Arch Insurance Company, as Subrogee and Indemnifier of Linbeck Group, LLC v. Soprema, Inc. ( 2022 )


Menu:
  • AFFIRMED and Opinion Filed February 24, 2022
    In The
    Court of Appeals
    Srttth Aratrict of Cexas at Dallas
    No. 05-20-00586-CV
    ARCH INSURANCE COMPANY, AS SUBROGEE AND INDEMNIFIER
    OF LINBECK GROUP, LLC, Appellant
    V.
    SOPREMA, INC., Appellee
    On Appeal from the 101st Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-17-17759
    MEMORANDUM OPINION
    Before Justices Pedersen, III, Goldstein, and Smith
    Opinion by Justice Smith
    Appellant Arch Insurance Company, as subrogee and indemnifier of Linbeck
    Group, LLC, appeals the trial court’s order granting appellee Soprema, Inc.’s motion
    for summary judgment. The central issue in this appeal is whether the waiver-of-
    subrogation paragraph contained in the construction contract was triggered when
    Arch funded a settlement, under a commercial general liability (CGL) insurance
    policy, to pay for the repair or replacement of the building’s damaged roof allegedly
    caused, in part, by a defective roofing membrane supplied by Soprema, a sub-
    subcontractor on the construction project. Because we conclude that the damages to
    the roof were covered by “property insurance applicable to the Work” as evidenced
    by Arch’s payment under the CGL policy covering property damage, we affirm the
    trial court’s order granting summary judgment for Soprema.
    Background
    The Dallas Center for the Performing Arts Foundation, Inc. (DCPAF)
    contracted with Linbeck in September 2006 to build the Margot and Bill Winspear
    Opera House, now known as the AT&T Performing Arts Center (PAC), in the Dallas
    Arts District. Linbeck served as the general contractor on the project and
    subcontracted out parts of the project, including the roofing installation. The roofing
    subcontractor, Anchor Roofing Systems, Ltd. (who is no longer a party to this appeal
    because the parties reached a settlement agreement while the appeal was pending),
    contracted with Soprema to supply the roofing membrane.
    After the PAC opened in October 2009, the DCPAF discovered blistering on
    the roof, which had resulted in water intrusion and leaks during weather events.
    Expert analysis determined that the roof needed to be replaced and opined that
    Anchor’s poor workmanship and Soprema’s defective membrane were the causes of
    the roof damage.
    Arch, as Linbeck’s CGL insurer, paid $1.6 million to the DCPAF to repair or
    replace the roof and for a release of Linbeck. Arch then filed suit against Anchor
    and Soprema to recover damages from the alleged construction defects. In
    Soprema’s answer, it asserted that Arch was barred from recovery due to the
    following subrogation clause in the general conditions of the construction contract:
    12.7 DCPAF and Contractor waive all rights against the City, each other and any of their
    Subcontractors, Sub-Subcontractors, agents and employees, each of the other, if any, for
    damages caused by fire or other causes of loss to the extent covered by property insurance
    obtained or required to be obtained by Contractor (excluding deductibles) pursuant to this
    Article 12.7, or other property insurance applicable to the Work, except such rights as they
    have to proceeds of such insurance held by Contractor as fiduciary. The Contractor, as
    appropriate, shall require of the Subcontractors, Sub-Subcontractors, agents and
    employees of any of them, by appropriate agreements, written where legally required for
    validity, similar waivers of each in favor of other parties enumerated herein. The insurance
    policies obtained by Contractor pursuant to this Article 12.7 shall be endorsed to provide a
    waiver of subrogation in favor of Contractor, DCPAF, the City, Subcontractors and Sub-
    Subcontractors. The City is a third-party beneficiary of this Article 12.7.
    Soprema moved for summary judgment on this affirmative defense, and Arch moved
    for a partial summary judgment asserting that the waiver of subrogation was not
    triggered by payment under a CGL policy.
