Ginger Light and James Justin Light v. Mike Thoma ( 2021 )


Menu:
  •                                    In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-20-00311-CV
    GINGER LIGHT AND JUSTIN LIGHT, APPELLANTS
    V.
    MIKE THOMA, APPELLEE
    On Appeal from the 99th District Court
    Lubbock County, Texas
    Trial Court No. 2019-534,943, Honorable William C. Sowder, Presiding
    June 14, 2021
    MEMORANDUM OPINION
    Before QUINN, C.J., and PARKER and DOSS, JJ.
    Appellants, Ginger and Justin Light, appeal the trial court’s judgment awarding
    damages to appellee Mike Thoma in the parties’ residential construction contract dispute.
    On appeal, the Lights challenge the sufficiency of the evidence to support the damages
    awarded to Thoma, the trial court’s finding that the Lights materially breached first, and
    the trial court’s adverse finding that Thoma did not fraudulently file a mechanic’s and
    materialman’s lien against the property. We affirm.
    Background
    In August 2018, the Lights and Thoma entered into a fixed price construction
    contract. Through it, Thoma agreed to build the couple’s home for $364,354. The fixed
    price would be paid to Thoma through periodic draws when certain milestones or phases
    of the construction were substantially completed.
    Thoma proposed a draw request form and utilized it in draw requests 1 through 5.
    Each were emailed to and approved by the Lights without complaint. Each was also paid
    by the Lights. They totaled $224,423.02.
    Also included in the Light-Thoma contract was a procedure for change orders.
    They came into play when the Lights made revisions or additional requests that were not
    included in the original agreement.
    By February 5, 2019, Thoma submitted Draw Request #6 and demand for payment
    on certain change orders. The Lights refused to pay either. They questioned the detail
    or purported lack thereof in the draw request and maintained that they had paid for certain
    items included in it. They communicated an offer to modify the contract, which offer
    Thoma refused. That, coupled with their failure to resolve their differences, resulted in
    Thoma forwarding them a default notice, calling off subcontractors, and ceasing work on
    the project. He also sued the Lights for breach of contract, contending that they failed to
    pay the draw request and change orders as required by their agreement. The Lights
    counterclaimed for breach of contract and fraudulently filing a mechanic’s and
    materialman’s lien. The Lights contend that Thoma failed to comply with the agreement’s
    draw request procedure and failed to provide the quality and grade of workmanship and
    materials as agreed upon in the contract.
    2
    Thoma sought damages in the form of the amount he was “in the hole” at that point
    in the project. As he explained, the arrangement with the lender in this type of agreement
    was to pay a certain percentage of the fixed price upon the builder’s substantial
    completion of certain phases or “milestones” of the project. Its effect was to have the
    contractor cover the construction expenses incurred in reaching that milestone. As
    Thoma explained, he was either even or in the hole on a project until it approached
    completion. Only as the project reached completion would he begin to realize a profit.
    When Draw #6 was submitted, he had expended $249,767 and been paid only
    $224,423.02 toward the fixed price. His lost profit also approximated $49,953.
    Trial was to the bench. It was tasked with determining which of the two parties
    breached first and concluded that the Lights did. That breach occurred when they refused
    to pay the submitted draw request and change order. Damages of $24,750 were then
    awarded to Thoma. They generally encompassed the difference between his
    expenditures and the draws paid by the Lights. In turn, the claims asserted by the Lights
    were denied.
    Standards of Review
    The standard of review is well-settled and need not be reiterated. It is adequately
    explained in Tex. Outfitters Ltd., LLC v. Nicholson, 
    572 S.W.3d 647
     (Tex. 2019), City of
    Keller v. Wilson, 
    168 S.W.3d 802
     (Tex. 2005), and Cain v. Bain, 
    709 S.W.2d 175
     (Tex.
    1986) (per curiam).
    Sufficiency of Evidence Concerning Breach
    We first address whether Thoma materially breached the contract. In that regard,
    the Lights posit:
    3
    this Court should reverse the district court’s decision and find that Thoma’s
    refusal was a material breach. Because he never actually provided a
    compliant draw request, the Lights’ obligation was never triggered. In the
    alternative, if Thoma’s performance was not material, then the Lights’
    performance under the same provision should not be material either.
    Moreover, even if this Court were to disagree and find that Thoma’s
    compliance was not material, this Court should still reverse because the
    undisputed evidence shows that Thoma breached the Contract—whether
    material or not. As a result, the Lights were entitled to seek their damages
    against Thoma and at the least, offset Thoma’s damages.
    We overrule the issue and begin by assessing the sufficiency of the evidence
    underlying the trial court’s pertinent fact finding. The latter consisted of the court stating:
    “Thoma did not commit a material breach of the Contract; the defects of Thoma’s
    performance of which the Lights complained did not seriously impair the purposes
    underlying the Contract.” Those defects consisted of his failure to include information
    specified within paragraph 5(C) of the contract in his 6th draw request. The paragraph
    said, among other things, that “each draw shall reflect the construction costs and any
    compensation to the Builder for the time and effort expended in connection with this
    transaction” and “[t]he Draw Request shall include the name and address of each person
    who subcontracted directly with Builder and who Builder intends to pay from the
    requested funds.” Such was omitted from the sixth request, just as it was from the prior
    five. Yet, the Lights paid the prior five in short order and without demanding compliance
    with 5(C).
    Materiality is an issue “to be determined by the trier of facts.” Bartush-Schnitzius
    Foods Co. v. Cimco Refrigeration, Inc., 
    518 S.W.3d 432
    , 436 (Tex. 2017) (per curiam).
    In making the determination, the Texas Supreme Court outlined a number of nonexclusive
    considerations that are “significant in determining whether a failure to perform is material”:
    4
    (a) the extent to which the injured party will be deprived of the benefit which
    he reasonably expected;
    (b) the extent to which the injured party can be adequately compensated for
    the part of that benefit of which he will be deprived;
    (c) the extent to which the party failing to perform or to offer to perform will
    suffer forfeiture;
    (d) the likelihood that the party failing to perform or to offer to perform will
    cure his failure, taking account of the circumstances including any
    reasonable assurances; [and]
    (e) the extent to which the behavior of the party failing to perform or to offer
    to perform comports with standards of good faith and fair dealing.
    
