Melanie Shea Thompson v. Southland Constructors ( 2020 )


Menu:
  •                IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    September 2, 2020 Session
    MELANIE SHEA THOMPSON ET AL. v. SOUTHLAND CONSTRUCTORS
    ET AL.
    Appeal from the Circuit Court for Sumner County
    No. 83CC1-2018-CV-1032 Joe H. Thompson, Judge
    No. M2019-02060-COA-R3-CV
    This action involves a tragic accident resulting in the death of Tommy Smith (“Decedent”),
    who was working as a plumber connecting a sewer line when the trench he was in collapsed
    and crushed him. Decedent’s children (“Plaintiffs”) sued, among others, Focus Design
    Builders, LLC, general contractors for the building project, alleging negligence. The trial
    court granted Focus Design’s motion to dismiss the complaint for failure to state a claim
    upon which relief can be granted, pursuant to Tenn. R. Civ. P. 12.02(6). The trial court
    held that Focus Design did not owe a duty of reasonable care under the circumstances
    because Decedent’s death was unforeseeable. We hold the complaint states a cause of
    action for negligence and consequently reverse the judgment of the trial court.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court
    Reversed; Case Remanded
    KRISTI M. DAVIS, J., delivered the opinion of the Court, in which JOHN W. MCCLARTY and
    THOMAS R. FRIERSON, II, JJ., joined.
    David Randolph Smith and Dominick R. Smith, Nashville, Tennessee, for the appellants,
    Melanie Shea Thompson and Tyler Thomas Smith.
    Richard Spicer and Lance W. Thompson, Nashville, Tennessee, for the appellee, Focus
    Design Builders, LLC.
    OPINION
    I. BACKGROUND
    The construction project was the design and building of a new student activity center
    and gymnasium on the campus of Welch College in Gallatin, Tennessee. Welch College
    hired defendant Southland Constructors, Inc. as general contractor and on-site construction
    manager. According to the complaint, Welch College also “hired defendant Focus Design
    Builders, LLC as a general contractor . . . with the duties and responsibilities imposed by
    its contracts and by taking out the building permit . . . for the project with the city of Gallatin
    on March 16, 2017.”
    Defendant Music City Fire Sprinkler, LLC, the utility contractor, installed the sewer
    lines for the project. Music City laid the pipe for the sewer line at issue but did not connect
    it to the building before it was buried. The Welch College basketball team was scheduled
    to play its opening game in the new gymnasium on October 27, 2017. The plumbing issue
    resulting from the unconnected sewer line was not discovered until approximately one day
    before the scheduled game. The complaint alleges that “negligently and recklessly the[]
    defendants proceeded in a rush and hurry to open the building to the public before proper
    inspections and a certificate of use and occupancy had been obtained.”
    Southland Constructors discovered the plumbing issue and called Mitchell
    Plumbing, Decedent’s employer, to fix the problem. According to the complaint,
    Upon discovery of the negligent defect, Defendant SouthLand1 Constructors,
    Inc. as agent for the owner (Welch College) and/or Welch College hired
    Mitchell Plumbing to connect the sewer line by a trenching and excavation
    job on an emergent basis to make the sewer operational for the opening
    basketball game scheduled the next night (Friday, October 27, 2017)—
    despite the fact that the building had not received a final inspection nor any
    use and occupancy permit.
    Contrary to its obligations as an owner, construction manager, and general
    contractor, Welch College, SouthLand Constructors, Inc. and Focus Design
    Builders failed to inspect the work that had been done by the contractors
    involved in the plumbing and sewer line construction and failed to advise of
    the need for special precautions and equipment for the excavation that was
    being rushed in wet weather, in a flood plain, on ground and soil that was
    dangerous and unstable (having previously been disturbed when the sewer
    line was installed some 35-40 feet from the building. . . .)
