Pakistan Petroleum Limited v. Specialty Process Equipment Corporation ( 2023 )


Menu:
  • Opinion issued January 26, 2023
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-21-00341-CV
    ———————————
    PAKISTAN PETROLEUM LIMITED, Appellant
    V.
    SPECIALTY PROCESS EQUIPMENT CORPORATION, SPEC ENERGY
    DMCC, SPEC OIL & GAS FZCO, S7 CONSTRUCTION INC., AND
    NEWPORT OIL & GAS (USA), LLC, Appellees
    On Appeal from the 11th District Court
    Harris County, Texas
    Trial Court Case No. 2019-35747
    MEMORANDUM OPINION
    Background
    In this accelerated interlocutory appeal, appellant Pakistan Petroleum Limited
    (PPL) appeals the trial court’s order denying its special appearance in the suit
    brought against it by appellees Specialty Process Equipment Corporation, SPEC
    Energy DMCC, SPEC Oil & Gas FZCO, S7 Construction Inc., and Newpoint Oil &
    Gas (USA) LLC, asserting claims for breach of contract, unjust enrichment, and
    quantum meruit. In two issues, PPL contends that the trial court erred in denying its
    special appearance because there is insufficient evidence to support the exercise of
    personal jurisdiction over it. We reverse and render.
    Background
    A.    Factual History
    PPL is a gas exploration and production company organized and existing
    under the laws of Pakistan and with its principal place of business in Karachi. SPEC
    Energy DMCC (DMCC) is a company organized and existing under the laws of the
    United Arab Emirates (UAE) with its principal place of business in Dubai.
    In 2015, PPL sought bids for a project to build a gas processing facility at
    Gambat South Block in Sindh, Pakistan (the Project). It published an invitation to
    bid in Dawn, the local newspaper in Pakistan, the Khaleej Times, a UAE newspaper,
    and the Houston Chronicle in Texas. Fareed Siddiqui, PPL’s corporate
    representative, testified that PPL published the invitation in the Houston Chronicle
    because its website is widely read by oil and gas business professionals throughout
    the world and PPL wanted to reach an international audience. DMCC did not see
    2
    PPL’s invitation in the Houston Chronicle but instead learned about the invitation to
    bid through “word of mouth.” DMCC submitted a bid for the Project.
    PPL and DMCC conducted negotiations in Dubai and Pakistan. Following
    PPL’s selection of DMCC as the contractor for the Project, PPL and DMCC
    executed a Works Contract for Gas Processing Facility (GPF-III) at Gambat South
    Block on Engineering, Procurement, Construction and Commissioning (EPCC)
    Basis (the Contract) in Pakistan on May 9, 2016.
    Under the Contract, DMCC was responsible for the design engineering,
    procurement (supply) of materials, construction, installation/erection, pre-
    commissioning, commissioning, and startup of the Project, as well as remedying any
    defects arising during the defect liability period. Under Section 3.2 of the Contract,
    all equipment and materials had to be supplied from vendors on PPL’s approved
    vendor list which included vendors from all over the world. DMCC decided which
    approved vendors to select from the list. Section 3.7 of the Contract provided that
    DMCC was responsible for the cost of all services, including materials and personnel
    required for its performance, and the import of equipment and materials. Under
    Section 3.10, PPL was responsible for the issuance of documents required for
    DMCC’s execution of its work.
    Section 3.15 provided that daily progress review meetings would be held at
    the plant site and monthly progress review meetings would be held in Karachi,
    3
    Pakistan. Under Section 3.17, DMCC was required to provide insurance that
    complied with the applicable laws in the country of operation. Section 3.19 stated
    that the Contract “shall be construed and governed in accordance with the laws in
    Pakistan” and contract disputes were to “be referred for resolution by arbitration in
    Karachi.” Section 3.34.1 provided:
    In case of JV/Consortium, the invoice(s) shall be raised by the lead
    consortium partner on behalf of itself and other JV consortium
    partner(s) clearly stating the amounts attributable to each consortium
    partner. The COMPANY shall make payment to the designated
    accounts of each consortium partner respectively as per the amounts
    mentioned in the invoices(s) [sic].
