MKM Engineers, Inc., and Pika International, Inc. v. Jal B. Guzder ( 2015 )


Menu:
  • Reversed and Remanded and Opinion filed November 24, 2015.
    In The
    Fourteenth Court of Appeals
    NO. 14-14-00077-CV
    MKM ENGINEERS, INC., AND PIKA INTERNATIONAL, INC., Appellants
    V.
    JAL B. GUZDER, Appellee
    On Appeal from the 434th Judicial District Court
    Fort Bend County, Texas
    Trial Court Cause No. 07-DCV-155803A
    OPINION
    Appellee Jal B. Guzder sued appellants MKM Engineers, Inc. (“MKM”) and
    PIKA International, Inc. (“PIKA”), seeking to enforce a Rule 11 agreement to
    settle pending litigation. Guzder moved for summary judgment on his breach of
    contract claim, and MKM and PIKA jointly filed a cross-motion for summary
    judgment contending that the Rule 11 agreement was unenforceable. The trial
    court granted a judgment in favor of Guzder. In six issues, MKM and PIKA
    contend that the trial court erred by granting Guzder’s motion for summary
    judgment and denying MKM and PIKA’s cross-motion. We conclude that the
    agreement is enforceable, but fact issues concerning Guzder’s performance under
    the Rule 11 agreement preclude summary judgment in his favor. We reverse and
    remand.
    FACTUAL BACKGROUND
    MKM provides environmental remediation and disposal of unexploded
    munitions to government agencies. Its customers include the United States Army
    Corps of Engineers, the Department of Homeland Security, Defense Reutilization
    Marketing Services, and the Environmental Protection Agency. Khodi Irani is
    MKM’s majority shareholder. MKM was a participant in the Small Business
    Administration’s “Minority Set-aside Program,” also referred to as the “8(a)
    program,” which is designed to help small businesses obtain government contracts.
    Similar to MKM, PIKA is an environmental consultant and remediation firm
    whose primary customers are U.S. government agencies. PIKA also participated in
    the 8(a) program. Tirandaz Kasnavia is PIKA’s owner and Irani’s brother-in-law.
    Guzder owns an environmental remediation consulting company named
    Energy & Environmental Technology Company (“EETCO”). Guzder and EETCO
    initially provided consulting services to MKM, but in 1999, Guzder became an
    officer, director, and 1% shareholder of MKM. In 2002, Guzder sued MKM, Irani,
    and others over his compensation and the case ultimately settled. The settlement
    documents provided that disputes over the agreement would be referred to
    arbitration before the American Arbitration Association (“AAA”).
    In 2005, Guzder sued MKM, Irani, PIKA, and Kasnavia in federal court,
    citing the qui tam provisions of the False Claims Act. See 31 U.S.C. § 3730(b) (the
    “Qui Tam Lawsuit”). Guzder alleged that MKM, Irani, PIKA, and Kasnavia
    fraudulently misrepresented their eligibility for the 8(a) program and submitted
    2
    inflated bid proposals to the government. The U.S. investigated the allegations and
    declined to intervene. On Rule 12(b)(6) grounds, the federal court dismissed
    several of the claims against MKM and Irani, and all of the claims against PIKA
    and Kasnavia. See Fed. R. Civ. P. 12(b)(6). Four claims against MKM and Irani
    remained pending.
    In 2007, Guzder and EETCO filed the present lawsuit in the district court in
    Fort Bend County, contending that MKM and Irani breached the 2002 settlement
    documents (the “Fort Bend Lawsuit”). Guzder also sued Irani’s wife, Parinaz Irani,
    PIKA, Kasnavia, and several members of Kasnavia’s family. The trial court
    ordered Guzder’s and EETCO’s claims against MKM, Irani, and Parinaz to
    arbitration (the “AAA Arbitration”) and stayed the lawsuit as to all other parties
    until the arbitration resolved. In March 2010, less than a month after the federal
    court had dismissed some of Guzder’s claims against MKM and Irani in the Qui
    Tam Lawsuit, Guzder filed another suit related to the 2002 settlement agreement
    against MKM’s former auditor, Suhrid Thakore. Although not parties to that
    lawsuit, MKM, the Iranis, PIKA, and its employees were served with discovery
    requests as third-party witnesses.
    In an attempt to resolve the pending disputes, the parties engaged in
    mediation and settlement conferences. On May 27, 2011, counsel for MKM and
    Irani drafted a letter on their law firm’s letterhead to “memorialize the terms of the
    proposed settlement agreement pursuant to Tex. R. Civ. P. 11.” (the “Rule 11
    Agreement”). Under the Rule 11 Agreement, MKM and PIKA together agreed to
    pay Guzder $1.7 million “to settle fully and finally” the Fort Bend Lawsuit and the
    AAA Arbitration. The Rule 11 Agreement was executed by counsel for Guzder
    same day. PIKA, Kasnavia, and Kasnavia’s family members also signed the
    document.
    3
    Under the Rule 11 Agreement, the parties agreed to execute a “final
    settlement agreement” to include specified material terms, including the exchange
    of mutual releases and payment of the settlement amount. In the proposed releases,
    Guzder, his wife Zenobia Guzder, and EETCO would agree to exchange mutual
    releases with MKM, Irani, PIKA, Kasnavia, and others. The releases would “grant
    a full and final release of any and all claims or potential claims, known or
    unknown, against the respective parties,” except that Guzder would not release
    “any claims against MKM’s outside auditors or accountants, including, but not
    limited to, Suhrid Thakore.” The Rule 11 Agreement further provided that, prior to
    disbursement of the settlement amount, Guzder, Zenobia, and EETCO would agree
    to release all claims asserted by them in the Fort Bend Lawsuit and the AAA
    Arbitration and to dismiss all claims asserted in those lawsuits. Khodi Irani, his
    wife Parinaz Irani, and MKM would agree to release all claims asserted by them in
    the AAA Arbitration and dismiss all claims asserted in that dispute.
    In addition, Guzder would provide (through counsel) notice to MKM and
    PIKA “10 days before filing motions to dismiss the disputes as contemplated
    herein.” After receiving that notice, and prior to the filing of the motions to
    dismiss, MKM and/or PIKA were to wire transfer the settlement amount to
    Guzder’s counsel within 10 days, to be held in trust until the required dismissals
    were entered. If all the actions were not dismissed, then the settlement amount was
    to be returned to MKM and PIKA and any releases provided by the parties would
    automatically be rescinded and ineffective.
    Guzder also agreed to provide a “Side Letter” simultaneously with the
    execution of the final settlement agreement. In the Side Letter, Guzder was to
    memorialize his intent to obtain a dismissal of the Qui Tam Lawsuit and to explain
    “that he no longer wishes to prosecute” that lawsuit.
    4
    Contemporaneously, and before the execution of the Rule 11 Agreement,
    MKM sought confirmation that Guzder would sign a proposed form of the Side
    Letter detailing Guzder’s reasons for dismissing the Qui Tam Lawsuit, including a
    statement that “the evidence developed in the lawsuit does not support the
    allegations of fraud or violations of the False Claims Act made against [Irani] and
    MKM in the Qui Tam Lawsuit.”1 MKM and PIKA wanted the Side Letter with the
    proposed language because they were concerned that Guzder’s allegations in the
    Qui Tam Lawsuit would jeopardize PIKA’s ongoing participation in the 8(a)
    program and MKM’s continued work for governmental entities. Via email,
    Guzder’s counsel confirmed Guzder’s approval of the proposed Side Letter “as
    part of the Settlement Agreement and consistent with our discussions regarding the
    confidentiality provisions.”
    After executing the Rule 11 Agreement, the parties continued to negotiate
    the final settlement documents well beyond the 12-day deadline. From June
    through November 2011, the parties negotiated terms such as the scope and content
    of the releases, confidentiality provisions, covenants not to sue, disclaimers of
    rights, damage caps on suits related to the final settlement agreement, and non-
    disparagement provisions.
    1
    The proposed Side Letter included, among other things, the following language:
    During the six years since filing the Qui Tam Lawsuit, I understand that the
    Government elected not to intervene in the action after its investigation of the
    allegations. I have been integrally involved in discovery in the Qui Tam Lawsuit,
    including specifically in the review of documents provided by your family’s
    and/or MKM’s banks, insurers and accountants, and by other third parties.
    Importantly, I also reviewed the Small Business Administration’s files that the
    agency produced in the lawsuit.
    Based on my assessments regarding the merits of the claims and, in particular, my
    review of information obtained in discovery, explanations provided by
    defendants, the SBA records, and SBA regulations, I have concluded that the
    evidence discovered to date does not support claims against you and MKM for
    fraud against the U.S. Government or violations of the False Claims Act.
    5
