San Jacinto River Authority v. City of Conroe, Texas and City of Magnolia, Texas ( 2024 )


Menu:
  •           Supreme Court of Texas
    ══════════
    No. 22-0649
    ══════════
    San Jacinto River Authority,
    Petitioner,
    v.
    City of Conroe, Texas and City of Magnolia, Texas,
    Respondents
    ═══════════════════════════════════════
    On Petition for Review from the
    Court of Appeals for the Ninth District of Texas
    ═══════════════════════════════════════
    Argued January 9, 2024
    JUSTICE BUSBY delivered the opinion of the Court.
    These parties to water sales contracts are before the Court for a
    second time. Unlike a typical contract dispute, all the parties here are
    government entities with immunity from suit. So far, their taxpayers
    and ratepayers have been funding only procedural and jurisdictional
    skirmishes distantly related to the merits of the dispute.
    Today’s legal skirmish concerns the scope of the statutory waiver
    of immunity for contractual claims against local government entities.
    The contracts at issue obligate two cities to buy surface water from a
    river authority. When a dispute over fees and rates arose, the cities
    stopped paying their complete balances, and the authority sued the
    cities to recover those amounts. The trial court granted the cities’ plea
    to the jurisdiction, and the court of appeals affirmed on the ground that
    the authority did not engage in pre-suit mediation as the contracts
    required.
    We hold that contractual procedures for alternative dispute
    resolution, which are enforceable against local governments under
    section 271.154 of the Local Government Code, do not serve as limits on
    the waiver of immunity set out in section 271.152. Nor does the parties’
    agreement to mediate apply to the authority’s claims. We also reject the
    cities’ alternative position that the agreements do not fall within the
    waiver because they fail to state their essential terms. Accordingly, we
    reverse and remand to the trial court for further proceedings to resolve
    the authority’s claims on the merits.
    BACKGROUND
    As we explained in more detail in our last opinion involving these
    parties,    the   Legislature   created   the   Lone   Star   Groundwater
    Conservation District to address concerns about the growing population
    in Montgomery County and that region’s reliance on groundwater. See
    City of Conroe v. San Jacinto River Auth., 
    602 S.W.3d 444
    , 448 (Tex.
    2020). Lone Star developed a Regulatory Plan to reduce groundwater
    usage.     The Regulatory Plan encourages water providers to work
    together     to   reduce   groundwater    usage,   establishes   goals   for
    groundwater use reduction, and requires water providers to report on
    their groundwater use.       Under the Regulatory Plan, Lone Star set
    2
    groundwater pumpage limits for all high-volume groundwater users in
    Montgomery County, including cities and other utilities.
    Petitioner San Jacinto River Authority (SJRA), a preexisting
    entity, developed a groundwater reduction plan (GRP) to draw surface
    water from Lake Conroe—which it controls—and sell the water to cities
    and utilities to help them comply with Lone Star’s Regulatory Plan.
    SJRA invited all water providers in Montgomery County to participate
    so that they could share the costs and benefits of transitioning from
    groundwater use to surface water use. Under the GRP, SJRA would
    design, construct, and operate a treatment plant and related systems,
    which it would finance by issuing over $550 million in bonds.
    Many cities and utilities within Lone Star’s district, including
    Respondents Conroe and Magnolia, opted to join the GRP and signed
    decades-long contracts with SJRA.        These GRP contracts secured
    SJRA’s outstanding bonds.        By entering into the contracts, the
    participants sought to reduce the overall cost of complying with Lone
    Star’s Regulatory Plan while obtaining favorable financing terms.
    Certain features of the GRP contracts are in dispute. As relevant
    here, these features include: procedural and substantive requirements
    that SJRA must follow in setting the price of water, limits on SJRA’s
    authority to set the quantity of water a municipality or utility must take,
    and procedures for handling different types of defaults.        The GRP
    contracts provide that a “payment default” occurs when any party “fails
    to timely pay any fees, rates, charges, or other amounts due” under the
    GRP contracts. A “performance default” occurs when any party “fails to
    perform or is in breach or violation of any of its other obligations” under
    3
    the GRP contracts.     The contracts require the parties to engage in
    pre-suit mediation for performance defaults but not payment defaults.
    SJRA began supplying water under the GRP contracts in 2015.
