Akram Mushtaha v. Tile Roofs of Texas ( 2014 )


Menu:
  • Affirmed and Memorandum Opinion filed December 11, 2014.
    In The
    Fourteenth Court of Appeals
    NO. 14-13-00793-CV
    AKRAM MUSHTAHA, Appellant
    V.
    TILE ROOFS OF TEXAS, Appellee
    On Appeal from the 129th District Court
    Harris County, Texas
    Trial Court Cause No. 2010-31789
    MEMORANDUM OPINION
    This is an appeal from a final judgment rendered after a trial by jury. The
    question is whether the evidence is legally and factually sufficient to support the
    jury’s findings. For the reasons explained below, we conclude that the evidence is
    sufficient, and we affirm the trial court’s judgment.
    BACKGROUND
    This case is a breach of contract action between a roofing company and a
    homeowner. The primary dispute focuses on the installation of tile shingles in an
    area of the roof known as the valley. The valley is the site where two planes of the
    roof intersect and form a trough. A valley can be found wherever one portion of
    the roof branches out from another on a perpendicular angle, such as a dormer. The
    valley is sloped so that it may function as a conduit, collecting rainwater from the
    sides of the roof and channeling it away from the structure. Its design is intended to
    prevent rainwater from pooling.
    A valley can be either open or closed. When a valley is open, its metal lining
    is visible to the naked eye. When a valley is closed, the lining is covered by the
    same material used to shingle the roof. Both methods of installation are accepted
    within the industry.
    As will be seen in this case, one advantage of having a closed valley system
    is aesthetics: the shingles blend together seamlessly between all planes of the roof,
    creating a uniform look. There is a disadvantage, however. Over time, the
    functionality of a closed valley system can deteriorate in the presence of certain
    environmental factors. If leaves, pine needles, or other debris accumulate in the
    valley, they can impede the natural drainage of the roof. And in really bad cases,
    this accumulation can cause rainwater to spill under the shingles adjacent to the
    valley, causing the roof to leak.
    Akram Mushtaha, the homeowner in this case, had a tile roof with a closed
    valley system that was damaged by Hurricane Ike. Mushtaha entered into a
    contract with Tile Roofs of Texas to replace the roof on his home. The contract
    provided that the tile was to be installed “as per industry specifications” and that
    the valleys were “to be open.” Mushtaha did not inquire into the meaning of these
    2
    terms. His only concern during the negotiation stage was the cost of the project.
    The parties bargained for a contract price of $102,000, with fifty percent due at
    signing and the rest due upon completion.
    During the demolition process, Tile Roofs found that Mushtaha’s closed
    valley system had not been functioning properly. The valleys were heavily clogged
    with dirt and debris. When the tile was removed, the plywood under the valleys
    was rotting. The rot showed several years’ worth of water intrusion, which
    predated Hurricane Ike. Tile Roofs replaced the plywood at no additional cost to
    Mushtaha.
    As the new tile was being installed, Mushtaha noticed that the valleys on his
    new roof were not resembling the valleys on his old roof. Mushtaha demanded that
    Tile Roofs change the valleys to make them closed. Tile Roofs explained to
    Mushtaha that the valleys were being installed according to the terms of the
    contract. Tile Roofs also advised that a closed valley system was not recommended
    because Mushtaha lived in a wooded area with tall trees, and debris from those
    trees had accumulated in the valleys and had caused his previous roof to leak.
    Mushtaha complained as well about the appearance of the tiles at the edge of
    his roof, in an area known as the rake. Mushtaha demanded that Tile Roofs
    reinstall the rake tiles to make them appear as before. Tile Roofs responded that the
    original installation of the rake tiles had been backwards. Tile Roofs explained that
    installing the rake tiles in any manner contrary to the industry specifications would
    cause the roof to leak, leading to the destruction of the fascia boards.
    Mushtaha persisted, stating that he wanted his new roof to look exactly as
    his old roof. Tile Roofs offered to redo the valleys as closed and to install the rake
    tiles backwards, but only if Mushtaha paid for the extra labor and waived his
    warranty by signing a letter acknowledging that he had requested the installation to
    3
    be against the manufacturer’s instructions. Mushtaha refused the offer and ordered
    Tile Roofs to leave his property.
