Christopher Hall v. Germania Farm Mutual Insurance Association ( 2017 )


Menu:
  •                                    In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-16-00304-CV
    CHRISTOPHER HALL, APPELLANT
    V.
    GERMANIA FARM MUTUAL INSURANCE ASSOCIATION, APPELLEE
    On Appeal from the 181st District Court
    Potter County, Texas
    Trial Court No. 102599-B, Honorable John B. Board, Presiding
    October 13, 2017
    MEMORANDUM OPINION
    Before QUINN, C.J., and CAMPBELL and PIRTLE, JJ.
    This appeal involves property insurance, damage to the insured’s property, the
    insurer’s attempt to adjust the claim, a dispute regarding the quantum of loss derived by
    the adjuster, a lawsuit filed by the insured against the insurer, an appraisal clause, the
    invocation of the appraisal clause by the insurer once suit was filed, an eventual
    appraisal, the purported tender of the appraised loss by the insurer, the doctrine of
    estoppel, and the question of whether any extra-contractual claims of the insured
    survived tender of the appraised amount.
    The dispute comes to us in the setting of a final summary judgment. The insurer,
    Germania Farm Mutual Insurance Association, filed a traditional motion for such relief.
    It believed that payment of the appraised loss erected an insurmountable obstacle to
    the insured’s recovery on not only his breach of contract claims but also his extra-
    contractual statutory and common law tort claims. The trial court agreed and granted
    the motion.   The insured, Christopher Hall, appealed and contended through three
    issues that granting the motion was error.
    One may wonder if the factual circumstances before us comport with those
    contemplated by our Texas Supreme Court in recognizing the legitimacy of insurers’
    decisions to include appraisal clauses in their policies. Though agreeing to purchase an
    insurance policy containing one may have been an “‘injudicious’” decision, according to
    our Supreme Court, the high court nevertheless deemed them enforceable. State Farm
    Lloyds v. Johnson, 
    290 S.W.3d 886
    , 888 (Tex. 2009), quoting Scottish Union & Nat’l
    Ins. Co. v. Clancy, 
    71 Tex. 5
    , 
    8 S.W. 630
    (Tex. 1888). Apparently, they were to serve
    the purpose of avoiding the expense of litigation.        See 
    id. at 894
    (stating that
    “[a]ppraisals require no attorneys, no lawsuits, no pleadings, no subpoenas, and no
    hearings. It would be a rare case in which appraisal could not be completed with less
    time and expense than it would take to file motions contesting it.”). And, to achieve that
    end, completing the appraisal process was “intended to take place before suit [was]
    filed” and be a “condition precedent to suit.” 
    Id. Despite the
    existence of an appraisal
    clause in the policy at bar, no one invoked its terms before suit. Instead, more than two
    years from the time of loss and one year from the date of suit lapsed before Germania
    moved the trial court to compel appraisal.
    2
    Counsel for Hall asserted, at oral argument, that insureds have little incentive to
    seek appraisal under the policy due to the costs inherent in the process and its
    tendency to reduce their recovery. It was also suggested that delaying appraisal and
    ultimate payment of the loss is economically beneficial to the insurance company.
    Given the multiple years of delay, the attorney’s fees, and other litigation costs
    undoubtedly incurred by both litigants atop the appraisal costs, it is doubtful that either
    will reap more monetary benefit than anyone would have if appraisal were invoked soon
    after the dispute arose in 2013.             Humming “I need money, that’s what I want,”1
    sometimes results in “you can’t always get what you want but if you try sometimes you
    might . . . get what you need,”2 or deserve. We reverse.
    Standard of Review
    Being that it filed a traditional motion for summary judgment, Germania had the
    burden to prove the absence of any genuine issue of material fact and its entitlement to
    judgment as a matter of law.          First United Pentecostal Church of Beaumont v. Parker,
    
    514 S.W.3d 214
    , 220 (Tex. 2017); Mad-Mag Dev., L.L.C. v. Cargle, No. 07-16-00132-
    CV, 2017 Tex. App. LEXIS 5891, at *1 (Tex. App.—Amarillo June 26, 2017, no pet.)
