northwest-construction-company-inc-v-the-oak-partners-lp-morgan ( 2008 )


Menu:
  •                   COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 2-07-293-CV
    NORTHWEST CONSTRUCTION                           APPELLANT
    COMPANY, INC.
    V.
    THE OAK PARTNERS, L.P.,                          APPELLEES
    MORGAN DEVELOPMENT
    AND SUPPLY, INC.,
    METROPLEX MASONRY, INC.,
    ARI-TEX, INC., MAX PLUMBING
    CONTRACTORS, INC.,
    S & S TILE, LTD., AND
    KENT-ANDERSON CONCRETE, L.P.
    D/B/A ANDERSON CONCRETE
    CONSTRUCTION
    ------------
    FROM THE 355TH DISTRICT COURT OF HOOD COUNTY
    ------------
    AND
    NO. 2-07-328-CV
    IN RE NORTHWEST                                                        RELATOR
    CONSTRUCTION COMPANY, INC.
    ------------
    ORIGINAL PROCEEDING
    ------------
    OPINION
    ------------
    This consolidated mandamus proceeding and interlocutory appeal arise
    from the trial court’s order denying relator and appellant Northwest
    Construction Company, Inc.’s motion to compel arbitration in the underlying
    suit involving construction of an assisted living center in Granbury, Texas. In
    both the appeal and mandamus proceeding, Northwest raises the following four
    issues: (1) whether there is a valid arbitration clause binding the parties that
    encompasses the dispute; (2) whether the trial court had jurisdiction to
    determine if Northwest waived its right to arbitrate the dispute; (3) whether the
    trial court erred by ruling that Northwest waived its right to arbitrate by
    substantially invoking the judicial process to the detriment of the other parties;
    and (4) whether appellees have waived their right to rely on mediation as a
    2
    condition precedent to the enforceability of the arbitration clause. We affirm
    the trial court’s order in part and reverse it in part.       We also dismiss
    Northwest’s petition for writ of mandamus.
    Background Facts
    On April 27, 2004, Northwest entered into a construction contract with
    The Oak Partners, L.P., an appellee and real party in interest, to design and
    construct an assisted living facility in Granbury, Texas. The contract referenced
    the facility to be constructed as “more particularly described in the design
    development plans and specifications and design criteria identified in Exhibit B”
    attached to the contract.      Exhibit B, in turn, provided that the project
    specifications were the “Project Manual for The Courtyards at Lake Granbury,
    Granbury, Texas, prepared by GSR Andrade Architects dated April 16, 2004.”
    The April 16, 2004 Project Manual included a provision incorporating into it
    “[t]he ‘General Conditions of the Contract for Construction’, AIA Document
    A201, Fourteenth Edition, 1997, Articles 1 through 14 inclusive.”        A new
    Project Manual dated May 28, 2004 contained the same language.
    AIA Document A201-1997 contains an arbitration clause, which reads as
    follows, in pertinent part:
    Claims not resolved by mediation shall be decided by arbitration
    which, unless the parties mutually agree otherwise, shall be in
    accordance with the Construction Industry Arbitration Rules of the
    3
    American Arbitration Association currently in effect. The demand
    for arbitration shall be filed in writing with the other party to the
    Contract and with the American Arbitration Association, and a copy
    shall be filed with the Architect.
    The term “Claim” is defined as
    a demand or assertion by one of the parties seeking, as a matter of
    right, adjustment or interpretation of Contract terms, payment of
    money, extension of time or other relief with respect to the terms
    of the Contract. The term “Claim” also includes other disputes and
    matters in question between the Owner and Contractor arising out
    of or relating to the Contract.
    After entering into the contract with Oak Partners, Northwest entered into
    subcontractor agreements with S & S Tile, Ltd., Morgan Development and
    Supply, Inc., Metroplex Masonry, Inc., Ari-Tex, Inc., Kent-Anderson Concrete
    L.P. d/b/a Anderson Concrete Construction, and Max Plumbing Contractors, Inc.
    Each of the subcontract agreements contained the following provisions:
    The terms of the dispute resolution and claims procedure contained
    in the General Contract shall be binding upon Subcontractor,
    whether or not Subcontractor records or files a mechanic’s lien,
    stop notice or prosecutes suit thereon or against any bond posted
    by Contractor; and Subcontractor hereby acknowledges that this
    Subcontract waives, affects, and impairs rights it would otherwise
    have in connection with such liens, stop notices and suits on said
    bonds.
    ....
    Any disputes or controversies not resolved or settled by the parties
    under the previous provisions shall be submitted to binding
    arbitration in accordance with the Construction Industry Rules of
    the American Arbitration Association and any judgment upon the
    4
    award by the arbitrators may be entered by any court having
    jurisdiction. The venue for any hearing under this arbitration
    provision shall be in Dallas County, Texas.
    After Northwest constructed the facility, Oak Partners sued Northwest
    on August 30, 2005, in the 355th District Court of Hood County, alleging that
    Northwest had breached the contract; Oak Partners claimed that the facility had
    failed to pass inspections by the Texas Department of Aging and Disability
    Services because certain parts of the design and construction were not in
    accordance with the Department’s applicable rules and regulations. Northwest
    filed its original answer in the suit on December 12, 2005.
    S & S Tile and Max Plumbing sued Oak Partners and Northwest in
    separate suits in the 355th District Court, claiming they were owed money on
    the project. On January 11, 2006, Northwest filed a motion to consolidate the
    Max Plumbing and Oak Partners cases. The trial court granted the motion the
    next day and consolidated the cases. On January 19, 2006, Northwest filed
    a motion to consolidate the S & S Tile case with the two consolidated cases.
    Before the trial court ruled on the motion to consolidate, S & S Tile filed a
