Texas Commission on Environmental Quality and Dos Repúblicas Coal Partnership v. Maverick County, City of Eagle Pass, Environmental Defense Fund, Walter Herring, Ernesto Ibarra, Gabriel De La Cerda, Mike Hernandez, Boulware and Anson Family, Ltd., and Maverick County Environmental and Public Health Association ( 2022 )


Menu:
  •          Supreme Court of Texas
    ══════════
    No. 19-1108
    ══════════
    Texas Commission on Environmental Quality and
    Dos Repúblicas Coal Partnership,
    Petitioners,
    v.
    Maverick County, City of Eagle Pass, Environmental Defense
    Fund, Walter Herring, Ernesto Ibarra, Gabriel De La Cerda,
    Mike Hernandez, Boulware and Anson Family, Ltd., and
    Maverick County Environmental and Public Health Association,
    Respondents
    ═══════════════════════════════════════
    On Petition for Review from the
    Court of Appeals for the Third District of Texas
    ═══════════════════════════════════════
    Argued October 27, 2021
    JUSTICE BLACKLOCK delivered the opinion of the Court.
    In 2013, Dos Repúblicas Coal Partnership (DRCP) applied to the
    Texas Commission on Environmental Quality for renewal of a permit for
    wastewater discharge at a coal mine. TCEQ granted the permit. Years
    later, the primary question before this Court is whether, all along,
    DRCP was the correct permit applicant. We hold that it was.
    The parties agree that TCEQ rules required both “the operator
    and the owner [of the facility]” to apply for a permit. 30 TEX. ADMIN.
    CODE § 305.43(a). DRCP owns the mine. It hired a contractor to conduct
    day-to-day activities at the mine. The dispute is whether DRCP or the
    contractor is the mine’s “operator.” TCEQ’s rules define “operator” as
    “[t]he person responsible for the overall operation of a facility.” Id.
    § 305.2(24). TCEQ concluded that DRCP remains the mine’s operator
    because it retains overall responsibility for the mine’s operation despite
    having contracted away day-to-day duties.
    The court of appeals disagreed.        Applying its precedent, it
    understood “operator” to mean “the entity responsible for [the] personal
    performance of causing the [facility] to function.” See Heritage on San
    Gabriel Homeowners Ass’n v. Tex. Comm’n on Env’t Quality, 
    393 S.W.3d 417
    , 430 (Tex. App.—Austin 2012, pet. denied). Because DRCP hired a
    contractor to personally perform the daily running of the mine, the court
    of appeals concluded that the contractor is the mine’s “operator” and
    therefore a required—but absent—permit applicant.
    When a statute or rule defines its terms, courts should not
    construct a restated definition using alternative verbiage that adds or
    subtracts substantive requirements or limiting factors. The court of
    appeals erred by substituting a judicially crafted definition of “operator”
    for the definition provided by TCEQ’s rules. Even if the definition
    supplied by the rule’s drafters leaves room for interpretation in some
    cases, the touchstone must remain the text of the definition—not a
    judicial paraphrase of it.
    2
    Applying the rule’s definition of “operator” to this case, we hold
    that substantial evidence supports TCEQ’s conclusion that DRCP—
    despite having contracted out the day-to-day running of the mine—
    remains “responsible” for the “overall operation” of the mine.        The
    “personal performance” requirement proposed by Respondents imposes
    an additional limiting factor not dictated by the rules themselves. By
    requiring that a permit applicant have responsibility only for the
    facility’s overall operation, the rule is best read to reject—rather than
    embrace—the narrowing “personal performance” requirement that
    dictated the outcome below. The judgment of the court of appeals is
    reversed, and the case is remanded to that court for consideration of the
    parties’ remaining arguments.
    I.
    The Legislature authorized TCEQ to “issue permits and
    amendments to permits for the discharge of waste or pollutants into or
    adjacent to water in the state.” TEX. WATER CODE § 26.027(a). As for
    who must apply for such a permit or what a permit application will look
    like, the Legislature vested TCEQ with broad discretion: “A person
    desiring to obtain a permit or to amend a permit shall submit an
    application to [TCEQ] containing all information reasonably required by
    [TCEQ].”   Id. § 26.027(b).   TCEQ has adopted administrative rules
    governing applications for a “Texas Pollutant Discharge Elimination
    System” (TPDES) permit, the permit for which DRCP applied.            See
    generally 30 TEX. ADMIN. CODE § 305.1 et seq. One such rule—which the
    parties agree applies here—is that “it is the duty of the operator and the
    owner to submit an application for a permit.” Id. § 305.43(a).
