Paul E. Johnson v. The Metropolitan Government Of ( 2002 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    January 9, 2002 Session
    PAUL E. JOHNSON v. THE METROPOLITAN GOVERNMENT OF
    NASHVILLE AND DAVIDSON COUNTY, TENNESSEE, AND LESTER L.
    WILLIAMS, JR., DIRECTOR OF THE DEPARTMENT OF WATER AND
    SEWERAGE SERVICES OF THE METROPOLITAN GOVERNMENT OF
    NASHVILLE AND DAVIDSON COUNTY.
    Appeal from the Chancery Court for Davidson County
    No. 99-1886-II   Carol McCoy, Chancellor
    No. M2001-00633-COA-R3-CV - Filed December 11, 2002
    Paul E. Johnson, a Nashville real estate developer, filed a complaint demanding a refund for
    sewer access fees paid to the Metropolitan Department of Water and Sewerage Services. A
    counterclaim was filed by Metro alleging Mr. Johnson executed a valid contract to contribute
    $1,000,000 toward the construction of the Mill Creek sewer trunk line, less the net amount of
    any excess access fees paid under a previous agreement. Mr. Johnson denied the existence of a
    contract to share the cost of extending the trunk sewer link. The trial court dismissed Mr.
    Johnson’s claims and entered judgment in favor of the Metropolitan Department of Water and
    Sewerage Services for $688,942.88. Mr. Johnson appealed.
    Tenn.R.App.P.3 Appeal as of Right; Judgment of the Chancery Court
    Affirmed
    ASH ,S.J., delivered the opinion of the court, in which Ben H. Cantrell, P.J.,M.S., and Patricia
    Cottrell J., joined.
    Carol D. Kilgore, Nashville, Tennessee, for the appellant, Paul E. Johnson.
    Thomas G. Cross, Nashville, Tennessee, for the appellees, The Metropolitan Government of
    Nashville and Davidson County, Tennessee.
    1
    OPINION
    I. Background
    In 1988, Paul E. Johnson (“Johnson”/ “the developer”), a Nashville real estate developer,
    sought sewer access for a parcel of land that was eventually developed as the Bradford Hills and
    Holt Woods subdivisions. This property naturally drains into Mill Creek, a tributary of the
    Cumberland River. The Metropolitan Department of Water and Sewerage Services (“Metro”)
    informed Johnson the sewer line nearest the property, known as the Whittemore Branch sewer,
    was nearing capacity. At the time, Metro believed the increased flow from proposed
    development would encroach upon the limited capacity of the Whittemore Branch natural
    drainage basin. Harold Delk, Johnson’s engineer and agent for sewer project negotiations, wrote
    to Metro on August 1, 1988, and agreed for the developer to pay $1,000 per lot in lieu of the
    present $500 per lot access charge, to help finance any necessary enlargements or extensions of
    the Whittemore trunk line and construction of a new Mill Creek-Holt Creek trunk sewer.1
    Correspondence from Metro Director Buddy Williams to Harold Delk, dated March 17, 1989
    clarified the $1,000 access fee proposed by Delk by designating $500 as participation in the
    construction of the Mill Creek sewer trunk and $500 as the sewer charge authorized by the
    Metropolitan Council through the Metro Charter. Mr. Delk’s letter in response dated March 22,
    1989 accepted the terms of the Whittemore Agreement. Johnson developed Bradford Hills and
    Holt Woods subdivisions as planned and paid Metro $394, 500 over the succeeding years
    pursuant to the Whittemore Agreement.
    Johnson originally planned to engage a contractor to complete the Mill Creek sewer
    extension, and Metro would contribute funds for part of the cost. Bids were let for the project
    but returned exceeding the authorized budget of $1.3 million and the project was not undertaken
    at that time. Negotiations continued between Metro and Johnson and his agents. On March 2,
    1994, Metro wrote Johnson regarding his participation in the Mill Creek trunk sewer. Metro
    acknowledged they had no objection to capping Johnson’s participation at $1,000,000 toward the
    cost of the project, less credit for the net amount previously paid for excess capacity fees under
    the Whittemore Agreement. Mr. Johnson wrote Metro on October 17, 1994 to memorialize the
    terms of the Mill Creek Agreement in a single document. Johnson modified the outlined formal
    agreement and signed the letter indicating his acceptance of the terms set forth therein. He also
    stated he would neither be subject to, nor the beneficiary of, any subsequent basis impact fees or
    participation by other users of the proposed sewer system, and all construction work on phase
    one would include plans by Anderson Delk and Associates, Inc. approved by the Water
    Department on June 14, 1993. The agreement by the parties was subject to construction of the
    sewer beginning not later than June 1, 1995. The Mill Creek Agreement was also contingent
    1
    The trial court found H arold Delk was Johnson’s agent for sewer project nego tiations. D elk was prominently
    involved in negotiations with Metro o n behalf of M r. Johnson for bo th the W hittemo re and Mill Creek Agreements.
