Dow Roofing Systems, LLC v. Great Commission Baptist Church and Chamberlin Dallas, LLC F/K/A Chamberlin Dallas, Ltd. D/B/A Chamberlin Roofing and Waterproofing F/K/A Chamberlin Roofing & Waterproofing, Ltd. ( 2017 )


Menu:
  •                          COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-16-00395-CV
    DOW ROOFING SYSTEMS, LLC                             APPELLANT
    V.
    GREAT COMMISSION BAPTIST                             APPELLEES
    CHURCH AND CHAMBERLIN
    DALLAS, LLC F/K/A CHAMBERLIN
    DALLAS, LTD. D/B/A CHAMBERLIN
    ROOFING AND WATERPROOFING
    F/K/A CHAMBERLIN ROOFING &
    WATERPROOFING, LTD.
    ----------
    FROM THE 236TH DISTRICT COURT OF TARRANT COUNTY
    TRIAL COURT NO. 236-269529-13
    ----------
    MEMORANDUM OPINION1
    ----------
    1
    See Tex. R. App. P. 47.4.
    In two issues, Appellant Dow Roofing Systems, LLC appeals from the trial
    court’s denial of its motion to compel arbitration against Appellee Great
    Commission Baptist Church (the Church) and Appellee Chamberlin Dallas, LLC
    f/k/a Chamberlin Dallas, Ltd. d/b/a Chamberlin Roofing And Waterproofing f/k/a
    Chamberlin Roofing & Waterproofing, Ltd. Although the Court is sympathetic to
    the arguments presented—particularly by the Church—that militate against
    arbitration, we are bound by precedent and must reverse under the
    circumstances presented.
    I.    Background
    The parties’ dispute arose from the construction of a building for the
    Church in Fort Worth. Construction began in early 2005 and was substantially
    completed by March 2006.
    The architect’s project manual for the construction required the roof to be
    covered with a thermoplastic polyolefin elastomeric membrane (TPO membrane).
    Chamberlin installed the building’s roof using a TPO membrane manufactured
    and supplied by Dow Roofing’s predecessor, Stevens Roofing Systems, Inc.
    Several years before, Chamberlin had executed an applicator agreement with
    Stevens Roofing (the Applicator Agreement), which authorized Chamberlin to
    install Stevens Roofing products.    The Applicator Agreement contained an
    arbitration provision.
    At the time of construction, Stevens Roofing was a division of JPS
    Elastomerics Corporation.   JPS provided the Church with a limited warranty
    2
    against leaks in the installed roofing system (the Limited Warranty). The Limited
    Warranty had a ten-year term starting with the date of substantial completion and
    the Church’s acceptance of the roofing system.         It included an arbitration
    provision covering “[a]ny controversy or claim arising out of or relating to this
    document, or the breach thereof.” In December 2006, the facilities manager for
    the Church signed the Limited Warranty. After JPS issued the Limited Warranty,
    Dow Roofing bought Stevens Roofing from JPS.
    After the building’s substantial completion, the roof consistently leaked
    during and after periods of rainfall, and over time the leaks became more
    frequent. Indeed, on at least five occasions, the Church requested repairs from
    Dow Roofing under the Limited Warranty.        Dow Roofing responded to each
    request and each time assured the Church that the TPO membrane was in good
    condition. Eventually, after its insurer denied a claim for roof repair because of
    an alleged manufacturing deficiency in the TPO membrane, the Church was
    forced to sue Chamberlin, Dow Roofing, and the builder (not a party to this
    appeal).
    In response to the Church’s lawsuit, Chamberlin filed cross-claims against
    Dow Roofing for contribution, indemnity, and fraud.     In support of its claims,
    Chamberlin alleged that Stevens Roofing inspected and warranted the roofing
    system, that Dow Roofing made warranty repairs to the roof, and that any leaks
    resulted from a defect in the roofing system. Also, Chamberlin pointed out that in
    the Applicator Agreement, Stevens Roofing had provided a warranty against
    3
    defects and had required Chamberlin to allow it to inspect and approve the
    installation of its roofing system.
    Dow Roofing moved to compel arbitration of the Church’s and
    Chamberlin’s claims based on the arbitration provisions in the Limited Warranty
    and the Applicator Agreement, respectively. Neither the Church nor Chamberlin
    filed a response to the motions.