    Conroe received water from SJRA, but Magnolia did not. Conroe paid
    for the surface water it took from SJRA, and both it and Magnolia paid
    “pumpage fees” as required by their GRP contracts.             When SJRA
    increased both water rates and pumpage fees in 2017, Conroe and
    Magnolia (collectively, the Cities) objected. The Cities have short-paid
    SJRA—refusing to pay the new higher rates or fees—ever since. See
    Conroe, 602 S.W.3d at 449-450.
    Meanwhile, several utilities and cities sued Lone Star and its
    officials, seeking to invalidate the Regulatory Plan that had motivated
    the GRP contracts. The trial court in that case signed a final judgment
    invalidating the pumpage limits contained in the Regulatory Plan,
    concluding that the limits were made “without legal authority and
    consequently [were] . . . unlawful, void, and unenforceable.” But the
    trial court left the remainder of the Regulatory Plan in place.1
    As for the GRP contracts, SJRA initially responded to the Cities’
    partial refusal to pay by suing them in Travis County under the
    Expedited Declaratory Judgments Act, which resulted in the parties’
    first visit to this Court in 2020. Id. at 450. We held that SJRA could
    1The parties to the Lone Star suit reached a settlement while the case
    was on interlocutory appeal. See Lone Star Groundwater Conserv. Dist. v. City
    of Conroe, No. 09-18-00383-CV, 
    2019 WL 611519
     (Tex. App.—Beaumont Feb.
    14, 2019, no pet.) (dismissing appeal due to settlement). The final judgment
    was the product of that settlement. No issues regarding the validity of the
    Regulatory Plan are before us.
    4
    obtain declarations regarding the valid execution of the GRP contracts
    but not regarding compliance with those contracts. 
    Id. at 448, 458-59
    .
    While that suit was pending, several private utilities sued SJRA
    in Montgomery County for breach of GRP contracts. SJRA brought
    counterclaims against the utilities and third-party claims against the
    Cities, alleging they breached the contracts by failing to pay the required
    rates and fees.
    The Cities then filed the pleas to the jurisdiction at issue here,
    arguing that their immunity had not been waived under the Local
    Government Contract Claims Act (the Act)—sections 271.151 through
    271.160 of the Local Government Code—for two reasons: SJRA failed to
    submit its claims to pre-suit mediation, and the GRP contracts failed to
    state their essential terms. The trial court ordered the parties to confer
    regarding mediation, but no party asked the court to order mediation.
    The court eventually granted the pleas and dismissed SJRA’s claims
    against the Cities, though without ordering a severance.
    SJRA filed an interlocutory appeal, and the court of appeals
    affirmed. The court held that the waiver of immunity in section 271.152
    of the Act is limited by section 271.154, which provides that dispute
    adjudication procedures stated or incorporated in the contract are
    enforceable, and that immunity was not waived because SJRA failed to
    engage in pre-suit mediation as required by the GRP contracts. The
    court did not reach the issue of essential terms. 
    683 S.W.3d 1
    , 12-13
    (Tex. App.—Beaumont 2022). SJRA then filed a petition for review,
    which we granted.
    5
    ANALYSIS
    SJRA raises three issues in its petition. First, it argues that
    contractually agreed procedures for adjudicating disputes, such as the
    pre-suit mediation requirements in the GRP contracts, do not limit the
    Act’s waiver of a local government entity’s immunity. Second, SJRA
    contends that its claims are not covered by the contracts’ pre-suit
    mediation requirements. Third, SJRA asserts that the GRP contracts
    state their essential terms, so the Act’s waiver of governmental
    immunity applies. We address each issue in turn. Because these issues
    concern whether governmental immunity has been waived, we review
    them de novo. Fraley v. Tex. A&M Univ. Sys., 
    664 S.W.3d 91
    , 97 (Tex.
    2023).
    I.       Contractual adjudication procedures made enforceable by
    section 271.154 are not limitations on section 271.152’s
    waiver of immunity.
    Governmental    units,   including   political   subdivisions   like
    municipalities and river authorities, are generally immune from suit
    absent a legislative waiver. City of San Antonio v. Maspero, 
    640 S.W.3d 523
    , 528 (Tex. 2022). Whether governmental immunity has been waived
    in a given case implicates subject-matter jurisdiction. Univ. of Tex. M.D.
