rmdg-construction-llc-dba-dudley-general-contractors-and-dudley ( 2014 )


Menu:
  •                                  IN THE
    TENTH COURT OF APPEALS
    No. 10-11-00310-CV
    RMDG CONSTRUCTION, LLC D/B/A DUDLEY
    GENERAL CONTRACTORS AND DUDLEY
    CONSTRUCTION, LTD D/B/A R.M. DUDLEY
    CONSTRUCTION COMPANY,
    Appellants
    v.
    OAKWOOD CUSTOM HOMES GROUP, LTD
    AND INSURORS INDEMNITY COMPANY,
    Appellees
    From the 361st District Court
    Brazos County, Texas
    Trial Court No. 07-002207-CV-361
    MEMORANDUM OPINION
    RMDG Construction, LLC d/b/a Dudley Construction (Dudley) filed suit
    against Oakwood Custom Homes Group, LTD, and Insurors Indemnity Group for
    breach of contract, quantum meruit, and action on the bonds. Oakwood filed a counter-
    petition alleging breach of contract and other claims. The jury found that both parties
    materially breached the contract, but that each party’s breach was excused. The trial
    court entered judgment that Dudley take nothing against Oakwood and Insurors
    Indemnity and that Oakwood and Insurors Indemnity take nothing against Dudley.
    Dudley and Oakwood both appeal from the trial court’s judgment. We affirm.
    Sufficiency of the Evidence
    In the first issue, Dudley argues that there is no evidence to support a finding
    that Dudley materially breached the contract first. Dudley contends that the evidence
    establishes that Oakwood was the first to materially breach the contract. In the second
    issue, Dudley contends that the evidence is insufficient to support the jury’s finding that
    Oakwood’s breach was excused.
    In reviewing a legal sufficiency challenge to the evidence, we credit evidence that
    supports the verdict if reasonable jurors could have done so and disregard contrary
    evidence unless reasonable jurors could not have done so. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex.2005). We will sustain a legal sufficiency challenge when (a) there
    is a complete absence of evidence of a vital fact, (b) the court is barred by rules of law or
    of evidence from giving weight to the only evidence offered to prove a vital fact, (c) the
    evidence offered to prove a vital fact is no more than a mere scintilla, or (d) the evidence
    conclusively establishes the opposite of the vital fact. Merrell Dow Pharm., Inc. v. Havner,
    
    953 S.W.2d 706
    , 711 (Tex.1997).
    Background Facts
    Oakwood, a residential homebuilder and developer, contracted to develop a new
    residential subdivision to be named Horse Haven Estates. Mark Dudley is a principal
    in several construction corporations. Oakwood and Dudley entered into a contract
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                              Page 2
    where Dudley was to provide grading work, installation of a sewer system, installation
    of a water-line system, and streets for the subdivision. The contract included a time is
    of the essence provision and stated that the work would be completed within 60 days
    for Phase II and 90 days for Phase III allowing for two weeks for the pre-ordering of
    materials.   The contract further provided that Oakwood would make progress
    payments on or about the 30th day of each month based upon Dudley’s applications for
    payment. The payments were required to be made within ten days from the date of
    submission of the pay application.
    The contract further provided that Oakwood “is responsible for removing all
    structures (barns, mobile homes, septic systems, fences, concrete slabs, etc.) and trees
    before [Dudley] is to proceed with their portion of the Contract.” Oakwood was to
    employ and pay for the services of an independent testing laboratory to perform all
    inspections, tests, or approvals required by the contract documents.      The contract
    further stated that “[b]efore starting work, [Oakwood] will furnish [Dudley] ‘set aside’
    letter from his lending institution which will state that the contract amount has been
    placed in an account for which the sole purpose is to pay [Dudley]…”
    The record shows that Oakwood did not provide a set-aside letter as provided in
    the contract and that Oakwood did not remove all the trees and structures from the job
    site as provided in the contract. Dudley, however, began work on the project. There
    were many delays, and the project was not timely completed. Oakwood removed
    Dudley from the job and hired another contractor to complete the project. Oakwood
    made payments to Dudley for the first three pay applications, but the fourth and fifth
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                         Page 3
    pay applications remain unpaid. Dudley filed three liens related to the contract, and
    Oakwood filed bonds to indemnify against the liens. The liens remain on file.