    The Contract price was US $70,750,644.1 Under the Contract, PPL was
    required to pay DMCC various percentages of the Contract price based upon
    DMCC’s achievement of certain milestones. Section 3.28.13 of the Contract set forth
    the procedure for DMCC to submit an invoice for payment by PPL of a percentage
    of the Contract price once particular milestones were met. DMCC also provided
    bank guarantees and bonds from financial institutions located in Pakistan and the
    UAE.
    B.     Procedural History
    By September 2018, relations between PPL and DMCC had deteriorated.
    Citing Section 3.24, DMCC invoked the arbitration clause of the Contract and filed
    1
    The amount due was (i) US $63,000,764; and (ii) PKR 811,800,027.00 (equivalent
    to US $7,749,880 on the date of the Contract) for the work.
    4
    for arbitration of the dispute in Pakistan. DMCC also filed claims against PPL in a
    court in Dubai related to the encashing of performance bonds DMCC had provided
    to PPL under the terms of the Contract. Additionally, DMCC and PPL have pending
    claims in the High Court of Sindh, Pakistan, related to the contract dispute. In
    February 2019, PPL and DMCC met in Islamabad to discuss their dispute and
    attempt to reach a resolution, but to no avail. On May 10, 2019, PPL terminated the
    Contract.
    On May 23, 2019, DMCC and its “sister companies”—Specialty Process
    Equipment Corporation (SPEC) (a Texas corporation), SPEC Oil & Gas FZCO
    (SPEC Oil & Gas) (a UAE company), and S7 Construction Inc. (S7) (a Texas
    corporation)—filed suit against PPL in Harris County, Texas, asserting claims for
    breach of contract, unjust enrichment, and attorney’s fees. They alleged that they
    entered into the Contract with PPL as a joint venture alliance with DMCC as the lead
    partner. They later amended their petition to add Newpoint Oil & Gas (USA) LLC,
    formerly known as Newpoint Gas LLC (a Texas limited liability company)
    (Newpoint), as a plaintiff as well as a claim for quantum meruit. DMCC and the
    other plaintiffs pleaded that the trial court had jurisdiction over PPL “pursuant to §
    17.042 of the Texas Civil Practice and Remedies Code because [PPL] contracted
    with a Texas resident (namely SPEC, S7[,] and Newpoint), and each of SPEC, S7,
    and Newpoint performed the contract in whole or in part in Harris County, Texas.”
    5
    On June 24, 2019, PPL filed a special appearance and motion to dismiss for
    lack of jurisdiction which it later amended. PPL argued that (1) it is a non-resident
    foreign corporation with its principal place of business in Pakistan, (2) the Contract
    was executed by PPL and DMCC only, (3) PPL had no relationship or connection
    with any other plaintiff, and (4) the entire work under the Contract was to be
    completed in Pakistan. It further asserted that the contract was executed in Pakistan
    and governed by the laws of Pakistan and that all payments under the Contract were
    made to DMCC from Pakistan. It attached copies of the filings related to the
    arbitration and litigation in Pakistan and the Contract as exhibits to its amended
    special appearance.
    On September 26, 2019, DMCC and the other plaintiffs filed a motion for
    continuance of the special appearance hearing, a request for sanctions, and a motion
    for limited discovery. On September 27, 2019, they filed a response to PPL’s
    amended special appearance arguing that Texas courts could exercise specific
    jurisdiction over PPL because (1) the Contract specifically authorized work to be
    performed in Texas and (2) PPL’s contacts with Texas were substantial. They
    attached the following as exhibits to their response:
    1) a copy of the Contract,
    2) a Recommended Vendors/Manufacturers List,
    6
    3) Franchise Tax Account Status printouts reflecting that SPEC and S7 are
    registered businesses in the State of Texas,
    4) the declarations of Zafar Sheikh, a Director of DMCC, SPEC, SPEC
    Oil & Gas, and S7, and Irtaza Sheikh, a Director of S7,
    5) various purchase orders, and
    6) photographs of employees at the Project site.
    The trial court granted the motion for continuance and the request for limited
    discovery.
    The parties completed jurisdictional discovery and subsequently filed
    additional briefing and evidence prior to the hearing on the special appearance.
    Following a non-evidentiary hearing, the trial court signed an order denying PPL’s
    special appearance on June 7, 2021. The trial court also denied PPL’s request for
    findings of fact and conclusions of law. This interlocutory appeal followed.
