Star Operations, Inc. and Great American Insurance Company of New York v. Dig Tech, Inc. ( 2017 )


Menu:
  •       TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
    NO. 03-15-00423-CV
    Star Operations, Inc. and Great American Insurance Company of New York, Appellants
    v.
    Dig Tech, Inc., Appellee
    FROM THE DISTRICT COURT OF CALDWELL COUNTY, 22ND JUDICIAL DISTRICT
    NO. 12-0-337, HONORABLE TODD A. BLOMERTH, JUDGE PRESIDING
    MEMORANDUM OPINION
    This appeal arises out of a lower-tier subcontract related to a highway-construction
    project. Appellant Star Operations, Inc. was hired as a subcontractor by Central Texas Highway
    Constructors, the design-build contractor for the project, to build infrastructure for the illumination,
    signal, intelligent-transportation, and toll-collection systems as part of the construction of SH 130
    toll-road Segments 5 and 6 southeast of Austin. Appellee Dig Tech, Inc. sued Star and its
    payment-bond surety, appellant Great American Insurance Company of New York, asserting that
    Star had breached an oral contract with Dig Tech. Dig Tech alleged that Star had hired it to perform
    some of the hole-boring work for the installation of electrical conduit needed for Star to complete
    its part of the construction project and that Star did not pay Dig Tech for the work it did. After a jury
    trial, the jury found in Dig Tech’s favor and awarded Dig Tech the amount of its unpaid invoices,
    $228,524, and attorneys’ fees. On appeal, Star and Great American Insurance raise fourteen issues
    challenging the judgment. For the reasons explained below, we will affirm the judgment in part, and
    we will reverse in part on the issue of court costs and remand the cause for further proceedings on
    that issue.
    BACKGROUND
    The Texas Department of Transportation (TxDOT) entered into a facility concession
    agreement (FCA) with SH 130 Concession Company, the developer, for SH 130 Concession to
    finance and perform the construction of SH 130 toll-road Segments 5 and 6 southeast of Austin and
    to grant SH 130 Concession the concession to lease the sections and toll them for 50 years after the
    project’s completion.1 See generally Tex. Transp. Code §§ 223.201-.209 (authorizing TxDOT to
    enter into public-private partnership agreements to facilitate private-sector investment and
    participation in development of state’s transportation system). SH 130 Concession hired Central
    1
    Star asserts that “it was undisputed and uncontroverted that the Project involved the use
    of federal funds.” We note that the record citations provided by Star include a citation to the section
    of TxDOT’s agreement with SH 130 Concession that states “[r]egardless of whether federal credit
    or funds are made available to Facility, Developer shall comply and require its Contractors to
    comply with all federal requirements applicable to transportation projects that receive federal credit
    or funds, including those set forth in Exhibit 8.” (Emphasis added.) The remainder of its record
    citations in support of this point are to Attachment 1 to Exhibit 8, which was attached to each of the
    parties’ individual subcontracts with Central Texas. That portion of the form attachment states:
    “The work herein proposed will be financed in whole or in part with Federal funds, and therefore
    all of the statutes, rules and regulations promulgated by the Federal Government and applicable to
    work financed in whole or in part with Federal funds will apply to such work.” No party has pointed
    us to any evidence in the record of the federal government’s participation in or funding of the project
    outside of these record citations. For purposes of this appeal, we will assume that the project
    received some unknown amount of federal funding because Dig Tech does not challenge
    Star’s assertion.
    2
    Texas Highway Constructors as the design-build contractor on the project. As previously mentioned,
    Central Texas in turn hired Star as a subcontractor to build infrastructure for the illumination, signal,
    intelligent-transportation, and toll-collection systems. Star and Central Texas entered into two
    subcontracting agreements related to this work. As part of those agreements, Central Texas required
    Star to furnish a performance bond and a payment bond for each subcontract. Star’s surety on the
    bonds is Great American. The payment bond at issue here provides that “Star Operations, Inc., as
    principal, . . . and Great American Insurance Company of New York, . . . as surety, . . . are held and
    firmly bound unto CENTRAL TEXAS HIGHWAY CONSTRUCTORS LLC as Obligee . . . for the
    use and benefit of Claimants as herein below defined in the amount of . . . $3,100,000.00 for the
    payment whereof Principal and Surety bind themselves, their heirs, executors, administrators,
    successors and assigns, jointly and severally, firmly by these presents.”2 Central Texas also
    2
    There is no dispute that Dig Tech is a “claimant” as that term is defined in the bond. In
    their arguments about notice of the bond claim, however, Star and Great American allude to the fact
    that Dig Tech’s May 1 notice letter only references one of the payment bonds and one of Star’s
    subcontracts with Central Texas. When Dig Tech had not received payment from Star by late April,
    on April 23, 2012, Dig Tech’s vice-president and owner Mike Furry requested “a copy of the
    contract” between Star and Central Texas and “a copy of your payment bond” from Lana Lewis, the
    president and founder of Star. Furry testified that he never received a copy of the contract from
    Lewis. Later correspondence among the various entities involved in the projects refers to both
    contracts and both bonds. The bond attached to the May 1 notice letter was admitted into evidence
    at trial. The judgment states that Great American “is obligated under the terms of its bond to make
    the payments that Star Operations failed to make,” but does not specify the bond number. Star does
    not assert on appeal that the work performed by Dig Tech related only to one or the other of its
    subcontracts or that funds to pay the judgment are lacking under either bond. Because we have not
    been asked to determine whether both bonds applied to Dig Tech’s work or whether the trial court’s
    award refers to one or both bonds, we express no opinion and make no determination about whether
    the judgment applies to one or both bonds. For simplicity’s sake, throughout this opinion, we will
    refer to the “bond,” not the “bonds.”
    3
    separately hired Dig Tech as a subcontractor responsible for relocating and adjusting
    electric-distribution facilities owned by Bluebonnet Electric Cooperative. The contract at issue in
    this case is an oral lower-tier subcontract that Star later entered into with Dig Tech for some
    hole-boring work for the installation of electrical conduit that Star needed done to complete its part
    of the construction project.3
    Dig Tech completed the requested work and sought payment for it from Star. Dig
    Tech sent Star a letter on March 13, 2012, requesting payment for the invoices that had been
    submitted before that time and copied Central Texas on the letter. After inquiry from Central Texas
    to Star on Friday, March 16, Star informed Central Texas that the invoices were set up to be paid the
    following Tuesday. On April 12, Central Texas’s project-controls manager, Michael Kiehnau,
    emailed Star’s president and founder, Lana Lewis, to inform her that Dig Tech’s vice-president and
    owner, Mike Furry, had called Kiehnau to let him know that Star had not contacted Dig Tech about
    payment, and consequently, Dig Tech would be filing a bond claim. Kiehnau told Lewis, “I urge you
    to resolve this issue immediately.” On April 23, Furry requested that Lewis send him “a copy of the
    contract between Star [O]perations and [Central Texas]. Also, I would like you to provide me with
    a copy of your payment bond.” Furry testified that he never received a copy of the contract from
    Lewis. On May 1, 2012, Dig Tech notified Star, Central Texas, and Great American of Dig Tech’s
    3
    Although Star refers to this contract in its briefing as the “purported oral contract,” Star
    does not challenge the sufficiency of the evidence supporting the jury’s verdict that “Dig Tech and
    Star Operations agree[d] that Dig Tech would conduct boring work for Star Operations, and that Star
    Operations would pay Dig Tech for such boring work.”
    4
    claim via certified mail, return receipt requested, and further notified them that if all invoices were
    not paid in full, Dig Tech would file suit on the bond “on the 91st day after April 4, 2012, the last
    day on which Dig Tech’s work or labor was done or performed.”4 Dig Tech subsequently filed suit
    against Star and Great American, alleging claims for breach of contract (express or implied),
    quantum meruit, and attorneys’ fees.
    After a ten-day trial, the jury found that Dig Tech and Star Operations had an
    agreement that Dig Tech would perform hole-boring work for Star and Star would pay for that work,
    but Star failed to comply with its agreement to pay and its failure to comply was unexcused.5 The
    jury also found that although Dig Tech intentionally interfered with Star’s subcontract with
    design-build contractor Central Texas, Dig Tech did so only because it had a good-faith belief that
    it had a right to threaten garnishment for the work it performed and any harm to Star did not result
    from any malice on the part of Dig Tech. The jury further found that Star, but not Dig Tech, had
    “unclean hands.”
    The jury awarded Dig Tech $228,524 for its unpaid work and also awarded attorneys’
    fees. The final judgment included an award of court costs, “including the cost of deposition
    4
    The bond states: “Principal [Star] and Surety [Great American] hereby jointly and
    severally agree with the Obligee [Central Texas] that every Claimant as herein defined, who has not
    been paid in full before the expiration of a period of ninety (90) days after the date on which the last
    of such Claimant’s work or labor was done or performed, or materials were furnished by such
    Claimant, may sue on this bond for the use of such Claimant, prosecute the suit to final judgment
    of such sum or sums as may be justly due Claimant, and have execution thereon. The Obligee
    [Central Texas] shall not be liable for payment of any costs or expenses of any such suit.”
    5
    The evidence at trial included e-mails stating a quote and proposed terms, start date, and
    projected duration of work, as well as evidence that the work was completed and accepted by Star.
    5
    transcripts and subpoenas necessarily obtained for use in this suit,” pursuant to Texas Rule of Civil
    Procedure 131. The trial court also ordered in the judgment that “Dig Tech substantially complied
    with the notice provisions of the McGregor Act in order to perfect its bond claim against Great
    American Insurance,” and accordingly, Great American “is obligated under the terms of its bond to
    make the payments that Star Operations failed to make.” Star and Great American appeal from
    the judgment.
    ANALYSIS
    Star and Great American challenge the judgment in fourteen issues. Seven issues
    flow from their contention that the trial court should have applied federal law to Dig Tech’s contract
    claim. Issues eight through eleven concern the law related to Dig Tech’s claim against the Great
    American payment bond and whether Dig Tech perfected its claim against the bond. In their twelfth
    issue, Star and Great American contend that the trial court erred by awarding damages to Dig Tech
    without any evidence of Dig Tech’s actual damages as net loss after reduction of income-tax
    payments or unpaid income-tax liability, which they assert is required by Texas Civil Practice and
    Remedies Code Section 18.091. In issue thirteen, they challenge the trial court’s award of attorneys’
    fees to Dig Tech based on their contention that Dig Tech failed to segregate recoverable attorneys’
    fees from unrecoverable attorneys’ fees. In issue fourteen, Star and Great American argue that the
    trial court erred by awarding Dig Tech costs for copies of deposition transcripts as “taxable costs”
    when Dig Tech did not notice or initiate the depositions.
    6
    Application of the Christian doctrine
    The first seven issues are related to Star and Great American’s contention that the trial
    court should have applied a federal-law principle, the Christian doctrine, to Dig Tech’s contract
    claim because the highway project was federally funded. Star and Great American assert that the
    Christian case stands for the proposition that when the subject matter of a contract is governed by
    valid federal regulations, the regulations are incorporated into the contract as a matter of law, even
    if the parties had not agreed to be bound by them. See G. L. Christian & Assocs. v. United States,
    