    Johnson and D elk co-authored m uch of the pro ject co rrespondence, which was frequently prepared b y Delk’s
    secretary and mailed from D elk’s office.
    2
    upon approval of the Metropolitan Council.2 Metro replied to Johnson’s offer by letter dated
    December 27, 1994 as written confirmation of acceptance of the developer’s latest
    modifications. However, Metro cautioned Johnson the project involved complex preliminary
    review of environmental and archeological issues. Consequently, they could not guarantee
    construction of the project would begin by June 1, 1995. On June 8, 1995, after the expiration of
    the June 1, 1995 deadline for beginning construction expired, Johnson voluntarily wrote Metro
    and offered to extend the date to begin construction until August 15, 1995. When construction
    had not begun by August 15, 1995, Johnson again wrote to Metro on August 30, 1995, stating,
    “if the Mill Creek Sewer can not be advertised for bids by September 15, 1995, I will have no
    choice but to withdraw my offer of one million dollars for the construction of this project.”
    Metro advertised the project for bids on September 3, 1995. Metro then conducted a pre-bid
    meeting attended by Johnson’s engineer, Harold Delk. The parties did not have any direct
    contact with each other after this meeting.
    Excavation work began in April of 1996. Johnson observed the construction of the
    project throughout until its completion approximately three years later. Johnson did not
    contribute anything to the funding of the Mill Creek extension pursuant to the agreement with
    Metro and reflected in ordinance number095-1488. Furthermore, the developer demanded a
    refund of the excess access fees paid under the Whittemore Agreement four months after the
    Bradford Hills and Holt Woods subdivisions were connected to the sewer. Metro completed the
    project shortly thereafter and requested Johnson pay the outstanding balance under the Mill
    Creek Agreement. The developer claimed any obligation he may have had to make such
    payments terminated August 15, 1995 because construction was delayed. Johnson filed a
    complaint demanding a refund for the sewer access fees. Metro counterclaimed seeking
    enforcement of the Mill Creek Agreement as either a unilateral or bilateral contract or under
    unjust enrichment or promissory estoppel theories. Johnson denied the existence of a contract to
    share the cost of extending a trunk sewer link and claimed the excess access fees were paid
    under extortion or duress.
    The trial court made the following findings of fact and conclusions of law: First,
    Johnson’s claim that his obligation terminated on August 15, 1995 ignored the existence of a
    contract with Metro on that date. Second, an ordinance was passed, and Johnson was not
    entitled to cancel the contract by his silence. Third, Johnson may have been in a position to
    cancel the contract had he acted affirmatively. However, Johnson unilaterally and voluntarily
    demanded bids be let by September 16, 1995, and Metro complied with this demand.
    Consequently, Metro was in a position to have a binding contract at that time despite the fact
    construction had not started. Johnson’s silence and acquiescence waived the provision requiring
    construction to begin by August 15, 1995. Fourth, Johnson continued to participate in the Mill
    Creek Branch extension in accordance with the terms of the agreement with Metro except for the
    payment of the additional monies he had promised. Fifth, it was evident from proof that Johnson
    greatly desired the Mill Creek Branch extension. Without his promise of $1,000,000, the
    extension would not have gone forward on a timely basis, benefiting Johnson. Sixth, Metro did
    2
    Ordinance number 095-1488 authorizing the acceptance of an amount not to exceed $1,000,000 from Johnson for
    the installation of the Mill Creek and Holt Creek trunk sewers was introduced to the M etropolitan Council on June
    20, 1995 and approved on August 3, 1995. Ho wever, the Metropolitan Council ordinance did not state all of the
    terms se t forth in the letter of agreem ent.
