Park Plaza Solo, LLC v. Benchmark-Hereford, Inc. ( 2016 )


Menu:
  •                                    In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-16-00004-CV
    PARK PLAZA SOLO, LLC, APPELLANT
    V.
    BENCHMARK-HEREFORD, INC., APPELLEE
    On Appeal from the 222nd District Court
    Deaf Smith County, Texas
    Trial Court No. CI-2013C-54, Honorable Roland D. Saul, Presiding
    October 24, 2016
    MEMORANDUM OPINION
    Before QUINN, C.J., and CAMPBELL and HANCOCK, JJ.
    Park Plaza Solo, LLC, (Park) appeals from a judgment entered in favor of
    Benchmark-Hereford, Inc. (Benchmark). The latter sued Park for duress and breach of
    contract. The claims arose from a lease relationship between the two. Benchmark had
    leased a portion of a building from Park in which to open a Sears store. The leased
    area had to be portioned from the non-leased area via the construction of a wall. Other
    construction had to occur as well, such as the installation of a front door and electrical
    wiring. The obligations to perform those various projects were apportioned among the
    parties.   Eventually, Benchmark would complain about Park’s performance of its
    promises, Park’s interference with Benchmark’s performance of its own tasks, and of
    Park’s alleged effort to wrongfully saddle Benchmark with the duty to pay certain
    electrical utility charges. These complaints made the basis for Benchmark’s suit along
    with claims of breached contract and duress.
    The cause was tried to a jury which entered findings favorable to Benchmark.
    Judgment was then entered on those findings, and Park appealed.
    Through four issues, Park contends that 1) the evidence is legally and factually
    insufficient to support the jury’s answers to the questions posed in the charge, 2)
    question 3 of the charge required the jury to answer a question of law, 3) questions 2, 4
    and 5 were rendered immaterial because of “Benchmark’s failure to obtain effective
    liability finding,” and 4) the trial court erroneously awarded post judgment interest. We
    reverse.
    Issue One
    Park initially attacks the legal and factual sufficiency underlying the answer of
    “yes” to the first question submitted to the jury. Via that question, the jury was asked:
    “Do you find that BENCHMARK . . . payed utility charges under duress caused by
    PARK . . . in threatening an unlawful action to-wit eviction for nonpayment of utility
    charges.” We sustain the issue.
    Evidence is legally insufficient to support a verdict when 1) evidence of a vital
    fact is completely absent; 2) the court is barred by rules of law or of evidence from
    giving weight to the only evidence offered to prove a vital fact; 3) the evidence offered to
    prove a vital fact is no more than a mere scintilla; or 4) the evidence establishes
    2
    conclusively the opposite of the vital fact. Southwestern Energy Prod. Co. v. Berry-
    Helfand, 
    491 S.W.3d 699
    , 713 (Tex. 2016). In assessing whether the record before us
    falls within any of those four categories, we restrict our review to the evidence tending to
    support the jury’s verdict and disregard all other to the contrary, and construe that
    evidence and possible, rational inferences therefrom in the light most favorable to the
    verdict. BNSF Railway Co. v. Phillips, 
    485 S.W.3d 908
    , 910 (Tex. 2015). And, if in so
    considering the evidence, we conclude that it is sufficient to enable a reasonable and
    fair-minded juror to reach the verdict in question, then the evidence is legally sufficient
    to support that verdict. Seger v. Yorkshire Ins. Co., No. 13-0673, 2016 Tex. LEXIS 503,
    at *41 (Tex. June 17, 2016).
    In reviewing a factual sufficiency challenge, our task is a bit different. Under it,
    the jury finding may be negated only if, after considering and weighing all of the
    evidence in the record pertinent to that finding, we determine that the credible evidence
    supporting the finding is so weak, or so contrary to the overwhelming weight of all the
    evidence that a new trial be ordered. Crosstex N. Tex. Pipeline, L.P. v. Gardiner, No.
    15-0049, 2016 Tex. LEXIS 580, at *82-83 (Tex. June 24, 2016).
