Keith B. Alexander v. Eddie Kent , 2015 Tex. App. LEXIS 11521 ( 2015 )


Menu:
  •                          COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-13-00469-CV
    KEITH B. ALEXANDER                                                   APPELLANT
    V.
    EDDIE KENT                                                             APPELLEE
    ----------
    FROM THE 141ST DISTRICT COURT OF TARRANT COUNTY
    TRIAL COURT NO. 141-225394-07
    ----------
    OPINION
    ----------
    Eddie Kent sued K.B. Alexander Co. of Texas, Inc. (KBA) and Keith B.
    Alexander (Alexander), individually, for breach of contract and fraud in the course
    of performance by KBA of a contract for construction of a car lot. Kent alleged
    KBA and Alexander obtained progress payments from Kent based upon false
    payment applications misrepresenting that subcontractors had been paid for their
    work on the project when they had not. When KBA declared bankruptcy, Kent
    nonsuited KBA and proceeded on his fraud claim against Alexander, individually.
    After a bench trial, the trial court rendered judgment in favor of Kent for fraud
    against Alexander, awarded Kent $20,061.32 in actual damages and $25,249.97
    in attorney’s fees, and made findings of fact and conclusions of law to support
    the judgment. Alexander appeals from the judgment against him.
    Alexander presents seven issues, contending that (1) the pay applications’
    verbiage did not constitute fraudulent representations; (2) Kent’s equal access to
    subcontractor information is fatal to his claim; (3) Kent did not justifiably rely on
    the pay applications; (4) Kent produced no evidence that Alexander intended at
    the outset of the contract not to perform; (5) the pay applications were not signed
    by Alexander, individually, precluding individual fraud liability; (6) there is legally
    and factually insufficient evidence to support the attorney’s fees awarded to Kent;
    and (7) there is factually insufficient evidence to support the damages award.
    We affirm in part and reverse and render in part.
    BACKGROUND
    Alexander was president and sole stockholder of KBA, a construction
    company. In 2006, Kent obtained bids from several contractors and chose KBA
    as general contractor to construct a car lot and an office building for his used car
    business, “Easy Ed’s Autos.” KBA agreed to build a 20,000-square-foot fenced
    concrete lot and an 800-square-foot building with a storefront.
    2
    The Construction Contract
    By a written standard form construction contract entered into between the
    parties, KBA agreed to act as general contractor on the project and to provide all
    labor, materials, equipment, and services necessary to complete the work.1
    Whatever work KBA did not perform itself would be performed by subcontractors.
    The parties agreed on a “lump sum” contract price for the project of $383,871,
    which Kent would pay through a series of monthly progress payments. Article 9
    of the contract set out the specific provisions regarding payment. KBA was to
    prepare a schedule of values apportioned to the various categories of the work,
    with the total of all values to equal the contract price. The schedule of values for
    Kent’s project contained seventeen separate categories of work to be performed.
    Each month, KBA was to submit an “application for payment” to Kent for
    payment of an amount that would be itemized and supported by KBA’s schedule
    of values and any other substantiating data required by the contract. The total of
    the payments would equal the lump sum contract price. Kent agreed to pay the
    amount due on each payment application, less retainage, within ten days of
    receipt.
    Under the terms of the contract, Kent had the right to require partial lien
    and claim waivers from KBA in the amount of the payment applications and
    1
    The printed contract stated on the front page that it was produced from
    software under a grant of a license to subscribers of AGC Docubuilder software,
    was headed “The Associated General Contractors of America, AGC Document
    No. 200,” and was entitled “Standard Form of Agreement and General Conditions
    Between Owner and Contractor (Where the Contract Price is a Lump Sum).”
    3
    affidavits from subcontractors and material suppliers for work that had been
    completed at that time as a prerequisite to payment. He also had the right to
    adjust or reject a payment application or nullify a previously approved application
    for any failure of KBA to properly pay subcontractors or material suppliers. If
    Kent made timely payments but a subcontractor filed a lien against Kent’s
    property, KBA had thirty days to remove the lien, and if it failed to do so, Kent
    could remove the lien himself and recover his costs and expenses directly from
    KBA.
    The Applications for Payment
    Beginning in September 2006 and continuing during the course of
    construction, KBA presented monthly applications for payment to Kent, each
    entitled “APPLICATION AND CERTIFICATE FOR PAYMENT,” requesting
    payment for work completed at the time each application was presented.
    Alexander signed and swore to each application as “President” of KBA. Only the
    last three applications for payment are at issue in this case.2 The first of the
    three applications at issue was dated November 20, 2006, represented that work
    had been completed totaling $228,563, less previous certificates of payment by
    Kent of $96,787, and requested payment from Kent of $120,346. The second
    application at issue, dated December 20, 2006, stated that work had been
    completed totaling $359,719, less previous certificates of payment by Kent
    2
    While previous applications for payment were presented to and paid by
    Kent, those are not at issue.
    4
    totaling $217,133, and requested payment from Kent of $129,307. The third and
    final application for payment at issue was dated January 19, 2007, reflected that
    all work was 100 percent completed, and requested Kent to pay the balance of
    the contract price.
    Each application submitted by KBA to Kent for payment was supported by
    an itemized schedule of values showing the percentage of work completed to
    that date for each of the categories of work listed on the schedule, the dollar
    amounts previously paid by KBA to subcontractors for their work completed, the
    total dollar amount of previous payment applications presented to and paid by
    Kent, and the dollar amount being charged to Kent for progress on the job since
    the previous payment application. Each application contained this certification:
    The undersigned Contractor certifies that to the best of the
    Contractor’s knowledge, information and belief the Work covered by
    this Application for Payment has been completed in accordance with
    the Contract Documents, that all amounts have been paid by the
    Contractor for Work for which previous Certificates of Payment were
    issued and payments received from Owner, and that current
    payment shown herein is now due.
    Shari Riddle, KBA’s project coordinator, kept the books and prepared the
    applications for payment.     She would receive information about the work
    completed to date from pay applications (similar to the payment applications
    submitted by KBA to Kent) filled out by the subcontractors and submitted to KBA
    as to what work they had completed each month, as verified by KBA’s project
    manager. She would input the information and create a payment application to
    be submitted by KBA to Kent. The payment applications were presented to the
    5
    architect to verify the percentage of work completed. She would then present the
    payment applications to Alexander, who would sign each payment application as
    “President” of KBA, and Riddle would notarize his signature on each application
    as “subscribed and sworn to” before her. Each application for payment would
    then be sent by KBA to Kent by fax or by delivery by a project manager for
    payment.
    When Kent received each payment application, he took it to his bank and
    drew against his loan for the project and then wrote a check to KBA. He would
    take the check to KBA’s office and go over the pay application with Riddle. He
    would ask her if it was correct and whether the subcontractors had been paid for
    work completed to the date of each application; Kent’s testimony was undisputed
    that Riddle informed him on each occasion that the subcontractors had been
    paid. Kent made checks out to KBA, which were deposited into KBA’s corporate
    operating account.   Alexander did not dispute that Kent paid the amounts
    requested by each application for payment. Kent was satisfied with KBA’s work
    on the project, and other than a screen and a crash gate, he had no complaints
    about the construction.   He acknowledged that KBA and its subcontractors
    successfully completed the work with the exception of a few punch list items.
    Kent moved onto the newly constructed property after it was completed in
    January 2007.
    6
    Unpaid Subcontractors
    Shortly after Kent moved onto the property and opened for business, one
    of the subcontractors came to Kent’s place of business and asked him if he had
    paid KBA. The subcontractor explained that he had not been paid for his work
    and said that Alexander had told him that he could not pay the subcontractor
    because Kent had not paid him. Concerned that a subcontractor had not been
    paid,    Kent   contacted   Alexander   and    demanded     identification   of   any
    subcontractors who were still owed payment by KBA for work on the project.
    Alexander responded, sending Kent a list of subcontractors to whom KBA still
    owed payment, to which Kent added two more, for a total of between $119,000
    and $120,000 still owed to subcontractors on the project.
    A total of nine subcontractors were still owed money at the end of the job,
    eight of which filed liens against Kent’s property.          Some of the unpaid
    subcontractors made claims against Kent. One subcontractor, who had been
    paid nothing, filed a civil suit against Kent and KBA, which Kent settled for fifty
    cents on the dollar. Kent settled with three other subcontractors who had not
    been paid by KBA or at least not paid in full, giving them cashier’s checks and
    obtaining assignments and releases of their liens.          Specifically, Kent paid
    $6,271.67 to Business Flooring Specialists, $9,413.65 to Ajax Glass, and $4,376
    to Jerry’s Cabinetry.       Other liens were filed against Kent’s property for
    nonpayment by KBA for subcontractors’ work or materials, but he did not pursue
    them in this suit. The only actual damages that he sought to recover were the
    7
    amounts of the three cashier’s checks to Business Flooring Specialists, Ajax
    Glass, and Jerry’s Cabinetry, which totaled $20,061.32.
    THIS SUIT
    Kent sued both KBA and Alexander, individually, for breach of contract and
    fraud. KBA filed for bankruptcy, and Kent nonsuited the company but continued
    his suit against Alexander, individually, based only on his cause of action for
    fraud.     During trial, counsel for Kent argued in his opening statement and
    proceeded to put on evidence to show that the representations made by
    Alexander in the payment applications that subcontractors had been paid were
    false; that the false representations were made intentionally; that Kent justifiably
    relied on those misrepresentations, as well as Alexander’s experience in the
    construction industry, in making the payments requested by the payment
    applications; and that he was damaged as a result by having to settle with and
    obtain releases of mechanic’s and materialmen’s liens filed against his property
    by subcontractors who had not been paid.
    In his opening statement, counsel for Alexander stipulated that
    subcontractors were left unpaid but contended that KBA had other projects that
    just stopped and that other clients of KBA “went under,” causing KBA to fail as
    the result of the economic downturn occurring during the period of Kent’s
    construction project. He argued that the suit was a simple breach of contract
    case that Kent had turned into a vendetta against Alexander.
    8
    Eddie Kent
    Kent testified it was his understanding that each payment application
    presented to him for payment each month certified that subcontractors had been
    paid in full for the work they had completed the previous month. He testified he
    relied upon those certifications in making payments and would not have made
    the payments to KBA as requested by the last three applications for payment had
    he known that subcontractors were not being paid. When he took a payment
    check to KBA, he would talk to Riddle and ask her if the amounts were correct
    and if the subcontractors had been paid, and she would assure Kent they had
    been paid. Kent further said when he learned that the architect offered a service
    to verify that payments had been made to the subcontractors, he consulted
    Alexander about it, but Alexander told him that the architect’s service would be a
    waste of money, that Alexander himself “would see that everybody got paid,” and
    that Kent need not have that sort of due diligence done.
    As an example of how the schedules showing the work completed and
    payments made to subcontractors attached to the payment applications were
    false, Kent testified the figures in the schedule attached to the November 2006
    pay application misrepresented that Jimmy Sanders, who owned General
    Building and Erections, had been paid $12,610, misrepresented that $23,066 had
    been paid for plumbing and storm drainage, and misrepresented that $27,072
    had been paid for electrical work. Kent testified he hired and paid attorneys to
    consider putting KBA in bankruptcy in an effort to get the subcontractors’ unpaid
    9
    bills paid, but the owner of Ajax Glass persuaded him not to. Instead, Kent
    settled with the unpaid subcontractors for fifty cents on the dollar and obtained
    assignments of their liens against his property.
    Shari Riddle
    Riddle, who no longer worked for KBA, testified and explained that every
    subcontractor filled out a form for the work they had completed during each
    month, which was verified by the project manager and given to her for invoicing.
    She did not check to see if the information was correct. Her job in preparing
    payment applications did not include checking to see who had been paid; she
    said that was Alexander’s duty. She explained that the amounts shown each
    month in the column entitled “Previous Applications” in the schedule of values
    attached to each payment application were not necessarily the amounts KBA
    paid to each subcontractor for their work because those amounts included
    overhead and profit. She would input the data she was given and the software
    program would “spit out” the applications for payment owed by the owner based
    on the percentage of work completed. She further testified that Alexander was
    the only person authorized to write checks for KBA.
    Keith Alexander
    Called as an adverse witness, Alexander acknowledged that he
    represented that he had paid the subcontractors as stated in each of the
    certifications in the payment applications presented to Kent.         He further
    acknowledged that the construction contract put the responsibility for payment of
    10
    liens on KBA, that liens were filed against Kent’s property on the project, and that
    KBA was not able to satisfy all of them.
    As to who at KBA specifically had responsibility to see that payments to
    subcontractors were made, Alexander testified that at the time of Kent’s project,
    his company had a bookkeeper and project managers who would approve the
    subcontractor payouts. But they would not necessarily report to him that payouts
    had been made because their focus was on the percentage of completion of the
