E & J Construction Company v. Liberty Building Systems, Inc. ( 2010 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    July 6, 2010 Session
    E & J CONSTRUCTION COMPANY v.
    LIBERTY BUILDING SYSTEMS, INC.
    Appeal from the Circuit Court for Campbell County
    No. 12757    John D. McAfee, Judge
    No. E2009-01403-COA-R3-CV - FILED AUGUST 27, 2010
    E & J Construction Company (“Plaintiff”) purchased a metal building from Liberty Building
    Systems, Inc. (“Defendant”). The metal building was purchased by Plaintiff for one of its
    customers, Camel Manufacturing Company (“Camel”). Plaintiff constructed the metal
    building for Camel and connected it to an existing building. Almost from the outset, there
    was a problem with leaking. Plaintiff sued Defendant raising various claims including,
    among others, breach of contract. After the Trial Court granted Defendant’s motion for
    partial summary judgment, the case proceeded to trial on the few remaining claims. At the
    conclusion of Plaintiff’s proof, the Trial Court granted Defendant’s motion for directed
    verdict. Plaintiff appeals. We reverse the grant of a directed verdict on Plaintiff’s breach of
    contract claim and remand for further proceedings. The judgment of the Trial Court
    otherwise is affirmed.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit
    Court Affirmed in Part and Reversed in Part; Case Remanded
    D. M ICHAEL S WINEY, J., delivered the opinion of the court, in which H ERSCHEL P. F RANKS,
    P.J., and J OHN W. M CC LARTY, J., joined.
    Thomas M. Leveille, Knoxville, Tennessee, for the Appellant, E & J Construction Company.
    James G. O’Kane, Knoxville, Tennessee, for the Appellee, Liberty Building Systems, Inc.
    OPINION
    Background
    In May of 2005, Plaintiff filed a complaint asserting several causes of action
    against Defendant arising from the purchase of an allegedly defective metal building.
    According to the complaint:
    In late 2003, [Plaintiff] issued a purchase order to
    [Defendant] for a metal building which was designed and
    engineered by [Defendant]. The purchase price for this building
    was $102,811.90. [Plaintiff] subsequently erected this building
    for its customer, [Camel Manufacturing Company (“Camel”)]
    at Camel’s facility in Campbell County, Tennessee.
    At the time that this building began to be erected by
    [Plaintiff], [Plaintiff’s] personnel observed that the gutter for
    this large building appeared to be too small. [Plaintiff] had
    purchased other metal buildings from [Defendant] and
    recognized that this guttering appeared to be under-sized. Prior
    to the building being erected, [Plaintiff] notified [Defendant’s
    personnel] and [Plaintiff] was assured that the guttering was
    correctly sized.
    The building was erected according to [Defendant’s]
    specifications and in accordance with [Defendant’s] drawings.
    [Defendant’s personnel] inspected the building and certified that
    the building was erected correctly.
    Shortly after the building was erected, leaks began to
    occur as a result of the guttering being undersized. [Plaintiff]
    had been concerned from the outset about this guttering and its
    fears came true. [Defendant] was contacted and [Plaintiff] was
    instructed to do various things to try to attempt to resolve the
    guttering problem. [Plaintiff] utilized its personnel and
    materials in attempting to repair the gutter, when [Defendant],
    in fact, knew that the gutter was mis-sized and that the
    replacement of the gutter was the only solution to this problem.
    -2-
    [Plaintiff] expended approximately $4,200.00 in labor
    and materials in trying to follow [Defendant’s] instructions with
    regard to these attempted repairs.
    [Plaintiff] had enjoyed an excellent relationship with
    Camel . . . , a business that is growing quickly in Campbell
    County. In fact, [Plaintiff] had been involved in some
    construction of 8 buildings at Camel’s facility at the time that
    this particular building was erected. Unfortunately, the leaking
    problems impacted [Plaintiff’s] relationship with Camel, making
    it impossible for [Plaintiff] to bid on other Camel projects until
    this problem was solved.
    Plaintiff went on to allege that Camel threatened to sue Plaintiff if the leaks
    were not repaired. According to Plaintiff, in order to avoid litigation with its client, Plaintiff
    designed a new guttering system and incurred expenses in the amount of $17,852.38 in the
    fabrication and installation of the new gutter. Plaintiff further claimed that its business
    relationship with Camel has been ruined. Plaintiff sued Defendant for: (1) breach of
    contract; (2) violation of the Tennessee Consumer Protection Act, 
    Tenn. Code Ann. § 47-18
    -
    101 et seq.; (3) interference with business relationships; and (4) intentional and/or negligent
    misrepresentation.