    (Numbering in original omitted). Southland Constructors advised Mitchell Plumbing that
    a trench about fifteen feet long and three feet deep would be required to access the end of
    1
    In various places in the record, the defendant’s name is spelled “SouthLand,” and in others,
    “Southland.” The defendant’s own answer consistently spells it “Southland,” but in its answer to the
    amended complaint, it is primarily spelled “SouthLand.” The record leaves us unsure of the correct
    capitalization.
    2
    the sewer line. This information turned out to be inaccurate; the trench required was longer
    and deeper than this estimate. Mitchell Plumbing allegedly relied on this misinformation
    and did not bring materials to shore up the sides of the trench.
    Decedent and another Mitchell Plumbing employee arrived with a trackhoe
    excavator to connect the sewer line. The end of the sewer line was buried about five feet
    deep. Plaintiffs allege the soil in the area was in an especially dangerous condition because
    it was wet and loose due to the previous excavation. Shortly after Decedent entered the
    trench to connect the PVC piping from the bathroom to the sewer line, the walls collapsed
    on him and he was crushed to death.
    Plaintiffs sued Welch College, Southland Constructors, Focus Design, and Music
    City for negligence resulting in Decedent’s wrongful death. Specifically, the amended
    complaint alleges as follows in pertinent part:
    Defendant SouthLand Constructors, Inc. and Focus Design Builders, LLC
    through employees, agents, had the responsibility as a general contractor and
    site manager to make sure and ensure that no dangerous and hazardous
    conditions existed on said property and premises.
    *      *       *
    The death of Tommy Smith was caused by the direct and proximate result of
    the negligence of Defendants in the following particulars:
    a. In failing to construct, inspect and oversee that the sewer line had never
    been connected to the building;
    b. In misinforming Mitchell Plumbing and its employees that the trench that
    needed to be dug was 15 feet in length and 3 feet in depth;
    c. In failing to inform Mitchell Plumbing and its employees that the buried
    sewer line would require excavation protection (as depth was 5 feet or
    greater);
    d. Ordering and scheduling the work when it was wet, raining, cold and the
    soil was in a dangerous condition not suitable for excavation due to these
    conditions (Type C soil) and because of the prior excavation that had
    previously disturbed and loosened the soil.
    3
    e. Ordering work on a rush basis to accommodate the public in a building
    whose sewer line that had not been approved on a final inspection and had
    not been approved for use and occupancy.
    f. Negligently failing to inspect or realize that a bathroom sewer line had not
    been properly connected and installed prior to burying and sodding the area.
    g. Failing to properly plan the trenching and excavation and failing to have a
    proper competent person approve the trenching plan.
    h. Failing to close the adjacent pavement and parking lot to vehicles while
    the excavation was occurring. Having failed to close the parking lot to
    vehicles and traffic, vibrations were from vehicles were a substantial factor
    in causing the trench wall to give way and cave in. The parking lot was at
    all relevant times under the exclusive control of SouthLand Constructors
    Inc., Welch College and/or Focus Design Builders, LLC.
    i. In failing to take the necessary steps and adequate precautions to see or
    ensure that the excavation was undertaken safely;
    j. In failing to perform reasonable inspections which would have detected the
    dangerous and/or hazardous conditions which existed;
    k. In negligently failing to determine the depth of the sewer line before
    misinforming Mitchell Plumbing that its depth was only three feet;
    l. In failing to perform regular or routine inspections of the soil, premises,
    bathroom, drain(s) and sewer line to ensure that no dangerous or hazardous
    condition existed;
    m. In negligently rushing this job due to the previous delays and the
    scheduled basketball game thereby failing to take proper planning and safety
    precautions;
    n. Failing to connect the sewer line to the bathroom line and drain thereby
    creative [sic] a defective and dangerous condition that directly caused the
    emergency/rushed excavation;
    o. Failing to obtain a final approval and final inspection for the sewer line
    from the White House Utility District;
    4
    p. Failing to warn that the sewer line had been left unconnected to the
    building and concealed and covered up with dirt and sod to grade, thereby
    concealing the sewer line and creating a dangerous condition[.]