    Anderson Cancer Ctr. v. McKenzie, 
    578 S.W.3d 506
    , 512 (Tex. 2019). In
    response to SJRA’s claims under the contracts, the Cities filed pleas to
    the jurisdiction asserting that their governmental immunity has not
    been waived. We begin our analysis by considering the Cities’ argument
    that contractual dispute-resolution procedures made enforceable by
    6
    section 271.154 of the Act limit the scope of the immunity waiver in
    section 271.152.
    A.     When section 271.152 waives immunity for
    adjudicating a claim, section 271.154 provides that
    the waiver includes enforcement of agreed
    procedures for that adjudication.
    The Act’s waiver of immunity for certain breach-of-contract suits
    against local government entities “alter[ed] decades of one-sided
    bargains, in which local governments were wholly immune from
    breaches of their obligations.” San Antonio River Auth. v. Austin Bridge
    & Rd., L.P., 
    601 S.W.3d 616
    , 625 (Tex. 2020). Section 271.152 provides
    that when a local government entity authorized to make contracts—
    including a city or a river authority—“enters into a contract” for goods
    or services that meets certain requirements, that entity “waives
    sovereign immunity to suit for the purpose of adjudicating a claim for
    breach of the contract, subject to the terms and conditions of [the Act].”
    TEX. LOC. GOV’T CODE § 271.152 (emphasis added); see id. § 271.151(2),
    (3) (defining which contracts and local government entities are covered).
    In situations where this waiver applies, section 271.154 recognizes that
    the parties may state or incorporate in their contract “[a]djudication
    procedures”—that is, procedures for adjudicating the breach-of-contract
    claim expressly permitted by section 271.152—and provides that those
    procedures generally “are enforceable” by a court or arbitrator.
    Id. § 271.154.
    In effect, the Act establishes an order of operations: if the waiver
    of immunity in section 271.152 applies to the claim for breach of
    contract, then the contractual procedures for adjudicating that claim
    7
    referenced in section 271.154 are enforceable. This understanding is
    supported by our opinion in Zachry Construction Group v. Port of
    Houston Authority, where we recognized that section 271.154 relates “to
    the litigation and adjudication of a claim” rather than to “the scope of
    immunity,” and that the concluding “subject to” phrase in section
    271.152 “does not preclude . . . other contractual procedures.”        
    449 S.W.3d 98
    , 107-08 (Tex. 2014); see also Austin Bridge, 601 S.W.3d at 625
    (“Before [the Act], there was no ‘adjudication’ of a contract claim against
    a local government. Now, a local government can be held to promises
    made within the chapter’s framework.” (citation omitted)).
    The Cities and the court of appeals point out that we have also
    referred to the other provisions of the Act collectively as “limitations on
    the waiver of immunity.” Hays St. Bridge Restoration Grp. v. City of
    San Antonio, 
    570 S.W.3d 697
    , 706 (Tex. 2019) (quoting Zachry, 449
    S.W.3d at 108). On that basis, the court of appeals held that “to show
    waiver of immunity, a claimant must plead facts showing that
    conditions of section 271.154 have been met.” 683 S.W.3d at 12 (quoting
    Mission Consol. Indep. Sch. Dist. v. ERO Int’l, LLP, 
    579 S.W.3d 123
    , 128
    (Tex. App.—Corpus Christi—Edinburg 2019, no pet.)). We disagree.
    Nothing in section 271.154 indicates that it is narrowing section
    271.152’s waiver of immunity to exclude cases in which parties have not
    complied with the agreed-upon adjudication procedures.            Instead,
    section 271.154 provides that such procedures—which may include
    “requirements for . . . engaging in alternative dispute resolution
    proceedings before bringing a suit”—“are enforceable.” TEX. LOC. GOV’T
    C ODE § 271.154. The word “enforceable” makes clear that the waiver of
    8
    immunity for a court or arbitrator to adjudicate the claim includes the
    ability to require parties to comply with their agreed procedures for that
    adjudication.
    If there were no waiver of immunity, local government entities
    could enforce agreements for mandatory pre-suit alternative dispute
    resolution (ADR) against private parties, but the reverse would not be
    true. Section 271.154 ensures that under the waiver, both sides are on
    equal footing so that private parties can similarly enforce pre-suit ADR
    agreements against local government entities. As we said in Austin
    Bridge, this section “is better read to authorize contracting parties to
    devise methods for dispute resolution in their contracts for claims now
    viable through the subchapter’s limited waiver of immunity.”          601
    S.W.3d at 625 n.45 (emphasis added).
