Henry Hendrickson D/B/A H&M Construction v. Charles Heard ( 2018 )


Menu:
  • Affirmed and Memorandum Opinion filed October 4, 2018.
    In The
    Fourteenth Court of Appeals
    NO. 14-17-00659-CV
    HENRY HENDRICKSON D/B/A H&M CONSTRUCTION, Appellant
    V.
    CHARLES HEARD, Appellee
    On Appeal from the 335th District Court
    Washington County, Texas
    Trial Court Cause No. 35759
    MEMORANDUM OPINION
    This dispute arises from a construction contract between appellant Henry
    Hendrickson d/b/a H&M Construction (“Hendrickson”) and appellee Charles
    Heard. Heard sued Hendrickson alleging that Hendrickson breached the parties’
    contract by failing to pay Heard for work Heard performed. Heard moved for
    traditional summary judgment on his contract claim, relying in part on deemed
    admissions resulting from Hendrickson’s failure to respond to Heard’s discovery
    requests. The trial court granted Heard’s summary judgment motion. For the
    reasons below, we affirm.
    BACKGROUND
    Heard and his wife own property in Washington County, Texas. Heard
    planned to build a house on the property and contracted with Hendrickson to
    oversee its construction.
    Heard took out a $200,000 loan from Round Top State Bank to finance
    construction of the house. Under the terms of the loan, the Bank would make
    periodic payments to Hendrickson as the construction’s contractor and
    Hendrickson would disburse payments to his employees, vendors, and
    subcontractors for work completed. According to Heard, he and Hendrickson
    agreed that Heard would complete construction work on the house in exchange for
    payment.
    Heard sued Hendrickson in May 2015 and asserted that Hendrickson “has
    not paid to [Heard] the value of the work performed by [Heard].” Heard sought
    $38,746 in damages as well as interest, attorney’s fees, and expenses. Hendrickson
    filed a handwritten, one-page answer stating, “I Henry Hendrickson denie [sic] I
    owe this money.”
    As part of his discovery requests, Heard served Hendrickson with the
    following requests for admission:
    1.     That [Hendrickson] hired various trades to perform work for the
    Construction Project performed by [Hendrickson] at the Premises.
    2.     There was a contract between Hendrickson and the Heards in the
    Heards’ capacities as the owners of the Premises for the Construction
    Project.
    3.     Hendrickson was involved in the Loan between the Bank and the
    Premises owners.
    4.     Money was paid by the Bank to Hendrickson to perform the work at
    2
    the Construction Project.
    5.    Hendrickson hired [Heard] to perform some of the work at the
    Construction Project.
    6.    Heard in fact performed work on the Construction Project.
    7.    Hendrickson reported to the Bank that the work done by Heard as part
    of the Construction Project was done by and for Hendrickson for
    purposes of the loan advances made by the Bank in payment of the
    work for the Construction Project.
    8.    Hendrickson supervised the work done by Heard as part of the
    Construction Project.
    9.    Hendrickson coordinated the work done by Heard as part of the
    Construction Project with the work done by other trades during the
    life of the Construction Project.
    10.   The dollar value of the work done by Heard as part of the
    Construction Project was $38,746.
    11.   Hendrickson did not pay any money to Heard for any of the work
    done by Heard as part of the Construction Project.
    12.   Hendrickson received a written demand from counsel for Heard prior
    to the filing of the lawsuit of Heard v. Hendrickson in Cause # 35759.
    13.   Hendrickson did not pay any money to Heard after Hendrickson
    received a written demand for payment from counsel for Heard for
    work done by Heard that was part of the Construction Project.
    Hendrickson did not respond to the requests for admission.
    Heard filed a motion requesting the trial court deem admitted his requests
    for admission because of Hendrickson’s failure to respond. Heard also filed a
    motion for traditional summary judgment on his breach of contract claim. See Tex.
    R. Civ. P. 166a(c). Heard asserted that the elements of his contract claim were
    “deemed admitted by Hendrickson when he failed to respond to valid discovery
    requests including Requests for Admission.” Hendrickson did not respond to
    Heard’s motions.