    Focus Design filed a Rule 12.02(6) motion to dismiss the complaint for failure to
    state a claim upon which relief can be granted. Welch College filed an answer denying
    liability, and cross-claims against Southland Constructors and Focus Design. The trial
    court granted Focus Design’s motion to dismiss, holding as follows:
    Generally, an owner or occupier of land owes an independent contractor
    hired to perform work on the premises a duty to use reasonable care to
    provide a reasonably safe place in which to work. . . . But even assuming
    that as the general contractor, Focus Design Builders was the occupier of the
    property and therefore obligated to provide to independent contractors a
    reasonably safe place to work, such a duty does not carry with it the
    requirement of constant care and inspection under any and all circumstances.
    *      *       *
    Respectfully, the court finds that the Plaintiffs have failed to demonstrate that
    Focus Design Builders reasonably knew or should have known of the
    probability of injury to Mr. Smith. To extend the duty of care to Focus
    Design Builders under the facts alleged in this case would require Focus
    Design Builders to foresee the risk that another contractor would leave a
    sewer line disconnected, that Southland Constructors would hire Mitchell
    Plumbing to excavate the sewer line but misinform it of the depth of the line,
    that Mitchell Plumbing and Mr. Smith would continue to excavate below
    three (3) feet to a depth of more than five (5) feet without a trench box or
    sidewall protection, and that Mr. Smith would climb into a trench more than
    five (5) feet deep that was not supported with any sidewall protection.
    (Citations omitted). The trial court granted Focus Design’s motion to deem the court’s
    dismissal of the complaint a final and appealable order pursuant to Tenn. R. Civ. P. 54.02,
    notwithstanding that other issues against other parties remain unadjudicated.
    II. ISSUES
    Plaintiffs appeal, raising these issues, as quoted from their brief:
    1.     Whether the Trial Court, at the Rule 12.02(6) pleadings stage, erred by
    finding that the allegations in the First Amended Complaint were insufficient to
    5
    establish a duty of care owed by Focus Design Builders to Plaintiffs’ decedent,
    Tommy Smith due
    to lack of foreseeable harm?
    2. Whether it was reasonably foreseeable that Focus Design Builders’ breach of its
    duty of care could result in a cave-in injury to Mr. Smith?
    III. STANDARD OF REVIEW
    As this Court has recently reiterated, “[a] motion to dismiss filed pursuant to Tenn.
    R. Civ. P. 12.02(6) challenges the legal sufficiency of the complaint, not the strength of the
    plaintiff’s proof or evidence.” Mershon v. HPT TA Properties Trust, No. M2018-00315-
    COA-R3-CV, 
    2018 WL 5793564
    , at *2 (Tenn. Ct. App., Nov. 5, 2018) (quoting Webb v.
    Nashville Area Habitat for Humanity, Inc., 
    346 S.W.3d 422
    , 426 (Tenn. 2011) (internal
    quotation marks omitted)). “A defendant who files a motion to dismiss admits the truth of
    all of the relevant and material allegations contained in the complaint, but asserts that the
    allegations fail to establish a cause of action.”
    Id. (ellipses and internal
    quotation marks
    omitted). According to our Supreme Court,
    “Our motion-to-dismiss jurisprudence reflects the principle that this stage of
    the proceedings is particularly ill-suited for an evaluation of the likelihood
    of success on the merits or of the weight of the facts pleaded, or as a docket-
    clearing mechanism.” Webb v. Nashville Area Habitat for Humanity, 
    346 S.W.3d 422
    , 437 (Tenn. 2011). In reviewing these motions, we are required
    to construe the complaint liberally, presume that all factual allegations are
    true and give the plaintiff the benefit of all reasonable inferences.
    Id. Only when it
    appears that the plaintiff can prove no set of facts in support of the
    claim that would entitle the plaintiff to relief should a trial court grant a
    motion to dismiss. 