    On March 16, 2015, the trial court granted the motions to compel
    arbitration.   The parties took no action for a year.     On March 16, 2016, the
    Church, having obtained new counsel, moved to set aside the trial court’s
    arbitration order and to allow it to present arguments against arbitration. The trial
    court granted the motion and set aside its March 16, 2015 order compelling
    arbitration.
    The Church then filed a response to Dow Roofing’s motion to compel
    arbitration. In its response, the Church asserted that Dow Roofing had recently
    declared the warranty to be “null and void,” and as a result, the warranty never
    came into existence—and, thus, neither did the arbitration provision. The Church
    further argued that:    (1) the Limited Warranty was illusory; (2) the Church’s
    claims arose before execution of the Limited Warranty, and the arbitration
    provision thus had no application; and (3) the arbitration provision was
    unconscionable.
    Dow Roofing then filed a consolidated amended motion to compel
    arbitration of the Church’s and Chamberlin’s claims against it, addressing the
    4
    Church’s contentions. Again, Chamberlin did not file a response to the renewed
    motion to compel arbitration.
    The trial court denied Dow Roofing’s motion to compel arbitration. Dow
    Roofing now appeals.
    II.    Standard of Review
    We review a trial court’s denial of a motion to compel arbitration for an
    abuse of discretion, but we review whether there is a valid and enforceable
    arbitration agreement de novo.       Brand FX, LLC v. Rhine, 
    458 S.W.3d 195
    ,
    203 (Tex. App.—Fort Worth 2015, no pet.).           If the party seeking to compel
    arbitration proves that a valid arbitration agreement exists, “a strong presumption
    in favor of arbitration arises and the burden shifts to the party resisting arbitration
    to establish a defense to enforcing arbitration.” 
    Id. at 203–04.
    We review the question of whether the party resisting arbitration has
    established a defense to arbitration de novo. 
    Id. at 204.
    However, we give
    deference to the trial court’s determination of any facts relevant to a defense, if
    those determinations are supported by the record.             
    Id. “If an
    arbitration
    agreement is present, the claims are encompassed by the agreement, and the
    party opposing arbitration failed to prove any defense to enforcement, the trial
    court has no discretion but to compel arbitration,” and in that case, the trial
    court’s denial of a motion to compel arbitration is an abuse of discretion. 
    Id. 5 III.
       Analysis
    Dow Roofing challenges the trial court’s denial of its motion to compel
    arbitration as to both Chamberlin and the Church.
    A.    The Trial Court Abused Its Discretion by Denying Arbitration of
    Chamberlin’s Claims.
    In its first issue, Dow Roofing argues that the arbitration provision in the
    Applicator Agreement is enforceable and that Chamberlin’s claims fall within the
    arbitration provision’s scope.
    Chamberlin does not dispute that it executed an agreement containing an
    arbitration provision. Rather, Chamberlin first argues that Dow Roofing failed to
    prove that Chamberlin’s claims fell within the scope of a valid arbitration
    agreement because although the arbitration provision calls for application of the
    American Arbitration Association (AAA) construction rules, it prohibits the
    arbitrator from following those rules.        See American Arbitration Association,
    Construction Industry Arbitration Rules and Mediation Procedures, Rule 9(b)
    (effective July 1, 2015) (AAA construction rules), https://www.adr.org/sites/
    default/files/Construction%20Rules.pdf.       Chamberlin points out that the AAA
    construction rules give the arbitrator the power to determine the validity of a
    contract of which an arbitration provision forms a part, and it contends that these
    rules conflict with the arbitration provision, which prohibits the arbitrator from
    modifying the Applicator Agreement. See 
    id. 6 Chamberlin
    further argues that because the arbitration provision provides
    that the arbitrator has no power to modify the Applicator Agreement or render an
    award that effects or creates a modification, the arbitration provision is
    unconscionable.     Chamberlin contends that the arbitration provision is
    unconscionable because even if the arbitrator determines that terms of the
    Applicator Agreement are unenforceable, the arbitrator may not modify the
    agreement to omit those terms, and the arbitration provision prevents the
    arbitrator from interpreting the agreement in any way contrary to Dow Roofing’s
    interests.
    As for Chamberlin’s argument relating to the scope of the arbitration
    provision, we may not consider it. The arbitration provision requires arbitration
    “in accordance with” the AAA construction rules. This language makes the AAA
    construction rules part of the arbitration provision.   See Schlumberger Tech.