    Defendant answered the complaint and generally denied any liability to
    Plaintiff. Defendant admitted that Plaintiff purchased the metal building in question from
    Defendant, but denied that the guttering was too small or otherwise improperly sized.
    Defendant averred that Plaintiff negligently constructed the building and that the Tennessee
    Consumer Protection Act claim was barred by the one year statute of limitations.
    In August of 2007, Defendant filed a motion for summary judgment and/or
    motion for partial summary judgment. Defendant claimed it was entitled to summary
    judgment on Plaintiff’s claims because the undisputed material facts established that the
    gutter was of a proper size. Alternatively, Defendant argued that Plaintiff’s Consumer
    Protection Act claim was barred by the one year statute of limitations. Attached to
    Defendant’s motion was the affidavit of David Ryan Hill (“Hill”). Hill is employed by
    Defendant as an engineering manager. Hill earned a bachelor of science degree in
    engineering in 1996 and has been a licensed engineer since 2002. Hill has continuously
    worked in the metal building business. According to Hill:
    At the request of [Defendant’s attorney], I have reviewed
    the drawings of the metal buildings which [Defendant] provided
    -3-
    to [Plaintiff], and I have also reviewed a drawing with
    dimensions, which illustrates the relationship of the existing
    buildings to the new metal buildings that were constructed on
    the Camel Manufacturing Company premises. I have also
    reviewed the purchase order documents for this project. Finally,
    I have been asked to assume that the valley gutter that was
    placed between the existing building and the newly
    manufactured Liberty buildings had six equally spaced down
    spouts as described by [Plaintiff] in its purchase order and the
    testimony of [Jack Heatherly, a licensed contractor and
    Plaintiff’s director of field operations]. . . .
    Based on the information I reviewed and my knowledge
    and expertise as a structural engineer, experienced in the design
    and manufacture of metal buildings, I have been asked to
    determine whether or not in my opinion the valley gutter that
    was provided to [Plaintiff] by [Defendant] was correctly sized
    or whether it was too small as alleged by [Plaintiff]. I have
    completed an analysis, and it is my opinion within a reasonable
    degree of engineering certainty that the valley gutter
    manufactured by [Defendant] and provided to [Plaintiff] was
    properly sized, and was at least one inch deeper than necessary.
    In addition thereto, it is my opinion within a reasonable degree
    of engineering certainty that any roof leaks that occurred near
    the valley gutter which is at issue in this case were not caused by
    an undersized or missized valley gutter. In my opinion, as set
    forth above, this valley gutter was of proper size for the
    application, and [Plaintiff’s] allegation that it was too small is
    incorrect. (original paragraph numbering omitted)
    Plaintiff responded by filing the affidavit of Jack Heatherly (“Heatherly”),
    whose wife is the owner of Plaintiff. Although Heatherly is not an engineer, he is a field
    supervisor for Plaintiff. Heatherly stated that Plaintiff ordered a series of three metal
    buildings that were to be connected to Camel’s existing building. When the components
    were uncrated, Heatherly was concerned that the guttering was too small and contacted Ben
    Barcroft, a district manager for Defendant. Barcroft supposedly contacted one of
    Defendant’s engineers and was told that the guttering was the proper size. Barcroft relayed
    this information to Heatherly. Relying on that representation, Heatherly proceeded to install
    the gutter and complete the metal buildings. Heatherly then stated:
    -4-
    Had I known at that time that the gutter was incorrectly
    sized, I would not have continued building the building.
    [Defendant] sold [Plaintiff] a pre-engineered building which
    was represented to be correctly designed and to comply with all
    standards applicable in the State of Tennessee and I relied on
    that representation.
    After the building was completed during the summer of
    2004, there were problems with leaks in the building. I went
    back and checked the screws and the gutter. After the problem
    continued, I contacted Ben Barcroft and a series of
    recommendations were made by [Defendant] for me to do
    various things to the building which I did. None of those things
    worked. It was not until the summer of 2004 when the building
    was completed that I knew about the valley gutter overflowing.
