Untitled Texas Attorney General Opinion ( 1991 )


Menu:
  •                                @fficeof tfieBttornep
    ti3eneraI
    #Mate of ?ICexas
    September 17,199l
    DAN  MORALES
    Al-KmNLY
    GENERAL
    Honorable John B. Holmes                      Opinion No. DM-43
    Harris County District Attorney
    201 Fannin, Suite 200                         Re: Whether the acquisition and con-
    Houston, Texas 77002                          stmction of a monorail transit system is
    subject to competitive bidding (RQ-64)
    Dear Mr. Holmes:
    You ask two questions regarding the proposed construction of a rail transit
    system by the Metropolitan Transit Authority of Harris County (METRO). You ask
    whether the construction of a rail, monorail, or fixed guideway transit system
    constitutes an improvement to real property and whether the purchase of a transit
    system is subject to the competitive bidding requirements of V.T.C.S. article 1118x.
    We conclude that the procurement of a new transit system is subject to the
    competitive bidding requirement of article 1118x, but that the board of METRO
    may grant a waiver of this requirement for portions of the project and may award
    contracts for those portions through competitive negotiation upon a finding of the
    conditions specified in section 14(a) of the statute. Whether the conditions of
    section 14(a) were met under the circumstances described in this opinion is a fact
    question that cannot be resolved by this office in the opinion process.
    I. Background
    A brief submitted on behalf of METRO acquaints us with some of the history
    of the METRO rail project. In 1988 the voters residing in the METRO service area
    approved by referendum a comprehensive regional mobility plan that included a
    proposal to construct a fixed guideway transit system Soon thereafter, the board of
    METRO embarked upon a strategy to develop a comprehensive plan to procure
    and construct the new transit system Following consultation with legal counsel, the
    METRO board concluded, contrary to its initial intentions. that the entire rail
    project could not be completed on a turnkey basis.’ The board determined that
    certain portions of the project could only be procured pursuant to competitive
    %x Attorney General Opinion JM-1189 (1990) 0.1 (dchition   of “turnkey’contracting in the
    -00       contcat).
    p.   210
    Honorable John B. Holmes - Page 2            (DM-43)
    bidding while other portions could not. For example, the board understood that
    architectural and engineering services would have to be procured in accordance. with
    the Professional Services Procurement Act. V.T.CS. art. 664-4, see Attorney
    General Opinion JM-1189 (1990). The board also decided to divide the rail project
    into different components and pursuant to section 14(a) of article 111% to
    procure some components of tbe project through competitive bidding and others
    through competitive negotiation.
    The components of the rail project to be acquired by METRO through
    competitive bidding include terminal complexes, parking lots, maintenance and
    storage buildings, the central control facility, roadways, and guideway supports. The
    portions of the project to be obtained via competitive negotiation constitute the
    nucleus of the equipment involved in the project and are called “System Elements.”
    These items include vehicles, the traction power system, automatic train control and
    commmdcations system, the fare collection system, trackage, supporting girders,
    maintenance equipment and tools, and other equipment used in the operation of the
    system The METRO board determined that the contract for all of these elements
    would be awarded to a single supplier selected following an evaluation of proposals
    submitted in response to a detailed Request for Proposals (RFP). On March 28,
    1991, the METRO board selected one proposal for the “System Elements.” The
    general manager of METRO is currently engaged in negotiations with the Houston
    Monorail Team (I-WI’), offerors2 of the selected proposal.
    II. Metropolitan Transit Authority (MTA)statutory procurement requirements
    METRO’s purchasing practices are governed by section 14 of article 1118x.
    Subsection (a) of that section requires that contracts of a metropolitan transit
    authority (MTA)
    for more than SlO,OOO    for the construction of improvements or
    the purchase of materi& machinery, equipment supplies [sic]
    and all other property, shall be let on competitive bids.
