Lawrence E. Young and Judith A. Young v. Dimension Homes, Inc. ( 2016 )


Menu:
  • Opinion issued August 30, 2016
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-14-00331-CV
    ———————————
    LAWRENCE E. YOUNG AND JUDITH A. YOUNG, Appellants
    V.
    DIMENSION HOMES, INC., Appellee
    On Appeal from the 400th District Court
    Fort Bend County, Texas
    Trial Court Case No. 12-DCV-197202
    MEMORANDUM OPINION
    Appellants, Lawrence E. Young and Judith A. Young, appeal the judgment
    following a jury trial rendered in favor of appellee, Dimension Homes, Inc., in
    Dimension’s suit for breach of contract and quantum meruit. In six issues, the
    Youngs contend that: (1) the trial court erred in awarding Dimension damages on its
    quantum meruit claim; (2) there is legally and factually insufficient evidence to
    support the jury’s finding of $146,000 in quantum meruit damages; (3) the Youngs
    are entitled to a new trial because of procedural errors including (a) an untimely
    pleading of that claim in the alternative and (b) a finding by the jury that is
    inconsistent with the quantum meruit issue; (4) the trial court erred in awarding
    Dimension the unpaid retainage as breach of contract damages because Dimension
    failed to get a jury finding that the Youngs breached the contract; (5) there is legally
    and factually insufficient evidence supporting the jury’s findings that (a)
    Dimension’s failure to execute and deliver an Affidavit of Completion to the Youngs
    was excused, and (b) Dimension’s failure to obtain written Change Orders was
    excused; and (6) the trial court abused its discretion in awarding $260,417.70 in
    attorney’s fees, plus over $140,000 in contingent appellate fees.
    We affirm the breach of contract award, reverse the quantum meruit award,
    and remand for further proceedings with respect to the award of attorney’s fees.
    Background
    The Youngs hired Dimension, a custom home builder, to build their new home
    in Fort Bend County. The construction contract, executed by the parties on January
    15, 2007 (the Contract), obligated Dimension to “furnish all labor, services,
    equipment, materials, and all other facilities (the Work) for the construction of
    certain improvements, generally described as a private residence, Plan 9767 (the
    2
    Improvements)” on the Youngs’ property. In exchange, the Youngs agreed to pay
    Dimension for the cost of the Work, defined by the Contract, plus fifteen-percent of
    the cost of the Work.
    The parties initially agreed to an overall budget amount of approximately
    $1,812,000. The Contract, however, expressly stated that Dimension did not
    “represent these budgets to be the actual cost,” and that the Youngs “acknowledge[d]
    and agree[d] that any overage in the budgets is the sole responsibility of the
    [Youngs].” The parties also agreed on a “Construction Loan Budget for building the
    plan with the defined specifications [which] contains detail[ed] budgets itemizing
    the necessary labor, material, permits, approvals, assessments, insurance, and all
    other costs associated with the construction of the Improvements,” which was
    attached to the contract. The Construction Loan Budget included two line items
    allocating $20,000 to pay for any “construction extras.”
    The parties also included a “Change Order” provision in the Contract which
    required the parties to execute a Change Order for any “changes or alteration[s] to
    the Work” that were requested by the Youngs and approved by Dimension, and
    stated that any such Change Order would serve as an amendment to the Contract.
    Construction on the Youngs’ home began in February 2007. Dimension’s
    president, Jeff Dzuik, testified that although there was a working draft of the plans
    and specifications when the Contract was executed, there was no final agreed set of
    3
    plans and specifications, and, in fact, many items were still left open for decision.
    According to Dzuik, the plans and specifications grew while the home was under
    construction as the Youngs made changes and added upgrades and extras. Among
    other things, the square footage of the house was increased, low voltage was
    substantially increased, the Youngs’ choice of brick was upgraded, additional
    HVAC added, driveway gates and openers were added, entrance columns added,
    countertops and appliances were upgraded, additional stone work was added and
    windows were upgraded. Despite the Change Order provision, the Youngs never
    asked Dzuik for a Change Order covering any of the modifications. Dzuik testified
    that he advised the Youngs of the cost impacts of their decisions and that he “did
    exactly what Larry Young asked [him] to do.”
    Larry Young, on the other hand, testified that the Contract capped the total
    cost of the home at approximately $1,812,000 and that he understood that any
    additional costs incurred as a result of their design choices would be offset by
    savings elsewhere in the budget. Young testified that he learned that the original
    budget had been exceeded for the first time in February 2008. According to Young,
    he and Dzuik met that month to discuss the blown budget and, at the meeting, Young
    agreed to pay an additional $254,355.18, which covered the additional cost incurred
    up to that point, for a total of cost of $2,079,223.14 (the February Amendment).