    312 F.2d 418
    , 424-26 (Ct. Cl. 1963), aff’d on reh’g, 
    320 F.2d 345
    (Ct. Cl. 1963) (denying
    contractor’s breach-of-contract claim when government terminated construction contract for its own
    convenience even though contract lacked termination clause because court concluded that standard
    termination clause required by Armed Service Procurement Regulations must be read into contract).
    According to Star and Great American, applying the Christian doctrine in this case means that Dig
    Tech failed to comply with three conditions precedent. They contend that federal law required Dig
    Tech to obtain a written contract with Star and to obtain approval from TxDOT for the oral contract
    with Star as conditions precedent to formation of an enforceable contract. They further contend that
    federal law required Dig Tech to provide statutorily compliant certified payrolls as a condition
    precedent to any liability arising from Star’s failure to pay Dig Tech, and that the payrolls provided
    by Dig Tech were not statutorily compliant based on errors in the classification or pay rate of
    approximately four employees in a one-week period. Therefore, they argue that the trial court erred
    by refusing to submit jury questions on (1) Dig Tech’s alleged failure to obtain a written contract
    7
    with Star, (2) Dig Tech’s alleged failure to obtain approval from TxDOT for the purported oral
    contract with Star, and (3) Dig Tech’s alleged failure to provide statutorily compliant certified
    payrolls. They also argue that the trial court erred in awarding contract damages to Dig Tech based
    on their contention that Dig Tech’s failure to satisfy these three conditions precedent renders the oral
    agreement that Dig Tech sued upon unenforceable by law. We first consider the effect of the
    Christian doctrine on Dig Tech’s contract claim.
    Under the Christian doctrine, which has been developed in a line of decisions from
    the Federal Circuit, “a mandatory contract clause that expresses a significant or deeply ingrained
    strand of public procurement policy is considered to be included in a contract by operation of law.”
    S.J. Amoroso Constr. Co., Inc. v. United States, 
    12 F.3d 1072
    , 1075 (Fed. Cir. 1993) (emphasis
    added) (citing 
    Christian, 312 F.2d at 424
    , 427). The doctrine “echoes Supreme Court law that the
    United States is neither bound nor estopped by its agents who act beyond their authority or contrary
    to statute and regulations,” and its application “turns not on whether the clause was intentionally or
    inadvertently omitted, but on whether procurement policies are being ‘avoided or evaded
    (deliberately or negligently) by lesser [governmental] officials.’” 
    Id. (quoting Christian,
    320 F.2d
    at 351). “Thus, under the Christian Doctrine a court may insert a clause into a government contract
    by operation of law if that clause is required under applicable federal administrative regulations,”
    so long as the clause “express[es] a significant or deeply ingrained strand of public procurement
    policy.” General Eng’g & Mach. Works v. O’Keefe, 
    991 F.2d 775
    , 779 (Fed. Cir. 1993) (emphasis
    added) (holding that Navy was entitled to reimbursement based on contractor’s failure to maintain
    8
    material-handling charges in separate cost pool as required by regulatory payments clause
    incorporated into contract by operation of law). The Christian doctrine does not allow all mandatory
    contract clauses to be automatically incorporated by operation of law into a contract. 
    Id. The doctrine
    is limited to those mandatory clauses expressing significant public procurement policy and
    to “less fundamental or significant mandatory procurement contract clauses if not written to benefit
    or protect the party seeking incorporation.” 
    Id. at 779-80.
    Star and Great American contend that the Christian doctrine should be applied to
    incorporate into the alleged oral agreement between Star and Dig Tech all applicable federal
    regulations, but most specifically those regulations requiring (1) prior written consent of TxDOT to
    any subcontract, (2) a written contract between Star and Dig Tech, and (3) Dig Tech’s provision of
    statutorily compliant certified payroll. See 23 C.F.R. § 635.116(b) (subcontractor and contractor
    responsibilities related to federally funded highway projects); 29 C.F.R. §§ 3.1-.11 (wage regulations
    for contractors and subcontractors on public building or work financed with federal funds). Star and
    Great American have not argued that these regulations “express a significant or deeply ingrained
    strand of public procurement policy.” See General Eng’g & Mach. 
    Works, 991 F.2d at 779
    . More
    importantly, however, none of the regulations that Star and Great American want to incorporate in
    the Dig Tech contract prescribe mandatory contract clauses like those incorporated into contracts
    under the Christian doctrine. See, e.g., 
    Amoroso, 12 F.3d at 1075
    (applying Christian doctrine to
    construction contract to substitute mandatory clause of Buy American Act applicable to construction
    contracts by operation of law when contract had incorrectly included clause for nonappropriated fund
    9
    supply contracts); 
    Christian, 312 F.2d at 424
    (incorporating standard termination clause that
    regulation required to “be inserted in all fixed-price construction contracts amounting to more
    than $1,000”).
    Section 635.116 of Title 23 establishes requirements for entering into a subcontract
    on a federally funded highway project, but the regulation does not mandate that any specific clause
    be incorporated into the contract:
    The [state transportation department] shall not permit any of the contract work to be
    performed under a subcontract, unless such arrangement has been authorized by the
    [state transportation department] in writing. Prior to authorizing a subcontract, the
    [state transportation department] shall assure that each subcontract is evidenced in
    writing and that it contains all pertinent provisions and requirements of the prime
    contract. The Division Administrator [chief federal highway administration official
    for the particular state] may permit the [state transportation department] to satisfy the
    subcontract assurance requirements by concurrence in a [state transportation
    department] process which requires the contractor to certify that each subcontract
    arrangement will be in the form of a written agreement containing all the
    requirements and pertinent provisions of the prime contract. Prior to the Division
    Administrator’s concurrence, the [state transportation department] must demonstrate
    that it has an acceptable plan for monitoring such certifications.
    23 C.F.R. § 635.116(b). Similarly, Sections 3.3 and 3.4 of Title 29 require contractors and
    subcontractors engaged in construction of any federally funded public work to furnish weekly wage
    statements to the federal or state agency contracting for or financing the work and to keep payroll
    records reflecting the correct classification, rate of pay, hours worked, etc., for each worker, but
    those sections do not mandate the inclusion of any specific clause into the contract or subcontract
    10
    governing the work.6 See generally 29 C.F.R. §§ 3.1-3.10 (prescribing anti-kickback regulations
    under Copeland Act and regulations intended to aid in enforcement of minimum-wage
    requirements); see also 
    id. § 3.11
    (requiring federally funded public-work contracts to expressly bind
    contractors or subcontractors to comply with applicable regulations, but not mandating inclusion of
    specific clause). Star and Great American seek to broaden the reach of the Christian doctrine,
    arguing not only that under the doctrine all applicable federal regulations should be incorporated into
    the subcontract between Dig Tech and Star, but also that those incorporated regulations should be
    read as implied conditions precedent to the formation or performance of the oral subcontract. We
    decline to extend the reach of the Christian doctrine in this manner. Based on this record, we
    conclude that the regulations relied upon by Star and Great American do not require the
    incorporation of any mandatory contract clauses under the Christian doctrine into the oral
    subcontract between Dig Tech and Star.
    Star and Great American also argue, however, that the federal requirements were
    expressly incorporated into any and all contracts on the highway project, and thus would be
    incorporated into any subcontract between Dig Tech and Star. While Star and Great American are
    correct that the federal requirements were expressly incorporated into Central Texas’s subcontracts
    6
    Evidence was admitted at trial that Dig Tech submitted certified payroll records to Star for
    the twenty-six-week period that Dig Tech performed work for Star on the project. Star points to
    evidence in the record that four individuals were either misclassified or paid the wrong amount of
    hourly pay for their classification or both for at least one week that they worked and an instance in
    which two employees were listed incorrectly as being paid straight time when they had worked
    overtime in one week. Dig Tech responds by pointing to evidence in the record that Star never
    reviewed the certified payrolls that were submitted or notified Dig Tech of any compliance issues
    so that Dig Tech could correct them until after Dig Tech filed suit against Star.
    11
    with Star and with Dig Tech, as required by the FCA (the contract between TxDOT and SH 130
    Concession Company),7 the FCA also explicitly provides that those provisions “shall not be
    incorporated by reference in any case” in any lower-tier subcontracts.
    “FCA Exhibit 8—Federal Requirements” is an attachment to Star’s subcontracts with
    Central Texas and to Dig Tech’s contract with Central Texas, and its Attachment 2 (titled “Required
    Contract Provisions Federal-Aid Construction Contracts”) contains the following general provision:
    Except as otherwise provided for in each section, the contractor [Central Texas]
    shall insert in each subcontract all of the stipulations contained in these Required
    Contract Provisions, and further require their inclusion in any lower tier subcontract
    or purchase order that may in turn be made. The Required Contract Provisions shall
    not be incorporated by reference in any case. The prime contractor [Central Texas]
    7
    The FCA provides:
    Developer [SH 130 Concession Company] shall comply and require its contractors
    to comply with all federal requirements applicable to transportation projects that
    receive federal credit or funds, including those set forth in Exhibit 8.
    In FCA Section 10.2, concerning “Responsibility for Work, Contractors and Employees,” the FCA
    further provides that:
    Each Contract shall include terms and conditions sufficient to ensure compliance by
    the Contractor with the requirements of the FCA Documents, and shall include those
    terms that are specifically required by the FCA Documents to be included therein
    including, to the extent applicable, those set forth in Exhibit 8.
    Star’s subcontracts with Central Texas and Dig Tech’s subcontract with Central Texas expressly
    incorporate the entire FCA into those subcontracts:
    Facility Concession Agreement (FCA) is the agreement between the Developer [SH
    130 Concession Company] and the Texas Department of Transportation. The FCA
    and related FCA documents are incorporated into this Subcontract Agreement.
    12
    shall be responsible for compliance by any subcontractor or lower tier subcontractor
    with these Required Contract provisions.8
    (Emphases added.) Attachment 2’s Section VII, “Subletting or Assigning the Contract,” includes
    the following provision:
    No portion of the contract shall be sublet, assigned or otherwise disposed of except
    with the written consent of the SHA [state highway authority] contracting officer
    [defined as TxDOT or its Authorized Representative], or authorized representative,
    and such consent when given shall not be construed to relieve the contractor [defined
    as Design-Build Contractor (Central Texas)] of any responsibility for the fulfillment
    of the contract. Written consent will be given only after the [state highway authority]
    has assured that each subcontract is evidenced in writing and that it contains all
    pertinent provisions and requirements of the prime contract.
    In Section V, “Statements and Payrolls,” Attachment 2 also incorporates by express reference the
    Copeland Act regulations found in 29 C.F.R. pt. 3 and includes the requirement of weekly
    submission of certified payroll statements, as provided in those regulations.
    However, Star’s subcontracts with Central Texas also include the following provision
    concerning lower-tier subcontracts:
    9.4 SUBCONTRACTS. Seller [Star Operations] shall not subcontract any Work