    V.T.C.S. art. 1118x, 0 14(a). The subsection also prescrii general procedures for
    the advertising of proposed purchases. The board of an MTA may adopt rules
    p.   211
    Honorable John B. Holmes - Page 3                  (DM-43)
    governing the taking of bids and the awarding of such contracts. It is also
    authorized to grant waivers of the bidding requirement under the circumstances
    itemized below:
    (1) ‘in the event of emergency,
    (2) ‘in the event the needed materials are available from only
    one source;
    (3) ‘in the event that, except for construction of improvements
    on real property, in a procurement requhing design by the
    supplier competitive bidding would not be appropriate and
    competitive negotiation, witb proposals solicited from an
    adequate number of quaJified sources, would permit reasonable
    competition consistent with the nature and requirements of tbe
    procurement;’ or
    (4) “in the event that, except for construction of improvements
    on real property, after solicitation it is ascertained that there will
    be only one bidder.
    See V.T.C.S. art. 1118x, 0 14(a). Subsection (a) of section 14 does not apply to
    contracts for personal or professional services, for the acquisition of existing transit
    systems, or for services covered by the Professional Services Procurement Act,
    V.T.CS. article 664-4. Id; see u.50 Attorney General Opinion JM-1189 (1990).
    The complete text of section 14(a) is set out below.3
    p.   212
    Honorable John B. Holmes - Page 4             (DM-43)
    The METRO board granted a waiver from competitive bidding for portions
    of the rail project under the third form of waiver authorized by section 14(a), which
    we will generally refer to as the “design waiver.” You question whether the board
    was authorized to grant the waiver under these circumstances. Before addressing
    the specific issues you raise, we will examine the competitive negotiation technique
    under section 14(a) and other statutes.
    III. Charactehtics of competitive negotiation
    The language of the design waiver of section 14(a) reveals that prior to
    granting the waiver the board must make four critical determinations - (1) that a
    particular procurement “requires design by tbe supplier,” (2) that it does not
    constitute an “improvement on real property,” (3) that “competitive bidding would
    not be appropriate” under the circumstances, and (4) that competitive negotiation
    would permit reasonable competition under the circumstances. As indicated at the
    outset of this opinion, these inquiries involve factual questions that CannOt be
    resolved in an opinion of the attorney general. It is possible, however, to address
    some of the issues regarding the proper interpretation of section 14(a). The balance
    of this opinion wilI address such issues.
    Another sig.niiIcant feature of tbe language of section 14(a) is that it
    authorizes procurement contracts to be awarded on the basis of competitive
    negotiation, an alternative to competitive sealed bidding, the traditional mode of
    government procurement. The approxlmate scope of the design waiver and its
    precise meaning are matters left unsettled by the terms of article 11%. The statute
    does not prescribe specific procedures or time frames for competitive negotiation,
    but specikahy grants the board rulemaking power over the process. It nonetheless
    offers some insight into the differences between the two procurement modes.
    For instance, competitive negotiation under section 14 does not require
    formal advertising of the MTA’s decision to make a particular procurement as it
    does for competitive bidding. Instead, the board may solicit proposals directly from
    sources it determines are qualified to meet the MTA’s needs. The MTA is required
    only to post an amrouncement that it is considering such a contract in its principal
    office for at least two weeks before the contract is awarded. V.T.C.S. art. 111&4
    814(b).
    Also, section 14 authorizes the board of the hITA to determine what level of
    competition is appropriate for a contract awarded by competitve negotiators and
    requires only “reasonable competition” among “an adequate number of qualified
    p.   213
    Honorable John B. Holmes - Page 5              (DM-43)
    sources.” On the surfacx, this standard differs from the widely-recognized view that
    competitive bidding requires and generates maximum open competition among all
    interested parties. See Tarac Highway Conun’n v. Tarar A&n of Steel Zmporers, 372
    S.W2d 525 (Ten. 1963). Yet it is apparent from the experience in other jurMictior``
    that competitive negotiation can also be conducive to maximum competition. See
    gemdy Paul v. United Statfs, 371 U.S. 245,2X%53 (1963) (discussing competitive
    negotiation procedures for military procurements).