    (mem. op.).       In deciding if it carried that burden, we accept as true all evidence
    favorable to the nonmovant (i.e., Hall) and indulge in every reasonable inference and
    resolve all doubts regarding the evidence in the nonmovant’s favor. Cantey Hanger,
    L.L.P. v. Byrd, 
    467 S.W.3d 477
    , 481 (Tex. 2015); Mad-Mag Dev., L.L.C. v. Cargle, 2017
    Tex. App. LEXIS 5891, at *1.             Authority also prevents us from affirming summary
    1
    Due nod to the hit factory of Mr. Gordy’s Motown.
    2
    Due nod to Misters Jagger and Richards.
    3
    judgment on grounds unmentioned in the written motion. State Farm Lloyds v. Page,
    
    315 S.W.3d 525
    , 532 (Tex. 2010).
    Summary Judgment
    The underlying dispute arose from a storm that struck the area in May of 2013. It
    resulted in damage to Hall’s home and other property insured by Germania. A claim
    was made, and an adjuster was assigned to assess the loss. He ultimately valued the
    net claim to be approximately $13,000. In June of 2013, Germania tendered Hall two
    checks totaling $9,700.       The sum was derived after making adjustments for the
    deductible and depreciation.        Hall found the amount unacceptable, after which
    Germania issued Hall another check for about $1,200 in October of 2013.             Hall
    remained unsatisfied.
    Hall engaged his own adjuster to estimate the loss. That person conducted his
    inspection in May of 2014 and valued the loss at about $76,600. Whether this was
    disclosed to Germania is unclear. What is certain, though, is that Hall sued Germania
    by the end of May 2014. The causes of action alleged were 1) breached contract, 2)
    violation of the Texas Prompt Pay Act, 3) violation of chapter 541 of the Texas
    Insurance Code, and 4) violation of the Texas Deceptive Trade Practices Act.
    Germania answered the suit in June of 2014. But not until October of 2014 did
    the insurer move to compel an appraisal under the insurance contract. It made the
    demand after accusing Hall of neglecting his own obligation to complete the process
    before filing suit, even though either party had the right to require it.
    An appraisal ensued. It was finalized on February 12, 2016, when the second of
    the two appraisers signed it. Together, they valued the loss at $31,497, plus change.
    4
    Given that decision, Germania issued a check for $18,566.32 payable to Hall. The
    check was dated February 20, 2016, and apparently sent to the insurer’s attorney. The
    latter then drafted a letter dated February 25, 2016, to counsel for Hall, which letter
    purported to enclose the check. In writing the letter, counsel for Germania mentioned a
    joint motion to dismiss Hall’s suit and conditioned the negotiation of the check upon Hall
    agreeing to dismiss the suit. That is, he told opposing counsel that: “[t]he check is to be
    held in trust and not distributed until dismissal documents have been signed and
    forwarded to our office.” Needless to say, Hall did not agree to that condition.3
    Germania subsequently filed the summary judgment underlying this appeal. It
    contended therein that:
    [a]s Germania invoked the appraisal provision of his Homeowners’ Policy and as
    Germania has complied with the policy terms by paying the award, Plaintiff is
    now estopped from maintaining a breach of contract claim as a matter of law.
    Additionally, Plaintiff has no extra-contractual claims because he has suffered no
    independent injury that would otherwise entitle him to damages and because
    Germania properly handled and timely investigated his claim. Thus, summary
    judgment is warranted and appropriate as to all of Plaintiff’s causes of action.
    The trial court granted the motion thereby denying Hall any recovery. Hall appealed.
    Issue One – Estoppel Defense
    Hall initially contends that the trial court erred in granting summary judgment
    because Germania failed to establish, as a matter of law, essential elements of its
    estoppel defense as a matter of law. The elements were “acceptance [and] timeliness
    of the payment.” We sustain the issue in part.
    As previously mentioned, appraisal clauses found in insurance contracts have
    been deemed enforceable for quite some time. Furthermore, compliance with such
    3
    The evidence of record fails to reveal the status of the check. Whether it eventually was cashed
    is unknown.
