Greg Calfee Builders LLC v. Neill Magee and Diane Magee ( 2020 )


Menu:
  •                                                                                        06/29/2020
    IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    June 9, 2020 Session
    GREG CALFEE BUILDERS LLC v. NEILL MAGEE AND DIANE MAGEE
    Appeal from the Chancery Court for Bradley County
    No. 2016-CV-068    Jerri S. Bryant, Chancellor
    No. E2019-00905-COA-R3-CV
    This appeal concerns an alleged breach of contract. Greg Calfee (“Mr. Calfee”), on
    behalf of Greg Calfee Builders LLC (“GCB”), and Neill MaGee (“Mr. MaGee”) signed
    an agreement (“the Contract”) whereby GCB would custom-build a home for Mr. MaGee
    and his wife, Diane MaGee (“the MaGees,” collectively). Mr. MaGee, citing a number
    of construction defects, later terminated GCB from the job and told Mr. Calfee that GCB
    could not come back despite GCB’s willingness and offer to correct the defects. GCB
    sued the MaGees in the Chancery Court for Bradley County (“the Trial Court”) seeking
    to recover money it alleged was still owed to it. Mr. MaGee filed a counterclaim. GCB
    filed a motion for summary judgment, which the Trial Court granted. The MaGees
    appeal. We find and hold, inter alia, that under both Tennessee caselaw and the
    Contract, Mr. MaGee was required to give GCB notice and a reasonable opportunity to
    cure the defects, yet he failed to do so. GCB is entitled to judgment as a matter of law.
    We affirm.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed;
    Case Remanded
    D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which JOHN W.
    MCCLARTY and THOMAS R. FRIERSON, II, JJ., joined.
    W. Lewis Jenkins, Jr., Dyersburg, Tennessee, for the appellants, Neill MaGee and Diane
    MaGee.
    Stuart F. James, Chattanooga, Tennessee, and, Michael E. Jenne, Cleveland, Tennessee,
    for the appellee, Greg Calfee Builders LLC.
    OPINION
    Background
    In 2014, Mr. Calfee of GCB and Mr. MaGee signed the Contract. Under the
    Contract, GCB was to build a home for the MaGees in Bradley County, Tennessee for
    $694,175. The home was to be custom-built with a number of highly particularized
    features such as floors made from reclaimed cypress wood. The Contract provided for an
    initial down payment by the MaGees to be followed by “progress payments” as GCB
    completed work. The Contract also provided for final payment prior to occupancy after
    final walkthrough and corrections. As pertinent to the issues on appeal, the Contract
    provided these additional terms:
    10. Contractor Warranties: . . . . (d) . . . If a defect appears which Owner
    believes is covered by the Contractor’s duty of quality workmanship,
    Owner shall notify Contractor in writing describing such defect, also stating
    the times during the day Owner will be available at the improvements so
    Contractor can schedule service calls appropriately. Upon receipt of
    Owner’s written report of a defect, if the defective item is covered by the
    Contractor’s duty and quality workmanship, Contractor shall repair or
    replace it at no charge to Owner within thirty (3)1 days (unless due to
    delays caused by weather conditions, labor problems or material shortages).
    Notwithstanding the foregoing Contractor and Owner expressly waive the
    statutory limitations on actions for defective improvements of real estate, as
    provided by TCA 28-3-201 et. seq., and in lieu thereof covenant and agree
    that all actions recoverable under the statutory provision shall be brought
    within one (1) year after substantial completion of the improvements.
    ***
    19. Termination by Owner: If the Contractor materially defaults or
    materially neglects to carry out the work in accordance with the contract
    documents, Owner may, after five (5) days written notice to the Contractor
    and without prejudice to any other remedy they may have, make good such
    deficiencies and may deduct the cost thereof from the payment then or
    thereafter due the Contractor, or, at their option, may terminate the contract
    and take possession of the site and of all materials, and may finish the work
    by whatever method they may deem expedient, and if the unpaid balance of
    the contract price exceeds the expense of finishing the work, such excess
    1
    This discrepancy between “thirty” and “(3)” is contained within the Contract.
    -2-
    shall be paid to the Contractor, but if such expense exceeds such unpaid
    balance, the Contractor shall pay the difference to the Owner.
    20. Litigation Fees: The parties agree that in the event either party breaches
    this agreement, the non-defaulting party as additional damages shall be
    entitled to the cost of litigation, including reasonable attorney’s fees to
    enforce this agreement.