    Soprema argued that the insurance policy, under which Arch paid the
    settlement, contained “property insurance applicable to the Work” because it
    covered property damage and the roofing system was part of the construction
    project—the Work; thus, the subrogation waiver applied. Arch responded that the
    claim was paid under liability insurance, not property insurance, so the subrogation
    waiver did not apply. Specifically, Arch alleged that the claim was paid pursuant to
    the products-completed operations coverage of the CGL policy. Arch argued that
    the builder’s risk insurance, which Linbeck was required to maintain under the
    contract, was the “property insurance” contemplated by the waiver-of-subrogation
    paragraph.
    After a hearing, the trial court granted Soprema’s motion. The trial court
    denied Arch’s partial motion for summary judgment after a separate hearing and,
    although Arch stated it intended to appeal from the tral court’s orders on both
    motions in its notice of appeal, Arch’s brief challenges only the trial court’s order
    granting Soprema’s motion.
    Summary Judgment Standard of Review
    We review a summary judgment de novo. 7rial v. Dragon, 
    593 S.W.3d 313
    ,
    316 (Tex. 2019). A traditional motion for summary judgment requires the moving
    party to show that no genuine issue of material fact exists and that it is entitled to
    judgment as a matter of law. TEX. R. Civ. P. 166a(c); Lujan v. Navistar, Inc., 
    555 S.W.3d 79
    , 84 (Tex. 2018). If the movant carries this burden, the burden shifts to
    the nonmovant to raise a genuine issue of material fact. Lujan, 555 S.W.3d at 84.
    We take evidence favorable to the nonmovant as true, and we indulge every
    reasonable inference and resolve any doubts in the nonmovant’s favor. Ortiz v. State
    Farm Lloyds, 
    589 S.W.3d 127
    , 131 (Tex. 2019).
    Waiver-of-Subrogation Paragraph Was Triggered
    Soprema had the burden to conclusively prove its affirmative defense of
    waiver of subrogation. The waiver-of-subrogation paragraph contains two operative
    clauses: (1) “property insurance obtained or required to be obtained by [Linbeck]
    (excluding deductibles) pursuant to this Article 12.7”; or (2) “other property
    insurance applicable to the Work.” Thus, Soprema had to prove that (1) the damage
    _4-
    was covered by “property insurance” that (2) was obtained or required to be obtained
    pursuant to Article 12.7 or was “applicable to the Work.”
    We review the construction of a contract, including whether it is ambiguous,
    de novo. Kachina Pipeline Co. v. Lillis, 
    471 S.W.3d 445
    , 449 (Tex. 2015). We must
    ascertain the true intentions of the parties as expressed in the agreement itself.
    Italian Cowboy Partners, Ltd. v. Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 333
    (Tex. 2011). In doing so, we “examine and consider the entire writing in an effort
    to harmonize and give effect to all the provisions of the contract so that none will be
    rendered meaningless.” J.-M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex.
    2003). Generally, “the instrument alone will be deemed to express the intention of
    the parties for it is objective, not subjective, intent that controls.” Matagorda Cty.
    Hosp. Dist. v. Burwell, 
    189 S.W.3d 738
    , 740 (Tex. 2006) (per curiam) (citation
    omitted). “We give terms their plain, ordinary, and generally accepted meaning
    unless the instrument shows that the parties used them in a technical or different
    sense.” Heritage Res., Inc. v. NationsBank, 
    939 S.W.2d 118
    , 121 (Tex. 1996).
    Ambiguity does not exist simply because the parties disagree over a term’s meaning
    and present different interpretations of the agreement. Dynegy Midstream Servs.,
    Ltd. P’ship v. Apache Corp., 294 S$.W.3d 164, 168 (Tex. 2009); DeWitt Cty. Elec.
    Coop., Inc. v. Parks, 
    1 S.W.3d 96
    , 100 (Tex. 1999).
    Property Insurance
    Arch contends that Soprema failed to meet its burden because it offered
    evidence only that “some” insurance policy paid the claim, not that the claim was
    paid by “property insurance” as required by the contract provision. Arch argues that
    CGL insurance, a liability policy, is not property insurance. Soprema maintains that
    the CGL policy contained property insurance coverage and that Arch’s payment
    under the CGL was based on such coverage; it paid for property damage to the roof.