    Webb, 346 S.W.3d at 426
    . The lower courts’ legal
    conclusions are reviewed de novo without any presumption of correctness.
    Id. Cullum v. McCool,
    432 S.W.3d 829
    , 832 (Tenn. 2013). Whether a defendant owes a
    plaintiff a duty of care in a negligence case is a question of law that we review de novo.
    Id. at 832-33. IV.
    ANALYSIS
    A plaintiff must prove the following elements to establish a negligence claim: “(1)
    a duty of care owed by the defendant to the plaintiff; (2) conduct by the defendant falling
    below the standard of care amounting to a breach of the duty; (3) an injury or loss; (4)
    6
    causation in fact; and (5) proximate (legal) causation.” Helton v. Lawson, No. E2018-
    02119-COA-R3-CV, 
    2019 WL 6954180
    , at *9 (Tenn. Ct. App. Dec. 18, 2019) (quoting
    Bradshaw v. Daniel, 
    854 S.W.2d 865
    , 869 (Tenn. 1993)). “Duty is ‘a legal obligation to
    conform to a reasonable person standard of care in order to protect others against
    unreasonable risks of harm.’” 
    Cullum, 432 S.W.3d at 833
    (quoting Satterfield v. Breeding
    Insulation Co., 
    266 S.W.3d 347
    , 355 (Tenn. 2008).
    As this Court stated in Miranda v. CSC Sugar, LLC, No. W2017-01986-COA-R3-
    CV, 
    2018 WL 3302035
    at *3 (Tenn. Ct. App. July 5, 2018),
    In premises liability cases, persons in control of real property have a duty to
    exercise reasonable care under the circumstances to prevent injury to persons
    lawfully on the premises. Johnson v. EMPE, Inc., 
    837 S.W.2d 62
    , 65 (Tenn.
    Ct. App. 1992). Under Tennessee law, the employee of an independent
    contractor enjoys the status of an invitee while performing work on the
    premises of the owner-contractee. Dempster Bros. Inc. v. Duncan, 61 Tenn.
    App. 88, 
    452 S.W.2d 902
    , 906 (1969). As a result of the employee’s status
    as an invitee, the premises owner owes the employee “the duty to exercise
    reasonable care to see that an employee has a reasonably safe place to work.”
    Id. This general duty
    includes the specific responsibility of either removing,
    or warning the independent contractor of, any hidden or latent dangers on the
    property. Bennett v. Trevecca Nazarene Univ., 
    216 S.W.3d 293
    , 299 (Tenn.
    2007).
    Tennessee appellate courts addressing situations where an employee of a
    subcontractor is injured at a workplace have looked to, among other things, the contracts
    governing the relationships between the landowners, prime contractors, and subcontractors
    to examine the scope of parties’ respective duties. See, e.g., Johnson v. EMPE, Inc., 
    837 S.W.2d 62
    , 65-68 (Tenn. Ct. App. 1992); Oman Constr. Co. v. Tenn. Cent. Ry. Co., 
    370 S.W.2d 563
    , 575 (Tenn. 1963) (noting that “[t]he existence of a contract may furnish the
    occasion for a tort obligation” and ruling “there was ample proof introduced at the trial to
    make an issue for the jury as to negligence on the part of [defendants] in constructing the
    tunnel beneath plaintiff’s property”); Martin v. Garner & Law, No. 03A01-9102-CV-
    00080, 
    1991 WL 177915
    , at *1-2 (Tenn. Ct. App. Sept. 13, 1991). In Martin, a case
    involving the death of a contractor’s workers in a trench cave-in, the Court observed that
    “[t]he contract between the owner and the contractor (decedents’ employer) utilizes the
    standard American Institute of Architects form, which places sole responsibility for
    supervision and safety on the contractor.” 
    1991 WL 177915
    , at *1.
