tuscan-builders-lp-v-1437-sh6-llc-dba-sweetwater-aesthetic-spa ( 2014 )


Menu:
  • Opinion issued May 15, 2014
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-13-00685-CV
    ———————————
    TUSCAN BUILDERS, LP, Appellant
    V.
    1437 SH6 L.L.C. D/B/A SWEETWATER AESTHETIC SPA
    & WELLNESS CENTER, SHELENA C. LALJI, M.D., P.A. D/B/A
    DR. SHEL WELLNESS & MEDICAL SPA AND LALJI DENTAL,
    P.C. D/B/A LAKE POINTE DENTAL AND SPECIALTY, Appellees
    On Appeal from the 151st District Court
    Harris County, Texas
    Trial Court Case No. 2012-33706
    OPINION ON REHEARING
    Appellant Tuscan Builders, LP has moved for rehearing and en banc
    consideration. We grant rehearing, withdraw our opinion and judgment of January
    30, and issue the following in their stead. We dismiss as moot Tuscan’s motion for
    en banc consideration. Our disposition of the appeal remains unchanged.
    In this construction dispute, a builder appeals the trial court’s order denying
    its motion to compel arbitration against the building’s owners.           The builder
    contends that the trial court erred in finding that the builder had waived
    enforcement of an arbitration clause by invoking the judicial process and delaying
    its effort to compel arbitration for more than a year. Finding no error, we affirm.
    Background
    The contract dispute
    The commercial building owners, 1437 SH6 L.L.C. d/b/a Sweetwater
    Aesthetic Spa & Wellness Center, Shelena C. Lalji, M.D., P.A. d/b/a Dr. Shel
    Wellness & Medical Spa, and Lalji Dental, P.C. d/b/a Lake Pointe Dental and
    Specialty (collectively, Sweetwater) sued Tuscan, the builder, for breach of
    warranty associated with alleged construction defects. Sweetwater had contracted
    with a construction design team, the Mirador Group, Inc., and an architect, Todd
    Blitzer, to design a building suitable for a dental office, a wellness clinic, and other
    health-related businesses. Sweetwater’s design services agreement with Mirador
    provides that venue for any suit “shall be in a Texas State District Court in Harris
    County, Texas.”      The design agreement incorporates by reference specific
    provisions of the “Standard Form of Agreement between Owner and Architect
    2
    (AIA Document B141–1997),” but it expressly excludes “Sections 1.3.4,
    Mediation and 1.3.5, Arbitration.”
    Sweetwater hired Tuscan to construct the building according to Mirador’s
    design specifications.   Tuscan prepared the construction contract using AIA
    Document A101–1997, the “Standard Form of Agreement between Owner and
    Contractor where the basis of payment is a stipulated sum.”              The parties’
    construction contract incorporates by reference an industry form document—AIA
    Document A201–1997, the “General Conditions of the Contract for Construction”
    [General Conditions]—but it does not attach a copy of that document. Like AIA
    Document B141–1997, incorporated into the design agreement, A201–1997 calls
    for mediation in the first instance, followed by arbitration. Unlike the design
    agreement, the construction contract does not exclude the AIA Document’s
    arbitration provisions that were incorporated by reference, but not attached to the
    contract. The pertinent sections of A201–1997 provide:
    Claims not resolved by mediation shall be decided by arbitration
    which, unless the parties mutually agree otherwise, shall be in
    accordance with the Construction Industry Arbitration Rules of the
    American Arbitration Association currently in effect. The demand for
    arbitration shall be filed in writing with the other party to the Contract
    and with the American Arbitration Association, and a copy shall be
    filed with the Architect.
    After it moved in, Sweetwater noticed water leaking into the building. It
    informed Mirador and Tuscan of the problem, and they attempted to repair the
    3
    leaks. During a rainstorm in July 2010, however, significant water leaks appeared
    in the exterior walls and roof, causing substantial damage to the structure and
    interior walls. Sweetwater again sought to have Mirador and Tuscan repair the
    building, but Sweetwater was not satisfied with the results.