    3
    not coerce Johnson to enter the agreement, nor was the agreement void for duress. Any duress
    felt by Johnson was the result of his acquisition of a parcel of land for development without prior
    inquiry regarding sewer capacity or availability. Seventh, Johnson’s proposed payment toward
    the development of the Mill Creek Branch was properly made and accepted in accordance with
    Metro code §15.36.040 regarding developers who wish to fund construction or expansion of
    trunk sewers. The participation in the development came to fruition over a period of years,
    beginning with a $500 per unit payment that was later supplemented by the offer of $1,000,000
    capping Johnson’s contribution.
    The trial court found there was a contract obligating Johnson to pay $1,000,000. This
    agreement was appropriately authorized by Williams on behalf of the Metropolitan Government
    and the contract was properly ratified by the Metropolitan Council by its ordinance.      The
    requirements that contractual obligations be sworn to and executed by the participating parties
    were formalities waived by both parties. Johnson’s actions ratified the agreement, where he
    requested the funds previously paid to Metro in excess of $300,000 be applied towards his
    $1,000,000 obligation. Johnson was given credit accordingly. The trial court emphasized these
    parties entered into a contractual agreement and concluded Metro was not entitled to equitable
    relief or recovery under a theory of promissory estoppel or implied contract. The trial court
    ultimately dismissed Johnson’s claims and entered judgment in favor of Metro for $688,942.88.
    Johnson appealed.
    II. Statement of Issues
    The following issues are before the court: (A) Whether the trial court properly
    determined Johnson breached a valid and binding contract requiring him to pay an agreed
    amount to Metro toward the cost of extending the Mill Creek trunk sewer; and (B) Whether the
    trial court should have determined Johnson was liable, in the absence of a binding contract,
    under principles promissory estoppel or implied contract.
    III. Analysis
    A.      Whether the trial court properly determined Johnson breached a valid and
    binding contract requiring the developer to pay an agreed amount toward the
    cost of extending the Mill Creek trunk sewer.
    Johnson asserts the trial court erred in determining he breached a valid and binding
    contract obligating him to pay the balance owing under an offer to contribute $1,000,000 to the
    extension of the Mill Creek trunk sewer. Instead, the developer argues his unilateral offer to
    participate in the sewer extension project expired when construction did not begin on August 15,
    1995 and he is entitled to a refund of $395,000 previously paid to Metro. Johnson specifically
    challenges the enforceability of the agreement under four theories:
    4
    1.        Whether the trial court erred by holding Johnson became contractually
    bound after the Metropolitan Council passed ordinance number 092-384
    approving the developer’s unilateral offer on August 3, 1995, even though
    Metro did not commence construction by August 15, 1995, or by any other
    date dictated by the time pressures of the developer’s business.
    2.        Whether the trial court erred in holding Johnson became contractually
    bound by virtue of his writing of August 30, 1995, where he threatened to
    terminate his participation in the Mill Creek sewer extension unless Metro
    advertised the project for bids by September 15, 1995, followed by
    Metro’s advertisement on September 3, 1995, when such advertisement
    was not proven to have been published in response to the developer’s
    letter, and when bid advertisement was not a valuable benefit sought by
    Johnson but merely a preparatory act essential to the commencement of
    construction, when the tenor of the developer’s August 30, 1995 letter did
    not reaffirm his prior expired offer nor incorporate it by reference, and
    Metro did not inform him that it had advertised the project nor seek any
    extension of the date required for the commencement of construction.
    3.        Whether the trial court erred in holding Johnson was contractually bound
    upon the theory that a metro ordinance provision authorized the Water and
    Sewer Department Director to enter into the contractual arrangement with
    the developer, where the understanding, as set out in correspondence, did
    not conform to the requirements of the cited Metro provision.
    4.        Whether the trial court erred in rejecting Johnson’s claim of a right to a
    refund of the unauthorized sewer connection charges of $500 per lot, plus
    interest, imposed upon him in addition to the $500 capacity fee authorized
    by the Metro Code, where Johnson paid such amounts totaling $395,000 as
    the only way he could get sewer service, but insisted the amounts were
    paid under duress.
    In contrast, Metro argues this dispute is a simple breach of contract case. Metro suggests
    the Mill Creek agreement can be construed as either a bilateral contract based on the parties’
    exchange of promises, or a unilateral contract arising from Johnson’s offer and Metro’s
    acceptance by performance.
    The court will address each of these questions in turn.
