Charles Griffin Custom Ready-Built Homes, Inc. v. Brandon Dieringer and Laura Dieringer ( 2018 )


Menu:
  •                                     In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    ________________________
    No. 07-16-00341-CV
    ________________________
    CHARLES GRIFFIN CUSTOM READY-BUILT HOMES, INC., APPELLANT
    V.
    BRANDON DIERINGER AND LAURA DIERINGER, APPELLEES
    On Appeal from the 237th District Court
    Lubbock County, Texas
    Trial Court No. 2014-511,371; Honorable Les Hatch, Presiding
    May 29, 2018
    MEMORANDUM OPINION
    Before QUINN, C.J., and CAMPBELL and PIRTLE, JJ.
    This appeal arises from a dispute between Appellant, Charles Griffin Custom
    Ready-Built Homes, Inc. (hereinafter “Griffin”), and Appellees, Brandon Dieringer and
    Laura Dieringer, concerning a contract whereby Griffin agreed to construct and deliver to
    the Dieringers a ready-built home. Griffin originally filed suit alleging the Dieringers failed
    to pay certain contractual sums due and owing and the Dieringers asserted counterclaims
    for breach of contract and for claims under the Texas Deceptive Trade Practices Act
    based on negligent misrepresentation, breach of an implied warranty of habitability, and
    breach of an implied warranty of good and workmanlike construction. Following a bench
    trial, the trial court entered a judgment in favor of Griffin for $45,759.21.
    Asserting two issues, Griffin maintains the trial court erred by not awarding it
    recovery of (1) its reasonable and necessary attorney’s fees and (2) an “occupancy fee”
    specified in the contract. By a cross-appeal, the Dieringers contend they were the
    “prevailing party” and the trial court erred in not awarding them recovery of attorney’s fees
    and costs. We affirm.
    BACKGROUND
    The Dieringers contracted with Griffin to purchase a custom, ready-built home that
    would be partially constructed at Griffin’s site in Lubbock County and then transported to
    the Dieringers property in Glasscock County, Texas. The contract provided, in relevant
    part, that the Dieringers would “close” on the agreement within ten days after the house
    was completed on location and that they would not move into the house until the balance
    was paid in full. The contract also provided that the Dieringers would pay Griffin $40.00
    per day for any period of occupancy prior to final payment. The contract further provided
    that in the event of non-payment, Griffin would be entitled to recovery of interest at the
    rate of 12 percent on any amounts owed, together with reimbursement of “any legal
    expenses needed to enforce payment of the contract in full after ten days.”
    Work on the home at Griffin’s site was completed in November 2013. At the time,
    the Dieringers performed a walk-through of the home and tendered the progress payment
    due on “completion on the Seller’s site.” The home was then delivered and assembly of
    the two pre-constructed pieces began on approximately November 22, 2013.
    2
    Subsequent to assembly of the home, Griffin subcontractors made numerous trips to the
    property to complete the construction of porches and final touch-up work. When the work
    was finally complete, Lyndall Hurst, Griffin’s owner, met with the Dieringers and agreed
    on the final amount owed. Subsequent to that agreement, the Dieringers moved into the
    home but did not make the final payment. Griffin filed suit for breach of contract on May
    9, 2014, and the Dieringers subsequently filed their counterclaims. The cause proceeded
    to a bench trial on May 9, 2016.
    Hurst testified at trial that there were no structural, foundational, or non-cosmetic
    defects in the home, and he claimed that all work and services Griffin agreed to provide
    had been completely performed. Specifically, he testified that he had fixed everything the
    Dieringers had brought to his attention and he was unaware of any additional concerns
    or problems. In contrast, the Dieringers maintained that there were additional items that
    needed repair, including roof repairs, rebricking, door repairs, texture and paint repairs,
    and carpet repairs. They also maintained that certain final inspections were lacking.
    Upon closing, the Dieringers nonsuited their causes of action against Griffin for negligent
    misrepresentation and for all claims under the Texas Deceptive Trade Practices Act.