    Shortly after the Rule 11 Agreement was signed, and before any final
    settlement documents were executed, Guzder circulated draft dismissal papers for
    the Fort Bend Lawsuit, the AAA Arbitration, and the Qui Tam Lawsuit. On July
    18, Guzder’s counsel gave notice to MKM and PIKA that Guzder intended to file
    the dismissals of the present lawsuit and the AAA arbitration, and stated that the
    notice triggered the Rule 11 Agreement’s provision that the settlement funds were
    to be wired to Guzder’s counsel’s trust account within ten days. MKM and PIKA
    did not wire the funds, however, contending in an August 8 email that the Rule 11
    Agreement was merely a “preliminary agreement to agree” and that Guzder’s
    proposed notice of dismissal of the Qui Tam Lawsuit was premature because the
    terms of a final settlement had not been reached and Guzder had not provided the
    Side Letter. Nevertheless, the parties continued negotiations.
    On September 6, Guzder’s counsel forwarded a signed version of the Side
    Letter that differed substantially from the May 27 version. The entirety of the
    substantive portion of the letter read as follows:
    Based on the settlement memorialized in our Rule 11 Agreement of
    May 27, 2011, I no longer wish to prosecute the Qui Tam Lawsuit. In
    accordance with paragraph 5 and 6 of our settlement, I have complied
    with all terms of the Rule 11 Agreement, including instructing my
    lawyers to communicate my desires to the Department of Justice and
    obtain the government’s consent in the dismissal of my Qui Tam
    Lawsuit, which they have done and which resulted in the Court’s final
    dismissal of the Qui Tam Lawsuit on August 29, 2011.
    Guzder also signed this version as President of EETCO, rather than individually as
    in the May 27 version.
    That same day, Guzder filed a supplemental petition, alleging that MKM and
    PIKA breached the Rule 11 Agreement by failing to fund the settlement ten days
    after Guzder gave notice of his intent to dismiss the pending actions. Guzder also
    6
    sought reasonable attorney’s fees under section 38.001(8) of the Texas Civil
    Practice and Remedies Code. Attached to Guzder’s supplemental petition was a
    copy of the Rule 11 Agreement, which had been filed with the trial court on July
    25.
    After Guzder alleged that appellants had breached the Rule 11 Agreement,
    the parties nevertheless continued to negotiate and exchange drafts, but the parties
    were unable to reach an agreement. In April 2012, Guzder filed a “Motion for
    Summary Judgment to Enforce Rule 11 Settlement.” MKM and PIKA filed
    amended answers and responses to the summary judgment motion. MKM and
    PIKA also jointly filed a cross-motion for summary judgment asserting that the
    Rule 11 Agreement was unenforceable. Guzder responded to the cross-motion. On
    August 29, 2013, the trial court granted Guzder’s motion for summary judgment,
    impliedly denying the cross-motion. Guzder moved for rendition of a final
    judgment, which the defendants opposed because not all parties and claims had
    been addressed or disposed of. Guzder filed a motion for severance.
    On October 22, 2013, the trial court signed a document titled “Interlocutory
    Final Judgment as to Some Parties,” which reiterated its grant of summary
    judgment to Guzder and awarded $1.7 million in damages plus prejudgment
    interest on that amount and attorney’s fees of $260,000. The trial court then
    granted Guzder’s motion for severance. MKM and PIKA jointly filed a motion for
    new trial or to modify the judgment, as well as a request for findings of fact on the
    attorney’s fees issue. Ultimately, the trial court signed a “Modified Final
    Judgment” in Guzder’s favor on January 27, 2014.2 No findings of fact were filed.
    2
    The Modified Final Judgment reflected that the trial court granted in part the motion for
    new trial or motion to modify the judgment and deleted an award of conditional appellate
    attorney’s fees to Guzder, but otherwise did not alter any relief previously awarded.
    7
    SUMMARY JUDGMENT STANDARD OF REVIEW
    We review summary judgments de novo. Mann Frankfort Stein & Lipp
    Advisors, Inc. v. Fielding, 
    289 S.W.3d 844
    , 848 (Tex. 2009). Under the well-
    established standards governing traditional motions for summary judgment, the
    movant must show there is no genuine issue of material fact and he is entitled to
    judgment as a matter of law. Tex. R. Civ. P. 166a(c); Nixon v. Mr. Prop. Mgmt.
    Co., 
    690 S.W.2d 546
    , 548 (Tex. 1985). We take as true all evidence favorable to
    the non-movant, and we indulge every reasonable inference and resolve any doubts
    in the non-movant’s favor. Provident Life & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 215 (Tex. 2003). We review a summary judgment for evidence that
    would enable reasonable and fair-minded jurors to differ in their conclusions. Wal-
    Mart Stores, Inc. v. Spates, 
    186 S.W.3d 566
    , 568 (Tex. 2006) (per curiam).
    When a movant meets that burden of establishing each element of the claim
    or defense on which it seeks summary judgment, the burden then shifts to the non-
    movant to disprove or raise an issue of fact as to at least one of those elements.
    Amedisys, Inc. v. Kingwood Home Health Care, LLC, 
    437 S.W.3d 507
    , 511 (Tex.
    2014. When a party asserts an affirmative defense to defeat a summary judgment,
    it must come forward with evidence sufficient to raise a fact issue on each element
    of at least one of its affirmative defenses. Brownlee v. Brownlee, 
    665 S.W.2d 111
    ,
    112 (Tex. 1984). To prevail on the affirmative defense, the non-movant must prove
    each element of its defense as a matter of law, leaving no issues of material fact.
    See Johnson & Johnson Med., Inc. v. Sanchez, 
    924 S.W.2d 925
    , 927 (Tex. 1996).
    When we review cross-motions for summary judgment, we consider both motions
    and render the judgment that the trial court should have rendered. Coastal Liquids
    Transp., L.P. v. Harris Cty. Appraisal Dist., 
    46 S.W.3d 880
    , 884 (Tex. 2001).
    8
    ANALYSIS OF MKM AND PIKA’S ISSUES
    Appellants MKM and PIKA contend the trial court erred by granting
    summary judgment on Guzder’s breach of contract claim based on the Rule 11
    Agreement and by denying appellants’ cross-motion on the Rule 11 Agreement’s
    enforceability. In support of these contentions, appellants make six principal
    arguments: (1) the Rule 11 Agreement is unenforceable as a matter of law or,
    alternatively, fact issues as to the parties’ intent and the affirmative defense of
    fraudulent inducement preclude summary judgment for Guzder; (2) Guzder failed
    to perform as required to recover for breach of contract; (3) Guzder’s failure to
    perform conditions precedent relieves appellants of the duty to pay Guzder; (4)
    Guzder failed to prove damages of $1.7 million as a matter of law under any
    accepted legal measure; (5) the judgment effectively awarded specific performance
    unilaterally to Guzder even though he never requested that equitable remedy and
    appellants were not awarded anything in exchange for the $1.7 million; and (6)
    Guzder failed to prove as a matter of law that his reasonable and necessary
    attorney’s fee was $260,000.
    I.     The Rule 11 Agreement is an Enforceable Contract
    In their first issue, appellants contend that the trial court erred by granting
    summary judgment in Guzder’s favor and by failing to grant appellants’ motion for
    summary judgment. According to appellants, the Rule 11 Agreement is not
    enforceable as a matter of law because the parties did not intend the Rule 11
    Agreement to be a final settlement agreement and it lacks essential and material
    terms. Consequently, appellants argue, the Rule 11 Agreement is no more than an
    unenforceable agreement to agree and appellants are entitled to summary judgment
    in their favor. Alternatively, appellants contend that genuine issues of material fact
    exist on the enforceability of the Rule 11 Agreement. Finally, appellants contend
    9
    that a fact question exists whether Guzder fraudulently induced appellants into
    signing the Rule 11 Agreement.
    A.    Enforceability of the Rule 11 Agreement
    The trial court granted summary judgment on Guzder’s breach of contract
    claim based on the Rule 11 Agreement purporting to settle the parties’ disputes.
    See Tex. R. Civ. P. 11.3 To prevail on his breach of contract claim, Guzder was
    required to prove: (1) a valid contract existed between Guzder and appellants; (2)
    Guzder tendered performance or was excused from doing so; (3) appellants
    breached the terms of the contract, and (4) Guzder sustained damages as a result of
    appellants’ breach. See WTG Gas Processing, L.P. v. ConocoPhillips Co., 
    309 S.W.3d 635
    , 643 (Tex. App.—Houston [14th Dist.] 2010, pet. denied).
    Rule 11 agreements have long been recognized as “an effective tool for
    finalizing settlements by objective manifestation so that the agreements ‘do not
    themselves become sources of controversy.’” Knapp Med. Ctr. v. De La Garza,
    