    job.   Likewise, the architect would verify that the amount of work completed
    matched up with the percentage of completion but verifying that payments to
    subcontractors had been made for their work was not the architect’s
    responsibility; it was KBA’s office’s duty.
    Alexander admitted that he did not review anything before signing the
    December 20, 2006 payment application but relied on “the folks at the office.” He
    had no idea whether the information was true and correct. They had multiple
    projects going at one time. His main job at the corporation was to try to get new
    business and crisis management. If Riddle put a document in front of him to
    sign, he “just signed it.”
    Alexander agreed the final payment application dated January 19, 2007,
    represented that the job was done, except for the five percent retainage, and it
    requested payment by Kent of the balance owed under the contract of $38,210,
    which Kent paid. Alexander acknowledged that, as with the previous applications
    for payment submitted to Kent, Riddle just handed the application to Alexander,
    11
    he signed it, and she notarized it. He explained that KBA’s procedure for the end
    of a month was to gather up all of the payouts to be submitted to the owners and
    give them to him for his signature. Nevertheless, it was his belief that when he
    signed each pay application, each was true and correct.
    As to how applications for progress payments were presented to owners,
    Alexander recalled that payment applications were first sent to the architect for
    his review and verification of percentage of completion and then delivered to the
    owner by fax, by a project manager, or sometimes by himself.             He did not
    remember exactly. When Alexander was asked whether he explained to Kent at
    any time that all of the subcontractors had not been paid, he acknowledged that
    he thought that discussion about subcontractors being owed “was later on in the
    job” when Kent requested the list of subcontractors to whom balances were still
    owed. That answer was consistent with Kent’s testimony that he did not learn of
    any subcontractor not having been paid until one of them came to see him after
    the project was completed, after he had made his last payment of the balance
    owed on the contract, and after he had moved onto the property and opened for
    business. Alexander did not recall when Kent knew that subcontractors were
    owed or on what timeline.
    Alexander knew generally that subcontractors had only a limited amount of
    time—ten to fifteen days after their work was done—to send notification of any
    nonpayment by the general contractor to the property owner and thirty days after
    that to file a lien and that material suppliers had a similarly limited period of time
    12
    after delivery of materials to give notification and then file a lien. He knew that it
    was important for a subcontractor to file a lien quickly and that if a lien was not
    timely filed, the subcontractor could not collect on his lien.
    Subcontractors’ claims
    Kent offered into evidence a copy of a petition filed in a suit by Jerry’s
    Cabinetry against him and KBA for work Jerry’s Cabinetry had done on Kent’s
    construction project. Alexander admitted Jerry’s Cabinetry had not been paid.
    Counsel for Alexander objected to the admission of the petition into evidence,
    stating that Alexander was stipulating that there were unpaid invoices to
    subcontractors and was admitting that Kent suffered injury as a result of KBA not
    paying some subcontractors. In response to an observation by the trial court that
    Kent still needed to prove the damages alleged in his petition, Kent’s counsel
    stated he believed that they would prove about $20,000 in damages from paying
    certain subcontractors to release the liens, plus additional damages incurred
    because of the liens filed against Kent’s property, such as Kent’s inability to get
    loans and having to release the liens, and that the evidence was also relevant to
    show not only a failure of Alexander to pay attention to his business but also the
    way Alexander did business. The trial court overruled Alexander’s objection.
    Upon further questioning about the Jerry’s Cabinetry’s claim and suit,
    Alexander admitted that to his knowledge, KBA did not pay the claim, that the
    claim arose out KBA’s failure to pay Jerry’s Cabinetry for work done on Kent’s
    project, and that Jerry’s Cabinetry had filed a lien against Kent’s property and
    13
    sued, claiming it was owed $8,752. Alexander finally admitted: “I don’t know
    exactly who was paid and who was not paid.” Yet Alexander continued to insist
    that, to the best of his knowledge, his company had paid the subcontractors on
    Kent’s project.   When asked what he did to satisfy that to-the-best-of-his-
    knowledge requirement, Alexander could say only that he would inquire and get
    “different reports back and forth,” that he would ask his office what had been paid
    and what had not been paid, and that he “tried [his] best to assume what the
    information was.” The information would vary from job to job, from month to
    month. But he did not have an exact recollection.
    Kent introduced a letter to Feris Electric & Lighting signed by Alexander
    and dated September 7, 2007, that stated, “Dear Mitch, we are working very hard
    to resolve the mess of the Easy Ed’s project and remedy the remaining balance
    owed on your contract for this project.” Alexander could not recall exactly what
    he was referring to back then as “resolve the mess” but assumed it was the
    close-out of the project—paying the subcontractors the money they were owed
    and completing the punch list and the close out documents. Alexander admitted
    that after September 7, 2007, KBA did not directly pay any subcontractors on
    Kent’s project.   Instead, Alexander said he had an ongoing relationship with
    several subcontractors and was able to pay them indirectly by giving them
    additional work on other projects to make up some of the money not paid to them
    on Kent’s project. He did not dispute that Kent paid the full contract price for the
    14
    project. He insisted that the money went to payments to the subcontractors per
    the terms of the contract.
    A fax Alexander sent to Feris Electric & Lighting on March 27, 2007, said:
    “We are experiencing some un[fore]seen delays in issuing payment for invoices
    that are currently due.” Alexander explained at trial that the “un[fore]seen delays”
    were caused by his clients on several projects filing for bankruptcy. He named
    Coastal Trucking Company and the Family Partnership as clients who had filed
    for bankruptcy and mentioned that several other jobs had some contract
    disputes. But he could not remember which ones.
    Alexander could not give a specific reason why he did not have enough
    money to pay the subcontractors when Kent had paid him the full contract price.
    He could not recall, he said, why he did not fully pay Feris Electric & Lighting. He
    suggested only that, at that time, they may have been doing some warranty work,
    or alternatively, there were some close-out items. He could not remember. He
    acknowledged that the November 2006 payment application represented to Kent
    that previous payments of $27,072 had been made to Feris Electric & Lighting for
    its work on the project. But Alexander could not recall if that amount had actually
    been paid to Feris Electric & Lighting then or if it was paid at a later date. Nor
    could he recall how much he paid Feris Electric & Lighting. On the January 2007
    payment application, previous applications paid to Feris Electric & Lighting were
    shown as $39,020. But Alexander acknowledged that in September 2007, he
    15
    offered Feris Electric & Lighting a promissory note for $25,219.50, which he was
    willing to sign individually, and Feris Electric & Lighting refused to accept it.
    Alexander denied he represented to Kent that Feris Electric & Lighting had
    been paid in the November 2006 and January 2007 payment applications.
    Alexander insisted that the payment application form was not meant to show how
    much the subcontractors had been paid but was primarily used to show progress
    on the job and for the architect to show percentage of completion of the project.
    But he admitted that the application for payment form was entitled “Application
    and Certificate for Payment,” that he used it to present to Kent to obtain payment
    of funds from him, and that as of the January 2007 application for payment,
    Alexander had already received payment from Kent of $346,000 “plus.” And he
    admitted that he had represented in the payment application that “all payments
    have been paid by the contractor for which previous certificate for payment were
    issued.” He admitted that a balance was still owed to Feris Electric & Lighting at
    the time and that he did not tell Kent that. He admitted that he did not tell Kent
    that he was not paying the subcontractors as represented. Had Kent known that
    there was over $100,000 that the subcontractors on his project had not been paid
    as represented, Alexander agreed that Kent probably would have had the right
    not to continue paying KBA. But Alexander did not tell Kent there were unpaid
    balances owed at the end of the project.
    Alexander insisted he did notify Kent that there were some balances still
    owed on the project and stated that he was in the process of getting them paid.
    16
    But he informed Kent of this in the correspondence that went “back and forth”
    between them after Kent had paid in full for the construction and had moved into
    the building. Specifically, Alexander said, he sent a subcontractor audit update
    to Kent. Alexander admitted that the update showed that KBA owed more than
    $80,000 to the subcontractors listed on the audit update. As to what happened
    to the $80,000 that was not paid to those subcontractors for their work,
    Alexander said it went to complete other construction projects; there were
    several going on while KBA was in the process of trying to complete Kent’s
    project.
    All funds paid by Kent and by owners on other projects went into KBA’s
    single corporate operating account. Alexander was head and sole owner of KBA.
    Alexander made his living by construction projects. KBA did not pay him a salary
    but paid him on draws at certain points. He did not recall how much he was paid
    by KBA; it could have been anywhere from $2,000 to $50,000. KBA paid $4,000
    per month to rent space in a building that was owned by Alex Partners, a
    partnership owned by Alexander and his father.
    Alexander recognized a full waiver and release affidavit and release of lien
    filed by CBS Mechanical Services, Inc. in October 2007. He admitted KBA did
    not pay CBS Mechanical for its plumbing work. Alexander said KBA had reached
    an agreement to settle that account and signed a promissory note to CBS
    Mechanical for $26,290, but he admitted that KBA was unable to honor it
    although he thought they made payments toward it. CBS Mechanical’s proof of
    17
    claim filed in KBA’s bankruptcy proceeding stated it was owed $26,974, which
    included interest.   Alexander admitted that he had represented in the final
    payment application for payment submitted to Kent that the scheduled value for
    CBS Mechanical’s services was $24,635 and that CBS Mechanical had been
    paid when, in fact, it had received nothing. Alexander insisted that KBA made
    some payments under its settlement agreement with CBS Mechanical but had no
    documents to substantiate any amounts of additional payments. It was possible,
    he said, that some of the work was done by another company under the heading
    of drainage work or excavation, which had a budget of $9,000, and which he
    represented had been paid.
    Alexander admitted that when he certified that all amounts had been paid
    to subcontractors for work completed, it would be reasonable for someone in
    Kent’s position to rely on that representation. Alexander qualified this admission
    by stating that “most every client asks for back up,” meaning that clients could
    take advantage of provisions in the construction contract to insist on partial lien
    waivers but denied that he was urging that because Kent did not ask for back up,
    he was giving KBA an open door not to pay the subcontractors. He also argued
    that a customer in most instances, if they had a question, would ask for specific
    progress lien releases from each subcontractor and that was an option available
    to Kent under the contract, but Alexander denied that because Kent did not do
    that, it somehow relieved KBA from paying its subcontractors.
    18
    Alexander was aware that KBA also still owed S&S Concrete Contractors,
    Inc., that KBA was probably notified of S&S Concrete’s demand for payment, and
    that S&S Concrete filed a lien against Kent’s property. S&S Concrete supplied
    the concrete and also did the paving on the job. The final payment application
    presented to Kent for payment represented that S&S Concrete had been paid in
    full, but S&S Concrete filed a claim for $8,274 after completion of the project.
    Alexander admitted KBA did not pay S&S Concrete in full, contrary to the final
    application for payment presented to Kent.
    CND Construction provided the drywall work on the project. KBA received
    a bill from that company for $4,138. Alexander did not recall how much CND
    Construction was paid.      They would normally have been included under the
    category of interior finishes, which was listed as fully paid, but Alexander did not
    recall whether everyone was paid on the interior finishes on that job.
    Business Flooring Specialists also did work on the project.           The final
    payment application listed the company as having completed its work and that it
    was paid in full. Alexander also initially testified that it was paid in full. However,
    he then admitted Business Flooring Specialists had filed an affidavit and
    mechanic’s lien against Kent’s property, which he assumed his office was aware
    of.   He knew they sued and got a judgment against KBA and thought they
    received payment from one of KBA’s other projects.
    Peterson’s Landscape was also a subcontractor on the job. Alexander
    admitted that it also was not paid in full. It sued KBA and got a judgment for
    19
    $6,271.67. Peterson’s Landscape filed a claim in KBA’s bankruptcy proceeding
    for $4,012.31; thus, it appeared that KBA paid about $2,000 toward satisfying the
    judgment.
    Lambert Ornamental Iron put fencing around Kent’s project. During the
    same period, Lambert built a fence at Alexander’s personal home. Alexander did
    not believe he used any of the funds from the project to pay for his home’s
    fencing.      But he did not know what Lambert would say about it.     The final
    payment request stated that $29,700 had been paid to Lambert for its work.
    By a letter of May 7, 2007, Alexander wrote Kent that it was “our full
    understanding that we owe balances to some of the subcontractors that
    performed work on your project and it is also our full intention to satisfy the
    balances owed and obtain full releases of liens for your project.”    Alexander
    testified that he assumed that at that time, he had a full understanding that KBA
    still owed money on the project and that, between January and May of 2007, he
    was being informed by his office that KBA had not paid some of the
    subcontractors’ bills. After May 7, 2007, the only payments he recalled making
    were to Peterson’s Landscape and to S&S General Building; he gave more work
    on another project to S&S General Building to help resolve some of the balance
    owed to it.
    Alexander did not know why the twenty-three page summary of schedules
    of unsecured creditors in KBA’s bankruptcy proceeding showed Business