    Discussion
    PPL contends that the trial court erred in denying its special appearance
    because PPL lacks sufficient minimum contacts to support the assertion of specific
    or general jurisdiction, and that any implied finding from the trial court that PPL had
    sufficient minimum contacts to support the exercise of jurisdiction is not supported
    7
    by legally or factually sufficient evidence.2 In support of its contention, it argues that
    (1) PPL contracted only with DMCC, a UAE company, and not the Texas plaintiffs,
    (2) an analysis of the factors applicable to breach-of-contract disputes demonstrates
    that jurisdiction is lacking, and (3) the remaining alleged minimum contacts relied
    on by appellees are insufficient. It further argues that exercising jurisdiction over
    PPL would offend traditional notions of fair play and substantial justice.
    Appellees respond that PPL failed to satisfy its burden to negate each of the
    bases of personal jurisdiction alleged in their amended petition. They argue that PPL
    engaged in sufficient minimum contacts to establish specific jurisdiction because it
    (1) contracted with an entity with a strong presence in Texas, (2) conducted business
    with Texas residents, (3) advertised in Texas, and (4) required appellees, vendors,
    and contractors to comply with Texas law. It also asserts that a substantial amount
    of work within the scope of the Contract was performed in Texas.
    A.    Standard of Review
    We review de novo a trial court’s decision to grant or deny a special
    appearance. Am. Type Culture Collection, Inc. v. Coleman, 
    83 S.W.3d 801
    , 806
    (Tex. 2002). A plaintiff must plead allegations that bring a non-resident defendant
    2
    A nonresident’s contacts can give rise to either general or specific personal
    jurisdiction. Moncrief Oil Int’l, Inc. v. OAO Gazprom, 
    414 S.W.3d 142
    , 150 (Tex.
    2013). Because appellees concede on appeal that, on these facts, general jurisdiction
    does not exist as to PPL, we consider only whether specific jurisdiction exists.
    8
    within the provisions of the Texas long-arm statute. BMC Software Belg., N.V. v.
    Marchand, 
    83 S.W.3d 789
    , 793 (Tex. 2002). The Texas long-arm statute provides
    that a non-resident who “does business” in the state, such as by contracting with a
    Texas resident where the contract is to be performed in whole or in part in Texas, is
    subject to personal jurisdiction. TEX. CIV. PRAC. & REM. CODE § 17.042(1); BMC
    Software, 83 S.W.3d at 795.
    Once the plaintiff has pleaded sufficient jurisdictional allegations, the
    defendant filing a special appearance bears the burden to negate all bases of personal
    jurisdiction alleged by the plaintiff. Kelly v. Gen. Interior Const., Inc., 
    301 S.W.3d 653
    , 658 (Tex. 2010). “Because the plaintiff defines the scope and nature of the
    lawsuit, the defendant’s corresponding burden to negate jurisdiction is tied to the
    allegations in the plaintiff’s pleading.” Id. at 658; Brenham Oil & Gas, Inc. v. TGS–
    NOPEC Geophysical Co., 
    472 S.W.3d 744
    , 764 (Tex. App.—Houston [1st Dist.]
    2015, no pet.). The defendant can negate jurisdiction on either a factual or legal
    basis. Kelly, 301 S.W.3d at 659. Factually, the defendant can present evidence that
    it has no contacts with Texas, effectively disproving the plaintiff’s allegations. Id.
    Legally, the defendant can show that even if the plaintiff’s alleged facts are true, the
    evidence is legally insufficient to establish jurisdiction. Id.
    When, as here, a trial court does not issue findings of fact and conclusion of
    law in support of a special appearance ruling, then “all facts necessary to support the
    9
    judgment and supported by the evidence are implied.” BMC Software, 83 S.W.3d at
    795. However, these findings are not conclusive when the appellate record includes
    both the clerk’s and reporter’s records, as it does here, and a party may challenge
    these findings for legal and factual sufficiency on appeal. Id.; Waterman Steamship
    Corp. v. Ruiz, 
    355 S.W.3d 387
    , 402 (Tex. App.—Houston [1st Dist.] 2011, pet.
    denied).