    Corp. v. Baker Hughes Inc., 
    355 S.W.3d 791
    , 803 (Tex. App.—Houston [1st
    Dist.] 2011, no pet.) (holding that such language incorporates the cited AAA rules
    into the arbitration agreement); AAA construction rules, Rule 1(a) (providing that
    the parties shall be deemed to have made the AAA construction rules part of
    their arbitration agreement if they have provided for arbitration under the rules).
    The AAA construction rules give the arbitrator the authority to decide questions
    about the scope of the arbitration provision. AAA construction rules, Rule 9(a).
    Accordingly, Chamberlin must raise any challenges to the scope of the
    agreement in arbitration. See Douglas v. Regions Bank, 
    757 F.3d 460
    , 462 (5th
    7
    Cir. 2014) (“Parties may agree to arbitrate whether a particular claim is subject to
    arbitration,” and “[d]elegation provisions thus normally require an arbitrator to
    decide in the first instance whether a dispute falls within the scope of the
    arbitration provision”).
    As for Chamberlin’s unconscionability argument, it is well-settled that
    “parties can agree to arbitrate ‘gateway’ questions of ‘arbitrability,’ such as
    whether the parties have agreed to arbitrate or whether their agreement covers a
    particular controversy.” Rent-A-Ctr., W., Inc. v. Jackson, 
    561 U.S. 63
    , 68–69,
    
    130 S. Ct. 2772
    , 2777 (2010). In fact, under the AAA construction rules, the
    arbitrator has the power to rule on the validity of the arbitration provision. See
    AAA construction rules, Rule 9(a). When an arbitration provision incorporates
    such a rule and also provides for arbitration of all claims between the parties, the
    arbitration provision evidences a clear and unmistakable delegation of
    arbitrability. Burlington Res. Oil & Gas Co. LP v. San Juan Basin Royalty Tr.,
    
    249 S.W.3d 34
    , 41 (Tex. App.—Houston [1st Dist.] 2007, pet. denied).           The
    language of the arbitration provision in the Applicator Agreement evidences such
    a delegation.    Accordingly, it is the arbitrator that must decide Chamberlin’s
    unconscionability defense.
    In summary, because the parties agreed to the arbitration provision, the
    arbitrator must decide the scope of that provision, and the arbitrator must
    address Chamberlin’s unconscionability defense.        Accordingly, the trial court
    abused its discretion by denying the motion to compel arbitration of Chamberlin’s
    8
    claims. We sustain Dow Roofing’s first issue. Accordingly, we do not address
    Dow Roofing’s remaining arguments under this issue. See Tex. R. App. P. 47.1.
    B.    The Trial Court Abused its Discretion by Denying Arbitration of the
    Church’s Claims.
    Dow Roofing argues in its second issue that the trial court erred by
    declining to compel arbitration of the Church’s claims against Dow Roofing, given
    that the mandatory arbitration provision in the Limited Warranty: (1) is a valid
    and enforceable agreement to arbitrate subject to the Federal Arbitration Act
    (FAA);2 (2) applies to the Church’s claims against Dow Roofing; and (3) is subject
    to no valid defenses or, at least no defenses that should be addressed anywhere
    but arbitration.
    A party resisting arbitration may raise three types of challenges to an
    arbitration provision in a contract. In re Morgan Stanley & Co., Inc., 
    293 S.W.3d 182
    , 185–87 (Tex. 2009).         First, a party may challenge the validity or
    enforceability of a contract containing the arbitration provision. 
    Id. An arbitrator
    must decide the question of whether a contract that meets the requirements for
    contract formation is nevertheless unenforceable. 
    Id. at 185.
    Second, a party
    may challenge the arbitration provision itself.    
    Id. at 187.
       A court, not the
    2
    The Church does not dispute that the FAA applies. See Rapid
    Settlements, Ltd. v. Green, 
    294 S.W.3d 701
    , 705 (Tex. App.—Houston [1st Dist.]
    2009, no pet.) (citation and internal quotation marks omitted) (explaining that the
    FAA applies when the dispute concerns a “contract evidencing a transaction
    involving commerce,” which includes a contract “relating to” interstate
    commerce).
    9
    arbitrator, hears such challenges unless the parties have expressly delegated
    that issue to the arbitrator. 
    Id. Third, a
    party may raise the question of whether
    any contract was ever concluded.         
    Id. A court
    decides challenges to the
    requirements for contract formation.      
    Id. Here, the
    Church raised all three
    challenges in resisting arbitration.