    The term “property insurance” is not defined in the contract, nor are any of
    the types of insurance coverage that Linbeck was required to maintain in accordance
    with the contract titled, “property insurance,” although several required coverage for
    property damage or loss, such as the CGL policy, the builder’s risk policy, and the
    all-risk property policy. Thus, the contract does not suggest that the parties used the
    term “property insurance” in a technical manner or in a different manner than its
    plain, ordinary meaning. See Heritage Res.,939 S.W.2d at 121.
    The term “property insurance” is defined by Merriam-Webster as “insurance
    against direct loss or damage, consequential loss, loss due to liability for damages,
    29
    or loss due to dishonesty or failure of others to perform their duty.” Property
    Insurance, MERRIAM-WEBSTER.COM DICTIONARY, https://www.merriam-
    webster.com/dictionary/property%o20insurance (last visited Feb. 16, 2022).
    Black’s Law Dictionary defines “property insurance” as “[a]n agreement to
    indemnify against property damage or destruction . . . [a]lso termed property-
    _6-
    damage insurance.” Property Insurance, BLACK’S LAW DICTIONARY (11th ed.
    2019).
    Applying the plain meaning of the word “property insurance,” we conclude
    that the CGL policy, or at least the portion under which Arch funded the settlement,
    was a form of property insurance in this case. According to the contract, Linbeck
    was required to maintain CGL coverage as follows:
    12.2.4 Contractor shall maintain commercial general liability (CGL) insurance covering
    all operations by or on behalf of the Contractor on an occurrence basis against claims for,
    but not limited to:
    Premises Operations;
    Products and Completed Operations;
    Independent Contractors;
    Contractual Liability;
    Personal Injury (including contractual liability);
    Advertising Injury (including contractual liability);
    Fire Damage Legal Liability;
    Broad Form Property Damage (including completed operations);
    Extended Bodily Injury;
    Work Performed by Subcontractors;
    Severability of Interests;
    Incidental Medical Malpractice;
    Work for municipalities;
    Host Liquor Liability Coverage
    The CGL policy specifically included insurance for property damage to completed
    operations and, thus, was “property insurance” under the plain meaning of the term.
    Arch argues that the insurance industry, Texas Legislature, and the courts
    recognize that “property insurance” means a first-party policy covering an owner’s
    property and does not include a liability policy that covers the insured’s liability for
    damage to a third-party’s property. But our interpretation of “property insurance”
    _7-
    must first be governed by an examination of the entire writing in which the term
    appears. See J.M. Davidson, 128 S.W.3d at 229. The construction contract at issue
    here did not require the owner, DCPAF, to purchase first-party insurance covering
    its property. In fact, the owner was not required to purchase any insurance under the
    construction contract. Instead, the construction contract required Linbeck and its
    subcontractors to purchase various insurance policies, including the CGL policy.
    This is significantly different from the contracts and waiver provision that have been
    previously interpreted by the courts, and relied on by Arch, because the contract and
    provision at issue here are not the standard contract and clause provided by the
    American Institute of Architects, which requires the owner to purchase property
    insurance. See, e.g., Am. Zurich Ins. Co. v. Barker Roofing, L.P., 
    387 S.W.3d 54
    ,
    61-62, 64-65 (Tex. App.—Amarillo 2012, no pet.); Walker Eng’g, Inc. yv.
    Bracebridge Corp., 
    102 S.W.3d 837
    , 840-44 (Tex. App.—Dallas 2003, pet. denied);
    Temple EasTex, Inc. v. Old Orchard Creek Partners, Ltd., 
    848 S.W.2d 724
    , 729-31
    (Tex. App.—Dallas 1992, writ denied).
    Additionally, we find Arch’s argument that “property insurance” meant
    “builder’s risk insurance” unpersuasive. Section 12.8 of the general conditions,
    the section immediately following the waiver-of-subrogation paragraph,
    specifically provides that if an event occurs which is covered by “builder’s risk
    insurance” and other conditions are met, the DCPAF and Linbeck agree to enter
    into a Change Order to increase the Guaranteed Maximum Price. Thus, if the
    _g-
    parties meant for “property insurance” to mean only builder’s risk insurance, they
    would have used the term “builder’s risk insurance” as they did in section 12.8
    instead of the term “property insurance.”
