LBSP, Inc. v. Forest Dale, Inc. ( 2016 )


Menu:
  • Affirmed; Opinion Filed June 7, 2016.
    In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-14-01295-CV
    LBSP, INC., Appellant
    V.
    FOREST DALE, INC., Appellee
    On Appeal from the 162nd Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-13-10542
    MEMORANDUM OPINION
    Before Justices Francis, Evans, and Stoddart
    Opinion by Justice Evans
    Appellant LBSP, Inc. asserts that the trial court committed reversible error by
    (1) granting appellee Forest Dale, Inc.’s motion for summary judgment and (2) sustaining Forest
    Dale’s objections to LBSP’s summary judgment evidence. We affirm.
    BACKGROUND
    Forest Dale is the owner of Forest Dale Apartments, an independent living community
    for senior citizens. The United States Department of Housing and Urban Development (“HUD”)
    is the owner and holder of two promissory notes secured by the property. In 2010, Forest Dale
    and LBSP entered into a contract in which LBSP agreed to purchase the property from Forest
    Dale. The contract had an effective date of October 4, 2010. It also had an approval period of
    twenty-four months which ended on October 4, 2012. During the approval period, LBSP could
    determine whether it wanted to buy the property. Section 8.1 of the contract provided for a
    “Closing Date” which was “one hundred twenty (120) days after the expiration of the Approval
    Period” (January 31, 2013). Section 8.1 also provided that “[i]f applicable, the Closing Date
    shall be automatically extended to the date which is one hundred twenty (120) days after the date
    [LBSP] has received written notice that (i) [Forest Dale] has satisfied all title conditions and
    (ii) the HUD Approval has been obtained.” In short, LBSP was required to close on the sale by
    January 31, 2013 unless the parties agreed to a different date or LBSP was entitled to an
    extension.
    The contract also contained a provision regarding the debt owed by Forest Dale to HUD.
    The contract noted that HUD took the position that any prepayment required its approval which
    it had previously refused to provide. Forest Dale and LBSP wanted to obtain either HUD
    approval for prepayment or a final judicial determination that HUD approval for prepayment was
    not required. Accordingly, in the contract, Forest Dale authorized LBSP, at LBSP’s expense, to
    obtain such approval on Forest Dale’s behalf and to initiate litigation to obtain a judicial
    determination that HUD approval was not required.
    The closing did not occur. LBSP sent Forest Dale a letter dated January 30, 2013,
    claiming to invoke the HUD-approval 120-day extension of the closing date beyond January 31,
    2013.    On March 4, 2013, Forest Dale notified LBSP by letter that the extension was
    inapplicable and the contract had expired.
    LBSP continued to pursue HUD approval and filed suit against Forest Dale alleging
    breach of contract and seeking specific performance of the contract. In the petition, LBSP
    alleged that although it did submit a proposal to HUD for the prepayment of the HUD
    indebtedness, it was delayed in submitting the proposal because Forest Dale did not provide the
    necessary financial information.
    –2–
    In its answer, Forest Dale alleged that LBSP was required to use “reasonable efforts” to
    obtain HUD approval prior to closing the real estate transaction. Forest Dale alleged that it
    “timely provided all of LBSP’s requested due diligence items” but that LBSP did not formally
    seek HUD approval until December 4, 2012, two years and two months after the contract’s
    effective date and fifty-nine days before the end of the 120 day closing period.1 Forest Dale
    argued that because LBSP failed to obtain HUD approval, or use reasonable efforts to obtain
    HUD approval, that the contract expired.                Forest Dale then asserted a counterclaim for
    declaratory judgments that (1) the contract had terminated,2 and (2) LBSP failed to use
    reasonable efforts to obtain HUD approval.
    Forest Dale also filed a traditional summary judgment motion on its counterclaim and on
    all of LBSP’s claims, asserting three independent grounds: (1) the contract had terminated
    according to its terms; (2) LBSP failed to use reasonable efforts to obtain HUD approval; and
    (3) alternatively, LBSP failed to obtain HUD approval within a reasonable time.
    The trial court granted a partial summary judgment to Forest Dale in the form of
    declaratory relief and determined that:            (1) the contract required LBSP to close within a
    reasonable amount of time and LBSP had not done so; (2) the contract was no longer in force;
    and (3) LBSP failed to use reasonable efforts to obtain HUD approval pursuant to the contract.
    Forest Dale nonsuited its claim for attorney’s fees and the trial rendered final judgment. LBSP
    filed this appeal.