    . . . without the prior written consent of D&C Contractor [Central Texas], which
    consent shall not be unreasonably withheld or delayed. Seller [Star] shall be solely
    responsible for the engagement and management of its Subcontractors in the
    performance of the Work, for the performance of Work by its Subcontractors and for
    all acts or omissions of Subcontractors. Seller shall insure that all Work furnished
    or performed by Subcontractors conforms to the requirements of the Agreement
    Documents. Neither the consent by D&C Contractor, nor anything contained herein,
    8
    Attachment 1 to Exhibit 8 establishes the following definitions for the required contract
    provisions included in Exhibit 8: “‘contractor,’ ‘prime contractor,’ ‘bidder’ or ‘prospective
    primary participant’ . . . shall be construed to mean the Design-Build Contractor or its
    authorized representative.”
    13
    shall create any contractual relationship between any lower tier Subcontractor and
    D&C Contractor. All lower-tier subcontracts must contain the terms and conditions
    that are incorporated in this Agreement.
    No Subcontractor is intended to be or shall be deemed to be a third party beneficiary
    of the Agreement. Each agreement between Seller and any Subcontractor shall be
    in writing, and shall be assignable to D&C Contractor upon the completion or
    termination of the Work. A copy of each such agreement with pricing removed shall
    be provided to D&C Contractor upon request.
    . . . . The Seller agrees that it is fully responsible to the D&C Contractor for the acts
    and omissions of its subcontractors . . . .
    (Emphases added.)
    Construing all of these provisions together, we conclude that the parties’ subcontracts
    with Central Texas expressly contained the federal requirements that were included as terms of the
    FCA. But nothing in the record indicates that the parties intended to incorporate those requirements
    into Star’s oral contract with Dig Tech, and we have concluded that the Christian doctrine does not
    require their wholesale incorporation into that contract. In fact, the federal requirements themselves
    state that “[t]he Required Contract Provisions shall not be incorporated by reference in any case.”
    We note that Section 9.4 of Star’s contract with Central Texas explicitly places responsibility on Star
    for the engagement of any lower-tier subcontractors and the lower-tier subcontractor’s acts and
    omissions. To the extent that Star’s contract with Central Texas required any lower-tier subcontracts
    to be in writing and approved by TxDOT, it was the responsibility of Star, not the lower-tier
    subcontractor engaged by Star, to ensure compliance. In this case, Star seeks to use its own
    noncompliance with its subcontracts with Central Texas as a defense to enforcement of its oral
    contract with Dig Tech.
    14
    In essence, Star seeks to use promises it made to perform in its contract with Central
    Texas to create conditions precedent in Star’s separate contract with Dig Tech. Conditions precedent
    are not favored in the law. When courts construe contracts, “forfeiture by finding a condition
    precedent is to be avoided when another reasonable reading of the contract is possible.” Criswell
    v. European Crossroads Shopping Ctr., Ltd., 
    792 S.W.2d 945
    , 948 (Tex. 1990) (citing
    Schwarz-Jordan, Inc. of Hous. v. Delisle Constr. Co., 
    569 S.W.2d 878
    , 881 (Tex. 1978)). “A
    condition precedent may be either a condition to the formation of a contract or to an obligation to
    perform an existing agreement. Conditions may, therefore, relate either to the formation of contracts
    or to liability under them.” Hohenberg Bros. Co. v. George E. Gibbons & Co., 
    537 S.W.2d 1
    , 3
    (Tex. 1976); see also Rincones v. Windberg, 
    705 S.W.2d 846
    , 848 (Tex. App.—Austin 1986, no
    writ) (distinguishing between condition precedent, which postpones effective date of instrument until
    happening of contingency, and condition subsequent, which refers to future event that excuses
    obligation to perform an already binding contract).
    A condition precedent to formation occurs if the parties to a contract agree that it shall
    not become effective or binding until or unless some specified condition is performed or occurs. See
    Perry v. Little, 
    377 S.W.2d 765
    , 769 (Tex. Civ. App.—Tyler 1964, writ ref’d n.r.e.). “Conditions
    precedent to an obligation to perform are those acts or events, which occur subsequently to the
    making of a contract, that must occur before there is a right to immediate performance and before
    there is a breach of contractual duty.” Hohenberg 
    Bros., 537 S.W.2d at 3
    . When construing written
    contracts, although no particular words are required for the existence of a condition, terms such as
    “if,” “provided that,” or “on condition that,” usually indicate an intent that the provision be a
    condition precedent rather than a promise. 
    Id. To determine
    whether a condition precedent exists,
    15
    we must ascertain the intention of the parties by looking at the whole contract. 
    Criswell, 792 S.W.2d at 948
    .
    Courts look to the communications between the parties, as well as to the acts and
    circumstances surrounding their communications, when determining the existence and terms of an
    oral contract. See Davis v. Chaparro, 
    431 S.W.3d 717
    , 722 (Tex. App.—El Paso 2014, pet. denied)
    (holding evidence supported trial court’s finding of meeting of minds to pay reasonable fee for
    services rendered based on parties’ conversations). Star points to no evidence in the record, and we
    have found no evidence, that indicates the parties intended the agreement between Star and Dig Tech
    to become binding only after it was memorialized in a written contract and approved by TxDOT.
    Star’s allegation that Dig Tech was required to submit statutorily compliant certified payroll to Star
    as a condition precedent to Star’s obligation to pay Dig Tech for its work is likewise not supported
    by the evidence in the record. Although Dig Tech submitted a certified payroll report to Star each
    week during the period that it did work for Star, as required by federal regulations, there is no
    evidence of Star and Dig Tech communicating about making payment conditional on submission of
    statutorily compliant payroll before Dig Tech began its work, and the parties’ actions afterward also
    support the conclusion that the parties had not agreed on such a condition. Star’s human-resources
    and payroll director testified that she did not do anything with Dig Tech’s certified payroll statements
    except electronically store them in a computer file; Star never forwarded the certified payroll
    statements to Central Texas; Star’s president testified that she never reviewed the payroll statements
    before Dig Tech filed suit or discussed any classifications in the payroll statements with her
    employees or Dig Tech; and Star’s president never told Dig Tech that one of the reasons Star refused
    to pay is because of any mistake or error in the payroll statements or provided Dig Tech with an
    16
    opportunity to correct the errors that Star asserts are in some of the certified payroll statements.
    Furthermore, Star’s president admitted that Star refused to pay Dig Tech before she had ever
    reviewed Dig Tech’s certified payroll statements. We conclude that the parties never agreed that
    these three federal requirements should be conditions precedent to their agreement that Dig Tech
    would perform hole-boring work for Star.
    We overrule Star’s first seven issues. The trial court correctly concluded as a matter
    of law that the Christian doctrine did not require the incorporation of the three federal requirements
    propounded by Star into Star’s subcontract with Dig Tech. While those three requirements were
    express provisions of Star’s contracts with Central Texas and Dig Tech’s contracts with Central
    Texas, they were not incorporated into Star’s oral subcontract with Dig Tech. Star and Dig Tech did
    not agree to make them conditions precedent to the formation or enforceability of Star’s subcontract
    with Dig Tech. Accordingly, the trial court did not err by refusing to submit proposed jury questions
    on the lack of a written contract, the lack of TxDOT approval of the oral contract, or Dig Tech’s
    alleged failure to provide statutorily compliant certified payroll statements. Likewise, because the
    three federal requirements were not conditions precedent to the formation of an enforceable contract,
    the trial court did not err by awarding Dig Tech contract damages.
    Dig Tech’s claim against the Great American payment bond
    In issues eight through eleven, Star and Great American challenge the trial court’s
    application of the law to Dig Tech’s claim against the payment bond. Star and Great American
    assert that the federal Miller Act applies to the project, and therefore, federal courts have exclusive
    subject-matter jurisdiction over the bond dispute. Alternatively, if the Texas McGregor Act applies,
    Star and Great American assert that the evidence at trial showed that Dig Tech failed to comply with
    17
    that Act’s notice requirements and thus failed to perfect its bond claim as a matter of law. Star and
    Great American consequently challenge the trial court’s ruling as a matter of law that Dig Tech
    perfected its bond claim, the trial court’s denial of Great American’s motion for instructed verdict
    and of Star and Great American’s motion for judgment notwithstanding the verdict, and the trial
    court’s refusal to submit Great American’s proposed jury questions on whether Dig Tech
    substantially complied with the McGregor Act’s notice requirements.
    Miller Act v. McGregor Act
    We first consider whether the Miller Act applies to Dig Tech’s bond claim.9 The
    Miller Act requires bonds to be issued as follows:
    (b)     Type of bonds required.--Before any contract of more than $100,000 is
    awarded for the construction, alteration, or repair of any public building or
    public work of the Federal Government, a person must furnish to the
    Government the following bonds, which become binding when the contract
    is awarded:
    (1)     Performance bond.--A performance bond with a surety satisfactory
    to the officer awarding the contract, and in an amount the officer
    considers adequate, for the protection of the Government.
    (2)     Payment bond.--A payment bond with a surety satisfactory to the
    officer for the protection of all persons supplying labor and material
    in carrying out the work provided for in the contract for the use of
    each person. The amount of the payment bond shall equal the total
    amount payable by the terms of the contract unless the officer
    awarding the contract determines, in a writing supported by specific
    findings, that a payment bond in that amount is impractical, in which
    case the contracting officer shall set the amount of the payment bond.
    9
    Star and Great American raised this issue in a plea to the jurisdiction, in Great American’s
    motion for directed verdict, and in Star and Great American’s motion for judgment notwithstanding
    the verdict; none of these motions were granted.
    18
    The amount of the payment bond shall not be less than the amount of
    the performance bond.
    40 U.S.C. § 3131(b) (italics added). Article 7 of the contracts between Central Texas and Star
    required Star to provide both a performance bond and a payment bond each in an amount equal to
    the full contract price on forms attached to the contracts. The bond at issue in this case is the
    payment bond issued by Star and Great American on behalf of Central Texas. The “Subcontract
    Labor and Material Payment Bond” that Star and Great American executed is a payment bond
    provided for the use and benefit of claimants who furnish labor or materials required for use in the
    performance of Star’s contract with Central Texas. The bond provides that Star, Great American,
    and Central Texas agree that claimants not timely paid in full may sue on the bond “in a state court
    of competent jurisdiction in and for the county or other political subdivision of the state in which the
    project, or any part thereof, is situated, or in the United States District Court for the district in which
    the project, or any part thereof, is situated, and not elsewhere.”
    Star and Great American argue that the Miller Act requires contractors on “public
    work” projects to provide performance and payment bonds and that this highway project is a public
    work because it is a federally funded project for the purpose of creating a roadway for public use.
    Star relies on a Fifth Circuit case, Continental Casualty Co. v. C.O. Brand, Inc., for the proposition
    that “a ‘public work’ within the Miller Act is ‘any work in which the United States is interested and
    which is done for the public and for which the United States is authorized to expend funds.’”
    