    3
    Once TCEQ’s executive director determines an application is
    “administratively complete,” the applicant must provide public notice of
    its intent to obtain the permit. TEX. WATER CODE § 5.552(b)(1). The
    executive director then “shall conduct a technical review of and issue a
    preliminary decision on the application.” Id. § 5.553(a). The applicant
    must publish notice of the preliminary decision, which is then subject to
    public comment. Id. § 5.553(b)–(c). A public meeting and a contested
    case hearing may follow. See id. §§ 5.554 (requiring public meetings
    during the comment period), 5.556(a) (allowing for contested case
    hearings).
    In 2009, DRCP acquired a coal mine in Maverick County. It
    contracted with Camino Real Fuels, LLC (CRF) to “develop, construct,
    operate and perform on-going reclamation at the Mine and to remove
    and deliver coal from the Mine” to DRCP. The mine is near the City of
    Eagle Pass. Wastewater from the mine may flow into nearby waterways
    that feed into the Rio Grande River, from which the City gets its water
    supply.   Because of these wastewater discharges, DRCP needed a
    TPDES permit. See id. § 26.121.
    DRCP’s predecessor held a TPDES permit for the mine dating to
    1994 (renewed in 2001, 2006, and 2011) that was set to expire on
    September 1, 2015. DRCP alone applied for the renewal of the permit.
    DRCP started the renewal process in September 2013. Relative to the
    existing permit, DRCP requested permission to alter its wastewater
    management practices in various ways, the technicalities of which are
    not relevant to our decision.
    4
    In January 2014, TCEQ’s executive director determined DRCP’s
    application administratively complete. See id. § 5.552(a). The executive
    director completed his technical review in December 2014, after which
    he issued a “Notice of Application and Preliminary Decision.” See id.
    § 5.553(a). This document granted a “draft permit” and gave notice of a
    public meeting on the permit. See id. § 5.553(b)–(c) (requiring notice of
    public meeting). During the meeting, TCEQ took public comments. See
    id. §§ 5.554, 5.555(a) (requiring the executive director to respond to
    relevant and material public comments).
    At relevant times during the administrative process, Maverick
    County, the City of Eagle Pass, the Environmental Defense Fund,
    Walter Herring, Ernesto Ibarra, Gabriel De La Cerda, Mike Hernandez,
    Boulware and Anson Family, Ltd., and the Maverick County
    Environmental and Public Health Association (collectively “Permit
    Contestants”) opposed the permit. See id. § 5.556(a), (c), (d) (authorizing
    “affected person[s]” to contest the executive director’s decision or request
    a contested case hearing). They challenged TCEQ’s conclusion that
    DRCP was the mine’s “operator” and raised many other environmental
    and property-rights complaints.
    On January 15, 2015, DRCP requested that TCEQ refer the
    application to SOAH for a contested case hearing. Id. § 5.557(a). Permit
    Contestants were admitted as parties.           In November 2015, two
    administrative law judges held a four-day hearing.          In addition to
    considering a variety of substantive objections to the permit, the ALJs
    considered whether DRCP’s contractor, CRF, should have applied as the
    mine’s “operator.”
    5
    In April 2016, the ALJs issued a proposal for decision (PFD),
    recommending TCEQ grant the permit with “the addition of a boron
    limit and a requirement that aluminum be monitored.”               On the
    “operator” question, the ALJs found that DRCP was both the owner and
    the operator of the mine. They noted that while CRF performed the
    day-to-day work of running the mine, CRF was merely a contractor
    acting under DRCP’s direction. The ALJs acknowledged testimony that
    DRCP only had “financial responsibility” for the mine, while CRF had
    “operational responsibility.” They pointed to other evidence, however,
    tending to show that DRCP was responsible for the overall operation of
    the mine despite CRF’s responsibility for day-to-day activities:
    DRCP is solely responsible for the acquisition and
    maintenance of all interests and rights in real property and
    the reserves, provides its requirements and expectations to
    CRF, approves every plan and budget prior to the
    incurrence of any costs by CRF, pays all actual costs during
    design and construction of the Mine, pays all operation
    costs during production at the Mine, and is required to
    retain, maintain, and comply with all permits.
    PFD at 16. The ALJs also noted that a DRCP representative visits the
    mine daily to provide oversight.
    TCEQ largely agreed with the PFD, but it found that the boron
    limit and aluminum monitoring requirements were unnecessary. See
    TEX. GOV’T CODE § 2003.047(m) (authorizing TCEQ to amend factual
    findings contained in a PFD). TCEQ instead required water-quality
    testing periodically over the life of the permit. In July 2016, TCEQ
    issued a final order granting DRCP’s application with modifications.
    Permit Contestants sued TCEQ in Travis County District Court.