    1.The Metropolitan Council’s Authorizing Ordinance
    5
    Johnson first challenges the trial court’s determination he became contractually bound
    after the Metropolitan Council passed ordinance number 092-384 approving the developer’s
    unilateral offer, even though Metro did not commence construction by August 15, 1995, or by
    any other date dictated by the time pressures of the developer’s business. A unilateral contract
    arises from an offer calling for acceptance by performance of some act rather than by a return
    promise. Hutchinson v. Dobson-Bainbridge Realty Co., 
    217 S.W.2d 6
    (Tenn. Ct. App. 1946). It
    is the performance of all required acts that converts an offer into a unilateral contract. Allen v.
    Elliott Reynolds Motor Co., 
    230 S.W.2d 418
    (Tenn. Ct. App. 1950). Johnson maintains his offer
    to participate in the Mill Creek extension was a unilateral contract requiring acceptance through
    Metro’s construction of the project. The developer argues Metro was under no obligation to
    accept a bid or proceed with construction. Johnson claims Metro must have commenced
    construction by a stated date, originally June 1, 1995, in order to bind him under the offer.
    When construction did not begin on that date, Mr. Johnson wrote Metro proposing an extension
    for the commencement of construction until August 15, 1995. Johnson acknowledges the
    voluntary extension of a new deadline constitutes a new offer where the offeree fails to meet the
    stated deadline. Robinson v. Tennessee Farmers Mut. Ins. Co., 
    857 S.W.2d 559
    (Tenn. Ct. App.
    1993). However, the developer disputes the trial court’s finding the Metropolitan Council’s
    adoption of the authorizing ordinance on August 3, 1995 created a contract because he suggests
    acceptance of the unilateral offer required the beginning of construction within the stated
    deadline. Johnson maintains there is no contract if the new deadline was not met. 
    Id. Thus, he alleges
    the offer expired when Metro failed to begin construction by August 15, 1995.
    Metro directs the court’s attention to the Restatement (Second) of Contracts § 45(2), and
    suggests the doctrine of partial performance would preclude Mr. Johnson from revoking his
    offer. The doctrine of partial performance provides the offeror may not revoke an offer calling
    for acceptance via performance of some act once the offeree begins performance. The doctrine
    of partial performance would appear to be applicable to the Mill Creek agreement. The
    negotiation and construction of this complex sewer extension project involved the performance
    of many steps toward the project’s ultimate completion over a period of nearly a decade rather
    than the performance of a single act.
    Johnson’s argument fails to consider the existence of a bilateral contract formed through
    the parties’ exchange of promises and correspondence. A bilateral contract is based upon a
    conventional exchange of promises. In a bilateral contract, the promise on side is viewed as
    consideration for the return promise, and both parties are bound from the moment they exchange
    promises. Hutchinson at 9. Notably, if the offer does not specify how it is to be accepted, either
    a return promise or performance is effective. Metro directs the court’s attention to Restatement
    (Second) of Contracts § 32, which provides, “In case of doubt, an offer is interpreted as inviting
    the offeree to accept either by promising to perform what the offer requests or by rendering
    performance, as the offeree chooses.” Thus, the Mill Creek agreement may be viewed as a
    bilateral agreement, where Metro’s December 27, 1994 letter accepting the offer posed in
    Johnson’s October 17, 1994 letter created a contract that bound both parties at that time. These
    items of correspondence reflect the assent of both parties to the essential terms of the agreement.
    6
    This court affirms the trial court’s holding Johnson became contractually bound after the
    Metropolitan Council passed ordinance number 092-384 approving the developer’s offer to
    participate in the Mill Creek sewer extension.
    2.Mr. Johnson’s August 30, 1995 Writing Threatening to Terminate Participation
    Johnson concedes the Chancellor correctly ruled the offer was voluntarily reinstated by
    his writing extending the date for the commencement of construction until August 15, 1995.
    However, the developer challenges the trial court’s determination his subsequent writing
    demanding bids be let by September 15, 1995, or he would withdraw his offer of $1,000,000,
    kept the agreement alive. Mr. Johnson maintains the mere referral to a prior contract or offer
    does not incorporate the same by reference or re-state the old-offer. Frierson v. International
    Agricultural Corp., 
    148 S.W.2d 27
    (Tenn. Ct. App. 1940). The developer insists the tenor of this
    writing did not reaffirm his prior expired offer nor incorporate it by reference. This court finds
    Johnson’s writing, and Metro’s compliance with this demand, support the existence of the
    contract. When offers have been made, and the actions of both parties indicate they believe
    there is a contract, this tends to compel the conclusion a contract exists. APCO Amusement Co.
    v. Wilkins Family Restaurants, Inc., 
    673 S.W.2d 523
    (Tenn. Ct. App. 1984). The Mill Creek
    trunk sewer at issue was completed in 1998. Bradford Hills and Holt Woods subdivisions are
    connected to Mill Creek as well as the Autumn Oaks property owned by Mr. Johnson. Johnson
    argues these facts lead to the conclusion that Metro did nothing at all to indicate a contract was
    formed.