    It was not until August 2 and 3, 2004, that Daniel Moore
    visited the building in question at Camel. . . . I was working on
    another job at the time and my son Jack Heatherly, Jr., was
    present at Camel and went up on the building with Daniel
    Moore. Daniel Moore stated at that time that the gutter was too
    small and that was reported to me by Jack Heatherly, Jr. That
    was the first time that anyone from [Defendant] admitted that
    the gutter was too small.
    After that date, I continued to be called to Camel
    Manufacturing Company whenever it rained because the
    building leaked at the location of the valley gutter. I continued
    to try to deal with this problem and my wife and I continued to
    keep [Defendant] advised that the problem was not solved.
    It was not until November, 2004, that Daniel Moore came
    back to the site. At that time, he guaranteed that the work he
    performed would stop the leaking. His work did not stop the
    leaking and I continued to get complaints from Camel and
    continued to contact [Defendant] regarding these problems.
    *   *     *
    -5-
    I have stood on the roof of this building in question at
    Camel during a rainstorm in 2004. I observed the gutter
    overflowing. I checked the downspouts and none were blocked.
    When I went inside the building, I observed leaks from the
    valley gutter. The size of the gutter caused the gutter to
    overflow and, in turn, caused leaks in the building. (original
    paragraph numbering omitted)
    Heatherly went on to explain that prior to this situation involving the leaking
    metal building, Camel was a very good customer of Plaintiff. After the incident involving
    the leaking metal building, Plaintiff no longer was asked to perform any work for Camel.
    Plaintiff also filed the affidavit of Louis Cortina (“Cortina”) an engineer who
    has been licensed since 1987. According to Cortina:
    I have reviewed the calculations by Ryan Hill and in my
    professional opinion, the gutter originally provided by
    [Defendant] is too small. A gutter with the dimensions
    suggested by Ryan Hill would likely overfill and cause leaks in
    the building.
    The design by [Defendant] and the dimensions of the
    gutter suggested by Mr. Hill leave very little or no additional
    capacity for blocked downspouts, heavy downpours, or debris
    in the gutter. Based on my past experience with regard to the
    design of gutters and roof[s], additional capacity is necessary
    and as a result, I would not agree with Mr. Hill’s
    recommendation.
    A gutter in the dimension of 10O deep by 12O wide would
    be my recommendation and it is my opinion that a gutter 11½O
    wide by 6O deep is inadequate. . . . (original paragraph
    numbering omitted)
    The contract between Plaintiff and Defendant contained the following
    provision:
    Warranty: Liberty Building Systems, Inc., warrants all materials
    included in our building systems package for a period of one
    year from date of shipment. All materials must be properly
    -6-
    installed and erected in a timely fashion upon receipt of
    shipment. Prolonged storage or exposure to the elements or
    hazardous environments will void this warranty. Any damaged
    materials discovered while unloading the shipment must be
    reported and signed off by the delivery driver for validation. All
    shortages and concealed damage must be reported within 10
    working days of receipt of shipment.
    A hearing was conducted on Defendant’s motion for summary
    judgment/motion for partial summary judgment. Following the hearing, the Trial Court
    entered an order stating as follows:
    This cause came on to be heard . . . on defendant’s Motion for
    Summary Judgment and Motion for Partial Summary Judgment.
    The parties were represented by counsel and presented their
    argument to the court. The court having considered defendant’s
    Motion for Partial Summary Judgment, plaintiff’s response
    thereto, the supporting evidence of record, and having heard the
    argument and representations of counsel, the court made its
    ruling from the bench with respect to defendant’s Motion for
    Partial Summary Judgment.1 The court found that defendant’s
    Motion for Partial Summary Judgment seeking dismissal of
    plaintiff’s claims pursuant to the Tennessee Consumer
    Protection Act that defendant engaged in unfair or deceptive
    acts or practices pursuant to 
    Tenn. Code Ann. § 47-18-104
    should be granted. Having found that plaintiff’s Tennessee
    Consumer Protection Act claims of unfair or deceptive acts or
    practices should be dismissed, the court ruled that defendant’s
    motion to dismiss the Tennessee Consumer Protection Act
    claims pursuant to the one-year statute of limitations is moot.