    On July 1, 2016, the trial court entered judgment that Griffin recover from the
    Dieringers the sum of $45,759.21. Both parties subsequently requested findings of fact
    and conclusions of law. In its Findings of Fact and Conclusions of Law, the trial court
    found that both parties had breached the contract and, as such, neither party was a
    “prevailing party” for purposes of an award of attorney’s fees. The trial court further
    concluded that Griffin’s breach was not material, that it had substantially performed the
    3
    terms of the contract, and that it was entitled to a judgment in the sum of $45,759.27,1
    after all offsets, payments, and credits. The trial court also found that Griffin was not
    entitled to recover the contractually agreed-upon occupancy fees because the Dieringers
    were excused from performance by Griffin’s demand for payment in full without credit for
    reasonable and necessary repairs.
    On appeal, Griffin contends the trial court erred in not awarding it recovery of
    contractual occupancy fees, its reasonable and necessary attorney’s fees, and costs. By
    way of cross-appeal, the Dieringers contend the trial court erred by entering a judgment
    in favor of Griffin because it never pled nor proved a claim based on substantial
    performance and the issue was not tried by consent. Alternatively, the Dieringers contend
    the evidence is legally and factually insufficient to establish the required elements of
    substantial performance.
    SUBSTANTIAL PERFORMANCE
    When a contractor has substantially performed a building contract, he is entitled to
    recover the full contract price less the cost of remedying non-material defects that are
    remedial. Vance v. My Apartment Steak House, 
    677 S.W.2d 480
    , 481 (Tex. 1984) (citing
    Atkinson v. Jackson Bros., 
    270 S.W. 848
    , 850 (Tex. Comm’n App. 1925)). In those
    instances where a contract has not been fully performed, substantial performance is
    regarded as a condition precedent to the right to sue on that contract. Atkinson, 
    270 S.W. 1
     In its Findings of Fact and Conclusions of Law, the trial court concluded that the amount owed to
    Griffin by the Dieringers is the contract amount of $384,308.69 (including overages), minus $75,784.26
    incurred by the Dieringers for reasonable and necessary repairs, minus the cost of the angle iron of $383.16,
    minus payments made of $279,801.00, for a total of $28,340.27. The Dieringers also owe Griffin sales tax
    it paid the State in the amount of $7,525.86 for a total of $35,866.13 and contracted interest of 12 percent
    on that amount from March 4, 2014 to date of judgment in the amount of $9,893.14, for a grand total of
    $45,759.27. The trial court further acknowledged that there was a $.06 difference between its findings and
    the actual judgment award of $45,759.21. We consider this discrepancy to be de minimus for purposes of
    any reformation.
    4
    at 850; RAJ Partners, Ltd. v. Darco Constr. Corp., 
    217 S.W.3d 638
    , 643 (Tex. App.—
    Amarillo 2006, no pet.); Carr v. Norstok Bldg. Systems, Inc., 
    767 S.W.2d 936
    , 940 (Tex.
    App.—Beaumont 1986, no writ). Usually, the doctrine of substantial performance comes
    into play when both parties to a construction contract are alleged to have breached the
    contract in question—the contractor with respect to minor (non-material) defects, and the
    owner with respect to final payment of sums due.
    In Vance, the Texas Supreme Court acknowledged Atkinson as correctly stating
    that “the doctrine of substantial performance is an equitable doctrine that was adopted to
    allow a contractor who has substantially completed a construction contract to sue on the
    contract rather than being relegated to his cause of action for quantum meruit.” 
    Vance, 677 S.W.2d at 482
    . By definition, this doctrine recognizes that the contractor has not
    totally fulfilled his obligations under the construction contract and is, therefore, technically
    in breach of contract. 
    Id. In such
    cases, to allow for this lack of full performance, “the
    amount recoverable by the contractor is the contract price, less the reasonable cost of
    remedying the defects or omissions in such a way as to make the building conform to the
    contract.” 
    Id. (quoting Atkinson,
    270 S.W. at 851). It is the burden of the contractor to
    plead and prove his entitlement to recovery under a theory of substantial performance.
    
