Charles G. Hooks, III v. Samson Lone Star, Limited Partnership, N/K/A Samson Lone Star Llc ( 2015 )


Menu:
  •                 IN THE SUPREME COURT OF TEXAS
    444444444444
    NO . 12-0920
    444444444444
    CHARLES G. HOOKS III, ET AL., PETITIONERS,
    v.
    SAMSON LONE STAR, LIMITED PARTNERSHIP, N/K/A SAMSON LONE STAR LLC,
    RESPONDENT
    4444444444444444444444444444444444444444444444444444
    ON PETITION FOR REVIEW FROM THE
    COURT OF APPEALS FOR THE FIRST DISTRICT OF TEXAS
    4444444444444444444444444444444444444444444444444444
    Argued September 17, 2014
    JUSTICE DEVINE delivered the opinion of the Court.
    In this oil and gas appeal, we consider whether a mineral owner’s claims of fraud and breach
    of contract in the leasing and pooling of his mineral interests are, as a matter of law, barred by
    limitations. A jury determined that the mineral owner, in the exercise of reasonable diligence,
    discovered the fraud less than four years before filing suit, and the trial court accordingly concluded
    that the claims were not barred by limitations. The jury also found fraud and damages in the mineral
    owner’s favor, and the trial court rendered judgment on the jury’s verdict. The court of appeals,
    however, reversed most aspects of the mineral owner’s judgment, concluding that the fraud should
    have been discovered, as a matter of law, more than four years before the mineral owner filed suit
    because the relevant information was available in the Texas Railroad Commission’s public records.
    
    389 S.W.3d 409
    , 429–30, 439–40 (Tex. App.—Houston [1st Dist.] 2012).
    While we agree that public records may under certain circumstances establish a lack of
    diligence in the discovery of fraud as a matter of law, here the records themselves were tainted by
    fraud and thus provide no conclusive proof on the subject. Because we conclude that the mineral
    owner’s diligence in discovering the underlying fraud was in this instance a question of fact for the
    jury, we reverse the court of appeals’ judgment on this and other issues in part, affirm its judgment
    on other issues in part, and remand the cause to the court of appeals for review of a factual
    sufficiency of the evidence complaint and other issues not considered because of the court’s ruling
    on limitations.
    I. Background and Procedural History
    Charles G. Hooks III (“Hooks”)1 sued Samson Lone Star Limited Partnership, now known
    as Samson Lone Star, LLC (“Samson”), in 2006,2 alleging, among other things, breach of contract
    and failure to pay royalties under Texas Natural Resources Code section 91.404. Later amendments
    to Hooks’ petition included allegations of fraud, fraudulent inducement, and statutory fraud. These
    claims centered on three oil and gas leases that Hooks, the lessor, executed with Samson, the lessee,
    1
    The plaintiffs consist of multiple parties. W e refer to them collectively as “Hooks.” Specifically, the parties
    are Charles G. Hooks III, acting individually and as independent executor of the estate of Charles G. Hooks, Jr., as
    Trustee of the Scott Ira McKeever Trust and the David W ayne McKeever Trust, and on behalf of Chas. G. Hooks & Son,
    a General Partnership; McKeever Partnership, Ltd.; and Charles G. Hooks III and Sue Ann Hooks, as co-trustees under
    the will of Charles G. Hooks, Sr.
    2
    Hooks joined a preexisting lawsuit brought by various lessors against Samson. Hooks’ suit was later severed
    from the other claims.
    2
    in 1999. Two leases were in Hardin County, Texas (the “Hardin County Leases”), and one was in
    Jefferson County, Texas (the “Jefferson County Lease”).
    This appeal from a final judgment involves seven claims raised by Hooks. First, Hooks
    alleges that Samson fraudulently induced Hooks to amend the Jefferson County Lease to allow for
    pooling. Second, Hooks asserts that Samson breached the most-favored-nations clause in all three
    leases, failing to pay Hooks the same higher royalty that it paid to a nearby lessor. Third, Hooks
    contends that Samson breached the formation-production clause in each lease by calculating gas
    royalties based on proceeds instead of the volume of gas leaving the reservoir. Fourth, Hooks claims
    that Samson wrongly “unpooled” a unit into which the two Hardin County Leases were pooled, and
    seeks damages for royalties allegedly owed from this unit. Fifth, Hooks alleges that Samson
    breached certain offset provisions in the two Hardin County Leases. Sixth, pursuant to a pretrial
    stipulation, Hooks contends that Samson must reimburse Hooks for attorney’s fees. And seventh,
    Hooks asserts that the proper post-judgment interest rate is 18%, rather than 5% as decided by the
    court of appeals.
    Hooks prevailed on the majority of his claims in the trial court. The trial court granted
    summary judgment for Hooks on the most-favored-nations clause claims and “unpooling” claims,
    but granted summary judgment for Samson regarding Hooks’ allegations that Samson breached the
    offset provisions of the Hardin County Leases. The jury returned a verdict for Hooks on the fraud
    and formation-production claims. The trial court’s final judgment awarded Hooks more than
    $21 million in damages, ordered Samson to pay the stipulated attorney’s fees, and applied a post-
    judgment interest rate of 18%. The court of appeals, however, reversed, holding that Hooks take
    3
    nothing except for $52,257.22, a stipulated amount to reimburse Hooks for payment of ad valorem
    taxes. 
    Id. at 440–41.
    II. Fraud and Limitations
    Hooks’ fraud claims relate to the Jefferson County Lease. This lease, which prohibited
    pooling, contained “offset obligations” providing that if a gas well were completed within 1,320 feet
    of Hooks’ lease line but was not unitized with Hooks’ acreage, then Samson would either drill an
    offset well, pay Hooks compensatory royalties, or release the offset acreage. In 2000, Samson drilled
    a well that bottomed about 1,186 feet from Hooks’ lease, within the 1,320-foot protected zone. But,
    instead of complying with the original offset obligations, Samson asked Hooks to amend the
    Jefferson County Lease in 2001 to pool into a unit associated with the new well. In connection with
    this request, Samson provided Hooks with a plat that incorrectly placed the well’s bottom hole
    outside of the protected zone. A plat with the same false information had already been filed with the
    Railroad Commission. Older Railroad Commission records, however, contained a directional survey
    and an attached plat3 that correctly placed the bottom hole within the 1,320-foot boundary.4 Other
    preliminary Railroad Commission filings demonstrated that Samson originally intended the well to
    bottom within 1,320 feet of Hooks’ lease.
    3
    The parties dispute whether, based on the record in this case, the plat was attached to the directional survey
    in the Railroad Commission filing. This does not affect our holding, and we assume without deciding that it was
    attached.