    The arbitration provision in the Limited Warranty expresses the parties’
    intent to arbitrate claims covered by the agreement, and the Church’s building
    manager acknowledged execution of this agreement.              The Church argued,
    however, that despite the parties’ execution of the Limited Warranty, and despite
    Dow Roofing’s performance under the Limited Warranty, no contract between the
    parties ever existed or, alternatively, that any such contract is unenforceable.
    1.     The Arbitrator Must Decide the Effect of the “Null and Void”
    Provision.
    The Church first posits that because Dow Roofing nullified the Limited
    Warranty, no contract containing an arbitration agreement exists. The Church
    contends that “a contract declared ‘null and void’ legally ‘never came into
    existence.’” The Church argues that, consequently, because Dow Roofing has
    declared the Limited Warranty “null and void,” the Limited Warranty never
    existed, and thus neither did the arbitration provision contained in it. We note
    that while the timing and circumstances surrounding Dow Roofing’s actions with
    regard to the Limited Warranty are certainly troubling, it is not for the trial court,
    10
    but for the arbitrator to decide what effect, if any, Dow Roofing’s declaring the
    Limited Warranty null and void has on the Limited Warranty’s validity.
    Under the Limited Warranty’s specific terms, Dow Roofing could declare
    the Limited Warranty “null and void” if, in its discretion, it determined that one of
    three specific events had occurred: (1) the Church had alterations or repairs
    made on the roof without Dow Roofing’s authorization; (2) the Church failed to
    use reasonable care in maintaining the roof; or (3) the Church failed to comply
    with the Limited Warranty’s terms. But an argument relying on this termination
    provision is not a challenge to the contract’s formation because the termination
    provision, on its face, is not a condition precedent to formation. See Sharifi v.
    Steen Auto., LLC, 
    370 S.W.3d 126
    , 143–44 (Tex. App.—Dallas 2012, no pet.) (“If
    there is a condition precedent to the formation of a contract, then no binding
    contract will arise until the specified condition has occurred or been performed.”);
    Bans Props., L.L.C. v. Hous. Auth. of City of Odessa, 
    327 S.W.3d 310
    , 313 (Tex.
    App.—Eastland 2010, no pet.) (“[C]onditions precedent are events that must be
    performed before a right accrues to enforce a contract.”). This provision allows
    Dow Roofing to cancel the Limited Warranty in certain limited circumstances after
    the agreement was entered, but it does not prevent the formation of the
    agreement in the first place. In fact, that Dow Roofing could cancel the Limited
    Warranty presupposes that a valid contract existed that could be cancelled.
    The Church cites two cases that used “null and void” language to describe
    disputed contracts, and the Church relies on them to support its point that the
    11
    Limited Warranty—and thus its arbitration provision—never came into existence.
    Unfortunately, these cases are of no assistance to the Church. In both cases,
    the contract at issue contained conditions precedent to the formation of the
    contract.     See,   e.g.,   Bannum,    Inc.   v.   Mees,   No.   07-12-00458-CV,
    
    2014 WL 2918436
    , at *1 (Tex. App.—Amarillo June 24, 2014, no pet.) (mem. op.)
    (reviewing contract with a provision rendering the contract “null and void” if the
    appellant was not awarded a particular government contract or if it could not
    begin performance); Elijah Ragira/VIP Lodging Grp., Inc. v. VIP Lodging Grp.,
    Inc., 
    301 S.W.3d 747
    , 754 (Tex. App.—El Paso 2009, pet. denied) (reviewing
    enforceability of a contract with unsatisfied conditions precedent). Here, unlike in
    Bannum and Elijah Ragira, the “null and void” provision of the Limited Warranty
    named no events that had to occur before the contract became binding and could
    be enforced. See Cal-Tex Lumber Co. v. Owens Handle Co., 
    989 S.W.2d 802
    ,
    809 (Tex. App.—Tyler 1999, no pet.) (“Courts will not construe a contract
    provision as a condition precedent unless they are compelled to do so by
    language that may be construed in no other way.”). In point of fact, until the filing
    of this lawsuit, both parties acted in conformance with the existence of the
    Limited Warranty—the Church by requesting repairs under the Limited Warranty
    and Dow Roofing by responding to the repair requests.
    The Church also cites Shri Lakshmi Cotsyn Ltd. v. HN Intern. Grp. Inc., No.
    2:12-CV-01614, 
    2013 WL 1222718
    , at *3 (D.N.J. Mar. 25, 2013) (unpublished), in
    support of its argument. The Church is correct that the federal district court
    12
    explained in that case that a “voidable contract is one in which a party has the
    power . . . to disaffirm the agreement,” while “a declaration that a contract is void
    nullifies all aspects of the agreement . . . giving neither party the power to ratify or
    disaffirm its provisions.” 