    7
    The complaint in this case alleges that Focus Design, “as general contractor for the
    construction . . . [had] the duties and responsibilities imposed by its contracts and by taking
    out the building permit.” It further alleges:
    Plaintiff avers Southland Constructors, Inc. acted as an agent of Focus
    Design Builders, LLC by both the common law of agency and/or by virtue
    of Focus Design Builder’s duties imposed under the building permit and/or
    by its contractual relationship with Welch College and/or SouthLand
    Constructors, Inc.
    *      *       *
    Focus Design Builders, LLC through employees, agents, had the
    responsibility as a general contractor and site manager to make sure and
    ensure that no dangerous and hazardous conditions existed on said property
    and premises.
    In their initial response to Focus Design’s motion to dismiss, plaintiffs argued that
    dismissal of their complaint was premature because they had not been allowed time and
    opportunity to conduct discovery of the alleged contracts, among other things. We agree
    that plaintiffs were entitled to conduct discovery to substantiate their claims that Focus
    Design undertook a duty to oversee and supervise the construction project, inspect the work
    done by subcontractors, and warn employees of hazardous conditions. In Martin, this
    Court stated the following in response to a similar argument:
    On the remaining issue, the trial judge abused his discretion in restricting
    plaintiffs’ discovery to Blount Excavating employees. Plaintiffs were placed
    in [the] position of responding to a motion for summary judgment without
    meaningful discovery of all defendants. While the trial judge has broad
    discretion over the discovery process, this discretion is abused when
    summary judgment is granted without permitting adequate discovery.
    
    1991 WL 177915
    , at *2.
    When Welch College filed its cross-claim against Focus Design, it attached its
    contract with Focus Design to its answer and cross-claim, and further expressly alleged the
    following in its pleading:
    Welch College entered into a contract with [Focus Design], AIA® Document
    A103TM - 2007, Standard Form of Agreement Between Owner and
    8
    Contractor, . . . (the “Contract”), regarding the construction by [Focus
    Design] of a Student Recreation Center for Welch College.
    The Contract incorporated the AIA® Document A201TM - 2007 General
    Conditions of the Contract for Construction (“General Conditions”), a copy
    of which is attached hereto as Exhibit B. Section 3.3 of the General
    Conditions entitled SUPERVISION AND CONSTRUCTION
    PROCEDURES contains the following relevant provisions:
    § 3.3.1 The Contractor shall supervise and direct the Work, using the
    Contractor’s best skill and attention. The Contractor shall be solely
    responsible for, and have control over, construction means, methods,
    techniques, sequences and procedures and for coordinating all portions of the
    Work under the Contract, unless the Contract Documents give other specific
    instructions concerning these matters. If the Contract Documents give
    specific instructions concerning construction means, methods, techniques,
    sequences or procedures, the Contractor shall evaluate the jobsite safety
    thereof and, except as stated below, shall be fully and solely responsible for
    the jobsite safety of such means, methods, techniques, sequences or
    procedures. If the Contractor determines that such means, methods,
    techniques, sequences or procedures may not be safe, the Contractor shall
    give timely written notice to the Owner and Architect and shall not proceed
    with that portion of the Work without further written instructions from the
    Architect. . . .
    *      *       *
    § 3.3.3 The Contractor shall be responsible for inspection of portions of
    Work already performed to determine that such portions are in proper
    condition to receive subsequent Work.
    The Contract, at Section 10.2 of the General Conditions entitled SAFETY
    OF PERSONS AND PROPERTY, provides:
    § 10.2.1 The Contractor shall take reasonable precautions for safety of, and
    shall provide reasonable protection to prevent damage, injury or loss to
    .1 employees on the Work and other persons who may be
    affected thereby;
    .2 the Work and materials and equipment to be incorporated
    therein, whether in storage on or off the site, under care,
    9
    custody or control of the Contractor or the Contractor’s
    Subcontractors or Sub-subcontractors; and
    .3 other property at the site or adjacent thereto, such as trees,
    shrubs, lawns, walks, pavements, roadways, structures and
    utilities not designated for removal, relocation or replacement
    in the course of construction.