    7
    Johnson argues the advertisement was not proven to have been published in response to
    his August 30, 1995 demand, Metro did not inform him that it had advertised the project for
    bids, nor seek any extension of the date required for the commencement of construction. His
    demand for advertisement of the project for bids did not include notification of compliance.
    Furthermore, the developer’s argument also overlooks the trial court’s conclusion his writing
    constituted acquiescence and waiver of the provision requiring construction begin by August 15,
    1995. Vested bilateral contract rights may be waived, such as where a seller has a duty to ship
    by a stated date and the buyer has a right to have the goods shipped by that date. The buyer may
    waive his vested right by continuing to demand shipment after the breach occurred. Petway v.
    Loew’s Nashville & Knoxville Corp., 
    117 S.W.2d 975
    (Tenn. Ct. App. 1938). Metro had a duty
    to begin construction of the Mill Creek sewer extension by August 15, 1995. Johnson had a
    vested right to performance on this date. Metro breached the terms of the Mill Creek agreement
    when construction did not commence by the stated date for performance. However, Johnson
    waived his right to performance by August 15, 1995 when he wrote Metro and demanded the
    project be advertised for bids by September 15, 1995 “or he would withdraw his offer of
    $1,000,000.” The time for performance is converted to a reasonable time when waiver of the
    time for performance pursuant to a bilateral contract occurs. The party entitled to performance
    may establish a new performance deadline by giving reasonable notice of this requirement.
    Thompson v. Menefee, 
    6 Tenn. App. 118
    (Tenn. Ct. App. 1927). Consequently, Metro was
    obligated to commence construction of the Mill Creek sewer extension within a reasonable time
    rather than some unspecified date dictated by the time pressures of the developer’s business.
    The project was advertised for bids on September 3, 1995. The bids were evaluated, a contractor
    was selected and excavation work for the Mill Creek sewer extension began in April of 1996.
    This court finds construction commenced within a reasonable time after Johnson’s demand for
    the project to be advertised for bids.
    Nor is the court persuaded by Johnson’s argument that advertisement for bids was merely
    a preparatory act conferring no benefit on the developer. Johnson compares this case to Savage
    v. Spur Distributing Co., 
    228 S.W.2d 122
    (Tenn. Ct. App. 1949), a case considering an
    individual promised permanent (lifetime) employment as a corporate officer if he would relocate
    from St. Louis to Nashville. The court held moving to Nashville did not furnish consideration
    because it was not the objective sought by the company, but was merely a preparatory act
    necessary to accept the offer of employment. We do not believe permanent employment
    conditioned upon relocation is analogous to the negotiation and completion of a complex sewer
    construction project lasting nearly a decade. The parties in this case understood the extension of
    the Mill Creek would be a lengthy process. The developer’s demand for the advertisement of the
    project for bids by September 15, 1995 reflected his continued desire for the construction of the
    Mill Creek sewer extension. Metro’s compliance with this demand reflected their belief that a
    contract existed between the parties and their continued commitment to the project.
    This court affirms the trial court’s determination Johnson’s subsequent writing
    demanding bids be let by September 15, 1995, or he would withdraw his offer of $1,000,000,
    demonstrated acquiescence and waiver of his right to performance by August 15, 1995. The
    developer’s failure to designate a new deadline for performance converted the time the
    commencement of construction to a reasonable time. This court finds construction commenced
    within a reasonable time after Johnson’s demand for the project to be advertised for bids.
    8
    3.Authorization of Metro Director Williams to Enter Into the Mill Creek Agreement
    Johnson also argues the trial court erred in holding he was contractually bound upon the
    theory that a Metro ordinance provision authorized the Water and Sewer Department Director to
    enter into the Mill Creek agreement. The developer claims the understanding between the
    parties, as set out in correspondence, did not conform to the requirements of Metro Code §
    15.36.040. Johnson further argues the excess access fees in dispute were unlawful, as they were
    not authorized by any Metro ordinance or Code provision. In support, the developer directs the
    court’s attention to Lebanon v. Baird, 
    756 S.W.2d 236
    (Tenn. 1988), where the Supreme Court
    held a contract was void and of no effect because the terms of the city charter provided this
    power could only be exercised through the enactment of an ordinance. Johnson suggests the
    decision in Lebanon v. Baird applies to any and every municipal action for whose achievement
    the charter provision requires an ordinance procedure to be followed.