    See id. § 2001.171 (authorizing judicial review of a final decision in a
    6
    contested case). DRCP intervened. Permit Contestants raised the same
    issues they raised before SOAH, with the addition of an objection to
    TCEQ’s modification of the PFD. The district court held that DRCP was
    not the mine’s operator and that TCEQ’s decision to the contrary “was
    not reasonably supported by substantial evidence considering the
    reliable and probative evidence in the record as a whole, and was
    arbitrary and capricious.” The district court affirmed TCEQ’s decision
    on all other issues. Cf. id. § 2001.174 (reviewing court may affirm in
    whole or in part or reverse or remand for further proceedings).
    Both sides appealed. 
    628 S.W.3d 497
    , 500 (Tex. App.—Austin
    2019). DRCP and TCEQ appealed the “operator” issue. 
    Id.
     Permit
    Contestants appealed on issues affirmed by the district court. 
    Id.
     The
    court of appeals affirmed the district court’s holding that DRCP was not
    the “operator” of the mine. 
    Id.
     Relying on its prior decision in Heritage
    v. TCEQ, 
    393 S.W.3d 417
    , the court of appeals understood “operator” to
    mean “the entity responsible for its personal performance of causing the
    [facility] to function.” 628 S.W.3d at 506. Applying this definition, the
    court of appeals concluded that substantial evidence did not support
    TCEQ’s finding that DRCP was the mine’s operator. Id. at 511. As a
    result, the application lacked the required applicant and should have
    been denied. Id. at 511–12. Having concluded that the permit should
    not have been granted regardless of its substantive content, the court of
    appeals held it lacked jurisdiction over the remaining issues regarding
    the content of the permit. It vacated the district court’s judgment as to
    those issues. Id. at 512.
    7
    TCEQ and DRCP ask this Court to reinstate TCEQ’s decision in
    its entirety. They argue that the court of appeals departed from the
    plain text of TCEQ’s administrative definition of “operator” by
    employing the court’s own definition. They also complain of the court of
    appeals’ application of the substantial-evidence rule.            Permit
    Contestants contend that Heritage’s “more precise” definition of
    “operator” controls and, applying that definition, there is no substantial
    evidence to support TCEQ’s conclusion that DRCP is the mine’s
    operator. The parties also dispute whether the court of appeals should
    have—and,     indeed,   could   have—addressed     Permit    Contestants’
    remaining issues after ruling on the “operator” issue.
    II.
    Courts reviewing agency action under the Administrative
    Procedure Act may reverse or remand agency orders, and:
    shall reverse or remand the case for further proceedings if
    substantial rights of the appellant have been prejudiced
    because the administrative findings,              inferences,
    conclusions, or decisions are:
    (A) in violation of a constitutional or statutory
    provision;
    (B) in excess of the agency’s statutory authority;
    (C) made through unlawful procedure;
    (D) affected by other error of law;
    (E) not reasonably supported by substantial
    evidence considering the reliable and probative
    evidence in the record as a whole; or
    (F) arbitrary or capricious or characterized by abuse
    of discretion or clearly unwarranted exercise of
    discretion.
    TEX. GOV’T CODE § 2001.174(2).
    8
    The parties agree that we should review TCEQ’s conclusion that
    DRCP is the mine’s “operator” under subpart E, which asks whether the
    agency’s decision is “reasonably supported by substantial evidence.”
    When applying the substantial-evidence rule, “a court may not
    substitute its judgment for the judgment of the state agency on the
    weight of the evidence on questions committed to agency discretion.” Id.
    § 2001.174. “The true test is not whether the agency reached the correct
    conclusion, but whether some reasonable basis exists in the record for
    the action taken by the agency.”        Tex. Health Facilities Comm’n v.
    Charter Med.–Dall., Inc., 
    665 S.W.2d 446
    , 452 (Tex. 1984).
    III.
    The parties’ arguments can be distilled into three questions:
    (1) how to define “operator”; (2) whether there was substantial evidence
    that DRCP is the mine’s “operator”; and (3) whether the court of appeals
    should have ruled on the remaining issues. We address each question
    in turn.
    A.
    Before we can apply the substantial-evidence rule to TCEQ’s
    decision that DRCP is the mine’s operator, we must understand the
    meaning of the word “operator,” as TCEQ’s rules use it. This definitional
    inquiry raises a predicate legal question, which we address de novo. See
    R.R. Comm’n v. Tex. Citizens for a Safe Future & Clean Water, 
    336 S.W.3d 619
    , 624 (Tex. 2011).
    The Legislature conferred on TCEQ very broad discretion to set
    the requirements for permit applications of this sort. See TEX. WATER
    CODE § 26.027(b). Applicants must “submit an application [] containing
    9
    all information reasonably required by [TCEQ].” Id. The Legislature
    authorized TCEQ to promulgate rules governing TPDES permits. See
    id. §§ 26.011, 26.027. TCEQ has done so. See generally 30 TEX. ADMIN.