    motion for summary judgment. While that motion was pending, the trial court
    granted Northwest’s motion to consolidate the S & S Tile case with the other
    two cases on February 2, 2006.
    5
    Northwest filed a counterclaim against Oak Partners on February 3, 2006,
    alleging that Oak Partners breached the contract by failing to pay for change
    orders, causing delays, and refusing to release retainage.      Northwest also
    brought causes of action for quantum meruit, promissory estoppel, and
    foreclosure of statutory and constitutional liens; a Prompt Payment Act claim;
    and a claim for attorneys’ fees.
    Northwest and Oak Partners filed responses to S & S Tile’s motion for
    summary judgment on March 10, 2006. The motion was set for a hearing on
    March 17, 2006, but S & S Tile and Northwest entered into a rule 11
    agreement to remove the motion from the court’s docket.1 The motion was
    never reset.
    On February 17, 2006, Kent-Anderson filed a separate suit against
    Northwest and Oak Partners, which the trial court consolidated with the other
    three cases upon Northwest’s motion. Oak Partners then filed a first amended
    petition adding GSR as an additional defendant and alleging causes of action for
    breach of contract and negligence. After the addition of GSR as a defendant,
    subcontractors Morgan Development and Supply, Inc., Metroplex Masonry, Inc.,
    and Ari-Tex, Inc. intervened in the suit.
    1
    The copy of the agreement in the record is signed only by counsel for
    S & S Tile and Northwest.
    6
    Northwest filed a motion for partial summary judgment on May 2, 2007.
    In it, Northwest sought a ruling that Oak Partners could not recover damages
    arising from design flaws or errors or omissions in the project design.
    Northwest asserted the affirmative defenses of estoppel, contractual bar,
    violation of the express negligence rule, and waiver.        Oak Partners filed a
    response on May 30, 2007.       GSR also filed a response and an affidavit in
    opposition to the motion.
    On     June   25, 2007, Northwest filed         a   First Amended   Original
    Counterclaim and Original Cross-Claim, re-alleging its claims against Oak
    Partners, adding declaratory and unjust enrichment claims, and alleging cross-
    claims against GSR and the subcontractors. On July 9, 2007, Northwest filed
    a “Motion to Compel Arbitration” and a “Motion for Leave to Designate
    Responsible Third Parties,” which it expressly made contingent upon the trial
    court’s denial of its motion to compel arbitration.
    The trial court denied Northwest’s motion to compel arbitration on the
    ground that Northwest had waived its right to arbitration by substantially
    invoking the judicial process to the detriment of all of the opposing parties in
    the case.2      Before this court, Oak Partners is the only party opposing
    2
    At trial, the only parties who opposed Northwest’s motion to compel
    arbitration were Oak Partners, Kent-Anderson, and Ari-Tex. Kent-Anderson has
    7
    Northwest’s request for arbitration. Accordingly, we will review whether the
    trial court properly denied Northwest’s motion to compel arbitration.
    This Court’s Jurisdiction
    To determine whether we have jurisdiction over the interlocutory appeal
    in addition to the mandamus petition, we must decide whether the trial court
    denied Northwest’s motion to compel pursuant to the Federal Arbitration Act
    (FAA), the Texas General Arbitration Act (TGAA), or both. See 9 U.S.C.A. §§
    1-16 (West 1999 & Supp. 2007); T EX. C IV. P RAC. & R EM. C ODE A NN. §§
    171.001-.098 (Vernon 2005); In re Citigroup Global Mkts., Inc., 
    202 S.W.3d 477
    , 480 (Tex. App.—Dallas 2006, orig. proceeding). In Texas, a trial court’s
    denial of arbitration under the FAA may be challenged only by mandamus and
    not by interlocutory appeal. In re D. Wilson Constr. Co., 
    196 S.W.3d 774
    , 779
    (Tex. 2006) (orig. proceeding); Jack B. Anglin Co. v. Tipps, 
    842 S.W.2d 266
    ,
    272 (Tex. 1992) (orig. proceeding).       But a party may seek to enforce an
    arbitration agreement under both the FAA and TGAA if, like the agreement
    here, it does not say whether the FAA or TGAA applies. D. Wilson Constr. 
    Co., 196 S.W.3d at 778-79
    .        Texas appellate courts have jurisdiction over
    indicated in both the appeal and mandamus proceeding that it no longer
    opposes arbitration, and Ari-Tex has not filed any documents in either cause in
    our court.
    8
    interlocutory appeals from the denial of arbitration under the TGAA only or
    under both the FAA and TGAA.          T EX. C IV. P RAC. & R EM. C ODE A NN. §
    171.098(a)(1); D. Wilson Constr. 
    Co., 196 S.W.3d at 778-79
    .
    Here, the agreement upon which Northwest relies does not purport to be
    governed by either the FAA or the TGAA. In its motion to compel, Northwest
    sought arbitration under both the FAA and TGAA. Oak Partners contends in its
    response to the petition for writ of mandamus that Northwest did not bring
    forward any evidence of interstate commerce showing that the agreement is
    enforceable under the FAA; thus, according to Oak Partners, enforceability of
    the agreement is governed by the TGAA only.
    The trial court’s order denying arbitration does not specify whether the
    denial was under the FAA or TGAA. Northwest filed both a petition for writ of
    mandamus and an interlocutory appeal in this court, contending that the
    agreement is enforceable under the TGAA as well as the FAA. Accordingly, we
    have jurisdiction over both the appeal and the mandamus unless the FAA
    pre-empts the TGAA in this instance. See 
    id. at 779-80.
    To determine whether an agreement that does not purport to be under
    either the FAA or TGAA is governed only by the FAA (i.e., whether the FAA
    pre-empts the TGAA), thus precluding an appellate court’s jurisdiction over an
    interlocutory appeal, we must determine whether (1) the agreement is in
    9
    writing, (2) it involves interstate commerce, (3) it can withstand scrutiny under
    traditional contract defenses, and (4) state law affects the enforceability of the
    agreement. 9 U.S.C.A. § 2; D. Wilson Constr. 
    Co., 196 S.W.3d at 780
