Sandeep Patel and ERCC Construction Company, LLC v. Warwick Construction, Inc. ( 2022 )


Menu:
  • Opinion issued January 20, 2022
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-20-00208-CV
    ———————————
    SANDEEP PATEL AND ERCC CONSTRUCTION COMPANY, LLC,
    Appellants
    V.
    WARWICK CONSTRUCTION, INC., Appellee
    On Appeal from the 268th District Court
    Fort Bend County, Texas
    Trial Court Case No. 14-DCV-219641
    MEMORANDUM OPINION
    Appellee Warwick Construction, Inc. sued Sandeep Patel and ERCC
    Construction Company, LLC, and others who settled before trial, for unpaid amounts
    owed on a contract to build a hospice facility. Warwick also alleged that Patel and
    others committed fraud and engaged in a conspiracy to commit fraud. A jury found
    that ERCC breached the construction contract and violated the Texas Prompt Pay
    Act, that Patel and ERCC violated the Texas Construction Trust Fund Act by
    misapplying funds and committed fraud against Warwick. The jury found the
    following amounts of damages: $463,406.48 for breach of contract; $373,000 for
    misapplication of trust funds; $33,000 for fraud, plus $500,000 each against Patel
    and ERCC as exemplary damages relating to fraud. The trial rendered judgment on
    the jury verdict, awarding Warwick damages for breach of contract, misapplication
    of trust funds, fraud, exemplary damages of $200,000 each (the statutory maximum)
    against Patel, pre- and post-judgment interest, statutory penalty interest for failing
    to promptly pay, and attorney’s fees. The final judgment made ERCC and Patel
    “jointly and severally” liable for “$372,000.00 for ERCC’s breach of contract and
    for Patel’s [misapplication of trust funds], respectively,” and awarded “an additional
    $91,406.48 for ERCC’s breach of contract,” which is the difference between the
    jury’s award for breach-of-contract damages and $372,000.
    Patel and ERCC appealed, raising seven issues. They assert that the trial court
    erred by: (1) assigning joint and several liability for breach-of-contract damages
    awarded solely against ERCC; (2) violating the “one satisfaction rule” and awarding
    double recovery by rendering judgment on both breach of contract and
    misapplication of trust funds; (3) failing to apply settlement credits to the
    misapplication of trust funds damages award; (4) rendering judgment on fraud when
    2
    the contract language allegedly precludes a finding of justifiable reliance;
    (5) rendering judgment on fraud when the evidence was legally insufficient and
    (6) factually insufficient; and (7) awarding constitutionally excessive exemplary
    damages based on legally and factually insufficient evidence.
    Because we conclude that the one satisfaction rule applies in this case and that
    recovery is not viable on either the claim for misapplication of trust funds or the
    claim for fraud, we reverse the trial court’s judgment and render take-nothing
    judgment on the misapplication of trust funds claim and the fraud claim, and we
    remand to the trial court for entry of judgment consistent with this opinion, including
    calculation of prejudgment interest.
    Background
    Sandeep Patel is the managing member of ERCC. Syed Anwar, Aman Jafar,
    and Khurram Ibrihim are the other members of ERCC, which was formed in 2011.1
    Patel, Anwar, Jafar, and Ibrihim also had an ownership interest in Altus Sugarland
    Realty, L.P. (“Altus”). Patel also owns Sterling Group of Engineering Companies
    (“Sterling Engineering”). Stanley Robinson worked for ERCC. Years before
    working for ERCC and while working for another company, Robinson hired and
    1
    Anwar, Jafar, and Ibrihim settled with Warwick before trial, and they are not parties
    to this appeal.
    3
    worked with Tony Annan, who founded and remained as the president of Warwick
    Construction.
    In late October 2013, Altus entered into a contract with ERCC to build the
    Altus Hospice Home (“Altus Hospice”), a health care facility to be located in Sugar
    Land, Texas. Sterling Engineering was designated as the “architect” for the project.
    The contract price was $3,200,000. The contract required ERCC as “contractor” to
    provide a payment and performance bond in the amount of $3,200,000. But ERCC,
    which had not yet done any construction projects, was unable to obtain a payment
    and performance bond.
    Robinson invited Annan to bid on the Altus Hospice job, and Warwick
    Engineering submitted a bid. Although Annan later testified that he initially believed
    that Warwick would be contracting directly with Altus, Annan learned that ERCC
    would be contracting directly with Altus. In November 2013, ERCC as “design-
    builder” for the project entered into a contract with Warwick, as contractor, for the
    construction of Altus Hospice. The contract stated that it “represents the entire and
    integrated agreement between the parties hereto and supersedes prior negotiations,
    representations or agreements, either written or oral.” The contract price was
    $3,200,000. The contract required Warwick to provide a payment and performance
    bond in the amount of $3,200,000. The parties later agreed to remove landscaping
    from the scope of work contractually assigned to Warwick. Warwick also agreed
    4
    that $352,000 of its contract price would instead be paid to Sterling Engineering for
    project management.
    Warwick obtained a payment and performance bond, which Annan personally
    guaranteed. The bond was accepted by Altus in lieu of a bond obtained by ERCC.
    According to Patel’s trial testimony, ERCC reimbursed Warwick for the cost of
    obtaining the payment and performance bond. Construction began, and, in
    accordance with the contract, Warwick submitted applications for payment on a
    monthly basis. The first five applications for payment were timely paid in full.