    The trial court signed an order granting Heard’s motion to deem admitted
    3
    the requests for admission. The trial court signed a separate order granting Heard’s
    motion for traditional summary judgment.
    After the final judgment was signed, Hendrickson filed a petition for bill of
    review in a separate action.1 According to Heard’s appellate brief, the trial court
    granted Hendrickson’s petition for bill of review and reinstated the underlying
    proceeding.
    Heard filed a second motion for traditional summary judgment in the
    underlying action; Heard’s second motion was substantially the same as his first
    motion. Heard again asserted that the elements of his contract claim were deemed
    admitted by Hendrickson when Hendrickson failed to respond to the requests for
    admission. Heard also included the following evidence attached as exhibits to his
    second summary judgment motion: an exhibit labeled “Bank Contract Signed by
    both Parties and Bank Draws;” an exhibit labeled “Check Copies for
    Expenditures;” and Heard’s affidavit.
    The “Bank Contract” lists the different tasks that would be completed as part
    of the house’s construction and the cost to complete each task. The “Bank Draws”
    exhibit shows several requests for payment from Hendrickson to Round Top State
    Bank to pay for certain subcontractors and suppliers. The “Check Copies for
    Expenditures” exhibit includes photocopies of checks signed by Heard or his wife
    for various construction expenses. Heard’s affidavit, in relevant part, states:
    I contracted with [Hendrickson] for him to perform work at my home.
    [Hendrickson] retained me as a sub-contractor to perform some of the
    work. I performed the work. [Hendrickson] failed to pay me for my
    work despite [Hendrickson] being paid in full by the bank that loaned
    money to my wife and I for the totality of the work done by
    1
    This court did not receive either the clerk’s record or the reporter’s record for this
    separate proceeding.
    4
    [Hendrickson].
    Hendrickson responded to Heard’s second summary judgment motion and asserted
    that Heard failed to prove as a matter of law the elements of his contract claim.
    Hendrickson asserted that “payment was made in the manner of reduced overall
    costs” for the house’s construction. Hendrickson included his affidavit as an
    exhibit to his response; Hendrickson’s affidavit states, in relevant part:
    [Heard] agreed to do some of the work on the house that was being
    built by [Hendrickson]. In exchange for that work, the totals costs of
    his house would be reduced. It was never agreed that he would be
    paid any cash for his services whatsoever.
    Hendrickson’s response did not address the deemed admissions.
    The trial court granted Heard’s second summary judgment motion in a final
    judgment signed July 6, 2017. Hendrickson timely appealed.
    ANALYSIS
    Hendrickson asserts on appeal two issues challenging the trial court’s July 6,
    2017 final judgment granting Heard’s second summary judgment motion. In his
    first issue, Hendrickson asserts that the deemed admissions “preclude[d]
    presentation of the merits of the case” and “violate due process.” Hendrickson
    claims in his second issue that Heard failed to prove his contract claim as a matter
    of law. We overrule both of Hendrickson’s issues.
    I.     Deemed Admissions
    Hendrickson argues that the deemed admissions are overly broad, merits-
    preclusive, and violate due process. In response, Heard asserts that Hendrickson’s
    challenges to the deemed admissions are waived because “Hendrickson had
    numerous opportunities to withdraw or amend the deemed admissions, but he
    failed to do so.”
    5
    After an action is filed, a party may serve written requests for admission that
    encompass “any matter within the scope of discovery, including statements of
    opinion or of fact or of the application of law to fact . . . .” Tex. R. Civ. P. 198.1;
    Marino v. King, 
    355 S.W.3d 629
    , 632 (Tex. 2011) (per curiam). If the opposing
    party does not respond to the admissions requests within 30 days, the matters in the
    requests are deemed admitted against the party without the necessity of a court
    order. Tex. R. Civ. P. 198.2(c); 
    Marino, 355 S.W.3d at 633
    . A matter deemed
    admitted is conclusively established unless the trial court, on motion, permits
    withdrawal or amendment of the admission. Tex. R. Civ. P. 198.3.
    Unifund CCR Partners v. Weaver, 
    262 S.W.3d 796
    (Tex. 2008) (per
    curiam), analyzed facts similar to those presented here and concluded that the
    defendant waived his ability to challenge the deemed admissions.