    Assuming arguendo that duress constitutes an independent cause of action, see
    Zouzalik v. Wells Fargo Bank, N.A., No. 07-08-00411-CV, 2010 Tex. App. LEXIS 3211,
    at *3-4 (Tex. App.—Amarillo April 29, 2010, no pet.) (mem. op.)(describing duress as a
    defense to the enforcement of a contract), its elements require proof of 1) a threat to do
    something a party has no legal right to do, 2) some illegal exaction or some fraud or
    deception, and 3) imminent restraint such as to destroy free agency without present
    means of protection. Id.; Meyer Farms, Inc. v. Texaco Producing Co., No. 07-98-0029-
    3
    CV, 1999 Tex. App. LEXIS 1640, at *11-12 (Tex. App.—Amarillo March 10, 1999, pet.
    denied)(op. on reh’g); see Dale v. Simon, 
    267 S.W. 467
    , 470 (Tex. Comm’n App. 1924,
    judgm’t adopted) (stating that there is no duress unless the threat is of such character
    as to destroy the free agency of the party to whom it is directed); Matthews v. Matthews,
    
    725 S.W.2d 275
    , 278 (Tex. App.—El Paso 1986, writ ref’d) (stating the same). Falling
    outside the scope of the third element, though, are situations where the demand is
    wrongful but the party making it must resort to the court to enforce it. Meyer Farms, Inc.
    v. Texaco Producing Co., 1999 Tex. App. LEXIS 1640, at *13-14. And, related to this
    principle is another that simply declares that a threat to institute a civil action or the
    actual initiation of such an action cannot constitute duress, as a matter of law.
    Continental Casualty Co. v. Huizar, 
    740 S.W.2d 429
    , 430 (Tex. 1987). Finally, whether
    or not circumstances of duress are established is generally a question of fact, but
    whether established facts constitute duress is a matter of law to be determined by the
    court. Sea Hoss Marine Enterprises, Inc. v. Angleton Bank of Commerce, 
    536 S.W.2d 592
    , 596 (Tex. Civ. App.—Houston [1st Dist.] 1976, writ ref’d n.r.e)
    With the foregoing in mind, we turn to the record at bar. The lease, which was
    executed in September of 2011, provided Park with the right to “terminate this lease as
    if the term had expired and exercise all right of entry and re-entry” should Benchmark
    materially breach provisions of the agreement.                 Furthermore, one such provision
    obligated Benchmark to pay its “portion of the utilities.”                 In view of its promise,
    Benchmark periodically received an invoice representing the portion of utilities due from
    it.1 At trial though, Benchmark’s representative said he “. . . was forced to pay it by
    1
    Benchmark alleged that Park had no right to demand payment because the promise to pay
    utilities was unenforceable due to § 93.012 of the Texas Property Code. Via that statute, a “landlord may
    4
    threat of eviction several times.” This evidence is undisputed. And in viewing it in a
    light most favorable to the jury’s verdict, what we see is a situation fundamentally
    distinct from a typical duress scenario.
    Normally, the promise or agreement sought to be avoided is exacted via a threat
    to do something the party issuing the threat had no legal right to do. The promise or
    agreement by Benchmark to pay its pro rata share of the utilities was made before or at
    the time it executed the lease.            Its agreement to accord Park the right to gain
    possession of the premises should a breach occur was also made before or at the time
    of the lease’s execution. Moreover, no evidence of record indicates that either the
    promise Benchmark sought to avoid (i.e. pay utilities) or its agreement to vest Park with
    the means of enforcing that promise (i.e. right to re-entry) were extracted by some
    preceding threat of any kind. Indeed, the evidence indicates that Benchmark had its
    own attorney draft a proposed lease, and in that proposal it had agreed to pay all the
    utilities attributable to the entire vacant space. Park amended the provision to reduce
    Benchmark’s liability merely to the utilities attributable to the limited space it intended to
    rent. No one proffered evidence of any threat compelling Benchmark to agree to Park’s
    proposal when the lease was ultimately signed. Nor did anyone proffer evidence or
    authority suggesting that a potential landlord lacks the legal right to negotiate with his
    prospective tenant to have the latter pay utilities. Simply put, Benchmark sought to
    avoid the contractual promise without showing that the promise was exacted by some
    not assess a charge, excluding a charge for rent or physical damage to the leased premises, to a tenant
    unless the amount of the charge or the method by which the charge is to be computed is stated in the
    lease, an exhibit or attachment that is part of the lease, or an amendment to the lease.” TEX. PROP. CODE
    ANN. § 93.012(a) (West 2014). Without attempting to explain if an agreement to pay utilities is a
    “charge,” Benchmark nonetheless concluded that § 93.012(a) prevented Park from enforcing the
    obligation since the amount of the “charge” or method by which it was to be computed was omitted from
    the lease.