    According to Annan, the next six or seven applications were not timely paid, but
    they were paid by the time of trial. Annan testified that not being promptly paid may
    have hurt his relationships with his subcontractors and could harm his business in
    the future, but he did not quantify these costs. Annan also testified at trial that ERCC
    still owed Warwick $463,406.48 for work completed pursuant to change orders,
    which are changes to the scope of the construction project due to engineering
    requirements or owner choices.
    Warwick filed a mechanic’s and materialman’s lien and a constitutional lien
    against Altus Hospice, and later Warwick filed suit to foreclose the liens. Warwick
    amended its petition, adding various claims against ERCC, Patel, and Sterling
    Engineering. Warwick settled with Altus, and Sterling Engineering declared
    bankruptcy. Warwick removed the case to the bankruptcy court, and when Sterling
    5
    Engineering’s bankruptcy was finally resolved, the case was remanded to state court
    for disposition of Warwick’s remaining claims against ERCC and Patel.
    In response to interrogatories, and prior to the settlement with Anwar, Jafar,
    and Ibrihim, Warwick stated:
    After all just and lawful offsets, payments, and credits have been
    allowed, Warwick remains unpaid in the amount of $870,302.03 for the
    labor, materials, and equipment it provided to the Defendants for which
    it has not been paid, plus $352,000 which was fraudulently withheld
    from its contract based on the fraudulent misrepresentations that
    [Sterling Engineering] would act as the Project Manager in exchange
    for such funds.
    The trial court held a pretrial hearing on the parties’ motions in limine at which
    Warwick raised the issue of settlements. Warwick stated that it had received a
    settlement from Altus on its lien claim, that it had informed ERCC and Patel of the
    amount, and it asked for any comments about settlements to be excluded from trial.
    Warwick then asked the court how it preferred to address settlement credits:
    So the issue we wanted to talk about with you is how—how do you
    want us to do it with regard to our damages. For instance, we have a set
    damage amount, plus attorney’s fees. We received a settlement from
    Altus. A portion of that settlement would go to the segregated
    attorney’s fees that are just Altus related and then the rest goes to the
    principal of our damage number.
    We can do it one of two ways. We can either present our whole damage
    model without deducting anything out for the Altus settlement, and in
    the event we prevail at the time that judgment is entered, you apply the
    credit at that time to reduce our judgment by whatever we have received
    on the principal and the attorney’s fees. Or we can present the reduced
    number taking out the amount that we’ve received that applies to the
    principal.
    6
    The trial court responded: “Let’s do it that way.” ERCC and Patel’s counsel
    then stated on the record that Anwar, Jafar, and the estate of Ibrihim had reached a
    settlement with Warwick. The record indicates that Anwar, Jafar, and the estate of
    Ibrihim each agreed to pay Warwick $40,000, without joint and several liability, to
    fully settle the claims against them.
    The next day, before opening statements, ERCC and Patel’s counsel objected
    to Warwick pre-applying a settlement credit:
    We . . . believe it’s appropriate for the plaintiff to put on all their
    evidence of whatever damages are. If they recover, then we can
    approach the Court as to how that settlement credit should be applied.
    Because they’ve asserted multiple causes of action, multiple theories of
    recovery against multiple defendants, and depending on how that
    shakes out, we don’t think we can sort of pre- you know, do the pre-
    arithmetic on the potential settlement credit at this time.
    The trial court disagreed, saying: “I think we can do the pre-arithmetic and I
    think that that would be a better way to get away from the jury issues that they really
    aren’t going to be dealing with. . . [I]f you’ve already had those amounts in pre-
    settlement, then we need to take them out.” Warwick’s counsel agreed with the trial
    court saying: “Yes, that’s correct. . . . [I]nstead of saying we’re seeking $870,000,
    we’re seeking a reduced amount . . . I’ve adjusted last night based on the $120,000
    settlement that was recorded on the record yesterday. I took that out as well . . . .”
    The trial court stated: “We will continue with the order of the decision I made
    yesterday.”
    7
    The case was tried to a jury. At trial, Patel acknowledged that Warwick was
    not paid for the labor and materials for the change orders at issue. Annan testified
    that ERCC owed Warwick $463,406.48 for charges arising from the change orders.2
    Annan acknowledged that ERCC informed Warwick that it needed more
    documentation relating to some of the change orders in order to authorize payment.
    Tiffany Nowak, who worked for Sterling Engineering and handled all the accounting
    for the project, also testified that ERCC did not receive sufficient documentation
    from Warwick on its payment requests relating to the change orders.
    Nowak testified about the accounting records for the project. She said that
    ERCC had one bank account and did not maintain separate accounts for different
    projects. Nowak testified that ERCC received a total of $2,883,074.19 in payments
    from Altus for the Altus Hospice project, and $2,506,422.74 of that amount was paid
    to Warwick. She also testified that ERCC paid a total of $2,891,156.60, which was
    more than it received from Altus, to complete the project. Nowak further testified
    that ERCC repaid each of its four members their $5,000 initial investments.
    Annan testified that, based on ERCC’s accounting records, ERCC withheld
    $376,651.45 in money from Altus that should have been paid to Warwick in
    satisfaction of the labor and materials charges due to the change orders. Instead,
    2
    This figure represents the difference between the $870,302.03 alleged in response
    to discovery and the amount of settlement that Warwick deducted based on the
    court’s determination at the pretrial conference.