    CODE § 305.1 et seq.      Despite its broad statutory authority over
    applications, once TCEQ promulgates rules governing the application
    process, it must follow them.         TEX. WATER CODE § 5.234 (“An
    application . . . shall be presented to the executive director and handled
    as provided . . . in the rules adopted by the [TCEQ].”). This case is about
    whether it did so.
    Courts interpret agency regulations “using the same principles
    we apply when construing statutes.” Patients Med. Ctr. v. Facility Ins.
    Co., 
    623 S.W.3d 336
    , 341 (Tex. 2021). The starting point is the rule’s
    plain text. TGS–NOPEC Geophysical Co. v. Combs, 
    340 S.W.3d 432
    , 439
    (Tex. 2011). As with statutes, when a rule “assigns a particular meaning
    to a term, we are bound by” it. 
    Id.
     It is often stated that courts will
    uphold an agency’s interpretation of its own rule if the interpretation “is
    reasonable and does not contradict [the rule’s] plain language.” R.R.
    Comm’n, 336 S.W.3d at 625 (quotation omitted). Even so, courts must
    first determine what the rule’s text means before they can decide
    whether the agency’s interpretation contradicts the text.        See, e.g.,
    Harris Cnty. Appraisal Dist. v. Tex. Workforce Comm’n, 
    519 S.W.3d 113
    ,
    119 (Tex. 2017).
    The rule at issue requires both “the operator and the owner [of
    the facility]” to apply for a TPDES permit.        30 TEX. ADMIN. CODE
    10
    § 305.43(a).1 Another provision defines the term “operator” as “[t]he
    person responsible for the overall operation of a facility.” Id. § 305.2(24).
    In a dispute over who must apply as the “operator,” courts are bound by
    the definition provided in TCEQ’s rules, just as they are bound when the
    Legislature defines terms in a statute. See Combs, 340 S.W.3d at 439.
    Following its precedent, the court of appeals understood
    “operator” to mean “the entity responsible for its personal performance
    of causing the facility to function.” 628 S.W.3d at 505 (quoting Heritage,
    
    393 S.W.3d at 430
    ). In Heritage, landowners challenged TCEQ’s order
    concluding that Waste Management was the “operator” of a landfill. 
    393 S.W.3d at 422, 426
    .2 The court of appeals agreed with TCEQ. In so
    1   The full text of the relevant provision is:
    (a) It is the duty of the owner of a facility to submit an
    application for a permit or a post-closure order. However, if the
    facility is owned by one person and operated by another and the
    executive director determines that special circumstances exist
    where the operator or the operator and the owner should both
    apply for a permit or a post-closure order, and for all Texas
    Pollutant Discharge Elimination System permits, it is the duty
    of the operator and the owner to submit an application for a
    permit.
    The parties agree that only the final portion of the provision, specific to TPDES
    permits, applies here.
    2 Petitioners argue that Heritage has no application here because it
    involved a different category of permit. But the disputed definition of
    “operator” applies to both wastewater and solid-waste permits. See 30 TEX.
    ADMIN. CODE § 305.2 (“The following words and terms, [including ‘operator,’]
    when used in this chapter, have the following meanings.”); see also RSUI
    Indem. Co. v. The Lynd Co., 
    466 S.W.3d 113
    , 126 (Tex. 2015) (“Generally, the
    law recognizes ‘a natural presumption that identical words used in different
    parts of the same act are intended to have the same meaning.’” (quoting Atl.
    Cleaners & Dyers, Inc. v. United States, 
    286 U.S. 427
    , 433 (1932))).
    11
    doing, it relied on dictionary definitions of “operates”—“to cause to
    function usu[ally] by direct personal effort”—and “operation”—“doing or
    performing especially of action.”         
    393 S.W.3d at
    428–30 (citing
    WEBSTER’S THIRD NEW INTERNATIONAL DICTIONARY (2002)).                  After
    lengthy analysis, the court summarized its understanding of “operator”
    using the “personal performance” language quoted above. 
    Id. at 430
    .3
    It bears noting that Heritage affirmed TCEQ’s decision that
    Waste Management was the “operator” and therefore the correct
    applicant. When Heritage is read in its context, as all judicial decisions
    should be, the court employed the “personal performance” concept not to
    exclude parties from the definition of “operator” but to explain why the
    definition included Waste Management. And it did so within a statutory
    scheme that gives TCEQ remarkably broad discretion to determine
    which entities must file applications. See TEX. WATER CODE § 26.027(b).