    4
    Although the plat correctly placed the bottom hole within the protected zone, some data on the plat does not
    completely correspond to data on a later correct plat.
    4
    Hooks brought his fraud claims in 2007, alleging that Samson deprived Hooks of
    compensatory royalties by misrepresenting the well’s bottom-hole location and fraudulently inducing
    Hooks to amend the lease and pool. A jury found that Samson committed fraud and statutory fraud,
    awarding more than $20 million in damages on these claims, and the trial court rendered judgment
    on the jury’s verdict. The court of appeals, however, reversed, holding that the four-year statute of
    limitations for fraud barred the claims. 
    Id. at 428–29
    (citing TEX . CIV . PRAC. & REM . CODE
    § 16.004(a)(4)).
    Hooks argues that the court of appeals erred because the statute of limitations did not begin
    to run until Hooks “knew or should have known of facts that in the exercise of reasonable diligence
    would have led to the discovery of the wrongful act.” Exxon Corp. v. Emerald Oil & Gas Co., 
    348 S.W.3d 194
    , 216 (Tex. 2011) (quoting Little v. Smith, 
    943 S.W.2d 414
    , 420 (Tex. 1997)). The jury
    found that, in the exercise of reasonable diligence, Hooks should have discovered Samson’s fraud
    by 2007. Samson responds that, as a matter of law, reasonable diligence would have discovered the
    true location of the well’s bottom hole in 2000 or 2001. Samson points to this Court’s decisions in
    BP America Production Co. v. Marshall, 
    342 S.W.3d 59
    (Tex. 2011), and Shell Oil Co. v. Ross, 
    356 S.W.3d 924
    (Tex. 2011), where reasonable diligence required sophisticated lessors to acquaint
    themselves with “readily accessible and publicly available information” from Railroad Commission
    records. 
    Ross, 356 S.W.3d at 929
    ; see 
    Marshall, 342 S.W.3d at 68
    –69. According to Samson, the
    directional survey and its associated plat, as well as filings showing the original proposed location
    of the well’s bottom hole, should have been discovered by the exercise of reasonable diligence by
    2001 at the latest, meaning that Hooks’ fraud claims are barred by limitations.
    5
    We have long held that “fraud prevents the running of the statute of limitations until it is
    discovered, or by the exercise of reasonable diligence might have been discovered.” Ruebeck v.
    Hunt, 
    176 S.W.2d 738
    , 739 (Tex. 1943).5 Generally, “[c]auses of action accrue and statutes of
    limitation begin to run when facts come into existence that authorize a claimant to seek a judicial
    remedy,” Emerald 
    Oil, 348 S.W.3d at 202
    , but “a person cannot be permitted to avoid liability for
    his actions by deceitfully concealing wrongdoing until limitations has run,” S.V. v. R.V., 
    933 S.W.2d 1
    , 6 (Tex. 1996). Because “fraud vitiates whatever it touches,” Borderlon v. Peck, 
    661 S.W.2d 907
    ,
    909 (Tex. 1983), limitations does not start to run until the fraud is discovered or the exercise of
    reasonable diligence would discover it, 
    Marshall, 342 S.W.3d at 69
    .
    The same rule applies to claims of fraudulent inducement. Fraudulent inducement is a
    subspecies of fraud; “with a fraudulent inducement claim, the elements of fraud must be established
    as they relate to an agreement between the parties.” Haase v. Glazner, 
    62 S.W.3d 795
    , 798–99 (Tex.
    2001). Accordingly, the same principle applies: limitations does not start to run until the fraud with
    respect to the contract is discovered or the exercise of reasonable diligence would discover it.
    5
    See also Emerald Oil, 348 S.W .3d at 216; Marshall, 342 S.W .3d at 68; Computer Assocs. Int’l, Inc. v. Altai,
    Inc., 918 S.W .2d 453, 455 (Tex. 1996); Woods v. William M. Mercer, Inc., 769 S.W .2d 515, 517 (Tex. 1988).
    6
    And just when would reasonable diligence discover the wrong?6 And who decides?
    Although “the date a cause of action accrues is normally a question of law,” Etan Indus., Inc. v.
    Lehmann, 
    359 S.W.3d 620
    , 623 (Tex. 2011) (per curiam), reasonable diligence is an issue of fact,
    Estate of Stonecipher v. Estate of Butts, 
    591 S.W.2d 806
    , 809 (Tex. 1979).7 Nevertheless, in some
    circumstances, we can still determine as a matter of law that reasonable diligence would have
    uncovered the wrong.8 A survey of our decisions reveals the reasons for holding, as a matter of law,
    6
    Hooks and amicus Cardwell, Hart & Bennett, LLP cite cases stating that if there is a fraudulent
    misrepresentation, it is no defense that proper inquiry might have revealed the truth. See, e.g., Buchanan v. Burnett, 119
    S.W . 1141, 1142 (Tex. 1909); Labbe v. Corbett, 6 S.W . 808, 811 (Tex. 1888); Mitchell v. Zimmerman, 
    4 Tex. 75
    , 79–80
    (1849). These cases, however, stand for the general proposition that one may be liable for fraud even if it could be
    discovered by due diligence; they do not hold that limitations is extended even if due diligence would reveal the fraud.
    Also, at least one amicus, Cardwell, Hart & Bennett, LLP, invokes a lessee’s implied covenant to act as a reasonably
    prudent operator. But we held in HECI Exploration Co. v. Neel that “[i]mplied covenants do not dispense with the need
    for royalty owners to exercise due diligence in enforcing their contractual rights, express or implied, within the statutory
    limitations period.” 982 S.W .2d 881, 887 (Tex. 1998).
    7
    See also Shah v. Moss, 67 S.W .3d 836, 846 (Tex. 2001) (“To avoid summary judgment on limitations grounds,
    Moss must have raised a fact issue to support his fraudulent-concealment assertion.”); Hurlbut v. Gulf Atl. Life Ins. Co.,
    749 S.W .2d 762, 766 (Tex. 1987) (“[W ]e agree that whether the plaintiffs knew or should have known of the fraud . . .
    raises a fact issue . . . .”); Borderlon, 661 S.W .2d at 909 (“A fact issue exists whether, in the exercise of reasonable
    diligence, Borderlon knew, or should have known . . . , that the presence of the foreign object in her abdomen gave rise
    to a cause of action against Dr. Peck.”); Cherry v. Victoria Equip. & Supply, Inc., 645 S.W .2d 781, 782 (Tex. 1983)
    (“The ultimate duty to weigh the evidence, determine credibility and decide if fraudulent concealment actually existed
    rests upon the trier of fact.”); Ruebeck, 176 S.W .2d at 740 (“W hat will constitute reasonable diligence to discover fraud
    and when the fraud might have been discovered by the exercise of such diligence are necessarily questions which must
    be determined from all the facts and circumstances in evidence in each particular case. W hen, under the facts in
    evidence, reasonable minds might differ on such issues, the findings of the jury thereon are binding on the appellate
    court.”).