    8
    ERCC used that money to pay its landscaping contractors and vendors and to pay
    other direct job costs ERCC incurred. Patel’s testimony was equivocal. First, he
    testified that he used money that should have been paid to Warwick to pay for other
    direct project expenses, such as landscaping contractors, but he maintained that this
    was a permissible use of the funds. Later, he testified that ERCC paid Warwick
    “every dime” that was intended for Warwick, and he said that none of the money
    used to repay the initial investors came from a source that should have been paid to
    Warwick.
    As to his allegations of fraud, Annan testified that Robinson, on behalf of
    ERCC, told him that ERCC was going to obtain a payment bond. Annan said that he
    signed the contract on behalf of Warwick because he trusted Robinson and relied on
    that representation. Annan testified that he read and understood the contract with
    ERCC before he signed it. He admitted that he did not ask to see ERCC’s bond when
    he signed the contract, but he said: “They lied to me about the bond.” He also
    testified that, unbeknownst to him and Warwick, ERCC used his bond to satisfy its
    contractual obligation to provide Altus with a payment and performance bond.
    Annan said: “They hid it from me.” Patel, however, testified that Annan never asked
    ERCC to provide a payment bond and that ERCC would not have done so because
    the purpose of a payment and performance bond is to protect, ultimately, the project
    owner.
    9
    Annan testified that Warwick was damaged by ERCC’s misrepresentation
    about the bond because it had no payment bond to rely on when ERCC failed to pay
    for labor and materials relating to the change orders. Annan also testified that
    Warwick was not alleging any fraud relating to the $352,000 payment to Sterling
    Engineering.
    The jury unanimously found that: (1) ERCC breached the contract with
    Warwick; (2) ERCC failed to pay Warwick promptly for its work; (3) ERCC and
    Patel were trustees of trust funds received from the owner of the project, Altus;
    (4) Warwick was a beneficiary of trust funds for the project; (5) ERCC and Patel
    misapplied project trust funds; (6) ERCC and Patel committed fraud against
    Warwick; (7) clear and convincing evidence showed that Warwick was harmed by
    ERCC and Patel’s fraudulent misrepresentation; (8) ERCC and Patel did not engage
    in a conspiracy to damage Warwick. The jury found the following amounts of
    damages:
    Breach of contract                            $ 463,406.48
    Misapplication of trust funds                   372,000.00
    Fraud                                             33,000.00
    Exemplary damages against ERCC                  500,000.00
    Exemplary damages against Patel                 500,000.00
    10
    Warwick moved for entry of judgment on the verdict, and ERCC and Patel
    responded. ERCC and Patel argued that Warwick was required to elect a remedy
    between breach of contract and misapplication of trust funds in violation of the
    TCTFA. They also argued that they were entitled to settlement credits as to the award
    of $372,000 on the misapplication of trust funds claim because Warwick sought the
    full amount of damages for this claim, instead of reducing the amount sought to
    account for settlement credits. ERCC and Patel also argued that the settlement
    credits exceeded the jury’s award of damages for the misapplication of trust funds
    claim and the fraud claim. ERCC and Patel argued, in the alternative, that the
    exemplary damages should be reduced to $200,000 under the mandatory cap in the
    Texas Civil Practice and Remedies Code and further reduced to $132,000 to comport
    with due process.
    The trial court vacated its first judgment, and it entered final judgment on
    December 20, 2019. The trial court accepted all of the jury’s findings and rendered
    judgment that Warwick “have and recover from and against” ERCC and Patel
    “jointly and severally, $372,000 for ERCC’s breach of contract and for Patel’s
    [misapplication of trust funds in] violation of the Texas Construction Trust Fund
    statute, respectively . . . .” The trial court also awarded Warwick $91,406.48 against
    ERCC “for breach of contract, which when taken together with the amount in the
    foregoing paragraph equals the total amounts awarded by the jury for ERCC’s
    11
    breach of contract . . . .” The court awarded $33,000 for fraud against ERCC and
    Patel “jointly and severally” and $200,000 each, from ERCC and Patel, as exemplary
    damages. The court awarded 18% statutory penalty interest from ERCC due to its
    violation of the Texas Prompt Payment Act in addition to 5.5% prejudgment interest
    from both ERCC and Patel. Finally, the trial court awarded costs of court and
    attorney’s fees.
    The trial court denied ERCC and Patel’s motion to modify the judgment, and
    ERCC and Patel appealed.
    Analysis
    ERCC and Patel raise seven issues on appeal. Because they control our
    disposition of this appeal, we focus on the second, third, and fourth issues. First, we
    consider whether the trial court’s judgment violated the “one satisfaction rule.”
    Because we agree that it does, we must consider how to reform the judgment to
    afford Warwick the maximum relief to which it is entitled. ERCC and Patel argue
    on appeal (1) that the entire damages award on Warwick’s misapplication of trust
    funds claim is extinguished by the proper application of settlement credits and
    (2) that Warwick’s fraud claim is entirely precluded because the parties’ contract
    negates justifiable reliance as a matter of law.