    The pro se defendant in Weaver was served with requests for admission; the
    record did not show that the defendant served the plaintiff with his responses. 
    Id. at 797.
    The plaintiff filed a motion for summary judgment “asserting that the facts
    set out in its requests for admissions were automatically admitted when [the
    defendant] failed to timely serve his responses.”       
    Id. The defendant
    did not
    respond to the summary judgment motion and the motion was granted by the trial
    court. 
    Id. The defendant
    first challenged the deemed admissions in a post-judgment
    filing and asserted that he had properly served the plaintiff with his responses. 
    Id. The supreme
    court held that the defendant “waived his right to challenge the
    deemed admissions.” 
    Id. at 798.
    Noting that the plaintiff’s “motion for summary
    judgment put [the defendant] on notice of the deficiency of his response,” the court
    stated that the defendant “knew of his mistake before judgment and could have
    responded to [the plaintiff’s] motion, but because he did not, he waived his right to
    6
    raise the issue thereafter.” Id.; see also Cleveland v. Taylor, 
    397 S.W.3d 683
    , 693-
    95 (Tex. App.—Houston [1st Dist.] 2012, pet. denied) (the defendants did not
    respond to the plaintiffs’ requests for admissions and challenged the requests only
    after the trial court rendered judgment despite earlier “notice of their mistake;” the
    court held that the defendants’ challenges to the deemed admissions were waived);
    Johnson v. Lewis, No. 14-10-00293-CV, 
    2011 WL 2083965
    , at *3 (Tex. App.—
    Houston [14th Dist.] May 19, 2011, no pet.) (mem. op.) (the defendants, although
    aware of their failure to serve responses to the plaintiff’s requests for admission,
    did not challenge the admissions until after summary judgment was granted; the
    defendants waived the right to challenge the admissions on appeal).
    Hendrickson’s failure to challenge the deemed admissions in the trial court
    waives his ability to raise these issues for the first time on appeal.
    The record shows that Hendrickson had notice of his failure to respond to
    the requests for admission. Heard filed a motion requesting the trial court deem
    admitted his requests for admission because of Hendrickson’s failure to respond.
    The trial court granted Heard’s request in a signed order. Heard’s first and second
    summary judgment motions substantially relied on the deemed admissions.
    Hendrickson’s response to Heard’s second summary judgment motion did not
    challenge the propriety of the deemed admissions and asserted only that the
    admissions failed to prove Heard’s contract claim as a matter of law.
    Like the defendant in Weaver, Hendrickson was on notice of his failure to
    respond to Heard’s requests for admission. See 
    Weaver, 262 S.W.3d at 797-87
    .
    Despite this notice, Hendrickson did not raise in the trial court his challenges to the
    deemed admissions. We decline to consider these issues for the first time on
    appeal. See Weaver, 
    262 S.W.3d 797-98
    ; 
    Cleveland, 397 S.W.3d at 693-95
    ; see
    also Johnson, 
    2011 WL 2083965
    , at *3.
    7
    Hendrickson relies on Wheeler v. Green, 
    157 S.W.3d 439
    (Tex. 2005) (per
    curiam), to support his claim that the deemed admissions give rise to due process
    concerns, but Wheeler is distinguishable from the facts presented here.
    The pro se litigant in Wheeler filed her responses to the requests for
    admissions two days late because of a miscalculation with respect to the mailbox
    rule. 
    Id. at 441.
    The supreme court held that the litigant did not waive her
    complaint regarding withdrawal of the deemed admissions by presenting it for the
    first time in her motion for new trial because “nothing in this record suggests that
    before summary judgment was granted, [the litigant] realized that her responses
    were late, that she needed to move to withdraw deemed admissions, or that she
    needed to file a response to the summary judgment raising either argument.” 
    Id. at 442.
    Unlike the litigant in Wheeler, Hendrickson was on notice of his failure to
    respond to Heard’s requests for admission. Despite this notice, Hendrickson did
    not seek to withdraw the admissions and did not address the admissions in his
    response to Heard’s second summary judgment motion. Hendrickson raised his
    challenges to the deemed admissions for the first time on appeal.