    355 F.2d 969
    , 974 (5th Cir. 1966) (quoting Peterson v. United States ex rel. Marsh Lumber Co.,
    
    119 F.2d 145
    , 147 (6th Cir. 1941)). In Continental Casualty, the court was not considering whether
    to apply either the Miller Act or a state act requiring bonds in a construction project. The issue in
    19
    that case was whether the notice provision of the Miller Act requiring notice only to the prime
    contractor or the dual-notice provision of the Capeheart Military Housing Act requiring notice to any
    two of the prime contractor, any one of the obligees, and the surety should apply in a suit on a
    Capeheart Act bond. 
    Id. at 970.
    In making the statement quoted by Star, the court was disagreeing
    with the Tenth Circuit’s holding that Capeheart Act housing projects are not “public works” within
    the meaning of the Miller Act. 
    Id. at 974.
    In a more recent case deciding whether the Miller Act should apply to a company’s
    bonds issued for various “public-works contracts” entered into with Arizona state and municipal
    entities, including highway construction with funding from the Federal Highway Administration, the
    Ninth Circuit upheld the district court’s determination that the projects were not “public works of
    the United States.” Operating Eng’rs Health & Welfare Trust Fund v. JWJ Contracting Co.,
    
    135 F.3d 671
    , 675-76 (9th Cir. 1998). The court explained that:
    Although there is no clear test for designating a project a “public work of the United
    States,” courts often look to the following as indicia: whether the United States is a
    contracting party, an obligee to the bond, an initiator or ultimate operator of the
    project; whether the work is done on property belonging to the United States; or
    whether the bonds are issued under the Miller Act.10
    10
    Star relies on two cases that it asserts stand for the proposition that the Miller Act applies
    to “public works,” even if the United States does not own the real estate, is not a party to the
    construction contract, and is not an obligee on the bond. See Roth Bros., Inc. v. Ohio Farmers Ins.
    Co., 1:12-CV-0158-JMS-DKL, 
    2012 WL 2120013
    (S.D. Ind. June 11, 2012) (order denying motion
    to dismiss); Sullivan v. Faras-RLS Grp., Ltd., 
    795 F. Supp. 305
    (D. Ariz. 1992). Both are
    distinguishable from the facts in this case. In Sullivan, the project was initiated by the United States
    Postal Service, funded entirely with federal funds through the United States Bureau of Indian Affairs,
    built to Postal Service specifications and federal construction-project standards, “located on a
    ‘federal Indian reservation,’” and leased to the federal government for twenty years. 
    Sullivan, 795 F. Supp. at 306
    . When concluding the Miller Act applied to the post-office project, the court
    distinguished the project at issue from another case in part because the state highway project in the
    other case, like the project at issue in this case, was only partially federally funded, was not built for
    20
    
    Id. at 675.
    The court concluded that all those indicia were absent in the case before it, and in
    addition, that JWJ Contracting as principal and Continental Insurance as its surety were unlikely to
    have issued the bonds in the sum total amount payable under the contract terms as required by state
    law when they could have issued them for half that amount under the terms of the Miller Act then
    in effect. 
    Id. at 675-76.
    Moreover, the court determined that the bonds were not “furnished to the
    United States” or “for the protection of the United States,” as required by the Miller Act. 
    Id. at 676;
    see also 40 U.S.C. § 3131(b).
    In this case, the United States or an agency of the United States or a person acting as
    the agent of the United States did not contract for the work at issue. See United States ex rel. Miller
    v. Mattingly Bridge Co., 
    344 F. Supp. 459
    , 461 (W.D. Ky. 1972) (holding that Miller Act applies
    only in these situations based on its construction of word “contracts” as covering only contracts
    between United States and prime contractor, not contracts to which United States was not a party).
    The bond here was issued on the contract between Star, as subcontractor, and Central Texas, as
    prime contractor. Star does not contend that either of these parties was acting as an agent of the
    United States. In addition, the United States government is not an initiator or ultimate operator of
    the project, and the work was not done on property belonging to the United States. See Operating
    
    Eng’rs, 135 F.3d at 675-76
    . The property is not intended to be leased to any agency of the United
    States government, and “the project [is] to benefit the people of [Texas] and not the general public
    of the United States.” See Sullivan v. Faras-RLS Grp., Ltd., 
    795 F. Supp. 305
    , 307 (D. Ariz. 1992).
    leasing to the United States, and “was to benefit the people of [the state] and not the general public
    of the United States.” 
    Id. at 307.
    Similarly, the bond claim at issue in Roth Brothers involved a
    building project for a building to be leased to the federal government and used for the FBI.
    