    In contrast, the court of appeals’ interpretation would thwart
    enforcement of contractual ADR and other agreed adjudication
    procedures. Absent a waiver of immunity, a court lacks subject-matter
    jurisdiction and must dismiss the suit—it cannot order the parties to
    engage in ADR procedures. The Cities maintain that courts can, in some
    sense, enforce the agreed-upon mediation procedure by dismissing
    SJRA’s claims, but that view is contrary to the common understanding
    of the word “enforceable.” The Legislature’s choice of that word signals
    that enforcement of agreed adjudication procedures falls within the
    scope of section 271.152’s waiver of immunity for adjudicating the claim
    for breach of contract, enabling a court or arbitrator to order compliance
    with those procedures.
    9
    B.     Section 311.034 of the Government Code is
    inapplicable because these adjudication procedures
    are neither statutory nor a prerequisite to suit.
    In support of its contrary holding, the court of appeals cited
    section 311.034 of the Government Code, which provides that
    “[s]tatutory prerequisites” to suit “are jurisdictional requirements in all
    suits against a governmental entity.” TEX. GOV’T C ODE § 311.034; see
    683 S.W.3d at 12 n.48. We conclude that this statute does not apply to
    section 271.154 of the Local Government Code because contractually
    selected    adjudication   procedures     are   not   statutory   and their
    enforcement by a court would necessarily occur after suit is brought.
    Although section 271.154 is a statute, it simply provides that
    certain agreements to adjudication procedures are enforceable by a
    court or arbitrator; those procedures need not be prerequisites to suit.
    Here, the parties did agree to mediate certain claims prior to suit, but
    that agreement is a contractual prerequisite, not a statutory one. And
    as this case shows, a court must determine after suit is filed whether a
    party was required to comply with the mediation procedure—including
    disputes about whether the claim was within the procedure’s scope and
    any defenses to the procedure’s application, as well as what the proper
    remedy would be for failure to comply. For example, that remedy could
    be an order compelling mediation—perhaps coupled with abatement of
    the ongoing suit—rather than dismissal,2 which further demonstrates
    2Cf. In re Universal Underwriters of Tex. Ins. Co., 
    345 S.W.3d 404
    , 412
    & n.5 (Tex. 2011) (holding contractual requirement that parties engage in
    appraisal process for dispute resolution before filing suit is enforceable by
    motion to compel but declining to order abatement of pending suit); In re U.S.
    10
    that compliance with the procedure is not an absolute prerequisite to
    suit.
    For these reasons, we conclude that compliance with any
    contractually agreed adjudication procedures is not a condition
    precedent to the waiver of immunity in section 271.152. Section 271.154
    provides that a court or arbitrator may enforce those procedures, not
    that it must dismiss a claim for breach of contract unless a party
    complies with them.
    II.     SJRA’s claims were for payment defaults, so the pre-suit
    mediation procedures in the GRP contracts do not apply.
    The Cities’ argument that SJRA’s claims should be dismissed for
    failure to comply with the contractual pre-suit mediation procedure also
    falls short because that procedure does not apply to these claims. The
    GRP contracts require mediation of claims for “performance default” but
    not claims for “payment default.” A payment default occurs when a
    party “fails to timely pay any fees, rates, charges, or other amounts due.”
    A performance default occurs when a party “fails to perform or is in
    breach or violation of any of its other obligations” under the contracts.
    In determining whether the type of default claimed by SJRA
    triggered the pre-suit mediation requirement, the court of appeals
    looked in part to “allegations between the parties”—that is, beyond
    SJRA’s claims for breaches by the Cities to allegations regarding
    Home Corp., 
    236 S.W.3d 761
    , 764 (Tex. 2007) (finding no indication in contract
    that parties who agreed to mediate prior to arbitration intended to dispense
    with arbitration if mediation did not occur first, although defendant could have
    sought to delay arbitration pending mediation).
