
    Co., supra, at 570-571
    (BRENNAN, J., concurring). This axiom recognizes the fact that
    arbitrators derive their authority to resolve disputes only because the parties have
    agreed in advance to submit such grievances to arbitration. Gateway Coal Co. v.
    Mine Workers, 
    414 U.S. 368
    , 374 (1974).
    The second rule which follows inexorably from the first, is that the question
    of arbitrability - - whether a collective-bargaining agreement creates a duty for the
    parties to arbitrate the particular grievance - - is undeniably an issue for judicial
    determination. Unless the parties clearly and unmistakably provide otherwise, the
    question of whether the parties agreed to arbitrate is to be decided by the court, not
    the arbitrator. Warrior & 
    Gulf, supra, at 582
    -583. See Operating Engineers v. Flair
    Builders, Inc., 
    406 U.S. 487
    , 491 (1972); Atkinson v. Sinclair Refining Co., 
    370 U.S. 238
    , 241 (1962), overruled in part on other grounds, Boys Markets, Inc. v. Retail
    Clerks, 
    398 U.S. 235
    (1970). Accord, Mitsubishi Motors Corp. v. Soler Chrysler-
    Plymouth, Inc., 
    473 U.S. 614
    , 626 (1985).
    The Court expressly reaffirmed this principle in John Wiley & Sons, Inc. v.
    Livingston, 
    376 U.S. 543
    (1964). The “threshold question” there was whether the
    court or an arbitrator should decide if arbitration provisions in a collective-bargaining
    contract survived a corporate merger so as to bind the surviving corporation. 
    Id., at 546. The
    Court answered that there was “no doubt” that this question was for the
    courts. “‘Under our decisions, whether or not the company was bound to arbitrate,
    as well as what issues it must arbitrate, is a matter to be determined by the Court on
    the basis of the contract entered into by the parties.’ . . . The duty to arbitrate being
    of contractual origin, a compulsory submission to arbitration cannot precede judicial
    determination that the collective bargaining agreement does in fact create such a
    duty.” 
    Id., at 546-547 (citations
    omitted).
    AT&T Techs., Inc. v. Communications Workers of America, 
    475 U.S. 643
    , 648-49 (1986).
    Further, we review this issue de novo, with no presumption of correctness.
    There are no factual disputes on appeal; the interpretation of the arbitration
    clause of the contract is a question of law. Rapp Constr. Co. v. Jay Realty Co., 
    809 S.W.2d 490
    , 491 (Tenn.App.1991). Therefore our review of the judgment below is
    de novo upon the record with no presumption of correctness of the trial court’s
    conclusion of law. Tenn. R. App. P. 13(d); Carvell v. Bottoms, 
    900 S.W.2d 23
    , 26
    (Tenn.1995).
    In Re: Estate of Wyatt, No. 02A01-9706-PB-00132, 
    1998 WL 477668
    , at *2 (Tenn.Ct.App.1998).
    A party cannot be required to arbitrate unless arbitration was the exclusive remedy for which
    the parties contracted. In this determination we turn to ordinary rules of contract construction.
    5
    Courts should generally apply “ordinary state-law principles” in deciding
    whether the parties agreed to submit certain issues to arbitration. See First Options
    of Chicago, Inc. v. Kaplan, 
    514 U.S. 938
    , 944, 
    131 L. Ed. 2d 985
    , 
    115 S. Ct. 1920
           (1995) (citing 
    Mastrobuono, 514 U.S. at 62-63
    , 
    115 S. Ct. 1212
    ). Under Tennessee
    law, the law governing this contract, the “cardinal rule [in interpreting contracts] . .
    . is to ascertain the intention of the parties and to give effect to that intention,
    consistent with legal principles.” Bob Pearsall Motors, Inc. v. Regal Chrysler - -
    Plymouth, Inc., 
    521 S.W.2d 578
    , 580 (Tenn.1975). Courts may determine the
    intention of the parties “by a fair construction of the terms and provisions of the
    contract, by the subject matter to which it has reference, by the circumstances of the
    particular transaction giving rise to the question, and by the construction placed on
    the agreement by the parties in carrying out its terms.” Penske Truck Leasing Co. v.