    Id.
     at 436–37 (Tex. 2017) (quoting Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 199 (Tex. 2004) (per curiam)). Regarding the first, it seems that the less the
    nonbreaching party is deprived of the expected benefit of the contract, the less material
    the breach. Hernandez v. Gulf Group Lloyds, 
    875 S.W.2d 691
    , 693 (Tex. 1994). And,
    here, the importance of the expected benefit allegedly denied the Lights (i.e., being
    denied information about the subcontractor being paid by the draw) is best illustrated by
    the Lights response to its omission. They had been denied it five previous times, and
    their response to those denials consisted of paying the requests without complaint. As
    we have oft said, “actions speak louder than words.” In re State, 
    572 S.W.3d 264
    , 276
    (Tex. App.—Amarillo 2018, orig. proceeding) (Quinn, C.J., concurring) (op. on reh’g); In
    re Marriage of McMahen, No. 07-13-00172-CV, 
    2014 Tex. App. LEXIS 6154
    , at *8 (Tex.
    App.—Amarillo June 6, 2014, no pet.) (mem. op.). The response exhibited by the Lights
    to Thoma’s prior defaults reveals an intent to assign minimal importance to the aspects
    of 5(C) in dispute. To that we also add the evidence about the type of construction
    contract they signed. It was one of “fixed price.” Being of that ilk, industry norm made
    5
    payment of a draw dependent upon the stage of completion, as opposed to which
    subcontractor was getting paid what sum. So, according to Thoma, his expenditures were
    irrelevant in the draw request process and to the Lights’ obligation to pay them. That, in
    turn, is some evidence indicating the omission did not violate standards of good faith and
    fair dealing in the home construction trade.
    Next, no one cited us to evidence addressing whether the Lights could be
    adequately compensated for Thoma’s failure to provide the omitted data. However, the
    Lights argue they could not since, without the information, “they would never know
    whether the correct goods were installed, unless they were to have another party examine
    the goods or somehow obtain the invoices from the third party.” Yet, Thoma told the trial
    court that he normally provided his clients the information in question if they asked for it.
    So too did he attest to providing the Lights with the name and contact information of the
    subcontractors he used. This is some evidence that the Lights always had the means to
    obtain the information they belatedly deemed important and with which to safeguard
    against injury arising from the installation of defective or noncompliant materials. Yet,
    they apparently did not ask for it until after 1) paying five prior draw requests and 2)
    animosities developed on both sides resulting in mutual intransigence.
    We remind the parties that the standard of review does not allow us to reweigh the
    evidence and select who to believe and who should win. Our task at bar is twofold. We
    first assess whether evidence supports the trial court’s decision when viewing the record
    in a light favorable to that decision. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827
    (Tex. 2005). Then, we assess whether the favorable evidence, if any, is so outweighed
    by all other evidence as to render the trial court’s decision manifestly unjust or clearly
    6
    wrong, not simply unjust or wrong. See Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 406–07 (Tex. 1998). Rather than attempt to 1) explain why no evidence supports
    what the trial court decided or why supporting evidence actually has no value for purposes
    of a legal sufficiency analysis or 2) compare supporting and nonsupporting evidence for
    purposes of a factual sufficiency analysis, the Lights tend to foist upon us evidence
    favoring their position. That tact seldom affords much assistance when addressing
    disputes implicating the sufficiency of the evidence. Nonetheless, we found more than
    some evidence in the record upon which a fact-finder at bar could reasonably conclude
    that noncompliance by Thoma with paragraph 5(c) was an immaterial breach and that the
    sum of the remaining evidence does not render that conclusion manifestly unjust or
    clearly wrong.       So the finding was not bereft of either legally or factually sufficient
    evidentiary support.1
    As for the contention that providing the information in 5(C) “triggered” the Lights’
    duty to pay, that harkens to the law of conditions precedent. See Solar Applications
    Eng’g, Inc. v. T.A. Operating Corp., 
    327 S.W.3d 104
    , 108 (Tex. 2010) (defining “condition
    precedent” as an event that must occur before a right can accrue to enforce an obligation).
    To render performance specifically conditional, terms such as “provided that,” “on
    condition that,” or some other phrase denoting conditionality must normally be utilized in
    1 It is also notable that the Lights failed to address a distinct material breach of theirs found by the
    court. That breach involved their nonpayment of the change orders. Paragraph 5(C) did not encompass
    the obligation to pay them. So, irrespective of whether Thoma’s failure to comply with 5(C) constituted a
    material breach relieving the Lights from paying the draws, it stands that they materially breached the
    agreement by refusing to pay the change orders. More importantly, demand for their payment came days
    before Thoma submitted the draw requests. Thus, that breach may well have preceded any alleged
    obligation that Thoma had to comply with 5(C) and actually relieved him from complying with 5(C). See
    PAJ, Inc. v. Hanover Ins. Co., 
    243 S.W.3d 630
    , 633 (Tex. 2008) (stating that a material breach by one party
    relieves the other from having to perform contractual obligations). And, if he had no obligation to comply
    with 5(C), then the sum and substance of the Lights’ current argument would be irrelevant.
    7
    the agreement. Daniels v. Cortez, No. 01-18-00086-CV, 
    2019 Tex. App. LEXIS 5914
    , at