    1
    Forest Dale specifically argued in the motion that it provided all of the due diligence items to LBSP by
    December 2010 with the exception of a property survey.
    2
    Forest Dale specifically requested that the trial court declare: (1) the contract permitted LBSP to have
    only a reasonable period of time after the expiration of 120 days after the approval period to close; (2) LBSP has
    failed to close within a reasonable period of time after the expiration of 120 days after the approval period; and
    (3) the contract is terminated and of no further force or effect.
    –3–
    ANALYSIS
    A.      Summary Judgment
    In its first issue, LBSP challenges the summary judgment arguing that there was at least a
    genuine issue of material fact regarding whether or not LBSP had a reasonable amount of time to
    close the transaction.
    1)        Standard of review
    We review the trial court’s traditional summary judgment de novo.             See Valence
    Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005). The party moving for summary
    judgment bears the burden of proof. Neely v. Wilson, 
    418 S.W.3d 52
    , 59 (Tex. 2013). Under
    rule 166a(c), the moving party must show that no genuine issue of material fact exists and that it
    is entitled to judgment as a matter of law. See TEX. R. CIV. P. 166a(c); W. Inv., Inc. v. Urena,
    
    162 S.W.3d 547
    , 550 (Tex. 2005). Further, in reviewing a summary judgment, we consider the
    evidence in the light most favorable to the non-movant and resolve any doubt in the non-
    movant’s favor. 
    Urena, 162 S.W.3d at 550
    . When a trial court’s order granting summary
    judgment does not specify the grounds upon which it was granted, reviewing courts will affirm
    the judgment if any of the grounds presented to the trial court in the motion for summary
    judgment that have been preserved for appellate review are meritorious. Provident Life &
    Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 216 (Tex. 2003).
    2)        Failure to Close within Reasonable Time
    LBSP argues that the trial court committed reversible error when it granted summary
    judgment to Forest Dale on its counterclaim and dismissed LBSP’s claim for specific
    performance on the ground that LBSP failed to close within a reasonable period of time after the
    –4–
    expiration of 120 days after the approval period.3 In essence, the trial court decided summary
    judgment on the basis of the more lenient of the two possible closing dates: (1) the January 31,
    2013 closing date because HUD approval had not been obtained by that date; or (2) a reasonable
    time after the January 31, 2013 closing date to obtain HUD approval and then close. We will
    limit our review to the trial court’s decision.
    i) Ground for summary judgment
    LBSP first argues that the trial court erred because Forest Dale did not seek summary
    judgment on this ground. We disagree. On the first page of its motion for summary judgment,
    Forest Dale argues that the “plain language of the Contract makes clear that it has terminated.”
    In its first ground for summary judgment, Forest Dale argued that the contract terminated on
    January 31, 2013 (120 days after the expiration of the approval period). However, Forest Dale
    also made an alternative argument in its summary judgment motion that “even if the Contract is
    interpreted to permit closing within a ‘reasonable time,’ such time has long passed as a matter of
    law.”     Forest Dale clarified in its summary judgment motion that “even if LBSP is correct in
    that the possible extension for the Closing Date does not apply until LBSP obtains HUD
    Approval,” then LBSP should have closed the contract in a reasonable amount of time after the
    closing date. Accordingly, Forest Dale clearly sought summary judgment on the ground that the
    contract terminated based on LBSP having only a reasonable amount of time after the expiration
    of the 120 days after the approval period and LBSP failed to close within a reasonable amount of
    time.
    3
    This addresses appellant’s sub-issue 1(A) regarding Forest Dale’s declaratory judgment counterclaim and the
    third argument of sub-issue 1(C) related to the dismissal by summary judgment of LBSP’s claim for specific
    performance.
    –5–
    ii) Failed to interpret section 8.1 in context of whole contract
    LBSP next argues the trial court relied upon section 8.1 of the contract in isolation rather
    than interpreting that section in the context of the whole contract when the trial court decided
    that LBSP had only a reasonable period of time after the January 31, 2013 closing date. In
    support of this contention, LBSP argues that the trial court failed to harmonize the entire contract
    by incorrectly determining that (1) the extension of 120 days following January 31, 2013 in
    section 8.1 of the contract was not an automatic extension and (2) the thirty-two days between
    January 31 and March 4 was a reasonable amount of time to close the contract.               Again, we
    disagree with LBSP’s arguments and will address each argument in sequence.