    We overrule Hendrickson’s first issue.
    II.      Summary Judgment
    In his second issue, Hendrickson asserts the trial court erred in granting
    Heard’s motion for traditional summary judgment because Heard failed to prove
    the elements of his contract claim as a matter of law. Hendrickson does not
    contend on appeal that a fact issue exists.
    A.    Standards of Review
    The party moving for traditional summary judgment bears the burden of
    8
    showing that there is no genuine issue as to any material fact and that it is entitled
    to judgment as a matter of law. Tex. R. Civ. P. 166a(c); see also Mann Frankfort
    Stein & Lipp Advisors, Inc., 
    289 S.W.3d 844
    , 848 (Tex. 2009). If the moving party
    meets this burden, the burden shifts to the nonmovant to raise a genuine, material
    fact issue sufficient to defeat summary judgment. M.D. Anderson Hosp. & Tumor
    Inst. v. Willrich, 
    28 S.W.3d 22
    , 23 (Tex. 2000) (per curiam).
    We review a summary judgment de novo. Travelers Ins. Co. v. Joachim,
    
    315 S.W.3d 860
    , 862 (Tex. 2010). We consider all the evidence in the light most
    favorable to the nonmovant, crediting evidence favorable to the nonmovant if
    reasonable jurors could and disregarding contrary evidence unless reasonable
    jurors could not. Mack Trucks, Inc. v. Tamez, 
    206 S.W.3d 572
    , 582 (Tex. 2006).
    The evidence raises a genuine issue of fact if reasonable and fair-minded jurors
    could differ in their conclusions in light of all the summary judgment evidence.
    Goodyear Tire & Rubber Co. v. Mayes, 
    236 S.W.3d 754
    , 755 (Tex. 2007) (per
    curiam).
    Deemed admissions are competent summary judgment evidence.                In re
    Estate of Herring, 
    970 S.W.2d 583
    , 587 (Tex. App.—Corpus Christi 1998, no
    pet.); see also Rowlands v. Unifund CCR, No. 14-05-01122-CV, 
    2007 WL 1395101
    , at *3 (Tex. App.—Houston [14th Dist.] Mar. 27, 2007, no pet.) (mem.
    op.). To the extent deemed admissions address the elements of proof of a claim,
    the admissions “provide uncontroverted proof of these elements as a matter of
    law.” Rowlands, 
    2007 WL 1395101
    , at *3. A party may not introduce testimony
    to controvert a deemed admission. Marshall v. Vise, 
    767 S.W.2d 699
    , 700 (Tex.
    1989).
    To recover for a breach of contract, a plaintiff must show (1) the existence of
    a valid contract; (2) the plaintiff performed or tendered performance; (3) the
    9
    defendant breached the contract; and (4) the plaintiff suffered damages because of
    the defendant’s breach. Parker Drilling Co. v. Romfor Supply Co., 
    316 S.W.3d 68
    ,
    72 (Tex. App.—Houston [14th Dist.] 2010, pet. denied).
    B.      Application of Legal Standards
    Heard’s summary judgment evidence established his breach of contract
    claim as a matter of law.
    The deemed admissions show that a contract existed between Hendrickson
    and Heard. According to the deemed admissions, Hendrickson and Heard entered
    into the contract to build a house on Heard’s property and “Hendrickson hired
    [Heard] to perform some of the work . . . .” The existence of the contract also is
    supported by Heard’s other summary judgment evidence, including the exhibit
    labeled “Bank Contract Signed by both Parties and Bank Draws,” the exhibit
    labeled “Check Copies for Expenditures,” and Heard’s affidavit.
    The deemed admissions and Heard’s affidavit also show that (1) Heard
    performed construction work on the house; (2) Hendrickson did not pay Heard for
    the work Heard performed; and (3) the work Heard performed was worth $38,746.
    This evidence is sufficient to establish the elements of Heard’s contract claim as a
    matter of law. See 
    id. at 72;
    see also Rowlands, 
    2007 WL 1395101
    , at *2-3
    (deemed admissions established the plaintiff’s breach of contract claim as a matter
    of law).