    *7 (Tex. App.—Houston [1st Dist.] July 11, 2019, no pet.) (mem. op.). If such language
    is not used, then generally the clause will be construed as a covenant to prevent a
    forfeiture. Criswell v. European Crossroads Shopping Center, Ltd., 
    792 S.W.2d 945
    , 948
    (Tex. 1990) (op. on reh’g). This is so because the absence of conditional language is
    probative of the parties’ intention to create a promise as opposed to a condition. 
    Id.
    Conditional language is missing from the obligation of Thoma to provide the data
    mentioned in 5(C). Nor from the context of the entire contract can we garner an intention
    to make the provision of the data a condition precedent to the Lights’ payment of a draw.2
    Thus, we reject the proposition that their duty to pay the sixth draw request was never
    “triggered.”
    Regarding the Lights’ allegation about breached contract and a right to pursue
    damages even if the breach were immaterial, the Lights did not assert below such a cause
    of action relating to noncompliance with 5(C). According to their live pleading, their
    breached contract allegation encompassed overpayment to and the cessation of work by
    Thoma.      Nothing was said about the contractor breaching the contract through
    noncompliance with 5(C). More importantly, the Lights have cited us to no authority
    holding that if a judgment is reversed, a reviewing court should afford a litigant opportunity
    to damages for a claim they neglected to allege.
    Sufficiency of Evidence on Damages
    The Lights next challenge the sufficiency of the evidence to support the trial court’s
    $24,750 award of damages to Thoma. We overrule the issue.
    2 Indeed, the Lights having paid the earlier draws without demanding the data hardly suggests they
    ever intended the part of 5(C) in dispute to be a condition to their performance.
    8
    We begin with a housekeeping issue. Trial began with the court reading into the
    record the stipulation regarding several items of evidence from both parties. It reflected
    that the parties agreed to the admission of many exhibits. Absent from the trial court’s
    recitation, though, is mention of Plaintiff’s Exhibit 16. The latter consisted of various
    receipts and invoices memorializing Thoma’s expenditures on the project. The record
    further indicates that the exhibit was not formally offered and accepted into evidence.
    Nevertheless, both parties referred to it without objection during the trial and treated it as
    if it were admitted.
    This is not the first time that litigants have treated exhibits as admitted when they
    formally were not. In those circumstances, reviewing courts followed the parties’ lead
    and deemed the exhibits part of the evidentiary record. See e.g., In re J.R., No. 07-18-
    00240-CV, 
    2018 Tex. App. LEXIS 7862
    , at *6–7 (Tex. App.—Amarillo Sept. 26, 2018,
    pet. denied) (mem. op.) (stating that though not formally admitted, the exhibit was, “for all
    practical purposes, admitted[,]” given the absence of an objection at trial) (citing, inter
    alia, Requeno v. State, No. 10-11-00046-CR, 
    2011 Tex. App. LEXIS 5609
    , at *2–3 (Tex.
    App.—Waco July 20, 2011, no pet.) (mem. op., not designated for publication)); see also
    Tex. Dep’t of Pub. Safety v. Monroe, 
    983 S.W.2d 52
    , 56 (Tex. App.—Houston [14th Dist.]
    1998, no pet.) (treating evidence as admitted because the trial court and the parties so
    treated it). Thus, we follow that lead and treat Exhibit 16 as part of the evidentiary record
    here.
    Exhibit 16 having been part of the evidentiary record before the trial court, it was
    incumbent to include it in the appellate record. That is, when an appellant complains of
    the legal or factual sufficiency of the evidence, the appellant’s burden to show that the
    9
    judgment is erroneous cannot be discharged in the absence of a complete or an agreed
    statement of facts. Schafer v. Conner, 
    813 S.W.2d 154
    , 155 (Tex. 1991) (per curiam).
    Therefore, a court reviewing the sufficiency of the evidence may overrule an appellant’s
    complaint concerning, as here, the sufficiency of the evidence supporting damages
    because, in the absence of a complete appellate record, it is presumed that the omitted
    evidence supports the trial court’s judgment. See id.; see also Sandoval v. Comm’n for
    Lawyer Discipline, 
    25 S.W.3d 720
    , 722 (Tex. App.—Houston [14th Dist.] 2000) (“Because
    [appellant] did not file a complete record on appeal or comply with the partial reporter’s
    record provisions of Appellate Rule 34.6, we continue to presume the omitted portions of
    the reporter’s record support the judgment.”). We employ this presumption here and
    presume that omitted Exhibit 16 supports the trial court’s judgment in favor of Thoma.
    And the evidence that is contained in the appellate record also supports the trial
    court’s judgment. Plaintiff’s Exhibit 15 consists of a document entitled “Job Estimates vs.
    Actuals for Light Home.” It depicts actual costs for goods and services expended. Items
    and services which had not yet been purchased or performed were shown to be “0.00.”
    Total expenditures shown were $249,767.00. See Supertrack Arlington v. Proton, PRC,
    Ltd., No. 07-19-00223-CV, 
    2021 Tex. App. LEXIS 1638
    , at *5–10 (Tex. App.—Amarillo
    Mar. 4, 2021, no pet. h.) (mem. op.) (per curiam) (wherein purchases and payments within
    a general ledger were found to be probative evidence illustrating damages). Deducting
    from that amount the draws actually paid by the Lights (i.e., $224,423.02) resulted in a
    difference of $25,343.98. Also within Exhibit 15 is a company “Custom Transaction Detail
    Report.” It illustrated that Thoma’s expenses relating to the project exceeded payments
    10
    from the Lights by about $24,157 as of February 16, 2019. This comported with Thoma’s
    own testimony.
    The fact-finder generally has discretion to award damages within the range of
    evidence presented at trial. Keywordvalet, LLC v. Parts Base, Inc., No. 01-20-00078-CV,
    