    Nevertheless, the court of appeals below applied the “personal
    performance” paraphrase as if it were the governing definition of
    “operator.”   Applying Heritage in this way was error.           A judicial
    paraphrase of a legislatively supplied rule of decision—no matter how
    well-reasoned or suitable to the case then before the court—does not
    become the rule of decision applicable to future cases. That role is
    reserved for the text chosen by the Legislature—or, in this case, by an
    3  Even if the court of appeals was correct that DRCP was the wrong
    applicant, Permit Contestants would only be entitled to relief under the APA
    “if substantial rights of the appellant have been prejudiced because” of the
    error. TEX. GOV’T CODE § 2001.174(2). Petitioners have not argued that
    Permit Contestants do not satisfy this requirement, and we express no opinion
    on that question.
    12
    agency acting with the Legislature’s permission. See PHI, Inc. v. Tex.
    Juv. Just. Dep’t, 
    593 S.W.3d 296
    , 305 (Tex. 2019) (holding that a
    description of a statute in a judicial “opinion is not itself the rule of
    decision. That role is reserved for the statute.”).
    Here, the governing definition of “operator,” to which courts are
    not free to add or subtract verbiage, is “[t]he person responsible for the
    overall operation of a facility.”      30 TEX. ADMIN. CODE § 305.2(24).
    Relative to the definition provided by the rule, the Heritage
    reformulation injects the limiting principle of “personal performance.”
    The effect on the definition is to replace the rules’ use of “overall
    operation”   with    the   court’s     use   of   “personal   performance.”
    Understanding “operation” to mean solely “personal performance” may
    make it easier to identify the operator by clarifying and limiting the
    scope of what counts as “operation.” But a court’s principal goal when
    interpreting text is not to achieve simplicity or ease of application—
    though these would be by-products of a well-drafted rule. Instead, a
    court’s duty is to stick to the text chosen by the rule-makers, without
    adding to it or subtracting from it.
    So what does it mean to be “responsible for the overall operation
    of the facility”?   Permit Contestants argue that “operation” entails
    “flipping the switches”—personally performing the tasks required to
    operate the facility. TCEQ and DRCP, on the other hand, argue that
    “operation” entails the ultimate authority to make decisions about how
    the facility will be operated. In a vacuum, neither is an unreasonable
    understanding of the word “operation.” But we are not in a vacuum. We
    are applying the text of the rule. And the rule itself tells us what kind
    13
    of operation it envisions—“overall operation.” We need look only at the
    modifier “overall,” a word chosen by the rulemakers, to resolve the
    parties’ disagreement about the rule’s meaning.4
    The question, properly framed, is not what “operation” means.
    Looking at the entire definition, the questions are what “overall
    operation” means, and what it means to be “responsible” for it. When
    we focus on all the words contained in the rule—not on dictionaries
    defining one of them—it becomes clear that TCEQ’s approach is
    well-supported by the text of its rule. The court of appeals erred by
    excluding from “operator” those entities who are responsible for overall
    operations even though they may not conduct daily operations.5
    4  Permit Contestants argue that the Court should look to the federal
    Environmental Protection Agency’s (EPA) view of “operator” because TCEQ
    amended its rules to include the operator requirement at the behest of the
    EPA. See 
    15 Tex. Reg. 5492
    , 5493 (1990). Permit Contestants assert that
    “EPA’s understanding as early as 1980 was that operational control, not
    financial or some other class of control, was the marker of an entity that needed
    to apply for the permit.” Even so, EPA’s definition is not any narrower than
    TCEQ’s. As the court of appeals noted, “[t]he federal regulations do not
    specifically define ‘operator’ as distinct from ‘owner’; rather, a definition is
    provided for ‘owner or operator,’ which ‘means the owner or operator of any
    facility or activity subject to regulation under the NPDES program.’” 628
    S.W.3d at 504 n.6 (quoting 
    40 C.F.R. § 122.2
    ). And, EPA reviewed and had no
    objection to the draft permit here.
    5 TCEQ advances its own restatement of the rule’s definition of
    “operator”: “an entity (owner or not) that is liable to be called on to answer, in
    general and taking everything into account, for the mine’s management or
    manner of functioning.” We decline to adopt that formulation, not because of
    any obvious defect in its substance, but because doing so would risk falling into
    the same error as the court of appeals. TCEQ’s proffered paraphrase is full of
    words not contained in the rule itself, such as “liable,” “in general,” and
    “management.” Such concepts may be helpful, in some cases, to courts
    grappling with what it means to be “responsible for the overall operation of the
    14
    B.