    The court further found that defendant’s Motion for Partial
    Summary Judgment seeking dismissal of plaintiff’s claim for
    tortious interference with a business relationship should be
    granted. The court further found that defendant’s Motion for
    Partial Summary Judgment seeking dismissal of plaintiff’s claim
    for lost profits should be granted. Finally, the court denied at
    1
    For obvious reasons, we should have been provided a transcript from this hearing, but the record
    contains no such transcript. Thus, we cannot ascertain what “representations” were made to the Trial Court
    and by whom.
    -7-
    this time defendant’s Motion for Partial Summary Judgment
    seeking dismissal of plaintiff’s intentional/negligent
    misrepresentation claims, and further withheld ruling on
    plaintiff’s Motion for Summary Judgment seeking dismissal of
    plaintiff’s suit, pending submission by defendant of a
    supplement to the Motion for Summary Judgment on or before
    Monday, March 10, 2008, or defendant’s announcement of a
    withdrawal of the Motion for Summary Judgment. . . . (footnote
    added)
    Following entry of the order partially granting Defendant’s motion for
    summary judgment, Defendant withdrew its motion on the remaining claims and this case
    proceeded to trial. For the most part and except as discussed below, the testimony of
    Plaintiff’s witnesses at trial was consistent with that set forth in their respective affidavits.
    At the close of Plaintiff’s proof, Defendant moved for and the Trial Court
    granted a motion for a directed verdict. According to the Trial Court:
    After the plaintiff rested, the jury was excused and defendant
    moved for a directed verdict in its favor. After hearing
    arguments of counsel and considering the evidence and record
    as a whole, the court found that defendant’s Motion for a
    Directed Verdict in its favor with respect to plaintiff’s claim of
    negligent or intentional misrepresentation and punitive damages
    is well-taken, because the plaintiff presented no competent proof
    of a negligent or intentional misrepresentation that would entitle
    the plaintiff to recover compensatory or punitive damages; and
    the court further found that defendant’s Motion for a Directed
    Verdict with respect to the remaining issue of a breach of
    contract and breach of the implied warranty of fitness for a
    particular purpose was well-taken, because there was no
    competent expert testimony presented that the gutter at issue
    was not fit for a particular purpose or that defendant breached its
    contract with the plaintiff. . . .
    After entry of the directed verdict for Defendant, Plaintiff filed a motion for
    a new trial. In this motion, Plaintiff claimed that not only was it pursuing a claim for breach
    of an implied warranty of fitness for a particular purpose, it also was seeking relief for breach
    of an implied warranty of merchantability. In addition, Plaintiff asserted that there was
    sufficient proof to withstand a motion for directed verdict as to whether Defendant breached
    -8-
    the contract and implied warranties, as well as whether Defendant had committed negligent
    and/or intentional misrepresentations. The Trial Court denied the motion, and Plaintiff
    appeals challenging both the granting of Defendant’s motion for partial summary judgment
    as well as the granting of Defendant’s motion for directed verdict following the close of
    Plaintiff’s proof at trial.
    Discussion
    We first discuss whether the Trial Court properly granted Defendant’s motion
    for partial summary judgment. Our Supreme Court reiterated the standard of review in
    summary judgment cases as follows:
    The scope of review of a grant of summary judgment is
    well established. Because our inquiry involves a question of
    law, no presumption of correctness attaches to the judgment, and
    our task is to review the record to determine whether the
    requirements of Rule 56 of the Tennessee Rules of Civil
    Procedure have been satisfied. Hunter v. Brown, 
    955 S.W.2d 49
    ,
    50-51 (Tenn. 1997); Cowden v. Sovran Bank/Cent. S., 
    816 S.W.2d 741
    , 744 (Tenn. 1991).
    A summary judgment may be granted only when there is
    no genuine issue of material fact and the moving party is entitled
    to judgment as a matter of law. Tenn. R. Civ. P. 56.04; Byrd v.
    Hall, 
    847 S.W.2d 208
    , 214 (Tenn. 1993). The party seeking the
    summary judgment has the ultimate burden of persuasion “that
    there are no disputed, material facts creating a genuine issue for
    trial . . . and that he is entitled to judgment as a matter of law.”
    
    Id. at 215
    . If that motion is properly supported, the burden to
    establish a genuine issue of material fact shifts to the
    non-moving party. In order to shift the burden, the movant must
    either affirmatively negate an essential element of the
    nonmovant’s claim or demonstrate that the nonmoving party
    cannot establish an essential element of his case. 