    Course of proceedings
    In June 2012, Sweetwater sued Mirador, Tuscan, and Blitzer for negligence,
    breach of contract, and breaches of express and implied warranties, as well as
    statutory claims under the Texas Deceptive Trade Practices Act. Tuscan answered
    the suit on June 29.     Tuscan denied Sweetwater’s allegations, raised several
    specific defenses, and made a verified denial; it did not mention arbitration in the
    filing. In November, Tuscan sued its five subcontractors, seeking indemnification
    under the indemnification provisions in each subcontractor agreement. Tuscan
    sued each subcontractor for negligence, breach of contract, and breach of warranty.
    Sweetwater later amended its petition to include its own claims against the
    subcontractors. The subcontractors answered, and several demanded a jury trial.
    In addition to pursuing written discovery, the subcontractors also sought to inspect
    the Sweetwater property, pursuant to Texas Rule of Civil Procedure 196.7. Tuscan
    participated with the third-party defendants in the inspection.
    The trial court’s docket control order called for the discovery period to end
    in March 2013 and trial to commence in April 2013. In January 2013, Tuscan
    4
    joined Sweetwater in filing an agreed motion for continuance. The joint motion
    requested the continuance for the “opportunity to conduct discovery and identify
    the relevant issues.” Tuscan did not mention arbitration. The trial court granted
    the motion and extended the discovery, motion, and pleading deadlines. It set trial
    to commence on September 16, 2013.
    On June 6, 2013, Tuscan, the other defendants, and the third-party
    defendants moved to extend the mediation deadline complaining that, before
    mediating the dispute, they required additional information concerning the various
    components    of   Sweetwater’s   alleged   damages,    responses   to   additional
    interrogatories, answers to requests for admissions they had propounded, and the
    depositions of Sweetwater’s corporate representatives and management agents,
    which, the motion represented, were scheduled for July 2 and 8.
    By July 14, the expert witnesses had been designated and the expert
    designation deadlines for all parties had passed; approximately one month
    remained of the discovery period.       The parties had completed their paper
    discovery. On that date, Tuscan invoked the arbitration provision incorporated by
    reference into the construction contract and included with its motion an unsigned
    copy of the General Conditions form containing that provision.
    The trial court held an evidentiary hearing on Tuscan’s motion to compel
    arbitration and denied the motion on August 1.
    5
    Discussion
    Tuscan challenges the trial court’s ruling, contending that it erred in denying
    Tuscan’s motion to compel arbitration because the evidence does not establish that
    Tuscan had waived its contractual right to arbitrate by substantially invoking the
    judicial process.1
    Applicable Law and Standard of Review
    Waiver is the intentional relinquishment of a known right or intentional
    conduct inconsistent with claiming that right. Jernigan v. Langley, 
    111 S.W.3d 153
    , 156 (Tex. 2003); Interconex, Inc. v. Ugarov, 
    224 S.W.3d 523
    , 533 (Tex.
    App.—Houston [1st Dist.] 2007, no pet.). “[A] party waives an arbitration clause
    by substantially invoking the judicial process to the other party’s detriment or
    prejudice.” Perry Homes v. Cull, 
    258 S.W.3d 580
    , 589–90 (Tex. 2008) (footnote
    omitted). A party substantially invokes the judicial process if it takes specific and
    deliberate actions that are inconsistent with the right to arbitrate or if it actively
    tries, but fails to achieve, a satisfactory result through litigation before turning to
    arbitration. In re Christus Spohn Health Sys. Corp., 
    231 S.W.3d 475
    , 478–79
    (Tex. App.—Corpus Christi 2007, orig. proceeding); see In re Vesta Ins. Grp., Inc.,
    1
    Tuscan also contends on appeal that it established the validity of the arbitration
    agreement. The trial court raised questions concerning the validity during the
    evidentiary hearing, but it but did not base its ruling on any specific ground. For
    purposes of this appeal, we assume that a valid arbitration agreement exists
    between Tuscan and Sweetwater.
    6
    
    192 S.W.3d 759
    , 763 (Tex. 2006) (orig. proceeding). Prejudice refers to the
    inherent unfairness caused by “a party’s attempt to have it both ways by switching
    between litigation and arbitration to its own advantage.”       Perry 
    Homes, 258 S.W.3d at 597
    .
    Whether a party has participated in the litigation process and thus waived the
    right to arbitrate is a question of law for the court. 
    Id. at 587.
    We apply a strong
    presumption against waiver of arbitration and resolve any doubt on the issue in
    favor of arbitration. 
    Id. at 584;
    see In re Bruce Terminix Co., 
    988 S.W.2d 702
    , 705
    (Tex. 1998).