    Our primary concern in contract interpretation is to ascertain the true intentions of the
    parties as expressed in the agreement. FPL Energy, LLC v. TXU Portfolio Mgmt. Co, L.P., 
    426 S.W.3d 59
    , 63 (Tex. 2014). We consider the entire writing to harmonize and effectuate all
    provisions such that none are rendered meaningless. 
    Id. Also, we
    construe contracts from a
    utilitarian standpoint bearing in mind the particular business activity to be served. 
    Id. LBSP first
    argues that the trial court failed to take into consideration sections 7.6.7 and
    7.7 (regarding possibility of judicial determination before closing), 9.1 (pertaining to purchaser’s
    available remedies upon seller’s default), and 15.13 (standstill agreement) of the contract when
    determining that the HUD-approval 120-day extension following January 31, 2013 was not
    automatic.    None of these contractual provisions, however, conflict with the trial court’s
    conclusion that the HUD-approval 120-day extension was only triggered if LBSP had obtained
    HUD approval. Although the contract does anticipate that litigation over HUD approval could
    take place, the contract also provided LBSP with over two years to complete the task of
    obtaining HUD approval or obtain through litigation a determination that HUD’s approval was
    not necessary. Neither the default by seller provision nor the standstill agreement provision
    –6–
    contain language which conflict with the trial court’s conclusion. Instead, the plain language of
    section 8.1 speaks for itself and provides that the closing date would only be extended an
    additional 120 days if the HUD approval had already been obtained. As LBSP had not obtained
    HUD approval by January 31, 2013 or within a reasonable time thereafter, we conclude that the
    closing date was not automatically extended for another 120 days.
    LBSP further argues that the trial court must have determined that the closing should take
    place before March 4, 2013 because on that date Forest Dale sent notice to LBSP terminating the
    contract. LBSP argues thirty-two days between January 31 and March 4 was not a reasonable
    amount of time to close the contract. The trial court, however, never specified a date in its
    summary judgment order. Instead, it simply concluded that “LSBP failed to close within a
    reasonable period of time after the expiration of 120 days after the Approval Period.” Further,
    Forest Dale’s April 2, 2014 motion for summary judgment contended that “the parties never
    closed” and its undisputed summary judgment evidence was that it owned the property. Thus,
    Forest Dale established as a matter of law that LBSP did not close within the fifteen months
    following the January 31, 2013 closing date and that was a reasonable amount of time for LBSP
    to perform under the contract.4
    iii) No genuine issue of material fact
    Finally, LBSP argues that what constitutes a “reasonable amount of time” is a fact issue
    that cannot be decided by summary judgment. Forest Dale argues that a “reasonable time” may
    be determined as a matter of law. The courts themselves appear to have decided that the issue is
    a mixed question of law and fact:
    4
    In its motion for summary judgment, Forest Dale argued this period as “approximately 3.5 years after the
    Effective Date” and contended “Forest Dale still has no indication that LBSP has obtained HUD Approval.”
    Although that supported Forest Dale’s ground for summary judgment, LBSP challenges, so we analyze here, the
    reasonableness of the amount of time after the end of the contractual closing period, January 31, 2013.
    –7–
    Some authorities hold that the question of what is a reasonable time is one of law
    for the court, while others hold it is a question of fact for the jury. The proper
    view seems to be that it is a matter of law for the court, when it depends upon the
    construction of a contract in writing or upon undisputed facts, and that it is a
    question of fact for the jury when it depends upon facts extrinsic to the contract,
    and which are matters in dispute.
    McGary v. Campbell, 
    245 S.W. 106
    , 115 (Tex. Civ. App.—Beaumont 1922, writ dism’d w.o.j.).
    Here, the undisputed fact is that LBSP did not obtain HUD approval. Without HUD approval,
    there was no trigger for section 8.1’s 120-day extension to apply.                       Thus, the trial court
    determined that LBSP only had a reasonable amount of time after January 31, 2013 to perform
    under the contract. The trial court could also determine, as a matter of law, whether LBSP
    received a reasonable amount of time to perform. See KMI Cont’l Offshore Prod. Co. v. ACF
    Petroleum Co., 
    746 S.W.2d 238
    , 243 (Tex. App.—Houston [1st Dist.] 1987, writ denied)
    (“[W]hen the material facts relating to whether a party acted in a reasonable time period are
    undisputed, a court can resolve the issue as a matter of law.”); Pearcy v. Envtl. Conservancy of
    Austin & Cent. Tex., Inc., 
    814 S.W.2d 243
    , 246 (Tex. App.—Austin 1991, writ denied) (“Where
    the material facts are undisputed, the question of what is a reasonable time is a matter of law.”).