    Id. (emphasis added).
    However, the New Jersey federal
    court’s holding is inapplicable to the Church’s defense. That case involved a
    challenge to the formation of the contract on the basis that the plaintiff had never
    signed the contract. 
    Id. at *4.
    In other words, the allegation there challenged the
    basic requirements for contract formation, rendering the facts and circumstances
    of Shri Lakshmi wholly distinguishable from this case.           See Harding Co. v.
    Sendero Res., Inc., 
    365 S.W.3d 732
    , 740 (Tex. App.—Texarkana 2012, pet.
    denied) (noting general rule that a person is not a party to a contract the person
    did not sign).
    Because the Church’s defense challenges the continuing validity of the
    Limited Warranty but does not challenge the requirements for formation of a
    contract, it is the arbitrator that must decide the consequences of Dow Roofing’s
    decision to declare the Limited Warranty “null and void.” See Morgan 
    Stanley, 293 S.W.3d at 185
    .
    2.    The Limited Warranty is Not Illusory.
    The Church’s second defense to arbitration is that the Limited Warranty is
    illusory.   The Church argues that because the Limited Warranty gave Dow
    Roofing the ability to unilaterally nullify that agreement in its entirety, the Limited
    13
    Warranty is illusory and, by extension, so is the arbitration provision.3 See J.M.
    Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 230 n.2 (Tex. 2003) (noting that
    courts generally hold that “if a party retains the unilateral, unrestricted right to
    terminate the . . . agreement, it is illusory”). The Church’s argument challenges
    the formation of the Limited Warranty. See In re 24R, Inc., 
    324 S.W.3d 564
    ,
    567 (Tex. 2010) (stating that when illusory promises are all that support a
    purported bilateral contract, there is no contract). Consequently, as explained
    herein, we address the Church’s argument.4 See Morgan 
    Stanley, 293 S.W.3d at 188
    .
    We determine that the Limited Warranty is not illusory simply because Dow
    Roofing could terminate it. Dow Roofing did not have an unrestricted right to
    cancel the Limited Warranty to avoid performance. To the contrary, the Limited
    Warranty specified limited grounds upon which Dow Roofing could, in its
    discretion, cancel it. Further, the parties do not dispute that Dow Roofing made
    repairs to the roof when requested under the Limited Warranty. See Cherokee
    Commc’ns, Inc. v. Skinny’s, Inc., 
    893 S.W.2d 313
    , 316 (Tex. App.—Eastland
    3
    The Church assumes in its brief that the Limited Warranty is a bilateral
    contract. For purposes of addressing its argument, we assume the same.
    4
    The San Antonio Court of Appeals considers illusoriness to be a contract-
    validity defense rather than a contract-formation defense. See Amateur Athletic
    Union of the U.S., Inc. v. Bray, 
    499 S.W.3d 96
    , 103 (Tex. App.—San Antonio
    2016, no pet.). In light of the Church’s position that mutual promises are the only
    consideration supporting the Limited Warranty, we consider its argument to be a
    contract-formation defense. See 
    24R, 324 S.W.3d at 567
    14
    1994, writ denied) (“A contract which provides for its termination at the option of
    one or either of the parties will be enforced if not contrary to equity and good
    conscience” and citing established rule that a party’s performance may constitute
    consideration even if the contract was void when made for lack of mutuality). We
    therefore reject the Church’s argument that the cancellation provision in the
    Limited Warranty rendered it illusory.5
    3.     The Arbitrator Decides Whether the Arbitration Provision Is
    Unconscionable.
    The Church next asserts as it did in the trial court that the arbitration
    provision is both procedurally and substantively unconscionable. This defense is
    a challenge to the arbitration provision itself, which is ordinarily a question for the
    court rather than the arbitrator. See Morgan 
    Stanley, 293 S.W.3d at 185
    . But
    Dow Roofing maintains that in this case, the arbitration provision delegates this
    issue to the arbitrator. We agree.
    As with the Applicator Agreement, the arbitration provision in the Limited
    Warranty requires arbitration in accordance with the AAA construction rules.
    This language makes the AAA construction rules part of the arbitration provision.
    See Schlumberger 
    Tech., 355 S.W.3d at 803
    ; AAA construction rules, Rule 1(a).