    12
    I.    Standard of review
    “[W]hether the plaintiff has complained of a single, indivisible injury, and
    whether the defendant is entitled to credit one or more settlements against the
    judgment, are legal determinations that we review de novo.” Sky View at Las
    Palmas, LLC v. Mendez, 
    555 S.W.3d 101
    , 109 n.8 (Tex. 2018). “Justifiable reliance
    usually presents a question of fact,” but “the element can be negated as a matter of
    law when circumstances exist under which reliance cannot be justified.” JPMorgan
    Chase Bank, N.A. v. Orca Assets G.P., L.L.C., 
    546 S.W.3d 648
    , 654 (Tex. 2018).
    We therefore review ERCC and Patel’s second, third, and fourth issues de novo. See
    Sky View, 555 S.W.3d at 109.
    II.   One Satisfaction Rule
    A.     A party is entitled to one recovery for one injury.
    A party may sue and seek damages on alternative theories of liability. Waite
    Hill Servs., Inc. v. World Class Metal Works, Inc., 
    959 S.W.2d 182
    , 184 (Tex. 1998);
    see Madison v. Williamson, 
    241 S.W.3d 145
    , 159 (Tex. App.—Houston [1st Dist.]
    2007, pet. denied). “Under the one-satisfaction rule, a plaintiff is entitled to only one
    recovery for any damages suffered because of a particular injury.” TMRJ Holdings,
    Inc. v. Inhance Techs., LLC, 
    540 S.W.3d 202
    , 208 (Tex. App.—Houston [1st Dist.]
    2018, no pet.); see Tony Gullo Motors I, L.P. v. Chapa, 
    212 S.W.3d 299
    , 303 (Tex.
    2006). “There can be but one recovery for one injury and the fact that more than one
    13
    defendant may have caused the injury or that there may be more than one theory of
    liability, does not modify this rule.” Stewart Title Guar. Co. v. Sterling, 
    822 S.W.2d 1
    , 8 (Tex. 1991). “Although the traditional ‘one satisfaction’ principle applies to
    cases in which an injured plaintiff is wholly compensated by settling defendants or
    other third parties,” it also applies “when a defendant commits technically different
    acts that result in a single injury.”3 Madison, 
    241 S.W.3d at
    158–59. “The one
    satisfaction rule may limit a plaintiff’s recovery even where the amounts awarded
    vary from claim to claim.” Lundy v. Masson, 
    260 S.W.3d 482
    , 506 (Tex. App.—
    Houston [14th Dist.] 2008, pet. denied).
    “When a defendant’s acts result in a single injury, and the jury returns
    favorable findings on more than one theory of liability, the plaintiff is entitled to
    judgment on the theory affording him the greatest relief.” Saden v. Smith, 
    415 S.W.3d 450
    , 465–66 (Tex. App.—Houston [1st Dist.] 2013, pet. denied) (citing
    Birchfield v. Texarkana Mem’l Hosp., 
    747 S.W.2d 361
    , 367 (Tex. 1987)). Ordinarily
    the prevailing party will elect which remedy it prefers prior to entry of judgment, but
    when it does not the trial court should use the findings to render judgment affording
    the maximum relief. Star Houston, Inc. v. Shevack, 
    886 S.W.2d 414
    , 422 (Tex.
    3
    “If a plaintiff pleads alternate theories of liability, a judgment awarding damages on
    each alternate theory may be upheld if the theories depend on separate and distinct
    injuries and if separate and distinct damages findings are made as to each theory.”
    Madison v. Williamson, 
    241 S.W.3d 145
    , 158 (Tex. App.—Houston [1st Dist.]
    2007, pet. denied).
    14
    App.—Houston [1st Dist.] 1994), writ denied per curiam, 
    907 S.W.2d 452
    , 452
    (Tex. 1995); accord Lundy, 
    260 S.W.3d at
    505–06.
    B.    Warwick advanced three liability theories arising from one injury.
    In their second issue, ERCC and Patel argue that the trial court’s judgment
    violated the one satisfaction rule because Warwick was not required to elect a
    remedy and was awarded multiple damages for a single injury. ERCC and Patel
    maintain that the three claims on which Warwick prevailed—breach of contract,
    misapplication of trust funds, and fraud—all sought recovery for the same injury:
    the nonpayment of Warwick for labor and materials related to the Altus hospice
    construction project. Warwick’s fifth amended petition was the live pleading at trial.
    In its live pleading, Warwick alleged that it had suffered at least $870,302.03 in
    breach-of-contract damages, $352,000 in fraud damages due to the reduction in
    contract price to pay Sterling Engineering to act as project manager, and unspecified
    damages for misapplication of trust funds under the Texas Construction Trust Fund
    Act.
    1.    Breach of contract
    Evidence at trial demonstrated that Warwick contracted with ERCC for the
    construction of the Altus hospice. Patel conceded that ERCC failed to pay Warwick
    for some labor and materials related to change orders that was owed under the
    contract, and the evidence was undisputed that the amount owed was $463,406.48.
    15
    Thus, liability and damages for breach of contract were established conclusively at
    trial. See AKIB Constr. Inc. v. Shipwash, 
    582 S.W.3d 791
    , 806 (Tex. App.—Houston
    [1st Dist.] 2019, no pet.) (stating essential elements of breach-of-contract claim).
    2.    Misapplication of trust funds
    Warwick’s misapplication of trust funds claim was based on the Texas
    Construction Trust Fund Act (“TCTFA”). See TEX. PROP. CODE §§ 162.001–.033.