    5
    clauses affords the parties to the agreement opportunity to raise estoppel as a means of
    settling debate regarding damages recoverable in a suit for breached contract. That is,
    the “effect of an appraisal award is to estop one party . . . from contesting the issue of
    damages, in a suit on the insurance contract, leaving only the question of liability.”
    Hennessey v. Vanguard Ins. Co., 
    895 S.W.2d 794
    , 797-98 (Tex. App.—Amarillo 1995,
    writ denied); accord Nat’l Sec. Fire & Cas. Co. v. Hurst, __S.W.3d__, __, 2017 Tex.
    App. LEXIS 4664, at *6-7 (Tex. App.—Houston [14th Dist.] May 23, 2017, no pet.)
    (stating the same); Garcia v. State Farm Lloyds, 
    514 S.W.3d 257
    , 264-65 (Tex. App—
    San Antonio 2016, pet. denied) (stating the same).       Yet, estoppel is an affirmative
    defense, and the onus normally falls upon the defendant to assert it. Hennessey v.
    Vanguard Ins. 
    Co., 895 S.W.2d at 797-98
    .
    That the defense was asserted by Germania through its motion for summary
    judgment imposed upon the insurer one other burden; it had to prove its entitlement to
    the defense as a matter of law. Johnson & Johnson Med., Inc. v. Sanchez, 
    924 S.W.2d 925
    , 927 (Tex. 1996) (stating that “[w]hen a party moves for summary judgment based
    upon an affirmative defense, the movant must establish each element of its defense as
    a matter of law”); Bruno Indep. Living Aids v. Yzaguirre, No. 13-15-00408-CV, 2016
    Tex. App. LEXIS 3253, at *5-6 (Tex. App.—Corpus Christi Mar. 31, 2016, no pet.)
    (mem. op.) (stating the same). And, again, under the standard of review, we view the
    evidence touching upon the defense in a manner most favorable to the nonmovant
    (Hall) and resolve against the movant any doubt as to the existence of a genuine issue
    of material fact on the estoppel defense. Garcia v. State Farm 
    Lloyds, 514 S.W.3d at 265
    .
    6
    Estoppel tends to be an amoebic defense available in different settings. It is
    amoebic in a sense because its elements may change depending on the setting. Here,
    the defense arises from contract, as opposed to the common law.            By including a
    provision in the insurance contract relating to appraisal, the parties have effectively
    adopted a procedure for calculating loss and cannot disregard it. Scottish Union & Nat’l
    Ins. Co. v. 
    Clancy, 8 S.W. at 631-32
    . So, where the value of the loss is in dispute and
    the contract provides for the manner of calculating that loss, calculating it in accordance
    with the contract terms generally prevents the parties from asserting the loss to have
    some other value.     In other words, they agreed to be bound to the results of the
    appraisal and, consequently, are estopped from seeking damages based upon some
    other calculation.
    Thus, the terms of the appraisal clause and other relevant contractual provisions
    would logically affect the elements of the ensuing estoppel claim. This is most likely
    why others have said that “[b]ecause courts seek to implement the intention of the
    parties as expressed in the language of a contract, it has long been the rule in
    Texas that an appraisal award made pursuant to the provisions of an insurance
    contract is binding and enforceable,” Floyd Circle Partners, LLC v. Republic Lloyds,
    No. 05-16-00244-CV, 2017 Tex. App. LEXIS 6906, at *18 (Tex. App.—Dallas July 24,
    2017, no pet.) (mem. op.) (emphasis added), and “tender of the full amount owed
    pursuant to the conditions of an appraisal clause is all that is required to estop the
    insured from raising a breach of contract claim.” Nat’l Security Fire & Cas. Co. v. Hurst,
    2017 Tex. App. LEXIS 4664, at *8 (emphasis added).
    7
    Given the aforementioned quotes from Nat’l Security and Floyd Circle, it is clear
    that payment of the loss (or at least tender of payment) as calculated via the appraisal
    clause is elemental to the applicability of estoppel. Indeed, failing to at least tender the
    appraised value hardly denotes compliance with the intent of the parties as expressed
    in their insurance agreement.            Here, though, the pivotal question is not so much
    payment but rather when it was to occur. Hall suggests that Germania had a five-day
    window based on the contract while Germania argues that it need have only been
    timely. We resolve the controversy by turning to the policy and general jurisprudence
    applicable to contracts.