    238 S.W.3d 767
    , 768 (Tex. 2007) (quoting Kennedy v. Hyde, 682 S.W 2d 525, 530
    (Tex. 1984)). Courts construe Rule 11 settlement agreements just as they would
    any contract. See Padilla v. LaFrance, 
    907 S.W.2d 454
    , 460 (Tex. 1995); Trudy’s
    Tex. Star, Inc. v. City of Austin, 
    307 S.W.3d 894
    , 914 (Tex. App.—Austin 2010, no
    pet.).
    The intent of the parties to be bound is an essential element of an
    enforceable contract. See Foreca, S.A. v. GRD Dev. Co., 
    758 S.W.2d 744
    , 746
    3
    Rule 11 provides: “Unless otherwise provided in these rules, no agreement between
    attorneys or parties touching any suit pending will be enforced unless it be in writing, signed and
    filed with the papers as part of the record, or unless it be made in open court and entered of
    record.” Compliance with Rule 11 is a threshold requirement for enforceability. Knapp Med. Ctr.
    v. De La Garza, 
    238 S.W.3d 767
    , 768 (Tex. 2007). It is undisputed that the Rule 11 Agreement
    in this case was in writing, signed, and filed with the court.
    10
    (Tex. 1988). A Rule 11 settlement agreement also must contain all the essential
    terms of the settlement. 
    Padilla, 907 S.W.2d at 460
    . Essential or material terms of
    a Rule 11 settlement agreement include payment terms and release of claims. See
    