    Work began on the home, and time passed. In late July 2015, Mr. MaGee sent Mr.
    Calfee a “punch list” via email of items he felt needed correcting. On July 31, 2015, Mr.
    Calfee met Mr. MaGee at the home and went through the punch list items room by room.
    Mr. Calfee told Mr. MaGee that he would correct these problems. Mr. MaGee agreed
    that Mr. Calfee could return on August 3, 2015 to begin making the corrections.
    However, when Mr. Calfee returned on August 3, 2015, Mr. MaGee told him “I
    don’t want you back into my home. I don’t want your subcontractors back in the home.”
    Mr. Calfee left. Later that day, Mr. Calfee sent Mr. MaGee an email stating that he still
    wanted to make the corrections. Mr. MaGee responded with an email confirming that
    “Neill and Diane do not want Greg Calfee or his subcontractors to work on the punch list
    items in the home.” On August 24, 2015, counsel for Mr. Calfee and GCB sent a letter to
    the MaGees stating that Mr. Calfee stood ready, willing and able to complete the items on
    the punch list at their earliest convenience.
    Meanwhile, Robert Thompson, an attorney and mutual friend of the parties, tried
    to help resolve the dispute. Mr. Thompson wrote a letter to both parties dated August 10,
    2015 containing these key points:
    --the balance owed to GCB was $163,770.22;
    --the MaGees would pay $138,351.71 in exchange for GCB executing a
    Contractor’s affidavit reflecting that all bills had been paid and there were
    no materialmen’s liens;
    --the only issue that remained was the floor repair; and,
    --the MaGees would initially retain $25,418.51 for the floor repairs.
    A follow-up letter from Mr. Thompson dated August 11, 2015 reflected that the
    matter had not been fully settled. Mr. Thompson updated where things stood:
    --the parties were at an impasse regarding the remaining balance of
    $25,418.51;
    -3-
    --per Mr. MaGee’s instruction, Robert Thompson had delivered the
    $138,351.71 check to GCB and was now providing the executed
    Contractor’s Affidavit to the MaGees; and,
    --the outstanding balance of $25,418.51 remained in dispute.
    In the August 11 letter, Mr. Thompson wrote also: “Both of you have reserved all
    of your rights to pursue whatever action you deem appropriate with respect to this
    dispute. I regret that I was unable to assist you in reaching a complete resolution.
    Therefore, neither of you owe me anything for my services.”
    Some three months after Mr. Calfee and GCB were told unequivocally that they
    were not allowed to come back, the MaGees finally relented. In a letter to GCB’s
    counsel dated November 23, 2015, counsel for the MaGees wrote:
    I have had lengthy conversations with Mr. & Mrs. MaGee concerning the
    numerous problems with their home. Based on those conversations they
    are willing to have Mr. Calfee and his subcontractors return and perform
    corrective work to bring the entire house into compliance with the plans,
    specifications and contract documents. . . .
    However, GCB did not return. Instead, in March 2016, GCB sued the MaGees in
    the Trial Court “for enforcement of lien, breach of Contract and/or quantum meruit.” The
    MaGees filed an answer. Mr. MaGee, for his part, filed a counterclaim seeking an
    accounting of funds paid under the Contract. Mr. MaGee later filed an amended
    counterclaim seeking no less than $600,000 in damages for the “defective and negligent
    work performed by Contractor and its subcontractors.”
    In May 2018, GCB filed a motion for summary judgment asserting that Mr.
    MaGee had denied it an opportunity to cure the defects. GCB sought $25,418.51 it
    alleged was still owed to it. As part of their response, the MaGees filed the affidavit of
    custom-building contractor and construction expert Charles Alexander, who detailed the
    alleged deficiencies in GCB’s work. The following is but a portion of Mr. Alexander’s
    lengthy affidavit:
    4. I observed that the finishes in the MaGee home did not meet the
    standards applicable to a custom house of this type. Any experienced
    custom home builder knows that the finishes are a critical part of the
    construction to meet the owner’s expectations. There were extreme
    variations in the quality of the workmanship in the finishes at the MaGee
    home. These variations reflect a lack of supervision by the contractor and
    its subcontractors and/or a lack of knowledge of what was required by the
    -4-
    particular trades. The variations in the quality of finishes showed some
    tradesmen had the skill to do the work correctly, but simply did not apply
    that skill in a consistent manner. There were also finishes that indicated
    particular trades lacked adequate training and skill or failed to take
    sufficient time and apply sufficient effort to do the work correctly.
