Pierre Pons v. Barry Harrison d/b/a B. Harrison Housewrights ( 2008 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    March 26, 2008 Session
    PIERRE PONS, ET AL. v. BARRY HARRISON d/b/a B. HARRISON
    HOUSEWRIGHTS
    Direct Appeal from the Chancery Court for Williamson County
    No. 32050    Jeffrey S. Bivins, Chancellor
    No. M2007-01909-COA-R3-CV - Filed July 9, 2008
    Defendant Homebuilder left plaintiff Homeowners’ job site before completing construction of their
    residence. Homebuilder appeals the chancery court’s confirmation of an adverse arbitration award,
    arguing that the arbitrator exceeded his authority by refusing to enforce a provision of the contract
    that would have rendered the plaintiff Homeowners’ suit time barred. The limitation provision
    applied to suits for defective improvements to real estate. The gravamen of this breach of contract
    action was partial performance, not defective performance. Further, the arbitrator awarded to
    Homeowners the cost to complete the construction plus interest, attorney’s fees, and arbitration costs.
    Finding that the limitation period does not apply to this action, we affirm.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; and
    Remanded
    DAVID R. FARMER , J., delivered the opinion of the court, in which ALAN E. HIGHERS, P.J., W.S., and
    HOLLY M. KIRBY , J., joined.
    L. Anthony Deas, Madison, Tennessee, for the appellant, Barry Harrison.
    Joel M. Leeman and Matthew C. Hardin, Nashville, Tennessee, and Douglas S. Hale, Franklin,
    Tennessee, for the appellees, Pierre Pons and Pauline Pons.
    OPINION
    Pierre and Pauline Pons (Mr. Pons, Mrs. Pons, or the Ponses) entered into a contract with
    Barry Harrison, d/b/a B. Harrison Housewrights (Mr. Harrison) on February 14, 2001, for the
    construction of a residence. The contract price for the house was $370,000, and Mr. Harrison was
    to use his best efforts to complete the construction within 180 days from the start of the framing,
    which began May 1, 2001. According to this time frame, the residence should have been completed
    around November 1, 2001. In February of 2002, Mr. Harrison ceased working on the house and left
    the job site. According to the Ponses, they had already paid Mr. Harrison a total of $369,476 by that
    time, but then had to pay an additional $100,000 to another contractor to complete the construction.
    The Ponses obtained a Certificate of Occupancy on March 7, 2002.
    On November 17, 2005, the Ponses filed a breach of contract action against Mr. Harrison in
    chancery court. After answering the Ponses’ complaint, Mr. Harrison obtained a stay of the
    proceedings pending the outcome of arbitration. The arbitration hearing occurred from February 21
    through February 23, 2007. On April 6, 2007, the arbitrator rendered an award in favor of the Ponses
    and specifically found that Mr. Harrison had breached the contract and that the defenses Mr.
    Harrison raised immediately prior to the hearing were not well taken.1 The arbitrator awarded the
    Ponses the sum of $214,866.35, which included the cost to complete construction, attorney’s fees,
    arbitration costs, and mortgage and construction loan interest.
    The Ponses then filed an application in chancery court for confirmation of the arbitrator’s
    award, after which Mr. Harrison filed a motion to vacate or modify the same. Following a July 30,
    2007, hearing, the chancellor confirmed the award and found that it complied with the requirements
    of the Uniform Arbitration Act as adopted in Tennessee. In accordance with Tennessee Rule of Civil
    Procedure 54.02, the chancellor directed the entry of a final judgment on August 10, 2007, reserving
    the issue of additional attorney’s fees for a later date. Mr. Harrison filed a notice of appeal on
    August 22, 2007.
    Issue Presented and Standard of Review
    On appeal, Mr. Harrison presents the following issue for review:
    [whether t]he Chancellor should have vacated the arbitrator’s award because the
    arbitrator exceeded his powers in making the award.
    The Tennessee Uniform Arbitration Act governs – and limits severely – the scope of judicial
    review of arbitration awards. D & E Constr. Co. v. Robert J. Denley Co., Inc., 
    38 S.W.3d 513
    , 518
    (Tenn. 2001); Arnold v. Morgan Keegan & Co., 
    914 S.W.2d 445
    , 447–48 (Tenn. 1996). In
    reviewing such decisions, our Court must apply a deferential standard of review. Arnold, 914
    S.W.2d at 450. The Tennessee Supreme Court has clarified this standard and stated that intermediate
    appellate courts should “review findings of fact under a ‘clearly erroneous’ standard, [accepting]
    those facts as found unless clearly erroneous.” D & E Constr. Co., 38 S.W.3d at 518. Further, on
    issues presenting a question of law, we review them “with the utmost caution, and in a manner
    designed to minimize interference with an efficient and economical system of alternative dispute
    resolution.” Id.
    Although Mr. Harrison asserted in his answer that he had not abandoned the job site, but
    rather had left at the instruction of the Ponses, he does not challenge the arbitrator’s finding that he
    1
    The arbitrator modified his award to specify that Mr. Harrison’s defenses were not well taken. He had
    mistakenly omitted the word “not” in his original award.
    -2-
    was in material breach of the contract between the parties. He relies solely on the question of
    whether the arbitrator exceeded his authority – and, thus, whether the chancellor erred in confirming
    the award. Accordingly, we shall narrow our focus upon this single question and now turn to it.