    Flooring Specialists as “not disputed,” CBS Mechanical Services as owed
    20
    nothing, Peterson’s Landscape as owed one dollar, and Easy Ed’s as owed one
    dollar. Alexander knew that Kent’s suit against KBA was filed before KBA filed
    for bankruptcy, and Kent was regularly letting him know what he claimed KBA
    owed him for the expense of settling and getting the subcontractors’ liens
    released from his property. Alexander acknowledged he had another dispute
    going on with another owner over a construction contract at the time he filed for
    bankruptcy on behalf of KBA, University Church of Christ, but he did not list them
    as a creditor; he did not know why. Alexander said the figures were put in by his
    attorneys. During the time frame he was working on Kent’s project, he was also
    working on other projects, including the Education Service Center, the Fort Worth
    Christian School, some churches, Coastal Transportation, Market Street Village,
    and a property in Cleburne. Liens were filed in the Fort Worth Christian School
    project that he thought were satisfied, and a suit had been filed against him by
    Spence Interior Trim with which he entered into an agreed judgment.
    On cross-examination by his own counsel, Alexander testified he signed
    the construction contract and pay applications as president of KBA on behalf of
    KBA, the undersigned contractor, not individually.        As to the bankruptcy
    schedules of creditors, Alexander said that the listings for payments owed to
    CBS Mechanical and to Peterson’s Landscape for work on Kent’s property were
    stated to be “zero” and one dollar because of his belief that, since he had
    settlement agreements with each, they were not owed anything. Easy Ed’s claim
    was listed as one dollar because Alexander did not know how much Kent
    21
    claimed he was actually due. Alexander further testified (after scolding by the
    trial court to not just make up stuff or to keep saying simply that he did not know)
    that counsel prepared the schedules in the bankruptcy proceedings based on
    documents he furnished and that any incorrect numbers were simply a mistake
    on his part and not intentional. Alexander said that the schedules for KBA’s
    bankruptcy were based on information he gave to his attorneys and that the
    information was accurate to the best of his knowledge at the time; he understood
    those schedules to be correct based on his attorneys’ recommendation.
    Alexander said that he signed the pay applications in reliance upon the
    information provided to him by his office staff, understanding that the
    subcontractors had been paid.      He never intended for any subcontractor or
    supplier working for KBA not to be paid or for any project to go unfinished. He
    attempted to get the subcontractors paid through settlement agreements,
    promissory notes, promising other work, and offering to be personally liable on
    notes for some of the debts to make sure the subcontractors understood that he
    was sincere and intent on trying to get the debts paid.
    Alexander testified he did not personally benefit directly from his work for
    Kent; instead, he lost everything. He lost his building, which he sold in a short
    sale after it was posted for foreclosure.      He was left with a deficiency of
    $34,185.20, for which he had to guarantee a note to the bank. He testified that
    over the past five years, he had personally paid over $100,000 to satisfy some of
    the claims against the business. While the Kent construction job was ongoing,
    22
    he was already facing legal issues. The Market Street project was in litigation;
    the developer placed $475,000 into the registry of the court, and KBA never
    received those funds.
    Alexander explained that he had jobs with bad estimates that he ended up
    losing money on, and Easy Ed’s Autos was one of those jobs. He testified that
    decisions about paying subcontractors were made by him based upon “managing
    the cash flow of the business.” There was never any intent not to pay anybody;
    he thought KBA went to great lengths to pay everybody.
    Alexander admitted he realized KBA was in serious financial distress when
    it was trying to wrap up the Market Street project in 2005.         He identified a
    materialman’s lien from that project for $156,000 that was signed March 20,
    2005. He did not enter into the contract for Kent’s project until over a year later.
    Alexander said he was not involved in day-to-day operations and was not paying
    attention to the bills, and he thought everything was being done the way it was
    supposed to be done. He admitted that, at the time he entered into the contract
    with Kent, he was having financial problems. At that juncture, he was spending a
    lot of time trying to collect the $485,000 owed to KBA on the Market Street
    project, and he had several lawsuits pending against a developer.
    In answer to questions by the trial court, Alexander admitted he had
    access to KBA’s bank statements but did not recall doing any due diligence to
    make sure they were accurate. He admitted that the $4,000 that came out of
    KBA’s operating account every month was for the rent on the building occupied
    23
    by KBA. In other words, Alexander admitted, even when subcontractors were
    not being paid, he managed to pay the rent for the building he owned with his
    father.
    Testimony of Subcontractors
    Joe Peterson, president of Peterson’s Landscape, testified he was
    “partially” paid but had to take action to enforce the payment. For the first three
    months or so, every week or every other week, Peterson would stop by KBA’s
    offices or call Alexander, who would tell him that he had never been paid by Kent
    and could not send Peterson his money until he got paid. After a few months of
    being told the same thing, Peterson was angry and called Kent to ask him why
    he had not paid KBA.      Kent told him he had paid and showed him proof.
    Peterson then sued KBA in small claims court and entered into an agreed
    judgment with KBA. Alexander made a few payments but then stopped three or
    four months prior to KBA declaring bankruptcy.
    Arthur Moses, owner of Ajax Glass and Mirror, testified he contacted
    Alexander multiple times in June or July 2008 about the money owed to Ajax
    Glass as a subcontractor. Alexander never told Moses why he could not pay
    Ajax Glass. Moses said he received only $800 in payment from KBA. He filed a
    lien against Kent’s property for the balance of $18,827.30.
    Jerry Eberly, owner of Jerry’s Cabinetry, Inc., testified he provided
    cabinetry services on the project and was not paid. Alexander gave him multiple
    answers for why he was not being paid, including that he had not been paid by
    24
    Kent. But Kent showed him documentation that he had paid KBA. KBA finally
    gave Eberly partial payment.
    Sanders’s company, General Building and Erections, provided the building
    portion of the roof units and canopies and was not paid. Sanders testified that
    Alexander told him KBA did not have the money to pay General Building and
    Erections but did not tell him why. Alexander agreed to a note with monthly
    installment payments. General Building and Erections did not file a lien on Kent’s
    property. Sanders stated that he had been in business forty-one years and had
    yet to file a lien on anyone’s property. Alexander paid half of the note before
    KBA filed for bankruptcy. He still owes about half of it. Sanders was still working
    with Alexander at the time of trial.
    Sanders testified that there were times when either Alexander did not get
    paid or could not pay, and in those situations, Sanders agreed to give KBA a bid
    on the next job in which Sanders would be paid a higher amount to pay the one
    on which KBA still owed him. At the time of trial, Sanders was working on a job
    in Grand Prairie for Alexander as general contractor. In 2012, he had worked on
    several jobs with Alexander as general contractor, including some Goodwill
    stores, Service Masters in Euless, CMC Trailers, and Lone Star Forklifts.
    Sanders testified he had also done work as a subcontractor for Alexander under
    the names of three different corporations in addition to KBA. He said he would
    bid a job for Alexander today and work for him, provided the contracts are drawn
    for joint check agreements.
    25
    Chris Guensfelder testified he owns Lambert Ornamental Iron, which
    fabricates and installs ornamental iron, fences, gates, and stairs. He provided a
    fence and manual slide gate on Kent’s project. He also did work on a fence for
    Alexander’s father’s home. He did not recall whether he was paid for that work
    from corporate funds. He invoiced Alexander in November 2006 for the work
    done on Kent’s project and received payment after seven months.                 KBA’s
    payment was in three or four installments. He recalled making repeated calls to
    be paid.
    Judgment
    Following the trial, as relevant to this appeal, the trial court entered written
    findings of fact and conclusions of law, finding and concluding as follows:
    (3)    The subcontractors completed the work on the project and a
    final draw was presented to Plaintiff on or about January 19, 2007.
    (4)   The final draw certified all subcontractors were paid in full and
    was signed by Keith Alexander and certified by Keith Alexander.
    (5)   Plaintiff paid all amounts due under the contract and as
    provided in the draw applications.
    (6)   All checks were paid to Keith Alexander.
    (7)  All subcontractors were not paid as represented by Keith
    Alexander.
    (8)   The representations that all subcontractors were paid
    were . . . false statement[s] made by Keith Alexander.
    (9)   Based on the false statements[,] Plaintiff Eddie Kent paid K.B.
    Alexander Co. of Texas, Inc. all sums due and owing under the
    contract.
    26
    (10) Plaintiff[,] after final payment was made to Keith Alexander[,]
    discovered all subcontractors on his project were not paid as
    represented by Keith Alexander.
    ....
    (12) The representations made to Plaintiff by Keith Alexander were
    material and relied upon by Plaintiff.
    (13) Keith    Alexander      knew     the    representations   about
    subcontractors being paid in full were false when made to plaintiff.
    (14) Plaintiff was damaged by Keith Alexander’s false statements.
    (15) Plaintiff was required to defend lawsuits, settle lawsuits, pay
    mechanic’s liens[,] and incur legal expenses that but for Keith
    Alexander’s false statements would not have been expenses the
    Plaintiff would have incurred.
    (16) Keith Alexander has been involved in a number of projects
    where project funds were not properly applied to the projects[’]
    expenses. Keith Alexander has been involved in a number of
    lawsuits and had mechanics [liens] filed on his company’s building
    projects in the past.
    (17) In other building projects[,] the land owners were subject to
    paying mechanic’s liens and [were] involved in lawsuits over
    payment of subcontractors by Keith Alexander or a company he
    control[l]ed.
    ....
    (21) Keith Alexander’s actions in filing a mechanic’s lien were done
    to harm the Plaintiff.
    (22) Keith Alexander’s failure to pay subcontractors on the
    Plaintiff’s project were a part of planned way of doing business by
    Keith Alexander and were done to defraud the Plaintiff.
    (23) Plaintiff has incurred actual damages in the amount of
    $20,061.32.
    27
    (24) Plaintiff has incurred legal fees and expenses with the office of
    David L. Pritchard as of August 1, 2013[,] in the amount $22,249.97.
    (25) Plaintiff [has] incurred legal fees with special bankruptcy
    counsel in the amount of $3[,]000.00[.]
    ....
    (27) Keith Alexander committed fraud by representing to Plaintiffs
    [that] subcontractors had been paid, when Keith Alexander knew all
    of said subcontractors had not been paid.
    (28) Plaintiff’s reliance on said fraudulent representations resulted
    in the Plaintiff being damaged.
    (29) Keith Alexander[’s] lien claim was done with the intent to harm
    the Plaintiff.
    (30) Keith Alexander[’s] actions were done knowingly with the
    intent to harm the Plaintiff and subject Keith Alexander to exemplary
    damages.
    ANALYSIS
    Although his issues, as worded, do not expressly challenge the legal and
    factual sufficiency of the evidence, Alexander’s summary of his arguments at the
    outset of his brief, as well as the substance of his arguments, reveal that he is
    challenging the legal and factual sufficiency of the evidence to support the trial
    court’s findings. On close scrutiny, all but one of his arguments (that one being
    his challenge to the verbiage of the pay applications) under his issues are
    essentially legal and factual insufficiency complaints that we read as “fairly
    included” in his issues. See Tex. R. App. P. 38.1(f) (“The statement of an issue
    or point will be treated as covering every subsidiary question that is fairly
    included.”), 38.9 (stating that briefing rules should be construed liberally and “are
    28
    meant to acquaint the court with the issues in a case and to present argument
    that will enable the court to decide the case”). Consequently, we will consider
    Alexander’s issues under the usual legal and factual sufficiency standards of
    review.
    STANDARD OF REVIEW
    A trial court’s findings of fact have the same force and dignity as a jury’s
    answers to jury questions and are reviewable for legal and factual sufficiency of
    the evidence to support them by the same standards. Catalina v. Blasdel, 
    881 S.W.2d 295
    , 297 (Tex. 1994); Anderson v. City of Seven Points, 
    806 S.W.2d 791
    , 794 (Tex. 1991); see also MBM Fin. Corp. v. Woodlands Operating Co., 
    292 S.W.3d 660
    , 663 n.3 (Tex. 2009). We defer to unchallenged findings of fact that
    are supported by some evidence.       Tenaska Energy, Inc. v. Ponderosa Pine
    Energy, LLC, 
    437 S.W.3d 518
    , 523 (Tex. 2014).
    When a party challenges the legal sufficiency of the evidence to support an
    adverse finding on which he did not have the burden of proof at trial, the party
    must demonstrate that there is no evidence to support the adverse finding.
    Thornton v. Dobbs, 
    355 S.W.3d 312
    , 316 (Tex. App.—Dallas 2011, no pet.). In
    determining whether there is legally sufficient evidence to support the finding
    under review, we must consider evidence favorable to the finding if a reasonable
    factfinder could and disregard evidence contrary to the finding unless a
    reasonable factfinder could not. Cent. Ready Mix Concrete Co. v. Islas, 
    228 S.W.3d 649
    , 651 (Tex. 2007); City of Keller v. Wilson, 
    168 S.W.3d 802
    , 807, 827
    29
    (Tex. 2005). Anything more than a scintilla of evidence is legally sufficient to
    support the finding. Cont’l Coffee Prods. Co. v. Cazarez, 
    937 S.W.2d 444
    , 450
    (Tex. 1996); Leitch v. Hornsby, 
    935 S.W.2d 114
    , 118 (Tex. 1996). More than a
    scintilla of evidence exists if the evidence furnishes some reasonable basis for
    differing conclusions by reasonable minds about the existence of a vital fact.
    Rocor Int’l, Inc. v. Nat’l Union Fire Ins. Co., 
    77 S.W.3d 253
    , 262 (Tex. 2002).
    When reviewing an assertion that the evidence is factually insufficient to
    support a finding, we set aside the finding only if, after considering and weighing
    all of the evidence in the record pertinent to that finding, we determine that the
    credible evidence supporting the finding is so weak, or so contrary to the
    overwhelming weight of all the evidence, that the answer should be set aside and
    a new trial ordered. Pool v. Ford Motor Co., 
    715 S.W.2d 629
    , 635 (Tex. 1986)
    (op. on reh’g); Cain v. Bain, 
    709 S.W.2d 175
    , 176 (Tex. 1986); Garza v. Alviar,
    