    Under the TCTFA, “[c]onstruction payments are trust funds . . . if the payments are
    made to a contractor or subcontractor or to an officer, director, or agent of a
    contractor or subcontractor, under a construction contract for the improvement of
    specific real property in this state.” Id. § 162.001(a). “A contractor, subcontractor,
    or owner or an officer, director, or agent of a contractor, subcontractor, or owner
    who receives trust funds or who has control or direction of trust funds, is a trustee of
    the trust funds.” Id. § 162.002. “An artisan, laborer, mechanic, contractor,
    subcontractor, or materialman who labors or who furnishes labor or material for the
    construction . . . of an improvement on specific real property . . . is a beneficiary of
    any trust funds paid or received in connection with the improvement.” Id. §
    162.003(a).
    “A trustee who, intentionally or knowingly or with intent to defraud, directly
    or indirectly retains, uses, disburses, or otherwise diverts trust funds without first
    fully paying all current or past due obligations incurred by the trustee to the
    16
    beneficiaries of the trust funds, has misapplied the trust funds.” Id. § 162.031.
    “‘Current or past due obligations’ are those obligations incurred or owed by the
    trustee for labor or materials furnished in the direct prosecution of the work under
    the construction contract prior to the receipt of the trust funds and which are due and
    payable by the trustee no later than 30 days following receipt of the trust funds.” Id.
    § 162.005(2). The TCTFA provides that the misapplication of trust funds is a Class
    A misdemeanor or felony of the third degree, depending on the circumstances. Id. §
    162.032. Although the statute lacks an express provision for a private civil right of
    action, this court has recognized a private right of action arising from a violation of
    the TCTFA because “a breach of a statutory duty normally gives rise to a private
    right of action on behalf of the injured person (or group of persons) for whose benefit
    the statute was enacted.” Lively v. Carpet Servs., Inc., 
    904 S.W.2d 868
    , 871 (Tex.
    App.—Houston [1st Dist.] 1995, writ denied).
    The TCTFA does not expressly require that the trustee and beneficiary of trust
    funds be in privity of contract, and the broad definitions of trustee and beneficiary
    indicate that they will not always be parties to the same contract. In this case,
    however, Warwick directly contracted with ERCC. And the damages Warwick
    alleged and proved at trial arose from ERCC’s failure to pay for labor and materials
    supplied related to change orders. Although Warwick advanced a different model of
    computing damages—the difference between the money ERCC received from Altus
    17
    and the money paid to Warwick—the damages arose from the same injury as the
    breach of contract damages: ERCC’s failure to pay money owed under the contract.
    On appeal Warwick concedes that all of the misapplication of trust funds damages
    overlapped with the breach of contract damages. We conclude that breach of contract
    and misapplication of trust funds were alternative theories of liability arising from
    the same injury.
    3.    Fraudulent inducement
    Warwick also pleaded a claim for fraudulent inducement. In its pleadings and
    discovery responses, Warwick alleged that ERCC and Patel fraudulently induced it
    to enter the contract with ERCC by promising to obtain a payment and performance
    bond. It also alleged fraud arising from the $352,000 that was deducted from
    Warwick’s contract price to pay Sterling Engineering to act as project manager, but
    at trial, Warwick disavowed this theory of recovery. Annan specifically testified that
    Warwick was not seeking any fraud damages from the reduction in its contract price
    to pay Sterling Engineering for project management.
    “Texas law has long imposed a duty to abstain from inducing another to enter
    into a contract through the use of fraudulent misrepresentations.” Anderson v.
    Durant, 
    550 S.W.3d 605
    , 614 (Tex. 2018) (stating elements of fraudulent
    inducement). “Fraudulent inducement is actionable when the misrepresentation is a
    false promise of future performance made with a present intent not to perform.” 
    Id.
    18
    The existence of a contract is an essential element of proof of a claim for fraudulent
    inducement. 
    Id.
     “Two types of direct damages are available for common-law fraud:
    out-of-pocket damages, measured by the difference between the value expended
    versus the value received, and benefit-of-the-bargain damages, measured by the
    difference between the value as represented and the value received.” 
    Id.
    At trial, Warwick’s attorney argued in closing that ERCC and Patel had
    fraudulently induced Warwick to enter into the construction contract by representing
    that it would obtain a payment and performance bond that it never obtained.
    On appeal, Warwick argues that it sought damages for nonpayment through
    its breach-of-contract and misapplication-of-trust-funds claims and damages for
    fraud. Warwick contends that the predicate for the fraud award is independent of
    nonpayment. Warwick argues on appeal that it sought out-of-pocket damages for
    fraud, specifically (1) the reduction of its contract price to pay Sterling Engineering
    for project management, (2) the lack of independent project management services,
    (3) damage to Warwick’s relationships with subcontractors, and (4) costs incurred
    to settle the claims with its subcontractors.
    The record does not support this argument. First, Annan testified that
    Warwick was not seeking any fraud damages from the reduction in its contract price
    to pay Sterling Engineering for project management. Second, Warwick did not
    introduce any evidence that it was injured by the absence of independent project
    19
    management services. Third, its evidence that its relationships with its
    subcontractors was damaged was limited to Annan’s testimony about ERCC’s
    failure to promptly pay Warwick. Annan testified that ERCC’s failure to promptly
    pay “hurt our relationships with our subs,” that Warwick “got through it, but it did
    do damage,” and that “[i]t made them question our judgment who we went into
    business with.” But Warwick provided no evidence quantifying those alleged out-
    of-pocket damages or additional expenses associated with settling claims with
    subcontractors. Instead, in closing Warwick relied on its evidence of damages due
    to ERCC’s failure to pay for labor and materials associated with the change orders.