    5
    threat from Park to do that which it had no right to do. Without such evidence there is
    no duress.
    To the extent that Benchmark suggested that application of § 93.012(a)
    somehow rendered Park’s effort to enforce Benchmark’s promise illegal, it failed to
    consider the effect of other provisions of the same statute. The provision in mind is
    § 93.012(b) which states that § 93.012 “does not affect a landlord’s right to assess a
    charge or obtain a remedy allowed under a statute or common law.” 
    Id. § 93.012(b).
    Again, we know of no law generally prohibiting a landlord from negotiating with its
    tenant to pay utilities incurred by the latter. And, given Benchmark’s promise to pay for
    utility services it used, Park was entitled to collect the value of those services under the
    common law theory of quantum meruit despite any purported failure to provide a
    formula in the lease by which the obligation to pay could be calculated. See Vortt
    Exploration Co. v. Chevron U.S.A., Inc., 
    787 S.W.2d 942
    , 944 (Tex. 1990) (stating that
    quantum meruit is an equitable remedy available when there is no express contract
    covering services or materials furnished and the person to be charged accepted those
    services or materials under circumstances which reasonably notified the person that
    payment was expected). It cannot be denied that Benchmark not only expected but
    also agreed to pay for the utility services provided by Park. So, it appears that § 93.012
    does not even apply to the scenario before us.
    Lastly, the mere threat of “eviction” poses its own complications. What was
    meant by the term is unknown because Benchmark failed to proffer evidence expanding
    upon its actual substance. In effect, the comment about why it eventually fulfilled its
    contractual promise and periodically paid utilities for about eighteen months was
    6
    conclusory. This is of import because an “eviction” may encompass a legal process
    initiated by the commencement of a lawsuit, see TEX. PROP. CODE ANN. § 24.0051
    (discussing the statutory remedy of forcible entry and detainer available to a landlord),
    and duress cannot arise from a threat to commence a lawsuit. Continental Caualty Co.
    v. 
    Huizar, supra
    .    So, merely saying that it was threatened with “eviction” without
    accompanying that utterance with evidence suggesting that the speaker meant
    something other than the commencement of a lawsuit is not enough to illustrate
    actionable duress.
    Issue Two
    Next, Park alleges that the jury’s answer to question two of the charge should be
    disregarded as immaterial. We agree and sustain the issue.
    Per the question, the jurors were asked to determine the amount of money that
    would fairly and reasonably compensate Benchmark for its damages caused by the
    aforementioned duress. Our having held that no evidence supported the finding of
    duress, it logically follows that Benchmark is not entitled to damages caused by that
    unproven wrong.
    Issue Three
    Next, Park contends that the jury’s answer to question three of the charge should
    be disregarded as immaterial and unsupported by the evidence.          We overrule the
    contentions.
    Our analysis begins with the allegation that the question was immaterial.
    According to Park, it was immaterial because it submitted a question of law and was
    fundamentally flawed. We disagree and agree in part.
    7
    Per question two, the jury was asked: “Did Defendant, Park . . . fail to comply
    with the Lease Agreement?”       The trial court followed its question with instructions.