    Jury Findings
    The jury found that Dudley Construction Ltd. and Oakwood Custom Homes,
    Ltd. intended to bind themselves mutually to the contract. The jury further found that
    both Dudley and Oakwood failed to comply with the contract and that the failure to
    comply was material. The jury determined that both Dudley and Oakwood’s failure to
    comply was excused. Because the jury found that both parties material breach was
    excused, the jury did not award either party damages.
    Analysis
    Dudley argues that there is no evidence that Dudley materially breached the
    contract first and that the evidence shows that Oakwood was the first to materially
    breach the contract. It is a fundamental principle of contract law that when one party to
    a contract commits a material breach of that contract, the other party is discharged or
    excused from further performance. Mustang Pipeline Company, Inc. v. Driver Pipeline
    Company, Inc., 
    134 S.W.3d 195
    , 196 (Tex. 2004).       Dudley contends that Oakwood
    materially breached the contract by:
     failing to remove all structures and trees before Dudley began work on the
    project,
     failing to furnish the set aside letter before Dudley began work,
     failing to pay for inspections and tests,
     failing to furnish materials to maintain access to the Kolbe tract,
     failing to timely pay the pay applications submitted by Dudley, and
     failing to extend the contractual deadlines for delays beyond Dudley’s
    control.
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                          Page 4
    Dudley argues that it was excused from performing under the contract because of the
    prior material breach by Oakwood.
    In Mustang Pipeline Company, Inc. v. Driver Pipeline Company, Inc., both parties
    obtained favorable jury findings as to the other’s breach of contract, and both parties
    moved for judgment notwithstanding the verdict. Mustang asked the trial court to
    disregard the jury’s finding that Mustang wrongfully terminated the contract arguing
    that once the jury found Driver breached the contract, it could not also find that
    Mustang wrongfully terminated the contract because a breaching party cannot
    subsequently enforce the contract. Mustang Pipeline Company, Inc. v. Driver Pipeline
    Company, 
    Inc., 134 S.W.3d at 197
    . The Court stated that the “problems could have been
    avoided had the trial court submitted the breach of contract question disjunctively
    accompanied by an appropriate instruction directing the jury to decide who committed
    the first material breach.” Mustang Pipeline Company, Inc. v. Driver Pipeline Company,
    
    Inc., 134 S.W.3d at 200
    . However, the Court found that the evidence established that
    Driver materially breached the contract and that Mustang was discharged from its
    duties under the contract. The Court held that the trial court should have granted
    Mustang’s judgment notwithstanding the verdict. 
    Id. In the
    case before us, the jury was not asked to determine which party was first
    to materially breach the contract. Dudley did not object to the charge or request an
    instruction on who was first to materially breach the contract. Dudley did not seek a
    judgment notwithstanding the verdict to set aside the jury’s finding that Dudley
    materially breached the contract.
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                        Page 5
    There was conflicting evidence on which trees and structures were to be
    removed prior to Dudley beginning work on the project. The record shows that Dudley
    began work on the project before all the trees and structures were removed and before
    Oakwood provided the set aside letter, even though they were required to occur before
    Dudley began work. There is evidence that Oakwood breached the contract by failing
    to timely pay Dudley, and there is evidence Dudley breached the contract by failing to
    timely complete the project. The jury found that both parties materially breached the
    contract and that both parties’ breach was excused. Dudley asserts several breaches by
    Oakwood and contends that the breaches by Oakwood were prior to the breach by
    Dudley. However, the jury’s answers do not indicate which breach alleged by Dudley
    that they found to be material.      We cannot conclude that the evidence is legally
    sufficient to establish that Oakwood materially breached the contract first.     Unlike
    Mustang Pipeline Company, Inc. v. Driver Pipeline Company, we cannot determine based
    upon the record before us that the evidence conclusively establishes that Oakwood
    materially breached the contract first discharging Dudley from performing under the
    contract. We overrule the first issue.