    At the time of the parties’ disagreement, the new roof was between eighty
    and eighty-five percent complete. Mushtaha hired another roofing company to
    finish the roof in the manner he desired. Tile Roofs was never invited back to the
    premises, despite several attempts to resolve the parties’ dispute.
    Tile Roofs filed this lawsuit, alleging a single cause of action for breach of
    contract. Mushtaha counterclaimed, but the counterclaims were dismissed. At trial,
    Tile Roofs produced evidence showing that it had spent $60,000 on labor and
    materials, and that it would have realized a profit of $20,000 as of the time it was
    ordered to stop working. Mushtaha responded that Tile Roofs had been installing
    the new roof against industry standards, and he claimed that Tile Roofs had
    repudiated the contract by choosing to walk away from the project.
    The jury made the following findings: (1) Mushtaha failed to comply with
    the contract; (2) Mushtaha’s failure to comply was not excused; and (3) Tile Roofs
    was entitled to $27,500 in damages, plus attorney’s fees.
    ISSUES PRESENTED
    Mushtaha appears pro se on appeal, and he asserts several issues in his brief.
    However, not all of the issues are presented in a manner that comports with the
    Texas Rules of Appellate Procedure. For example, Mushtaha asserts early in his
    brief that he intends to challenge the award of attorney’s fees and the striking of his
    counterclaims, but there are no arguments on either point. Without arguments,
    Mushtaha has failed to comply with the appellate briefing rules. Accordingly, we
    overrule these points as inadequately briefed. See Tex. R. App. P. 38.1(i).
    4
    We limit our review to the only issues that have been adequately presented:
    whether the evidence is legally and factually sufficient to support the jury’s
    findings on liability and damages.
    ANALYSIS
    A.    Breach
    We begin with the jury’s finding that Mushtaha failed to comply with the
    terms of the contract. In a legal sufficiency challenge, we consider the evidence in
    the light most favorable to the verdict, indulging every reasonable inference that
    would support the challenged finding, crediting favorable evidence if a reasonable
    factfinder could, and disregarding contrary evidence unless a reasonable factfinder
    could not. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 819, 827 (Tex. 2005). We
    will sustain a legal sufficiency challenge only when (1) there is a complete absence
    of evidence of a vital fact, (2) the court is barred by rules of law or evidence from
    giving weight to the only evidence offered to prove a vital fact, (3) the evidence
    offered to prove a vital fact is no more than a mere scintilla, or (4) the evidence
    conclusively establishes the opposite of the vital fact. 
    Id. at 810.
    The record reflects that Mushtaha executed a contract with Tile Roofs to
    replace his roof. After a dispute arose over the appearance of the new roof,
    Mushtaha ordered Tile Roofs to stop working and leave his property. Mushtaha
    never permitted Tile Roofs to reenter the property and finish the project, even
    though Tile Roofs was willing and able to finish. Mushtaha also failed to pay Tile
    Roofs any amount beyond the initial deposit. Based on this record, we conclude
    that the evidence is legally sufficient to show that Mushtaha breached the contract.
    See Tacon Mech. Contractors, Inc. v. Grant Sheet Metal, Inc., 
    899 S.W.2d 666
    ,
    670 (Tex. App.—Houston [14th Dist.] 1994, writ denied) (“When one party to a
    5
    contract, by wrongful means, prevents the other party from performing, this
    interference with performance constitutes breach of contract.”).
    Mushtaha argues next that the evidence is factually insufficient to support
    the finding of breach. When a party challenges the factual sufficiency of a finding
    for which he did not bear the burden of proof at trial, we review all of the evidence
    in a neutral light and will reverse only if the evidence supporting the finding is so
    contrary to the overwhelming weight of the evidence as to make the judgment
    clearly wrong and manifestly unjust. See Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 406–07 (Tex. 1998). Under this standard, we may not pass upon the
    credibility of witnesses or substitute our judgment for that of the factfinder, even if
    the evidence would clearly support a different result. 
    Id. at 407.