    Aspects of those instructions told the jury that 1) “[i]t is your duty to interpret the
    following language of the agreement to determine if one of the parties failed to comply
    with the terms of the agreement: [left blank]”; 2) “[y]ou must decide its meaning by
    determining the intent of the parties at the time of the agreement;” and 3) “[c]onsider all
    the facts and circumstances surrounding the making of the agreement, the
    interpretation placed on the agreement by the parties, and the conduct of the parties.”
    No one disputed the interpretation of the lease, though. Nor did the trial court include
    within the aforementioned passages any reference to the particular language in the
    lease purportedly necessitating interpretation.      Furthermore, neither trial attorney
    informed the trial court of either circumstance or otherwise objected to that part of the
    charge before the trial court read the instrument to the jury. In remaining silent, we
    assume that Benchmark is correct in contending that Park waived any complaint about
    the inclusion of the verbiage in the overall instructions. See TEX. R. CIV. P. 274 (stating
    that a party objecting to a charge must point out the objectionable matter).
    Yet, Park still claims that the question remains subject to attack as immaterial,
    despite the absence of an objection to the jury charge. It is correct. A request to
    disregard a jury answer as immaterial need not be raised as an objection to the charge.
    Dallas v. Moreau, 
    718 S.W.2d 776
    , 779 (Tex. App.—Corpus Christi 1986, writ ref’d
    n.r.e.) (holding that the trial court should have granted the motion for judgment
    notwithstanding verdict because the jury questions were immaterial).           Indeed, logic
    suggests that the jury must first answer a question before one can ask that the answer
    8
    be disregarded. Furthermore, the complaint urged here was incorporated into a post-
    judgment motion of Park. So, it is a complaint that we can address.2
    As support for the basis of the complaint, Park asserts that the trial court asked
    the jurors to decide a question of law and such questions are not within the bailiwick of
    a jury. Being an answer to a question of law, the finding may be ignored as immaterial,
    it concludes. We agree with the proposition that questions of law submitted to the jury
    are immaterial and that answers thereto may be disregarded. Quick v. City of Austin, 
    7 S.W.3d 109
    , 116 (Tex. 1999); accord, Rancho La Valencia, Inc. v. Aquaplex, Inc., 
    297 S.W.3d 781
    , 783 (Tex. App.—Amarillo 2008), aff’d in part, rev’d in part on other
    grounds, Aquaplex, Inc. v. Rancho La Valencia, Inc., 
    297 S.W.3d 768
    (Tex. 2009)
    (holding that because the interpretation of an unambiguous contract is a question of
    law, the jury’s finding on a question asking it to interpret the contract may be ignored as
    immaterial). Yet, as previously indicated, that specific question is not the source of
    Park’s complaint. Instead, its focus lies on an instruction submitted in conjunction with
    the question and that directed the jurors to interpret the contract when deciding if a
    breach occurred.
    Since no one contended that the contract was ambiguous, the trial court arguably
    directed the jury to address a question of law when told to “interpret” the unambiguous
    agreement. Rancho La Valencia, Inc. v. Aquaplex, 
    Inc., 297 S.W.3d at 783
    . And, by
    applying Quick, the jury’s effort, if any, to do that (i.e. determine what the provisions of
    the contract meant) can be ignored as immaterial. Yet, that does not mean we can or
    must ignore the answer to the actual question posed (i.e. “[d]id . . . Park . . . fail to
    2
    In so concluding, we do not address whether a like complaint may be raised on appeal for the
    first time without initially asking the trial court to consider the matter.
    9
    comply with the Lease Agreement?”).         There was a factual dispute regarding its
    performance of various obligations imposed by the lease, such as its completion of a
    wall by installing insulation. And, while asking whether a party “breached a contract” or
    “failed to comply with an agreement” may be a question of law in some circumstances,
    see Lafarge Corp. v. Wolff, Inc., 
    977 S.W.2d 181
    , 186 (Tex. App.—Austin 1998, pet.
    denied) (comparing a question asking if the “. . . Corporation fail[ed] to comply with the
    contract” to a question asking if the corporation breached the contract and holding that
    the submission of a “breach of contract” issue improperly requires the jury to determine
    a question of law), it is not when the facts underlying the purported breach are disputed.