    8
    See, e.g., Etan Indus., 359 S.W .3d at 623 (“On these facts, we hold as a matter of law that the estoppel effect
    of the alleged fraudulent concealment ended in December 2002 at the latest. By that date, the Lehmanns were apprised
    of facts, conditions, and circumstances sufficient to cause a reasonable person to make inquiry that would lead to the
    discovery of the concealed cause of action.”); Ross, 356 S.W .3d at 929 (“Because the Rosses could have discovered
    Shell’s alleged fraud through the use of reasonable diligence, we hold that, as a matter of law, the doctrine of fraudulent
    concealment cannot apply to toll the statute of limitations.”); Marshall, 342 S.W .3d at 69 (“[A]s a matter of law, the
    Marshalls would have been able to discover BP’s fraud through the use of reasonable diligence.”); Kerlin v. Sauceda,
    263 S.W .3d 920, 926 (Tex. 2008) (“As a matter of law, the Ballis could have discovered the existence of any claims
    before limitations expired through the exercise of reasonable diligence.”).
    7
    that the exercise of reasonable diligence would lead to the discovery of the wrong within the
    statutory period.9
    In Shell Oil Co. v. Ross, we considered untimely claims made by Ross—an attorney who
    “understood the oil and gas industry”—and his family that Shell had underpaid gas 
    royalties. 356 S.W.3d at 926
    . Despite Shell’s allegedly fraudulent representations, the Rosses had a duty to “make
    themselves aware of relevant information available in the public record.” 
    Id. at 928.
    We held that
    “[d]iligence is required when claimants have been ‘put on notice of the alleged harm of injury-
    causing actions.’” 
    Id. (quoting Emerald
    Oil, 348 S.W.3d at 207
    ).10 Discrepancies in royalties paid
    to the Rosses on different wells put them on notice. 
    Id. at 929.
    A publicly available price index
    illuminated the underpayments, as did General Land Office records demonstrating that Shell paid
    higher royalties to the State even though it owed the Rosses the same royalty. 
    Id. Had the
    Rosses
    exercised reasonable diligence, this “[r]eadily accessible and publicly available information” would
    have revealed the underpayments. 
    Id. Accordingly, as
    a matter of law, they did not exercise
    reasonable diligence.
    In BP America Production Co. v. Marshall, we held that the statute of limitations was not
    tolled when BP fraudulently represented that it was maintaining continuous operations on a lease.
    9
    Hooks denies relying on the discovery rule or fraudulent concealment. Although fraudulent concealment
    allows the statute of limitations to be tolled for causes of action besides fraud itself, the standard of reasonable diligence
    remains the same: “Fraudulent concealment only tolls the running of limitations until the fraud is discovered or could
    have been discovered with reasonable diligence.” Marshall, 342 S.W .3d at 67. Consequently, cases discussing
    fraudulent concealment are relevant to the meaning of reasonable diligence.
    10
    Samson and Hooks dispute whether parties must be put on notice of potential harm before they have a duty
    to exercise reasonable diligence, as well as whether Hooks was on notice. W e need not reach these questions here.
    Instead, we decide the case by assuming, without deciding, that Hooks should exercise reasonable diligence.
    
    8 342 S.W.3d at 67
    –69. This case also involved a sophisticated plaintiff who “understood the oil and
    gas industry.” 
    Id. at 69.
    The public record contained two public filings with the Railroad
    Commission: a well log and a plugging report that contained “highly technical information.” 
    Id. at 66.
    Had the Marshalls read these two documents together, they would have discovered that BP was
    not conducting good-faith continuous operations. 
    Id. at 69.
    “[A]s a matter of law, the Marshalls
    would have been able to discover BP’s fraud th[r]ough the use of reasonable diligence.” 
    Id. We have
    reached similar conclusions in other cases. For example, if the plaintiff has “actual
    knowledge . . . of injury-causing conduct,” then this “starts the clock on the limitations period”
    “[i]rrespective of the potential effect of fraudulent concealment.” Emerald 
    Oil, 348 S.W.3d at 209
    .
    The availability of court records may indicate under some circumstances that reasonable diligence
    would have found the information. See 
    Kerlin, 263 S.W.3d at 926
    . Land title records and probate
    proceedings create constructive notice, “an irrebuttable presumption of actual notice,” which
    prevents limitations from being delayed. Mooney v. Harlin, 
    622 S.W.2d 83
    , 85 (Tex. 1981);
    Sherman v. Sipper, 
    152 S.W.2d 319
    , 321 (Tex. 1941). These cases reveal that when there is actual
    or constructive notice, or when information is “readily accessible and publicly available,” 
    Ross, 356 S.W.3d at 929
    , then, as a matter of law, the accrual of a fraud claim is not delayed.
    The present case does not fall into any of the categories where we can determine, as a matter
    of law, that reasonable diligence would have timely uncovered the fraud. Though Samson relies
    extensively on Marshall and Ross, Hooks correctly identifies an important distinction: in those cases,
    the public record itself was not tainted by the fraud. We have not previously considered whether
    9
    reasonable diligence would uncover a correct public Railroad Commission filing when more recent
    filings contain false information.
    In December 2000, Samson submitted a plat to the Railroad Commission as part of an
    application to pool. The plat was signed by Glenn Lanoue, Samson’s landman, and dated November
    16, 2000, certifying that it was “a true and correct plat based on the best of my knowledge.” The plat
    had a label stating “Proposed Well Location,” but, unlike some earlier plats in the record, the
    individual data on this plat were not themselves also marked as “proposed.” The plat gave “X” and
    “Y” coordinates for the well’s bottom-hole location, the distance of the well from various survey
    lines, and the well’s surface location along with the bottom hole’s location relative to the surface.
    Trial testimony established that this data is internally consistent, placing the well’s bottom hole more
    than 1,320 feet from Hooks’ lease line even though the well actually bottomed within the 1,320-foot
    protected zone. When Lanoue was asked where he obtained the bottom hole’s distance from the
    survey lines, he testified that he created them himself.11
    Samson later provided a plat with the same information to Hooks in connection with
    Samson’s request to amend the lease and allow pooling. Samson argues the plat was ambiguous and
    indefinite, creating a need for Hooks, an experienced oil and gas lessor, to investigate further. On
    the plat is the notation “1400' ± scaled,” but trial testimony presented different interpretations of
    what points this distance measured between. Elsewhere, the plat expressly states that the bottom-
    hole location is “1400' ± scaled' FEL Unit.” Testimony indicated that “FEL” means “from the
    11
    His deposition testimony was: “I got them from myself.”