    Carr, 767 S.W.2d at 940
    .
    ANALYSIS
    Here, the Dieringers contend the theory of substantial performance was neither
    supported by Griffin’s pleadings nor tried by consent. We disagree. As previously stated,
    substantial performance is considered to be a condition precedent to the right to bring suit
    on a construction contract. Therefore, Griffin’s breach of contract pleadings supports its
    claim whether based upon substantial compliance or complete performance.
    5
    Furthermore, when issues not raised by the pleadings are tried by consent (either
    express or implied) they are to be treated in all respects as if they had been raised in the
    pleadings. See TEX. R. CIV. P. 67. An issue is tried by consent if the presentation of
    evidence puts the parties on notice that recovery under the unpled theory is conceivable,
    and the other party fails to make an appropriate complaint. Boyles v. Kerr, 
    855 S.W.2d 593
    , 601 (Tex. 1993).
    Here, a significant portion of the evidence presented centered around the nature
    and degree of Griffin’s alleged non-performance and the reasonable cost of remediating
    those deficiencies. Lyndall Hurst, Griffin’s President, testified in detail concerning the
    initial construction, approval, transportation, installation, repair, and final approval of the
    residence. In addition, both Brandon and Laura Dieringer testified to the long list of
    deficiencies identified and, with the assistance of their expert witnesses, to the reasonable
    cost of their remediation. Based on the amount of time spent and testimony received on
    those questions, we cannot say the trial court abused its discretion in finding that the
    theory of substantial performance was tried by consent.
    As to the Dieringers’ sufficiency of the evidence claims regarding substantial
    performance, the standards of review are well settled, and we refer the parties to Raw
    Hide Oil & Gas, Inc. v. Maxus Expl. Co., 
    766 S.W.2d 264
    , 275-276 (Tex. App.—Amarillo
    1988, writ denied), for further discussion of those standards.         The Dieringers place
    significant reliance on their contention that Griffin failed to meet its burden of proof
    because they—not Griffin—presented evidence of the remedial costs of Griffin’s contract
    performance deficiencies. This argument simply does not “hold water.” Unless otherwise
    specifically admitted for a singular purpose, evidence admitted at trial is admitted for all
    purposes and it does not matter whether Griffin or the Dieringers presented that evidence.
    6
    As referenced above, the principal parties each testified in detail (via both direct
    and cross-examination) concerning the contract deficiencies and the reasonable cost of
    remediation. Thirty-eight photographs were admitted showing the nature and extent of
    many of the deficiencies. Expert testimony was offered by both sides and invoices were
    admitted concerning the cost of remediation. Based on the appropriate standards of
    review, the judgment of the trial court concerning substantial performance was supported
    by legally and factually sufficient evidence. Appellees’ cross-issues concerning specific
    performance are overruled.
    ATTORNEY’S FEES AND COSTS
    Both parties contend that they are entitled to the recovery of their reasonable and
    necessary attorney’s fees under section 38.001 of the Texas Civil Practice and Remedies
    Code, as a “prevailing party” on their respective contract claims. See TEX. CIV. PRAC. &
    REM. CODE ANN. § 38.001 (West 2015). In order to recover attorney’s fees under section
    38.001, a litigant must (1) prevail on a cause of action for which attorney’s fees are
    recoverable and (2) recover damages. Expelled Grain Prods., LLC v. Corn Mill Enters.,
    LLC, No. 07-14-00398-CV, 2016 Tex. App. LEXIS 9002, at *26 (Tex. App.—Amarillo
    Aug.17, 2016, pet. denied) (citing MBM Fin. Corp. v. Woodlands Operating Co., 
    292 S.W.3d 660
    , 666 (Tex. 2009)). Where attorney’s fees are proper under section 38.001,
    the trial court has no discretion to deny them, provided, however, the party seeking to
    recover attorney’s fees still has the burden of proving the amount and reasonableness of
    those fees. Smith v. Patrick W.Y. Tam Trust, 
    296 S.W.3d 545
    , 547 (Tex. 2009); Expelled
    Grain, 2016 Tex. App. LEXIS 9002, at *27.
    Here, neither Griffin nor the Dieringers prevailed on their contract cause of action.
    Griffin did not establish complete performance—entitling it to recover the full contract
    7
    price, and the Dieringers did not establish a material breach—entitling them to repudiate
    the contract and withhold final payment. In fact, the trial court specifically found that,
    under the facts and circumstances of this case, neither party was a “prevailing party.”
    Because that finding is supported by substantial evidence, we will not disturb it, and
    because neither side was determined to be a “prevailing party,” the trial court did not err
    in denying either party the recovery of attorneys’ fees. Accordingly, we overrule Griffin’s
    first issue and the Dieringers’ cross-issue.
    OCCUPANCY FEES
    The construction contract in issue provided the Dieringers would not occupy the
    residence until the contract balance was paid in full. It further provided that in the event
    of “unusual circumstances,” Griffin could give the Dieringers “specific permission” to
    occupy the residence in exchange for an agreement to pay Griffin “$40.00 per day for
    occupancy prior to final payment.” In its Findings of Fact and Conclusions of Law, the
    trial court found that Griffin was not entitled to recover the contractually agreed-upon
    occupancy fees because the Dieringers were excused from performance by Griffin’s
    demand for payment in full without credit for reasonable and necessary repairs.
    As stated above, the trial court granted Griffin recovery based upon the equitable
    theory of substantial performance—not strict contractual performance. Because the trial
    court found that Griffin did not fully perform all its obligations under the contract, it did not
    err in finding that the occupancy fee provision was never triggered and that the Dieringers
    were excused from the strict contractual obligation to pay that fee. In any event, the trial
    court’s decision does not work an injustice to Griffin because the judgment incorporates
    prejudgment interest based upon the actual sums found to be due, from March 4, 2014
    8
    to date of judgment, in the amount of $9,893.14. Accordingly, Griffin’s second issue is
    overruled.
    CONCLUSION
    The judgment of the trial court is affirmed.
    Patrick A. Pirtle
    Justice
    Quinn, C.J., concurring in the result of issue one and joining in the remainder of the
    issues.
    9
    

Document Info

Docket Number: 07-16-00341-CV

Filed Date: 5/29/2018

Precedential Status: Precedential

Modified Date: 5/31/2018