    395 S.W.2d 821
    , 823 (Tex. 1965). The trial court, as factfinder in a bench trial, is
    the sole judge of the credibility of the witnesses. 
    Thornton, 355 S.W.3d at 315
    .
    We review a trial court’s conclusions of law de novo to determine whether the
    trial court correctly drew the legal conclusions from the facts. 
    Id. at 316.
    APPLICABLE LAW
    “The elements of fraud are a material misrepresentation, which was false,
    and which was either known to be false when made or was asserted without
    knowledge of its truth, which was intended to be acted upon, which was relied
    upon, and which caused injury.” Sears, Roebuck & Co. v. Meadows, 
    877 S.W.2d 30
    281, 282 (Tex. 1994) (quoting DeSantis v. Wackenhut Corp., 
    793 S.W.2d 670
    ,
    688 (Tex. 1990), cert. denied, 
    498 U.S. 1048
    (1991)); see also Formosa Plastics
    Corp. USA v. Presidio Eng’rs & Contractors, Inc., 
    960 S.W.2d 41
    , 47–48 (Tex.
    1998).
    APPLICATION OF LAW TO ISSUES
    “Verbiage” of the pay applications
    As part of his first issue, Alexander challenges findings of fact 4, 7, 8, 9,
    13, 14, 15, and 22, contending that the language of the pay applications
    submitted by KBA to Kent—certifying that to the best of KBA’s “knowledge,
    information, and belief . . . all amounts have been paid by the Contractor for
    Work for which previous Certificates of Payment were issued”—was not the type
    of affirmative statement of fact actionable for fraud.      Alexander places his
    reliance on a criminal case in which the court of criminal appeals rejected an
    attorney’s affidavit containing the same language in support of a motion for new
    trial based on jury misconduct because the affidavit stated no positive material
    fact, did not reveal what information the affiant had or relied upon or its source,
    and did not state that the affiant had any knowledge of the subject matter.3
    Alexander argues KBA’s certification is likewise devoid of substance because it
    did not assert that KBA had any knowledge on the subject, did not state that KBA
    had conducted any inquiry, reviewed documents, or completed an audit, and did
    3
    Calyon v. State, 
    174 S.W. 591
    , 600 (Tex. Crim. App. 1915), overruled in
    part by Means v. State, 
    271 S.W. 613
    , 614–15 (Tex. Crim. App. 1925).
    31
    not provide a context from which Kent could deduce KBA’s knowledge or
    information. In essence, he contends, it fails to meet the criteria for an affidavit.
    Therefore, Alexander asserts that the certification does not constitute an
    actionable statement for fraud.
    The issue is not whether Alexander’s certification in the applications met all
    the criteria for an affidavit as required for a motion for new trial or even for a
    motion for summary judgment but whether, under all of the circumstances viewed
    most favorably in the light of the trial court’s findings and judgment, it constituted
    a representation that, if false, would constitute an actionable misrepresentation
    that “all amounts have been paid by the Contractor for Work for which previous
    Certificates of Payment were issued.”         There is far more to the payment
    applications than a general statement with no context from which to determine
    the affiant’s personal knowledge such as in Calyon, in which an attorney averred
    that he had information from an unknown source about jury 
    misconduct. 174 S.W. at 598
    .     Each pay application, signed and sworn to by Alexander as
    representative of KBA, was supported by a schedule of values specifically listing
    each category on which work had been done to the date of the application and
    the percentage of completion of that work to date, as well as the amounts
    purported to have been previously paid to the subcontractors for each such
    category.     The trial court reasonably could have concluded from the
    circumstances surrounding the certifications as known to Kent that Alexander, as
    sole owner of KBA and with over twenty years of experience, was certainly in a
    32
    position to have personal knowledge of whether he had paid his own
    subcontractors for the work that previously had been completed.         Kent even
    followed up with KBA’s office manager to reassure himself that the
    subcontractors had been paid before making each of the progress payments.
    Significantly, Kent’s testimony was undisputed that when he approached
    Alexander about obtaining verification of payment to subcontractors through the
    architect’s optional service provided for that very purpose, Alexander verbally
    reassured him that it would be a waste of time and told him that Alexander
    himself would “see that everybody got paid.”
    It was undisputed and even stipulated by Alexander at trial that, contrary to
    the representations in the pay applications of November and December 2006,
    and January 2007, Alexander had not paid subcontractors for work completed in
    the last three months of the project to the extent of over $100,000, which was not
    revealed to Kent by Alexander and not discovered by Kent until after Kent paid
    for completion of the job and after he had moved onto the premises and opened
    for business. The trial court could also have reasonably concluded that by at
    least November 2006, Alexander knew KBA could not meet its obligations to its
    subcontractors for other projects as well as Kent’s and had ceased being able to
    pay the subcontractors. We hold that the trial court did not err in finding that the
    pay applications misrepresented that all subcontractors had been paid for work
    completed by them during the previous month.
    33
    Accordingly, we hold that legally and factually sufficient evidence supports
    the trial court’s findings of misrepresentation and that such misrepresentations
    constituted fraud in findings of fact numbers 4, 7, 8, 9, 13, 14, 15, and 22,
    particularly when considered in the light of the surrounding circumstances,
    including the verbal reassurance to Kent by Alexander that he would see that the
    subcontractors got paid.4 We overrule this portion of Alexander’s first issue.
    Kent’s “equal access” to knowledge
    In his second issue, Alexander contends that Kent possessed equal
    access to knowledge of KBA’s payments to its subcontractors by the terms of
    Kent’s construction contract with KBA. Alexander relies upon Paull v. Capital
    Resource Management, Inc., 
    987 S.W.2d 214
    (Tex. App.—Austin 1999, pet.
    denied), a case in which investors in working interests in an oil and gas
    waterflood project sued an oil and gas development corporation and its principals
    for, among other causes of action, fraud for allegedly misrepresenting that the
    investment was the “lowest risk” that the sellers had seen and for alleged
    misrepresentations in a field summary that analyzed economic forecasts,
    projected productivity, and predicted large revenues and profits from production
    in an analogous field. 
    Id. at 218–19.
    Affirming a summary judgment in favor of
    the sellers on the investors’ fraud claim, the appellate court held that, because
    4
    In his statement of issues, Kent states he is challenging findings 3–10,
    12–17, and 21–25, but he does not revisit his challenges to findings 3, 5, 6, 10,
    12, 16, 17, 21, 24, or 25 in any of his issues. We address his challenge to finding
    23 later in this opinion.
    34
    the investors were provided all information requested and the field summary was
    based upon publicly available records of prior oil and gas production history in
    analogous fields to which the investors had equal access, the investors were
    prevented from claiming they were defrauded by the company’s statements or
    opinions. 
    Id. at 221.
    We disagree that Paull is analogous. Alexander claims Kent had equal
    access to subcontractor information and points to the provisions of the contract
    under which Kent had rights entitling him to lien waivers, claim waivers, and
    affidavits from the subcontractors on demand as a prerequisite to payment, as
    well as the right to adjust or reject payment applications or even nullify previously
    approved applications if KBA failed to properly pay the subcontractors following
    receipt of payment from Kent. But unlike the records available to the public from
    analogous oil and gas fields in Paull, there were no records accessible to Kent by
    which he could have learned whether the subcontractors on his job were being
    paid by KBA. We find no provision in the contract giving Kent any access, much
    less equal access, to the bookkeeping or other internal records of KBA that
    would indicate whether or when subcontractors were being paid. Kent testified
    that when he went to KBA’s office each month with a check from the bank to
    make his progress payment, he would specifically inquire of Riddle whether the
    subcontractors were paid for their completed work before making his payment to
    KBA, and Riddle would assure him that they had been paid. And when Kent
    approached Alexander about the architect’s offer of a service to audit whether
    35
    the subcontractors were properly being paid for completed work, Alexander
    reassured Kent that he would see that the subcontractors were paid and that
    Kent did not need to waste money on an audit by the architect to make sure that
    they were, in fact, paid.
    Moreover, it was undisputed that the only person with check-writing
    authority in the company was Alexander.       Thus, the only person who knew
    whether the subcontractors were paid each month for work completed was
    Alexander. Alexander certified to Kent under oath in each pay application that
    the subcontractors had been paid for work completed at the time of each
    application. The one fact that Kent needed to know—that the subcontractors had
    been paid—was misrepresented in the pay applications, and thus, Kent had no
    knowledge, much less equal access to knowledge, that might have alerted him to
    exercise any of his contractual rights based upon KBA’s failure to pay the
    subcontractors. Once he obtained the knowledge that the subcontractors had
    not been paid and liens had been filed against his property, and after KBA failed
    within thirty days, as required by the contract, to remove the liens filed against
    Kent’s property by the subcontractors who had not been paid, Kent exercised his
    post hoc contractual remedy of negotiating and settling the claims for KBA’s
    nonpayment of subcontractors with his own funds, obtained releases of the liens
    placed against his property, and filed this suit against Alexander and KBA for
    recovery of his costs, expenses, and attorney’s fees. Accordingly, we overrule
    Alexander’s second issue.
    36
    Kent’s Reliance was “Justifiable”
    Alexander argues by his third issue that the evidence is factually
    insufficient to establish that Kent’s reliance on the pay applications was
    “justifiable” in light of Kent’s awareness of the risk that KBA would not pay the
    subcontractors and because Kent failed to exercise due diligence in asserting his
    negotiated contractual rights, which, Alexander says, would have protected his
    interests. Assuming that Kent had the burden to establish that his reliance on the
    pay applications was justifiable, Kent’s contractual rights gave Kent no protection
    absent knowledge that the subcontractors had not been paid by KBA. Instead,
    the contract expressly conditioned any right Kent would have to receive partial
    lien waivers and affidavits from subcontractors on his payment of amounts due to
    KBA on the pay applications. Likewise, although Kent had the right, upon written
    notice to KBA to “adjust” or “nullify” any previously approved payment application
    and to withhold payment to the extent KBA was responsible for failure to pay
    subcontractors, that right could do him no good when Alexander misrepresented
    in the pay applications that subcontractors had been paid. Alexander cites no
    evidence that Kent had reason to suspect otherwise.          And Kent expressly
    inquired and was reassured both by the office manager and by Alexander that
    the subcontractors had been paid before making his three final payments. We
    overrule Alexander’s third issue.
    37
    Intent Not to Perform
    By his fourth issue, Alexander contends there is no evidence that he had
    no intent to pay the subcontractors before the contract was executed, arguing
    that a plaintiff must show that a defendant had no intention to perform when it
    made a promise or entered into the contract in order to support a claim of fraud.
    Alexander points out that KBA completed the project, that Kent was happy with
    the work, and that KBA partially performed by paying some of the subcontractors.
    Alexander contends that his failure to pay all of the subcontractors was, at most,
    a breach of the contract that, standing alone, is not evidence of intent not to
    perform when the contract was made.
    This argument might have merit if Kent had alleged and attempted to prove
    a claim of fraud in the inducement of the contract when the contract was
    executed on August 25, 2006. See Haase v. Glazner, 
    62 S.W.3d 795
    , 798–99
    (Tex. 2001) (stating that fraudulent inducement is a “particular species of fraud
    that arises only in the context of a contract and requires the existence of a
    contract as part of its proof. That is, with a fraudulent inducement claim, the
    elements of fraud must be established as they relate to an agreement between
    the parties.”). But Kent did not allege or attempt to prove fraud in the inducement
    of the contract. In his original petition, which was Kent’s live pleading at trial,
    Kent alleged that “Defendants induced Plaintiff to make payments under the
    agreement by presenting Plaintiff with statements signed by Defendant Keith B.
    Alexander that claimed all the subcontractors had been paid in full.” Kent further
    38
    alleged that the statements were false and were relied upon by him to his
    detriment, proximately resulting in damages of having liens placed on his
    property, a reduced credit rating, liability to subcontractors, and an inability to get
    the remainder of the contract completed. In conformity with his pleadings, Kent
    never contended at trial that he was fraudulently induced into the contract but put
    on evidence that the misrepresentations in the last three pay applications of
    November and December 2006 and January 2007 certifying that subcontractors
    had been paid caused him to make the final three progress payments to KBA on
    the contract when he would not have done so otherwise and could have avoided
    the mechanic’s and materialmen’s liens being placed on his property and the
    expense of paying the subcontractors himself and getting the liens released. We
    overrule Alexander’s fourth issue.
    Individual Liability of Alexander
    By his fifth issue, Alexander asserts that he cannot be individually liable
    because he was not a party to the contract and signed the contract and the pay
    applications only in his corporate capacity as president of KBA.             First, he
    contends there is no evidence that he acted in his individual capacity in
    representing “that all amounts have been paid by the Contractor for work for
    which previous Certificates of Payment were issued and payments received from
    Owner.” Alexander argues that this statement contained in each application for
    payment presented to Kent shows on its face that it is the statement of the
    corporation, not Alexander, individually. Secondly, Alexander contends that he
    39
    cannot be held individually liable because a corporate officer cannot be held
    liable for inducing the corporation to violate a contractual obligation as long as he
    acted in good faith, and Kent failed to produce any evidence that Alexander
    acted in a manner so contrary to the best interest of the corporation that his
    actions could only be motivated by personal interest. Alexander did not argue
    these theories in the trial court. Because legal insufficiency of the evidence may
    be raised for the first time on appeal from a judgment after a nonjury trial,
    however, these theories are properly raised in that context, and we will consider
    them. See Tex. R. App. P. 33.1(d).
    Alexander relies upon Leitch v. Hornsby for the proposition that a
    corporate officer’s acts taken on the corporation’s behalf are deemed corporate
    