    For a waiver to have occurred, the appellant “must, at the very least, [have]
    engage[d] in some overt act in court that evince[d] a desire to resolve the [same]
    arbitrable dispute through litigation rather than arbitration.” Haddock v. Quinn,
    
    287 S.W.3d 158
    , 177 (Tex. App.—Fort Worth 2009, pet. denied). In assessing
    whether Tuscan waived its right to arbitrate, we consider whether Tuscan’s
    conduct in the litigation portrays the kind of “aggressive litigation strategy” that
    substantially invokes the litigation process. See Okorafor v. Uncle Sam & Assocs.,
    
    295 S.W.3d 27
    , 40 (Tex. App.—Houston [1st Dist.] 2009, pet. denied); see also In
    re Christus Spohn Health Sys. 
    Corp., 231 S.W.3d at 479
    (explaining that actions
    inconsistent with right to arbitrate may include “some combination of filing an
    answer, setting up a counterclaim, pursuing extensive discovery, moving for a
    7
    continuance, and failing to timely request arbitration”) (citing Cent. Nat’l Ins. Co.
    of Omaha v. Lerner, 
    856 S.W.2d 492
    , 494 (Tex. App.—Houston [1st Dist.] 1993,
    orig. proceeding)). In determining whether a party waived an arbitration clause,
    the courts can consider, among other factors: (1) whether the movant for arbitration
    was the plaintiff (who chose to file in court) or the defendant (who merely
    responded), (2) when the movant learned of the arbitration clause and how long the
    movant delayed before seeking arbitration, (3) the amount of the movant’s pretrial
    activity related to the merits rather than arbitrability or jurisdiction, (4) the amount
    of discovery conducted, and (5) whether the movant sought judgment on the
    merits. See Perry 
    Homes, 258 S.W.3d at 591
    –92; In re Hawthorne Townhomes,
    L.P., 
    282 S.W.3d 131
    , 141 (Tex. App.—Dallas 2009, no pet.).               We analyze
    whether waiver occurred based on the totality of the circumstances presented in
    each case. See In re Citigroup Global Mkts., Inc., 
    258 S.W.3d 623
    , 625 (Tex.
    2008); 
    Okorafor, 295 S.W.3d at 38
    ; Interconex, 
    Inc., 224 S.W.3d at 533
    .
    The Perry Homes Factors
    Tuscan began as a defendant in the suit. Early in the litigation, however,
    Tuscan also became a third-party plaintiff by suing its subcontractors. Although a
    party invokes the judicial process when it sues in court, the filing of a third-party
    action, standing alone, may not be enough to constitute waiver of an agreement to
    arbitrate. In D.R. Horton-Tex., Ltd. v. Drogseth, for example, the Fort Worth
    8
    Court of Appeals held that the defendant did not waive its right to arbitrate by
    filing a third-party action because the defendant concurrently had moved in the
    trial court to abate the case and submit it to binding arbitration. No. 02–12–
    00435–CV, 
    2013 WL 3377121
    , at *5–6 (Tex. App.—Fort Worth July 3, 2013, no
    pet.) (mem. op.). In its motion to compel arbitration filed six weeks later, the
    defendant explained that it had filed the third-party petition before the hearing on
    its motion to compel to preserve its claims against the third-party defendants and
    did not intend a waiver of right to arbitration. 
    Id. at *5.
    In contrast to the movant
    in D.R. Horton, Tuscan did not accompany its answer or its third-party claims with
    any notice of an intent to pursue arbitration, nor did Tuscan seek an abatement of
    the case pending resolution of its claim to arbitration.
    Based on the record, the trial court reasonably could have found that Tuscan
    knew of the arbitration clause before it answered Sweetwater’s suit, but that it did
    not reveal the existence of the arbitration agreement to Sweetwater until after
    Tuscan had sued third parties and the parties had conducted a property inspection
    and completed written discovery, including expert designations. 2          The owner-
    contractor agreement, prepared by Tuscan for Sweetwater’s execution,
    2
    On rehearing, Tuscan contends that we should disregard counsel’s statements
    concerning the status of discovery in the proceedings because they are not
    evidence, only argument. Tuscan, however, waived any complaint about their
    evidentiary value by failing to object in the trial court. See Banda v. Garcia, 
    955 S.W.2d 270
    , 272 (Tex. 1997).