    Under both the AAA construction rules currently in effect and those in effect at
    the time the parties executed the Limited Warranty, the arbitrator has “the power
    5
    The Church did not raise a separate argument specifically challenging the
    illusoriness of the arbitration provision itself, so we do not address whether the
    parties delegated that issue to the arbitrator or whether they could have done so.
    15
    to rule on his or her own jurisdiction, including any objections with respect to the
    existence, scope, or validity of the arbitration agreement” (the delegation rule).
    AAA construction rules, Rule 9(a); American Arbitration Association, Construction
    Industry Arbitration Rules and Mediation Procedures, Rule 9(a) (effective
    October 1, 2009–July 1, 2015), https://www.adr.org/ArchiveRules. And like the
    Applicator Agreement, the Limited Warranty’s arbitration provision calls for
    arbitration of any controversy or claim arising out of or relating to the Limited
    Warranty. It does not carve out any category of claims, and it does not include
    only specific categories of claims that the arbitrator must decide. That language,
    combined with the language incorporated from the AAA construction rules
    assigning arbitrability questions to the arbitrator, is a clear and unmistakable
    delegation of arbitrability to the arbitrator. See 
    Burlington, 249 S.W.3d at 41
    .
    The Church relies on Haddock v. Quinn to argue that because the
    arbitration provision does not specify what version of the AAA construction rules
    apply, Dow Roofing has not proven that the parties agreed to submit questions of
    arbitrability to an arbitrator. See 
    287 S.W.3d 158
    , 175 (Tex. App.—Fort Worth
    2009, pet. denied). That case is distinguishable because there, the version of
    the AAA rules in effect at the time the parties executed the arbitration agreement
    differed from the version in effect at the time of the dispute, and the earlier
    version did not contain the delegation rule. 
    Id. The arbitration
    agreement at
    issue in Haddock had been modified several times over the years with no change
    to its language to specify which version of the AAA construction rules applied. 
    Id. 16 This
    court concluded that we could not tell which version the parties intended to
    apply, and we consequently held that “we cannot assume from silence in the
    agreement as to the issue of arbitrability or as to which version of the AAA rules
    is to apply, that the parties intended to incorporate [the delegation rule], which did
    not exist when the arbitration agreement was added.” 
    Id. Here, unlike
    in Haddock, at the time the parties executed the Limited
    Warranty, the AAA construction rules contained the delegation rule, and the
    parties never amended the Limited Warranty after its execution. Further, the
    current AAA construction rules retain the delegation rule. The parties clearly and
    unmistakably intended to incorporate the delegation rule.
    Because the parties delegated arbitrability to the arbitrator, we do not
    decide the Church’s unconscionability argument.
    4.     The Arbitrator Decides the Scope of the Arbitration Provision.
    As a final defense, the Church argues that the Limited Warranty does not
    apply to claims arising before the Limited Warranty’s execution, such as its
    claims for fraud and breach of the implied warranty of merchantability.          The
    Church bases its argument on the arbitration provision’s language requiring
    arbitration of “[a]ny controversy or claim arising out of or relating to this
    document, or breach thereof.” [Emphasis added.] Again, our review is limited
    because the arbitration provision delegates to the arbitrator the determination of
    the arbitration provision’s scope. See 
    Douglas, 757 F.3d at 462
    (noting that
    delegation provisions can require an arbitrator to decide the scope of the
    17
    arbitration provision); AAA construction rules, Rule 9(a).       Accordingly, the
    arbitrator must decide whether any of the Church’s claims do not fall within the
    scope of the arbitration provision.
    Because Dow Roofing established the existence of a valid arbitration
    provision, the Church failed to establish a defense to arbitration, and the
    arbitrator must decide the scope of the arbitration provision and whether the
    arbitration provision is unconscionable, we are compelled to hold, despite our
    strong concerns about Dow Roofing’s action in canceling the Limited Warranty,
    that the trial court abused its discretion by denying Dow Roofing’s motion to
    compel arbitration. Accordingly, we sustain Dow Roofing’s second issue.
    IV.   Conclusion
    Having sustained Dow Roofing’s two issues, we reverse the trial court’s
    order denying arbitration, and we remand this case to the trial court with
    instructions to grant the motion to compel arbitration.
    /s/ Mark T. Pittman
    MARK T. PITTMAN
    JUSTICE
    PANEL: MEIER, SUDDERTH, and PITTMAN, JJ.
    DELIVERED: August 3, 2017
    18