    In closing argument, Warwick’s attorney argued:
    So Question 11 is what we call the damages question on the fraud claim.
    You have to figure out how much my client’s been damaged by that
    fraud. . . . But at the very least, the 463,000 that they didn’t pay us are
    our damages, and you may find that the trust funds as well, the fact that
    they got our money and kept it are also part of our fraud damages. So
    at a minimum it’s the 463. You can add the trust fund claims to that as
    well for an additional 376, and you can put a number in the blank that
    you ladies and gentlemen feel is the appropriate measure of damages
    that the evidence has shown was suffered by my client.
    We conclude that Warwick sought benefit-of-the-bargain damages for its
    fraudulent inducement claim, specifically asking the jury to award the amount “that
    they didn’t pay us.” This represents the same injury for which Warwick sought
    recovery under theories of breach of contract and misapplication of trust funds.
    ***
    20
    We conclude that Warwick’s three successful liability theories all sought
    damages for the same injury—the nonpayment of labor and materials Warwick
    expended on construction of the Altus hospice. See Madison, 
    241 S.W.3d at
    158–59
    (jury may return favorable findings on alternative theories of liability). We sustain
    ERCC and Patel’s second issue. Warwick is entitled to recover its damages based
    on the theory that afforded it the greatest or most favorable relief. See 
    id.
     On appeal,
    ERCC and Patel raise additional challenges to the viability of judgment based on
    misapplication of trust funds and fraud.
    II.   Application of settlement credits extinguishes recovery on misapplication
    of trust funds theory.
    In their third issue, ERCC and Patel argue that the trial court erred by failing
    to    apply      settlement    credits     to    Warwick’s       recovery     on     its
    misapplication-of-trust-funds claim. They contend that application of the settlement
    credits would extinguish Warwick’s recovery for that claim entirely.
    In addition to preventing a plaintiff from obtaining multiple recoveries on
    alternative theories of liability when it has suffered only one injury, the
    onesatisfaction rule also prevents a plaintiff from obtaining more than one recovery
    by crediting a non-settling defendant for payments made in settlement of damages
    from a singular injury. Sky View, 555 S.W.3d at 106–07. The Texas Supreme Court
    has explained:
    21
    [W]hen a plaintiff files suit alleging that multiple tortfeasors are
    responsible for the plaintiff’s injury, any settlements are to be credited
    against the amount for which the liable parties as a whole are found
    responsible, but for which only the non-settling defendant remains in
    court. The rationale for this doctrine is that the plaintiff should not
    receive a windfall by recovering an amount in court that covers the
    plaintiff’s entire damages, but to which a settling defendant has already
    partially contributed. The plaintiff would otherwise be recovering an
    amount greater than the trier of fact has determined would fully
    compensate for the injury.
    First Title Co. of Waco v. Garrett, 
    860 S.W.2d 74
    , 78 (Tex. 1993).
    “A defendant seeking a settlement credit has the burden to prove its right to
    such a credit.” Utts v. Short, 
    81 S.W.3d 822
    , 828 (Tex. 2002); Mobil Oil Corp. v.
    Ellender, 
    968 S.W.2d 917
    , 927 (Tex. 1998); Alanis v. US Bank Nat’l Ass’n, 
    489 S.W.3d 485
    , 509 (Tex. App.—Houston [1st Dist.] 2015, pet. denied). Under the
    common law, the record must show the amount of the settlement credit. Utts, 81
    S.W.3d at 828; Ellender, 968 S.W.2d at 927 (citing Garrett, 860 S.W.2d at 78);
    Alanis, 489 S.W.3d at 509. Once the non-settling defendant demonstrates a right to
    a settlement credit, the burden shifts to the plaintiff to show that certain amounts
    should not be credited because of the settlement agreement’s allocation of damages,
    for example between actual and exemplary damages. Utts, 81 S.W.3d at 828;
    Ellender, 968 S.W.2d at 928 (recognizing that settling plaintiffs are in better position
    than non-settling defendants to ensure that settlement awards are properly allocated).
    The record demonstrates that Warwick settled with Altus and with Anwar,
    Jafar, and the estate of Ibrihim. Warwick informed the trial court on the record
    22
    outside the presence of the jury that it had settled with Altus and sought to deduct
    the amount of settlement from the damages it asked the jury to find. Warwick
    explained that the total amount of damages it sought for nonpayment was
    $870,302.03. ERCC and Patel informed the court that Anwar, Jafar, and the estate
    of Ibrihim had settled with Warwick for $40,000 each, for a total of $120,000.
    Warwick told the court that it had deducted the $120,000 from the amount of
    damages it would ask the jury to find, which was $463,406.48 after deducting all
    settlements. The jury did find $463,406.48 as damages for breach of contract. ERCC
    did not dispute that amount at trial and has not challenged the amount or the
    application of settlement credits on appeal. Based on this information in the record,
    it is possible to calculate the settlement credits that that ERCC and Patel wish to
    apply to the misapplication of trust fund damages. See Utts, 81 S.W.3d at 828;
    Ellender, 968 S.W.2d at 927; Alanis, 489 S.W.3d at 509.