    ; In re
    Nexion Health at Humble, Inc., 
    173 S.W.3d 67
    , 69 (Tex. 2005) (orig.
    proceeding). For the FAA to pre-empt the TGAA, state law must refuse to
    enforce an arbitration agreement that the FAA would enforce, either because
    (1) the TGAA has expressly exempted the agreement from coverage, or (2) the
    TGAA has imposed an enforceability requirement not found in the FAA. D.
    Wilson Constr. 
    Co., 196 S.W.3d at 780
    .       In other words, the FAA pre-empts
    only contrary state law, not consonant state law. 
    Id. at 779.
    We conclude that the FAA does not pre-empt the TGAA here. Northwest
    has not directed us to, nor have we found, any evidence of interstate
    commerce in the record. Likewise, Northwest did not direct the trial court to
    any such evidence.     Because this suit involves a construction project, it is
    possible that materials may have come from out of state, but Northwest has
    not directed us to anything in the record to support that conclusion, nor have
    we found any evidence in the record that would support such a conclusion.
    See, e.g., In re Nasr, 
    50 S.W.3d 23
    , 25-26 (Tex. App.—Beaumont 2001, orig.
    proceeding) (holding that construction contract involved interstate commerce
    because list of subcontractors in record included Wal-Mart).       We hold that
    10
    Northwest has failed to prove that the arbitration agreement involves interstate
    commerce; thus, the FAA does not pre-empt the TGAA in this instance, and we
    have jurisdiction over Northwest’s interlocutory appeal. For the same reason,
    we do not have jurisdiction to grant relief on Northwest’s petition for writ of
    mandamus. See In re D. Wilson Constr. 
    Co., 196 S.W.3d at 779
    . Because we
    have jurisdiction over the interlocutory appeal only, we will address Northwest’s
    issues within the context of that proceeding.
    Existence of Valid Arbitration Agreement
    In its first issue, Northwest contends that it proved the existence of a
    valid arbitration agreement and that all of the claims asserted against it in the
    underlying suit are within the scope of that agreement. Oak Partners responds
    that Northwest failed to prove that all claims were within the scope of a valid
    arbitration agreement because
    Northwest . . . did not present any evidence at the hearing on its
    Motion to Compel. The only documents presented were unsworn
    and unauthenticated exhibits to its Motion to Compel, and even
    those exhibits do not contain enough information to make an
    informed decision regarding whether the documents refer to each
    other or are all a part of the construction contract at issue in this
    case.
    In Jack B. Anglin Co. v. Tipps, the Texas Supreme Court held that “the
    trial court may summarily decide whether to compel arbitration on the basis of
    affidavits, pleadings, discovery, and stipulations”; the trial court is not required
    11
    to conduct an evidentiary hearing unless the “material facts necessary to
    determine the issue” are controverted. 
    842 S.W.2d 266
    , 269 (Tex. 1992).
    Northwest attached the contract, and the pertinent documents that were
    incorporated into it by reference, to its motion to compel. The trial court clearly
    reviewed these documents at the hearing on the motion to compel. 3 See T EX.
    R. E VID . 201; Barnard v. Barnard, 
    133 S.W.3d 782
    , 786 (Tex. App.—Fort
    Worth 2004, pet. denied) (“[T]he trial court may take judicial notice of its file
    at any stage of proceedings and is presumed to have done so with or without
    a request from a party.”). At the conclusion of the hearing, the trial court
    concluded, “Well, of course, it appears that there’s an arbitration provision here
    in this contract. The issue would certainly seem to be whether or not there has
    been a waiver.”
    We conclude that the trial court properly determined, based on the
    procedure promulgated in Tipps, that a valid arbitration existed and that the
    3
    For example, during a discussion between Northwest’s counsel and the
    trial court regarding the exhibits attached to the motion to compel, the
    following exchange occurred:
    THE COURT:         Where are you again?
    [NORTHWEST’S COUNSEL]: The very first page.
    THE COURT:         All right. I see it.
    12
    claims in the underlying suit were included within the scope of that agreement.4
    We sustain Northwest’s first issue; however, we must address its remaining
    issues relating to whether the trial court properly determined that it waived its
    right to arbitrate.
    Subject Matter Jurisdiction of Trial Court
    Northwest argues in its second issue that the trial court did not have
    subject matter jurisdiction to decide whether it waived its right to arbitration
    because, once a trial court decides that a dispute is subject to arbitration, the
    arbitrator must determine any defenses to arbitration raised by an opposing
    party, including waiver.
    In support of its contention, Northwest relies on Howsam v. Dean Witter
    Reynolds, Inc., 
    537 U.S. 79
    , 
    123 S. Ct. 588
    (2002). In that case, the United
    States Supreme Court held that “‘procedural’ questions which grow out of the
    dispute and bear on its final disposition’ are presumptively not for the judge, but
    4
    Oak Partners attached to its response to Northwest’s motion to compel
    an affidavit from Teresa Shook, a Director of Assisted Living Consultants, Inc.,
    which is a managing member of the general partner of Oak Partners. In her
    affidavit, Shook asserted that “Oak Partners did not agree to be bound by
    arbitration, and does not agree it is bound by arbitration.” But this conclusory
    statement, without more, does nothing to controvert the evidence of the
    agreement as attached to Northwest’s motion to compel. Moreover, Oak
    Partners never challenged the existence of an arbitration agreement in its
    response, which was premised solely on its contention that Northwest waived
    its right to arbitrate.
    13
    for an arbitrator, to decide. . . . So, too, the presumption is that the arbitrator
    should decide ‘allegation[s] of waiver, delay, or a like defense to arbitrability.’”
    