    acts. 935 S.W.3d at 117
    . In Leitch, the Texas Supreme Court held that officers
    and directors of the plaintiff’s corporate employer could not be held liable for
    negligence in failing to furnish the plaintiff with safety equipment that could have
    prevented his work-related injuries. 
    Id. at 120.
    This was because the employer
    corporation, but not the individual corporate officers, owed a nondelegable duty
    to provide an employee of the corporation a safe workplace.          
    Id. at 117–18.
    Leitch has no application to this case because that case involved liability of a
    corporate agent to an employee of the corporation, not liability to a third party.
    See id.; see also PWS Food, Inc. v. Taco Bell Corp., No. 05-01-01211-CV, 
    2002 WL 523697
    , at *7 n.3 (Tex. App.—Dallas Apr. 9, 2002, no pet.) (not designated
    for publication).
    40
    The general rule in Texas has always been that “[a] corporation’s
    employee is personally liable for tortious acts which he directs or participates in
    during his employment.” Gore v. Scotland Golf, Inc., 
    136 S.W.3d 26
    , 32 (Tex.
    App.—San Antonio 2003, pet. denied); see Graham Land & Cattle Co. v. Indep.
    Bankers Bank, 
    205 S.W.3d 21
    , 32 (Tex. App.—Corpus Christi 2006, no pet.)
    (“[A]n employee who commits, directs[,] or participates in a tortious act while
    acting within the scope of his employment is personally liable for those acts.”);
    Morris v. Kohls–York, 
    164 S.W.3d 686
    , 695 (Tex. App.—Austin 2005, pet.
    dism’d) (“Corporate agents are individually liable for fraudulent or tortious acts
    committed while in the service of their corporation.”); Cimarron Hydrocarbons
    Corp. v. Carpenter, 
    143 S.W.3d 560
    , 564 (Tex. App.—Dallas 2004, pet. denied)
    (“It is a longstanding rule in Texas that a corporate agent is personally liable for
    his own fraudulent or tortious acts, even when acting within the course and scope
    of his employment.”).
    In a footnote, Alexander cites Karl & Kelly Co., Inc. v. McLerran, 
    646 S.W.2d 174
    , 175 (Tex. 1983), to suggest that individual liability against him is
    impossible without piercing KBA’s corporate veil, which Kent never alleged nor
    sought to prove. McLerran was implicitly overruled by the supreme court in Light
    v. Wilson, 
    663 S.W.2d 813
    , 814–15 (Tex. 1983).          See Miller v. Keyser, 
    90 S.W.3d 712
    , 717 (Tex. 2002) (agreeing with concurring opinion in Light, which
    stated that Light implicitly overruled McLerran). In the same vein, Alexander also
    argues that an officer is insulated from individual liability for his own actions if
    41
    they are taken in his capacity as an agent of the corporation and on its behalf.
    To the contrary, this argument merely brings us full circle back to “the
    longstanding rule in Texas . . . that ‘[a] corporation’s employee is personally liable
    for tortious acts which he directs or participates in during his employment.’”
    Kingston v. Helm, 
    82 S.W.3d 755
    , 758 (Tex. App.—Corpus Christi 2002, pet.
    denied) (quoting Leyendecker & Assocs., Inc. v. Wechter, 
    683 S.W.2d 369
    , 375
    (Tex. 1984)).    “The law is well-settled that a corporate agent can be held
    individually liable for fraudulent statements or knowing misrepresentations even
    when they are made in the capacity of a representative of the corporation.”
    