    B.    Applicable Law
    Texas courts may assert personal jurisdiction over a nonresident defendant if
    (1) the Texas long-arm statute authorizes the exercise of jurisdiction, and (2) the
    exercise of jurisdiction is consistent with federal and state due process standards.
    Moki Mac River Expeditions v. Drugg, 
    221 S.W.3d 569
    , 574 (Tex. 2007). The Texas
    long-arm statute allows Texas courts to exercise personal jurisdiction “as far as the
    federal constitutional requirements of due process will permit.” BMC Software, 83
    S.W.3d at 795 (quotation omitted). Federal due process requires that the nonresident
    defendant have purposefully established minimum contacts with the forum state,
    such that the defendant reasonably could anticipate being sued there. Curocom
    Energy LLC v. Young–Sub Shim, 
    416 S.W.3d 893
    , 896 (Tex. App.—Houston [1st
    Dist.] 2013, no pet.). The exercise of personal jurisdiction must also comport with
    traditional notions of fair play and substantial justice. 
    Id.
    10
    Specific jurisdiction arises when the defendant purposefully avails itself of
    conducting activities in the forum state, and the cause of action arises from or is
    related to those contacts or activities. Burger King Corp. v. Rudzewicz, 
    471 U.S. 462
    ,
    472 (1985); Kelly, 301 S.W.3d at 658; Retamco Operating, Inc. v. Republic Drilling
    Co., 
    278 S.W.3d 333
    , 338 (Tex. 2009). In a specific jurisdiction analysis, “we focus
    . . . on the ‘relationship among the defendant, the forum[,] and the litigation.’” Moki
    Mac, 221 S.W.3d at 575–76 (quoting Guardian Royal Exch. Assurance, Ltd. v.
    English China Clays, P.L.C., 
    815 S.W.2d 223
    , 228 (Tex. 1991)). The plaintiff must
    show a substantial connection between the defendant’s contacts with the forum state
    and the operative facts of the litigation. Id. at 585. The “purposeful availment”
    inquiry has three parts. See Michiana Easy Livin’ Country, Inc. v. Holten, 
    168 S.W.3d 777
    , 785 (Tex. 2005). First, only the defendant’s contacts with the forum are
    relevant, not the unilateral activity of another party or a third person. 
    Id.
     Second, the
    contacts relied upon must be purposeful rather than random, fortuitous, or
    attenuated. Id.; see also Burger King, 
    471 U.S. at
    475 n.18. Third, the “defendant
    must seek some benefit, advantage, or profit by ‘availing’ itself of the jurisdiction.”
    Michiana, 168 S.W.3d at 785.
    C.    Specific Jurisdiction —Breach of Contract Claim
    In its amended petition, appellees pleaded that “[t]he Court has jurisdiction
    over PPL pursuant to § 17.042 of the Texas Civil Practice and Remedies Code
    11
    because [PPL] contracted with a Texas resident (namely SPEC, S7[,] and Newpoint),
    and each of SPEC, S7[,] and Newpoint performed the contract in whole or in part in
    Harris County, Texas.” PPL contends that the evidence conclusively negates this
    alleged basis for jurisdiction. It argues that even if the evidence showed that such a
    contract existed, jurisdiction would nevertheless be lacking.
    1.     Parties to the Contract
    “As a general rule, the benefits and burdens of a contract belong solely to the
    contracting parties, and no person can sue upon a contract except he be a party to or
    in privity with it.” First Bank v. Brumitt, 
    519 S.W.3d 95
    , 102–03 (Tex. 2017)
    (quotation omitted); Kenyon Int’l Emergency Servs., Inc. v. Starr Indem. & Liab.
    Co., No. 01-17-00386-CV, 
    2018 WL 6241461
    , at *5 (Tex. App.—Houston [1st
    Dist.] Nov. 29, 2018, pet. denied) (mem. op.). Here, the Contract for the construction
    of the gas processing facility in Pakistan states that it is between PPL, the Company,
    and DMCC, the Contractor. The contract is signed only by two parties: PPL and
    DMCC. No other party appears on the face of the Contract.