    10
    eastern line” of the pooled unit. Another testified that taking the notation literally would be
    unreasonable because if the well truly bottomed about 1,400 feet from the eastern line of the unit,
    as opposed to Hooks’ lease line, it would be very close to Hooks’ lease, perhaps even within it.
    Months earlier, a directional survey performed by an independent surveyor and an
    accompanying plat were filed with the Railroad Commission. Some information on the directional
    survey clearly contradicts the Lanoue plat discussed above, and Samson urges that the information
    on the survey could have easily been used to estimate the bottom hole’s true location. Hooks argues
    that it would take an expert to interpret the survey and pinpoint its location.
    We cannot say that, as a matter of law, Hooks should have discovered the accurate
    information when the more recent filing falsely conveyed that the well had been completed outside
    the protected zone. Although reasonable diligence should examine readily available information in
    the public record, it may stop at more recent filings with the Railroad Commission, without needing
    to double-check more recent filings against earlier filings. This accords with our prior decisions.
    We have held that “fraud vitiates whatever it touches,” 
    Borderlon, 661 S.W.2d at 909
    , in this case,
    the public record. We have held that not all Railroad Commission records create constructive notice,
    HECI Exploration 
    Co., 982 S.W.2d at 886
    , meaning that, in some circumstances, Railroad
    Commission filings may exist that one is not charged with discovering. We have held that fraudulent
    concealment is “an equitable doctrine that . . . is fact-specific.” 
    Marshall, 342 S.W.3d at 67
    . And
    we have held that “a person cannot be permitted to avoid liability for his actions by deceitfully
    concealing wrongdoing until limitations has run.” 
    S.V., 933 S.W.2d at 6
    . Though reasonable
    diligence should lead to information in the public record, here, the fraudulent information itself taints
    11
    the public record. To require, as a matter of law, that Hooks double-check the more recent filings
    against earlier filings is a higher burden than reasonable diligence requires.
    Samson argues that the directional survey is the “gold standard,” and that the fraudulent plat
    was filed to show unit lines for pooling purposes, not to provide the exact location of the well’s
    bottom hole. Samson observes that, in some situations, Texas law mandates directional surveys
    performed by independent surveyors, see 16 TEX . ADMIN . CODE §§ 3.11(c)(2)(A); 3.12 (Tex. R.R.
    Comm’n), and asserts that Hooks should have known this and looked for the survey to establish the
    bottom hole’s true location. Samson also argues that because Lanoue told Hooks the well was about
    1,500 feet from the lease line, but then sent Hooks a plat indicating the bottom hole was about 1,400
    feet away, very close to the protected zone, these inconsistencies should have caused Hooks to
    inquire further. None of these arguments avail. Had Hooks gone to the Railroad Commission, the
    more recent filing would have been a plat with the same inaccurate information, placing the well’s
    bottom hole beyond the protected zone. Hooks is not required, as a matter of law, to double-check
    it against the earlier directional survey. To the extent some information on the Lanoue plat is
    unclear, a careful reader could have examined other information on the plat (e.g., the “X” and “Y”
    coordinates, distances from lease lines, and location of the bottom hole relative to the surface) to
    resolve any ambiguity, determining that the plat placed the bottom hole outside the protected zone.
    Indeed, Hooks presented testimony that this plat clearly placed the bottom hole outside of the
    protected zone. Thus, though Samson’s arguments regarding potential ambiguities on the plat, and
    the availability and superiority of the directional survey, may be appropriate for the factfinder to
    12
    consider when determining whether reasonable diligence would have uncovered the fraud, they do
    not establish that, as a matter of law, Hooks did not exercise reasonable diligence.
    Amicus Texas Oil and Gas Association suggests that holding for Hooks will encourage
    litigants to guise their breach-of-contract claims as fraud claims to avoid the statute of limitations.
    We disagree. To establish fraudulent inducement, “the elements of fraud must be established as they
    relate to an agreement between the parties.” 
    Haase, 62 S.W.3d at 798
    –99. Many breach-of-contract
    cases do not implicate the elements of fraud. Only when fraud is established with regard to the
    contract may fraudulent inducement be established, and, in any case, the suit is based on the fraud
    itself rather than a breach of contract. Moreover, because fraudulent concealment may toll the statute
    of limitations for contract claims, no incentive will exist to recast them as fraud claims.
    We hold that when the defendant’s fraudulent misrepresentations extend to the Railroad
    Commission record itself, earlier inconsistent filings cannot be used to establish, as a matter of law,
    that reasonable diligence was not exercised. Under these circumstances, reasonable diligence
    remains a fact question. The factfinder, no doubt, may consider the failure to examine older records
    when determining whether reasonable diligence was exercised, but their availability is not enough
    to establish that reasonable diligence was not exercised as a matter of law.
    Because the court of appeals mistakenly concluded that the date by which Hooks reasonably
    should have discovered Samson’s fraud was a question of law, it did not reach Samson’s other
    arguments concerning Hooks’ fraudulent inducement claims. 
    See 389 S.W.3d at 428
    –30. These
    include the factual and legal sufficiency of the evidence with regard to common-law fraud, statutory
    fraud, and damages for fraud, as well as the factual sufficiency of the evidence regarding when
    13
    Hooks, by the exercise of reasonable diligence, would have discovered the fraud. We remand these
    issues for the court of appeals’ consideration.
    III. Breach of Most-Favored-Nations Clause Claims
    When an oil and gas lease contains a most-favored-nations clause, it typically provides that
    a lessee who pays higher royalties on nearby leases must pay matching royalties to the lessor under
    the subject lease. Here, all three leases contain an identical most-favored-nations clause, providing
    that
    If Lessee shall enter into an oil and gas lease(s) part of which is located within
    three (3) miles of any exterior boundary of the subject lands covered by the subject
    Lease, hereinafter referred to as “Third Party Lease”, Lessee shall notify Lessor of
    such fact. If the reserved royalty or the amount per acre payable for delay rentals,
    shut-in rentals or minimum royalty, at any time payable under such Third Party
    Lease, is higher than the like royalty and amounts payable as provided in the subject
    Lease, the royalty or amount payable per acre in the subject lease, which is less than
    that provided in the Third Party Lease shall be immediately increased so that it will
    equal the royalty or other amounts payable under the Third Party Lease. The subject
    Lease and the Third Party Lease must be calculated in substantially the same manner,
    such that the comparison of the subject Lease and the Third Party Lease is based on
    the same effective net royalty or other payments, and that same shall include or
    deduct the same types of charges, taxes and other burdens from such interests.
    The trial court determined on summary judgment that Samson breached the clause by paying a higher
    royalty to the State of Texas.