    Grohman v. Kahlig, 
    318 S.W.3d 882
    , 887 (Tex. 2010) (stating that “[w]hether a party
    has breached a contract is a question of law for the court, not a question of fact for the
    jury, when the facts of the parties’ conduct are undisputed or conclusively established.”).
    So, the jury’s answer to the actual question cannot be deemed immaterial due to it
    purportedly involving a question of law.
    Having rejected the materiality argument, we now turn to the second prong of
    Park’s contention. Through it, the corporation asserts that “[t]here is neither legally nor
    factually sufficient evidence to support a finding that [Park] materially failed to comply
    with any provision of the Lease Agreement.”        This is allegedly so since “[t]he only
    ‘breach of contract’ that Benchmark alleged [in its live pleading] was in its ‘Count 1 –
    Breach of Contract – Breach of Express Warranty Quit (sic) Enjoyment Access,’” and
    there was no evidence establishing each element of a breach of express warranty of
    quiet enjoyment. We disagree.
    10
    Benchmark’s live pleading (i.e. its second amended petition) may be inartfully
    drawn. Nevertheless, within its “Count 1 - Breach of Contract - Breach of Express
    Warranty to Quit [sic] Enjoyment Access,” it alleged that 1) “Defendant refused to
    insulate the partition wall” as was its “responsibility,” and 2) “Defendant was responsible
    for electrical wiring to Sears’ requirements” and “[a]s a result of Sears’ requirements,
    TBar Electrical, Inc. installed electrical wiring and charged the bill to [Benchmark].”
    Furthermore, those allegations must be liberally construed, due to the absence of any
    special exceptions filed by Park. See Prudential Ins. Co. of Am. v. Financial Review
    Servs., Inc., 
    29 S.W.3d 74
    , 81 (Tex. 2000) (stating that “[a]bsent special exceptions, we
    construe a petition liberally in favor of the pleader.”).   And, in so construing them, we
    conclude that they accuse Park of breaching the lease because it did not build a
    partition wall and wire the facility as promised. So, Benchmark alleged more than just a
    claim of breached warranty of quiet enjoyment. Furthermore, Park did not explain why
    the two claims falling outside the warranty allegation were not supported by either
    legally or factually sufficient evidence.
    However, we do agree with the allegation that no evidence established a breach
    of warranty to quiet enjoyment of the leased premises. The elements of such a cause
    of action are the same as those applicable to a claim of constructive eviction. 1221
    Eldridge Rd., Inc. v. Life Changing Ministries & Fellowship, Inc., No. 01-14-00893-CV,
    2016 Tex. App. LEXIS 598, at *23-24 (Tex. App.—Houston [1st Dist.] January 21, 2016,
    pet. denied) (mem. op.).       Among other things, each requires proof that the act
    complained of “permanently deprived” the tenant of the use and enjoyment of the
    premises. 
    Id. Nothing in
    the record here discloses that Benchmark either abandoned
    11
    the premises or was permanently deprived of its use and enjoyment. On the contrary,
    Benchmark remained at the locale and opened its Sears store after Park committed the
    acts about which Benchmark complained. Thus, one element of the cause of action
    went unproven, and any finding that the alleged warranty of quiet enjoyment was
    breached lacks all evidentiary support.
    Issue Four
    Via Question 4 of the charge, the trial court asked the jury:                    “[w]hat sum of
    money, if any paid now in cash, would fairly and reasonably compensate
    Benchmark . . . for its damages, if any that resulted from such failure to comply” with the
    lease agreement?         It answered the question with the sum of “$24,276.20.”3                      This
    response does not support the judgment, according to Park, because it lacked legally or
    factually sufficient evidentiary support. We agree.
    Though various damages were sought by Benchmark, all the litigants seem to
    agree that the only ones awarded by the jury were for the purported breaches relating to
    the installation of electrical wiring, the wiring of an outdoor sign, and the failure to
    insulate the partition wall.4        Indeed, based upon the damage figures submitted by
    Benchmark related to those acts, the injury it allegedly suffered equaled $24,276. Thus,
    we determine whether that award has the support of legally or factually sufficient
    evidence by looking at the three components mentioned.