    We conclude that the term “property insurance” as used in the contract here
    includes the CGL coverage under which Arch funded the settlement agreement with
    DCPAF.
    Applicable to the Work
    We next look to whether the “property insurance” was “obtained or required
    to be obtained by [Linbeck] . . . pursuant to this Article 12.7” or was “applicable to
    the Work.” We conclude that the CGL coverage was “applicable to the Work.”
    Arch argues that the Work means ongoing construction, not completed
    construction. We disagree. The construction contract provides that “[t]he Work
    shall consist of all labor and materials required for the construction of the Project in
    accordance with the Contract Documents, including, without limitation, all of the
    items described in Article 1.1.14 of the General Conditions, together with all such
    other items as are reasonably inferable from the Contract Documents to complete
    the Work.” The “Project” is the PAC. The general conditions required that Linbeck
    provide certificates of insurance to the DCPAF to evidence that Linbeck had
    acquired the mandatory insurance, such as the CGL policy, before proceeding with
    any Work. The CGL policy was thus “applicable to the Work” not only because it
    was required before any Work could be performed but also because it covered
    _9_
    damages associated with the Work, including property damage to Work that had
    been completed and Work performed by subcontractors. Regardless of whether the
    Work had been completed, the labor and materials necessary to construct the roof as
    part of the Project were necessarily part of the Work. And, thus, because Arch paid
    for the roof to be repaired or replaced under the CGL policy due to damage to the
    roof alleged to be caused by poor workmanship and a defective roof membrane—
    labor and materials provided for the construction of the Project—the insurance was
    “applicable to the Work.”
    Our interpretation that the parties intended to extend the application of the
    subrogation waiver beyond the construction period is consistent with the public
    policy underlying subrogation waivers in that it continues to preserve economic
    relations, anticipates risks, and affords contracting parties certainty as to liability.
    See TX. C.C., Inc. v. Wilson/Barnes Gen. Contractors, Inc., 
    233 S.W.3d 562
    , 571
    (Tex. App.—Dallas 2007, pet. denied).
    Soprema conclusively established that Arch’s subrogation claims were
    waived under the contract. Because the waiver-of-subrogation paragraph is not
    ambiguous, Arch failed to raise a genuine issue of material of fact. See 
    id. at 567
    (the interpretation of an ambiguous contract is an issue of material fact). Therefore,
    the trial court did not err by granting Soprema’s traditional motion for summary
    judgment. We overrule Arch’s sole issue on appeal.
    _10—
    Conclusion
    We affirm the trial court’s summary judgment in favor of Soprema.
    /Craig Smith/
    CRAIG SMITH
    JUSTICE
    200586F P05
    _|]-
    Court of Appeals
    Srttth Aratrict of Cexas at Dallas
    JUDGMENT
    ARCH INSURANCE COMPANY, On Appeal from the 101st Judicial
    AS SUBROGEE AND District Court, Dallas County, Texas
    INDEMNIFIER OF LINBECK Trial Court Cause No. DC-17-17759.
    GROUP, LLC, Appellant Opinion delivered by Justice Smith.
    Justices Pedersen, HI and Goldstein
    No. 05-20-00586-CV V. participating.
    SOPREMA, INC., Appellee
    In accordance with this Court’s opinion of this date, the judgment of the trial
    court is AFFIRMED.
    It is ORDERED that appellee SOPREMA, INC. recover its costs of this
    appeal from appellant ARCH INSURANCE COMPANY, AS SUBROGEE AND
    INDEMNIFIER OF LINBECK GROUP, LLC.
    Judgment entered February 24, 2022.
    _12-
    

Document Info

Docket Number: 05-20-00586-CV

Filed Date: 2/24/2022

Precedential Status: Precedential

Modified Date: 3/2/2022