    11
    breaches by SJRA. 683 S.W.3d at 11. But jurisdiction is determined on
    a claim-by-claim basis. Heckman v. Williamson County, 
    369 S.W.3d 137
    ,
    152-53 (Tex. 2012). Accordingly, we focus on the “nature” or “gravamen”
    of SJRA’s third-party claims against the Cities to determine whether
    those claims fall under the GRP contracts’ mandatory pre-suit ADR
    procedure. In re Breviloba, LLC, 
    650 S.W.3d 508
    , 512 (Tex. 2022).
    SJRA alleged that the Cities “breached their respective GRP
    contracts by refusing to pay the GRP rates adopted in accordance with
    their GRP contracts.” These claims fall within the contracts’ definition
    of “payment default” because they concern a failure to pay rates due.
    The court of appeals noted that SJRA has also alleged a “controversy . . .
    between the parties concerning the compliance of SJRA’s rates with the
    GRP Contracts.” But SJRA is asserting that it did not default in setting
    those rates, which is a necessary predicate for its claim that the Cities
    did default by failing to pay them. SJRA does not allege any other basis
    for relief and does not contend that the Cities face liability for any reason
    other than their failure to remit the full payment due under the GRP
    contracts’ rate and fee provisions. Thus, the contracts did not require
    SJRA to mediate its claims before filing suit, which confirms that the
    courts below erred in holding that the Cities were entitled to dismissal
    based on SJRA’s failure to mediate.
    III.   Because the GRP contracts state their essential terms,
    executing them waived the Cities’ immunity.
    As relevant here, the Act limits its waiver of immunity to properly
    executed “written contract[s] stating the essential terms of the
    agreement for providing goods or services to the local governmental
    12
    entity.” TEX. LOC. GOV’T C ODE § 271.151(2)(A). The Cities argue that
    their contracts with SJRA do not state their essential terms, which
    provides a separate reason that their immunity has not been waived
    under section 271.152.
    Although the court of appeals did not address this issue, the Cities
    raised it in their plea to the jurisdiction, which the trial court granted.
    Because this issue of law relates to jurisdiction and reaching it now will
    help resolve the remainder of this litigation efficiently, we address the
    issue ourselves rather than remanding for the court of appeals to do so.
    See Jones v. Turner, 
    646 S.W.3d 319
    , 325 (Tex. 2022).
    A.     A contract states its essential terms if it satisfies the
    common law and complies with the Act’s
    requirements.
    We have explained that the Act’s reference to “essential terms”
    incorporates the requirements of the common law. See Dall./Fort Worth
    Int’l Airport Bd. v. Vizant Techs., 
    576 S.W.3d 362
    , 368-69 (Tex. 2019)
    (citing Fischer v. CTMI, L.L.C., 
    479 S.W.3d 231
    , 237 (Tex. 2016)). For
    example, the common law addresses which terms must be stated: those
    that are “basic obligations” of the type of contract at issue, as well as
    particular terms that the parties to the specific contract would
    reasonably regard as “vitally important ingredients of their bargain.”
    Campbellton Rd., Ltd. v. City of San Antonio, ___ S.W.3d ___, ___,
    No. 22-0481, slip op. at 20 n.63 (Tex. Apr. 12, 2024) (quoting Kirby Lake
    Dev., Ltd. v. Clear Lake City Water Auth., 
    320 S.W.3d 829
    , 838 (Tex.
    2010), and Vizant Techs., 576 S.W.3d at 369). The common law also
    speaks to how these terms must be stated: with “a reasonable degree of
    certainty and definiteness” sufficient to confirm the parties’ intent to be
    13
    bound, and to “enable a court to understand and enforce” the obligations
    “and provide an appropriate remedy when breached.” Vizant Techs., 576
    S.W.3d at 369 (citing Fischer, 479 S.W.3d at 237).
    The Cities argue that this interpretation renders the language
    “essential terms” surplusage because the Act applies only to contracts,
    which already must state their essential terms to be enforceable. The
    alternative offered by the Cities is that the Act requires a higher, but
    unspecified, standard for a contract to state its essential terms.          We
    adhere to our precedent and reject this alternative.