    Huddleston, 
    795 S.W.2d 669
    , 671 (Tenn.19909). No single clause in a contract is
    to be viewed in isolation; rather, the contract is to be “viewed from beginning to end
    and all its terms must pass in review, for one clause may modify, limit or illuminate
    another.” Cocke County Bd. of Highway Comm’rs v. Newport Utils. Bd., 
    690 S.W.2d 231
    , 237 (Tenn.1985).
    Frizzell 
    Constr., 9 S.W.3d at 85
    . These rules of construction are further elaborated in Coble Systems,
    Inc. v. Gifford Co., 
    627 S.W.2d 359
    (Tenn.Ct.App.1981).
    From the four corners of the agreement then, what did the parties intend when
    this agreement was executed? There are other rules of construction that can be
    applied to help resolve the apparent conflict. First and most important is the primary
    rule that the intent of the parties must prevail. Ohio Cas. Co., Inc. v. Travelers
    Indemnity Company, 
    493 S.W.2d 465
    (Tenn.1973). Second, the courts will construe
    the writing so as to avoid the conflict if possible. Bartlett v. Phillips - Carey Mfg.
    Co., 
    216 Tenn. 323
    , 
    392 S.W.2d 325
    (1965). Third, if the provisions are so
    repugnant that they cannot stand together, the first shall be given effect and the latter
    rejected. 17 Am.Jur.2d Contracts, § 267; Bartlett v. Phillips-Cary Mfg. Co., supra;
    Smithart v. John Hancock Mut. Life Insurance Company, 
    167 Tenn. 513
    , 
    71 S.W.2d 1059
    (1934). Fourth, written or typewritten terms will control printed parts of an
    agreement where there is an apparent inconsistency. 17 Am.Jur.2d Contracts, § 271;
    Tindell v. Bowers, 31 Tenn.App. 474, 
    216 S.W.2d 752
    (1949). Fifth, doubtful
    language in a contract should be interpreted most strongly against the party who drew
    or prepared it. 17 A.Jur.2d Contracts, § 276. This last rule is to be applied, however,
    only where other rules of construction fail to give certainty to the written expression.
    17 Am.Jur.2d Contracts, § 276; Crouch v. Shepard, 
    44 Tenn. 383
    (1867).
    Coble 
    Systems, 627 S.W.2d at 363
    . It should also be remembered that courts are precluded from
    creating contracts for the parties. Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc., 
    521 S.W.2d 578
    , 580 (Tenn.1975).
    6
    In reviewing this contract and the language of the “Governing Laws” section that is alleged
    to contain an arbitration agreement, we cannot say this language constitutes an agreement to arbitrate
    as the sole method of dispute resolution. The section is ambiguous and the intent of the parties is
    not clear from reading the language as written. Section 8.1 contemplates a cause of action for breach
    of the agreement being “commenced and maintained only in a court of appropriate jurisdiction.”
    Section 8.2 requires arbitration in the same appropriate jurisdiction set out in 8.1. Numerous cases
    from other states cited by Balaton Power have harmonized a choice of law provision with an
    arbitration clause in the same contract. However, none of those cases contain the mandatory
    “commenced and maintained” language in the contract at issue. The language of section 8.1
    provides that a legal action for breach “will be commenced and maintained” in a court of law. The
    conflict between these two sections is unavoidable. Except through a strained reading that ignores
    or avoids words, the two sections cannot be reconciled.
    Due to the unresolvable ambiguity of the language and Tennessee’s rules of contract
    interpretation, “the first section should be given effect and the latter rejected.” Coble 
    Systems, 627 S.W.2d at 363
    . As such, the trial court was correct in rejecting Balaton’s Motion to Compel
    Arbitration. We find no contractual agreement between the parties giving up their right to redress
    in a court of law.
    Mr. Brown also argued that Balaton Poiwer had waived its right to arbitration. However, as
    we find that Balaton has no right to arbitration, that issue is moot.
    The ruling of the trial court is affirmed.
    ___________________________________
    WILLIAM B. CAIN, JUDGE
    7