    Id.
     at 215 n.5;
    Hannan v. Alltel Publ’g Co., 
    270 S.W.3d 1
    , 8-9 (Tenn. 2008).
    “[C]onclusory assertion[s]” are not sufficient to shift the burden
    to the non-moving party. Byrd, 
    847 S.W.2d at 215
    ; see also
    Blanchard v. Kellum, 
    975 S.W.2d 522
    , 525 (Tenn. 1998). Our
    state does not apply the federal standard for summary judgment.
    The standard established in McCarley v. West Quality Food
    -9-
    Service, 
    960 S.W.2d 585
    , 588 (Tenn. 1998), sets out, in the
    words of one authority, “a reasonable, predictable summary
    judgment jurisprudence for our state.” Judy M. Cornett, The
    Legacy of Byrd v. Hall: Gossiping About Summary Judgment
    in Tennessee, 
    69 Tenn. L. Rev. 175
    , 220 (2001).
    Courts must view the evidence and all reasonable
    inferences therefrom in the light most favorable to the
    non-moving party. Robinson v. Omer, 
    952 S.W.2d 423
    , 426
    (Tenn. 1997). A grant of summary judgment is appropriate only
    when the facts and the reasonable inferences from those facts
    would permit a reasonable person to reach only one conclusion.
    Staples v. CBL & Assocs., Inc., 
    15 S.W.3d 83
    , 89 (Tenn. 2000).
    In making that assessment, this Court must discard all
    countervailing evidence. Byrd, 
    847 S.W.2d at 210-11
    .
    Recently, this Court confirmed these principles in Hannan.
    Giggers v. Memphis Housing Authority, 
    277 S.W.3d 359
    , 363-64 (Tenn. 2009).
    We begin by addressing the grant of Defendant’s motion for summary
    judgment with regard to Plaintiff’s Tennessee Consumer Protection Act (“TCPA”) claim.
    Plaintiff cites very little evidence and no law whatsoever in the argument section of its brief
    addressing the grant of Defendant’s motion for partial summary judgment. Plaintiff’s entire
    argument as to the dismissal of the TCPA claim comprises one paragraph in the argument
    section of its brief. Plaintiff cites Heatherly’s affidavit twice and improperly attempts to rely
    on trial testimony pertaining to Plaintiff’s misrepresentation claim.2 According to Plaintiff,
    Jack Heatherly’s statements in his affidavit: (1) that he was advised by Defendant that the
    guttering was the correct size; and (2) that Heatherly would not have continued building the
    building had he known the gutter was not the correct size, are sufficient to create a fact issue
    on the TCPA claim. As noted, Plaintiff cites absolutely no law supporting his claim that
    these two facts, standing alone, are sufficient to create a genuine issue of material fact as to
    its TCPA claim. Plaintiff does not even discuss what is required to properly set forth a
    TCPA claim. Plaintiff even fails to cite to the TCPA.
    2
    Plaintiff cites trial testimony when discussing the misrepresentation claim. Testimony at trial is
    irrelevant when ascertaining whether the pre-trial motion for partial summary judgment should have been
    granted.
    -10-
    The entire discussion in Plaintiff’s argument section of its brief addressing the
    grant of summary judgment on its claim for interference with business relationship is as
    follows:
    There was also a fact issue with regard to the claim for
    interference with the business relationship with Camel
    Manufacturing. The Affidavit and deposition testimony showed
    that Liberty contacted representatives of Camel Manufacturing
    directly and placed blame on the Plaintiff for the problems with
    the gutter system. Affidavit of Jack Heatherly ¶ 21.
    Again, Plaintiff cites no law setting forth the elements necessary to state a
    claim for intentional interference with a business relationship or any law supporting its
    argument that the two alleged facts set forth in Heatherly’s affidavit, standing alone, are
    sufficient to withstand a properly supported motion for summary judgment on such a claim.
    The same can be said for Plaintiff’s argument as to the grant of summary judgment for lost
    business profits.
    In Bean v. Bean, 
    40 S.W.3d 52
     (Tenn. Ct. App. 2000) we observed:
    Courts have routinely held that the failure to make appropriate
    references to the record and to cite relevant authority in the
    argument section of the brief as required by Rule 27(a)(7)
    constitutes a waiver of the issue. See State v. Schaller, 
    975 S.W.2d 313
    , 318 (Tenn. Crim. App. 1997); Rampy v. ICI
    Acrylics, Inc., 
    898 S.W.2d 196
    , 210 (Tenn. Ct. App. 1994); State
    v. Dickerson, 
    885 S.W.2d 90
    , 93 (Tenn. Crim. App. 1993). . . .