    ***
    8. I understand from my investigation that the general contractor
    understood the owners were going to use reclaimed cypress wood for the
    flooring throughout the house. I further understand that the supplier of the
    reclaimed cypress wood had telephone conversations with the general
    contractor in which he reviewed the culling and selecting procedures that
    would be necessary. Finally, I understand that as the work progressed, the
    supplier made a trip to the MaGee home to review these procedures for
    culling and selecting boards with the general contractor.
    9. Based on my observations, the resulting floors at the MaGee home
    show that these instructions were not followed by the general contractor.
    Boards were used that had gaps and openings at joints and places in the
    boards that should have been cut out prior to installation, which displays a
    lack of attention to the culling and selection process. This is what results
    when the installer is inexperienced or in a rush to perform without taking
    the time and care demanded by the nature of the materials he is working
    with. It also shows a lack of knowledge, experience and/or supervision by
    the contractor to be sure the proper care and precautions were taken.
    10. Because the cypress wood flooring was installed incorrectly, the
    subcontractor hired to finish the floors had a much more challenging job.
    The incorrect installation made it far more difficult for the finisher. I
    understand that in spite of this, the subcontractor assured the owner that
    with extra work, and extra compensation for that work, the subcontractor
    could produce the floors expected by the owner.
    11. I understand that the owner raised issues with the general
    contractor and the flooring subcontractor about the condition of the floor
    before the finished coat was applied. I understand that the owner was
    assured these conditions would be corrected in a satisfactory manner.
    However, my personal observation showed areas where the floors were
    damaged, apparently by efforts to remove and substitute some of the boards
    and where gaps, joint openings remain. See, Ex.
    12. The result was a floor surface that required remedial action. The
    only way to produce a finished floor that meets the owner’s intention and
    expectation is to move out of the house, remove the interior trim, such as
    -5-
    the baseboards, remove all built-in cabinetry and all appliances, (remove
    the existing floor system and replace it).
    13. I understand that the floor finisher tried to remove paint and
    plaster from the unfinished floors and charged extra for it. I understand the
    floor boards arrived before the plastering work was begun and the
    contractor stored the boards in the dining room thereby subjecting the
    boards to moisture gain and swelling. After the flooring was installed,
    plaster repair and painting was done which allowed plaster and paint to
    penetrate the flooring before it was sealed.
    14. I understand that records have been furnished that show the
    flooring finish subcontractor charged extra in a failed attempt to remove
    plaster and paint that had fallen on the sanded, reclaimed cypress floors.
    This is a wholly improper sequence in the work and not only exposed the
    boards to damage, but would create open gaps as the swollen flooring,
    which had been incorrectly stored at the job site by the contractor, became
    exposed to conditioned air as the building was closed in. This indicates a
    failure to properly schedule the work and resulted in damage to the
    reclaimed cypress. The result is the finisher improperly sealed in the
    paint/plaster splatters in the finished floor.
    ***
    24. The flaws in the floor installation, trim, staircase, ceramic tile,
    paint and plaster are such that they should have been seen and corrected
    before the owner ever did a punch list. Based on my investigation and
    overall evaluation of the project, and my experience as a general contractor
    who constructs custom homes, it is understandable that an owner would
    refuse to let the same contractor and subcontractors attempt to correct the
    defective work when the project is supposed to be substantially complete.
    In September 2018, the Trial Court entered an order denying GCB’s motion for
    summary judgment. The Trial Court stated, in part:
    [T]he Court finds that first, identifying the party who committed the first
    material breach is a question of fact and that there are disputed issues of
    fact in the record, and second, the reasonableness of Mr. MaGee’s conduct
    on August 3, 2015 and thereafter in refusing Plaintiff access to the property
    to make repairs and/or correct defects is also a question of fact and that
    there are disputed issues of fact in the record, the Motion is hereby denied.
    -6-
    GCB filed a motion to alter or amend. In October 2018, the Trial Court entered
    another order, this time granting GCB’s motion for summary judgment. The Trial Court
    stated:
    This cause came to be heard on the 26th day of September 2018 upon
    Plaintiff’s motion to alter or amend and notice of hearing. The Court treats
    this motion to alter or amend its previous denial of the motion for summary
    judgment as a re-argument of the motion for summary judgment based on
    the case law that was released by the Court of Appeals on August 10, 2018,
    after the hearing on the original motion for summary judgment.
    Plaintiff is heavily relying on the case of Manor Homes LLC v.