    2012 WL 2120013
    , at *1-2.
    21
    Furthermore, the Miller Act specifically requires that the payment bond be furnished to the United
    States government. 40 U.S.C. § 3131(b). The contract between Central Texas and Star required that
    the bond be furnished to Central Texas, and there is no evidence in the record showing that the bond
    at issue was furnished to the United States, rather than Central Texas, or that the United States was
    also an obligee on the bond. See United States ex rel. Tri-State Road Boring, Inc. v. United States
    Fid. & Guar. Co., 
    959 F. Supp. 345
    , 347 (E.D. La. 1996) (holding subcontractor’s payment bond on
    contract for construction of airport control tower was not Miller Act bond because it was not
    furnished to United States). In addition, the form of the bond itself provided that suit may be brought
    in state court or federal court where the project is situated, providing another indication that the
    parties did not intend for the bond to be construed as a Miller Act bond, because federal courts have
    exclusive subject-matter jurisdiction over Miller Act claims. See United States ex rel. Harvey Gulf
    Int’l Marine, Inc. v. Maryland Cas. Co., 
    573 F.2d 245
    , 247 (5th Cir. 1978) (noting federal courts’
    exclusive jurisdiction over Miller Act claims). For all these reasons, we conclude that the bond was
    not issued on a contract governed by the Miller Act.
    We conclude that the trial court correctly decided as a matter of law that the Miller
    Act did not deprive it of subject-matter jurisdiction over Dig Tech’s suit seeking payment on the
    bond. We overrule Star and Great American’s eighth issue.
    Application of the McGregor Act
    Star and Great American argue in the alternative that if the McGregor Act applies to
    Dig Tech’s claim against the bond, the trial court erred by ruling as a matter of law that Dig Tech
    perfected its claim. At trial, evidence was admitted showing that Dig Tech provided notice to Star,
    Central Texas, and Great American of its claim on the payment bond that Central Texas required
    22
    Star to furnish as part of the subcontracts between Central Texas and Star. Star and Great American
    challenge the effectiveness of Dig Tech’s notice to Central Texas and to Great American. At the
    close of Dig Tech’s case, Great American moved for directed verdict on the notice issues, which it
    had previously raised in defendants’ plea to the jurisdiction. Great American argued that Dig Tech
    never gave notice to the “prime contractor,” as that term is defined in the Act, and never gave sworn
    notice to Great American, as required by the Act. The trial court denied Great American’s motion.
    Later in trial, during the charge conference, Dig Tech asked the trial court for an order that “Dig
    Tech has substantially complied with the notice provisions such that [Great American] has notice
    of our bond claim.” The trial judge stated that he was not submitting that issue to the jury and
    “essentially that’s exactly what’s happened here. . . . I’ve agreed not to submit this to the jury as a
    fact question — as a matter of law[,] I’m making that determination . . . .”
    Star and Great American contend that this was error because Dig Tech failed to
    comply in two ways with the Act’s notice provisions. First, they assert that the Act required Dig
    Tech to provide notice to the “prime contractor” of its claim, and that as the Act defines “prime
    contractor,” the prime contractor in this case was SH 130 Concession. See Tex. Gov’t Code
    §§ 2253.001 (defining “prime contractor” as “a person, firm, or corporation that makes a public work
    contract with a governmental entity”), .041 (establishing notice to prime contractor and surety
    required from payment-bond beneficiary for payment claim), .047 (establishing additional notice
    required from payment-bond beneficiary without direct contractual relationship with prime
    contractor). Second, they assert that Dig Tech never provided a sworn statement of account to Great
    American that complied with the requirements of Section 2253.041.
    23
    The Texas Legislature passed the McGregor Act to create a method to ensure that
    subcontractors and suppliers on public-works projects are paid for their labor and materials because
    they generally may not place liens against public buildings or other public works. See Dealers Elec.
    Supply Co. v. Scroggins Constr. Co., 
    292 S.W.3d 650
    , 653 (Tex. 2009); Featherlite Bldg. Prods.
    Corp. v. Constructors Unlimited, Inc., 
    714 S.W.2d 68
    , 69 (Tex. App.—Houston [14th Dist.] 1986,
    writ ref’d n.r.e.); see also City of LaPorte v. Taylor, 
    836 S.W.2d 829
    , 831 (Tex. App.—Houston [1st
    Dist.] 1992, no writ) (explaining that “[g]enerally, in construction contracts, in the absence of an
    express agreement to the contrary, a subcontractor is not in privity with the owner and must look to
    the general contractor alone for payment, while the owner is liable for payment only to the general
    contractor,” but subcontractor’s normal remedy is to assert mechanic’s lien). The Act (1) requires
    a prime contractor who makes a contract with a governmental entity to secure a payment bond from
    a surety and execute it to the governmental entity, (2) allows a subcontractor or supplier to “sue the
    principal and surety, jointly or severally, on the payment bond” for unpaid balances for work and
    materials, and (3) allows for the award of reasonable attorneys’ fees. Tex. Gov’t Code §§ 2253.021
    (mandating that governmental entity making public-work contract with prime contractor must require
    contractor to execute payment and performance bonds to governmental entity), .073 (allowing
    payment-bond beneficiary to sue principal or surety, jointly or severally, on payment bond), .074
    (allowing reasonable and equitable attorneys’ fees); see also United Fire & Cas. Co. v. Boring &
    Tunneling Co. of Am., 
    321 S.W.3d 24
    , 27 (Tex. App.—Houston [1st Dist.] 2010, pet. denied). The
    Act was not intended to set up “technical tricks, traps, and stumbling blocks to the filing of
    legitimate notices of claims,” but “to provide a simple and direct method of giving notice and
    24
    perfecting claims.” Argee Corp. v. Solis, 
    932 S.W.2d 39
    , 52-53 (Tex. App.—Beaumont 1995), rev’d
    on other grounds sub nom. Green Int’l Inc. v. Solis, 
    951 S.W.2d 384
    (Tex. 1997).
    The McGregor Act is remedial in nature and “should be liberally construed to achieve
    its purposes.” Dealers Elec. Supply 
    Co., 292 S.W.3d at 653-54
    (citing 
    Featherlite, 714 S.W.2d at 69
    (The Act “is to be given the most comprehensive and liberal construction possible.”)).
    Consequently, while courts typically find that parties must strictly comply with notification
    deadlines, only substantial compliance is required for other notice provisions. Compare Suretec Ins.
    Co. v. Myrex Indus., 
    232 S.W.3d 811
    , 815-16 (Tex. App.—Beaumont 2007, pet. denied)
    (determining that Code Construction Act did not apply to extend deadline to mail notice to Monday
    when 15th of month falls on Sunday because McGregor Act requires claimants to mail notice on or
    before 15th of month, “a specific and clear deadline”); Commercial Union Ins. Co. v. Spaw-Glass
    Corp., 
    877 S.W.2d 538
    , 540 (Tex. App.—Austin 1994, writ denied) (holding that surety could not
    recover from prime contractor for surety’s payment made to claimants because surety’s payment to
    supplier claimants was not required under McGregor Act when claimants had not notified prime
    contractor of claims before prime contractor released retention payment to subcontractor who did
    not pay suppliers) with e.g., Boring & Tunneling 
    Co., 321 S.W.3d at 28-29
    (holding as matter of law
    that notice lacking notary signature and seal was not deficient when evidence presented that omission
    was clerical error, statement was sworn, corrected statement was sent, and surety had timely actual
    notice); Capitol Indem. Corp. v. Kirby Rest. Equip. & Chem. Supply Co., 
    170 S.W.3d 144
    , 147-48
    (Tex. App.—San Antonio 2005, pet. denied) (holding as matter of law that sworn statement that did
    not precisely comport with statutory language substantially complied with statutory requirements);
    Acme Brick, a Div. of Justin Indus., Inc. v. Temple Assocs., 
    816 S.W.2d 440
    , 441 (Tex. App.—Waco
    25
    1991, writ denied) (holding as matter of law that claimant’s notice with affiant’s signature in
    incorrect place on sworn statement substantially complied with Act even if it was not valid affidavit);
    
    Featherlite, 714 S.W.2d at 69
    -70 (holding as matter of law that exact language of notice provision
    not required in sworn statement in case in which surety and contractor did not dispute that Featherlite
    supplied materials or amount of claim); United States Fid. & Guar. Co. v. Parker Bros. & Co.,
    
    437 S.W.2d 880
    , 881-82 (Tex. Civ. App.—Houston [1st Dist.] 1969, writ ref’d n.r.e.) (holding as
    a matter of law that claimant substantially complied with notice provisions by sending sworn
    statements to prime contractor even though copies sent to surety were unsworn). Substantial
    compliance has been defined as satisfaction of the “essential requirements of a statute” and occurs
    when an actor’s deviation does not seriously impede the legislative purpose of the statutory
    requirements. See Stratton v. Austin Indep. Sch. Dist., 
    8 S.W.3d 26
    , 30 (Tex. App.—Austin 1999,
    no pet.).
    Star and Great American argue that their complaints about Dig Tech’s notice are
    analogous to the issues in cases holding that untimely notification does not substantially comply with
    the McGregor Act. See, e.g., 
    Suretec, 232 S.W.3d at 815-16
    ; Laboratory Design & Equip., Inc.
    v. Brooks Dev. Auth., No. 04-07-00284-CV, 
    2008 WL 36614
    , at *3 (Tex. App.—San Antonio
    Jan. 2, 2008, no pet.) (mem. op.) (holding as matter of law that notice mailed over one year late
    without sworn statement prevented subcontractor from recovering against payment bond). The
    substance of Star and Great American’s issues with Dig Tech’s notice, however, is not that the notice
    was untimely. Instead, they argue that Great American never received the sworn statement required
    to be delivered with notice of the claim and that Dig Tech did not serve the proper party as
    prime contractor.
    26
    We first address Star and Great American’s argument that Great American never
    received the sworn statement required to be delivered with notice of the claim because our
    disposition of that issue aids in our resolution of the other notice issue. Dig Tech’s counsel sent
    Great American a letter via certified mail on May 1, 2012 (with return receipt signed May 7),
    informing Great American that the law firm represented Dig Tech in its claim for unpaid amounts
    due based on labor and materials provided to Star on the SH 130 Segments 5 and 6 project. The
    letter advised Great American that no payments at all had been made to Dig Tech, and accordingly,
    suit would be filed on the bond “on the 91st day after April 4, 2012, the last day on which Dig Tech’s
    work or labor was done or performed, if all invoices have not been paid in full by that time.” The
    letter further advised Great American that all invoices and claims for payment had previously been
    sent to Star and that “the invoices and descriptions of work” were copied and enclosed with the
    letter. Great American does not dispute that the invoices and descriptions were attached to the letter.
    Great American also does not assert that the amount claimed was later materially amended.
    While notice is a substantive condition precedent to a party’s ability to pursue a claim
    on a bond, numerous courts have liberally construed the requirement that written notice of a claim
    “must be accompanied by a sworn statement of account that states in substance: (1) the amount
    claimed is just and correct; and (2) all just and lawful offsets, payments, and credits known to the
    affiant have been allowed.” Tex. Gov’t Code § 2253.041(c) (emphasis added); see also, e.g., Boring
    & Tunneling 
    Co., 321 S.W.3d at 28-29
    (First Court of Appeals); Kirby Rest. 
    Equip., 170 S.W.3d at 147-48
    (Fourth Court of Appeals); Acme 
    Brick, 816 S.W.2d at 441
    (Tenth Court of Appeals);
    