    The competitive negotiation procedure is said to allow comparative,
    judgmental evaluations to be made when selecting from a number of acceptable
    proposals. Attorney General opinion MW440 (1982) at 3. The principal difference
    between competitive negotiation and the traditional method of procurement
    (competitive bidding) is that the former permits alteration and refinement of a
    proposal following the opening and initial review of the proposal by the governing
    body and prior to award of the contract, whereas the traditional method requires a
    contract to be awarded solely on the basis of the information contained in the bid at
    the time of opening. See The Council of State Governments, State and Local
    Govemment Ptuddng        64-65 (3rd ed. 1988); Nash & Love, Znnovationr in Federal
    Conhrdion ccmfm&g, 45 Geo. Wash. L Rev. 309,324-33 (1977). Competitive
    bidding utilizes price as either the sole criterion or one of two chief criteria for
    contract awards. Competitive negotiation, on the other hand allows evaluation of a
    proposal in light of important criteria in addition to price, such as quality,
    experience, and staff@ Id
    The competitive negotiation technique also affords a governmental body
    somewhat greater flexibility than the traditional method because it is usually
    associated with the use of “performance” specifications. Performance specifications
    permit the governmental body to describe a need and invite prospective vendors to
    devise unique solutions to the problem See Ztuwvationr in Federal Constmcthn
    Contract@, supm, 1135 at 32526. Competitive bidding is typically associated with
    the use of “prescriptive” or “design” specifications, which describe the means of
    meeting the governmental body’s needs and customarily employ dimensional and
    other physical requirements of the item being procured. See id; State and Local
    Govemment Ptuddng, suptn, at 45.
    Under the negotiation technique, the governmental body is allowed to
    conduct dkcussions with offerors regarding the particulars of their proposals, to
    negotiate with offerors to obtain the most advantageous contract for the agency, and
    to award the contract to the offeror submitting the best overall proposal. Id As
    prescriid in statutes other than article Ill&r, competitive negotiation generally
    Ij.   214
    Honorable John B. Holmes - Page 6                (DM-43)
    requires the governmental body to specify the relative importance of the additional
    evaluative criteria and to give all offerors fair and equal treatment with respect to
    any opportunity for diswssion or revision of proposals. E.g., Educ. Code
    0 21.9012(g); Local Gov? Code $0 252.04~ 262.030.
    Iv. Divisibility of publk works or improvement projects into separate components
    You ask whether the purchase of a transit system is subject to the
    competitive bidding requirement of section 14(a), but your brief focuses on a
    different issue: i.e., whether the METRO board was authorized to divide the rail
    project into separate wmponents for the purpose of submitting wntracts for some
    of the components to competitive bidding. You argue that the board was required
    to award a single contract for the entire project pursuant to competitive bidding.
    We disagree.
    It has long been the rule in Texas that a governmental body has discretion to
    award separate contracts for different portions of a single public improvement
    project when, in its honest judgment, separate wntracts are in the public interest.
    Wbig Bnx v. Cfty qf DaUas, 91 S.W3d 336,338 (Tex. 1936); see aIro 64 AM. JUR
    26 Acbk Works and Contmcts 0 56 (1972). Thus, the METRO board required no
    special statutory authorization to divide the rail project into separate components.
    In this instance, section 14(a) expressly recognizes that competitive bidding
    may be inapplicable to some components of a public works or improvement project
    (e.g., some professional services). See V.T.C.S. arts. m       1118x, 0 14(b). Where
    competitive bidding is required, a governmental body may only act to promote the
    unmistakable legislative policy favoring unrestricted competition for public
    wntracts. Teuzr Highway Comm’n v. Texas Ash of Steel Zmmen. supm. Likewise,
    where some aspects of a contract are subject to a waiver of competitive bidding and
    others not, those aspects that are not subject to waiver are controlled by the
    competitive bidding statute. See Wiakce v. ~Gxnmirsioners’ Court of Madiron
    County, 281 S.W. 593,595 (Tex. Civ. App.-Waco 1926), r&d on other groundr, 
    15 S.W.2d 535
    (Tex. 1929).