    Samson leased a qualifying oil and gas interest from the State at the same 25% royalty
    Samson paid Hooks. In 2003, to induce the State to consent to a Pooling Agreement, Samson
    increased the State’s royalty. This Pooling Agreement allocates production among different interest
    owners based on their individual shares in their own tracts and the proportion that their tracts play
    in the overall unit. This general allocation is made “provided that the state[’]s unit royalty interest
    14
    shall be 0.7969%.” Considering the size of the State’s tract relative to the size of the entire unit, this
    is equivalent to a royalty of 28.28896% on the production allocated to the State’s tract. In other
    words, the State’s royalty of 0.7969% on production from the unit equates to a 28.28896% royalty
    on production allocated to the State’s tract.
    Samson argues that the most-favored-nations clause does not apply because the clause
    regards the “reserved royalty . . . payable under” another lease, whereas Samson paid the State higher
    royalties under the Pooling Agreement. If the clause were to apply to more than just leases, then it
    would have said so, Samson argues. Samson also asserts that the Pooling Agreement increased the
    State’s allocation of production from the unit without raising the royalty.
    We disagree. To resolve this dispute, we apply the “‘primary legal consequence’ of pooling
    to this case—that production anywhere on a pooled unit is treated as production on every tract in the
    unit.” See Key Operating & Equip., Inc. v. Hegar, 
    435 S.W.3d 794
    , 798–99 (Tex. 2014) (quoting
    Se. Pipe Line Co. v. Tichacek, 
    997 S.W.2d 166
    , 170 (Tex. 1999)). The reason a lessor receives
    royalties under a pooling agreement, even if no production occurs directly on that lessor’s tract, is
    because production elsewhere on the pooled unit is attributed to the lessor’s tract. And the reason
    the lessor receives royalties on production attributed to the lessor’s tract is because of the underlying
    lease. It follows that a lessor’s royalty on production from the unit as a whole reflects the lessor’s
    royalty on production from its individual tracts in proportion to the size of the tracts relative to the
    overall unit. This accords with the nature of pooling, which “effects a cross-conveyance among the
    owners of minerals under the various tracts of royalty or minerals in a pool so that they all own
    undivided interests under the unitized tract in the proportion their contribution bears to the unitized
    15
    tract.” Montgomery v. Rittersbacher, 
    424 S.W.2d 210
    , 213 (Tex. 1968). In other words, the royalty
    owed on production from the whole unit is necessarily tied to the royalty owed on production from
    the lessor’s individual tracts. To increase one is to increase the other.
    Thus, by definition, Samson’s grant of a royalty to the State of 0.7969% on production from
    the unit means that Samson increased the State’s 25% royalty on production from its tract to
    28.28896%. For purposes of the most-favored-nations clause, the royalty imposed by the Pooling
    Agreement is “payable under” the lease, and the Pooling Agreement itself states that it was entered
    into by the State “as Lessor” and Samson “as Lessee.”
    The court of appeals here defined a most-favored-nations clause as “a vendor protection
    clause” that “enables the vendor to receive the benefit of increases in the market price of his product
    over the term of a long range contract with a 
    purchaser.” 389 S.W.3d at 435
    (quoting Lone Star Gas
    Co. v. Howard Corp., 
    556 S.W.2d 372
    , 374 (Tex. Civ. App.—Texarkana 1977), writ ref’d n.r.e., 
    568 S.W.2d 129
    (Tex. 1978) (per curiam)) (emphasis added). Though this may be the purpose of such
    clauses, unless they expressly so provide, we are not authorized to examine whether increased prices
    were caused by market forces or, as seems to be the case here, other considerations. The reason for
    giving the State a higher royalty—inducing it to pool—is irrelevant in determining whether the most-
    favored-nations clause applies.
    For all these reasons, we conclude that the court of appeals erred in holding that Samson did
    not breach the most-favored-nations clause.
    16
    IV. Breach of Formation-Production Clause Claims
    Article III of each lease specifies a 25% royalty on “gas, including casinghead gas or other
    gaseous substances produced from said land,” as well as a 25% royalty on “all other liquid
    hydrocarbons that may be produced from said land.” At the end of Article III, each lease also states
    that
    For the purposes of calculating all royalties payable under Article III. herein, it is
    expressly provided that all such calculations shall be based on formation production
    as reported on Texas Railroad Commission forms P-1 and P-2.
    Hooks claims that Samson has paid gas royalties on proceeds from gas sales rather than on the total
    amount of formation production. Samson disputes Hooks’ interpretation of the formation-production
    clause. The trial court awarded damages for breach of the clause, but the court of appeals 
    reversed. 389 S.W.3d at 437
    .
    “In construing contracts, we must ascertain and give effect to the parties’ intentions as
    expressed in the document.” Lopez v. Muñoz, Hockema & Reed, L.L.P., 
    22 S.W.3d 857
    , 861 (Tex.
    2000). We attempt to harmonize all contractual provisions by “analyzing the provisions with
    reference to the whole agreement.” Frost Nat’l Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 312
    (Tex. 2005) (per curiam). We “construe contracts from a utilitarian standpoint bearing in mind the
    particular business activity sought to be served,” and, when possible and proper, we avoid a
    “construction which is unreasonable, inequitable, and oppressive.” Reilly v. Rangers Mgmt., Inc.,
    
    727 S.W.2d 527
    , 530 (Tex. 1987). If, through the use of relevant rules of construction, the contract
    can be given a definite meaning, we construe it as a matter of law. Frost Nat’l 
    Bank, 165 S.W.3d at 312
    .
    17
    The parties do not dispute the meaning of formation production; rather, they dispute what it
    means to calculate all royalties based on formation production. As used on the old Railroad
    Commission forms P-1 and P-2,12 formation production describes the total volume of gas removed
    from the underground reservoir. Not all gas, however, that leaves the reservoir as gas continues to
    be a gas at the surface; instead, some condenses. “Condensate is hydrocarbons that exist in the form
    of gas when contained in the natural gas reservoir underground, which condense into a liquid form
    when released from the reservoir’s higher pressure and temperature.” Bowden v. Phillips Petroleum
    Co., 
    247 S.W.3d 690
    , 704 n.7 (Tex. 2008). When reporting the total volume of gas removed from
    the reservoir to the Railroad Commission, Samson would convert the volume of condensate at the
    surface to its equivalent volume as a gas.
