Untitled Texas Attorney General Opinion ( 1954 )


Menu:
  •                      November 1.6,,1954
    Mr. Milburn L&than          Opinion No. S-145
    Executive Assistant
    Texas SouthernUniversity   Re:   Payment of liquidated damages
    3201 Wheeler Avenue              for default on completion
    Houston, Texas                   date of st,udentdormitory and
    a student unionbuilding~ at
    Dear Mr. Lathan:                 Texas Southern University.
    On October 15, 1952, a Texas corporation contracted
    to build a dormitory group for Texas Southern University.
    The contract emphasized the importance of the time element in
    completing the work. Tn Paragraph 3 of the General Condi-
    tions in the contract we find the statement:
    "All time limits stated in these documents are
    of the'essence of the contract."
    Again, in Paragraph 27 of the General Conditions is found the
    statement:
    "All contract work shall be completed on or
    before the date set out incontract.
    "Contractors must recognize the necessity
    for completing~the ivorkeon time,:and'they shall
    take all'neees-sary,steps'toassure~this end.
    Contracts-between~Cont~ractorand Sub-Contractors,
    special contractors, and~material dealers shall
    provide properly scheduled~work and deliveries
    to assure  the completion within ~the agreed time
    limit.'
    "Contractors shall g,uaranteethe completion
    of the work 'uponthe agreed date and shall agree
    to then ayment to Owner liquidated damages in the
    sum.of $50.00 per day, for each and every calendar
    day's delay beyond the date fixed for the completion
    ~of'the work and the same shall constit~utea charge
    to be paid by Contractor to Owner, prior to final
    settlement on the Contract.
    "Should Contractor begdelayed in-the prose&-
    tion or completion of the work-by act, neglect or
    default of Owner, of Architect, or of any other
    -.
    &.   Milburn .Lathan,   Page   2 (s-145)
    Contractor employed,by~Owner-'upon~:the
    wdrk,,,or'
    by any dadige caused by fire,:Weather~conditions
    bti'
    C&h& casualty fortihich Contractoris-not
    responsIble:or~by general strikesor 'lockouts'
    caused by the'acta.'of‘employe``,~.then
    the time
    fixed for completion of the~workshall be
    extended,for a perlod equIvalent'tb the time
    lost byereason oftany ofthe causes.aforesaXd,
    .i#hichextended'period'shall':be~det~emriined
    and "
    fixed by:Architect; but no suchallo$iance shalI~'
    be madeunless a claim thereforeis presented in
    writingto 'ArchLtedtwithin forty-eight hours of
    the‘occ'urence.of,'such
    delay."
    Again/in Paragraph 28 of 'the General Conditions is'the
    statement:
    II      The damages set for-the benefZt of    ~
    Owner ~.ihaliapplyat the~time for final settlement
    a8 a charge:against Contractor.. Tin@ being :a
    honslderation in :awardingof the~"contractOwner
    accepts the above stipulateddait@$jesas the ".-
    meas~ure'ofits~damage'in~:theevent that'thework
    is'not substantially .coritplete'd~gnd,',ready,for
    'occupandy,,onthe Contract CompletXon Date; The
    said sums are ~agreed'uponas the measure-of
    lSP,uidated~,damages'andshall not be,considered in
    any sense as penalties."
    Paragraph 3 of ~Addendum#l to this contract againemphasized
    the time~element:
    "@me? ~desires to'be able‘to ,pi?ovide
    hausin for stuaentsfor~ the Pa~U Semester``of
    ,1953-,e:.,
    opening'~on-or~,~aboutSeptember.~1,~,1953.
    Bidders'should'~notethat both loti'cost&-&time
    fo+``obxipaticyare ~of'vital:concern.,to~
    Owner and
    that cost should ``nbt be penalized adversely to
    save time and"simllarly~that time~should'not be
    penallied tomsavecost.     Tiine~of'completion,,how-
    ever'may 'be a factor in awarding a.,contractas
    betHeen twosbidsreasonably close'together. At
    least partial ocixpancy of Hen'sand Women's @ormi-
    tory Buildings by Septemb~erI,,1953 is desirable,
    tiith~completionof 'the remainderof the,work.there-
    after as is feasible.,"
    The Contractor's 'bid,df 427calendar'~days 'was
    accepted by the Board~of Directors'of'Texas Southern
    ,University. Completion @at,eaccording ,to the bid'submitted
    Mr. Milburn Lathan, page 3 (s-145)
    by Contractor was'December 16, 1953. Under the provisions
    of Paragraph 27, supra,'the Contractor requested"and the
    Architect granted extensionsof 60'days because of weather
    conditions and of 70 days because of general strikes. This
    total 130 days extended the Contract Completion Date to April
    25, 1954. However, Contractor did not complete the
    dormitory group contract ,untilAugust l/1954, when the
    Union Building was substantially ready~for use. The two
    dormitories were substantially ready for use on or about
    June 1, 1954.
    You ask three q,uestionsin regard to the foregoing
    statements:
    1. Is the provision in the contract
    specifying a fixed sum as liquidated damages for
    default in completion date an enforceable obli-
    gation under the facts presented?