    As noted in England v. Burns Stone Company, Inc., 
    874 S.W.2d 32
    , 35 (Tenn. Ct. App. 1993), parties cannot expect this court to
    do its work for them.
    Bean, 
    40 S.W.3d at 55-56
    .
    Because Plaintiff has failed to cite any authority whatsoever with respect to its
    argument that the Trial Court improperly granted Defendant’s motion for partial summary
    judgment as to the various claims at issue in that motion, we find that Plaintiff has waived
    these issues on appeal. Accordingly, we affirm the Trial Court’s grant of partial summary
    judgment to Defendant.
    -11-
    The next issues surround the Trial Court’s granting of a directed verdict to
    Defendant. With respect to the Trial Court’s granting of Defendant’s motion for directed
    verdict, our standard of review is different from that related to a summary judgment. In
    Johnson v. Tennessee Farmers Mut. Ins. Co., 
    205 S.W.3d 365
     (Tenn. 2006), our Supreme
    Court set forth the standard of review with regard to directed verdicts, stating:
    In reviewing the trial court’s decision to deny a motion
    for a directed verdict, an appellate court must take the strongest
    legitimate view of the evidence in favor of the non-moving
    party, construing all evidence in that party’s favor and
    disregarding all countervailing evidence. Gaston v. Tenn.
    Farmers Mut. Ins. Co., 
    120 S.W.3d 815
    , 819 (Tenn. 2003). A
    motion for a directed verdict should not be granted unless
    reasonable minds could reach only one conclusion from the
    evidence. 
    Id.
     The standard of review applicable to a motion for
    a directed verdict does not permit an appellate court to weigh the
    evidence. Cecil v. Hardin, 
    575 S.W.2d 268
    , 270 (Tenn. 1978).
    Moreover, in reviewing the trial court’s denial of a motion for
    a directed verdict, an appellate court must not evaluate the
    credibility of witnesses. Benson v. Tenn. Valley Elec. Coop.,
    
    868 S.W.2d 630
    , 638-39 (Tenn. Ct. App. 1993). Accordingly,
    if material evidence is in dispute or doubt exists as to the
    conclusions to be drawn from that evidence, the motion must be
    denied. Hurley v. Tenn. Farmers Mut. Ins. Co., 
    922 S.W.2d 887
    , 891 (Tenn. Ct. App. 1995).
    Johnson, 
    205 S.W.3d at 370
    .
    Plaintiff claims Defendant violated both the implied warranty of fitness for a
    particular purpose and the implied warranty of merchantability. Neither of these warranty
    claims was specifically asserted in the complaint, and we were unable to find in the record
    an amended complaint setting forth these claims. Plaintiff does not direct us to anywhere in
    the record where breach of either implied warranty actually was pled. As to the implied
    warranty of merchantability, the Trial Court obviously did not believe that Plaintiff was
    pursuing this un-pled claim. The pleadings support this conclusion. We hold that a claim
    for breach of the implied warranty of merchantability never was properly raised.
    As to the implied warranty of fitness for a particular purpose, at trial Plaintiff’s
    expert, Louis Cortina, expressly testified that the gutter at issue was fit for its particular
    purpose. While Cortina testified that the gutter would have been more effective had it been
    -12-
    deeper, he, nevertheless, acknowledged to the Trial Court that the gutter was built according
    to industry guidelines and was fit for its particular purpose. Specifically, Cortina stated:
    THE COURT: Do you agree or disagree, was that gutter fit for
    the particular purpose and that purpose would be to handle the
    water volume coming off that roof line for a 50-year rain. . . .
    THE WITNESS: Based on the volume, it meets the minimum
    guidelines.
    THE COURT: Which would be fit for the particular purpose in
    which it was designed.
    THE WITNESS: For handling quantity of water, yes.