    Appellees argue that they are parties to the Contract because they bid on the
    Project and executed the Contract as a consortium/joint venture. They assert that the
    consortium/joint venture consisted of DMCC, as the lead consortium/joint venture
    partner, and the other entities including SPEC, SPEC Oil & Gas, and S7. They argue
    that the Contract “indisputably acknowledges that a consortium/joint venture is
    12
    being used for the Project.” In support of their argument, appellees point to Section
    3.34.1 of the Contract:
    In case of JV/Consortium, the invoice(s) shall be raised by the lead
    consortium partner on behalf of itself and other JV consortium
    partner(s) clearly stating the amounts attributable to each consortium
    partner. The COMPANY shall make payment to the designated
    accounts of each consortium partner respectively as per the amounts
    mentioned in the invoices(s) [sic].
    Section 3.34.1 does not establish that appellees executed the Contract as a
    consortium/joint venture. Rather, the provision provides the procedure for invoicing
    in the event of a joint venture/consortium. And, as noted above, the Contract itself
    does not reflect execution as a consortium/joint venture. Siddiqui testified that the
    bidding procedure for the Contract requires any joint venture be identified in writing
    and that a copy of the joint venture agreement, which would include the composition
    of the joint venture, be provided with the bidding document. There is nothing in the
    record showing that a joint venture agreement was provided in the bid. Irtaza Sheikh,
    appellees’ corporate representative, testified that he did not know if an agreement
    among the purported consortium members existed. There is no evidence that
    appellees executed the Contract as a joint venture.
    PPL argues that even if DMCC had executed the Contract as a joint
    venture/consortium, this fact alone would not render each individual member of the
    joint venture an actual party to the agreement. We agree. “[A] joint venture, like a
    partnership, is an entity legally distinct from the partners.” Bank One, Tex., N.A. v.
    
    13 Stewart, 967
     S.W.2d 419, 444 (Tex. App.—Houston [14th Dist.] 1998, pet. denied).
    And, “a contract with one corporation . . . is generally not a contract with any other
    corporate affiliates.” In re Merrill Lynch Trust Co. FSB, 
    235 S.W.3d 185
    , 191 (Tex.
    2007) (orig. proceeding); see also R. Hassell Builders, Inc. v. Texan Floor Serv.,
    Ltd., 
    546 S.W.3d 816
    , 829–30 (Tex. App.—Houston [1st Dist.] 2018, pet. denied)
    (noting that while corporation and joint venture were part of same “corporate
    family,” they were each separate legal entities and “[a]s such, they are each
    responsible for their own debts and liabilities.”).
    2.     Purchase Orders
    Appellees argue that, pursuant to the Contract, each individual invoice for
    approved work performed by the consortium members constituted an agreement for
    PPL to pay. They assert that each individual invoice that DMCC sent for SPEC and
    S7 (Texas corporations) was an individual contract for PPL to pay SPEC and S7.
    This argument is unavailing. The “invoices” upon which appellees rely are purchase
    orders sent by DMCC to various vendors. PPL is not named as a purchaser on any
    of the purchase orders. The materials purchased were all to be shipped to SPEC Oil
    & Gas in Dubai. Irtaza Sheikh testified that only DMCC, and no other party, was to
    receive payments from PPL under the Contract. This comports with Section 3.7.20
    of the Contract which provides that DMCC was responsible for procuring and paying
    vendors for the materials. Because PPL was not a party to the purchase orders, the
    14
    orders do not establish a contract between PPL and SPEC or PPL and S7. See
    Brumitt, 519 S.W.3d at 102 (noting benefits and burdens of contract belong only to
    contracting parties); see also Shell Compania Argentina de Petroleo, S.A. v. Reef
    Expl., Inc., 
    84 S.W.3d 830
    , 838 (Tex. App.—Houston [1st Dist.] 2002, pet. denied)
    (holding that defendant was not party to various agreements and therefore
    agreements were not relevant to consideration of issue of specific jurisdiction).
    3.     Factors Applicable in Breach-of-Contract Disputes
    Moreover, even if appellees could demonstrate that PPL contracted with the
    Texas entities, that fact alone is insufficient to confer jurisdiction. Merely
    contracting with a Texas corporation does not satisfy the minimum contacts
    requirement. Shell Compania Argentina, 
    84 S.W.3d at
    837 (citing TeleVentures, Inc.
    v. Int’l Game Tech., 
    12 S.W.3d 900
    , 908 (Tex. App.—Austin 2000, pet. denied)).