    Analysis
    Mr. Harrison contends that a one-year time limitation provision in the contract barred the
    Ponses’ law suit. He asserts that the arbitrator exceeded his authority when he refused to enforce this
    provision and to dismiss the matter. He further argues that the chancellor erred in refusing to vacate
    the award. We disagree.
    The Tennessee Code directs trial courts to vacate an arbitration award if, among other
    reasons, the arbitrator has exceeded his or her power in rendering it. Tenn. Code Ann. § 29-5-
    313(a)(3) (2000); D & E Constr. Co., 38 S.W.3d at 518. The terms of the agreement between the
    parties determine the scope of the arbitrator’s authority. Williams Holding Co. v. Willis, 
    166 S.W.3d 707
    , 711 (Tenn. 2005); D & E Constr. Co., 38 S.W.3d at 518; Arnold, 914 S.W.2d at 450 (stating
    that arbitrators exceed their authority “when they go beyond the scope of authority granted by the
    arbitration agreement”). The subject contract provided that “[t]he arbitrators’ authority is limited
    to the interpretation and application of this Agreement, and the arbitrator may not alter, modify or
    refuse to enforce any provision of this Agreement, even if the arbitrator believes such provision to
    be unfair or unconscionable.” Although the contract charged the arbitrator with the task of
    interpreting its provisions, it expressly prohibited the alteration, modification, or selective
    enforcement of applicable provisions.
    Paragraph 14 of the contract, which addressed the builder’s limited warranty and provided
    for the repair of covered defects, contained the provision in question. Subparagraph (F) provided
    as follows:
    Repairs. Upon receipt of Owner’s written report of a defect, if the defective
    item is covered by Builder’s Limited Warranty, Builder shall repair or replace it at
    no charge to Owner, within thirty (30) days, (extended for delays caused by weather
    conditions, labor problems or material shortages).
    Notwithstanding the foregoing, Builder and Owner expressly waive the
    statutory limitations on actions for defective improvements of real estate, as provided
    by Tennessee Code Section 28-3-201 et seq., and in lieu thereof covenant and agree
    that all actions recoverable under this statutory provision shall be brought within one
    (1) year after substantial completion of the House.
    The code section waived by the parties establishes a four year statute of repose for “[a]ll actions to
    recover damages for any deficiency in the design, planning, supervision, observation of construction,
    or construction of an improvement to real property.” Tenn. Code Ann. § 28-3-202 (2000). Mr.
    -3-
    Harrison argues that the arbitrator was required to enforce the waiver and one-year limitations
    provision. We are not convinced, however, that the limitation period applies to the Ponses’ lawsuit.
    To determine whether this lawsuit falls within the ambit of the referenced statute of repose,
    thus making it subject to the one-year limitation, we look to the gravamen of the complaint and to
    the basis for which the damages are sought. See Vance v. Schulder, 
    547 S.W.2d 927
    , 931 (Tenn.
    1977); Tip’s Package Store, Inc. v. Commercial Ins. Managers, Inc., 
    86 S.W.3d 543
    , 551 (Tenn. Ct.
    App. 2001); Keller v. Colgems-EMI Music, Inc., 
    924 S.W.2d 357
    , 359 (Tenn. Ct. App. 1996).
    Although there are some references made to inferior workmanship2 in the complaint, the suit plainly
    rests upon nonfeasance more so than malfeasance, or partial performance rather than defective
    performance. The Ponses averred, and it is undisputed, that the following items were left
    uncompleted by Mr. Harrison: plumbing items, electrical items, heating and air conditioning,
    flooring (including carpet, hardwood, and tile), painting, septic system connection, concrete work,
    interior and exterior trim work, window screens, gutters, landscaping, shutters, and installation of
    the dryer vent, the range and hood, the door to the crawl space, vanity mirrors, and kitchen and
    laundry appliances. Moreover, it appears that the arbitrator awarded them the cost to complete the
    residence. The Ponses averred that they were required to pay another contractor approximately
    $100,000 to complete the house, even after having paid Mr. Harrison (almost) the entire contract
    price. The compensatory damages for the home’s physical shortcomings amounted to $99,598.65,
    less than half of the arbitrator’s $214,866 award. The balance of that amount consisted of additional
    interest on the construction loan, additional mortgage interest, attorney’s fees, and costs of
    arbitration.
    In this breach of contract case, the chief complaint was nonfeasance, not malfeasance. This
    distinction removes the action from the purview of Tennessee Code Annotated Section 28-3-202
    because the statute applies to actions predicated upon defective improvements to real property,
    property damage, and personal injury or wrongful death attributable to the defective work. Because
    the statute does not apply, neither do the contractual waiver and one-year limitation period. We
    accordingly affirm the chancellor’s confirmation of the award. Costs of this appeal are taxed to the
    Appellant, Barry Harrison d/b/a B. Harrison Housewrights, and his surety, for which execution shall
    issue if necessary.
    ___________________________________
    DAVID R. FARMER, JUDGE
    2
    The complaint includes allegations of inferior painting, unauthorized modifications and substitutions, and
    improper fram ing of the house. The Ponses also asserted that these defects lowered the home’s market value;
    nonetheless, they sought and received their out of pocket expenses to complete the construction.
    -4-