    Section 11 of the written lease manifested the contractual obligation underlying
    the damages awarded at bar. It provided that:
    3
    The jury did not specify the components of the award, even though the trial court instructed it to
    “[a]nswer separately in dollars and cents for damages, if any.”
    4
    Benchmark indicated as much in its response to post-judgment motions filed by Park and the
    tenor of its appellee’s brief. Only the three components were discussed by Benchmark in its brief.
    12
    This space is to be built out to conform to the requirements of Sears. The width is
    to be a minimum of 60 feet and the depth is to be a minimum of 125 feet.
    Landlord’s responsibility is the partition wall, the back wall, electrical wiring to
    Sears’ requirements, a small office, and painting the walls and ceiling to Sears’
    requirements. The Tenant is responsible for all other improvements required by
    Sears.
    In reading that provision of the lease, we construe Park’s “responsibility” to be
    akin to the obligation of a contractor to complete a construction project. Simply put, the
    lessor agreed to perform various construction and installation tasks which would enable
    Benchmark to use the facility. Consequently, the damages available to Benchmark
    should Park fail to fulfill its responsibilities would be measured in the same way
    damages are measured for breach of a construction contract. And, as described in
    McGinty v. Hennen, 
    372 S.W.3d 625
    (Tex. 2012), such damages can be calculated in
    two ways. Under one, the difference-in-value comprises the available damages; that is,
    the complainant is entitled to receive the difference between the value of the building as
    constructed and its value had it been constructed according to the agreement. 
    Id. at 627.
    Under the other, injury is determined by the cost to complete or repair the project
    less the unpaid balance on the contract. 
    Id. This mode
    of recovery is known as the
    remedial damges, and if used, the party seeking the award must prove that the
    damages sought were reasonable and necessary. 
    Id. One satisfies
    that aspect of the
    test by doing more than simply proffering evidence of “‘the nature of the injuries, the
    character of and need for the services rendered, and the amounts charged therefor.’”
    
    Id., quoting, Dallas
    Ry. & Terminal Co. v. Gossett, 
    156 Tex. 252
    , 
    294 S.W.2d 377
    , 383
    (Tex. 1956). In other words, evidence of “put-of-pocket costs alone” do not establish
    13
    that the damages were reasonable and necessary. 
    Id., quoting Mustang
    Pipeline Co. v.
    Driver Pipeline Co., 
    134 S.W.3d 195
    , 200 (Tex. 2004). According to McGinty, “. . .
    ‘proof of the amounts charged or paid does not raise an issue of reasonableness, and
    recovery of such expenses will be denied in the absence of evidence showing that the
    charges are reasonable.’” Other evidence showing that the charges were reasonable is
    needed. 
    Id., quoting, Dallas
    Ry. & Terminal Co. v. 
    Gossett, supra
    .
    Furthermore, the claimant also has the burden to establish that the damages
    sought were caused by the contractual breach in dispute. One does this by proffering
    evidence illustrating that the breached promise was a substantial factor in causing the
    damages sought. Tamimi Global Co. v. Kellogg Brown & Root, L.L.C., 
    483 S.W.3d 678
    ,
    704-705 (Tex. App.—Houston [14th Dist.] 2015, no pet.).
    The first component of the damage award we address relates to “electrical
    wiring.”    As seen from the lease excerpt quoted above, Park assumed the
    “responsibility” to install “electrical wiring to Sears’ requirements.” Defense Exhibit 1
    disclosed those requirements. Furthermore, TBar Electrical was first hired by Park to
    perform the requisite task. But once Park ended that relationship, Benchmark retained
    TBar to finish the effort.
    The charges sought by TBar once the work was completed are reflected in
    Plaintiff’s Exhibit 7, and it is those charges that Benchmark attempted to recover from
    Park. So, it appears that the damages sought from Park and arising from the failure to
    complete its “electrical wiring” responsibility fall under the remedial damages discussed
    in McGinty.    That is, Benchmark was attempting to recover from Park the cost of
    14
    completing the project.   And, to support that recovery, the following evidence was
    tendered of record.