    Total amount of damages alleged by                                   $ 870,302.03
    Warwick
    Amount Warwick asked jury to find for                                  463,406.48
    breach of contract, after deduction of
    settlement amounts
    Difference (Total of settlements)                                      406,895.55
    Anwar, Jafar, Ibrihim settlements (total)                                 120,000
    Difference (Altus settlement, estimated)                               28,6895.55
    Because the record demonstrates the amount of settlement credits that ERCC
    and Patel seek to apply to the TCTFA claim, the burden shifted to Warwick to show
    that certain amounts should not be credited due to the allocation of damages in the
    23
    settlement agreements. See Utts, 81 S.W.3d at 828; Ellender, 968 S.W.2d at 928.
    But Warwick presented no evidence about the allocation of sums in the settlements.
    Instead, Warwick argues that ERCC and Patel are not entitled to a credit based
    on its settlement with Altus, because that settlement was based on a lien and ERCC
    and Patel were not jointly and severally liable on the lien. In Sky View, the Texas
    Supreme Court held that a finding of joint liability is not required for the application
    of the one satisfaction rule, which is not limited to situations in which defendants
    have been found liable on the same cause of action. Sky View, 555 S.W.3d at 112–
    13; see, e.g., Waite Hill Servs., 959 S.W.2d at 185 (holding trial court erred by
    refusing an election-of-remedy request when the jury awarded “contract, as well as
    tort damages, and the jury awarded the identical amount in response to both damages
    questions”). Warwick’s lien claim addressed the same injury as its claims for breach
    of contract, misapplication of trust funds, and fraud: nonpayment of labor and
    materials Warwick spent on the project. See TEX. PROP. CODE § 53.023(1)
    (mechanic’s or materialman’s lien secures payment for “labor done or material
    furnished for the construction”).
    Warwick also asserts that its settlements with Altus, Anwar, Jafar, and the
    estate of Ibrihim were already reflected in the economic damages it sought at trial.
    The record does not demonstrate that Warwick deducted any amounts reflective of
    the   settlements    from     what    it   asked    the    jury   to   find    on    its
    24
    misapplication-of-trust-funds claim. Warwick relied on an entirely different method
    of calculating damages for misapplication of trust funds than it did for its
    breach-of-contract claim, which relied on Annan’s undisputed testimony about how
    much remained unpaid. Warwick asserted that the proper measure of damages for
    its misapplication-of-trust-funds claim was the difference between the total amount
    of money that Altus paid ERCC ($ 2,891,156.60) and the total amount of money that
    ERCC paid Warwick ($ 2,506,422.74), or $ 384,733.76. Annan testified at trial
    ERCC received a total of $ 376,651.46 from Altus that ERCC should have—but
    failed to—disburse to Warwick. The jury awarded $ 372,000 as actual damages for
    misappropriation of trust funds. See Clerk’s R. 466 (“What sum of money, if any, if
    paid now in cash, would fairly and reasonably compensate Warwick for its damages,
    if any, that were proximately caused by such misapplication of trust funds?”).
    Although the jury here awarded different amounts of actual damages for
    breach-of-contract and misapplication of trust funds, our analysis that Warwick’s
    recovery depends on an election between these claims due to the one satisfaction
    rule remains unchanged. See Lundy, 
    260 S.W.3d at 506
     (noting that jury awarded
    different amounts of actual damages on alternative liability theories that addressed
    a singular injury).
    Because the record demonstrates ERCC and Patel’s entitlement to the
    application of settlement credits and because Warwick has not demonstrated that an
    25
    allocation in the settlement agreements precludes the application of settlement
    credits, we conclude that the trial court erred by failing to apply them. The jury
    awarded $372,000 in actual damages for misapplication of trust funds. The total
    amount of settlement credits is $406,895.55. We conclude that the settlement credits
    would entirely extinguish Warwick’s recovery under this theory of liability, and we
    hold that recovery under Warwick’s misapplication-of-trust-funds claim is not
    viable. We sustain ERCC and Patel’s third issue.
    III.   The parties’ contract makes Warwick’s reliance on representations that
    ERCC would obtain a bond unjustifiable.
    In their fourth issue, ERCC and Patel argue that the trial court erred by
    rendering judgment for Warwick on its fraud claim because its reliance on a
    representation that ERCC would obtain a payment and performance bond was
    contradicted by the parties’ contract. Warwick asserts that it could have relied on the
    representation despite the language in the contract. We disagree.
    Warwick alleged that it was fraudulently induced to enter the contract with
    ERCC by representations that the project would be bonded and ERCC would obtain
    the payment and performance bond. Annan testified at trial that he would not have
    signed the contract on behalf of Warwick had he known that ERCC would not obtain
    the bond. He also testified that he had read and understood the contract.
    “The elements of a claim for fraudulent inducement are ‘(1) a material
    misrepresentation, (2) made with knowledge of its falsity or asserted without
    26
    knowledge of its truth, (3) made with the intention that it should be acted on by the
    other party, (4) which the other party relied on and (5) which caused injury.’”