    Featherlite, 714 S.W.2d at 69
    -70 (Fourteenth Court of Appeals); Parker Bros. & 
    Co., 437 S.W.2d at 881-82
    (First Court of Appeals). Dig Tech’s letter indicated that it was presenting a claim for
    27
    “unpaid amounts due” for work completed for Star. This type of language has been deemed
    sufficient to inform the surety in substance that the amount claimed is “just and correct” and that “all
    just and lawful offsets, payments, and credits known to the affiant have been allowed.” See Kirby
    Rest. 
    Equip., 170 S.W.3d at 148
    & n.2. Great American also contends that because no sworn
    statement accompanied the notice, Dig Tech failed to perfect its claim, relying on Laboratory
    Design. See 
    2008 WL 36614
    , at *3 (holding claimant who mailed notice over one year after
    statutory deadline without including sworn statement did not substantially comply with statutory
    requirements). The opinion in that case describes an earlier letter informing the governmental
    authority (acting as surety) of the amount owed, but it does not provide any description of the later
    letter filed over a year after the deadline that the claimant argued substantially complied with the
    statutory requirements. See 
    id. at *1
    (describing June 3, 2004 letter), *3 (identifying letter mailed
    June 15, 2005, as letter relied on to establish notice of claim). Consequently, it is unclear what, if
    any, similarity the notice letter in that case has to the notice letter in this case. In addition, the court
    in Laboratory Design does not appear to have been presented with the issue of actual notice, which
    also makes it distinguishable from the facts here.
    In this case, Dig Tech presented evidence at trial supporting its contention that its
    notice to Great American substantially complied with the McGregor Act and that Great American
    had actual notice of Dig Tech’s claim. Substantial compliance occurs “‘when an actor’s deviation
    from compliance [with the essential requirements of a statute] does not seriously impede the
    legislative purpose of the statute,’ that is, when actual notice of the claims are provided.” Dudley
    Constr., Ltd. v. Act Pipe & Supply, Inc., ___ S.W.3d ___, 06-15-00045-CV, 
    2016 WL 3917211
    , at
    *9 (Tex. App.—Texarkana July 14, 2016, pet. granted) (quoting Boring & Tunneling Co.,
    
    28 321 S.W.3d at 28
    , and holding sufficient evidence to support finding of substantial compliance when
    entity’s former name was used on notices to prime contractor but actual notice was received). In this
    case, Dig Tech’s May 1 letter sent via certified mail to Great American and the May 9 letter from
    Central Texas to Star claimed an amount due based on the invoices included in the claim that was
    substantially the same as the amount Dig Tech sought at trial and was awarded. In addition, two
    other documents admitted at trial support Dig Tech’s claim that Great American had actual notice
    of the claim. The first document is a May 18, 2012 email from Star’s president to a Star employee,
    which states “Anthony - Please forward me any email correspondence you have concerning Dig
    Tech. I need to respond and coordinate with our attorney and surety. Please send today as this has
    been escalated.” (Emphasis added.) The second document is a February 1, 2013 letter from Star’s
    president presenting a formal prompt-payment complaint against Central Texas. In that letter, Star’s
    president states the following: “Dig Tech has asserted NO CLAIMS against [Central Texas]. Dig
    Tech asserted claims against STAR back in May 2012 and filed notice on STAR’S BOND furnished
    for the benefit of [Central Texas]. Star provided payment and performance bonds to [Central Texas]
    for both subcontract agreements . . . . Central Texas has no contractual reason to withhold funds
    claimed by Dig Tech.” (Italics added.)
    The legislative purpose of the McGregor Act “is to protect claimants who supply
    labor and material in the construction of public works, and to provide a simple and direct method
    of giving notice and perfecting claims.” 
    Argee, 932 S.W.2d at 52-53
    . The evident purpose of the
    Act’s requirement that a claimant accompany its written notice of a claim to a surety with a sworn
    statement is to provide the surety with true and accurate information about the amount of the claim,
    so that the surety may prepare to defend against the claim. On this record, Dig Tech’s deviation from
    29
    the Act’s requirement to include a sworn statement has not seriously hindered the legislature’s
    purpose in imposing the sworn-statement requirement because Great American had actual notice of
    true and accurate information about the amount of the claim. See 
    Stratton, 8 S.W.3d at 31
    . Actual
    notice to the surety constitutes substantial compliance with the notice requirements. See Dudley
    Constr., Ltd., ___ S.W.3d ___, 
    2016 WL 3917211
    , at *9.
    Similarly, on this record, we conclude that Dig Tech’s provision of actual notice to
    both Star, the principal and obligor on the bond, and Great American, the surety, constitutes
    substantial compliance with the Act’s requirement that the claimant notify the prime contractor and
    surety. See Tex. Gov’t Code §§ 2253.041, .047. As an initial matter, Star and Great American fail
    to explain why lack of notice to SH 130 Concession should preclude Dig Tech from recovery on the
    bond, when Dig Tech notified the three parties named on the bond—the obligee, Central Texas; the
    principal and obligor, Star; and the surety, Great American. See Redland Ins. Co. v. Southwest
    Stainless, L.P., 
    181 S.W.3d 509
    , 512-13 (Tex. App.—Fort Worth 2005, no pet.) (holding
    subcontractor’s failure to send notice of claim to prime contractor via certified mail did not preclude
    subcontractor from recovery on bond when surety received actual notice that complied with statutory
    requirements); see also Argee 
    Corp., 932 S.W.2d at 53
    (“We do not perceive the legislative purpose
    behind the McGregor Act to be that of creating technical tricks, traps and stumbling blocks to the
    filing of legitimate notices of claims.”).
    Moreover, the only payment bond required under the Act is the bond that the
    governmental entity requires the prime contractor to obtain. Tex. Gov’t Code § 2253.021(a)(2), (c).
    On that bond, the governmental entity is the obligee, while the prime contractor is the principal and
    obligor who is liable and who may be sued jointly and severally with its surety by a payment-bond
    30
    beneficiary if a claim is not paid. In contrast, on the bond at issue in this case, Central Texas is the
    obligee, while Star is the principal and obligor who is liable and who may be sued jointly and
    severally with Great American, its surety, if a claim is not paid. The parties do not dispute that Dig
    Tech is a payment-bond beneficiary of Great American’s bond, which was provided by Star for the
    protection of Cental Texas, the obligee named in the bond, from claims by subcontractors
    and suppliers.
    The McGregor Act contemplates projects that are more simply structured than the
    project at issue here. The Act requires a governmental entity that makes a public-work contract with
    a prime contractor to require the contractor to execute payment and performance bonds in favor of
    the governmental entity before work begins. Tex. Gov’t Code § 2253.021(a). The performance
    bond protects the state or governmental entity, 
    id. § 2253.021(b),
    while the payment bond protects
    “payment bond beneficiaries who have a direct contractual relationship with the prime contractor
    or a subcontractor to supply public work labor or material,” 
    id. § 2253.021(c)(1).
    The Act does not
    mandate that subcontractors on a public-work project obtain payment bonds. In this case, the
    SH 130 Segments 5 and 6 construction project was governed by a comprehensive development
    agreement (CDA) involving multiple contracts, including the Facility Concession Agreement
    entered into by TxDOT and SH 130 Concession Company.11 See generally Tex. Transp. Code
    §§ 223.201-.209 (authorizing TxDOT to enter into CDAs). As part of that agreement, TxDOT
    11
    That agreement explains that TxDOT entered into the CDA with Cintra-Zachry, LP and
    that the CDA contemplated that Cintra-Zachry or one of its affiliates (i.e., SH 130 Concession
    Company) may enter into agreements for development of one or more transportation facilities,
    including SH 130 Segments 5 and 6. Central Texas’s project-controls manager explained at trial
    that his employer was actually Zachry Construction Corporation because Central Texas was a
    special-purpose entity created by Zachry Construction Corporation for the purpose of designing and
    constructing the SH 130 Segments 5 and 6.
    31
    required SH 130 Concession Company to obtain payment and performance bonds. SH 130
    Concession Company, as developer on the project, then entered into an agreement with Central
    Texas for Central Texas to design and build the SH 130 Segments 5 and 6. Central Texas, in turn,
    entered into subcontracts with various subcontractors and suppliers, including Star. Central Texas
    contractually required Star to obtain its own payment and performance bonds. Given the complex
    structure of the CDA and its chain of contracts under which each subcontractor is contractually
    required to obtain its own payment bonds, essentially stepping into the shoes of a prime contractor
    vis-à-vis its lower-tier subcontractor, Dig Tech’s notice to Central Texas, Star, and Great American
    comports with the overarching purpose of the McGregor Act.
    The Act also requires a payment-bond beneficiary to give notice to the prime
    contractor of both unpaid claims and the amount of any retainage applicable to the account that has
    not become due under the terms of the agreement between the prime contractor or a subcontractor
    and the payment-bond beneficiary. 
    Id. § 2253.041(a),
    (d). The purpose of these notice requirements
    is “to protect the prime contractor from incurring double liability,” which could happen in the past
    before the legislature added the notice provisions to the statute, if a contractor paid a subcontractor
    in full and then later found a claim presented against it from someone who dealt only with the
    subcontractor. Spaw-Glass 
    Corp., 877 S.W.2d at 540
    . In this particular case, the record indicates
    that SH 130 Concession was the party who had a contract with the governmental entity (i.e., the
    “prime contractor” as defined by the Act), but that SH 130 Concession bore no risk of liability to Dig
    Tech, much less a risk of double liability. Under the terms of the bond, Star and Great American
    bound themselves to Central Texas as obligee “for the use and benefit of Claimants” in the amount
    of $3.1 million for payment for labor and material required for the performance of Star’s subcontract
    32
    with Central Texas. Both Star, as principal, and Great American, as surety, received actual notice
    of Dig Tech’s claim. See Tex. Gov’t Code § 2253.73 (allowing payment-bond beneficiary to “sue
    the principal or surety, jointly or severally on the payment bond” for unpaid claim); Dealers Elec.
    Supply 
    Co., 292 S.W.3d at 660
    (holding that McGregor Act provides “mandatory and exclusive
    remedy against a surety and obligor on a public-work payment bond” issued under the Act). On this
    record, we must give the statute “the most comprehensive and liberal construction possible” to
    accomplish the remedial purpose of the Act.12 See Dealers Elec. Supply 
    Co., 292 S.W.3d at 659
    (holding McGregor Act’s overarching purpose is “to protect unpaid laborers and materialmen by
    providing them an additional funding source—a payment bond—in the event the prime contractor
    fails to meet its obligations”); 
    Featherlite, 714 S.W.2d at 69
    . Under the circumstances presented
    12
    Although no party has raised this issue, it is questionable whether the McGregor Act
    should apply to the contractually required bond at issue in this case. The only payment bond
    required under the Act is one that a governmental entity requires a prime contractor to execute to the
    governmental entity before beginning the work. Tex. Gov’t Code § 2253.021; see also Johnson
    Serv. Co. v. Cinbar Eng’g Co., 
    409 S.W.2d 471
    , 473 (Tex. Civ. App.—Austin 1966, no writ)
    (holding that subcontractor’s bond to subcontractor was not required under McGregor Act because
    “[i]f the bond in suit is not a bond required by any statute, it is not a statutory bond; it is a
    common law bond” (citing Metropolitan Cas. Ins. Co. of New York v. Texas Sand & Gravel Co.,
    