    9
    incorporates a construction industry form that incorporates by reference another
    clause, contained in the General Conditions form, that allows for arbitration.
    The “General Conditions” form containing the arbitration clause declares
    that, “The Contract Documents consist of the Agreement between Owner and
    Contractor . . ., Conditions of the Contract (General, Supplementary, and other
    Conditions), Drawings, Specifications, Addenda issued prior to execution of the
    Contract, other documents listed in the Agreement and Modifications issued after
    execution of the Contract.” It further provides that “[t]he Contract Documents
    shall be signed by Owner and Contractor.” Tuscan, however, did not provide a
    signed copy of the form with its motion, nor did it deny Sweetwater’s assertion that
    it had no actual knowledge or notice of the form’s contents until it received
    Tuscan’s motion to compel.
    If Tuscan’s failure to attach the industry form to the construction contract
    did not render the arbitration provision invalid, the record, at a minimum,
    demonstrates that Tuscan understood the reference to its own industry form and
    was aware that it contained an arbitration provision, yet did not enlighten
    Sweetwater that its claims were subject to arbitration until Tuscan moved to
    compel arbitration more than a year after filing third party actions and proceeding
    with discovery.
    10
    Sweetwater’s contract with Mirador expressly excludes any obligation to
    arbitrate and requires litigation in Harris County district court.      As a result,
    Tuscan’s belated invocation of the arbitration clause to conduct arbitration would
    delay the resolution of the dispute between Tuscan and Mirador, and would make
    for an inefficient, piecemeal adjudication, to the expense of Sweetwater, who has
    prepared its case against the defendants in a single forum. Had Tuscan promptly
    moved for arbitration, Sweetwater and the other defendants would have been
    entitled to a stay of proceedings pending arbitration; instead, the parties engaged in
    considerable time and expense on the road to a court trial. These circumstances
    make the timing of Tuscan’s motion to compel more consistent with a late-game
    tactical decision than an intent to preserve the right to arbitrate.
    Tuscan joined in motions that prolonged the discovery period and postponed
    the trial date and mediation deadline to allow the parties to pursue additional
    discovery on the merits. By the time Tuscan moved to compel arbitration—more
    than a year after Sweetwater filed suit—the parties had completed written
    discovery, designated their experts for trial, and physically inspected the building,
    and the trial setting was less than a month away. The need for further merits
    discovery served as the basis for the parties’ successful requests for both the trial
    continuance and the extension of the mediation deadline. In opposing Tuscan’s
    11
    motion to compel arbitration, Sweetwater pointed out that Tuscan would not have
    been likely to obtain a building inspection in an arbitral forum.
    Tuscan responds that its own discovery activities were limited to written
    discovery. Tuscan’s litigation strategy, however, enhanced its discovery efforts.
    By suing its subcontractor-indemnitors, Tuscan benefited from the discovery
    sought by these additional parties, who are aligned with it against Sweetwater. For
    example, Tuscan availed itself of the opportunity, made possible by the
    subcontractors’ discovery request, to inspect the building.         By bringing the
    subcontractors into the suit, Tuscan accomplished indirectly what it did not do
    directly. The record supports the trial court’s conclusion that these tactics, taken
    together, were inconsistent with any intent to arbitrate these claims, and caused
    some prejudice to Sweetwater.
    The purpose of the presumption against finding a waiver of contractual
    arbitration is to preserve the purpose of the parties’ agreement to obtain a speedy
    and inexpensive final disposition of the disputed matter. See Porter & Clements,
    L.L.P. v. Stone, 
    935 S.W.2d 217
    , 221 (Tex. App.—Houston [1st Dist.] 1996, no
    pet.). Tuscan’s year-long delay in invoking or even mentioning the arbitration
    clause gave Tuscan litigation advantages it would not have had in an arbitration
    proceeding. We hold that the trial court properly denied Tuscan’s motion to
    12
    compel arbitration because Tuscan had substantially invoked the judicial process,
    to Sweetwater’s prejudice.
    Conclusion
    We hold that the trial court did not err in denying Tuscan’s motion to
    compel arbitration. We therefore affirm the trial court’s order and remand the
    cause for further proceedings.
    Jane Bland
    Justice
    Panel consists of Chief Justice Radack and Justices Bland and Huddle.
    13