    Id. at 84,
    123 S. Ct. at 592 (citations omitted). The issue in Howsam was not
    whether the trial court had subject matter jurisdiction to determine such
    procedural questions; rather, it was whether the presumption in favor of
    arbitration should be employed when determining which “forum-based
    decisionmaker”—an arbitrator or trial court judge—is the more appropriate
    choice “to decide forum-specific procedural gateway matters.” 
    Id. at 84-86,
    123 S. Ct. at 592-93. In Howsam, the petitioner had instituted an arbitration
    proceeding under the National Association of Securities Dealers (NASD) rules,
    and the respondent filed suit in federal court asking for a declaration that the
    arbitration could not proceed because NASD’s rules prohibited arbitrations after
    “six (6) years ha[d] elapsed from the occurrence or event giving rise to
    the . . . dispute.” 
    Id. at 81-82,
    123 S. Ct. at 590-91. In determining that the
    arbitrator was the more appropriate “forum-based decisionmaker” to decide
    whether the NASD rule operated to bar arbitration of the dispute, the Supreme
    Court noted that “NASD arbitrators, comparatively more expert about the
    meaning of their own rule, [would be] better able to interpret and to apply it.”
    
    Id. at 85,
    123 S. Ct. at 593.     The Court also relied on its prior decision in
    14
    Moses H. Cone Memorial Hospital v. Mercury Construction, in which it stated
    that
    [t]he Arbitration Act establishes that, as a matter of federal law,
    any doubts concerning the scope of arbitrable issues should be
    resolved in favor of arbitration, whether the problem at hand is the
    construction of the contract language itself or an allegation of
    waiver, delay, or a like defense to arbitrability.
    
    460 U.S. 1
    , 24-25, 
    103 S. Ct. 927
    , 941 (1983) (emphasis added); see also In
    re Serv. Corp. Int’l, 
    85 S.W.3d 171
    , 173 (Tex. 2002) (quoting above passage
    from Moses, yet going on to address merits of trial court’s decision on waiver).
    After carefully considering the Court’s precise language and holding in
    Howsam, and the Moses H. Cone case which it cites, we conclude that the
    issue here is not one of subject matter jurisdiction; rather, it is whether the
    presumption in favor of arbitrability should apply to the determination of which
    “forum-based decisionmaker” 5 is better suited to decide the procedural
    questions, such as “waiver, delay or a like defense to arbitrability.” 6 Because
    5
    See In re Neutral Posture, Inc., 
    135 S.W.3d 725
    , 728 (Tex.
    App.—Houston [1st Dist.] 2003, orig. proceeding) (discussing Howsam and
    holding that trial court was proper forum for determining issue of substantive
    arbitrability).
    6
    Thus, we need not decide whether this court should follow Howsam in
    the context of reviewing a trial court’s decision under the TGAA. See Grand
    Homes 96, L.P. v. Loudermilk, 
    208 S.W.3d 696
    , 703 (Tex. App.—Fort Worth
    2006, pet. filed); see also In re Global Constr. Co., 
    166 S.W.3d 795
    , 798 (Tex.
    App.—Houston [14th Dist.] 2005, orig. proceeding) (conditionally granting writ
    15
    the issue is not one of subject matter jurisdiction, Northwest was required to
    raise it in the trial court; it did not. See T EX. R. A PP. P. 33.1(a); Mack Trucks,
    Inc. v. Tamez, 
    206 S.W.3d 572
    , 577 (Tex. 2006). In fact, at the hearing on
    the motion to compel, Northwest told the trial court that it would have to
    decide the issue, arguing that
    the court must consider three questions; was there an agreement
    or set of agreements to arbitrate, whether the dispute . . . is
    subject to those agreements to arbitrate? If you answer . . . those
    first two questions, ‘Yes,’ then you must abate the action and
    must order the case to arbitration, unless Oak Partners or one of
    the other parties is able to prove waiver.” [Emphasis added.]
    Northwest and Oak Partners both devoted the majority of their arguments at
    the motion to compel hearing to whether Northwest had substantially invoked
    the judicial process to Oak Partners’ detriment. Accordingly, we conclude and
    hold that Northwest failed to preserve its complaint that the arbitrator, rather
    than the trial court, should have determined whether it waived its right to
    arbitrate by substantially invoking the judicial process to its opponents’
    detriment. We overrule Northwest’s second issue.
    of mandamus after holding, based on Howsam, that arbitrator rather than trial
    court should decide waiver issue in FAA-controlled case).
    16
    Whether Northwest Waived its Right to Arbitrate by Substantially Invoking
    the Judicial Process to Oak Partners’ Detriment
    Northwest contends in its third issue that the trial court incorrectly
    concluded that Northwest had waived its right to arbitrate any part of the
    dispute by substantially invoking the judicial process to its opponents’
    detriment.
    Because public policy favors arbitration, there is a strong presumption
    against finding that a party has waived its right to arbitration; the burden to
    prove waiver is thus a heavy one. In re Bank One, N.A., 
    216 S.W.3d 825
    , 827
    (Tex. 2007); In re Bruce Terminix Co., 
    988 S.W.2d 702
    , 704-05 (Tex. 1998);
    Jones v. Citibank (South Dakota), N.A., 
    235 S.W.3d 333
    , 340 (Tex.
    App.—Fort Worth 2007, no pet.). Any doubts regarding waiver are resolved
    in favor of arbitration. Bruce Terminix 
    Co., 988 S.W.2d at 705
    ; 
    Jones, 235 S.W.3d at 340
    ; Southwind Group, Inc. v. Landwehr, 
    188 S.W.3d 730
    , 735
    (Tex. App.—Eastland 2006, orig. proceeding).      Waiver may be express or
    implied, but it must be intentional. EZ Pawn Corp. v. Mancias, 
    934 S.W.2d 87
    ,
    89 (Tex. 1996); 
    Jones, 235 S.W.3d at 340
    ; Southwind Group, 
    Inc., 188 S.W.3d at 735
    . Whether waiver occurs depends on the individual facts and
    circumstances of each case. 
    Jones, 235 S.W.3d at 340
    ; Southwind Group,
    17
    