    68 S.W.2d 551
    , 552 (Tex. Civ. App.—Waco 1934, writ dism’d)). While the McGregor Act is a
    subcontractor or supplier’s “mandatory and exclusive remedy against a surety and obligor on a
    public-work payment bond” issued under the Act, “that exclusivity does not extend beyond suit
    against the [McGregor Act] bond itself” to preclude other statutory or common-law remedies.
    Dealers Elec. Supply Co. v. Scroggins Constr. Co., 
    292 S.W.3d 650
    , 659-60 (Tex. 2009). As stated,
    the parties proceeded at trial and on appeal as if the McGregor Act must apply if the Miller Act does
    not and have not raised the issue of the Act’s applicability. The bond itself contains no specific
    notice requirements, meaning that if the McGregor Act does not apply, Dig Tech was not required
    to provide notice of its claim at any particular time or in any particular form before suit. See Johnson
    Serv. 
    Co., 409 S.W.2d at 474
    (holding that because McGregor Act did not apply, claimant’s case
    against surety must be determined only by bond’s terms, not any McGregor Act provisions). As a
    result, whether we analyze Dig Tech’s claim against the bond under the McGregor Act or as a
    common-law contractual obligation, we conclude the trial court did not err by determining that Dig
    Tech perfected its bond claim against Great American.
    33
    here, Dig Tech’s deviation from the Act’s requirement to provide the prime contractor with notice
    has not seriously hindered the legislature’s purpose because Star as principal and Great American
    as surety on the bond both had actual notice of true and accurate information about the amount of
    the claim before suit was filed against them.13 See Tex. Gov’t Code § 2253.073 (allowing
    payment-bond beneficiary to “sue the principal or surety, jointly or severally, on the payment bond”);
    
    Stratton, 8 S.W.3d at 31
    . Based on the specific facts before us, this actual notice to the parties who
    were liable on the bond constitutes substantial compliance. See also Dudley Constr., Ltd.,
    ___ S.W.3d ___, 
    2016 WL 3917211
    , at *9. Releasing Great American from its liability on the bond
    because SH 130 Concession—who was not a party to the bond and who has no potential liability
    related to the bond—did not receive notice (and does not complain of its lack of notice) of the bond
    claim would be contrary to the purpose of the statutory scheme and create an absurd result. See FKM
    P’ship, Ltd. v. Board of Regents of Univ. of Hous. Sys., 
    255 S.W.3d 619
    , 633 (Tex. 2008) (“We use
    definitions prescribed by the Legislature . . . but otherwise, we construe the statute’s words according
    to their plain and common meaning unless a contrary intention is apparent from the context, or
    unless such a construction leads to absurd results.”).
    Having determined that Dig Tech’s actual notice to Central Texas, Star, and Great
    American substantially complies with the McGregor’s Act notice requirements, we conclude that
    13
    Star and Great American also allude to the fact that Dig Tech only references one of Star’s
    subcontracts and bonds in its May 1 letter, implying that therefore Great American had insufficient
    notice that both subcontracts and bonds were at issue. We note that before sending its notice, Dig
    Tech requested that Star send it a copy of Star’s contract with Central Texas and its bond. Dig
    Tech’s vice-president Mike Furry testified that Star’s president never sent him the contract. It is
    unclear from the record how Dig Tech eventually obtained any information about Star’s contracts
    and bonds, but this information was in Star’s possession, not Dig Tech’s. This is the sort of
    technical trap that the McGregor Act aims to prevent.
    34
    the trial court did not err by ruling that Dig Tech perfected its claim against the bond. Therefore, the
    trial court did not err by denying Great American’s motion for directed verdict and defendants’
    motion for judgment notwithstanding the verdict or by refusing to submit Great American’s
    proposed jury questions on Dig Tech’s substantial compliance with the McGregor Act’s notice
    requirements. We overrule Star and Great American’s issues nine through eleven.
    Application of Texas Civil Practice and Remedies Code Section 18.091
    In their twelfth issue, Star and Great American assert that the trial court erred in
    awarding damages to Dig Tech without any evidence of Dig Tech’s actual damages presented in the
    form of a net loss after reduction for income-tax payments or unpaid income-tax liability, which
    they contend is required by Texas Civil Practice and Remedies Code Section 18.091. Section
    18.091 states:
    § 18.091. Proof of Certain Losses; Jury Instruction
    (a)      Notwithstanding any other law, if any claimant seeks recovery for loss of
    earnings, loss of earning capacity, loss of contributions of a pecuniary value,
    or loss of inheritance, evidence to prove the loss must be presented in the
    form of a net loss after reduction for income tax payments or unpaid tax
    liability pursuant to any federal income tax law.
    (b)      If any claimant seeks recovery for loss of earnings, loss of earning capacity,
    loss of contributions of a pecuniary value, or loss of inheritance, the court
    shall instruct the jury as to whether any recovery for compensatory damages
    sought by the claimant is subject to federal or state income taxes.
    Tex. Civ. Prac. & Rem. Code § 18.091. Star and Great American’s argument focuses on the “loss
    of earnings” category in Subsection (a) and they make no assertion that the other three categories
    would be applicable to this case. Star and Great American reason that since Dig Tech’s invoices
    35
    would result in ordinary revenue, they constitute “earnings” within the meaning of the Internal
    Revenue Code and federal income tax would be duly owed by Dig Tech. Consequently, Star and
    Great American assert that Dig Tech’s failure to present net-of-taxes evidence precludes its recovery
    at trial.
    In support of their assertion that Section 18.091 requires Dig Tech to prove
    net-of-taxes damages in this case, Star and Great American rely on Interconex, Inc. v. Ugarov,
    