    The Metropolitan Charter empowers the Metropolitan Government to provide for the
    rates, charges, and assessments necessary for the operation of the water and sewer systems. The
    trial court acknowledged the Metropolitan Government may only enter contracts as authorized
    by the charter and the Metropolitan code. Under Title 15, regarding water, sewer and other
    public services, Metro Code § 15.36.040 “Capacity Charge” includes several important
    provisions.
    A.      Notwithstanding any other provision of the Metropolitan Code of Laws to the
    Contrary, there is established a capacity charge of five hundred dollars per unit of
    flow on all new connections where public sewers do not exist, as of the effective date
    of this section (February 21, 1984). The charge shall apply, where sewers do exist,
    for all units of flow in excess of four per acre not to exceed a maximum charge of
    twenty-five thousand dollars per acre. This capacity charge shall be distinguished
    from and collected in addition to the existing tap fee required by § 15.36.020.
    B.      Trunk sewer construction or expansion funding by the Metropolitan Government
    shall be only upon the basis of availability of funds. If developers fund construction
    or expansion of trunk sewers, the Metropolitan Government shall collect the charges
    created herein in accordance with subsection F, below. Nothing in this subsection
    shall be construed to create any obligation on the Metropolitan Government to fund
    in whole or in part the construction or expansion of trunk sewers.
    C.      The charges established herein shall be placed in the extension and replacement fund
    of the Metropolitan Department of Water and Sewerage services.
    9
    ***
    F. All charges established by the enactment of this section shall be due and payable prior to
    issuance of a permit for service connection to the public sewer. If a developer
    prepays any part or all of the fee charge, such payments may be indicated with filing
    of the property subdivision plat or other duly recorded instrument. This contribution
    may be in the form of cash payments or equivalent construction cost. In the event a
    developer contributes, in equivalent construction cost, an amount greater than the
    charge established by this section, such developers shall be reimbursed for such
    contribution to that extent when the department collects other applicable fees from
    properties served by the project. Any such reimbursement shall be made only after
    the Metropolitan Government has been reimbursed for the entirety of its costs. The
    Department of Water and Sewerage services shall keep permanent records for each
    project, and all contractual obligations shall be sworn to and executed by the
    participating party. The director of the Department of Water and Sewerage services
    is authorized to enter into said agreements on behalf of the Metropolitan Government.
    The trial court concluded Metro Director Williams was authorized to enter the Mill Creek
    agreement with Johnson under subsection F: “The director of the Department of Water and
    Sewerage services is authorized to enter into said agreements on behalf of the Metropolitan
    Government. Subsection F also specifically contemplates the possibility that developers may be
    required to participate in the funding of a trunk sewer extension beyond the $500 capacity
    charge: “In the event a developer contributes, in equivalent construction cost, an amount
    greater than the charge established by this section, (emphasis added) such developers shall be
    reimbursed for such contribution to that extent when the department collects other applicable
    fees from properties served by the project. Any such reimbursement shall be made only after the
    Metropolitan Government has been reimbursed for the entirety of its costs.” This court rejects
    Johnson’s contention that situations such as the Mill Creek agreement, where developers may be
    required to contribute excess access fees, are unlawful. This arrangement was specifically
    provided for within Metro Code § 15.36.040(F).
    10
    Johnson also claims the understanding between the parties, as set out in correspondence, did
    not conform to the requirements of Metro Code § 15.36.040 because the excess capacity fees
    were designated as non-refundable. The following language in subsection (F) is implicated: “In
    the event a developer contributes, in equivalent construction cost, an amount greater than the
    charge established by this section, such developers shall be reimbursed for such contribution to
    that extent when the department collects other applicable fees from properties served by the
    project. Any such reimbursement shall be made only after the Metropolitan Government has
    been reimbursed for the entirety of its costs.” The developer correctly indicates subsection (F)
    provides for mandatory reimbursement of excess access fees, but only after the Metropolitan
    Government has been reimbursed for the entirety of its costs. The failure of the Mill Creek
    agreement to follow this requirement may render the clause regarding reimbursement of the
    excess access fees unenforceable. However, the failure to follow this requirement does not
    render the entire Mill Creek agreement unenforceable. This court refuses to ultimately rule
    regarding the enforceability or severability of the reimbursement clause as this issue was not
    considered at trial. This court affirms the trial court’s determination Metro Director Williams
    was authorized to enter into these agreements with Mr. Johnson on behalf of the Metropolitan
    Government in spite of the clause regarding the reimbursement of excess access fees.