    § 10.2.2 The Contractor shall comply with and give notices required by
    applicable laws, statutes, ordinances, codes, rules and regulations, and lawful
    orders of public authorities bearing on safety of persons or property or their
    protection from damage, injury or loss.
    § 10.2.3 The Contractor shall erect and maintain, as required by existing
    conditions and performance of the Contract, reasonable safeguards for safety
    and protection, including posting danger signs and other warnings against
    hazards, promulgating safety regulations and notifying owners and users of
    adjacent sites and utilities.
    *      *        *
    § 10.2.6 The Contractor shall designate a responsible member of the
    Contractor’s organization at the site whose duty shall be the prevention of
    accidents. This person shall be the Contractor’s superintendent unless
    otherwise designated by the Contractor in writing to the Owner and
    Architect.
    § 10.2.7 The Contractor shall not permit any part of the construction or site
    to be loaded so as to cause damage or create an unsafe condition.
    (Bold font and capitalization in original; numbering omitted).
    The trial court dismissed the complaint on the ground that the chain of events
    leading to Decedent’s death was unforeseeable. Our Supreme Court, in the cases of
    Satterfield v. Breeding Insulation Co., 
    266 S.W.3d 347
    (Tenn. 2008) and Giggers v.
    Memphis Housing Auth., 
    277 S.W.3d 359
    (Tenn. 2009), provided guidance regarding a
    trial court’s role in assessing foreseeability at a pretrial stage of litigation. The Court
    explained:
    In order to determine whether a duty is owed in a particular circumstance,
    courts must first establish that the risk is foreseeable, and, if so, must then
    10
    apply a balancing test based upon principles of fairness to identify whether
    the risk was unreasonable. Satterfield v. Breeding Insulation Co., 
    266 S.W.3d 347
    , 366 (Tenn. 2008). That is, in consideration of, among other
    things, the presence or absence of prior similar incidents, and other
    circumstances, does the foreseeability of the harm outweigh the burden of
    the duty imposed? 
    McClung, 937 S.W.2d at 901
    . In Downs ex rel. Downs
    v. Bush, 
    263 S.W.3d 812
    , 820 (Tenn. 2008), we held as follows:
    The foreseeability of the harm is a key factor in the equation
    because, in general terms, “[f]oreseeability is the test of
    negligence.” 
    West, 172 S.W.3d at 552
    (quoting Linder Constr.
    
    Co., 845 S.W.2d at 178
    ); Hale v. Ostrow, 
    166 S.W.3d 713
    ,
    716–17 (Tenn. 2005). “ ‘A risk is foreseeable if a reasonable
    person could foresee the probability of its occurrence or if the
    person was on notice that the likelihood of danger to the party
    to whom is owed a duty is probable.’ ” 
    West, 172 S.W.3d at 551
    (quoting Linder Constr. 
    Co., 845 S.W.2d at 178
    ).
    However, foreseeability alone does not create a duty to
    exercise reasonable care. 
    McClung, 937 S.W.2d at 904
    . If the
    risk is foreseeable, then courts should weigh the remaining
    factors to determine if an imposition of duty is justified.
    Although no duty will arise when a risk of injury is not generally foreseeable,
    foreseeability alone “is not, in and of itself, sufficient to create a duty.”
    
    Satterfield, 266 S.W.3d at 366
    . Rather, when a minimum threshold of
    foreseeability is established, courts must engage in “an analysis of the
    relevant public policy considerations,”
    id. at 364–65,
    to determine whether a
    duty enforceable in tort must be imposed. While not exclusive, the factors
    are as follows:
    [T]he foreseeable probability of the harm or injury occurring;
    the possible magnitude of the potential harm or injury; the
    importance or social value of the activity engaged in by
    defendant; the usefulness of the conduct to defendant; the
    feasibility of alternative, safer conduct and the relative costs
    and burdens associated with that conduct; the relative
    usefulness of the safer conduct; and the relative safety of
    alternative conduct.