    Ashby Communities LLC, 
    218 WL 3814981
    (Tenn. Ct. App. Aug. 10,
    2018). Plaintiff argues that the Manor Homes case is on point with this
    case and this Court’s previous ruling that “identifying the party who
    committed the first material breach as a question of fact” is an incorrect
    statement of this Court’s initial duty. According to Manor Homes, this
    Court is to first determine what the contract required of the parties (Manor
    at p. 5).
    In this case, it is clear that in 2014 the Plaintiff agreed to construct a
    residence for Defendant in Bradley County, Tennessee. A Construction
    Contract was entered into between the parties. The construction contract
    contained a notice and opportunity to cure provision which provided in
    relevant part:
    “if a defect appears, which owner believes is covered by
    contractor’s duty of quality workmanship, owner shall notify
    contractor, in writing, describing such defect, also stating the
    times during the day Owner will be available at the
    improvements so contractor can schedule service calls
    appropriately. Upon receipt of Owner’s written report of a
    defect, if the defective item is covered by the contractor’s
    duty and quality of workmanship, contractor shall repair or
    replace it, at no charge to Owner, within three (3) days
    (unless due to delays caused by weather conditions, labor
    problems or material shortages…)”
    The Construction Contract also provided for “final payment prior to
    occupancy after final walk through and corrections”. On July 28, 2015
    Defendant submitted a “punch list” of items he felt needed correction via
    email to Plaintiff. On July 31, 2015 Defendant and Plaintiff met at the
    residence/home and went through the punch list items, room by room. At
    -7-
    the end of that process, Defendant agreed for Plaintiff to come back to the
    residence on August 3, 2015 to make repairs. Plaintiff returned to the
    residence on August 3, 2015 and was told by Defendant “I do not want you
    back into my home. I do not want your sub-contractors back in the home”.
    In response, Plaintiff left the premises and sent the Defendant an email
    stating he wanted to perform the punch list corrections. On August 24,
    2015 attorney for Plaintiff wrote Defendant stating that “Mr. Calfee stands
    ready, willing, and able to complete the items on your punch list at your
    earliest convenience”.
    The contract between Plaintiff and Defendant is clear. Defendant
    had a contractual obligation to allow Plaintiff the opportunity to cure. The
    right to cure alleged defects is clear in the contract. (See Statement of
    Material Facts #6) It is admitted, by the Defendant, that on July 27, 2015
    Defendant submitted a “punch list” of items he felt needed corrections via
    email to the Plaintiff. It is further admitted that on July 31, 2015, Plaintiff
    met with Defendant at the residence/home and went through the “punch
    list” items room by room. It is further admitted that on July 31, 2015
    Plaintiff stated to Defendant that Plaintiff would fix the problems noted and
    Defendant would be happy when Plaintiff was finished. It is further
    admitted Defendant agreed for Plaintiff to come back to the residence on
    August 3, 2015 to make those repairs. It is further admitted that when
    Plaintiff returned to the residence on August 3, 2015, Defendant told him “I
    don’t want you back in my home. I don’t want your sub-contractors back
    in the home.” It is further admitted Plaintiff left the premises and sent an
    email to Defendant on August 3, 2015 stating he wanted to perform the
    punch list of corrections. It is further admitted that Defendant answered the
    email and confirmed he did not want Plaintiff to make those corrections. It
    is further admitted that on August 24, 2015 attorney M. Jenne wrote a letter
    on behalf of Plaintiff to Defendant stating “Mr. Calfee stands ready, willing
    and able to complete the items on your punch list at your earliest
    convenience”. It is further admitted Defendant never communicated a
    response to that letter that Plaintiff would be allowed to complete the punch
    list.
    The Court finds the contract as well as case law requires the owner
    to give the opportunity to cure any defects in workmanship. By failing to
    do so, Defendant was in material breach of the contract.
    It is therefore, ORDERED, ADJUDGED and DECREED that the
    Motion for Summary Judgment is GRANTED on both the Plaintiff’s
    contract claim and dismissing Defendant’s counter-claim.
    -8-
    GCB filed an application for attorney’s fees, and the MaGees filed a motion to
    alter or amend. In January 2019, the Trial Court entered an order awarding GCB
    $62,844.96 in attorney’s fees to be assessed against Mr. MaGee. In May 2019, the Trial
    Court entered its final order, wherein it ruled on the MaGees’ motion to alter or amend.