    Mushtaha contends that the evidence is factually insufficient because the
    record shows that he was willing to pay for a new roof if Tile Roofs duplicated his
    old roof. This point is a red herring. The contract did not provide for the
    “duplication” of Mushtaha’s old roof. By expressly stating that the valleys would
    be open rather than closed, the contract clearly indicated that the new roof would
    look and function differently from the old roof. The contract also expressly stated
    that the roof would be installed “as per industry specifications.” The jury was
    asked to determine whether Mushtaha had breached this contract, and it is against
    that question that we must measure the sufficiency of the evidence. See St. Joseph
    Hosp. v. Wolff, 
    94 S.W.3d 513
    , 530 (Tex. 2003); Kamat v. Prakash, 
    420 S.W.3d 890
    , 899 (Tex. App.—Houston [14th Dist.] 2014, no pet.). Mushtaha cannot show
    that the jury’s finding of breach is clearly wrong and manifestly unjust because he
    would have performed under a different contract.
    Mushtaha argues next that the evidence is factually insufficient because the
    contract is ambiguous, and when the contract is construed in his favor, the record
    6
    shows that he did not fail to comply with it. Mushtaha believes that the contract is
    ambiguous because the words “industry specifications” and “open” valleys are
    undefined and capable of more than one reasonable interpretation. Even if we
    assumed that the contract were ambiguous, Mushtaha’s understanding of the
    parties’ intent was not conclusively established, and Mushtaha neither requested
    nor submitted to the jury any fact question regarding the issue of intent. Mushtaha
    waived any complaint about the contract’s alleged ambiguity. See Tex. R. Civ. P.
    279; Tex. R. App. P. 33.1.
    Mushtaha cites to no other evidence tending to show that he did not breach
    the terms of the contract. We accordingly conclude that the jury’s finding in
    support of breach is not so against the great weight and preponderance of the
    evidence as to render the judgment clearly wrong and manifestly unjust.
    B.    Excuse
    The second jury question asked, “Was Mushtaha’s failure to comply
    excused?” The charge instructions provided that the “failure to comply by
    Mushtaha is excused by Tile Roofs’ previous failure to comply with a material
    obligation of the same Agreement.” The jury answered the question in the
    negative. As before, Mushtaha asserts that the evidence is legally and factually
    insufficient to support the jury’s finding.
    Mushtaha had the burden at trial to demonstrate that his breach of contract
    was excused. See Sassoon v. Thompson, No. 14-02-00154-CV, 
    2003 WL 358703
    ,
    at *3 (Tex. App.—Houston [14th Dist.] Feb. 20, 2003, pet. denied) (mem. op.).
    When a party attacks the legal sufficiency of an adverse finding on an issue on
    which he bears the burden of proof, the party must demonstrate on appeal that the
    evidence establishes, as a matter of law, all vital facts in support of the issue. See
    Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 241 (Tex. 2001). In a “matter of law”
    7
    challenge, the reviewing court must first examine the record for evidence that
    supports the challenged finding, while ignoring all evidence to the contrary. 
    Id. If there
    is no evidence to support the finding, the reviewing court must then examine
    the entire record to determine if the contrary proposition is established as a matter
    of law. 
    Id. The evidence
    establishes that Tile Roofs did not fail to comply with a
    material obligation of the contract. When it was fired from the jobsite, Tile Roofs
    was installing the roof with open valleys, in accordance with the terms of the
    contract. Tile Roofs was also installing the rake tiles in accordance with the
    manufacturer’s directions. Viewing this evidence in the light most favorable to the
    jury’s finding, we conclude that there is legally sufficient evidence to show that
    Tile Roofs was performing under the contract and that Mushtaha had no excuse for
    his breach.
    When a party attacks the factual sufficiency of an adverse finding on an
    issue on which he has the burden of proof, the party must demonstrate that the
    adverse finding is so against the great weight and preponderance of the evidence as
    to be clearly wrong and manifestly unjust. 
    Id. at 242.
    Our scope of review includes
    all evidence relevant to the adverse finding. 
    Id. Mushtaha asserts
    in his brief that his nonperformance was excused because
    Tile Roofs “simply chose to stop working.” Mushtaha does not identify the date of
    this alleged repudiation, but in his brief, he refers to a meeting in September 2009,
    where the parties allegedly disagreed over funding matters and other work that had
    already been completed. The brief contains no record citations in support of these
    references, and we are not aware of any evidence that the meeting ever occurred.
    The uncontroverted evidence showed that demolition of the old roof began in
    October 2009 and installation of the new roof began in November 2009. Mushtaha
    8
    does not explain how any conflicts could have arisen over the installation of the
    new roof during a meeting held in September 2009.
    Setting aside the timing of the alleged meeting, the record still fails to
    establish Mushtaha’s claim that Tile Roofs “chose” to walk away from the project.