    2021 Tex. App. LEXIS 2187
    , at *12 (Tex. App.—Houston [1st Dist.] Mar. 23, 2021, no
    pet.) (mem. op.) (citing Gulf States Utils., Co. v. Low, 
    79 S.W.3d 561
    , 566 (Tex. 2002)).
    The foregoing evidence illustrates that Thoma expended between $24,157 and
    $25,343.98 more than what he had been paid on the project. The trial court’s award of
    $24,750 falls within that range. Consequently, the award had both legally and factually
    sufficient evidentiary support.
    Sufficiency of Evidence on Adverse Finding Concerning Fraudulent Intent
    The final issue we address is Lights’ contention that the trial court erred in not
    finding that Thoma fraudulently filed a mechanic’s and materialman’s lien. Purportedly,
    he knew he earlier had transferred the lien to AgTexas. We overrule the issue.
    Though the trial court invalidated the lien, it found Thoma’s lien had been filed
    without the intent to defraud. The latter is an element of the claim at issue. See TEX. CIV.
    PRAC. & REM. CODE ANN. § 12.002(c) (West 2017) (stating that when a lien is filed
    pursuant to Chapter 53 of the Texas Property Code involving liens of contractors and
    materialmen, a complaint seeking damages must also prove the encumbrance was filed
    with the intent to defraud). “Intent is a fact question uniquely within the realm of the trier
    of fact . . . .” Spoljaric v. Percival Tours, Inc., 
    708 S.W.2d 432
    , 434 (Tex. 1986). That
    trier of fact is free to draw reasonable inferences from both direct and circumstantial
    evidence. Consol. Reinforcement, L.P. v. Cheraif, No. 04-18-00443-CV, 2019 Tex. App.
    