    Kingston, 82 S.W.3d at 759
    (emphasis added); see Sanchez v. Mulvaney, 
    274 S.W.3d 708
    , 712 (Tex. App.—San Antonio 2008, no pet.) (holding corporate
    agents liable for their own fraudulent and tortious acts even when acting within
    the course and scope of their employment); see also Shapolsky v. Brewton, 
    56 S.W.3d 120
    , 133 (Tex. App.—Houston [14th Dist.] 2001, pet. denied) (“It is the
    general rule in Texas that corporate agents are individually liable for fraudulent or
    tortious acts committed while in the service of their corporation.”), disapproved of
    on other grounds by Michiana Easy Livin’ Country, Inc. v. Holten, 
    168 S.W.3d 777
    , 788–89 (Tex. 2005). In an action seeking to hold an officer liable for his
    own fraudulent statements, the corporate veil is not required to be pierced.
    
    Sanchez, 274 S.W.3d at 712
    ; 
    Kingston, 82 S.W.3d at 766
    .5                We overrule
    Alexander’s fifth issue.
    5
    Alexander’s argument that there is no evidence that Alexander acted in a
    42
    Attorney’s Fees
    By his sixth issue, Alexander asserts that the trial court’s award of
    $22,249.97 for attorney’s fees and $3,000 for additional bankruptcy counsel fees
    is supported by neither the law nor the evidence. We agree. A plaintiff may not
    recover attorney’s fees in a common-law fraud action. See MBM Fin. Corp. v.
    The Woodlands Operating Co., L.P., 
    292 S.W.3d 660
    , 667 (Tex. 2009) (holding
    attorney’s fees not recoverable for fraud even if fraud claim arose from breach of
    contract); Tony Gullo Motors I, L.P. v. Chapa, 
    212 S.W.3d 299
    , 311–12 (Tex.
    2006) (same). Because Kent’s action against Alexander was based on fraud
    alone, he is not entitled to recover attorney’s fees for prosecuting this action.
    Additionally, Kent is precluded from recovering the $3,000 the trial court
    awarded as special bankruptcy fees. He testified he retained legal counsel to
    attempt to place KBA into involuntary bankruptcy in order to collect from KBA the
    amounts he paid to subcontractors. He was later convinced by Arthur Moses of
    Ajax Glass to abandon the idea of putting Alexander into bankruptcy. Those fees
    were not reliance damages, nor were they shown to have been caused by the
    fraud. They also were not proved up by expert testimony or any other evidence
    that they were reasonable or necessary. We sustain Alexander’s sixth issue.
    manner so contrary to the best interest of the corporation that his actions could
    only be motivated by personal interest, is likewise inapplicable to this case.
    Alexander cites Holloway v. Skinner, 
    898 S.W.2d 793
    , 795 (Tex. 1995), for the
    test for individual liability of a corporate officer. But Holloway involved a cause of
    action against a corporate officer in his individual capacity for tortious
    interference with a contract between the corporation and a third party. 
    Id. at 794.
    Kent did not assert a claim for tortious interference with contract.
    43
    Damages
    In the remaining part of his first issue, Alexander contends Kent failed to
    produce even a scintilla of evidence that the payment applications admitted at
    trial “were tied to his actual damages” found by the trial court. We will liberally
    construe this contention as a complaint of no evidence to support the trial court’s
    findings that Kent was damaged by Alexander’s false statements (finding no. 14);
    that Kent was required to defend and settle lawsuits, to pay mechanic’s liens,
    and to incur legal expenses that he would not have incurred but for Alexander’s
    false statements (finding no. 15); and that Kent incurred actual damages of
    $20,061.32 (finding no. 23).
    As we related in summarizing the evidence, Kent testified he understood
    that each payment application Alexander presented to him certified that
    subcontractors had been paid in full for the work they had completed the
    previous month. And Kent said that he relied upon those certifications in making
    payments and would not have made the payments to KBA as requested in the
    last three applications for payment had he known that subcontractors were not
    being paid.
    Alexander admitted that he had represented that he had paid the
    subcontractors as he had certified in the payment applications he presented to
    Kent. He further acknowledged that the construction contract put the
    responsibility for payment of liens on KBA, that liens were filed against Kent’s
    44
    property on the project by unpaid subcontractors, and that KBA was not able to
    satisfy all of them.
    As to his damages for payment to release the lien of Business Flooring
    Specialists, Kent testified that the final payment application dated January 2007
    listed that subcontractor as having completed its work and that it was paid in full.
    Alexander also testified he had paid that subcontractor in full.      But he later
    acknowledged that Business Flooring Specialists filed an affidavit and
    mechanic’s lien against Kent’s property for unpaid amounts due, which he
    assumed his office was aware of, and knew that the subcontractor sued and got
    a judgment against KBA. Kent testified he paid Business Flooring Specialists
    $6,271.67, fifty percent of its claim, to settle with it and obtained an assignment
    of its lien.
    Alexander also admitted that Ajax Glass, another subcontractor on Kent’s
    project, was never paid “in full.” There was a payment shown as having been
    made to Ajax Glass by KBA for $18,510. But the lien affidavit filed by Ajax Glass
    in support of its lien against Kent’s property showed an amount unpaid and owing
    of $18,827.30. Alexander admitted KBA paid Ajax Glass less than $1,000. The
    lien affidavit filed by Ajax Glass against Kent’s property stated KBA had paid Ajax
    Glass only $800. Kent testified he paid Ajax Glass $9,413.65.
    Alexander admitted that, to his knowledge, KBA did not pay Jerry’s
    Cabinetry for its work as a subcontractor, that Jerry’s Cabinetry’s claim against
    Kent arose out of KBA’s failure to pay Jerry’s Cabinetry for its work on Kent’s
    45
    project, and that Jerry’s Cabinetry filed a lien against Kent’s property and sued
    Kent, claiming it was owed $8,752.      Kent settled with Jerry’s Cabinetry and
    obtained an assignment of its lien for $4,376.
    As to each of those liens filed against Kent’s property for amounts not paid
    by KBA to those subcontractors, and contrary to the representations made by
    Alexander in the payment applications, Kent testified:
    Q. All right. And each one of these pay applications, after you
    had the opportunity to do what review you could, you paid him; is
    that correct?
    A. Yes, sir.
    Q. And as a result of the pay applications not being -- or all of
    the subcontractors not being paid, you have heard testimony, you’ve
    heard that -- you’ve settled with several people; is that correct?
    A. Yes, sir.
    Q. Okay. And who did you settle with, sir?
    A. I settled with Mr. Moses of Ajax Glass, and Mr. Eberly [of
    Jerry’s Cabinetry], and Jeff Bennett . . . [of] . . . Business Flooring
    Special[ists], [which] were the three that there’s cashier’s checks in
    the exhibits where they were all paid, and they all assigned me the
    lien.
    Even though the cashier’s checks themselves were not admitted (the trial
    court sustained Alexander’s hearsay objection to them), Kent testified to the
    amounts he paid to each of those three subcontractors to settle with them and
    obtain assignments of their liens against his property, which totaled precisely the
    amount of damages awarded to him of $20,061.32, as the trial court found.
    Alexander did not dispute that Kent settled with the three subcontractors for that
    46
    amount. Accordingly, we hold that legally sufficient evidence supports the trial
    court’s findings that Kent incurred damages of $20,061.32 as a result of his
    reliance on Alexander’s misrepresentations.         We overrule the remainder of
    Alexander’s first issue.
    By his seventh issue, Alexander contends that the evidence is factually
    insufficient to support the damages of $20,061.32 that the trial court found were
    sustained by Kent and awarded to him in the judgment against Alexander. It is
    undisputed and Alexander acknowledges that Kent testified that he settled with
    the three subcontractors who had filed liens on his property by paying them the
    following sums in exchange for an assignment of their liens: $6,271.67 paid to
    Business Flooring Specialists; $9,413.65 paid to Ajax Glass; and $4,376 paid to
    Jerry’s Cabinetry, for a total as found by the trial court of $20,061.32.
    Alexander contends that Kent admitted that he did not pay the last pay
    application presented to him by KBA of $6,637. Alexander contends that when
    that amount is subtracted from the total amount of $20,061.32 paid to the
    subcontractors, Kent’s damages total no more than $13,424.32.               But Kent
    testified that he paid the contract in full. His last payment to KBA supported by a
    pay application from KBA was $38,210. We have found no pay application in the
    record for $6,637.     KBA did file a lien in 2009 on Kent’s property with an
    unsigned application for payment (dated July 5, 2007) for a balance Alexander
    claimed Kent still owed of $4,637, plus eighteen percent interest. But Alexander
    47
    acknowledged he did not recall such an application for payment ever being
    presented to Kent.
    The amount of any such balance owed on the contract by Kent, assuming
    such to be true, is apparently intended by Alexander to be in the nature of an
    offset. But Alexander is not entitled to an offset in the amount he now claims.
    Any such amount owed by Kent on the contract would have been owed only to
    KBA, the corporation with whom Kent contracted for the construction and which
    he agreed to pay, not to Alexander, individually. This suit is against Alexander,
    individually, for the damages to Kent resulting from Alexander’s fraud.
    Moreover, Alexander is making this claim for the first time on appeal. The
    right of offset, setoff, or reimbursement is an affirmative defense that must be
    pled and proved by the party asserting it. See Smith v. Davis, 
    462 S.W.3d 604
    ,
    614 (Tex. App.—Tyler 2015, pet. denied) (op. on reh’g); Tenet Health Sys.
    Hosps. Dallas, Inc. v. N. Tex. Hosp. Physicians Grp., P.A., 
    438 S.W.3d 190
    , 204
    (Tex. App.—Dallas 2014, no pet.) (citing Brown v. Am. Transfer & Storage Co.,
    