    The Trial Court stated:
    This cause came to be heard on the 28th day of February, 2019 upon
    the Defendants’ Motion to Alter or Amend the previous order entered in this
    matter. Defendant asked this Court to review its prior ruling on several
    bases. After review of each of those, the Court hereby grants the motion in
    part and denies the motion in part.
    Defendants asked this Court to clarify its previous order that Diane
    Magee was not a party to any contract in this case. On June 20, 2018 this
    Court previously reserved ruling on the motion to dismiss the breach of
    contract claim against Diane Magee. After review of the previous order in
    this matter, it appears there is no dispute that Ms. Magee was not a party to
    any contract with the Plaintiff in this case and therefore any breach of
    contract claim against her is dismissed.
    Next, Defendant has asked this Court to reconsider the October 2018
    order granting summary judgment and dismissing the Counter-complaint.
    Defendant takes the position there were two parts to the counter-claim: (1)
    a claim for damages for defective work; and (2) a claim for accounting
    under the contract. It is the Defendant’s position that the Motion for
    Summary Judgment did not address the accounting part of the claim.
    After review of the motion, this Court agrees in part. The Court did
    not address the accounting issue specifically. However, prior to suit being
    filed, the parties agreed to a partial settlement of the issues between them.
    This settlement obviated the need for an accounting.
    The only issue left between the parties was embodied in the
    agreement. Defendant admitted the amount owed per Exhibit 8 to Calfee
    Statement of Facts. The only issue remaining was the floor repair which
    Defendant refused to allow Plaintiff the opportunity to cure per the
    contract.
    Therefore, the motion to alter is denied. The motion to amend is
    granted to specifically reflect that the complaint for an accounting is
    dismissed.
    The MaGees timely appealed.2
    2
    In his reply brief on appeal, Mr. MaGee states: “Greg Calfee Builders, LLC does not appear to have
    appealed the determination by the trial court that Diane MaGee should be dismissed as a defendant, since
    she had never executed the contract with Greg Calfee Builders, LLC . . . Consequently, this reply brief is
    -9-
    Discussion
    The MaGees raise five issues on appeal. We restate and consolidate these five
    into the following two dispositive issues: 1) whether the Trial Court erred in granting
    GCB’s motion for summary judgment; and, 2) whether the Trial Court erred in declining
    to find that Mr. MaGee is entitled to an accounting of funds paid to GCB. Although not
    stated exactly as such, GCB raises the following separate issue: whether GCB is entitled,
    under the Contract, to an award of attorney’s fees incurred since the Trial Court entered
    its January 2019 order on attorney’s fees.
    As our Supreme Court has instructed regarding the standard of review on motions
    for summary judgment:
    Summary judgment is appropriate when “the pleadings, depositions,
    answers to interrogatories, and admissions on file, together with the
    affidavits, if any, show that there is no genuine issue as to any material fact
    and that the moving party is entitled to a judgment as a matter of law.”
    Tenn. R. Civ. P. 56.04. We review a trial court’s ruling on a motion for
    summary judgment de novo, without a presumption of correctness. Bain v.
    Wells, 
    936 S.W.2d 618
    , 622 (Tenn. 1997); see also Abshure v. Methodist
    Healthcare–Memphis Hosp., 
    325 S.W.3d 98
    , 103 (Tenn. 2010). In doing
    so, we make a fresh determination of whether the requirements of Rule 56
    of the Tennessee Rules of Civil Procedure have been satisfied. Estate of
    Brown, 
    402 S.W.3d 193
    , 198 (Tenn. 2013) (citing Hughes v. New Life Dev.
    Corp., 
    387 S.W.3d 453
    , 471 (Tenn. 2012)).
    ***
    [I]n Tennessee, as in the federal system, when the moving party does not
    bear the burden of proof at trial, the moving party may satisfy its burden of
    production either (1) by affirmatively negating an essential element of the
    nonmoving party’s claim or (2) by demonstrating that the nonmoving
    party’s evidence at the summary judgment stage is insufficient to establish
    the nonmoving party’s claim or defense. We reiterate that a moving party
    seeking summary judgment by attacking the nonmoving party’s evidence
    must do more than make a conclusory assertion that summary judgment is
    appropriate on this basis. Rather, Tennessee Rule 56.03 requires the
    submitted for Neill MaGee.” Indeed, GCB has not appealed Ms. MaGee’s dismissal, nor has it made any
    argument regarding Ms. MaGee. We leave the Trial Court’s dismissal of Ms. MaGee undisturbed.