    Prior negotiations, contemplated future consequences, the terms of a contract, and
    the parties’ course of dealing are all factors that must be considered in determining
    whether a defendant purposely established minimum contacts within the forum. 
    Id.
    In this case, the undisputed evidence shows that contract negotiations and
    execution of the Contract took place in Dubai or Pakistan, not Texas. As to
    contemplated future consequences, the Contract expressly provides that any future
    disputes would be governed by Pakistani law and subject to arbitration in Pakistan.
    This evidence supports a finding that PPL did not purposefully avail itself of Texas.
    15
    See Michiana, 168 S.W.3d at 792 (noting that “insertion of a clause designating a
    foreign forum suggests that no local availment was intended”).
    The “place of contractual performance” is also an important consideration in
    determining whether a defendant purposely availed itself of the forum state. See
    Sayers Constr., L.L.C. v. Timberline Constr., Inc., 
    976 F.3d 570
    , 573 (5th Cir. 2020).
    As part of this consideration, courts look at whether the contract contemplated or
    required performance in Texas, where the defendant performed its obligations, and
    where the contract centered. See M & F Worldwide Corp. v. Pepsi–Cola Metro.
    Bottling Co., 
    512 S.W.3d 878
    , 889 (Tex. 2017) (noting fact that contract did not
    contemplate or require performance in Texas); see also Moncrief Oil Int’l Inc. v.
    OAO Gazprom, 
    481 F.3d 309
    , 312 (5th Cir. 2007) (concluding plaintiff’s unilateral
    performance of activities in Texas was insufficient where “the defendant did not
    perform any of its obligations in Texas, the contract did not require performance in
    Texas, and the contract is centered outside of Texas.”). Here, the Contract is for the
    construction of a gas processing facility located in Pakistan—thus, the place of the
    Contract’s performance is centered in Pakistan. The Contract also provided that
    regular status meetings would be held either in Karachi or at the site in Pakistan. All
    payments were made to DMCC from Pakistan. Nothing in the Contract contemplates
    or requires performance in Texas. See Univ. of Ala. v. Suder Found., No. 05-16-
    00691-CV, 
    2017 WL 655948
    , at *7 (Tex. App.—Dallas Feb. 17, 2017, no pet.)
    16
    (mem. op.) (concluding circumstances did not establish purposeful availment where
    “[the Defendant’s] contract performance was substantially in Alabama, and the
    parties’ contractual relationship was centered in Alabama, not Texas”); Weatherford
    Artificial Lift Sys., Inc. v. A & E Sys. SDN BHD, 
    470 S.W.3d 604
    , 615 (Tex. App.—
    Houston [1st Dist.] 2015, no pet.) (concluding that evidence showing contract was
    negotiated in Malaysia and required that payment would have been made from
    Malaysia was insufficient to support exercise of jurisdiction in Texas).
    4.     Approved Vendor List
    Appellees argue that Section 3.2 of the Contract contemplated performance in
    Texas. That section provides: “All equipment and materials supplied under the
    CONTRACT shall be new/unused and from the vendor as mentioned in
    recommended manufacturer/vendor list . . .” They point out that over 90% of the
    approved vendors are located outside of Pakistan, with many of them in the United
    States, and the Contract contemplated that the parties to the Contract would use
    Texas vendors for performance of the Project. Thus, they argue, PPL specifically
    targeted Texas residents.
    While the forty-four page approved vendor list includes some Texas vendors,
    it includes companies from all over the world and nearly every one of the companies
    is listed as international. The international focus of the approved vendor list suggests
    that Texas was neither targeted nor the focus of the list. See Suder Found., 
    2017 WL 17
    655948, at *7 (concluding fact that defendant university was obligated to assist in
    development of Texas-based foundation’s national program and provide it with data
    to promote its larger nationwide mission underscored that contractual relationship
    was not Texas-centered). And, appellees’ corporate representative testified that it
    was DMCC who chose the Texas vendors, not PPL. Thus, it stands to reason that
    DMCC could have equally chosen a vendor from outside of Texas.