    Once it resolved to divide the rail project into components, the METRO
    board’s duty then became to ascertain which components were subject to
    competitive bidding and to award wntracts for those components acwrdingly. In
    answer to your Srst question, we conclude that article 1118x did not require the
    METRO board to award a single contract for the entire rail system project.
    p.   215
    Honorable John B. Holmes - Page 7                 (DM-43)
    V. Whether eonstn~ctionof a monorail system is an improvement to red property
    In light of the preceding disc&on, your next question is whether the
    contract for the “System Elements” is subject to the competitive bidding
    requirements of section 14(a)? The answer to this question hinges on the meaning
    of the word “improvement,” a term which appears susceptible to several different
    interpretations.
    METRO and HMT direct our attention to several cases which hold that
    railroad ties and trackage are personal property which do not become part of the
    underlying real estate and therefore do not constitute improvements to real
    property. Teaa & iKO.R Co. v. S&e&&f,            
    146 S.W.2d 724
    , 727 (Tex. 1941);
    Pmton v. Sabhe & E.T. Ry. Ca, 7 S.W. (L25(Tex. 1888); Moore v. Roteb, 719
    S.W.2d 372,376 (Tex. App.-Houston [14th Dist.] 1986, writ ref d n.r.e.). The HMT
    brief also invokes the familiar rule of statutory wnstruction establishing the
    presumption that the legislature intends to give undefiued words in a statute the
    meaning given those words by the wurts. See McBride v. Cluyton, 
    166 S.W.2d 125
    ,
    128 (RX. 1942); Tetm Employers’Ins A&n v. Hamchild, 
    527 S.W.2d 270
    , 275
    (Tex. Civ. App.-Amarillo 1975, writ refd n.r.e.). The HMT brief asserts that the
    legislature’s failure to define the word “improvement” gives rise to the presumption
    that it intended the word to carry the same meaning given it by the courts in the
    railroad cases. Drawing an analogy to the railroad cases, the METRO brief
    concludes that a monorail system does not wnstitute an improvement to real
    wwv.
    These arguments are persuasive, but we do not find them fully dispositive of
    the issue. You point out, in keeping with the rule of construction described above,
    that “improvement” has been broadly defined by the wmts. See Nine Hundred
    Main, Zne v. City of Houston, 150 S.W.2d 468,472 (Tex. Civ. App.-Galveston 1941,
    writ dism’d judgm’t car.) (“improvement” comprehends all additions to the freehold,
    except trade fixtures which may be removed without injury). Also, other rules of
    statutory wnstruction make it possible to draw different conclusions regarding the
    meaning of the word “improvement.”
    For instance, in contrast to the rule descriid above, the courts will also
    presume that the legislature, in leaving certain words in a statute undefined, is
    %esc   items indnde dkb%,     the traction power system, automarie train control and
    c0mmW           6yStem. the fare cdlcetion system, trackage, qpcuthg     girdeq maintenance
    quipmeat and too& aad other quipmeat usedin the operation of the system.
    p.   216
    Honorable John B. Holmes - Page 8                 (DM-43)
    aware of existing statutes employing similar terms. See Gmrso v. Cannon Ball Motor
    Freight Lutes, 81 S.W.2d 482,485 (Tex. 1935). Where the legislature has specially
    defined a word in a statute, it will be presumed that the word will be used in the
    same sense in a subsequent enactment, though this is not necessarily so when the
    two enactments deal with different subject matter. See Bmo&shk v. Houron Z&&p.