    Inc., 188 S.W.3d at 735
    ; Williams Indus., Inc. v. Earth Dev. Sys. Corp., 
    110 S.W.3d 131
    , 135 (Tex. App.—Houston [1st Dist.] 2003, no pet.).
    A party does not waive arbitration merely by delay; instead, the party
    urging waiver must establish that any delay resulted in prejudice. In re Vesta
    Ins. Group, Inc., 
    192 S.W.3d 759
    , 763 (Tex. 2006); Prudential Secs. Inc. v.
    Marshall, 
    909 S.W.2d 896
    , 898-99 (Tex. 1995) (orig. proceeding); 
    Jones, 235 S.W.3d at 340
    . Therefore, the test for determining waiver is two-pronged: (1)
    did the party seeking arbitration substantially invoke the judicial process, and
    (2) did the opposing party prove that it suffered prejudice as a result. 
    Jones, 235 S.W.3d at 340
    .
    Substantial Invocation of Judicial Process
    Merely taking part in litigation does not constitute substantial invocation
    of the judicial process. See In re Vesta Ins. 
    Group, 192 S.W.3d at 763
    ; Bruce
    Terminix 
    Co., 988 S.W.2d at 704
    ; 
    Jones, 235 S.W.3d at 340
    . To substantially
    invoke the judicial process, a party must make a specific and deliberate act after
    suit is filed that is inconsistent with its right to arbitrate, such as engaging in
    extensive discovery or requesting a jury. Nationwide of Bryan, Inc. v. Dyer,
    
    969 S.W.2d 518
    , 522 (Tex. App.—Austin 1998, no pet.).                  Substantially
    invoking the judicial process may occur when the party seeking arbitration
    actively has tried, but failed, to achieve a satisfactory result in litigation before
    18
    turning to arbitration. 
    Jones, 235 S.W.3d at 340
    ; Southwind Group, 
    Inc., 188 S.W.3d at 736
    ; Williams Indus., 
    Inc., 110 S.W.3d at 135
    . Examples include
    moving for summary judgment or seeking a final resolution of the dispute.
    Williams Indus., 
    Inc., 110 S.W.3d at 135
    . Another factor to consider is how
    much activity has taken place in the suit. Vireo, P.L.L.C. v. Cates, 
    953 S.W.2d 489
    , 497 (Tex. App.—Austin 1997, pet. denied). Actions constituting waiver
    may include the movant’s engaging in some combination of the following: filing
    an answer, setting up a counterclaim, pursuing discovery, and moving for a
    continuance prior to moving for a stay pending arbitration. Cent. Nat’l Ins. Co.
    of Omaha v. Lerner, 856 S.W .2d 492, 494 (Tex. App.—Houston [1st Dist.]
    1993, orig. proceeding); see also In re Vesta Ins. 
    Group, 192 S.W.3d at 764
    (holding, in FAA-controlled case, “We agree that allowing a party to conduct
    full discovery, file motions going to the merits, and seek arbitration only on the
    eve of trial defeats the FAA’s goal of resolving disputes without the delay and
    expense of litigation.”).7
    The evidence here shows that during the approximately nineteen months
    from the time it filed its answer in the suit to the time it filed its motion to
    7
    The standard for determining waiver of the right to arbitrate is the same
    under the TGAA and the FAA. Southwind Group, 
    Inc., 188 S.W.3d at 735
    ;
    Brown v. Anderson, 
    102 S.W.3d 245
    , 250 (Tex. App.—Beaumont 2003, pet.
    denied).
    19
    compel arbitration, Northwest served four sets of interrogatories, and one set
    each of requests for production and requests for admissions, to Oak Partners;
    served one set each of interrogatories, requests for disclosure, and requests for
    production on the subcontractors; filed four subpeonas for production of
    documents from third parties; filed a counterclaim and amended counterclaim
    against Oak Partners; filed cross-claims against the subcontractors; filed a
    motion for partial summary judgment seeking to preclude Oak Partners from
    seeking any damages related to design defects in the facility; agreed to
    extensions of the expert designation deadlines; and agreed to at least one
    extension of the trial setting. Northwest points out that it never received a
    ruling on its partial motion for summary judgment and that the motion did not
    request a final ruling on all of Oak Partners’ claims; it also characterizes its
    discovery as “minimal.”
    Northwest focuses on its various activities in the suit in isolation;
    however, when viewed together, all of Northwest’s actions in the suit indicate
    an intention to avail itself of the judicial process. Northwest admitted at the
    hearing on the motion to compel that it sought discovery to aid in mediation
    and that the failure of mediation was the impetus for its motion to compel
    arbitration. In other words, it appears that Northwest was prepared to avail
    itself of the judicial process so long as it was able to achieve the results it
    20
    desired. When Northwest finally filed its motion to compel in July 2007, trial
    was set for September 24, 2007. We conclude and hold that Northwest’s
    activity in the suit constituted substantial invocation of the judicial process.
    See In re Vesta Ins. 
    Group, 192 S.W.3d at 764
    ; 
    Lerner, 856 S.W.2d at 495
    ;
    see also Price v. Drexel Burnham Lambert, Inc., 
    791 F.2d 1156
    , 1159, 1162
    (5th Cir. 1986).
    Prejudice to Opposing Parties
    Northwest claims that even if it substantially invoked the judicial process,
    Oak Partners and the other parties to the suit, i.e., the subcontractors, failed
    to show prejudice as a result; thus, the trial court erred by finding that
    Northwest had waived its right to arbitrate the dispute.            According to
    Northwest, the discovery it sought and obtained in the suit is also discoverable
    in arbitration under the Construction Industry Arbitration Rules of the American
    Arbitration Association, and Oak Partners cannot show that its attorneys’ fees
    would not have been available to it in arbitration. Further, Northwest contends
    that even if Oak Partners is able to show prejudice, the subcontractors did not
    bring forward any evidence of prejudice; thus, the trial court erred in
    determining that Northwest waived arbitration as to all of the parties in the suit.
    The prejudice on which courts focus includes such things as (1) the
    movant’s access to information that is not discoverable in arbitration and (2)
    21
    the opponent’s incurring costs and fees due to the movant’s actions or delay.
    Williams Indus., 
    Inc., 110 S.W.3d at 135
    .        Although delay alone does not
    necessarily show prejudice, it is a material factor to consider.        Sedillo v.
    Campbell, 
    5 S.W.3d 824
    , 828 (Tex. App.—Houston [14th Dist.] 1999, no
    pet.). Showing prejudice is generally an evidentiary burden. Williams Indus.,
    