    5.      Insurance Provision
    Appellees assert that Section 3.17 of the Contract requires all vendors and
    subcontractors to carry insurance that complies with the law of the state that the
    vendor is in—that is, comply with the laws of the State of Texas. They argue that
    this evidence demonstrates that PPL purposely availed itself of Texas law. However,
    by its terms, Section 3.17 applies to any subcontractor anywhere in the world and is
    not specific to Texas. This means that Texas law would only be implicated when
    DMCC selected a Texas vendor. Such a contact is merely fortuitous rather than
    purposeful. See Michiana, 168 S.W.3d at 785 (stating that contacts relied upon must
    be purposeful rather than random, fortuitous, or attenuated to constitute purposeful
    availment).
    6.      Work Performed in Texas and Other States
    Appellees contend, as they did in the trial court below, that PPL engaged in
    more than $16 million worth of work related to the Contract with entities located in
    18
    the United States of which approximately 66% was performed in Texas or by Texas
    residents. They assert that the total amount of work contracted for by Texas residents
    on the project is $10,590,409.37. Thus, they argue, Texas residents made up a large
    part of PPL’s business dealings related to the Project.
    In their response to PPL’s special appearance, appellees included a chart
    listing the vendors chosen by DMCC who provided materials for the Project. The
    chart reflects that $16 million worth of work for the gas processing plant was
    performed in Texas and various other states. The chart shows that a significant
    portion of the materials were provided from vendors outside of Texas—including
    Wisconsin, Tennessee, New York, Indiana, and Oklahoma—and two of the locations
    are listed as “USA.” The work performed for the project outside of Texas is not
    relevant to determining whether PPL had any contacts with Texas. See J. McIntyre
    Mach., Ltd. v. Nicastro, 
    564 U.S. 873
    , 886 (2011) (plurality op.) (“Here the question
    concerns the authority of a New Jersey state court to exercise jurisdiction, so it is
    petitioner’s purposeful contacts with New Jersey, not with the United States, that
    alone are relevant.”). After the amount of work performed by the non-Texas entities
    is deducted, the chart shows that the amount of work performed in Texas is slightly
    more than $10.5 million. The chart also includes two purchase orders from Newpoint
    that DMCC stated in the arbitration were cancelled. With the cancellation of those
    purchase orders, the amount of work performed in Texas is reduced to slightly more
    19
    than $1.8 million, of which only $180,000 was performed by an appellee (S7) in this
    case. When viewed in the context of the entire amount ($16 million), and given the
    undisputed evidence that DMCC, not PPL chose the vendors for the project, this
    evidence is insufficient to support an implied finding that “millions of dollars’ worth
    of work was perform[ed] in Texas by SPEC plaintiffs.”
    7.     Inspection in Texas
    Appellees argue that, under the Contract, PPL ordered an inspection of the
    work completed in Texas, and that this contact demonstrates purposeful availment.
    Siddiqui testified that PPL hired TUV, an Austrian company, to perform
    inspections all over the world, and that the inspectors would go “anywhere where
    []DMCC tells them to go for inspection.” Siddiqui testified that the company
    performed one inspection in Texas, one in Colorado, and forty or fifty in the UAE.
    One inspection in Texas, which occurred at DMCC’s direction, is merely an isolated
    contact which cannot support jurisdiction. See Michiana, 168 S.W.3d at 785 (stating
    that, for purposes of purposeful availment inquiry, only defendant’s contacts with
    forum are relevant, not unilateral activity of third person, and contacts relied upon
    must be purposeful rather than random, fortuitous, or attenuated).
    20
    8.    Houston Chronicle Advertisement
    Appellees point to PPL’s advertisement in the Houston Chronicle to publish
    its invitation to bid on the Project as evidence that PPL targeted Texas businesses
    and marketed its project in Texas.
    Siddiqui testified that PPL published the invitation to bid on the Project in
    Dawn, the local newspaper in Pakistan, the Khaleej Times, a UAE newspaper, and
    the Houston Chronicle in Texas. He testified that PPL published the invitation in the
    Houston Chronicle because its website is widely read by oil and gas business
    professionals throughout the world and PPL wanted to reach an international
    audience. Irtaza Sheikh acknowledged that DMCC did not see the Houston
    Chronicle listing but instead learned about the invitation to bid through “word of
    mouth.” This single advertisement in the Houston Chronicle, intended for an
    international audience and which DMCC did not see, is an isolated contact that does
    not satisfy jurisdictional requirements. See id.