    When the Legislature uses language that tracks the common law,
    we generally infer that the Legislature intended to import the
    common-law understanding of that language. Sampson v. Univ. of Tex.,
    
    500 S.W.3d 380
    , 387 (Tex. 2016). Accordingly, we have held that the
    Legislature’s use of essential-terms language in section 271.151 was
    meant to import the common-law understanding of that language—
    namely, the common-law requirements for determining which terms
    must be included and whether those terms are stated with sufficient
    clarity that they can be enforced.3
    Contrary to the Cities’ argument, the reference to essential terms
    is not surplusage. The Act requires that a contract state some additional
    terms that the common law might not: the contract must be for goods or
    services, must be properly executed on behalf of a local government
    3 As we explain further below, this reference to “enforced” should not be
    read to suggest that a contractual right must ultimately be enforceable or that
    any defenses to enforcement must be disproved before immunity will be
    waived. See Campbellton Rd., No. 22-0481, slip op. at 23-24; El Paso Educ.
    Initiative, Inc. v. Amex Props., LLC, 
    602 S.W.3d 521
    , 534 n.66 (Tex. 2020).
    14
    entity, and must be in writing.           See TEX. LOC. GOV’T CODE
    § 271.151(2)(A).    Those additional terms are likewise essential for a
    contract to be “subject to this subchapter”—that is, to trigger a waiver
    of immunity.
    The Cities also fail to point to an alternative ordinary meaning
    for the essential-terms requirement. To construct a new standard out
    of whole cloth based only on the statute’s reference to essential terms
    would surely fail to comport with our preference for “ordinary meaning
    [over] an unusual meaning that would avoid surplusage.” Stephens v.
    Beard, 
    485 S.W.3d 914
    , 918 (Tex. 2016) (citation and internal quotation
    marks omitted). Moreover, the Cities’ interpretation is circular. In the
    Cities’ view, a contract must state its essential terms even if it would be
    enforceable at common law without those terms. But that makes no
    sense: the concept of “essential” terms only has relevance in our law in
    determining whether the contract is enforceable. See Vizant Techs., 576
    S.W.3d at 368-69.
    With this standard in mind, we turn to the Cities’ specific
    arguments that the GRP contracts do not state their “essential terms.”
    The price term. The Cities first contend that the GRP contracts’
    use of SJRA’s rate orders as a price-setting mechanism renders the
    essential price term too indefinite to be enforced. But the GRP contracts
    offer a detailed set of procedural and substantive limitations on how
    prices are to be set. These limitations include requirements that rates
    must be as low as possible while being “consistent with good
    management practices,”       “necessary   and proper”      under   certain
    provisions of the contracts, “consistent with [SJRA’s] statutory and
    15
    constitutional duties,” and “just, reasonable, and nondiscriminatory.” In
    addition, rates may be charged only to recoup the categories of expenses
    listed in the GRP contracts.
    These limitations, among others, provide sufficient guidance for
    a court to determine whether SJRA complied with the GRP contracts’
    rate-setting requirements.     See Fischer, 479 S.W.3d at 237 (“[T]he
    agreement’s terms must also be sufficiently definite to enable a court to
    understand the parties’ obligations, and to give an appropriate remedy
    if they are breached.” (citations and internal quotation marks omitted)).
    Accordingly, the price term is sufficiently definite.
    The quantity term. Conroe also argues that the quantity term
    in its GRP contract is too indefinite to enforce.4 In addition to signing a
    GRP contract, Conroe and SJRA signed a supplemental agreement that
    addresses quantity. The GRP contract allows SJRA to set the minimum
    quantity of water that Conroe must take from SJRA. Then, the GRP
    contract and supplemental agreement together set a floor on that
    minimum (“not less than sixty percent . . . of aggregate total
    groundwater usage of the City during calendar year 2009 according to
    the official records of the Conservation District”), as well as a ceiling on
    that minimum (“an amount equal to ninety percent . . . of the average
    daily amount of groundwater . . . supplied from any such site during the
    4 Magnolia has not argued that the quantity term of its GRP contract is
    indefinite, so we do not address that issue. Indeed, the quantity term in
    Magnolia’s GRP contract applies only if Magnolia begins taking surface water
    from SJRA, which it has not yet done. Magnolia must still pay pumpage fees,
    but those fees are not tied to any quantity of water taken from SJRA and have
    not been challenged as indefinite.
    16
    low-demand period preceding the date of calculation of the Contract
    Quantity”). The supplemental agreement also provides that SJRA will
    give “due deference” to Conroe’s director of public works and his
    “preferences and decisions” in setting the minimum. Under the GRP
    contract and the supplemental agreement, Conroe is free to take more
    than that minimum as its needs require.