    On appeal, Plaintiff argues that we should simply ignore the testimony of its
    own expert. This, we cannot do. We affirm the Trial Court’s judgment granting a directed
    verdict to Defendant on Plaintiff’s claim that Defendant violated the implied warranty of
    fitness for a particular purpose.3
    Next we address the Trial Court’s grant of a directed verdict for Defendant on
    Plaintiff’s claims for negligent and intentional misrepresentation. In Robinson v. Omer, 
    952 S.W.2d 423
     (Tenn. 1997), the Supreme Court discussed the essential elements of a negligent
    misrepresentation claim as follows:
    Tennessee has adopted Section 552 of the Restatement (Second)
    of Torts “as the guiding principle in negligent misrepresentation
    actions against other professionals and business persons.”
    Section 552 provides, in pertinent part, as follows:
    (1) One who, in the course of his business, profession or
    employment, or in any other transaction in which he has
    a pecuniary interest, supplies false information for the
    guidance of others in their business transactions, is
    subject to liability for pecuniary loss caused to them by
    their justifiable reliance upon the information, if he fails
    3
    Due to our resolution of this issue, we pretermit Defendant’s argument that Plaintiff never pled a
    violation of the implied warranty of fitness for a particular purpose.
    -13-
    to exercise reasonable care or competence in obtaining or
    communicating the information. . . .
    
    Id. at 427
    .
    The only alleged “misrepresentation” of Defendant at issue on appeal occurred
    when Plaintiff was told that the gutter was the correct size after concerns were initially raised
    by Mr. Heatherly. However, there was no proof offered by Plaintiff that Defendant or one
    of its representatives failed to exercise reasonable care when informing Plaintiff that the
    gutter was the correct size. Even Plaintiff’s expert agreed that the gutter met minimum
    industry standards and was fit for its particular purpose. Accordingly, the Trial Court
    correctly granted Defendant’s motion for directed verdict as to the negligent and intentional
    misrepresentation claims.
    The final issue is whether the Trial Court correctly granted Defendant’s motion
    for a directed verdict as to the breach of contract claim. As set forth previously, the contract
    between the parties contained the following express warranty:
    Warranty: Liberty Building Systems, Inc., warrants all materials
    included in our building systems package for a period of one
    year from date of shipment. All materials must be properly
    installed and erected in a timely fashion upon receipt of
    shipment. Prolonged storage or exposure to the elements or
    hazardous environments will void this warranty. Any damaged
    materials discovered while unloading the shipment must be
    reported and signed off by the delivery driver for validation. All
    shortages and concealed damage must be reported within 10
    working days of receipt of shipment.
    At trial, Heatherly testified that he installed the metal building according to
    Defendant’s specifications and that it, nevertheless, repeatedly leaked. The leaks began well
    before one year had elapsed from the date of shipment. Heatherly’s attempted repairs were
    unable to stop the leak, and eventually a new and deeper gutter was installed.
    As noted previously, when reviewing the grant of a motion for directed verdict,
    we “must take the strongest legitimate view of the evidence in favor of the non-moving party,
    construing all evidence in that party’s favor and disregarding all countervailing evidence.”
    Johnson, 
    205 S.W.3d at 370
    . When viewing the evidence in this light, we believe Plaintiff
    did present sufficient evidence to withstand Defendant’s motion for a directed verdict on
    Plaintiff’s breach of contract claim asserting that Defendant violated the express warranty
    -14-
    contained in the contract. Viewing the evidence in the light most favorable to Plaintiff,
    Plaintiff purchased the building from Defendant; Defendant instructed Plaintiff how to install
    the building; Plaintiff installed the building as directed by Defendant; and the building leaked
    despite being installed as directed by Defendant. In short, construing this evidence in
    Plaintiff’s favor, the building bought from Defendant leaked despite the fact that it was
    installed as directed by Defendant. We believe this evidence to be sufficient such that doubt
    exists as to the conclusions to be drawn from this evidence. We reverse the judgment of the
    Trial Court on this sole issue. Any remaining issues are pretermitted.
    Conclusion
    The judgment of the Trial Court granting Defendant’s motion for a directed
    verdict on Plaintiff’s breach of contract claim is reversed. In all other respects, the judgment
    of the Trial Court is affirmed. This case is remanded to the Campbell County Circuit Court
    for further proceedings consistent with this Opinion and for collection of the costs below.
    Costs on appeal are taxed one-half to the Appellant, E & J Construction Company, and its
    surety, and one-half to the Appellee, Liberty Building Systems, Inc., for which execution may
    issue, if necessary.
    ________________________________
    D. MICHAEL SWINEY, JUDGE
    -15-