    Inc., 110 S.W.3d at 135
    .
    Northwest contends that all of the discovery it propounded would be
    available to it in an arbitration proceeding under the AAA’s construction-related
    arbitration rules, which the parties agreed to employ in the event of arbitration.
    Those rules provide that “[a]t the request of any party or at the discretion of the
    arbitrator, consistent with the expedited nature of arbitration, the arbitrator may
    direct (i) the production of documents and other information, and (ii) the
    identification of any witnesses to be called.” They also compel the parties to
    “exchange copies of all exhibits they intend to submit at the [arbitration]
    hearing” at least five business days prior to the hearing. The rules further
    provide that “[t]here shall be no other discovery, except as indicated herein or
    as ordered by the arbitrator in extraordinary cases when the demands of justice
    require it.”
    Oak Partners correctly points out that the applicable arbitration rules do
    not provide for requests for admissions or for interrogatories, which constituted
    22
    the bulk of the discovery Northwest sought from Oak Partners.8 Oak Partners
    incurred legal fees for counsel and local counsel to review and respond to this
    discovery.9 At the hearing on Northwest’s motion to compel, Oak Partners
    offered as evidence an affidavit from its counsel averring that Northwest had
    served on Oak Partners four sets of interrogatories and one set each of a
    request for admissions, request for disclosure, and request for production. Oak
    8
    Northwest acknowledges that requests for admissions and interrogatories
    are not available under the applicable rules except “in extraordinary cases when
    the demands of justice require it.” However, Northwest contends that all of the
    information included in those forms of discovery would be nevertheless
    discoverable in arbitration via other forms of discovery. Regardless, Oak
    Partners presented evidence of its expense and time related specifically to the
    types of discovery that is unavailable in arbitration, and there is no evidence
    that this is the type of extraordinary case in which an arbitrator would allow
    additional discovery.
    9
    Northwest attributes any prejudice caused by Oak Partners’ engaging
    local counsel to Oak Partners’ own decision to sue in its chosen forum. See
    LJA Eng’g and Surveying, Inc. v. Richfield Inv. Corp., 
    211 S.W.3d 443
    , 446-47
    (Tex. App.—Beaumont 2006, no pet.); Transwestern Pipeline Co. v. Horizon Oil
    & Gas Co., 
    809 S.W.2d 589
    , 593 (Tex. App.—Dallas 1991, writ dism’d w.o.j.).
    But it is clear from the billing records submitted by Oak Partners that local
    counsel did not even begin to participate in the suit until Northwest filed its
    counterclaim and began to participate in those activities that we have
    determined substantially invoked the judicial process by indicating an intent to
    litigate the suit in Hood County. Thus, Oak Partners presented evidence
    directly relating its expenses to Northwest’s activity in the suit.
    23
    Partner’s counsel also averred that “Oak Partners has answered, responded,
    and/or objected to all of this discovery sent by Northwest.” 10
    Oak Partners also introduced evidence that it incurred attorney’s fees and
    expenses in responding to Northwest’s motion for partial summary judgment.
    Northwest did not cancel the partial summary judgment trial date until after Oak
    Partners had filed its response and incurred these fees and expenses.
    Moreover, Oak Partners contends that, regardless of the fees and expenses
    involved in responding to the motion, it was prejudiced because Northwest
    “now has in one document, forced Oak Partners to marshal its evidence, and
    even more damaging, marshal the thought processes and legal analysis of Oak
    Partners’ attorneys on these issues.”
    Northwest responds that the construction industry arbitration rules
    provide for summary dispositions by the arbitrator: “In addition to the final
    award, the arbitrator may make other decisions, including interim, interlocutory,
    10
    Although Oak Partners did not include copies of its answers to discovery
    in the appellate record, it did provide evidence that it answered the discovery
    and incurred expenses in doing so, in the form of billing records from its lead
    counsel and local counsel. Northwest did not present any evidence refuting
    Oak Partners’ counsel’s sworn statement indicating that Oak Partners had
    responded to all of Northwest’s discovery requests. Additionally, Northwest
    admitted that it sought discovery for mediation purposes and that after the
    initial mediation, it sought additional discovery for purposes of another
    mediation.
    24
    or partial rulings, orders, and awards.” Thus, according to Northwest, Oak
    Partners could not have been prejudiced by responding to the motion for partial
    summary judgment when the same procedure would have been available to
    Northwest in arbitration.
    Again, Northwest focuses only on the effects of its actions in isolation.
    Not only did it delay nineteen months before moving to compel arbitration,
    during which time it actively pursued litigation in the trial court, Northwest also
    sought discovery that cannot be characterized as only minimal. 11 It actively
    sought relief from the trial court, forcing Oak Partners to respond and to incur
    attorneys’ fees for lead counsel and local counsel that are directly linked to
    Northwest’s actions in the suit, which fees Oak Partners documented in its
    response to the motion to compel.12 Unlike in cases cited by Northwest, here,
    11
    See, e.g., In re Bruce Terminix 
    Co., 988 S.W.2d at 704
    (holding, when
    movant’s “use of the judicial process was limited to filing an answer and
    propounding one set of eighteen interrogatories and one set of nineteen
    requests for production,” that prejudice was not shown because “when only a
    minimal amount of discovery has been conducted, which may also be useful for
    the purpose of arbitration, the court should not ordinarily infer waiver based
    upon prejudice”) (emphasis added).
    12
    Northwest contends that Oak Partners cannot show prejudice due to its
    incurring attorneys’ fees as a result of Northwest’s actions (1) because the
    construction industry arbitration rules provide that an arbitration award “may
    include . . . an award of attorneys’ fees if all parties have requested such an
    award or it is authorized by law or their arbitration agreement” and because (2)
    section 171.048 of the TGAA requires arbitrators to award attorneys’ fees if
    25
    Oak Partners introduced evidence supporting its claims of prejudice. Cf. In re
    Vesta Ins. 
    Group, 192 S.W.3d at 763
    (“Because Cashion offered none of these
    documents in the trial court and presented no details about any of them, the
    record does not show whether these [discovery] requests were limited or
    extensive, whether they sought information for affirmative claims or defensive
    ones, or even whether they addressed the merits or merely the arbitration
    issue.”); Granite Constr. Co. v. Beaty, 
    130 S.W.3d 362
    , 367 (Tex.
    App.—Beaumont 2004, no pet.); Williams Indus., 
    Inc., 110 S.W.3d at 139-41
    .
    Accordingly, we conclude and hold that Oak Partners showed prejudice from
    Northwest’s substantial invocation of the judicial process. See 
    Price, 791 F.2d at 1161-62
    (“[W]here a party fails to demand arbitration during pretrial
    proceedings, and, in the meantime, engages in pretrial activity inconsistent with
    an intent to arbitrate, the party later opposing a motion to compel arbitration
    they are provided for in the arbitration agreement or they are provided for by
    law in a district court in a civil action. T EX. C IV. P RAC. & R EM. C ODE
    A NN. § 171.048 (Vernon 2005). But the language of the construction industry
    arbitration rules does not require an arbitrator to award fees even if a party
    presents evidence supporting such an award. Additionally, Northwest’s claims
    against Oak Partners include claims for breach of contract and negligence; Oak
    Partners’ attorneys’ fees are recoverable only if it prevails on its breach of
    contract action. See 
    id. § 38.001(8)
    (Vernon 1997); Green Int’l, Inc. v. Solis,
    
