Nichols v. Dixon , 99 Tex. 263 ( 1905 )


Menu:
  • The question before us concerns the proper distribution, among Nichols and other materialmen, of a small sum of money in the hands of Dixon, as the balance due upon a contract between him and one Hawkins for the construction of a building upon the homestead of Dixon and wife. We have concluded that the appeal was rightly decided in the Court of Civil Appeals, and shall discuss the question alone upon which the writ of error was granted.

    The contract for the improvement between Dixon and Hawkins was concluded January 2, 1902, and was duly filed for record January 9, 1902, the stipulated price being $3,800.00. After the completion of the improvement, there remained in the hands of Dixon, subject to the claims of materialmen entitled to claim interests in it, the sum of $513.90, and the proper distribution of this among the several claimants is the question now before us. The facts upon which its decision depends are the following:

    The Texas Builders' Supply Company, in January, February and March, 1902, furnished to Hawkins, to be used in the building, material, the balance due on the price of which amounts to $280.00. On March 21, 1902, that company gave the statutory notice of this claim. At that time there remained unpaid of the contract price of the improvement $1,044.99. Of this, Dixon properly paid out, prior to 5 o'clock P.M., April 30, 1902, the sum of $531.09, leaving on hand only *Page 267 $513.90. The Texas Builders' Supply Company, after giving the notice just stated, sold other material to Hawkins of the value of $121.00, but gave no notice thereof to Dixon; and on May 10, 1902, filed its claim of lien for the whole amount due from Hawkins — $401.00. Nichols, the plaintiff in error, sold to the contractor, Hawkins, at the following several dates, material used in the house of values stated, viz., February 12, 1902, $693.00; March 2, 1902, $70.81; and April 3, 1902, $70.00. He gave no statutory notice to Dixon of the sales to Hawkins until 5 o'clock p.m. of April 30, 1902, when he filed his claim in accordance with the statute to fix his lien. R.E. Wortham did work upon the building of the value of $65.00, but gave no notice to Dixon of his claim until May 16, and did not file his lien until May 31, 1902. The district court held that, out of the sum remaining in Dixon's hands, the claim of the Texas Builders' Supply Company for $280.00, of which notice was regularly given to Dixon March 21, should be paid in full; and that the balance of the fund should be applied ratably to the other claim of that company, of which no notice had been given, and those of Nichols and Wortham. Nichols alone appealed, and, upon the judgment being affirmed by the Court of Civil Appeals, prosecuted this writ of error.