    224 S.W.3d 523
    (Tex. App.—Houston [1st Dist.] 2007, no pet.) and Big Bird Tree Service
    v. Gallegos, 
    365 S.W.3d 173
    , 179 (Tex. App.—Dallas 2012, pet. denied). As a preliminary matter,
    neither of those cases stand for the specific proposition advanced by Star and Great American. In
    Interconex, there was a jury trial on the sole issue of damages, following a default judgment on
    liability claims of breach of contract, negligence, and 
    defamation. 224 S.W.3d at 527-28
    . The only
    elements of damages submitted to the jury were past and future lost earnings. 
    Id. at 530.
    On appeal,
    Interconex asserted that the plaintiff failed to comply with the net-of-taxes requirement of Section
    18.091, but the court found that such issue was waived and therefore it did not address the
    net-of-taxes requirement, nor did it expressly or tacitly approve the application of Section 18.091
    in a breach-of-contract case. 
    Id. at 532-33.
    In Gallegos, an employee brought a negligence action against his employer, seeking
    damages for lost earning capacity resulting from an on-the-job 
    injury. 365 S.W.3d at 175
    . The
    employee testified to pre-tax wages without objection and the court’s ultimate analysis came down
    to the sufficiency of the evidence supporting the jury’s award of lost earning capacity in the past and
    in the future. 
    Id. at 178-79.
    The case specifically involved damages resulting from a personal injury
    36
    and there was no discussion of the application of Section 18.091 to other types of damages such as
    contract damages.
    In their briefing, the parties advance differing views of whether Section 18.091
    applies to this type of case. A review of the pleadings, evidence, charge, and judgment in this case
    indicates that this is a breach-of-contract case as opposed to a case involving damages resulting from
    a personal injury rendering a party unable to work.14 Star and Great American argue that the
    language of Section 18.091 is broad and is not expressly limited to personal-injury cases. Dig Tech
    counters that Section 18.091 applies only to personal-injury cases, not contract cases, because
    damages received in a breach-of-contract case are taxable, and application of the section would
    effectively result in double taxation on such contract plaintiffs.
    Our inquiry starts with the language of the statute. Both Subsection (a) and (b)
    contain the phrase “if any claimant seeks recovery for . . .” preceding the types of losses that must
    be presented in the form of net of taxes. This language expressly points the analysis to the type of
    damages sought to be recovered, rather than the type of liability claims (contract or personal injury)
    in question. The liability claims are still relevant, however, because different liability claims result
    in different types of damages. Here, Dig Tech sought recovery of breach-of-contract damages from
    Star based on the amount of the unpaid invoices in question. After the evidence closed, the jury was
    charged with fairly standard breach-of-contract jury questions asking whether Dig Tech and Star had
    an agreement, whether Star failed to comply with the agreement, and whether Star’s failure to
    comply was excused by Dig Tech’s failure to comply with a material obligation of the same
    14
    Dig Tech also requested and received quantum meruit questions included in the charge
    but because the jury answered “Yes” to Question 1 (existence of a contract), the jury was instructed
    not to answer those questions.
    37
    agreement. Ultimately, the jury was asked the damages question conditioned on a finding of Star’s
    failure to comply. Question 4 of the charge (the damages question) reads as follows:
    Question 4
    What sum of money, if any, if paid now in cash, would fairly and reasonably
    compensate Dig Tech for its damages, if any, that resulted from Star Operations’
    failure to comply?
    Consider the following elements of damages, if any, and none other.
    The reasonable value of the work performed by Dig Tech at the time and
    place it was performed.
    Answer in Dollars and Cents, if any.
    Answer: _______________
    Dig Tech did not seek recovery of “loss of earnings” as that phrase is typically used in the Texas
    Pattern Jury Charge and Texas case law, nor was the jury charged to assess such an element of
    damages. The cases on loss of earnings tend to center on the burden of proof and distinguishing loss
    of earnings from loss-of-earning capacity. See Strauss v. Continental Airlines, Inc., 
    67 S.W.3d 428
    ,
    435-43 (Tex. App.—Houston [14th Dist.] 2002, no pet.). However, the parties have cited no cases,
    and we have found none, that allow a corporation such as Dig Tech to recover loss of earnings as a
    measure of damages following the breach of an agreement. The cases in which this measure of
    damages is sought to be recovered are generally personal-injury cases. The Internal Revenue Code
    authorizes compensation received on account of personal injuries or sickness to be excluded from
    gross income. 26 U.S.C. § 104(a)(2). “Presumably, the purpose of [Section 18.091] is to prevent
    a plaintiff from obtaining a windfall by being awarded pretax income on awards that are not subject
    to taxation.” 
    Gallegos, 365 S.W.3d at 179
    .
    38
    In contrast, a corporation such as Dig Tech would be required to report
    breach-of-contract damages from a court award as ordinary income. Internal Revenue Service,
    U.S. Dep’t of the Treasury, Pub. No. 525, Taxable and Nontaxable Income: For Use in Preparing
    2016 Returns 29 (2017), https://www.irs.gov/pub/irs-pdf/p525.pdf. Furthermore, Dig Tech did not
    seek recovery of loss of earnings, and the evidence did not demonstrate that it lost earnings or
    suffered a loss of the opportunity or ability to obtain earnings. Instead, Dig Tech failed to receive
    its benefit of the bargain—payment—after it had performed the work. Based on the facts of the
    business dispute presented by this case, Star and Great American’s assertion would require us to
    stretch the interpretation of Section 18.091 to fit a category of damages to which it seemingly was
    not intended to apply and in which there is no discernable potential for a plaintiff to obtain a windfall
    of tax-free damages. We decline to do so. Accordingly, we overrule Star and Great American’s
    issue twelve.
    Dig Tech’s attorneys’ fees award
    In their thirteenth issue, Star and Great American assert that the trial court erred in
    awarding attorneys’ fees to Dig Tech because Dig Tech failed to segregate recoverable attorneys’
    fees from unrecoverable attorneys’ fees. In support of this argument, Star and Great American cite
    Tony Gullo Motors I, L.P. v. Chapa, 
    212 S.W.3d 299
    (Tex. 2006). However, we need not address
    this issue. Star and Great American offered no objection to the attorneys’ fees question—Question
    No. 9—during the charge conference. Consequently, Star and Great American did not specifically
    object to the attorneys’ fees question on the ground that it failed to segregate recoverable fees from
    unrecoverable fees. See Tex. R. Civ. P. 272, 274. Accordingly, Star and Great American failed to
    preserve error on this issue. See Tex. R. App. P. 33.1; see Young v. Neatherlin, 
    102 S.W.3d 415
    , 420
    39
    (Tex. App.—Houston [14th Dist.] 2003, no pet.) (“[T]he Texas Supreme Court has held that error
    is preserved by an objection to the jury charge on the ground that the charge did not properly
    segregate attorney’s fees.” (citing Stewart Title Guar. Co. v. Sterling, 
    822 S.W.2d 1
    , 10 (Tex. 1991)).
    Taxable costs
    In their fourteenth and final issue, Star and Great American assert that the trial court
    erred in awarding Dig Tech costs for copies of deposition transcripts as “taxable costs” when Dig
    Tech did not notice or initiate the depositions in question. Whether a particular expense is
    recoverable under a statute or rule as court costs is a question of law, which we review de novo.
    Gumpert v. ABF Freight Sys., Inc., 
    312 S.W.3d 237
    , 239 (Tex. App.—Dallas 2010, no pet.). The
    allocation of costs is a matter for the trial court’s discretion and cannot be overturned on appeal
    absent an abuse of discretion. 
    Id. at 239.
    Texas Civil Practice and Remedies Code Section 31.007 provides in pertinent part:
    (b)     A judge of any court may include in any order or judgment all costs,
    including the following:
    (1)     fees of the clerk and service fees due the county;
    (2)     fees of the court reporter for the original of stenographic transcripts
    necessarily obtained for use in the suit;
    (3)     masters, interpreters, and guardians ad litem appointed pursuant to
    these rules and state statutes; and
    (4)     such other costs and fees as may be permitted by these rules and state
    statutes.
    Tex. Civ. Prac. & Rem. Code § 31.007(b). Relevant here is Subsection (b)(2), which allows the
    “fees of the court reporter for the original of stenographic transcripts necessarily obtained for use in
    40
    the suit” to be included as costs awarded in the judgment. The dispute here focuses not on whether
    the seven deposition transcripts in question were necessarily obtained for use in the suit but on
    whether Dig Tech could recover costs for obtaining copies of those deposition transcripts when it
    did not notice or initiate the depositions, and thus it was only paying for the copies, as opposed to
    paying the court reporter’s fee for the original transcript. Section 31.007(b)(2) specifically allows
    recovery of the court reporter’s fee for the original stenographic transcript as a taxable court cost.
    We agree with the reasoning of our sister court in Gumpert. In that case, the court concluded that
    Section 31.007(b) specifically limits recovery of costs to the fees of the court reporter for the original
    of stenographic transcripts necessarily obtained for use in the suit and that because no other statute
    or rule authorizes the recovery of costs to obtain copies of deposition transcripts, it was error to
    award such costs. 
    Id. at 241-42;
    see also Waste Mgmt. of Tex., Inc. v. Texas Disposal Sys. Landfill,
    Inc., No. 03-10-00826-CV, 
    2014 WL 6705741
    , at *4 (Tex. App.—Austin Nov. 14, 2014, no pet.)
    (mem. op.) (following Gumpert and holding that costs for video depositions or copies of depositions
    or transcripts are not recoverable as court costs).
    Similarly in this case, we conclude it was error for the trial court to award the costs
    of obtaining copies of deposition transcripts, and we sustain Star and Great American’s fourteenth
    issue. Accordingly, we will reverse that portion of the trial court’s judgment relating to court costs
    and remand this cause for further proceedings to allow the trial court the opportunity to recalculate
    the taxable costs.
    CONCLUSION
    We reverse that portion of the trial court’s judgment relating to court costs for
    obtaining copies of deposition transcripts, and we remand the case to the trial court for further
    41
    proceedings consistent with this opinion. As to all other trial-court rulings challenged by Star and
    Great American, we affirm.
    __________________________________________
    Cindy Olson Bourland, Justice
    Before Chief Justice Rose, Justices Pemberton and Bourland
    Affirmed in Part; Reversed and Remanded in Part
    Filed: July 27, 2017
    42
    

Document Info

Docket Number: 03-15-00423-CV

Filed Date: 7/27/2017

Precedential Status: Precedential

Modified Date: 8/2/2017

Authorities (33)

G. L. Christian and Associates v. The United States , 320 F.2d 345 ( 1963 )

Peterson v. United States Ex Rel. Marsh Lumber Co. , 119 F.2d 145 ( 1941 )

Commercial Union Ins. Co. v. Spaw-Glass Corp., Inc. , 877 S.W.2d 538 ( 1994 )

United States Fidelity & Guaranty Co. v. Parker Brothers & ... , 1969 Tex. App. LEXIS 2802 ( 1969 )

United States v. Mattingly Bridge Co. , 344 F. Supp. 459 ( 1972 )

United States Ex Rel. Tri-State Road Boring, Inc. v. United ... , 959 F. Supp. 345 ( 1996 )

operating-engineers-health-and-welfare-trust-fund-a-trust-operating , 135 F.3d 671 ( 1998 )

FKM Partnership, Ltd. v. Board of Regents , 51 Tex. Sup. Ct. J. 989 ( 2008 )

Continental Casualty Company v. C. O. Brand, Inc., and ... , 355 F.2d 969 ( 1966 )

Gumpert v. ABF Freight System, Inc. , 2010 Tex. App. LEXIS 3261 ( 2010 )

Dealers Electrical Supply Co. v. Scoggins Construction Co. , 52 Tex. Sup. Ct. J. 1088 ( 2009 )

United Fire & Casualty Co. v. Boring & Tunneling Co. of ... , 321 S.W.3d 24 ( 2010 )

Rincones v. Windberg , 1986 Tex. App. LEXIS 12484 ( 1986 )

Capitol Indemnity Corp. v. Kirby Restaurant Equipment & ... , 2005 Tex. App. LEXIS 4356 ( 2005 )

G. L. Christian and Associates v. The United States , 312 F.2d 418 ( 1963 )

Hohenberg Bros. Co. v. George E. Gibbons & Co. , 19 Tex. Sup. Ct. J. 310 ( 1976 )

united-states-of-america-for-the-use-and-benefit-of-harvey-gulf , 573 F.2d 245 ( 1978 )

Perry v. Little , 1964 Tex. App. LEXIS 2100 ( 1964 )

Metropolitan Casualty Ins. Co. of New York v. Texas Sand & ... , 68 S.W.2d 551 ( 1934 )

Sullivan v. Faras-RLS Group, Ltd. , 795 F. Supp. 305 ( 1992 )

View All Authorities »