    951 S.W.2d 384
    , 390 (Tex. 1997).
    26
    may more easily show that its position has been compromised, i.e.,
    prejudiced.”).
    Northwest did not just move to arbitrate Oak Partners’ claims, however;
    it also sought to arbitrate the claims involving the subcontractors. None of the
    subcontractors presented evidence to the trial court regarding prejudice. Thus,
    we cannot conclude that waiver was proved as to the subcontractors. See,
    e.g., Granite Constr. 
    Co., 130 S.W.3d at 367
    ; Williams Indus., 
    Inc., 110 S.W.3d at 139-41
    . Because the trial court’s order denied Northwest’s motion
    to compel in its entirety as to all parties, we conclude and hold that the trial
    court erred by refusing to compel arbitration of the claims between Northwest
    and the subcontractors.13 We therefore sustain Northwest’s third issue in part
    as to the claims involving the subcontractors; we overrule it in part as to the
    claims between Northwest and Oak Partners.
    13
    We realize this results in the unfortunate possibility of trying these cases
    in different forums but “considerations of efficiency and convenience cannot
    override either a signatory’s arbitration agreement or a nonsignatory’s right to
    a jury trial.” In re Merrill Lynch Trust Co. FSB, 
    235 S.W.3d 185
    , 192 (Tex.
    2007) (orig. proceeding) (holding arbitration agreement must be enforced
    regardless of presence of other people involved in the underlying dispute but
    not signatories to the arbitration agreement); see also Kilroy v. Kilroy, 
    137 S.W.3d 780
    , 787-88 (Tex. App.—Hous. [1 st Dist.] 2004, no pet.) (reversing
    trial court order staying arbitrable part of dispute pending determination of
    issues in nonarbitrable part of dispute remaining in trial court).
    27
    Mediation as Condition Precedent to Arbitration
    At the hearing on the motion to compel, one of the subcontractors, Ari-
    Tex, argued that the arbitration agreement with the subcontractors required
    Northwest to mediate before resorting to arbitration and that Northwest had
    failed to mediate with the subcontractors;14 therefore, arbitration could not be
    compelled until Northwest had attempted to mediate its disputes with the
    subcontractors. Ari-Tex has not responded to Northwest’s appeal; however,
    Northwest brings a fourth issue contending that appellees have waived their
    right to rely on mediation as a condition precedent to enforceability of the
    arbitration clause.
    Although the AIA Document A201-1997 that was incorporated into the
    parties’ agreements clearly states that mediation is a condition precedent to
    arbitration with regard to at least some claims arising from the agreements,
    none of the subcontractors allege any damages from Northwest’s failure to
    mediate with them. See In re U.S. Home Corp., 
    236 S.W.3d 761
    , 764 (Tex.
    2007). Moreover, the subcontractors initially filed suit against Northwest in
    district court rather than seeking mediation pursuant to the agreements. Thus,
    14
    Ari-Tex alleged that the subcontractors were not allowed to attend the
    mediation between Northwest and Oak Partners.
    28
    they waived their right to first proceed through mediation.      See id.; Dallas
    Cardiology Assocs., P.A. v. Mallick, 
    978 S.W.2d 209
    , 212-13 (Tex.
    App.—Texarkana 1998, pet. denied).
    Conclusion
    Having overruled Northwest’s dispositive issues as to Oak Partners, we
    affirm the part of the trial court’s order denying Northwest’s motion to compel
    arbitration as to the claims between Northwest and Oak Partners. However,
    having sustained Northwest’s dispositive issue as to the subcontractors, we
    reverse the part of the trial court’s order denying arbitration as to the claims
    between Northwest and the subcontractors and remand to the trial court with
    instructions to compel arbitration as to those claims only. Having determined
    that Northwest failed to bring forward any evidence of interstate commerce, we
    dismiss its petition for writ of mandamus.
    TERRIE LIVINGSTON
    JUSTICE
    PANEL B:    LIVINGSTON, DAUPHINOT, and WALKER, JJ.
    DAUPHINOT, J. filed a concurring and dissenting opinion.
    DELIVERED: March 6, 2008
    29
    COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 2-07-293-CV
    NORTHWEST CONSTRUCTION                           APPELLANT
    COMPANY, INC.
    V.
    THE OAK PARTNERS, L.P.,                          APPELLEES
    MORGAN DEVELOPMENT
    AND SUPPLY, INC.,
    METROPLEX MASONRY, INC.,
    ARI-TEX, INC., MAX PLUMBING
    CONTRACTORS, INC.,
    S & S TILE, LTD., AND
    KENT-ANDERSON CONCRETE, L.P.
    D/B/A ANDERSON CONCRETE
    CONSTRUCTION
    ------------
    FROM THE 355TH DISTRICT COURT OF HOOD COUNTY
    ------------
    AND
    NO. 2-07-328-CV
    IN RE NORTHWEST                                                        RELATOR
    CONSTRUCTION COMPANY, INC.
    ------------
    ORIGINAL PROCEEDING
    ------------
    CONCURRING AND DISSENTING OPINION
    ------------
    I agree that Northwest’s petition for writ of mandamus should be
    dismissed. I also agree that we should reverse the trial court’s order denying
    arbitration as to the claims between Northwest and the subcontractors and
    remand to the trial court with instructions to compel arbitration on those claims.
    I dissent, however, from the majority’s conclusion that Oak Partners met
    its heavy burden to show sufficient prejudice to overcome the strong
    presumption against waiver of arbitration.15 I would therefore reverse in its
    entirety the trial court’s order denying arbitration and remand this case to the
    trial court with instructions to compel arbitration on all claims.
    LEE ANN DAUPHINOT
    JUSTICE
    15
    See In re D. Wilson Constr. Co., 
    196 S.W.3d 774
    , 783 (Tex. 2006); In
    re Vesta Ins. Group, Inc., 
    192 S.W.3d 759
    , 763 (Tex. 2006).
    31
    DELIVERED: March 6, 2008
    32
    