    Hooks argues that because all royalties must be based on formation production, and
    formation production is the volume of all production while it existed in the reservoir as gas, then the
    25% royalty paid on gas should be for the volume of gas removed from the reservoir instead of the
    volume of gas at the surface. Notably, however, Hooks contends that Samson must still pay a 25%
    royalty on the volume of condensate taken from the wellhead. In other words, Hooks asserts that the
    formation-production clause requires that a 25% royalty be paid on the liquid condensate, which
    must then be converted to its equivalent in gas volume so that another 25% royalty may be paid on
    12
    These forms, referred to by the leases, are no longer used by the Railroad Commission. Instead, Form PR
    has replaced them. According to the instructions accompanying Form PR, “[f]or gas well gas, you no longer need to
    convert the condensate production to a gas equivalent volume; the RRC will automatically convert the volume.” T EX .
    R . R . C O M M ’ N , I N S T R U C T IO N S F O R M P R : M O N T H L Y P R O D U C T IO N R E P O R T , a v a i l a b l e a t
    http://www.rrc.texas.gov/media/2646/formpr-instructions-final-02-2005.pdf.          This opinion need not— and does
    not— interpret “formation production” as used by the new form.
    18
    it again. Samson responds that Hooks’ interpretation unreasonably imposes a double royalty by
    requiring Samson to pay royalties on condensate twice: first as condensate, and then again as a gas
    as part of formation production. Samson submits that the formation-production clause means
    Samson must pay for produced minerals, either as gas or as condensate, but not that Samson must
    pay royalties on condensate twice.
    The formation-production clause provides that all royalty calculations be based on formation
    production. Hooks’ approach, however, causes only gas royalties (for gas as gas and for condensate
    as gas) to be based on formation production. For royalties on condensate as condensate, Hooks’
    approach bases them solely on the amount of condensate without reference to formation production.
    We disagree with that interpretation.
    The formation-production clause simply requires Samson to convert the volume of
    condensate to its equivalent volume in gas, ensuring that the total volume that Samson pays royalties
    on relates to the volume that Samson reports to the Railroad Commission. The conversion ensures
    that Samson pays royalties on an appropriate volume of production, not that Samson pays royalties
    on some production twice. In other words, the clause does not require that royalties be paid on
    everything as gas. Otherwise, the instruction that all royalties be based on formation production
    would be ignored, because royalties would be paid on condensate without reference to formation
    production. This interpretation of the clause, unlike Hooks’, allows royalties on condensate (as well
    as on gas) to be based on formation production, as the leases require.
    Hooks also argues that Samson failed to pay royalties on gas that was not ultimately sold,
    such as lost or consumed gas. Hooks points to the testimony of a Samson employee that Samson
    19
    pays royalties based on dollars received rather than on formation production. But Hooks presented
    no evidence of the royalties that should have been paid on the unsold gas; Hooks merely aggregates
    this amount (if any) with the royalties that Hooks claims are owed on condensate when converted
    back to gas. Absent specific evidence of damages for lost and used gas—as opposed to a combined
    amount for lost and used gas and condensate as part of formation production—Hooks cannot prevail,
    and thus we need not determine whether Samson breached the contract by failing to pay royalties on
    lost and used gas. In sum, we agree with the court of appeals’ decision with regard to the formation-
    production claims.
    V. “Unpooling” Claims
    The two Hardin County Leases authorized Samson to pool. Samson pooled both of Hooks’
    Hardin County Leases into the “Blackstone Minerals ‘A’ No. 1” unit, effective as of the date of first
    production in June 2001. Because the owner of 87.5% of the mineral interest in the tract where the
    well in this unit was located refused to pool, Samson decided to “amend” the unit designation. A
    letter from Samson dated October 24, 2001, notified Hooks of an “Amendment and Name Change
    of Black Stone Minerals ‘A’ No. 1 Unit Designation, Hardin County, Texas”:
    Reference is made to Samson Lone Star Limited Partnership’s letter dated
    March 20, 2001, in which approval to pool on 640-acre plus 10% tolerance was
    received. Please note that the Unit Designation for the Black Stone Minerals “A”
    No. 1 is being amended and will now be called the Joyce Du Jay No. 1 Unit.
    No additional action is needed on your part, this letter is meant for
    informational purposes only. Please update your records with the new name and call
    the undersigned should you have any questions.
    The amended unit was effective in January 2002, when production began.
    20
    As filed in the Hardin County records, the amendment did not merely change the name of
    the existing unit but also significantly altered its boundaries. Whereas the original unit extended
    from a depth of 6,000 feet to a depth of 13,800 feet, the new Joyce Du Jay No. 1 Unit, beginning at
    12,400 feet below surface, extends down without limit. Samson has paid Hooks royalties on
    production from the Joyce Du Jay No. 1 Unit, but not from the original Blackstone Minerals A-1
    Unit. Accordingly, Hooks seeks royalties on the original unit, claiming that Samson did not have
    the authority to “unpool” the Blackstone Minerals A-1 Unit. The trial court agreed, granting
    summary judgment in Hooks’ favor. Samson responds—and the court of appeals held—that Hooks
    ratified the new unit by accepting royalties on it, and therefore cannot recover from the old 
    unit. 389 S.W.3d at 434
    . Samson also asserts that if Hooks is entitled to royalties from the original unit, then
    these should be offset by the royalties Hooks has already received on the Joyce Du Jay No. 1 Unit.
    Notably, Hooks does not question the validity of the Joyce Du Jay No. 1 Unit; rather, Hooks
    alleges that he should receive royalties from both the original unit and the Joyce Du Jay No. 1 Unit.
    Hooks notes that the Hardin County Leases allowed unlimited pooling. Although Samson claimed
    it was “amending” the original unit, Hooks suggests that the change effectively added another unit
    without eliminating the original one.
    Factually, Hooks’ position is problematic. Samson’s letter to Hooks made clear that it
    purported to “amend” the unit designation, not merely create an additional unit. The letter stated that
    it concerned an “amendment and name change,” (emphasis added), so Hooks should have been
    aware that the pooled area could change. The original designation and the amended designation, as
    well as their differences, were a matter of public record. Though Hooks did not know exactly how
    21
    Samson amended the unit designation, Hooks was nevertheless aware that Samson amended it, and
    Hooks regularly accepted royalty checks for the Joyce Du Jay No. 1 Unit without ever receiving
    royalties on the earlier designation. Under these circumstances, Hooks cannot claim additional
    royalties from the older unit because Hooks ratified the amendment, having full knowledge that
    something had changed and by his actions consenting to it, failing even to challenge the new unit.
    See Fortune Prod. Co. v. Conoco, Inc., 
    52 S.W.3d 671
    , 677 (Tex. 2000). Because Hooks does not
    deny the validity of the new unit, one that existed only after Hooks was notified that the old unit was
    being amended, Hooks cannot later assert that he should also receive royalties from the old unit. See
    Ohrt v. Union Gas Corp., 
    398 S.W.3d 315
    , 329 (Tex. App.—Corpus Christi 2012, pet. denied)
    (“Prolonged silence or inaction in not asserting a known right is conduct that may amount to
    waiver.”); see also Bob Montgomery Chevrolet, Inc. v. Dent Zone Cos., 
    409 S.W.3d 181
    , 195 (Tex.