    Mercedes-Benz USA, LLC v. Carduco, Inc., 
    583 S.W.3d 553
    , 557 (Tex. 2019)
    (quoting Anderson, 550 S.W.3d at 614). “Because fraudulent inducement arises only
    in the context of a contract, the existence of a contract is an essential part of its
    proof.” Anderson, 550 S.W.3d at 614.
    “To prevail on a fraud claim, a ‘plaintiff [must] show actual and justifiable
    reliance.’” Mercedes-Benz USA, 583 S.W.3d at 558 (quoting Grant Thornton LLP
    v. Prospect High Income Fund, 
    314 S.W.3d 913
    , 923 (Tex. 2010)). “Whether a
    party’s actual reliance is also justifiable is ordinarily a fact question, but the element
    may be negated as a matter of law when circumstances exist under which reliance
    cannot be justified.” Mercedes-Benz USA, 583 S.W.3d at 558. “[A] party to a written
    contract cannot justifiably rely on oral misrepresentations regarding the contract’s
    unambiguous terms.” Nat’l Prop. Holdings, L.P. v. Westergren, 
    453 S.W.3d 419
    ,
    424 (Tex. 2015).
    “In determining whether justifiable reliance is negated as a matter of law,
    courts must consider the nature of the parties’ relationship and the contract.”
    JPMorgan Chase, 546 S.W.3d at 654 (quotation omitted). A party must exercise
    ordinary care when entering into an arm’s length transaction, and his failure to do so
    is not excused by his “mere confidence in the honesty and integrity of the other
    27
    party.” Thigpen v. Locke, 
    363 S.W.2d 247
    , 251 (Tex. 1962). A party cannot blindly
    rely on a representation when he knows, based on his experience and background,
    that he should investigate, but he fails to do so. JPMorgan Chase, 546 S.W.3d at
    654. Reliance on a representation is not justified when there are “red flags” that
    indicate such reliance is unwarranted. Grant Thornton, 314 S.W.3d at 923. Reliance
    on an oral representation is also unjustified when the oral representation is “directly
    contradicted by the express, unambiguous terms of a written agreement between the
    parties.” DRC Parts & Accessories, L.L.C. v. VM Motori, S.P.A., 
    112 S.W.3d 854
    ,
    858 (Tex. App.–Houston [14th Dist.] 2003, pet. denied). A “party who enters into a
    written contract while relying on a contrary oral agreement does so at its peril” 
    Id. at 859
    .
    ERCC and Patel argue that the contract with Warwick directly contradicted
    the alleged representation that ERCC would obtain a payment and performance
    bond. The ERCC-Warwick contract incorporates “Exhibit E” in regard to “Insurance
    and Bonds.” Exhibit E provides
    ARTICLE E.2         SURETY BONDS
    § E.2.1      The Contractor [Warwick] shall provide surety bonds
    as follows:
    (Specify type and penal sum of bonds.)
    Type                       Penal Sum ($0.00)
    Payment and Performance    3,200,000.00
    28
    In Texas, payment and performance bonds are statutory and must comply with
    the provisions of Chapter 53, Subchapter I of the Texas Property Code (“Bond to
    Pay Liens or Claims”). See TEX. PROP. CODE §§ 53.201–.211. “An original
    contractor who has a written contract with the owner may furnish at any time a bond
    for the benefit of claimants.” Id. § 53.201(a). The bond protects the owner and its
    property from claims by the same class of people who would otherwise be entitled
    to file a mechanic’s and materialman’s lien. See id. § 53.201(b) (“Bond”);
    id. § 53.205(a) (“Enforceable Claims”); id. § 53.021 (“Persons Entitled to Lien”).
    The Property Code establishes a broad category of people entitled to a lien, and the
    statute does not contemplate multiple payment and performance bonds on a
    particular project because the original contractor’s bond would protect the owner
    from claims from tiers of subcontractors. See TEX. PROP. CODE § 53.021(a)(1) (“A
    person has a lien if . . . the person labors . . . or furnishes labor or materials for
    construction or repair in this state of . . . a house, building, or improvement . . . .”).
    The contract between ERCC and Warwick expressly required Warwick to
    provide a payment and performance bond in the total amount of the project, $3.2
    million. In light of the statutory scheme pertaining to such bonds, this contract
    provision directly contradicts Warwick’s reliance on the alleged representation that
    ERCC would obtain the exact same bond. See JPMorgan Chase, 546 S.W.3d at 660.
    We conclude that Warwick’s fraud claim fails as a matter of law because the element
    29
    of justifiable reliance is negated by the contract. We sustain ERCC and Patel’s fourth
    issue.
    Conclusion
    Having concluded that recovery is not viable under either the
    misapplication-of-trust-funds claim or the fraud claim, we hold that Warwick’s
    recovery must be limited to its breach-of-contract claim. We reverse the judgment
    of the trial court and render judgment that Warwick take nothing on its
    misapplication-of-trust-funds claim and its fraud claim, and we remand this case to
    the trial court for entry of judgment consistent with this opinion, including proper
    computation of prejudgment interest. We do not reach the remainder of ERCC and
    Patel’s issues on appeal because it is not necessary to the disposition of this appeal.
    See TEX. R. APP. P. 47.1.
    Peter Kelly
    Justice
    Panel consists of Chief Justice Radack and Justices Kelly and Landau.
    30
    

Document Info

Docket Number: 01-20-00208-CV

Filed Date: 1/20/2022

Precedential Status: Precedential

Modified Date: 1/24/2022