Document Info

Docket Number: 02-07-00293-CV

Filed Date: 3/6/2008

Precedential Status: Precedential

Modified Date: 2/1/2016

Authorities (30)

In Re Bank One, N.A. , 50 Tex. Sup. Ct. J. 456 ( 2007 )

Nasr v. Rubio , 2001 Tex. App. LEXIS 3621 ( 2001 )

In Re U.S. Home Corp. , 51 Tex. Sup. Ct. J. 42 ( 2007 )

Kilroy v. Kilroy , 2004 Tex. App. LEXIS 4182 ( 2004 )

Southwind Group, Inc. v. Landwehr , 2006 Tex. App. LEXIS 896 ( 2006 )

In Re Global Construction Co. , 2005 Tex. App. LEXIS 4406 ( 2005 )

In Re Bruce Terminix Co. , 41 Tex. Sup. Ct. J. 941 ( 1998 )

Fed. Sec. L. Rep. P 92,790 Rayford Price and Barbara Ashley ... , 791 F.2d 1156 ( 1986 )

VIREO PLLC v. Cates , 953 S.W.2d 489 ( 1997 )

Nationwide of Bryan, Inc. v. Dyer , 1998 Tex. App. LEXIS 2718 ( 1998 )

In Re Citigroup Global Markets, Inc. , 2006 Tex. App. LEXIS 8735 ( 2006 )

LJA Engineering & Surveying, Inc. v. Richfield Investment ... , 2006 Tex. App. LEXIS 10624 ( 2006 )

Sedillo v. Campbell , 1999 Tex. App. LEXIS 7637 ( 1999 )

Jones v. Citibank (South Dakota), N.A. , 2007 Tex. App. LEXIS 7083 ( 2007 )

Grand Homes 96, L.P. v. Loudermilk , 2006 Tex. App. LEXIS 9787 ( 2006 )

Williams Industries, Inc. v. Earth Development Systems Corp. , 110 S.W.3d 131 ( 2003 )

In Re Neutral Posture, Inc. , 2003 Tex. App. LEXIS 6549 ( 2003 )

Transwestern Pipeline Co. v. Horizon Oil & Gas Co. , 1991 Tex. App. LEXIS 1457 ( 1991 )

Jack B. Anglin Co., Inc. v. Tipps , 36 Tex. Sup. Ct. J. 205 ( 1992 )

Barnard v. Barnard , 2004 Tex. App. LEXIS 3009 ( 2004 )

View All Authorities »