    id. at 460–61.
    Essential terms are those terms that the parties “would reasonably
    regard as vitally important elements of their bargain.” Potcinske v. McDonald
    Prop. Invs., Ltd., 
    245 S.W.3d 526
    , 531 (Tex. App.—Houston [1st Dist.] 2007, no
    pet.).
    Agreements to enter into future contracts are enforceable if they contain all
    material terms. McCalla v. Baker’s Campground, Inc., 
    416 S.W.3d 416
    , 418 (Tex.
    2013) (per curiam). Thus, a binding settlement may exist when parties agree upon
    some terms, understanding them to be an agreement, and leave other terms to be
    made later. See, e.g., 
    Foreca, 758 S.W.2d at 746
    ; Eastman Gas Co. v. Goodrich
    Petroleum Co., 
    456 S.W.3d 319
    , 326 (Tex. App.—Texarkana 2015, pet. denied);
    Gen. Metal Fabricating Corp. v. Stergiou, 
    438 S.W.3d 737
    , 744 (Tex. App.—
    Houston [1st Dist.] 2014, no pet.). While Texas courts favor validating transactions
    rather than voiding them, a court may not create a contract where none exists and
    generally may not add, alter, or eliminate essential terms. Eastman Gas 
    Co., 456 S.W.3d at 326
    . Generally, the materiality of a contract term is determined on a
    contract-by-contract basis, in light of the circumstances of the contract. 
    Amedisys, 437 S.W.3d at 514
    . A settlement agreement containing all necessary terms is
    enforceable as a matter of law. 
    McCalla, 416 S.W.3d at 416
    .
    (1)   The Parties’ Intent to be Bound
    Appellants argue that the parties did not treat the Rule 11 Agreement as a
    binding contract because it: (1) contemplated a future “final settlement agreement”
    by a date certain; (2) stated the final settlement agreement would include the stated
    terms but did not state that the final agreement’s terms would be restricted to the
    11
    stated terms; (3) did not spell out the terms of the contemplated releases that had
    yet to be drafted; (4) contemplated releases to be signed by persons and entities
    who did not sign it; and (5) was drafted in the future tense, describing numerous
    events to occur in the future rather than simultaneously with its execution.
    Appellants also point to their affidavits controverting Guzder’s assertion of the
    Rule 11 Agreement as a final agreement and assert that this evidence must be
    accepted as true under the summary judgment standard of review.
    The opening line of the Rule 11 Agreement reflects it was prepared “to
    memorialize the terms of the proposed settlement agreement pursuant to Tex. R.
    Civ. P. 11.” The Rule 11 Agreement provides that “[t]he parties understand that the
    primary reason for entering into this agreement is to obtain peace though a
    complete and final resolution of all disputes among them . . . .” Under the Rule 11
    Agreement, MKM and PIKA together agreed to pay Guzder $1.7 million “to settle
    fully and finally” the Fort Bend Lawsuit and the AAA Arbitration. The parties also
    agreed to execute “a final settlement agreement” within twelve days of the
    execution of the Rule 11 Agreement.
    Courts have often “enforced settlement agreements that contemplate
    additional documentation or leave open certain terms for future negotiation.”
    
    Stergiou, 438 S.W.3d at 747
    –48 & n.8 (Tex. App.—Houston [1st Dist.] 2014, no
    pet.) (collecting cases); see also Scott v. Ingle Bros. Pac., Inc., 
    489 S.W.2d 554
    ,
    555 (Tex. 1972) (stating that parties may agree upon certain contractual terms and
    leave other matters for later negotiation). The critical issue for determining
    enforceability when the parties agree that some terms will remain open is whether
    the parties intended for their agreement to be a present, binding agreement in the
    absence of an agreement on the remaining terms or whether they intended their
    agreement to have no legal significance until agreement on the remaining terms is
    12
    reached. 
    Stergiou, 438 S.W.3d at 748
    . Although intent to be bound is generally a
    question of fact, it may be determined as a matter of law. 
    Foreca, 758 S.W.2d at 746
    ; WTG Gas 
    Processing, 309 S.W.3d at 643
    .
    In this case, the document was expressly drafted as a Rule 11 agreement—a
    recognized tool for finalizing settlements—presumably because the parties
    intended to settle their disputes by entering into an enforceable contract. See Knapp
    Med. 
    Ctr., 238 S.W.3d at 768
    . Moreover, the document contains no language
    indicating that it was merely intended as a preliminary, non-binding agreement.
    See John Wood Grp. USA, Inc., 
    26 S.W.3d 12
    , 19 (Tex. App.—Houston [1st Dist.]
    2000, pet. denied) (cautioning that a party who does not wish to be prematurely
    bound by a letter agreement should include a provision clearly stating that the letter
    is nonbinding). Nor does it provide that the parties’ agreement was “subject to” a
    more formal agreement or contain language indicating that certain actions were
    conditions precedent to the agreement’s enforceability. Compare MCRB I Ltd. v.
    Sw. Rail Indus., Inc., No. 14-10-00922-CV, 
    2011 WL 4031023
    , at *3–4 (Tex.
    App.—Houston [14th Dist.] Sept. 13, 2011, no pet.), with Martin v. Martin, 
    326 S.W.3d 741
    , 753–54 (Tex. App.—Texarkana 2010, pet. denied); John Wood Grp.
    