    601 S.W.2d 931
    , 936 (Tex. 1980)). Generally, an affirmative defense must be
    pled in a responsive pleading, or the defense is waived. See Tex. R. Civ. P. 94;
    MAN Engines & Components, Inc. v. Shows, 
    434 S.W.3d 132
    , 136–37 (Tex.
    2014) (stating Rule 94 makes clear that affirmative defenses must be raised in
    pretrial pleadings); Shoemake v. Fogel, Ltd., 
    826 S.W.2d 933
    , 937 (Tex. 1992)
    (stating affirmative defense waived if not pled). Alexander filed only a general
    denial in response to Kent’s original petition and never amended his answer to
    48
    assert offset or any other affirmative defense or counterclaim for the amount he
    now claims Kent owes. There is also no indication in the record that the parties
    tried such a claim for an offset by consent. See 
    Smith, 462 S.W.3d at 614
    ; see
    also Hartford Fire Ins. Co. v. C. Springs 300, Ltd., 
    287 S.W.3d 771
    , 779–80 (Tex.
    App.—Houston [1st Dist.] 2009, pet. denied) (noting trial by consent is reserved
    for exceptional cases, and we review the record not for admission of relevant
    evidence on the issue, but rather for evidence of trial of the issue).
    Because Alexander is not entitled to assert any balance owed on the
    contract to KBA as an offset to the damages awarded against him individually for
    fraud and because any such right to an offset is waived because it was never
    pled or tried by consent, we overrule Alexander’s seventh issue.
    49
    CONCLUSION
    Having sustained Alexander’s sixth issue complaining that Kent is not
    entitled to attorney’s fees for this suit or to special bankruptcy fees, we reverse
    the trial court’s judgment as to those fees in the total amount of $25,249.97 and
    render judgment that Kent take nothing on his claim for attorney’s fees. Having
    overruled Alexander’s first through fifth issues and his seventh issue, we affirm
    the judgment in favor of Kent and against Alexander for damages in the amount
    of $20,061.32, plus prejudgment and postjudgment interest and costs of court as
    awarded by the trial court.
    /s/ Anne Gardner
    ANNE GARDNER
    JUSTICE
    PANEL: DAUPHINOT, GARDNER, and WALKER, JJ.
    DELIVERED: November 5, 2015
    50
    