    -10-
    moving party to support its motion with “a separate concise statement of
    material facts as to which the moving party contends there is no genuine
    issue for trial.” Tenn. R. Civ. P. 56.03. “Each fact is to be set forth in a
    separate, numbered paragraph and supported by a specific citation to the
    record.”
    Id. When such
    a motion is made, any party opposing summary
    judgment must file a response to each fact set forth by the movant in the
    manner provided in Tennessee Rule 56.03. “[W]hen a motion for summary
    judgment is made [and] . . . supported as provided in [Tennessee Rule 56],”
    to survive summary judgment, the nonmoving party “may not rest upon the
    mere allegations or denials of [its] pleading,” but must respond, and by
    affidavits or one of the other means provided in Tennessee Rule 56, “set
    forth specific facts” at the summary judgment stage “showing that there is a
    genuine issue for trial.” Tenn. R. Civ. P. 56.06. The nonmoving party
    “must do more than simply show that there is some metaphysical doubt as
    to the material facts.” Matsushita Elec. Indus. 
    Co., 475 U.S. at 586
    , 106 S.
    Ct. 1348. The nonmoving party must demonstrate the existence of specific
    facts in the record which could lead a rational trier of fact to find in favor of
    the nonmoving party. If a summary judgment motion is filed before
    adequate time for discovery has been provided, the nonmoving party may
    seek a continuance to engage in additional discovery as provided in
    Tennessee Rule 56.07. However, after adequate time for discovery has
    been provided, summary judgment should be granted if the nonmoving
    party’s evidence at the summary judgment stage is insufficient to establish
    the existence of a genuine issue of material fact for trial. Tenn. R. Civ. P.
    56.04, 56.06. The focus is on the evidence the nonmoving party comes
    forward with at the summary judgment stage, not on hypothetical evidence
    that theoretically could be adduced, despite the passage of discovery
    deadlines, at a future trial.
    Rye v. Women’s Care Cntr. of Memphis, MPLLC, 
    477 S.W.3d 235
    , 250, 264-65 (Tenn.
    2015).
    Regarding contract interpretation, our Supreme Court has stated:
    When we interpret a contract, our role is to ascertain the intention of
    the parties. The intention of the parties is based on the ordinary meaning of
    the language contained within the four corners of the contract. The
    interpretation of a contract is a matter of law, which we review de novo
    with no presumption of correctness.
    84 Lumber Co. v. Smith, 
    356 S.W.3d 380
    , 383 (Tenn. 2011) (citations omitted).
    -11-
    We first address whether the Trial Court erred in granting GCB’s motion for
    summary judgment. The MaGees, arguing that the Trial Court erred, assert the
    following: (1) there is no duty to provide notice and opportunity to cure when the
    contractor has superior knowledge of deficiencies, is aware of these deficiencies in his or
    her own work, and/or continuously fails to meet the contract specifications during
    construction; (2) under the Contract, Mr. MaGee was permitted to terminate, without
    notice or opportunity to cure, for material neglect or a material breach; (3) even if Mr.
    MaGee was required to provide GCB notice and opportunity to cure, he did so; and, (4)
    genuine issues of material fact as to which party breached the Contract first preclude
    summary judgment. The MaGees argue further that paragraph 19 of the Contract
    concerning termination is operative here rather than paragraph 10 concerning warranties,
    including the language about the opportunity to cure.
    In granting summary judgment to GCB, the Trial Court relied on Manor Homes,
    LLC v. Ashby Communities, LLC, No. M2017-01369-COA-R3-CV, 
    2018 WL 3814981
    (Tenn. Ct. App. Aug. 10, 2018), no appl. perm. appeal filed. The parties dispute the
    significance and application of Manor Homes to this case. In Manor Homes, we
    discussed the requirement to give notice and a reasonable opportunity to cure
    construction defects as follows:
    With respect to the guidelines set forth in Exhibit H of the PSA [the
    contract], Mr. Cude admitted at trial that Manor Homes [the builder] was
    not in compliance with some of these guidelines. However, the trial court
    found, and Ashby Communities and Mr. Powell do not dispute, that Mr.
    Powell never mentioned any concerns he had with the work Manor Homes
    was doing on the house (after the initial disagreements at the beginning of
    the project) until shortly before Mr. Powell separated Manor Homes from
    the project. Mr. Cude wanted to know what Mr. Powell’s concerns were so
    he could address them and correct anything that might have been wrong,
    but Mr. Powell did not respond to Mr. Cude’s phone calls or e-mails. As
    stated above, the trial court did not find Mr. Powell’s testimony as to the
    breach of the PSA to be credible, and the court found that Ashby
    Communities and Mr. Powell committed the first material breach of the
    PSA by removing Manor Homes from the project and failing to give it a
    chance to cure the problems Mr. Powell identified before removing Manor
    Homes from the construction project.