    4.Duress
    11
    Finally, Johnson objects the excess access fees were unlawful as they were paid under
    duress. The developer complains he was in a position that gave him no alternative but to agree
    to these charges since his real estate development required sewer access. However, the trial
    court noted Johnson was not placed in that position by the actions of the Metropolitan
    Government. Johnson acquired, by option, a parcel of land he wished to develop without prior
    inquiry regarding the capacity or availability of sewer access. The trial court declared the
    developer’s duress was of his own making. The trial court found Metro did not impose any
    duress upon Johnson.
    Johnson remarks a public official’s imposition of some requirement upon a citizen is
    legally void when law does not authorize the requirement. Bradley v. State, 
    222 Tenn. 535
    , 
    438 S.W.2d 738
    (1969). However, as this court has previously stated, the imposition of the excess
    access fees by Metro Director Williams was specifically authorized by Metro Code § 5.36.040.
    The developer also directs the court’s attention to this Court’s decision in Reynolds v.
    Metropolitan Nashville - Davidson County, 1991 Tenn. App. LEXIS 123. Johnson declares
    official action done without authority and using governmental power to financially benefit a
    municipality or its officials by gaining assent to a protective contract constitutes duress and the
    contract is rendered illegal. However, the Reynolds case examined a threat to proceed with
    pending criminal charges in order to compel a defendant to sign a release of his rights under a
    personal injury claim after being shot by an officer. This court does not find Johnson’s
    allegations of duress analogous to the personal fear or threat of imprisonment considered in
    Reynolds.
    Furthermore, Johnson was free to reject the Mill Creek agreement if he objected to the
    excess access fees. The developer could have refused to proceed with the development of this
    parcel of land until more advantageous conditions were present. Likewise, Metro was under no
    obligation to extend the Mill Creek trunk sewer to Johnson’s planned real estate development.
    Metro Code § 5.36.040(B), specifically provides: “Nothing in this subsection shall be construed
    to create any obligation on the Metropolitan Government to fund in whole or in part the
    construction or expansion of trunk sewers.” Thus, Johnson freely chose to execute the Mill
    Creek agreement because it was financially in his best interest to participate in the construction
    of the sewer extension. This court affirms the trial court’s determination Metro did not force
    Johnson to execute the Mill Creek agreement under duress. This court concludes the Mill Creek
    agreement is valid and binding. Finally, Johnson also claims a constructive trust should be
    imposed on the excess access fees since they were obtained under duress. This court finds this
    issue is inapplicable as we affirmed the trial court’s determination Metro did not force Mr.
    Johnson to execute the Mill Creek agreement under duress.
    B. Whether the trial court should have determined Johnson was liable, in the absence
    of a binding contract, under principles promissory estoppel or implied contract.
    Alternatively, Metro argues they reasonably relied upon Johnson’s promises to pay an
    agreed share of the cost of the Mill Creek sewer extension and Johnson received a benefit from
    the project’s completion. Metro argues Johnson is obligated to keep his bargain even if no
    express contract existed. However, the issue of promissory estoppel or implied contract is moot,
    12
    as this Court has previously affirmed the trial court’s determination a binding contract obligated
    Johnson to contribute $1,000,000 to the cost of the Mill Creek sewer extension.
    IV. Conclusion
    This court affirms the trial court’s determination a binding contract existed between
    Johnson and Metro and the corresponding rejection of recovery for Metro under theories of
    promissory estoppel or implied contract. Johnson was obligated to contribute $1,000,000 toward
    the cost of the Mill Creek sewer extension under the terms of the Mill Creek agreement less
    credit for his previous participation. The trial court correctly dismissed Johnson’s claims and
    entered judgment in favor of Metro for $688,942.88. The judgment of the trial court is affirmed.
    The cost of this appeal shall be assessed against the appellant.
    __________________________________
    ASH, S.J.
    13