Document Info

Docket Number: 02-13-00469-CV

Citation Numbers: 480 S.W.3d 676, 2015 Tex. App. LEXIS 11521

Judges: Dauphinot, Gardner, Walker

Filed Date: 11/5/2015

Precedential Status: Precedential

Modified Date: 11/14/2024

Authorities (28)

Means v. State , 100 Tex. Crim. 1 ( 1925 )

Miller v. Keyser , 46 Tex. Sup. Ct. J. 178 ( 2002 )

Morris v. Kohls-York , 2005 Tex. App. LEXIS 3404 ( 2005 )

Gore v. Scotland Golf, Inc. , 136 S.W.3d 26 ( 2003 )

Karl and Kelly Company, Inc. v. McLerran , 26 Tex. Sup. Ct. J. 232 ( 1983 )

Paull v. Capital Resource Management, Inc. , 987 S.W.2d 214 ( 1999 )

Kingston v. Helm , 82 S.W.3d 755 ( 2002 )

Sanchez v. Mulvaney , 274 S.W.3d 708 ( 2008 )

Rocor International, Inc. v. National Union Fire Insurance ... , 77 S.W.3d 253 ( 2002 )

Garza v. Alviar , 9 Tex. Sup. Ct. J. 76 ( 1965 )

Holloway v. Skinner , 898 S.W.2d 793 ( 1995 )

Shapolsky v. Brewton , 56 S.W.3d 120 ( 2001 )

Calyon v. State , 76 Tex. Crim. 83 ( 1915 )

Leyendecker & Associates, Inc. v. Wechter , 28 Tex. Sup. Ct. J. 131 ( 1984 )

Cain v. Bain , 29 Tex. Sup. Ct. J. 214 ( 1986 )

Pool v. Ford Motor Co. , 29 Tex. Sup. Ct. J. 301 ( 1986 )

Formosa Plastics Corp. USA v. Presidio Engineers and ... , 960 S.W.2d 41 ( 1998 )

Catalina v. Blasdel , 881 S.W.2d 295 ( 1994 )

DeSantis v. Wackenhut Corp. , 33 Tex. Sup. Ct. J. 517 ( 1990 )

Shoemake v. Fogel, Ltd. , 826 S.W.2d 933 ( 1992 )

View All Authorities »