    We next address whether substantial evidence supports TCEQ’s
    conclusion that DRCP was the mine’s operator. “The question whether
    an agency’s determination meets [the substantial-evidence] standard is
    one of law.” Montgomery Indep. Sch. Dist. v. Davis, 
    34 S.W.3d 559
    , 566
    (Tex. 2000). Under substantial-evidence review, we consider “whether
    any evidence supports the [agency’s] determination.” Pub. Util. Comm’n
    v. Tex. Indus. Energy Consumers, 
    620 S.W.3d 418
    , 427 (Tex. 2021). We
    ask “not whether the agency’s decision is correct, but whether the record
    demonstrates a reasonable basis for it.” Ne. Indep. Sch. Dist. v. Riou,
    
    598 S.W.3d 243
    , 251 (Tex. 2020). “The findings, inferences, conclusions,
    and decisions of an administrative agency are presumed to be supported
    by substantial evidence, and the burden is on the contestant to prove
    otherwise.” Charter Med.–Dall., Inc., 665 S.W.2d at 453.
    In the Findings of Fact section of its Order granting the permit,
    TCEQ concluded the following:
    40. Based on the Contract Mining Agreement signed by Mr.
    Gonzalez Saravia Coss, DRCP is solely responsible for the
    acquisition and maintenance of all interests and rights in
    real property and the reserves, provides its requirements
    and expectations to CRF, approves every plan and budget
    prior to the incurrence of any costs by CRF, pays all actual
    costs during design and construction of the Eagle Pass
    Mine, pays all operation costs during production at the
    facility.” In other cases, undue focus on these extraneous words might inject
    limiting or expanding factors not justified by the text of the rule. If TCEQ
    wants to amend its rules’ definition of “operator” to include these additional
    concepts, it should do so through the appropriate process, not through
    litigation.
    15
    Eagle Pass Mine, and is required to retain and maintain
    all permits.
    41. DRCP has an office in Eagle Pass, and a DRCP
    representative visits the site on a daily basis to oversee all
    the functions for which it has responsibility.
    42. DRCP has ownership and control of mine operations,
    including activities subject to the TPDES permit; has
    responsibility over permit compliance, including the
    TPDES permit; is integrally involved in the activities at
    the Eagle Pass Mine; and has financial responsibility over
    the operations at the Eagle Pass Mine.
    Based on these findings of fact, TCEQ concluded that DRCP was the
    proper permittee as both the mine’s owner and its operator.
    Permit Contestants object to TCEQ’s conclusion primarily
    because, in their view, it cannot be squared with Heritage’s emphasis on
    personal performance, which they contrast with financial responsibility
    or high-level oversight. We have already explained why the court of
    appeals should not have viewed “operation” as entailing only personal
    performance. Any analysis of the evidence through the Heritage lens is
    therefore unhelpful, and this renders most of Permit Contestants’
    arguments about the evidence inapposite.6 As explained above, the
    rule’s definition of “operator” includes the decision-making entity with
    responsibility for overall operations, even if that entity is not personally
    performing the operations. This understanding of who qualifies as an
    6   Respondents come close to conceding that, unless Heritage’s
    understanding of “operator” controls, they cannot win under the substantial-
    evidence rule. See Maverick Cnty. Resp. Br. at 11 (“Unless the court of appeals
    was wrong in its understanding of the meaning of ‘operator,’ the evidence to
    which Petitioners point to claim that DRCP is the operator just does not reach
    the ‘scintilla’ level; it is so weak as to do no more than create a mere surmise
    or suspicion of the fact it is claimed to support.”).
    16
    “operator” must inform the inquiry into whether substantial evidence
    supports the conclusion that DRCP is one.
    Viewing the record as a whole and employing an understanding
    of “operator” based solely on the rule’s text, we hold that substantial
    evidence in the record supports TCEQ’s conclusion that DRCP is the
    mine’s operator. As noted above, TCEQ made several findings of fact in
    support of its conclusion that DRCP is the mine’s “operator.” DRCP
    owns the mine and “control[s]” mine operations, including activities
    subject to the TPDES permit.         DRCP is “integrally involved in the
    activities” at the mine. In addition to having “financial responsibil[ity]”
    for mine operations,7 DRCP must approve each plan and budget before
    CRF may incur costs. DRCP “provides its requirements and
    expectations to CRF.”8 DRCP is “solely responsible” for the acquisition
    and maintenance of all interests and rights in real property and
    reserves. DRCP is responsible for TPDES permit compliance. DRCP
    retains and maintains all permits. And finally, a DRCP representative
    from DRCP’s Eagle Pass office “visits the site on a daily basis to oversee
    7 The parties and the court of appeals focus on a distinction between
    “financial responsibility” and “operational responsibility.” We need not explore
    that distinction, however, because even assuming the distinction is valid, some
    evidence supports the conclusion that DRCP retained operational control—
    particularly, the requirement that it approve plans and budgets, its provision
    of requirements and expectations to CRF, its responsibility for permit
    compliance, and the daily presence of its representative to provide oversight.
    8 A DRCP officer described the relationship: “DRCP provides its
    requirements and expectations to CRF. For example, this could relate to
    amount of coal required. Based on these requirements, CRF develops a mine
    plan in which it describes the necessary steps to comply with DRCP’s
    expectations. . . . DRCP must, however, approve the plan and budget prior to
    the incurrence of any costs by CRF.”