    App.—Dallas 2013, no pet.) (“Any act inconsistent with an intent to avoid a contract has the effect
    of ratifying the contract.”). Because of the undisputed contents of the notice letter, Hooks’
    acceptance of royalties for the new unit, and Hooks’ refusal to challenge the new unit, we decide the
    question of ratification as a matter of law.13
    We base our holding solely on the facts that Hooks received notice of an amendment to the
    unit designation, accepted royalties from the amended unit, and does not challenge the amended unit.
    We need not decide other issues raised by the parties, such as whether Samson had authority to
    13
    See, e.g., Thomson Oil Royalty, LLC v. Graham, 351 S.W .3d 162, 166 (Tex. App.— Tyler 2011, no pet.);
    Barker v. Roelke, 105 S.W .3d 75, 85 (Tex. App.— Eastland 2003, pet. denied); Old Republic Ins. Co. v. Fuller, 919
    S.W .2d 726, 728 (Tex. App.— Texarkana 1996, writ denied).
    22
    amend the unit or whether pooled units may overlap. 
    See 389 S.W.3d at 431
    –33. We affirm the
    judgment of the court of appeals with regard to Hooks’ “unpooling” claims.
    VI. Breach of Hardin County Offset Provision Claims
    Like the Jefferson County Lease, the two Hardin County Leases also contain offset provisions
    requiring that if a well is completed within 1,320 feet of Hooks’ lease line but is not unitized with
    Hooks’ acreage, then within ninety days of production from the infringing well, Samson must either
    drill an offset well, pay Hooks compensatory royalties, or release the offset acreage. Under these
    offset provisions, if Samson elects to pay compensatory royalties, then it has a recurring monthly
    obligation to pay them. The first compensatory royalty would be due “following the expiration of
    ninety (90) days after the end of said calendar month in which production [is] first marketed.”
    The Hardin County Leases allow pooling and also contain what the parties have termed an
    “entire-acreage clause”:
    Operations for drilling on or production of gas from any part of the pooled
    unit which includes all or a portion of the Leased Premises . . . shall be considered
    as operations for drilling on or production of gas from the Leased Premises, . . . and
    the entire acreage constituting such unit or units shall be treated for all purposes,
    except the payment of royalties on production from the pooled unit, as if the same
    were included in this Lease.
    Samson pooled the Hardin County Leases and drilled additional gas wells within 1,320 feet
    of the pooled units but more than 1,320 feet from Hooks’ individual tracts. Hooks argues that the
    entire-acreage clause extended the 1,320-foot protected zone around the units themselves, and that
    Samson breached by disregarding the offset provisions. In the trial court, Samson moved for
    23
    summary judgment on this claim on several grounds, including limitations, which the trial court
    granted. The court of appeals affirmed because of 
    limitations. 389 S.W.3d at 440
    .
    Before analyzing the issue of limitations, we first consider Samson’s argument that Hooks
    waived his claims for breach of the offset provisions by filing a proposed judgment with the trial
    court. In Hooks’ motion for judgment, he averred that he moved for judgment “without waiving any
    rights to contest or appeal prior orders of the Court.” And, the statement “APPROVED AS TO
    FORM” was above Hooks’ attorney’s signature on the proposed judgment. Samson asserts that
    these reservations did not preserve Hooks’ right to appeal, invoking Litton Industrial Products, Inc.
    v. Gammage, where we “disapprove[d] a practice by which a party, by motion, induces the trial court
    on the one hand to render a judgment, but reserves in a brief the right for the movant to attack the
    judgment if the court grants the motion.” 
    668 S.W.2d 319
    , 322 (Tex. 1984). Importantly, Litton
    Industrial Products applies only to arguments inconsistent with the specifics of the requested
    judgment. See 
    id. In contrast,
    when the argument asserted on appeal is not inconsistent with the judgment, the
    argument is not waived. See Diamond Shamrock Ref. Co. v. Hall, 
    168 S.W.3d 164
    , 170 (Tex. 2005).
    This is because “[t]here must be a method by which a party who desires to initiate the appellate
    process may move the trial court to render judgment without being bound by its terms.” First Nat’l
    Bank v. Fojtik, 
    775 S.W.2d 632
    , 633 (Tex. 1989) (per curiam). Here, Hooks specifically reserved
    the right to challenge prior orders of the court, and by moving for judgment on the claims that Hooks
    won, Hooks did not waive his right to appeal on claims that he lost.
    24
    Regarding limitations, Samson argues, and the court of appeals held, that the four-year statute
    of limitations bars Hooks’ claims for breach of the offset provisions because the offset provisions
    were first breached in 2001, at least five years before Hooks filed 
    suit. 389 S.W.3d at 440
    ; see TEX .
    CIV . PRAC. & REM . CODE § 16.004. Hooks responds that compensatory damages under the offset
    provisions are owed monthly, Samson’s breach is recurring, and Hooks can recover damages for
    royalties that should have been paid during the four years preceding the filing of suit. See, e.g., Lyle
    v. Jane Guinn Revocable Trust, 
    365 S.W.3d 341
    , 355 (Tex. App.—Houston [1st Dist.] 2010, pet.
    denied). Samson denies that the breach, if any, has been recurring. Specifically, Samson argues that
    the offset provisions authorized Samson to elect to release the offset acreage or drill an offset well
    or pay compensatory royalties. Samson contends that it is not bound by the recurring provision when
    it could have opted for a non-recurring one, and damages for breach of a non-recurring provision are
    barred by limitations.
    It is true that, “if the terms of an agreement call for periodic payments during the course of
    the contract, a cause of action for such payments may arise at the end of each period.” Intermedics,
    Inc. v. Grady, 
    683 S.W.2d 842
    , 845 (Tex. App.—Houston [1st Dist.] 1984, writ ref’d n.r.e.).14 The
    question remains whether, because the contract gave Samson alternatives that were not recurring,
    Samson may prevent Hooks from suing based on the one recurring obligation. Samson cites a Fifth
    Circuit case holding that when a party refuses to make an election under an alternative contract, the
    14
    See, e.g., Barnes v. LPP Mortg., Ltd., 358 S.W .3d 301, 307 (Tex. App.— Dallas 2011, pet. denied); Lyle, 365
    S.W .3d at 355; Headington Oil Co., L.P. v. White, 287 S.W .3d 204, 214 (Tex. App.— Houston [14th Dist.] 2009, no
    pet.); F.D. Stella Prods. Co. v. Scott, 875 S.W .2d 462, 465–66 (Tex. App.—Austin 1994, no writ); Dvorken v. Lone Star
    Indus., Inc., 740 S.W .2d 565, 567 (Tex. App.— Fort W orth 1987, no writ).