    SchoolDist, 
    508 S.W.2d 675
    (Tea. Civ. App.-Houston [14th Dist.] 1974, no writ).
    “Improvement” is defined different@ in at least three codes. See Tax Code
    0 1.04(3) (Property Tax Code definition; “improvement” means, tier &z, “a
    building, structure, fixture, or fence erected on or affixed to land”); Property Code
    0 53.001(2) (defining term for purposes of mechanic’s, wntractor’s, and
    materialman’s liens to include abutting sidewalks and streets and utilities, wells.
    cisterns, tanks, reservoirs, pumps, siphons, windmills, and “other machinery or
    apparatus used for raising water for stock, domestic use, or irrigation”); Water Code
    Q53.001(3) (“improvement” means a facility for wnservin& transporting or
    dismhtingfresbwater).
    Furthermore, the analogy to railroads, while ilbmdnating, does not answer
    the issue with certitude, for a monorail might also draw wmparkons to other forms
    of transport. See A. Lerchen & Sons Rope Co. v. Moser, 
    159 S.W. 1018
    (Tex. Civ.
    App.-San Antonio 1913, no writ) (an aerial tramway was an improvement to real
    property for purposes of enforcing a materialman’s lien). These examples demon-
    strate the difficulty of conforming the word “improvement” in section 14(a) to cases
    and statutes reflecting altogether different wntextual considerations and policies.
    We think it is more productive to analyze the term in relation to the general body of
    law of which it is a part and by reference to its legislative history. On examination
    of these factors, we think it was not unreasonable for the METRO board to
    conclude that parts of the rail project could be accomplished by use of the
    competitive negotiation technique. Whether its decision with respect to particular
    components of the project was justified is, again, a question of fact that cannot be
    resolved here.
    Prior to 1985, section 14(a) required competitive bidding on all MTA
    purchases above S5000 and permitted a waiver of the sealed bidding requirement
    only in cases of emergency. In that year the legislature amended the provision to its
    current form. S.B. 440, Acts 198569th Leg., ch. 620, at 2306. As originally Sled,
    Senate Bill 440 would have permitted the board of an MTA to waive competitive
    bidding if it found that
    p.   217
    Honorable John B. Holmes - Page 9                 (DM-43)
    wnditions are not appropriate for formal advertisin& the
    needed materials are available from only one source, or after
    soiicitatio~ competition is inadequate.
    Bill File to S.B. 44469th Leg. (1985).
    The publicly stated purpose of the 1985 amendment was to wnfonn MTA
    procurement requirements to parallel federal guidelines, since most MTA capital
    projects are funded with a combination of state, local, and federal funds. Hearings
    on S.B. 440 Before the Senate Comm. on Intergovernmental Relations, 69th Leg.
    (March 5, 198S).J The most obvious effect of the 1985 amendment was to free
    MTAs from the rigid structural and discretionary wnstraints imposed by sealed
    competitive bidding. See Znnovaffonr in Fedeml Gwhucdon Contmcdng, supm, at
    324-33 (1977) (comparing competitive bidding to competitive negotiation, at the
    federal level).
    The most relevant item of legislative history is a statement by the sponsor of
    the bill indicating that the original language of the amendment to section 14(a) was
    changed in subcommittee to address, among other things, the concerns of a segment
    of the wnstruction industry - specifically, general wntractors. Hearings on S.B. 440
    Before the Senate Comm. on Intergovernmental Relations, 69th Leg. (March 5.
    1985) (testimony of Senator John Traeger). This most likely explains the addition to
    section 14(a) of tbe phrase “except for the wnstruction of improvements on real
    property.” We think the modification of the original language of Senate Bill 440 to
    its ultimate form indicates that the legislature was interested in preserving the status
    quo with respect to the award of mA wntracts for conventional construction
    projects. Viewed from this perspective, the legislature may have used the term
    “improvement” to denote, as you suggest, public improvements or public works.
