Untitled Texas Attorney General Opinion ( 1969 )


Menu:
  • Honorable Wm. J. Burke      Opinion No. M-366
    Executive Director
    Board of Control            Re:   Acceptance of Bid by
    P. 0. Drawer GG                   Board of Control under
    Capitol Station                   Art. 664-3, V.C.S.,
    Austin, Texas 78711               and related questions.
    Dear Mr. Burke:
    In response to your opinion request concerning
    the above subject, you advised that the State Board of
    Control sent out bid invitations relative to cell block
    equipment to be installed in the Department of Corrections.
    Included in.the invitations were lists of drawings and an
    extensive set of construction specifications, which in-
    cluded the following statement, to wit:
    "All bidders are required to submit,
    as a legal prerequisite to a qualified pro-
    posal, certain models and samples, as herein
    required, for examination by the owner and
    the architect."
    Decatur Iron and Steel Company submitted a bid
    of $552,000 and Southern Steel Company submitted a bid
    of $724,700. Decatur failed to submit  the models and
    samples in accordance with the above quoted specifica-
    tions, but~did submit them shortly after the bids were
    received. The models and samples were acceptable to the
    owner and the architect and you advised us that Decatur
    met all oftthe other requirements of the bid invitations.
    you have requested our opinion as to whether the
    contract may be awarded to Decatur under these facts.
    Certain provisions of the specifications are ambiguous
    and conflicting, as mentioned in your request for this
    opinion, but it is not deemed necessary to discuss these
    provisions in view of the ruling we make herein.
    Article 664-3, Section 5, Vernon's Civil Statutes,
    authorizes the State Board of Control to purchase equipment
    for the State Prison System. Section 8(e) provides that,
    -l&07-
    Hon. Wm. J. Burke, page 2 (M-366)
    "The Board shall have the authority to reject all bids,
    or parts of bids, when the interest of the state will be
    served thereby." Section 8(f) sets forth the matters
    and facts to be considered by the Board of Control in
    awarding contracts to the bidder submitting the lowest
    and best bid. The.statutes, however, do not require the
    Board of Control necessarily to accept the low bid as in
    a true competitive
    .   bidding situation. Section 8(f) con-
    tains no provision requiring that models and samples be
    furnished as a prerequisite to submitting a bid.
    The requirement that bidders submit the models
    and samples for examination is thus an extra-statutory
    condition, in the sense that it is not required by any
    statute. You state that this was required merely for
    "purposes of verification, rather than the determination
    of whether or not the bid was qualified." While the true
    purpose of the requirement, or the essentiality thereof,
    may raise a fact question which this office is without
    power'to resolve, nevertheless the ultimate facts that
    ~a11 parties have acted in good faith and that no fraud
    or overreaching is involved appear to ,be established
    without dispute. Where the requirement is found to be
    truly of the essence of the contract for the bidders,
    under statutes requiring the acceptance of the lowest
    and best bid, a public'body cannot waive the require-
    ments. Case v. Inhabitants of Trenton, 74 A 672 (N.J.
    1909L    If the models or samples were, in fact, not such
    a material requirement of the contract but, looking
    through form to substance, were mere1.y,forthe purpose
    of verification, as you advise, then it is the opinion
    of this office that the irregularity above-mentioned
    may be waived by the Board,of Control, upon a showing
    that all parties acted in good faith and no fraud was
    involved, particularly since the models were furnished
    and examined prior to the awarding of a contract.
    In 13 Tex.Jur.Zd 592, Contracts, Sec. 329, it
    is stated that a party to a contract may waive performance
    of the agreement; or a breach of any of the provisions that
    are for his benefit; thus, he may waive the performance of
    a condition precedent, or a failure to perform within the
    'timeprescribed. In the case of Gaynor Construction Company
    v. Board of Trustees, 233 S.W.Zd 472 (Tex.Civ.App. 1950
    error ref.) the Board of Trustees,a,ccepteda late bid and
    awarded a c&tract to the late bidder. The court held that
    the Board of Trustees could waive the irregularity in the
    time for submission of the low bid, if it acted in good
    - Y808-
    .   -
    Hon. Wm. J. Burke, page 3 (~-366)
    faith, and there was no fraud involved, since the general
    powers of the Board prescribed by Article 2752 authorized
    it to enter into a contract with Gaynor.
    If the Board of Control finds that the model re-
    quirement above discussed was not essential or material
    for the bidders to be on equal footing in submitting their
    bids, and that it w,as required only for purposes of verifica-
    tion! and if the equipment of Decatur meets all the other
    requirements of the bid invitations, it is our opinion that
    the mere fact that thenmodels and samples were submitted
    shortly af~terthe bids were opened will not prevent award-
    ing the contract to Decatur.on the basis of its substantial.
    compliance with the bid requirements. The Board of Control
    is vested with some discretion in the area of bidding re-
    quirements under Article 664-3, Sec. 8(f), such as the
    determination of the "quality, availability, and adapt-
    ability" of the item as well as the "number and scope of
    conditions attached to the bid." The court will not
    interfere.in its exercise of that discretion except for
    some cause which the law recognizes as sufficient to in-
    validate a contract. 49 Am.Jur. 277, States, Territories,
    and Dependencies, Sec. 63. In Attorney General's Opinion
    No. C-676 (1966), we held that under Article 664-3 the
    Board of Control could in the exercise of its discretion
    acceat for verification ourooses additional data after
    bid opening without jeopardizing the status of the bid.
    See also: Overstreet v. Houston County, 36,5S.W.Zd 409
    (Tex.Civ.App. 1963, error ref., n.r.e.) and Headlee v.
    Fryer, 
    208 S.W. 213
    (Tex.Civ.App. 1919, error dism.).
    SUMMARY
    -------
    The Board of Control has the authority
    to waive any extra-statutory bid requirements,
    'which are'found not to be material to the
    proper determination of the lowest and best
    bid as required by the statute. If the Board
    of Control is satisfied that the submitted bid
    of Decatur Iron and Steel Company meets all of
    the other requirements of the bid invitation,
    itbeing established without dispute that no
    fraud or overreaching was involved, and that
    'all parties acted in good faith, the mere fact
    that models and samples were submitted after
    the bids were opened will not otherwise prevent
    the awarding of the contract to.Decatur if such
    irregularity is found not to be of essential
    materiality.
    - 1809-
    Hon. Wm. J. Burke, page 4 (M-366)
    Prepared by Jack Sparks
    Assistant Attorney General
    APPROVED:
    OPINION COMMITTEE
    Kerns Taylor, Chairman
    George Xelton, Vice-Chairman
    James McCoy
    2. T. Fortescue
    Scott Garrison
    James Broardhurst
    John Banks
    W. V. GEPPERT
    Staff Legal Assistant
    -1818   -
    

Document Info

Docket Number: M-366

Judges: Crawford Martin

Filed Date: 7/2/1969

Precedential Status: Precedential

Modified Date: 2/18/2017