    USA, 26 S.W.3d at 18
    .
    Contrary to appellants’ assertions, the Rule 11 Agreement is not
    unenforceable merely because the parties contemplated taking additional actions
    and executing a final settlement agreement at a later date. And although appellants
    complain that the terms of the releases were not spelled out and had yet to be
    drafted, the Rule 11 Agreement identified the specific parties and claims that
    would be released, as well as the claims to be excluded from the releases.4 The
    4
    Although appellants complain that the Rule 11 Agreement is unenforceable because
    Zenobia Guzder (Guzder’s wife) and EETCO (Guzder’s company) did not sign it, the face of the
    Rule 11 Agreement, as drafted by MKM’s counsel, reflects that it was intended to bind only
    13
    Parties also agreed that Guzder would make certain representations in the Side
    Letter he was to provide contemporaneously with the final documentation.
    Appellants point to nothing in the language of the Rule 11 Agreement that
    conclusively shows that the parties did not intend it to be an enforceable contract
    or that raises a fact issue concerning the parties’ intent to be bound.
    Appellants next assert that the parties’ continued negotiations and other
    conduct after the Rule 11 Agreement’s execution show that the parties did not
    intend to be bound to a settlement contract. Appellants note that for months after
    executing the Rule 11 Agreement, the parties engaged in ongoing negotiations,
    conference calls, and exchanges of drafts over several months. But working toward
    final settlement documents is exactly what the Rule 11 Agreement contemplated
    the parties would do.
    Other conduct of the parties shows that immediately after the Rule 11
    Agreement was signed, the parties took actions consistent with an understanding
    that a binding agreement had been reached. For example, six days after the Rule 11
    Agreement was executed, MKM’s counsel notified the case manager in the AAA
    Arbitration that “the Parties have entered into an agreement to settle this
    proceeding” and requested that the proceeding be abated “while the parties worked
    toward a final, comprehensive settlement agreement.” In December, the parties and
    the court were notified by the AAA that the arbitration proceeding had been
    administratively closed.
    Guzder and appellants also filed a “Joint Notice of Settlement and Request
    for 30-Day Stay” with the federal court in the Qui Tam Lawsuit. Appellants point
    Guzder individually. In part, the document recites, “[i]f the terms of this proposal are acceptable
    to Mr. Guzder, please sign on his behalf below. . . . [T]his offer is available to Mr. Guzder until
    Friday, May 20, 2011 . . .” (emphasis added). Likewise, the signature line provides for Guzder’s
    counsel to sign “on behalf of Jal B. Guzder.”
    14
    out that the notice informed the federal court that a settlement was “pending” while
    the parties were “working toward executing final settlement documents,” and that
    parties were requesting only a stay rather than a dismissal. According to appellants,
    Guzder took these actions because he realized that the parties were still
    contemplating negotiating and signing a final agreement, “which might never reach
    fruition.” However, the notice further informs the court that “[o]n Friday, May 27,
    2011, [the parties’ settlement discussions] culminated in a settlement reflected in
    an Agreement under Texas Rule of Civil Procedure 11.” The evidence also shows
    that the parties requested a stay because several motions were pending and the stay
    allowed Guzder time to notify the government of his intent to dismiss the action.
    On June 10, Guzder circulated to counsel for MKM and PIKA a proposed
    dismissal order filed in the Qui Tam Lawsuit reciting that “[t]he Court . . [has]
    been advised . . . that an amicable settlement has been reached in a related lawsuit
    and [the parties] . . . want to dismiss this action . . . .” MKM’s counsel replied that
    the draft “looks fine to us.” The proposed order was submitted to the federal court,
    with copies to counsel for MKM and PIKA, and signed June 19, 2011. Counsel for
    MKM and PIKA lodged no objection. The order provided for dismissal with
    prejudice as to Guzder and without prejudice as to the government in forty-five
    days from the date of the order (August 4, 2011). After the government consented
    to the dismissal on August 3, the federal judge entered an order formally
    dismissing the Qui Tam case on August 29, 2011.
    Despite acknowledging a settlement in the federal and arbitration
    proceedings, MKM contends that throughout the entire process it “consistently
    communicated its position” that the Rule 11 Agreement was never intended to be
    “the final settlement agreement.” But the issue is not whether the parties intended
    the Rule 11 Agreement to be the final settlement agreement, it is whether they
    15
    intended the Rule 11 Agreement to be a binding contract. Significantly, the first
    time appellants communicated that they believed the Rule 11 Agreement was only
    an unenforceable “preliminary agreement to agree” was on August 8, 2011, after
    the date the Qui Tam Lawsuit was set for automatic dismissal with prejudice as to
    Guzder. Then, one day after the federal court had signed the dismissal order,
    MKM’s counsel communicated his “surprise[]” that the proposed dismissal order
    represented that the parties had reached an agreement, “since the Rule 11 letter was
    nothing more than an agreement to agree.”
    The only earlier communication appellants point to is a July 27, 2011 email
    concerning one of Guzder’s proposed draft settlement documents. In this email,
    MKM’s counsel “note[d]” that the Rule 11 Agreement was not signed by all of the
    parties and expressed disagreement with Guzder’s position that his preparation of
    the dismissal notice in the Qui Tam Lawsuit triggered the settlement funding
    requirement. The email, while critical of Guzder’s proposed draft, did not include
    any indication that appellants did not believe the Rule 11 Agreement was
    enforceable. The timing of appellants’ communications questioning the
    enforceability of the Rule 11 Agreement, coming only after substantial steps had
    been taken by both parties to dismiss the Qui Tam Lawsuit and the AAA
    arbitration, does not raise a fact issue concerning the parties’ intent to be bound.
    Finally, appellants complain that Guzder served MKM and PIKA with
    additional written discovery on the merits of the underlying claims in September,
    and that Guzder sought discovery from them in the Thakore lawsuit, which
    appellants contend they spent thousands of dollars defending from November 2011
    to August 2012. According to appellants, these actions are inconsistent with an
    understanding that the case was settled and show that Guzder knew the Rule 11
    Agreement was not intended to be final, because he knew appellants were
    16
    motivated to obtain peace with respect to all litigation. However, Guzder took
    these actions only after filing the supplemental petition alleging that appellants had
    breached the Rule 11 Agreement.
    We conclude that the language of the Rule 11 Agreement and the
    surrounding circumstances conclusively shows that the parties intended to enter
    into a binding, enforceable agreement even though the parties contemplated
    executing a formal settlement document and taking additional actions at a later
    date. Moreover, because the language unambiguously reflects the parties’ intent to
    be bound, appellants’ affidavits to the contrary may not be considered. See MCRB
    I, Ltd, 
    2011 WL 4031023
    , at *4.
    (2)    Essential and Material Terms
    Appellees also contend that the lack of essential and material terms shows
    the Rule 11 Agreement was not a final agreement. First, appellants argue that the
    Rule 11 Agreement contains no release language, but provides only that full
    releases “will” be provided in the future. Second, appellants argue that Guzder
    never provided the Side Letter in the form negotiated contemporaneously with the
    Rule 11 Agreement. Third, appellants argue that other material terms contemplated
    by the final settlement agreement remained unresolved, including assent to the
    final agreement and execution of comprehensive releases by Zenobia Guzder and
    EETCO, confidentiality provisions, covenants not to sue, disclaimers of rights,
    damage caps on related lawsuits, non-disparagement provisions, and discovery and
    associated costs in related litigation.
    As discussed previously, the Rule 11 Agreement provides that (1) MKM and
    PIKA will pay Guzder $1.7 million to fully and finally settle the Qui Tam Lawsuit
    and the AAA Arbitration, and (2) MKM, PIKA, Guzder, and the other remaining
    individual defendants in the Qui Tam Lawsuit will exchange mutual releases that
    17
    “will grant a full and final release of any and all claims or potential claims, known
    or unknown, against the respective parties.” It also requires Guzder to provide the
    Side Letter containing certain representations when the final settlement agreement
    is executed, which was to occur within 12 days. We conclude that these terms
    constitute the essential and material terms of the parties’ settlement. See, e.g.,
    Cantu v. Moore, 
    90 S.W.3d 821
    , 825 (Tex. App.—San Antonio 2002, pet. denied)
    (holding that settlement agreement contained all material terms when one party
    agreed to pay other party $150,000 and all parties agreed to execute full releases);
    CherCo Props., Inc. v. Law, Snakard, & Gambill, P.C., 
    985 S.W.2d 262
    , 265–66
    (Tex. App.—Fort Worth 1999, no pet.) (settlement agreement including terms of
    payment and a statement that the parties would execute releases contained all
    material terms).
    According to appellants, however, other terms negotiated after the Rule 11
    Agreement was signed remained unresolved, such as confidentiality provisions,
    covenants not to sue, disclaimers of rights, damage caps on suits related to the final
    settlement agreement, non-disparagement provisions, and discovery and associated
    costs in related litigation.5 While these terms may have been important to one party
    or the other, the parties’ failure to resolve their differences concerning other non-
    essential or collateral matters left for future negotiation do not render the Rule 11
    Agreement unenforceable as a matter of law. See 
    Stergiou, 438 S.W.3d at 744
    –45;
    see also E.P. Towne Ctr. Partners, L.P. v. Chopsticks, Inc., 
    242 S.W.3d 117
    , 122
    (Tex. App.—El Paso 2007, no pet.) (“Where the parties have intended to conclude
    a bargain, the agreement’s silence as to non-essential, or collateral, matters is not
    5
    In affidavits, appellants state in a conclusory fashion that they considered such terms
    “material” or “important” or “deal-breakers,” but do not provide any factual basis for their
    statements. Affidavits containing conclusory statements that fail to provide the underlying facts
    to support the conclusion are not proper summary judgment evidence. Nguyen v. Citibank N.A.,
    