    17
    all the functions for which [DRCP] has responsibility.” See TCEQ Order,
    Findings of Fact at 5, findings 40–42.9
    All of this evidence together demonstrates “a reasonable basis in
    the record” on which TCEQ could have concluded that DRCP is not
    merely a passive owner who has given responsibility for overall
    operations to someone else.       Instead, substantial evidence supports
    TCEQ’s conclusion that DRCP was the entity “responsible for the overall
    operation of the facility” and therefore the correct permit applicant.
    C.
    Permit Contestants raised several other objections to substantive
    elements of TCEQ’s decision, such as whether TCEQ properly conducted
    its “antidegradation review” and whether the permit should impose
    stricter limits on aluminum and boron. The district court affirmed
    TCEQ’s decision on all these issues.
    After holding DRCP was not the mine’s operator and thus the
    incorrect permit applicant, the court of appeals decided it could not
    reach the remaining issues and vacated the part of the district court’s
    judgment addressing them. 628 S.W.3d at 512. The court of appeals
    held that addressing the remaining issues would amount to rendition of
    an advisory opinion. For this proposition, it cited only the general
    prohibition on advisory opinions. See Valley Baptist Med. Ctr. v.
    9  Maverick County makes a token effort in this Court to contest these
    fact findings as unsupported by the record. It does not explain how the findings
    are unsupported, however, instead merely asserting that the findings
    overstate or misstate the record evidence. The burden is on Permit
    Contestants to show that TCEQ’s findings are not supported by substantial
    evidence. Charter Med.–Dall., Inc., 665 S.W.2d at 453. They have failed to
    make that showing here.
    18
    Gonzalez, 
    33 S.W.3d 821
    , 822 (Tex. 2000) (“Under article II, section 1 of
    the Texas Constitution, courts have no jurisdiction to issue advisory
    opinions.”).
    TCEQ, joined by DRCP, argues that the court of appeals erred by
    failing to address the remaining issues.      They contend the court of
    appeals had jurisdiction to reach these issues, and they ask this Court
    to reach them even though the court of appeals did not. Although we
    decline to reach the remaining issues, we hold that the court of appeals
    did not lack jurisdiction to reach them and therefore could have done so.
    The APA provides that a court reviewing an agency decision after
    a contested case “may affirm the agency decision in whole or in part.”
    TEX. GOV’T CODE § 2001.174(1).          The district court exercised its
    authority under this provision by affirming TCEQ’s decision in part.
    Despite reversing on the improper-applicant issue, the district court
    affirmed TCEQ’s decision as to the remaining issues. To the extent the
    court of appeals suggested the district court erred by reaching the
    remaining issues, we disagree. The APA plainly gave both the district
    court and the court of appeals the authority to affirm in part, as the
    district court did, even if other issues required partial reversal or
    remand to the agency. The only remaining question is whether, as the
    court of appeals suggested, a judicial ruling on the remaining issues
    violated the constitutional prohibition on advisory opinions. It did not.
    “The distinctive feature of an advisory opinion is that it decides
    an abstract question of law without binding the parties.” Tex. Ass’n of
    Bus. v. Tex. Air Control Bd., 
    852 S.W.2d 440
    , 444 (Tex. 1993). We see
    nothing “abstract” in the parties’ ongoing, vigorous dispute over TCEQ’s
    19
    scientific and environmental findings regarding this mine. The parties
    are   engaged     in   a   lengthy,   complicated,     and    very   expensive
    administrative process, of which judicial review is but a part—and of
    which the parties’ scientific and environmental disputes are but a part.
    Cases like this one frequently bounce back and forth between the agency
    and the courts or between levels of the court system. It may turn out,
    when the dust settles, that one element or another of a court’s decision
    ended up being irrelevant to the ultimate outcome. That does not mean
    the court lacked jurisdiction to decide that part of the case.             Even
    assuming the remaining issues were rendered superfluous by the court
    of appeals’ resolution of the “operator” question, the possibility remained
    that this Court would take a different view of the “operator” question,
    as we have done.       The dispute over the remaining issues therefore
    remained live, and its resolution still impacted the parties’ rights—even
    though the extent to which it did depended on how the case progressed
    in the future. Resolving the remaining issues would not have amounted
    to an advisory opinion by the court of appeals.10
    10 See, e.g., In re Camp Lejeune, N.C. Water Contamination Litig., 
    2012 WL 12869566
    , at *2 (N.D. Ga. May 11, 2012) (“While the court understands
    Plaintiffs’ concerns that the court is issuing an advisory opinion, it is not
    unusual for a court to rule on alternative arguments and the parties have
    briefed both arguments and provided oral argument to the court. Ruling on
    both arguments would allow the Court of Appeals to consider them at the same
    time rather than extending the litigation by returning to the district court and
    back up to the Court of Appeals a second time.”); cf. Cincinnati Life Ins. Co. v.