    To be sure, expressly specifying in the policy a time for performance of the
    particular obligation (i.e., payment after appraisal) would render that period controlling.
    If no period was specified, all is not lost. Under that circumstance, we would revert to
    the tenets of the common law relating to agreements. One such tenant provides that
    “where no time of performance is stated in a contract, the law will imply a reasonable
    time.” Moore v. Dilworth, 
    142 Tex. 538
    , 
    179 S.W.2d 940
    , 942 (Tex. 1944); Batjet, Inc. v.
    Jackson, 
    161 S.W.3d 242
    , 246-47 (Tex. App.—Texarkana 2005, no pet.).4
    Like estoppel, the idea of a “reasonable time” is also a bit amoebic, or “relative,”
    as noted by sister courts. Vlasak v. Taxco, Inc., No. 01-16-00191-CV, 2017 Tex. App.
    LEXIS 6337, at *19 (Tex. App.—Houston [1st Dist.] July 11, 2017, no pet.), quoting,
    4
    The court in Moore also said that as a “general rule . . . a contract to pay money, which does not
    specify a date of payment, is enforceable as soon as the contract is made.” Moore v. 
    Dilworth, 179 S.W.2d at 942
    . The latter passage from Moore seems particularly interesting. No other Texas opinion
    could be found reiterating the proposition after Moore, and the only authority cited by the Supreme Court
    to support it was the initial version of the legal encyclopedia American Jurisprudence. While that version
    of the encyclopedia was unavailable, a later one was not. In volume 17 of American Jurisprudence 2d,
    under § 337 of the topic “Contracts,” the writer explained that when the contract fails to specify the date
    of payment, the law deems the amount due and payable when the party fully performs his obligation
    under the contract and nothing remains to be done except paying the amount due. 17 Am. Jur 2d
    Contracts § 337, citing McCandlish v. Estate of Timberlake, 
    497 S.W.2d 191
    , 195-96 (Mo. Ct. App. 1973).
    8
    Chen v. Parkwood Creek Owner’s Ass’n, Inc., No. 05-10-01511-CV, 2012 Tex. App.
    LEXIS 7347 (Tex. App.—Dallas Aug. 30, 2012, no pet.).           For instance, it excludes
    unnecessary delay and “‘denotes such promptitude as the circumstances will allow for
    the action called for by the contract.’” 
    Id. So too
    is it affected by or dependent upon the
    facts and circumstances of the particular case. Allegiance Hillview, L.P. v. Range Tex.
    Prod., LLC, 
    347 S.W.3d 855
    , 869-70 (Tex. App.—Fort Worth 2011, no pet.). This most
    likely is why it normally encompasses a question of fact to be decided by the fact-finder
    based upon the circumstances peculiar to the dispute and contract. 
    Id. (stating that
    the
    question is one of fact). Yet, that rule is subject to change as well when the underlying
    facts are undisputed. In that scenario, whether one performed within a “reasonable
    time” becomes a question of law. 
    Id. With the
    foregoing being said, we turn to the record at bar. The appraisal clause
    found in Section 10, paragraph 10 of the Germania insurance policy stated:
    Appraisal: If you and we fail to agree on the amount of loss, either can
    make a written demand for appraisal. Each will then select an independent
    appraiser, and notify the other of the appraiser’s identity within 20 days of
    receipt of the written demand. The two appraisers will choose an umpire.
    If they cannot agree upon an umpire within 15 days, you or we may
    request that the choice be made by a judge or a district court of a judicial
    district where the loss occurred. The two appraisers will then set the
    amount of loss, stating separately the loss to each item.
    If the appraisers fail to agree they will submit their differences to the
    umpire. An itemized decision agreed to by any two of these three and
    filed with us will set the amount of the loss. Such award shall be binding
    on you and us.