    403 S.W.3d 927
    , 931 (Tex. App.—Houston [14th Dist.] 2013, pet. denied).
    18
    fatal.”); West Beach Marina, Ltd. v. Erdeljac, 
    94 S.W.3d 248
    , 259 (Tex. App.—
    Austin 2002, no pet.) (parties need not settle all pending issues for mediated
    settlement agreement to be enforceable, but may agree on certain severable issues,
    while not resolving the entire dispute). Appellants’ companion argument that
    Guzder never provided them with a signed release or a satisfactory Side Letter
    goes to whether Guzder failed to perform under the Rule 11 Agreement, not
    whether the Rule 11 Agreement contains the essential terms of the settlement.
    We conclude that appellants have failed to show that the Rule 11 Agreement
    is unenforceable as a matter of law or that material and genuine fact issues exist
    concerning its enforceability. We therefore hold that the trial court did not err by
    impliedly denying appellants’ summary judgment motion.
    (3)    Fraudulent Inducement
    Finally, appellants contend that a genuine issue of material fact exists as to
    their affirmative defense that Guzder fraudulently induced them into signing the
    Rule 11 Agreement.6 As the non-movants asserting fraudulent inducement as an
    affirmative defense, appellants were required to provide sufficient summary
    judgment evidence to create a fact issue on each element of the defense. See
    