    
    McCall, 913 S.W.2d at 153
    . See also 
    Burroughs, 118 S.W.3d at 329
    .
    11
    When and if the trial court determines that the foreseeability of the harm and
    its particular gravity outweigh the burden of taking reasonable protective
    measures, the question “of duty and of whether defendants have breached
    that duty . . . is one for the jury to determine based upon proof presented at
    trial.” 
    McClung, 937 S.W.2d at 904
    .
    
    Giggers, 277 S.W.3d at 365-66
    .
    The question of whether Plaintiffs have demonstrated “a minimum threshold of
    foreseeability,”
    id. at 366,
    and thereby established “a prima facie case of specific
    foreseeability,”
    id. at 367,
    is inextricably intertwined with questions of what Focus Design
    knew or reasonably should have known, and when. Tennessee appellate courts have
    focused on the often fact-driven questions of knowledge and awareness of alleged defects
    in determining foreseeability at a pretrial stage. For example, the Satterfield Court
    observed that “[u]nder the facts alleged in Ms. Satterfield’s complaint, Alcoa was aware of
    the presence of significant quantities of asbestos fibers on its employees’ work clothes. It
    was also aware of the dangers posed by even small quantities of asbestos and that asbestos
    fibers were being transmitted by its employees to 
    others.” 266 S.W.3d at 367
    . Based on
    these facts, among other things, the Court reversed the trial court’s grant of judgment on
    the pleadings for the defendant.
    Id. at 375.
    In Giggers, the Supreme Court, reversing
    summary judgment, found that Memphis Housing Authority, “with some general
    knowledge of criminal activity within its housing complexes and a particular knowledge
    of Miller’s altercation with another tenant four years earlier, could have reasonably
    foreseen the probability of a violent 
    act.” 277 S.W.3d at 367
    .
    This Court has stated on several occasions that “[p]remises liability stems from
    superior knowledge of the condition of the premises.” Keirsey v. K-VA-T Food Stores,
    Inc., No. E2018-01213-COA-R3-CV, 
    2019 WL 1301758
    , at *4 (Tenn. Ct. App. Mar. 20,
    2019); Shaw v. Metro. Gov’t of Nashville, 
    596 S.W.3d 726
    , 735 (Tenn. Ct. App. 2019)
    (stating that a premises owner’s “duty to exercise reasonable care under the circumstances
    to prevent injury to persons lawfully on the premises . . . is based on the understanding that
    an owner has ‘superior knowledge of any perilous condition that may exist on the
    property’”) (quoting Dobson v. State, 
    23 S.W.3d 324
    , 330 (Tenn. Ct. App. 1999)). Focus
    Design has not cited any appellate opinion upholding a trial court’s dismissal of a
    complaint on the ground that the plaintiff was unable to establish a minimum threshold of
    foreseeability, nor has our research revealed such a case. Conversely, we have reversed
    such decisions at either the motion-to-dismiss or summary judgment stage on several
    occasions. See, e.g., Mershon, 
    2018 WL 5793564
    , at *1 (reversing dismissal on
    foreseeability grounds because “dismissing the complaint is premature at this stage of the
    proceedings”); Richardson v. Trenton Special Sch. Dist., No. W2015-01608-COA-R3-CV,
    
    2016 WL 3595563
    , at *7 (Tenn. Ct. App. June 27, 2016) (“We conclude that the question
    12
    of whether this assault was foreseeable based on the school’s supervision policy is a
    question to be determined at trial, and that summary judgment is premature here”); Riggs
    v. Wright, 
    510 S.W.3d 421
    , 432 (Tenn. Ct. App. 2016) (affirming dismissal on other
    grounds but expressly not on foreseeability; stating “we assume arguendo that, at the
    motion to dismiss stage, Mr. Riggs has alleged sufficient facts from which to conclude that
    the harm involved was foreseeable”); Lourcey v. Estate of Scarlett, No. M2002-00995-
    COA-R3-CV, 
    2003 WL 21525259
    , at *3 (Tenn. Ct. App. July 8, 2003) (reversing dismissal
    on foreseeability grounds).