    Each party will pay its own appraiser and bear the other expenses of the
    appraisal and umpire equally.
    (Emphasis in original).   Under paragraph 12 of Section 10 of the same agreement
    appears the following language:
    9
    Loss Payment. We will adjust all losses with you. We will pay you
    unless some other person named in the policy is legally entitled to receive
    payment.
    a. If we notify you that we will pay your claim, or part of your claim, we
    must make payment not later than the 5th business day after we notify
    you.
    b. If payment of your claim or part of your claim requires the performance
    of an act by you, we must make payment not later than the 5th business
    day after the date you perform the act.
    (Emphasis in original). As can be seen, nothing in paragraph 10 specifies any particular
    date by which the loss derived via the appraisal procedure must be paid. Rather, it
    deals with the calculation (not payment) of the loss when the parties cannot agree on its
    monetary value and its wording serves that purpose. On the other hand, payment of
    loss is dealt with in paragraph 12. One reading that provision easily sees that it speaks
    of 1) payment of the loss, 2) the time within which to pay the loss, and 3) when that time
    period begins. The time to pay is within five business days, and when that period
    begins to run is either the date 1) the insurer notifies the insured that some aspect of the
    claim will be paid or 2) the insured performs all acts required of him. Missing from the
    words of paragraph 12 though is language alluding to the appraisal under paragraph
    10.5
    5
    That paragraph 10 and paragraph 12 were intended to cover distinct, as opposed to intertwined,
    matters is further exemplified by two scenarios. For instance, the latter paragraph speaks of paying the
    loss and the time within which to do that. Logically, before Germania could pay or represent that it would
    pay the loss, the loss would have to be valued or calculated. For those who deal in rhetorical questions,
    how could it agree to pay a particular monetary loss if it had yet to determine what that monetary loss
    was? And, if the parties were unable to agree on the value, appraisal is the means for settling the
    controversy. So, conceptually, the appraisal could possibly happen before the insurer represents that it
    would pay any part of the claim or loss and thereby triggers the time within which to pay. On the other
    hand, if the insurer had represented to pay at least part of the claim, like it did here, then it had five days
    to do so. But what if the parties came to disagree about the amount of the loss it calculated and
    incorporated into the ensuing check? In that situation, the insurer had the contractual right to demand an
    appraisal under paragraph 10. Pursuing an appraisal with its attendant time delays related to each party
    selecting appraisers, conducting dual appraisals, the appraisers selecting an umpire if the appraised
    sums differed, a court selecting an umpire if the appraisers could not agree on one, and the umpire
    10
    Nor do we find mention of when to pay after the appraisal in any other part of the
    insurance contract. Ways for interjecting such terminology into the policy were offered
    us. Yet, they involve rewriting parts of the agreement that, from their existing context
    and words, fail to evince that those parts were ever intended to designate when
    payment after appraisal was to be made.                 They would also obligate us to create
    language explaining whether payment after appraisal meant such things as 1) payment
    after each appraiser signed the final calculation, 2) payment after the final calculation
    was sent by the appraisers to the insurer, or 3) payment after the insurer receives the
    appraisal to which it agreed to be bound. None of those topics are covered in the
    existing agreement.
    Simply put, we cannot “rewrite . . . the contract merely because . . . one [or both]
    of the parties comes to dislike its provisions or thinks that something else is needed in
    it.”    Cross Timbers Oil Co. v. Exxon Corp., 
    22 S.W.3d 24
    , 26-27 (Tex. App.—Amarillo
    2000, no pet.). And, we make no effort to violate that prohibition here. The parties are
    left to their agreement, and their agreement says nothing about when payment is to be
    made after appraisal under paragraph 10. So, they are left to live with the common law
    rule.     That means Germania had a reasonable time to pay once the appraisal was
    completed.       Whether it complied with that edict depended on the facts and
    circumstances of the case, excluding “unnecessary delay” while considering such
    “promptitude as the circumstances will allow for the action called for by the contract.”
    selecting the final appraisal amount hardly suggests that the procedure could be accomplished within five
    days of the date Germania said it would pay part of the claim. So, the appraisal process would seem to
    be a circumstance that extended or otherwise altered the time periods specified in paragraph 12. Yet,
    both scenarios illustrate that paragraph10 does not dictate the time of payment (or even of appraisal) and
    paragraph 12 with its time limits does not necessarily apply when a party demands an appraisal.