    Brownlee, 665 S.W.2d at 112
    . Fraudulent inducement is a type of fraud claim that
    requires a showing that: (1) a false material misrepresentation was made that was
    either known to be false when made or was asserted without knowledge of its truth
    or falsity, (2) it was intended to be acted on, (3) it was relied on, and (4) it caused
    injury. See Formosa Plastics Corp. USA v. Presidio Eng’rs & Contractors, Inc.,
    6
    Guzder contends that PIKA waived the affirmative defense of fraudulent inducement
    because it neither pleaded nor raised it in its response to Guzder’s summary judgment motion.
    However, PIKA’s response specifically incorporated MKM’s arguments on the issue into its
    response and argued that if the Rule 11 Agreement was unenforceable as to MKM, it was also
    unenforceable as to PIKA. We conclude that the issue is not waived as to PIKA.
    19
    
    960 S.W.2d 41
    , 47 (Tex. 1998). Because appellants point to no evidence to show
    that they suffered any injury from Guzder’s alleged fraudulent inducement of the
    Rule 11 Agreement, they have failed to raise a genuine issue of fact on each
    element of the affirmative defense.
    II.   Fact Issues Exist Concerning Guzder’s Performance
    In their second issue, appellants contend that Guzder failed to perform as
    required to recover for breach of contract. To prevail on his breach of contract
    claim, Guzder was required to prove not only the existence of a valid contract, but
    also to prove he tendered performance or was excused from doing so. See WTG
    Gas Processing, 
    L.P., 309 S.W.3d at 643
    ; Williams v. Unifund CCR Partners
    Assignee of Citibank, 
    264 S.W.3d 231
    , 234 (Tex. App.—Houston [1st Dist.] 2008,
    no pet.). In the trial court, Guzder argued that he performed his part of the Rule 11
    Agreement by: (1) dismissing the Qui Tam Lawsuit; (2) circulating draft dismissal
    papers for the other proceedings; and (3) providing a version of the Side Letter.
    When one party to a contract materially breaches, the non-breaching party
    must elect to either terminate performance or continue performance. Gupta v. E.
    Idaho Tumor Institute, Inc., 
    140 S.W.3d 747
    , 756 (Tex. App.—Houston [14th
    Dist.] 2004, pet. denied). If the non-breaching party treats the contract as
    continuing and demands performance from the breaching party, then the non-
    breaching party must fully perform as well, because the contract continues in force
    for the benefit of both parties. 
    Id. A party
    who elects to treat a contract as
    continuing deprives himself of any excuse for ceasing performance on his own
    part. Long Trusts v. Griffin, 
    222 S.W.3d 412
    , 415–16 (Tex. 2006); 
    Gupta, 140 S.W.3d at 757
    .
    Guzder contends that appellants’ failure to transfer settlement funds to
    Guzder’s counsel within ten days after receiving notice of Guzder’s intent to file
    20
    motions to dismiss the Fort Bend Lawsuit and the AAA Arbitration was a breach
    of the Rule 11 Agreement. Guzder asserts that he provided such a notice on July
    18, 2011, but appellants failed to transfer the funds to Guzder’s counsel by July 28
    or any time thereafter. Assuming this action constituted a breach of the Rule 11
    Agreement, Guzder’s actions after July 28 conclusively demonstrate that he chose
    to treat the alleged agreement as continuing.
    Among other things, Guzder (1) allowed the federal court to sign the order
    dismissing the Qui Tam Lawsuit with prejudice on August 29, 2011, even though
    appellants allegedly breached the Rule 11 Agreement a month earlier; (2)
    continued negotiating and exchanging drafts for the “final settlement agreement”
    terms through November 2011; (3) provided a version of the Side Letter on
    September 6, 2011; (4) demanded performance from MKM and PIKA as late at
    October 2011; and (5) requested confirmation in November 2011 that appellants
    had transferred the settlement funds to their counsel. Because Guzder elected to
    continue performance under the Rule 11 Agreement, he was required to show that
    he fully performed under the contract. See 
    Gupta, 140 S.W.3d at 757
    –58 (holding
    non-breaching party’s failure to perform not excused).
    Appellants contend that Guzder failed to perform because, among other
    things, he never provided a Side Letter with the previously agreed text. As
    discussed above, before execution of the Rule 11 Agreement, MKM’s counsel sent
    a proposed form of the Side Letter, asking Guzder’s counsel to confirm that it
    would be signed by Guzder “in satisfaction of Paragraph 5 of the Rule 11
    Agreement.” Guzder’s counsel confirmed that the proposed Side Letter was
    “approved pursuant to paragraph 5 of the Rule 11 Agreement, as part of the
    Settlement Agreement and consistent with our discussions regarding the
    confidentiality provisions.” The version of the Side Letter Guzder provided to
    21
    appellants on September 6, 2011 tracks the Rule 11 Agreement by stating, in
    relevant part, that Guzder “no longer wish[es] to prosecute the Qui Tam Lawsuit.”
    However, this version omits the substantive language confirming the Qui Tam
    Lawsuit’s lack of factual and legal support, and is not signed by Guzder
    individually. Appellants maintain that they never would have signed the Rule 11
    Agreement without Guzder’s agreement to the form of the Side Letter previously
    approved by Guzder’s counsel.
    Both Irani and Kasnavia submitted affidavits in opposition to Guzder’s
    motion for summary judgment in which they explained the significance of
    obtaining a Side Letter. In his affidavit, Irani stated that that he informed Guzder’s
    counsel that a Side Letter was essential to any settlement to “help alleviate any
    concerns raised by clients or potential clients arising from Mr. Guzder’s false
    accusations that MKM committed fraud against the government.” Further, Irani
    stated he would not have agreed to the Rule 11 Agreement if Guzder or his counsel
    did not agree to execute and deliver the agreed-upon Side Letter, and he agreed to
    execute the Rule 11 Agreement only after Guzder’s counsel agreed to the form and
    language of the Side Letter. Kasnavia also stated that he wanted the Side Letter
    from Guzder for the purpose of “vindicating me and [PIKA] from serious
    allegations, including fraud,” and that without such a letter, neither he nor PIKA
    would consider the matter fully and finally resolved.
    Guzder forwarded the allegedly non-conforming version of the Side Letter
    to appellants on September 6, 2011. About two weeks later, Guzder’s counsel sent
    an email to counsel for Irani and MKM in which he expressed dismay at perceived
    delays and insisted on “receiv[ing] a firm commitment from your client as to what
    he will sign along with confirmation of funding before we can even begin to
    commit to anything related to the side-letter” (emphasis added). Guzder did not
    22
    provide any other signed version of a Side Letter.
    In his brief, Guzder argues that his counsel did not unqualifiedly approve the
    proposed May 27, 2011 Side Letter. Instead, he argues that his counsel conveyed
    that the draft was satisfactory “if it ultimately included, or was made subject to,
    confidentiality provisions.” Further, Guzder states that “[c]onfidentiality was
    required because the draft included statements in addition to those provided for by
    paragraph 5 of the Rule 11 Agreement.” But, Guzder’s approval of the proposed
    language was not expressly made “subject to” any confidentiality provision, and
    the proposed Side Letter’s text contained no confidentiality provisions. Instead,
    Guzder’s counsel confirmed approval of the proposed language “consistent with
    our discussions regarding the confidentiality provisions.” Because counsel
    “confirmed” that Guzder “approved” appellants’ proposed Side Letter, but did so
    with reference to the proposed Side Letter being “consistent” with discussions
    concerning unidentified confidentiality provisions, we conclude that genuine issues
    of material fact exist concerning whether counsel’s email constituted a
    representation that Guzder unqualifiedly agreed to the Side Letter terms proposed
    by appellants, and thus whether Guzder performed his obligation under the Rule 11
    Agreement to provide the Side Letter when he presented appellants with the
    September 6 version.
    Because we conclude that genuine issues of material fact exist concerning
    Guzder’s performance of his obligation to provide a Side Letter under the Rule 11
    Agreement, we hold that the trial court erred by granting Guzder’s motion for
    summary judgment.7
    7
    Because fact issues exist concerning Guzder’s performance require that the case be
    reversed and remanded, it is unnecessary to consider whether, as appellants assert, Guzder failed
    to fully perform his obligations to provide releases and to dismiss all clams in all proceedings,
    not merely the Qui Tam Lawsuit.
    23
    Conclusion
    We hold that the Rule 11 Agreement is an enforceable agreement, and
    therefore the trial court did not err by impliedly denying appellants’ motion for
    summary judgment on enforceability. However, genuine issues of material fact
    exist concerning Guzder’s performance of his obligations under the Rule 11
    Agreement that preclude summary judgment in his favor on his breach-of-contract
    claim. We therefore reverse the trial court’s judgment and remand the case for
    further proceedings consistent with this opinion.
    /s/    Ken Wise
    Justice
    Panel consists of Justices Christopher, Donovan, and Wise.
    24
    