    2. Is the collection of the sum specified
    as liquidated damages discretionary or mandatory
    with Texas Southern University?
    3. Does the completion date of the last com-
    ~pleted building determine the completion date or
    can a partial completionbe recognized for the
    p'urposeof determining liquidated damages on a
    pro rata basis?
    The leading ~case'on the subject of liquidated
    damages is Sun Printing and Publishing Association v. 'Moore,
    183~U.S:642, 22 S,Ct. ,240, 
    46 L. Ed. 366
    (1902). Beginning
    at page 673 the Court q.uotesfrom an early New York case the
    applicable rule:
    ?ihen the parties to a contract, in which
    the damages to be ascertained, growing out of a
    breach, are uncertain in amount, mutually agree
    that a certain sum shall be the damages, incase
    of fail'ure to perform, and in language plainly
    expressive of s,uchagreement, I know of no sound
    principle or rule applicable to the construction
    of contracts, that will enable a.court of law to
    say that they intended something else. Where
    the sum fixed is greatly disproportionate to the
    presumed actual damages, probably a court of
    equity may relieve; b,uta court of law has no right
    to erroneously construe the intention of the
    parties, when clearly expressed, in the endeavor
    Mr. Milburn Lathan, page 4 (S-145)
    to make better contracts for themthan   they have
    made for themselves. . *'
    In the instant situation it is clearly apparent
    that the University has suffered~substaritial,actualdamage
    &used by~the delay. The construction of ~the'buildings
    was financed'tiiththe proceeds froman issue of revenue
    bonds. The bonds are to be paid fromthe revenues   earned
    from the operation of the buildings, It has been determined
    that a revenue in excess of $3,000 per month may reasonably
    be expected from each of the dormitories, and a revenue in
    excess of $50,000 per month may reasonably be expected from
    the operation of the UnionBuilding.   The liquidated'damages
    provided in the contract have a reasonable relationto the
    acixal damages, are not punitive, and'therefore are valid
    charges against the Contractor. Stewart 'v.Basey,,l50
    Tex. 666, 
    245 S.W.2d 484
    (1952).
    The provision forliquidated damages need not be
    apportioned because some of the buildings were completed
    at an earlier time than the completion date for the last
    b,uilding.-The contract was a~single contract for three
    buildings, and until the last b,uildingwas completed it can-
    not be contended that there was compliance.with-the contract.
    The~case .of Wise v. United States, 
    249 U.S. 361
    , 39 S.Ct;
    303, '63,L.Ed. 647 (1919) involved a contract to build two-
    buildings for the Department of Agriculture in Washington,
    D.C. The Supreme Court expressly rejected the'argument
    that an apportionment of liq,uidateddamages should'be
    accorded for the completionof 'one building prior to final
    completion of 'the other building and of ~the contract. In
    concluding the Court made a statement which controls your
    situation:
    "There is nothing in the contract or in the
    record to indicate.that the partiesdid not take
    into consideration, when estimating ,theamount of
    damage which would be caused by delay,,the prospect
    of one building being delayed and the other not, and
    the amount of the damages stipulated, having regard
    to the circumstances of the case, may well have been
    adopted with reference to the probability of such
    a result."
    Since the charge for liquidated damages has
    accr,uedagainst the~Contractor,,it is now mandatory that
    the~Board of Directors of Texas Southern ~Universitycollect
    this liquidated sum. Sections 53 and 55 of Article III of
    the Constitution of Texas prohibit the~release of any
    indebtedness, liability or obligation of any corporation or
    Mr. Milb,urnLathan, page 5 (S-145)
    individual to this State. The Board of Directors of Texas
    Southern University operate under powers delegated to them
    by the Legisla,ture. Certainly the Legislat~ure'hasnot,
    and could not grant to them powers which the Legislat,urehas
    not itself.
    SUMMARY
    The Provision in the dormitory group contract
    specifying lfquidated damages is an enforceable
    obligation.
    The completion date on the last building
    determines the completion date of the contract.
    No apportionment of liq,uidateddamages is provided.
    It is mandatory that the Board of Directors of
    Texas Southern University collect the s'umspecified
    as liquidated damages.
    Yours very   truly,
    JOHN BEN SHEPPERD
    Attorney General
    BY
    APPROVED:                           Billy E. Lee
    Assistant
    J; C. Davis, Jr.
    County Affairs Division
    'W. V. Geppert
    Reviewer
    Phillip Robinson
    Reviewer
    Robert S. Trotti
    First Assistant
    BEL:es
    

Document Info

Docket Number: S-145

Judges: John Ben Shepperd

Filed Date: 7/2/1954

Precedential Status: Precedential

Modified Date: 2/18/2017