    The phrases “public improvements” and “public works” are often used
    interchangeably. Compare Navam~ Auto-Park, Znc v. Ci@ of Son Antonio, 574
    S.W.2d 582,584 (Ten. Civ. App.-San Antonio 1978, writ refd n.r.e.) (characterizing
    municipal public parking facility as a “public work”); with Zachty v. City of Son
    Antonio, 296 S.WL?d299,304 (Tex. Civ. App.-San Antonio 1956). t#‘d, 
    305 S.W.2d 558
    (Ten. 1957) (numicipal public parking facility is a “public improvement”).
    %rdbily,   interprcdons of the paraUel federal guideha would be approphtc sources of
    meaoing d section 14(a). See St& v. wicss. 171 S.WZd 848 (T~L l!X3). q Eourd of W&r Eng’n v.
    AkKnf$u, 
    229 S.W. 301
    (Tex 1921). I-hwer, WCbavc been unable to locate any federal standard
    emplojhg laquage comparable to the ‘design’waiver.
    p. 218
    Honorable John B. Holmes - Page 10             (DM-43)
    courts have generally applied these phrases to permanent structures or facilities,
    additionsofafixednaturetostructures,andtoroads.             SeeC&ofCopusChistiv.
    Haywad, 
    111 F.2d 637
    , 639 (5th Cir.), cert. denied, 
    311 U.S. 670
    (1940) (dam and
    reservoir); i&auf& v. C* of CR-M P&&s, 
    86 S.W.2d 204
    , 206 (Ten 1935) (water
    reservoir and pipelines); Enzpw          Gawalty Ca v. Stewatt, 
    17 S.W.2d 781
    (Tex.
    Comm’n App. 1929, judgm’t aff’d) (wntracts for building or road wnstntction
    included, but not wntracts for map and plat book preparation or purchase of road
    grader); Overslreet v. Houston County, 365 S.W2d 409,412 (Ten. Civ. App.-Houston
    [lst Dist.] 1963, writ rePd n.r.e.) (central air wnditioning system and window tits).
    We think the context and legislative history of section 14(a) support a comparable
    application.
    With these points in mind, it may be possible to draw initial conclusions
    regarding the propriety of the METRO board’s actions. These matters, however,
    are entrusted in the first instance to the discretion of the METRO board.
    Moreover, since this inquiry requires the examination and resolution of issues
    regarding facts which are not before us and are beyond our authority to investigate
    in the opinion process, we are unable to further advise you in this regard.
    To summa&e, we conclude that the procurement of a monorail transit
    system by the Metropolitan Transit Authority of Harris County is subject to
    competitive bidding, but the board of METRO may grant a waiver of this
    requirement for portions of the project and award wntracts for those portions
    pursuant to competitive negotiation upon a finding of the conditions described in
    section 14(a) of article 1118x. The board is not required to award a single contract
    for the entire project,
    The procurement of a transit system employing monorail
    technology by the Metropolitan Transit Authority of Harris
    County is subject to the competitive bidding requirement of
    article 1118x, V.T.C.S. The board of the authority is not
    required to award a single contract for tbe acquisition and
    wnstruction of the transit system, but in its discretion may
    divide the project into wmponents and award separate contracts
    p.   219
    Honorable John B. Holmes - Page 11            (DM-43)
    for those wmponents.     The board may grant a waiver of
    competitive bidding in favor of competitive negotiation
    procedures upon a finding of the conditions specified in section
    14(a) of article 1118x.
    DAN      MORALES
    Attorney General of Texas
    WILL PRYOR
    First Assistant Attorney General
    MARYKELLER
    Executive Assistant Attorney General
    JUDGE ZOIUE STEAKLEY (Ret.)
    Special Assistant Attorney General
    RENEAHIcKs
    Special Assistant Attorney General
    MADELEINE B. JOHNSON
    Chair, Opinion Committee
    Prepared by Steve Aragon
    Assistant Attorney General
    p.   220