    The law in Tennessee is that “a party alleging defects in the
    performance of a contract is required to give notice and a reasonable
    opportunity to cure the defects.” Forrest 
    Constr., 337 S.W.3d at 229
          (citing Carter v. Krueger, 
    916 S.W.2d 932
    , 935 (Tenn. Ct. App. 1995)).
    -12-
    The reason for this requirement is to encourage contracting parties to settle
    their disputes and avoid litigation by allowing the defaulting party the
    chance to repair defective work, reduce damages, and avoid additional
    problems.
    Id. (citing Custom
    Built Homes by Ed Harris v. McNamara, No.
    M2004-02703-COA-R3-CV, 
    2006 WL 3613583
    , at *5 (Tenn. Ct. App.
    Dec. 11, 2006)). In addition, the party that commits the first breach of a
    contract is precluded from recovering damages based on the other party’s
    later breach of the same contract.
    Id. at 226
    (citing United Brake Sys., Inc.
    v. Am. Envtl. Prot., Inc., 
    963 S.W.2d 749
    , 756 (Tenn. Ct. App. 1997), and
    McClain v. Kimbrough Constr. Co., Inc., 
    806 S.W.2d 194
    , 199 (Tenn. Ct.
    App. 1990)); see also Madden Phillips Constr., Inc. v. GGAT Dev. Corp.,
    
    315 S.W.3d 800
    , 812 (Tenn. Ct. App. 2009). Because Ashby Communities
    and Mr. Powell did not give Manor Homes notice and an opportunity to
    cure any defects in the house prior to removing it from the project, we
    affirm the trial court’s conclusion that Ashby Communities and Mr. Powell
    were the first to breach the PSA and are, therefore, not entitled to recover
    damages as a result of Manor Homes’ failure to comply with the
    specifications set out in Exhibit H to the PSA.
    Manor Homes, 
    2018 WL 3814981
    , at *12.
    Thus, Manor Homes bolsters GCB’s position that it was entitled to notice and a
    reasonable opportunity to cure defects. The MaGees, however, point out a number of
    cases standing for the proposition that notice and opportunity to cure may be excused in
    some circumstances. In Forrest Const. Co., LLC v. Laughlin, this Court discussed as
    follows:
    We believe that the cases of Custom Built, Eastbourne, Salley, and
    Vaccaro support the finding that Forrest Construction’s material breach of
    the contract by failing to adhere to the contract’s terms, and the substantial
    number of defects in the construction excused the Laughlins from the
    requirement to give notice and an opportunity to cure. While Forrest
    Construction seems to argue that the duty to give notice and an opportunity
    to cure is an unyielding requirement, the aforementioned cases indicate that
    the surrounding circumstances must be taken into account to determine
    what was reasonable under the circumstances. The Laughlins sought
    damages only for the defects that they discovered after moving into the
    residence in January of 2005. By this time, Forrest Construction had
    materially breached the contract by abandoning the job site, and did not
    return the phone call of Mr. Laughlin regarding this abandonment.
    Therefore, we affirm the trial court’s ruling that the Laughlins were
    -13-
    excused from the requirement to give notice and an opportunity to cure the
    alleged defects.
    Forrest Const. Co., LLC v. Laughlin, 
    337 S.W.3d 211
    , 231 (Tenn. Ct. App. 2009)
    (emphasis in original, footnote omitted).
    We see no necessary contradiction between Manor Homes and Forrest Const. Co.,
    LLC. Tennessee caselaw requires notice and an opportunity to cure construction defects.
    This requirement is not absolute, however. If, for instance, a contractor simply walks off
    a job, or is entirely incompetent, the requirement may be excused. In those
    circumstances, the builder has not merely been deficient in one detail or another on a
    project, but has demonstrated an unwillingness or complete inability to do the job. In that
    case, an opportunity to cure would be futile. That is distinct from scenarios involving
    defects that are amenable to cure. As reflected by paragraph 10 of the Contract, a
    construction project is almost certain to feature some imperfections along the way, and a
    builder almost always will be in a position to have superior knowledge about them. To
    excuse the requirement to give notice and a reasonable opportunity to cure any defects
    discovered because the builder had superior knowledge about them would effectively
    nullify the requirement. Here, it would be contrary to the language of paragraph 10 of the
    Contract, as well.