    Cates, 
    927 S.W.2d 623
    , 626 (Tex. 1996) (“We further conclude that the
    appellate court may consider other grounds that the movant preserved for
    review and trial court did not rule on in the interest of judicial economy.”).
    20
    The prudential practice of courts to decline to reach issues not
    necessary to the disposition of a case should not be confused with the
    constitutional prohibition on advisory opinions.        There is overlap
    between the two, of course. But particularly in a complex administrative
    appeal, litigation would become unmanageable if it were the rule that
    every issue not strictly necessary to each court’s disposition of the case
    were beyond that court’s constitutional power to decide. The court of
    appeals erred by vacating the district court’s judgment as to the
    remaining issues. Both the district court and the court of appeals had
    jurisdiction to address those issues. The court of appeals could have
    reached them. Whether the court of appeals was obligated to reach them
    is a separate issue, to which we now turn.
    Petitioners argue the court of appeals was obliged to reach the
    remaining issues. It observes that the APA allows courts of appeals to
    “affirm the agency decision . . . in part.” TEX. GOV’T CODE § 2001.174(1).
    Petitioners argue that “in part” carries with it the premise that the other
    part of the judgment reverses the remaining parts of the agency’s
    decision, suggesting that the entire decision has been reviewed. We do
    not read Section 2001.174(1) to obligate courts of appeals to reach all
    issues raised by the parties regardless of whether the issues are
    necessary to dispose of the appeal. The provision uses “may” in an
    apparent attempt to ensure courts have discretion to dispose of cases as
    they see fit.   If the Legislature sought to impose a requirement—
    unknown elsewhere in the law—that courts of appeals reach
    unnecessary issues, we would expect it to be much more clearly stated.
    21
    TCEQ further contends that the court of appeals was obligated by
    Rule of Appellate Procedure 47.1 to reach the remaining issues. Rule
    47.1 requires courts of appeals to “hand down a written opinion
    that . . . addresses every issue raised and necessary to final disposition
    of the appeal.” TCEQ argues that resolution of the remaining issues was
    “necessary to final disposition of the appeal” because the improper-
    applicant problem did not infect the entire proceeding. TCEQ suggests
    the improper-applicant problem can be fixed on remand to the agency
    without necessarily disturbing TCEQ’s findings on other matters,
    although it does not clearly state how this would happen.         Permit
    Contestants disagree. They argue that, if the applicant is improper, the
    entire process has been for naught and must be completely redone. If
    that is true, as they argue, then it was not necessary for the court of
    appeals to review TCEQ decisions that would need to be decided anew
    in a second proceeding.
    We need not resolve this dispute, which raises doubtful questions
    of administrative procedure that would be better decided by this Court
    on more complete briefing. One way or another, the court of appeals’
    judgment will be reversed, and this case will be remanded to the court
    of appeals for consideration of the remaining issues. Whether the court
    of appeals was obligated by Rule 47.1 to address those issues in the past,
    it appears it will be obligated to address them in the future—assuming
    the parties maintain their current positions.
    Finally, TCEQ and DRCP ask this Court to address the remaining
    issues without the benefit of the court of appeals having done so. “When
    presented with an issue the court of appeals could have but did not
    22
    decide, we may either remand the case or consider the issue ourselves.”
    RSL Funding, LLC v. Newsome, 
    569 S.W.3d 116
    , 124 (Tex. 2018) (citing
    TEX. R. APP. P. 53.4). “[O]rdinarily a case will be remanded to the court
    of appeals for further proceedings when we reverse the judgment of the
    appeals court and the reversal necessitates consideration of issues
    raised in but not addressed by that court.” State v. Ninety Thousand
    Two Hundred Thirty-Five Dollars & No Cents in U.S. Currency
    ($90,235), 
    390 S.W.3d 289
    , 294 (Tex. 2013). We conclude that our review
    of these issues, if it becomes necessary, would benefit from the court of
    appeals having addressed them first. We will take the ordinary course
    and remand the remaining issues for consideration by the court of
    appeals.
    IV.
    The judgment of the court of appeals is reversed. The part of the
    district court’s judgment vacated by the court of appeals is reinstated
    without regard to the merits. The case is remanded to the court of
    appeals for further proceedings consistent with this opinion.
    James D. Blacklock
    Justice
    OPINION DELIVERED: February 11, 2022
    23
    

Document Info

Docket Number: 19-1108

Filed Date: 2/11/2022

Precedential Status: Precedential

Modified Date: 2/14/2022