    11 LEXIS 4371
    , at *4–5 (Tex. App.—San Antonio May 29, 2019, no pet.) (mem. op.) (citing
    Zaragoza v. Jessen, 
    511 S.W.3d 816
    , 823–24 (Tex. App.—El Paso 2016, no pet.)). So
    too may it draw reasonable references about intent from a party’s actions. Aquaplex, Inc.
    v. Rancho La Valencia, Inc., 
    297 S.W.3d 768
    , 775 (Tex. 2009) (per curiam).
    As part of the transaction between Thoma and the Lights, the parties executed a
    document stating:
    Owner [The Lights] grant to Builder [Thoma] a mechanic’s lien to secure
    performance of the obligations of Owner. If Owner is obtaining an interim
    construction loan, Builder shall assign to the interim construction lender
    a portion of Builder’s mechanic’s lien equal to the amount of the
    interim construction loan advanced to or for the benefit of the Owner and
    paid to Builder, and to subordinate any remaining amount of Builder’s Lien
    to the interim construction loan. In the event that the improvements to be
    erected fail for any reason to be completed, or fail to be completed
    according to this Contract, . . . then Builder and the holder of the
    indebtedness under the builder’s and mechanic’s lien shall have a
    valid and subsisting lien for the Total Contract Price less such amount
    as would be reasonably necessary to complete the improvements
    according to the Construction Documents. In the event of any conflicts
    between this Contract and the builder’s and mechanic’s lien contract, the
    terms of this Contract shall control.
    (Emphasis added). Needless to say, the provision’s meaning is somewhat uncertain.3
    While we do not say that the legal effect of the contract was to allow Thoma to keep a lien
    after assigning one to a lender, we cannot ignore that one could so read it. Indeed, the
    first portion of the agreement (as reflected in the paragraph) obligated the contractor to
    assign a mechanic’s lien to the lender. Yet, the rights assigned were envisioned as pro
    rata. That is, they equaled only the amount of the construction loan advanced. So,
    between Thoma and the Lights, the contractor retained some liens, according to the
    3When the Lights’ trial counsel delved into how Thoma could retain lien rights via the contract when
    he had already assigned them to a lender, Thoma answered that he did not know because he was not a
    lawyer.
    12
    provision. The paragraph also indicates that the Lights agreed to give both the contractor
    and lender a lien equal to the “Total Contract Price,” less certain sums. So, under either
    provision, one could argue that Thoma retained some if not all his rights to a mechanic’s
    lien, at least between him and the Lights.
    Again, we are not construing the paragraph for purposes of determining its legal
    meaning. Instead, we assess what the effect of its words may have had on the element
    of intent to defraud. To the extent the paragraph can be read, correctly or not, as
    permitting Thoma to retain lien rights despite an earlier assignment of them to a lender,
    that is evidence which the fact-finder reasonably could construe as indicating the builder
    lacked the intent to defraud when actually filing the lien. And, again, the paragraph can
    be so read. Consequently, we cannot say that the trial court’s finding of no intent to
    defraud lacked legally or factually sufficient evidentiary support or was otherwise wrong.
    Having overruled the Lights’ issues, we affirm the trial court’s judgment in favor of
    Thoma.
    Brian Quinn
    Chief Justice
    13
    

Document Info

Docket Number: 07-20-00311-CV

Filed Date: 6/14/2021

Precedential Status: Precedential

Modified Date: 6/17/2021