    D.      Specific Jurisdiction—Unjust Enrichment and Quantum Meruit Claims
    In addition to their breach of contract claim, appellees asserted claims for
    unjust enrichment and quantum meruit against PPL. As to their unjust enrichment
    claim, appellees alleged:
    • Defendant received Plaintiffs’ work valued at the full amount of the
    contract. This money belongs to Plaintiffs in equity and good
    conscience. Further, the goods and services were obtained by
    21
    Defendant on account of fraud and taking undue advantage of Plaintiffs
    (directly and indirectly[)] through Defendant’s representatives.
    As to their quantum meruit claim, appellees alleged:
    • Plaintiffs provided valuable services and materials to Defendant PPL
    as evidenced by its detailed invoices documenting these items. These
    services and supplies were rendered for the direct benefit of Defendant
    PPL. Further, these services and supplies were accepted by Defendant
    PPL, and Defendant PPL was notified that in performing these services
    and providing these supplies, Plaintiff expected to be paid by Defendant
    PPL.
    Under Texas’s long-arm statute, appellees were required to plead that PPL
    committed the alleged tortious acts in Texas. See Kelly, 301 S.W.3d at 658–59 (“If
    the plaintiff fails to plead facts bringing the defendant within reach of the long-arm
    statute (i.e., for a tort claim, that the defendant committed tortious acts in Texas), the
    defendant need only prove that it does not live in Texas to negate jurisdiction.”);
    Proppant Sols., LLC v. Delgado, 
    471 S.W.3d 529
    , 536 (Tex. App.—Houston [1st
    Dist.] 2015, no pet.) (citing Kelly, 301 S.W.3d at 658–59). Neither appellees’
    amended petition nor its responsive briefing alleges that PPL committed any acts in
    Texas much less any tortious acts. That is, appellees did not plead where any alleged
    fraud and taking of undue advantage occurred, and appellees do not contend that
    these alleged acts occurred in Texas. Similarly, appellees’ allegations underlying
    their quantum meruit claim do not identify where PPL’s alleged actions occurred.
    Moreover, we note that any alleged services and supplies would presumably have
    22
    been accepted by PPL at the plant in Pakistan.3 See Vinmar Overseas Singapore PTE
    Ltd. v. PTT Int’l Trading PTE Ltd., 
    538 S.W.3d 126
    , 133 (Tex. App.—Houston [14th
    Dist.] 2017, pet. denied) (“When the plaintiff fails to allege an act by the defendant
    occurring in Texas, the plaintiff has not met its initial burden of pleading acts
    sufficient to invoke jurisdiction over the nonresident defendant.”); see also
    Moncrief, 414 S.W.3d at 153–54, 156–57 (holding nonresident defendant was
    subject to jurisdiction for misappropriation of trade secrets claim where defendant
    obtained trade secrets in Texas but not for tortious interference claim where alleged
    acts of interference occurred outside of Texas). Because PPL proved that it is not a
    Texas resident, it negated personal jurisdiction over appellees’ unjust enrichment
    and quantum meruit claims. See Kelly, 301 S.W.3d at 658–59.
    Accordingly, we conclude that the evidence is insufficient to support any
    implied finding that PPL had sufficient minimum contacts with Texas to support the
    exercise of jurisdiction over it. Because PPL did not purposefully avail itself of the
    privilege of conducting activities in Texas, the trial court erred in denying its
    amended special appearance. Having concluded that PPL negated all bases for the
    assertion of personal jurisdiction, we sustain PPL’s issues.4
    3
    Appellees do not address the issue of jurisdiction over their unjust enrichment and
    quantum meruit claims in their brief on appeal.
    4
    In light of our holding, we need not address the question of whether the exercise of
    personal jurisdiction would offend the traditional notions of fair play and substantial
    23
    Conclusion
    We reverse the trial court’s June 7, 2021 order denying PPL’s amended
    special appearance and render judgment dismissing appellees’ claims against PPL.
    Amparo Guerra
    Justice
    Panel consists of Justices Goodman, Hightower, and Guerra.
    justice. See 11500 Space Ctr., L.L.C. v. Private Cap. Grp., Inc., 
    577 S.W.3d 322
    ,
    336 n.9 (Tex. App.—Houston [1st Dist.] 2019, no pet.).
    24