    Again, we have Plaintiff’s Exhibit 7.      It consisted of a letter TBar sent to
    Benchmark stating: “Just a reminder that you have 1 overdue invoice, with an overdue
    balance of $10,566.55. Also, since building owner (William Home) has chosen not to
    pay invoices for initial electrical work @ this building requested as a result of Sears
    leasing building. I feel that Benchmark should pay these invoices totaling $11,902.31.
    Which [sic] makes a total balance owed of $22,468.86 that is long overdue.”          The
    invoices alluded to in the letter were not admitted into evidence, though. Nor did the
    letter itemize the particular work performed or materials provided by TBar.
    So too do we have the testimony of TBar’s representative that: 1) the corporation
    was involved in “doing the electrical work as per Sears”; 2) TBar gave no quote or price
    for the work it was to do; 3) TBar’s charges would be based on “[h]ow much time and
    whatever is used”; 4) TBar was told that Sears and Benchmark were to approve the
    work; 5) Sears and Benchmark had the specifications; 6) “we were doing it as per what
    they wanted”; 7) TBar “commenced working along those lines”; 7) Park directed TBar to
    stop; 8) when told to stop by Park, TBar had “a bill at that time of what was owed” by
    Park; 9) “[a]ll the invoices at that time that he [Park] owed are $11,902.31”; 10) “Sears
    or . . . Benchmark, wanted us to finish—go ahead and finish it so he [Benchmark] could
    open up”; 11) TBar continued to work “along the Sears specifications”; 12) Plaintiff’s
    Exhibit 7 “reflect[ed] the total bill”; 13) “all that electrical wiring was under Sears’
    specifications”; 14) Defense Exhibit 1 was what “they had laying down there on the
    table”; 15) a purported representative from Sears was present telling TBar what to do;
    15
    16) TBar “performed all the work set out in [its] bill”; 17) TBar ran conduit for the air
    conditioning; and 18) the witness did not know if Sears was requiring TBar to rewire
    existing systems though Benchmark apparently required it.
    Missing from the record is evidence comparing what TBar did to the written
    specifications sent to Park from Sears and expressed in Defense Exhibit 1. Missing is
    evidence that what the Sears representative and Benchmark told TBar to do was
    nothing more than what was encompassed by the actual specifications sent by Sears.
    Missing is any evidence indicating the amount of time spent in doing any of the work
    demanded by Benchmark and the Sears’ representative. Missing is evidence of the
    particular materials installed by TBar. Missing is evidence of the hourly or daily or
    weekly or monthly charge levied by TBar for its work. Missing is evidence that TBars’
    hourly or daily or weekly or monthly charge for the work done was reasonable. Missing
    is evidence of the actual materials installed by TBar. Missing is evidence of the costs of
    those materials and whether those costs were reasonable. Missing is evidence of the
    extent that existing systems were rewired as demanded by Benchmark but not
    necessarily Sears.   Missing is evidence that the work done and materials provided
    specifically related to “electrical wiring,” as opposed to some general “electrical work.”
    The absence of the latter evidence is of particular import since Park’s responsibility
    encompassed only “electrical wiring,” not electrical work in general.
    All we have here is evidence of Benchmark’s effort to collect from Park the
    charges purportedly incurred by TBar for doing some unknown quantum of “electrical
    work.” Furthermore, that unexplained work was done at the direction of a purported
    Sears’ representative who did not testify and Benchmark.          Whether the work and
    16
    charges related thereto were reasonable and necessary is unknown.          Whether the
    materials and charges related thereto were reasonable and necessary is unknown.
    Whether the work and materials included only that encompassed in the specifications or
    requirements sent by Sears to Park is unknown, and it was the “electrical wiring” per the
    requirements of Sears that Park agreed to perform.