    There is evidence that Tile Roofs was prepared to finish the project under the terms
    of the contract, but Mushtaha completely refused. The record supports a finding
    that Mushtaha fired Tile Roofs, not that Tile Roofs quit.
    Mushtaha argues next that Tile Roofs materially breached the contract
    because it was not installing the new roof according to industry standards.
    Mushtaha produced evidence from an inspector that the new roof had inconsistent
    spacing patterns between the tiles. The inspector testified that the ridge tiles were
    installed with substantially varying heights above the surrounding tiles. The
    inspector also expressed concerns over contact between the lead and copper
    flashing, which could result in corrosion. Finally, the inspector commented that
    Tile Roofs had appeared to be using old or damaged tar paper.
    On cross-examination, the inspector established that he had no experience
    installing roofs and that he had performed his inspection entirely from ground
    level. Tile Roofs produced testimony showing that there may have been some
    problems with the roof, but it asserted that these problems would have been
    corrected on a final walkthrough had it been allowed to complete the job. This
    opinion was shared by the contractor hired by Mushtaha to finish the roof with
    closed valleys, who testified that Tile Roofs could have corrected the problems in
    an appropriate manner upon a final walkthrough. The jury was free to accept this
    evidence and find that Tile Roofs had not materially breached the contract when
    Mushtaha ordered Tile Roofs to stop working. The jury’s finding that Mushtaha
    9
    had no excuse for his failure to comply is not so against the great weight and
    preponderance of the evidence as to be clearly wrong and manifestly unjust.
    C.    Damages
    We finally address whether the evidence is legally and factually sufficient to
    support the jury’s award of damages. The jury was asked to find “what sum of
    money, if any, if paid now in cash, would fairly and reasonably compensate Tile
    Roofs for its damages, if any, that resulted from Mushtaha’s failure to comply with
    the Agreement.” The instructions further provided that the jury was to calculate
    Tile Roofs’ lost contract profits as the measure of damages. Lost profits were
    defined as “the amount Mushtaha agreed to pay Tile Roofs less (a) the expenses
    Tile Roofs saved by not completing the job and (b) the amount paid to Tile Roofs
    by Mushtaha.” The jury answered that Tile Roofs was entitled to recover $27,500
    as a reasonable amount of damages.
    The jury’s finding is amply supported by the evidence adduced at trial. The
    undisputed evidence showed that Mushtaha paid $51,000 to Tiles Roofs before the
    project began, with a promise that the remaining balance on the contract would be
    paid when the project was completed. Tile Roofs produced additional evidence
    showing that, when it was ordered to stop working on the project, it had spent
    $60,000 on labor and materials, and it had accrued approximately $20,000 in profit
    from the work already performed. Tile Roofs received no other payments after
    being ordered to leave the job site.
    Tile Roofs would have been fully compensated if at the time of breach it had
    been paid $29,000, which is the difference between the value of services provided
    to Mushtaha and the amount that Mushtaha had already paid to Tile Roofs
    ($60,000 + $20,000 − $51,000). The jury’s award was $27,500, which is slightly
    less than that amount. As the trier of fact, the jury had the discretion to award
    10
    damages within the range of evidence presented at trial, and it did so here. See
    Howell Crude Oil Co. v. Donna Refinery Partners, Ltd., 
    928 S.W.2d 100
    , 108
    (Tex. App.—Houston [14th Dist.] 1996, writ denied). The jury’s finding is
    accordingly supported by legally sufficient evidence.
    Mushtaha does not clearly explain how the evidence is factually insufficient
    to support the jury’s finding. The only other figure discussed in his appellate brief
    is the amount he paid to another roofing company to complete the project. This
    evidence is irrelevant, however, because the jury was specifically instructed to
    calculate Tile Roofs’ lost profits by deducting the expenses saved “by not
    completing the job.” Without any controverting evidence to consider, we conclude
    that the jury’s finding is supported by factually sufficient evidence.
    CONCLUSION
    The judgment of the trial court is affirmed.
    /s/    Tracy Christopher
    Justice
    Panel consists of Chief Justice Frost and Justices Christopher and Busby.
    11
    

Document Info

Docket Number: 14-13-00793-CV

Filed Date: 12/11/2014

Precedential Status: Precedential

Modified Date: 9/22/2015