    Excuse
    Dudley also contends that there is no evidence to support the jury’s finding that
    Oakwood’s breach of the contract was excused. The jury was instructed that failure to
    comply is excused:
    a. By the non-occurrence of certain acts or events that must have occurred
    prior to Dudley’s right to immediate performance.
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                         Page 6
    b. By Dudley’s previous failure to comply with a material obligation of the
    same agreement.
    c. If compliance is waived by Dudley.
    “Waiver” is an intentional surrender of a known right or intentional
    conduct inconsistent with claiming the right.
    Again, the jury was not asked to determine which party was the first to materially
    breach the contract. The evidence does not conclusively establish that Oakwood was
    the first to materially breach the contract. Therefore, we cannot conclude that the
    evidence is legally insufficient to support a jury finding that Oakwood’s breach of the
    contract was excused by Dudley’s prior material breach. We overrule the second issue.
    Damages
    In the third issue, Dudley argues that the record conclusively establishes that
    Dudley’s damages include the invoiced amount in the fourth and fifth pay applications.
    Because of our disposition of the first and second issues, we need not address the third
    issue. See TEX. R. APP. P. 47.1
    Liens
    Oakwood brings two issues on appeal as cross-appellant.           Oakwood first
    contends that the evidence at trial conclusively establishes that the mechanic’s and
    materialman’s liens filed by Dudley are fraudulent as a matter of law. The contract
    stated that it was an agreement between Dudley Construction L.L.C and Oakwood
    Custom Homes Group, Ltd.          Mark Dudley testified at trial that he owns several
    companies and does business under each company. Mark Dudley stated that his main
    construction company is Dudley Construction Ltd.            He stated that the contract
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                         Page 7
    erroneously named Dudley Construction “LLC” rather than “Ltd.”             Mark Dudley
    further testified that Dudley Construction Ltd. and RMDG both do construction work.
    Mark Dudley intended to do the project under RMDG construction, but switched the
    job to Dudley Construction Ltd. because of the additional insurance and bonding.
    The jury was asked to determine the following:
    For each of the following liens, did either RMDG Construction L.L.C.
    d/b/a Dudley General Contractors or Dudley Construction Ltd. make,
    present or use a fraudulent lien with the intent that the document be given
    the legal effect of evidencing a valid lien to cause Oakwood Custom
    Homes Group, Ltd. to suffer financial injury?
    March 13, 2006 Affidavit for Mechanic’s & Materialman’s Lien
    Answer “Yes” or “No”__________
    September 15, 2006 Affidavit for Mechanic’s & Materialman’s Lien
    Answer “Yes” or No” __________
    December 15, 2006 Affidavit for Mechanic’s & Materialman’s Lien
    Answer “Yes” or “No” __________
    A lien is “fraudulent” if at the time the lien was filed, the party who filed
    the lien made a material false representation with the lien document, and
    such representation was either known to be false when made or was
    asserted without knowledge of its truth.
    The jury answered “no” to each of the three questions on the liens. Oakwood filed a
    motion for judgment notwithstanding the verdict asking the trial court to set aside the
    jury’s answers on the fraudulent liens, render judgment for Oakwood, and award
    damages.
    The denial of a motion for judgment notwithstanding the verdict is reviewed
    under a no-evidence standard. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 823 (Tex. 2005).
    We credit evidence favoring the jury verdict if reasonable jurors could, and disregard
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                             Page 8
    contrary evidence unless reasonable jurors could not. 
    Id. at 827.