    As Nichols is the only person complaining of the judgment below, the only question for decision is whether or not all that he was entitled to claim was allowed him. He claims, among other things, that under art. 3310, Rev. Stat., his claim stood upon an equal footing with the others, and that the priority given by the judgment to the claim of the Texas Builders' Supply Company is wrong. The article referred to is as follows: "The liens for work and labor done or material furnished, as provided in this chapter, shall be upon an equal footing, without reference to date of filing the account of lien; and in all cases, when a sale shall be ordered and the property sold, which may be described in any account of lien, the proceeds arising from such sale, if not sufficient to discharge all the liens against the same, without reference to the date of filing the account or lien, shall be paid pro rata on the respective liens; provided, such accounts or liens shall have been filed and suit brought as provided by this law; provided that nothing in this law shall be so construed as in any manner affecting the contract between said owner and original contractor as to the amount, manner or time of payment of said contract price." Equality is here given only to such liens as have been filed "as provided by this law," and Nichols can only secure it by showing that he has done that which the statute required. By art. 3296, it is provided that a person who may furnish material to a contractor, by giving written notice to the owner of each and every item furnished, and by showing how much there is due and unpaid on each bill of material furnished, at any time within ninety days after the indebtedness shall have accrued, may fix and secure the lien by filing in the office of county clerk an itemized account of his or their claim, etc. Art. 3298 prescribes a form of affidavit to be substantially followed in filing the lien, in the latter part of which the statement is required that the claimant "has given to the owner, etc., notice in writing of each item of said account, as required *Page 268 in art. 3296, as the same was furnished" to the contractor. The arrangement of the different clauses in art. 3296 might leave some doubt whether the ninety days' provision applied to the notice, or to the filing of the claim with the county clerk, or to both; but art. 3298 makes it plain that the time limitation refers to the filing, and that the notice is to be given as the material is furnished. In one of the provisions of art. 3308 is also found the requirement, with reference to material furnished for the improvement of a homestead, that "a copy of each bill of lumber furnished to the contractor or builder, as the same is furnished, shall be delivered to the owner of said homestead." A somewhat different rule is prescribed by art. 3305 to govern a different class of persons from that to which Nichols belongs. It thus appears that, in order for such a claimant as Nichols to have filed his lien "as provided by this law," he must have given the notice prescribed by arts. 3296, 3298 and 3308, and in filing his claim must have made affidavit to the giving of such notice; and it follows that, if he has omitted to do this, he is excluded by the first proviso in art. 3310 from the equality declared by the first part of that article. The reason for this is apparent. If all furnishers of material, as it is furnished, give the prescribed notice to the owner of the property, and then file their liens in the prescribed time, they have done all the statute requires, and have been equally diligent in their efforts to secure payment out of the price to be paid for the improvement, and hence are put upon an equality in the distribution. But as the owner may, so long as he receives no such notices, pay money to the contractor, and can not, under the provisions of arts. 3296, 3308 and 3310, be made liable for sums thus paid, the fund out of which such claims are to be secured may be diminished through the fault of those who delay giving the notice; and when, from such a cause, there is left in the hands of the owner a sum insufficient to pay all unpaid claims, it would be unjust for those from whose lack of diligence the diminution occurred to participate equally with those who gave the notice in time to secure their claims. That this was not intended, is apparent from the first proviso in art. 3310; and it follows that equality is not given by that article.

    But the Texas Builders' Supply Company did not comply strictly with the statute, in that it did not give notice of the items of its bills as the material was furnished, and it may be said that it is in no better position than the plaintiff in error. We think this may be met by the decisions of this court as to the purpose of the notice. The notice is required in order that the owner may withhold from the contractor moneys that should be paid to those furnishing him with material. This purpose is met if notice is given while the owner still has enough of the contract price to pay the claim, and when neither he nor any one else interested has been prejudiced by the delay, provided, of course, the lien of such a claimant is eventually asserted as the law permits. Johnson v. Amarillo Imp. Co., 88 Tex. 512. Under this principle the Texas Builders' Supply Company, by giving notice of its claim for $280.00, and fixing its lien at a time when Dixon had in his hands largely more than enough to pay it, and when no other claims had been presented, secured the right to have the owner withhold that sum *Page 269 from the contractor. If Dixon had then paid this claim, he would have been completely protected by art. 3308, and no one could have complained. The question whether or not, since it was not paid, but the amount remains in his hands, if others subsequently furnishing material had complied strictly with the law they could have secured the right under art. 3310 to equal participation, is not before us, and we express no opinion on it. Nichols does not occupy such a position. By far the larger part of his claim had already accrued, and he gave no notice of either that or of the part subsequently accruing; and in consequence of his neglect, the owner afterwards rightly paid out the larger portion of the amount held by him at the time he received notice from the other claimant.

    An equal distribution of the fund on hand would either require the Texas Builders' Supply Company to lose a part of that which it thus, by its diligence, held in the hands of Dixon to pay its own claim, by yielding it to another who, by his failure to comply with the statute, has allowed other sums to pass beyond his reach, or else require Dixon, in order to make the Company whole, to pay back a part of the money paid out by him when he had received no notice of other claims, and when he had reserved more than enough to pay the claim of which he had notice. The latter result is plainly forbidden by the statute, and the first would be obviously unjust and unauthorized by law. The equality provision of the statute applies, as we have seen, only between those lienors who have complied with the statute, and stand upon the same plane as to diligence.

    The plaintiff in error has no just cause to complain of the judgments.

    Affirmed.