    The situation before us is no different than that addressed in McGinty where the
    party seeking damages merely proffers evidence of his out-of-pocket costs or charges
    incurred or to be paid. That is not enough to satisfy the need to prove the damages
    sought were reasonable and necessary. And, without knowing the specifics about what
    was done or installed by TBar and the charges attached to those efforts, we cannot
    begin to assess the reasonableness of its charges even if we could do so without expert
    testimony from someone knowledgeable in the field of construction.
    It is not enough for Benchmark to fill the void by arguing that “[a]ll damages
    sought are from an agreement between Park . . . and TBar” for the averment ignores
    the mandate of McGinty.      And, Benchmark cites us to nothing that suggests Park
    agreed to pay TBar’s charges irrespective of whether they were reasonable or
    necessary.
    In short, without evidence that the electrical work done by TBar was reasonable
    and necessary, Benchmark failed to present evidence establishing a prerequisite to an
    award of damages. Simply offering evidence of the amount charged by TBar was not
    enough.      McGinty v. 
    Hennen, supra
    .     Consequently, we agree that no evidence
    supports the award of $22,468.86 as damages due to Park’s breach of its “electrical
    wiring” responsibility.
    17
    The second component of the damage award involves the outdoor sign, and it
    comprised $1,309.50 of the $24,276.20 sum. Benchmark concedes that Park’s sole
    obligation encompassed the provision of electrical wiring to the sign. And, to illustrate
    the damage suffered due to Park’s failure to provide such wiring, Benchmark offered
    into evidence a bill from the entity (Wellborn Sign Company) hired to complete the task.
    While that bill actually described the time expended and materials used to do the job, no
    one testified or proffered evidence to illustrate that the charges were reasonable or
    necessary. So, again, Benchmark was utilizing the remedial damages calculation to
    gauge its damages, and, again, it failed to prove the expenses or damages sought were
    reasonable and necessary. As said in McGinty, “recovery of such expenses will be
    denied in the absence of evidence showing that the charges are reasonable.” McGinty
    v. 
    Hennen, supra
    .
    The third component of the damage award related to the insulation of the
    partition wall. Whether the responsibility assumed by Park included the insulation of the
    partition wall we need not address at this time.5 Instead, we focus on the damages
    sought from Benchmark arising from that purported breach. Benchmark attempted to
    prove them by tendering into evidence Plaintiff’s Exhibit 4. It represented an invoice
    from a local business describing the amount of insulation acquired by Benchmark and
    the price therefor. Nothing was said about whether the charges or quantities reflected
    in the document were reasonable or necessary. Being that this evidence also evinces
    an attempt to recover damages via the remedial damages measurement, Benchmark
    was obligated to address the reasonability and necessity of the expense. It did not, so
    the expense was not recoverable due to the absence of requisite evidence.
    5
    The lease said nothing about insulating the wall.
    18
    In sum, there is legally insufficient evidence to support each component of
    damage encompassed in the $24,276.20 award. So, we sustain this particular issue of
    Park.
    Issue Four—Attorney’s Fees
    Next, Park attacks the award of attorney’s fees to Benchmark. It believes that
    the fees were not recoverable because Benchmark failed to obtain an effective liability
    finding. We sustain the issue.
    Benchmark sought fees under chapter 38 of the Texas Civil Practice and
    Remedies Code. To obtain the relief provided by that statute, “a litigant must prevail on
    a breach of contract claim and recover damages.” Ashford Partners, Ltd. v. ECO Res.,
    Inc. 
    401 S.W.3d 35
    , 40-41 (Tex. 2012). Our having found that Benchmark failed to
    prove itself entitled to the damages awarded by the jury, it also failed to satisfy the
    second prong of Ashford. It did not recover damages. So, attorney’s fees could not be
    awarded to Benchmark under chapter 38 of the Civil Practice and Remedies Code.
    Issue Five—Interest
    The last contention involves the calculation of post-judgment interest. We need
    not consider it given the manner in which we resolved the other issues raised by Park.
    Accordingly, we reverse the judgment awarding damages to Benchmark and
    render judgment denying Benchmark recovery against Park.
    Brian Quinn
    Chief Justice
    19