    The trial court could determine as a matter of law that the fifteen months following the closing
    period was a reasonable amount of time for LBSP to perform under the contract. See KMI Cont’l
    Offshore Prod. 
    Co., 746 S.W.2d at 245
    (holding that 20 months was an unreasonable and unfair
    length of time as a matter of law to perform under contract). For all the reasons stated above, the
    trial court did not err when it (1) granted Forest Dale’s traditional summary judgment motion on
    this ground and (2) dismissed LBSP’s claim for specific performance on this ground.5
    5
    As we have affirmed the trial court’s decision, it is unnecessary for us to reach Forest Dale’s cross-point in
    regard to sub-issue 1(A).
    –8–
    3)      Remaining Contract Issues
    As we affirm the trial court’s grant of summary judgment to Forest Dale on its
    counterclaim and the dismissal of LBSP’s claim for specific performance on the ground that
    LBSP failed to close within a reasonable period of time after the expiration of 120 days after the
    approval period, we need not reach appellant’s remaining sub-issues. Having so concluded, we
    resolve the first issue against LBSP.
    B.      Objections to LBSP’s Summary Judgment Evidence
    In its second issue, LBSP challenges the trial court’s summary judgment evidentiary
    rulings.
    1)      Standard of review
    We review a trial court’s ruling on the admissibility of evidence for an abuse of
    discretion. See Serv. Corp. Intern. v. Guerra, 
    348 S.W.3d 221
    , 235 (Tex. 2011). A trial court
    abuses its discretion when it rules without regard for any guiding rules or principles. See Owens-
    Corning Fiberglas Corp. v. Malone, 
    972 S.W.2d 35
    , 43 (Tex. 1998). An appellate court must
    uphold the trial court’s evidentiary ruling if there is any legitimate basis for the ruling. 
    Id. We will
    not reverse a trial court for an erroneous evidentiary ruling unless the error probably caused
    the rendition of an improper judgment. DeSoto Wildwood Dev., Inc. v. City of Lewisville, 
    184 S.W.3d 814
    , 828 (Tex. App.—Fort Worth 2006, no pet.).
    2)      Analysis
    LBSP submitted the affidavit of Lawrence Burk in support of its response to Forest
    Dale’s summary judgment motion. Forest Dale filed objections that certain of Burk’s statements
    violated the best evidence rule and that the contract should speak for itself. The trial court
    sustained certain objections and denied other objections to particular statements in the Burk
    –9–
    affidavit. LBSP argues that the trial court committed reversible error in sustaining Forest Dale’s
    objections. We disagree.
    The best evidence rule provides that “an original writing, recording, or photograph is
    required in order to prove its content unless these rules or other law provides otherwise.” See
    TEX. R. EVID. 1002. The rule does not apply unless a party is seeking to prove the contents of a
    document. See DeSoto Wildwood Dev., 
    Inc., 184 S.W.3d at 828
    . LBSP argues that the best
    evidence rule is inapplicable in this case because the contract was already in evidence when the
    trial court struck these paragraphs of the affidavit.      We cannot conclude that LBSP has
    demonstrated how this alleged erroneous evidentiary ruling caused the rendition of an improper
    judgment. 
    Id. As the
    affidavit paragraphs at issue summarized paragraphs of the contract, we
    cannot conclude that LBSP has suffered harm from the striking of this evidence because the
    contract itself was admitted into evidence. Both parties directly refer to the text of the contract
    when arguing its meaning; no argument depends on what a witness stated the text to mean.
    Without harm, there is no reversible error and we resolve the second issue against LBSP.
    CONCLUSION
    LBSP’s issues on appeal are overruled and we affirm the trial court’s judgment.
    /David Evans/
    DAVID EVANS
    JUSTICE
    141295F.P05
    –10–
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    LBSP, INC., Appellant                                 On Appeal from the 162nd Judicial District
    Court, Dallas County, Texas
    No. 05-14-01295-CV         V.                         Trial Court Cause No. DC-13-10542.
    Opinion delivered by Justice Evans.
    FOREST DALE, INC., Appellee                           Justices Francis and Stoddart participating.
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    AFFIRMED.
    It is ORDERED that appellee FOREST DALE, INC. recover its costs of this appeal from
    appellant LBSP, INC.
    Judgment entered this 7th day of June, 2016.
    –11–