    25
    choice does not devolve to the other party. See Liberty Bank v. Talman Home Mortg. Corp., 
    877 F.2d 400
    , 407 (5th Cir. 1989). The Fifth Circuit held that when the “breaching party had the option
    of choosing between two alternatives at the time of breach, ‘the measure of damages is the loss
    caused by reason of the promisor failing to perform the promise with the lesser value.’” 
    Id. (quoting Stewart
    v. Cran-Vela Rental Co., 
    510 F.2d 982
    , 986 (5th Cir. 1975)). Although Samson has not
    presented evidence of alternative measures of damages, it presumably argues that limitations reduces
    the alternative damages to zero. Hooks responds by citing a decision from 1849, Hemming v.
    Zimmerschitte, where this Court observed that there “does not appear on the record, as presented,
    a manifestation of willingness on the part of the obligor to discharge his obligation; and the right of
    election, if applicable at all, is lost and cannot avail the defendant.” 
    4 Tex. 159
    , 164 (1849). We
    have not addressed the issue since then.
    We need not reach the general issue of the measure of damages for breach of an alternative
    contract. The Hardin County Leases required Samson to begin drilling an offset well or release the
    acreage within ninety days of production from the infringing well. But Samson must pay
    compensatory royalties slightly later—“on or before the first day of the calendar month next
    following the expiration of ninety (90) days after the end of said calendar month in which production
    [is] first marketed.” Assuming that Samson breached, then by waiting without performing the first
    two alternatives, Samson impliedly elected to perform the later one, the only choice remaining after
    the first ninety days had passed. If Samson breached the offset provisions, then Samson’s failure to
    timely elect an alternative creates an implied election of the recurring compensatory royalty
    payments. Accordingly, if Samson did indeed breach, then Hooks is entitled to damages for royalties
    26
    owed within four years of filing suit. This accords with the nature of damages: providing “just
    compensation for the loss or damage actually sustained.” Stewart v. Basey, 
    245 S.W.2d 484
    , 486
    (Tex. 1952). When the law would allow compensation under a recurring alternative (i.e.,
    compensatory royalties) but not under a non-recurring alternative, it would not be just to allow the
    obligor’s silent, continuous breach to constitute an election of the non-recurring alternative.
    The court of appeals held for Samson on limitations and did not reach the merits of Hooks’
    claim for breach of the offset provisions and the proper construction of the entire-acreage clause.
    
    See 389 S.W.3d at 440
    . Because limitations does not apply to the compensatory royalties that may
    have been owed within the four years preceding suit, we remand for the court of appeals to consider
    the merits of Hooks’ claims.
    VII. Attorney’s Fees Claims
    The parties stipulated that if Hooks “prevail[ed] on any of [his] claims” (with exceptions not
    applicable here), Samson would reimburse Hooks for a stipulated amount of attorney’s fees.
    Because Hooks prevailed on several claims in the trial court, the trial court granted Hooks these
    attorney’s fees. The court of appeals, however, held that Hooks take nothing except for $52,257.22,
    a stipulated amount to reimburse Hooks for ad valorem taxes that the leases required Samson to pay.
    
    Id. at 438.
    It also held that reimbursement for the ad valorem taxes did not constitute “prevail[ing]
    on [a] claim[]” as contemplated by the stipulation. 
    Id. Accordingly, the
    court of appeals did not
    require Samson to pay attorney’s fees. 
    Id. We need
    not decide whether the ad valorem taxes trigger Samson’s obligation to pay
    attorney’s fees under the stipulation. Rather, under our decision today, Hooks prevails on another
    27
    claim such that he is entitled to the stipulated amount of fees.15 We reverse the court of appeals on
    this point.
    VIII. Interest Rate Claims
    Hooks seeks, and the trial court granted, a post-judgment interest rate of 18%. Each lease
    provides that “past due royalties . . . shall be subject to a Late Charge based on the amount due and
    calculated at the maximum rate allowed by law.” Because the court of appeals reversed all of
    Hooks’ damages except for compensation for ad valorem taxes, it reduced the interest rate to 5%.
    
    Id. at 439.
    The Texas Finance Code provides for a maximum post-judgment interest rate of 18% on
    contract claims:
    A money judgment of a court of this state on a contract that provides for interest or
    time price differential earns post-judgment interest at a rate equal to the lesser of: (1)
    the rate specified in the contract, which may be a variable rate; or (2) 18 percent a
    year.
    TEX . FIN . CODE § 304.002. But, if the contract does not specify the interest rate, then the rate is
    determined under section 304.003 of the Finance Code. Under section 304.003(c), the post-
    judgment interest rate is “the prime rate as published by the Board of Governors of the Federal
    Reserve System on the date of computation,” not to exceed 15% a year or fall below 5% a year. 
    Id. § 304.003(c).
    “On the 15th day of each month, the consumer credit commissioner shall determine
    the post-judgment interest rate to be applied to a money judgment rendered during the succeeding
    calendar month.” 
    Id. § 304.003(b).
    Here, the trial court’s final judgment was rendered in December
    15
    At the least, Hooks prevails on his claims under the most-favored-nations clause. Other claims, such as fraud
    and breach of the Hardin County offset provisions, are remanded to the court of appeals for further consideration.
    28
    2008, and the judgment interest rate according to the consumer credit commissioner was five
    percent.16
    The leases only impose “the maximum [interest] rate allowed by law” for past-due royalties.
    Accordingly, to the extent Hooks recovers for past due royalties, he is entitled to an 18% interest
    rate. For other recoveries, the statutory rate of 5% applies because Hooks has not directed us to any
    portion of the leases providing otherwise. We affirm in part and reverse in part the court of appeals’
    judgment regarding post-judgment interest rates.
    IX. Conclusion
    In summary, we reverse the court of appeals regarding limitations for fraud, the most-
    favored-nations clause, limitations for breach of the offset provisions in the Hardin County Leases,
    and attorney’s fees. We affirm in part and reverse in part regarding the applicable post-judgment
    interest rate. And we affirm regarding the formation-production and “unpooling” claims. We
    remand to the court of appeals for further action consistent with this opinion.
    _________________________________
    John P. Devine
    Justice
    OPINION DELIVERED: January 30, 2015
    16
    See O FFIC E O F TH E C O N SUM ER C RED IT C O M M ’R , J UD GM ENT R ATE S U M M ARY , available at
    http://www.occc.state.tx.us/pages/int_rates/Judgment%20Rate%20Summaries/Thru%202014% 20Judgment% 20Rate
    %20Summary.pdf.
    29