Document Info

Docket Number: 14-14-00077-CV

Filed Date: 11/24/2015

Precedential Status: Precedential

Modified Date: 9/29/2016

Authorities (20)

Provident Life & Accident Insurance Co. v. Knott , 47 Tex. Sup. Ct. J. 174 ( 2003 )

Cherco Properties, Inc. v. Law, Snakard & Gambill, P.C. , 1999 Tex. App. LEXIS 563 ( 1999 )

Long Trusts v. Griffin , 50 Tex. Sup. Ct. J. 209 ( 2006 )

Williams v. Unifund CCR Partners Assignee of Citibank , 2008 Tex. App. LEXIS 931 ( 2008 )

Martin v. Martin , 326 S.W.3d 741 ( 2010 )

Johnson & Johnson Medical, Inc. v. Sanchez , 924 S.W.2d 925 ( 1996 )

West Beach Marina, Ltd. v. Erdeljac , 2002 Tex. App. LEXIS 8539 ( 2002 )

Cantu v. Moore , 2002 Tex. App. LEXIS 6431 ( 2002 )

Formosa Plastics Corp. USA v. Presidio Engineers and ... , 960 S.W.2d 41 ( 1998 )

Gupta v. Eastern Idaho Tumor Institute, Inc. , 2004 Tex. App. LEXIS 5383 ( 2004 )

John Wood Group USA, Inc. v. Ico, Inc. , 26 S.W.3d 12 ( 2000 )

Brownlee v. Brownlee , 27 Tex. Sup. Ct. J. 259 ( 1984 )

WTG Gas Processing, L.P. v. ConocoPhillips Co. , 2010 Tex. App. LEXIS 1872 ( 2010 )

Scott v. Ingle Bros. Pacific, Inc. , 16 Tex. Sup. Ct. J. 145 ( 1972 )

Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding , 52 Tex. Sup. Ct. J. 616 ( 2009 )

TRUDY'S TEXAS STAR, INC. v. City of Austin , 2010 Tex. App. LEXIS 1760 ( 2010 )

E.P. Towne Center Partners, L.P. v. Chopsticks, Inc. , 2007 Tex. App. LEXIS 9001 ( 2007 )

Potcinske v. McDonald Property Investments, Ltd. , 245 S.W.3d 526 ( 2007 )

Wal-Mart Stores, Inc. v. Spates , 49 Tex. Sup. Ct. J. 373 ( 2006 )

Knapp Medical Center v. De La Garza , 51 Tex. Sup. Ct. J. 105 ( 2007 )

View All Authorities »