    We will uphold a
    judgment based on the jury's finding if more than a scintilla of competent evidence
    supports it.    Tanner v. Nationwide Mutual Fire Insurance Co., 
    289 S.W.3d 828
    , 830
    (Tex.2009). Therefore, we must decide whether the evidence presented at trial could
    allow reasonable and fair-minded people to reach the verdict under review. 
    Id. Section 12.002
    of the Texas Civil Practice and Remedies Code provides:
    (a) A person may not make, present, or use a document or other record
    with:
    (1) knowledge that the document or other record is a fraudulent court
    record or a fraudulent lien or claim against real or personal property
    or an interest in real or personal property;
    (2) intent that the document or other record be given the same legal
    effect as a court record or document of a court created by or
    established under the constitution or laws of this state or the United
    States or another entity listed in Section 37.01, Penal Code, evidencing
    a valid lien or claim against real or personal property or an interest in
    real or personal property; and
    (3) intent to cause another person to suffer:
    (A) physical injury;
    (B) financial injury; or
    (C) mental anguish or emotional distress.
    …
    (b) A person who violates Subsection (a) or (a-1) is liable to each injured
    person for:
    (1) the greater of:
    (A) $10,000; or
    (B) the actual damages caused by the violation;
    (2) court costs;
    (3) reasonable attorney's fees; and
    (4) exemplary damages in an amount determined by the court.
    (c) A person claiming a lien under Chapter 53, Property Code, is not liable
    under this section for the making, presentation, or use of a document or
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                             Page 9
    other record in connection with the assertion of the claim unless the
    person acts with intent to defraud.
    TEX. CIV. PRAC. & REM. CODE ANN. 12.002 (West Supp. 2013).
    Oakwood claims that the liens were fraudulent because two of the liens were
    filed by RMDG and RMDG did not perform any labor or provide materials to
    Oakwood. Oakwood was billed for the project by RMDG and made payments under
    that billing name. Mark Dudley owns all of the companies involved in the project with
    Oakwood. Mark Dudley testified that the liens were filed under the RMDG name
    because the invoices to Oakwood were in that name. The record does not show that
    Dudley acted with intent to defraud Oakwood in filing the liens under the RMDG
    name.
    Oakwood argues that the liens are fraudulent because they encumber property
    outside the 14.43 acres involved in the project. Mark Dudley agreed that he filed the
    lien on 29 acres of Horse Haven rather than the approximately 14 acres involved in the
    project. Mark Dudley stated that he believed the lien was good for the other properties
    because the work he performed increased the value on other areas of Horse Haven
    Estates. He further stated that he did not intend to harm Oakwood and that he filed the
    liens to secure payment. The jury could have reasonably found that Dudley did not
    intend to defraud Oakwood in filing the lien.
    Oakwood next argues that the liens are fraudulent because they contain an
    inaccurate amount allegedly owed by Oakwood. Oakwood argues that the lien amount
    was $81,860.39 and that the fourth pay application was for the amount of $80,928.85.
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                       Page 10
    Mark Dudley testified that he believes that the amount of $81,860.39 remains unpaid on
    the project. Mark Dudley stated that the higher amount reflects revisions that were
    made at the request of the engineer. The record does not show that the lien was
    fraudulent.   The evidence does not conclusively establish that any of the liens are
    fraudulent as a matter of law. We overrule Oakwood’s first issue. In the second issue,
    Oakwood argues that it is entitled to receive statutory damages under Section 12.002 of
    the Texas Practice and Remedies Code as a matter of law. Because we found that the
    liens were not fraudulent, we need not address the second issue. TEX. R. APP. P. 47.1
    Conclusion
    We affirm the trial court’s judgment.
    AL SCOGGINS
    Justice
    Before Chief Justice Gray,
    Justice Davis, and
    Justice Scoggins
    Affirmed
    Opinion delivered and filed June 5, 2014
    [CV06]
    RMDG Construction, LLC v. Oakwood Custom Homes Group, LTD                         Page 11