    In the present case, Focus Design argues that it was not aware that Southland
    Constructors called Mitchell Plumbing to fix the sewer line problem. Plaintiffs respond
    that this assertion of ignorance is disputable. They also allege that Focus Design should
    have known of the allegedly hazardous condition of the excavated soil, and should have
    discovered and been aware of the unattached sewer line. Moreover, Plaintiffs allege that
    Southland Constructors acted as Focus Design’s agent, a contention Focus Design denies,
    but which must be accepted as true at the motion-to-dismiss stage.2 Additionally, Plaintiffs
    have alleged direct conduct, or lack thereof, by Focus Design, which it argues was a cause
    of Decedent’s injuries, by, according to the complaint, “[f]ailing to close the adjacent
    pavement and parking lot to vehicles while the excavation was occurring. Having failed
    to close the parking lot to vehicles and traffic, vibrations . . . from vehicles were a
    substantial factor in causing the trench wall to give way and cave in.”
    In Cullum, the Supreme Court was also presented with a case where the trial court
    dismissed a complaint upon its finding that the defendant did not have a duty of reasonable
    care under the circumstances. The Court’s conclusory observations are pertinent and apt
    to the present case:
    Assuming, as we must at this stage of the proceeding, that the Cullums’
    allegations are true, the harm caused by Ms. McCool was reasonably
    foreseeable.
    *        *       *
    2
    Focus Design also argues that we should apply the “independent contractor rule” that, generally,
    “an employer or general contractor is not ordinarily liable for the negligence of an independent contractor,”
    quoting Wilson v. Thompson Const. Co, 
    86 S.W.3d 536
    , 541 (Tenn. Ct. App. 2001). Both parties recognize
    on appeal that this issue was raised but not addressed by the trial court. We note in passing that although
    Focus Design may continue to allege and argue comparative fault as a defense, Plaintiffs’ action is based
    on much more than simply any alleged negligence of the subcontractor Mitchell Plumbing or its employee,
    Decedent. Consequently, the independent contractor rule does not provide a ground to dismiss the
    complaint for negligence.
    13
    “As a practical matter, a court serves as a gate-keeper and may exclude a
    claim only if it finds, as a matter of law, that the defendant does not owe a
    duty to the plaintiff.” 
    Satterfield, 266 S.W.3d at 368
    . We do not shut the
    gate on the Cullums’ claims. But, we emphasize the limited nature of our
    holding, which turns in large part on its procedural posture. There has been
    no discovery, no trial and no decision by a factfinder. We are only reviewing
    the sufficiency of the allegations in the Cullums’ complaint, which we must
    accept as true. Our decision at this early stage of the case is not an evaluation
    of the likelihood of success on the merits of the claim. We do not know what
    either party will be able to prove when this matter is heard on the merits. We
    are simply holding that at this stage of the proceedings, Wal-Mart cannot
    show as a threshold matter of law that it did not have a duty to protect its
    patron, Ms. 
    Cullum. 432 S.W.3d at 835
    , 838-39. As did the Cullum Court, we reverse the judgment of the trial
    court because the Plaintiffs have made a threshold showing of foreseeability. Accepting
    the allegations of the complaint and reasonable inferences therefrom as true, dismissal was
    unwarranted.
    V. CONCLUSION
    The judgment of the trial court is reversed and the case remanded for such further
    actions as may be necessary, consistent with this opinion. Costs on appeal are assessed to
    the appellee, Focus Design Builders, LLC, for which execution may issue if necessary.
    ______________________________________
    KRISTI M. DAVIS, JUDGE
    14