    Hendrickson argues that “[a] conclusory admission that there is a contract
    between two people . . . is insufficient to prove that the contract is valid or
    enforceable.” Hendrickson does not cite any authority to support his contention
    that Heard’s summary judgment evidence amounts only to a “conclusory
    admission.”
    10
    A “conclusory” statement is defined as “‘[e]xpressing a factual inference
    without stating the underlying facts on which the inference is based.’” La China v.
    Woodlands Operating Co., 
    417 S.W.3d 516
    , 520 (Tex. App.—Houston [14th Dist.]
    2013, no pet.) (quoting Arkoma Basin Expl. Co. v. FMF Assocs. 1990-A, Ltd., 
    249 S.W.3d 390
    , 389 n.32 (Tex. 2008)).         Here, the summary judgment evidence
    addressed facts underlying the contract between Heard and Hendrickson and
    indicated that the purpose of the agreement was to build a house on Heard’s
    property.   Despite Hendrickson’s contention, the summary judgment evidence
    amounts to more than a “conclusory admission.” See 
    id. Hendrickson asserts
    that Heard cannot show that the contract was breached
    because “[r]eduction of the house price was the compensation owed for [Heard’s]
    work.” This argument appears to invoke an affirmative defense. See Tex. R. Civ.
    P. 194 (affirmative defenses include offset, accord and satisfaction, payment, and
    release); see also MAN Engines & Components, Inc. v. Shows, 
    434 S.W.3d 132
    ,
    137 (Tex. 2014) (“An affirmative defense presents a situation where a plaintiff
    cannot recover even if his claims are true because of some other fact that the
    defendant has pled as a bar.” (internal quote omitted)); Hassell Constr. Co. v.
    Stature Commercial Co., Inc., 
    162 S.W.3d 664
    , 667 (Tex. App.—Houston [14th
    Dist.] 2005, no pet.) (as a general rule, there must be specific pleading of excuses
    for nonperformance of a contract).
    “All affirmative defenses are waived when the defendant files only a general
    denial, and, absent trial by consent, failure to plead a matter of affirmative defense
    will preclude a defendant from asserting it.” Hassell Constr. Co., 
    Inc., 162 S.W.3d at 667
    . Hendrickson filed a general denial that did not plead any affirmative
    defenses. The record does not indicate that any affirmative defenses were tried by
    consent. Failing to plead any affirmative defenses waived Hendrickson’s argument
    11
    that a price reduction compensated Heard for the work performed on the
    construction project. See Tex. R. Civ. P. 194; MAN Engines & Components, 
    Inc., 434 S.W.3d at 137
    ; Hassell Constr. 
    Co., 162 S.W.3d at 667
    .
    Finally, Hendrickson contends the amount of damages cannot be calculated
    based on the deemed admissions. Hendrickson cites Resurgence Financial, LLC v.
    Taylor, 
    295 S.W.3d 429
    (Tex. App.—Dallas 2009, pet. denied).
    The court in Resurgence Financial, LLC held that the plaintiff’s evidence
    was insufficient to support a damages award for a breach of contract claim
    stemming from the defendant’s credit card debt. 
    Id. at 434.
    The court stated that
    “[t]here was not only insufficient information from which to calculate the interest
    due on the outstanding account balance, the evidence that was submitted conflicted
    as to the rate of interest to be charged.” 
    Id. Here, the
    summary judgment evidence is sufficient to calculate the damages
    awarded in the trial court’s final judgment. The deemed admissions and Heard’s
    affidavit state that Heard performed work worth $38,746 and did not receive any
    payment from Hendrickson for that work. In its final judgment signed July 6,
    2017, the trial court awarded Heard $38,746 in damages plus pre- and post-
    judgment interest as provided by statute. See Tex. Fin. Code Ann. § 302.001
    (Vernon 2016).      We reject Hendrickson’s contention that the evidence was
    insufficient to support the trial court’s damages award.
    We overrule Hendrickson’s second issue.
    12
    CONCLUSION
    We overrule Hendrickson’s issues on appeal and affirm the trial court’s July
    6, 2017 final judgment granting Heard’s motion for traditional summary judgment.
    /s/    William J. Boyce
    Justice
    Panel consists of Justices Boyce, Donovan, and Wise.
    13