    11
    The undisputed facts and circumstances appearing of record included 1) loss
    being initially appraised by an adjuster on behalf of Germania, 2) Hall deeming the
    amount of the appraisal deficient, 3) the eventual appraisal of the loss under paragraph
    10, 4) the appraisal being finalized by February 12, 2016, 5) Germania receiving the
    appraisal on February 15, 2016, 6) Germania issuing a subsequent check to Hall ten
    days later on February 24, 2016, and 7) counsel for Germania receiving the check and
    drafting a letter dated February 25, 2016, mentioning the check and the terms of its
    negotiation. Yet, we could not find evidence of the date on which the letter and check
    were actually sent to Hall or his attorney.6 Nor did we find evidence of the check being
    received by Hall or his attorney, the date of receipt, or the negotiation of the check by
    Hall or his attorney. We further note that, though Germania agreed (in the contract) to
    be bound by the appraisal award, tender of the check encompassing that award was
    subject to conditions.       The effect of appending conditions to payment despite the
    language in the contract could make one question whether Germania intended to delay
    or actually delayed payment while the conditions it imposed were met.
    We mention one other potential circumstance and it relates to the time periods in
    paragraph 12. While those periods do not specify when payment after appraisal was to
    be made, they nevertheless evince a joint intent that payment should occur rather
    quickly. Five days is not a lot of time. Furthermore, Germania previously had agreed
    not only to pay the claim but also to be bound by the appraisal award. Whether the
    eleven-day period between Germania receiving the appraisal award and sending the
    6
    Germania alleged in its motion for summary judgment that the check was mailed to Hall’s
    attorney on the day the letter was written. Yet, the allegation was not accompanied with supporting
    reference to any document or other evidence. Additionally, our own review of the record failed to uncover
    such supporting evidence.
    12
    check to its attorney comports with the intent underlying paragraph 12 is reasonably
    debatable.   Whether counsel’s effort to condition Hall’s ability to cash the check
    comports with the intent underlying paragraph 12 is also reasonably debatable. The
    latter seems especially true since Germania had agreed previously to pay the claim and
    be bound by the appraisal award. This, of course, assumes counsel actually sent the
    letter and check on February 25th.
    In short, the evidence of record coupled with the missing information created
    material issues of fact. This prevented the trial court from determining as a matter of
    law that Germania paid the appraisal award within a reasonable time. Or, at the very
    least, pertinent facts missing from the record prevent us from holding that the trial court
    correctly found, as a matter of law, that Germania paid the award within a reasonable
    time after the appraisal. Being unable to so hold and because the defense of estoppel
    was dependent upon proof of payment within a reasonable time, we must conclude that
    Germania failed to establish, as a matter of law, the defense. Consequently, it did not
    prove, as a matter of law, its entitlement to summary judgment on the claims of
    breached contract. So, again, we sustain issue one.
    Issue Two – Extra-Contractual Claims
    Hall next argues that the trial court erred in granting summary judgment favorable
    to Germania on his extra-contractual claims. We sustain the issue as well.
    Germania averred in its motion for summary judgment that without a breach of
    contact claim, Hall had no extra-contractual causes of action sounding in common law
    or statutory tort. That is, Germania alleged that the viability of Hall’s extra-contractual
    claims was directly related to the viability of his claims for breached contract. Because
    13
    it established that Hall was estopped from pursuing the contract claims, he could not
    pursue the others, according to the insurer. However, it did not prove its entitlement to
    summary judgment on the defense of estoppel and, therefore, the breach of contract
    claims. Thus, the foundation underlying Germania’s argument for summary judgment
    on those extra-contractual claims is non-existent.
    We reverse the summary judgment and remand the cause for further
    proceedings.
    Brian Quinn
    Chief Justice
    14