    Taken together, these provisions provide enough guidance for a
    court to determine whether SJRA complied with its requirements in
    setting the contract quantity.         Indeed, courts routinely uphold
    requirements contracts, in which there is no set quantity term and the
    conduct of the parties determines the quantity they are required to give
    or take. See, e.g., Pace Corp. v. Jackson, 
    284 S.W.2d 340
    , 345 (Tex.
    1955). Accordingly, the quantity term in Conroe’s GRP contract and
    supplemental agreement is sufficiently definite.
    Conroe also argues that the quantity term’s definiteness was
    undermined post-contract by the separate court judgment invalidating
    Lone Star’s groundwater pumpage limits. But the quantity provisions
    of the GRP contract and supplemental agreement are not directly tied
    to the groundwater pumpage limits. Instead, they reference Lone Star’s
    Regulatory Plan as a whole. Yet even if the quantity term were tied to
    those limits, that fact would not support the conclusion that the contract
    fails to state its essential terms.
    The language of section 271.152 reveals that whether there is a
    “contract”—including essential terms—is a question asked at the time
    of formation.    See Campbellton Rd., No. 22-0481, slip op. at 13-15.
    Section 271.152 provides that immunity is waived when an authorized
    17
    government entity “enters” into a contract subject to the Local
    Government Code, and section 271.151(2)(A) requires that the contract
    “stat[e]” its essential terms.    Accordingly, the relevant time for
    determining an immunity waiver is the time of contract formation, and
    courts evaluate compliance with the “essential terms” requirement
    based on the state of the contract at that time. See also RESTATEMENT
    (SECOND) OF CONTRACTS § 33 (AM. L. I NST. 1981) (listing certainty of
    contractual terms as element of formation).
    Of course, later events could render the contract unenforceable on
    the merits, but that does not affect whether there was—at formation—
    a contract stating its essential terms for purposes of the immunity
    waiver. See Campbellton Rd., No. 22-0481, slip op. at 23-24; El Paso
    Educ. Initiative, Inc. v. Amex Props., LLC, 
    602 S.W.3d 521
    , 534 n.66
    (Tex. 2020) (explaining that our precedent does not “require that a
    contract ultimately be enforceable to clear the jurisdictional hurdle”).
    For example, a contract could be held to be unconscionable, or a court
    might find that a condition precedent to an obligation has not been
    satisfied, thus rendering a contract unenforceable even though there
    was a contract stating its essential terms at formation. Similarly, the
    failure of an initially definite term may simply present grounds for a
    court to reform the contract or else substitute a reasonable term, such
    as when a bank rate that the parties selected as a reference point for
    interest later becomes unavailable. See, e.g., Bailey, Vaught, Robertson
    & Co. v. Remington Invs., Inc., 
    888 S.W.2d 860
    , 866-67 (Tex. App.—
    Dallas 1994, no writ); F.D.I.C. v. Ambika Inv., No. 94-10287, 
    1994 WL 18
    708818, at *2-3 (5th Cir. Dec. 1, 1994); see also R ESTATEMENT (SECOND)
    OF C ONTRACTS § 204.
    Ultimately, as long as the contract meets the common-law
    “essential terms” standard and the Act’s other stated requirements at
    the time it is formed, that is enough to show a waiver of immunity.
    Because those requirements were met here as we have explained, the
    court of appeals erred in affirming the trial court’s order granting the
    Cities’ pleas to the jurisdiction.
    CONCLUSION
    Contractual ADR provisions and other agreed adjudication
    procedures made enforceable against local governments by the Act’s
    waiver of sovereign immunity do not serve as limits on that waiver. And
    in any event, the parties’ agreement to pre-suit mediation did not apply
    to SJRA’s claims. In addition, the GRP contracts sufficiently state their
    essential terms as required by the common law and the Act.           We
    therefore hold that the Act waived the Cities’ immunity when they
    entered into the GRP contracts, and we reverse the court of appeals’
    judgment and remand the case to the trial court for further proceedings
    to resolve SJRA’s claims on the merits.
    J. Brett Busby
    Justice
    OPINION DELIVERED: April 12, 2024
    19
    

Document Info

Docket Number: 22-0649

Filed Date: 4/12/2024

Precedential Status: Precedential

Modified Date: 4/14/2024