    Our inquiry, then, centers on whether the defects alleged in the present case are of
    the sort that are amenable to cure. The MaGees contend that there are material facts in
    dispute regarding the severity of the defects and whether Mr. MaGee’s initial refusal to
    allow GCB back was reasonable. Specifically, the MaGees point to Charles Alexander’s
    affidavit detailing numerous defects in the home’s construction. At this, the summary
    judgment stage, we must discern whether there is a dispute of material fact necessitating
    determination by the trier-of-fact. The crux of the Alexander affidavit is that GCB did a
    badly rushed job. Taking that assessment as completely true, this was not enough to
    excuse Mr. MaGee from giving GCB notice and a reasonable opportunity to cure as he
    originally agreed to do before changing his mind.
    Nevertheless, the MaGees assert that Paragraph 19 of the Contract, set forth in the
    Background section of this Opinion, provides a right to terminate. Indeed, the Owner
    may terminate in instances where the Contractor “materially defaults or materially
    neglects to carry out the work in accordance with the contract documents.” However,
    another provision of the Contract, Paragraph 10, provides for an opportunity to cure
    defects. These provisions are not at odds. Paragraph 19 obviates neither Tennessee
    caselaw on the opportunity to cure nor the terms of Paragraph 10 of the Contract.
    Paragraph 10 states, in part, that “[u]pon receipt of Owner’s written report of a defect, if
    the defective item is covered by the Contractor’s duty and quality workmanship,
    -14-
    Contractor shall repair or replace it at no charge to Owner within thirty (3) days.” We
    note the discrepancy in the Contract as to the amount of time the Contractor has to makes
    repairs or replacements. However, we need not decide whether the Contract provided for
    three days or thirty days because Mr. MaGee went back on his initial assent and told
    GCB unequivocally that it could not return to cure the defects. The MaGees did not
    budge for three months until their counsel sent GCB a letter stating it could return, which
    leads us to consider whether this late change of mind constituted a reasonable opportunity
    to cure.
    The MaGees assert that their allowing GCB back—albeit after three months had
    passed—reflects that GCB was, in fact, given a reasonable opportunity to cure.
    According to the MaGees, “the trial court appears to have taken no account of the
    undisputed fact that Mr. MaGee made the effort to have GCB cure its construction
    defects in November 2015,” and “[t]he trial court’s failure to give credit to the
    opportunity to cure provided by Mr. MaGee warrants reversal of the summary judgment
    granted in favor of GCB. . . .” What the MaGees overlook is that Mr. MaGee told GCB,
    unequivocally, that it could not return to the jobsite. Mr. MaGee later confirmed this.
    Mr. MaGee’s tardy reversal after three months passed was in no sense a reasonable
    opportunity to cure for GCB. We find, as did the Trial Court, that Mr. MaGee committed
    a material breach of the Contract.
    We next address whether the Trial Court erred in declining to find that Mr. MaGee
    is entitled to an accounting of funds paid to GCB. The MaGees contend that there was no
    formal settlement of the non-flooring issues, and that they retained their rights under the
    Contract. According to the MaGees, the Trial Court found an accord and satisfaction that
    does not exist. However, the record is clear that the parties settled their non-flooring
    issues. All that remained was the $25,418.51 in dispute related to the flooring. In view
    of the partial settlement, we agree with the Trial Court that an accounting of all funds
    paid is neither appropriate nor necessary. We affirm the Trial Court in its dismissal of
    Mr. MaGee’s request for an accounting.
    The final issue we address is whether GCB is entitled, under the Contract, to an
    award of attorney’s fees incurred since the Trial Court entered its January 2019 order on
    attorney’s fees. To recap, the Trial Court already has awarded GCB $62,844.96 in
    attorney’s fees incurred in a lawsuit over approximately $25,000, notwithstanding Mr.
    MaGee’s counterclaim. Moreover, it does not appear that all of the awarded attorney’s
    fees were related to the flooring issue. Under these circumstances, GCB is entitled to no
    additional attorney’s fees under the Contract. GCB already has received a reasonable fee.
    We affirm the judgment of the Trial Court in all respects.
    Conclusion
    -15-
    The judgment of the Trial Court is affirmed, and this cause is remanded to the
    Trial Court for collection of the costs below. The costs on appeal are assessed against the
    Appellant, Neill MaGee, and his surety, if any.
    _____________________________________
    D. MICHAEL SWINEY, CHIEF JUDGE
    -16-