    4
    Dzuik disagreed with Young’s interpretation of that meeting and testified that
    he would never have represented that the $2,079,223.14 was the total cost of the
    home because the home was still under construction in February 2008 and additional
    specifications were still being added. According to Dzuik, the Youngs made changes
    to the project after the parties’ February Amendment. Among other things,
    substantial upgrades to the interior woodwork were added, additional concrete work
    (flatwork) was added, upgrades to the driveway were made, additional fencing was
    added, the pool was expanded, additional landscaping was added, wood floors
    upstairs were added, and lighting fixtures were upgraded. Dzuik testified these
    changes caused several categories included in the original budget to be exceeded.
    The Youngs closed on the home in April 2008. At the closing, Dzuik and the
    Youngs executed an “Owner’s and Contractor’s Affidavit” in which they averred
    that:
    ‘all of the persons, firms, and corporations . . . including the General
    Contractor and all sub-contractors, who have furnished services, labor,
    or materials, according to the plans and specifications, or extra items,
    used in the construction or repair of such improvements, have been paid
    in full, that there are no mechanics’ or materialmen’s liens against said
    property . . . and that such construction or repair has been fully
    completed and accepted by the Owner. General Contractor hereby
    waives and releases his right to file a mechanics’ or materialmen’s lien
    against the property. . . .”
    It is undisputed that the Youngs paid Dimension $1,963,036.84 and that they
    have not paid Dimension the remaining five percent retainage of $103,317.71. Larry
    5
    Young and his counsel testified that they would have paid Dimension the retainage,
    if Dzuik had provided them with the documentation they were requesting. The
    record also includes various correspondence between the Youngs or their counsel
    and Dzuik in which the Youngs offered to pay Dimension if Dzuik provided a final
    all-bills paid affidavit and provided them with lien releases from all of the
    subcontractors who had worked on the Youngs’ home. At trial, the Youngs’ counsel
    “stipulate[d] that if [Dimension] g[a]ve [the Youngs] an affidavit of the completion
    executed by [Dimension], [the Youngs] will pay the $103,000-plus retainage.”
    The Youngs’ position at trial was that the February Amendment fixed the final
    amount that they were obligated to pay under the Contract at $2,066,354.57.
    Dimension argued that the amendment did not cap the Youngs’ liability under the
    Contract, but that if it did, Dimension was entitled to recover in quantum meruit for
    the additional extras and upgrades that were added after the February Amendment.
    The jury found that the Youngs agreed to pay no more than $2,066,354.57 for
    the construction of the home (Question 1). Dimension’s failure to execute and
    deliver an Affidavit of Completion to the Youngs and obtain written Change Orders,
    was excused because the Youngs waived compliance with those contractual
    provisions (Questions 4 and 6). The jury also found that Dimension did compensable
    work for the Youngs in excess of $2,066,354.57 (Question 7) and they determined
    that “the reasonable value of such compensable work in excess of $2,066,354.57 at
    6
    the time and place it was performed” was $146,000 (Question 8).1 Attorney’s fees
    were submitted to the trial court by agreement and findings of fact and conclusions
    of law were entered.
    On February 10, 2014, the trial court entered judgment based on these
    findings, awarding Dimension $103,317.71 in contract damages for the unpaid
    retainage, $146,000 in quantum meruit damages, and $260,417.70 in attorney’s fees,
    plus $140,000 in contingent appellate fees.
    Standard of Review and Applicable Law
    A.    Contract Interpretation
    In construing a written contract, the primary concern is to ascertain and give
    effect to the parties’ intentions as expressed in the document. Italian Cowboy
    Partners, Ltd. v. Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 333 (Tex. 2011); Frost
    Nat’l Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 311–12 (Tex. 2005). We begin
    our analysis with the contract’s express language. Italian 
    Cowboy, 341 S.W.3d at 333
    . Contract terms will be given their plain, ordinary, and generally accepted
    meanings unless the contract itself shows them to be used in a technical or different
    sense. Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 662 (Tex. 2005). If, after
    applying the pertinent contract construction rules, the contract can be given a certain
    1
    The jury also made additional findings on Dimension’s fraud and negligent
    misrepresentation claims that are not being challenged on appeal.
    7
    or definite legal meaning or interpretation, then it is not ambiguous, and we will
    construe the contract as a matter of law. Frost Nat’l 
    Bank, 165 S.W.3d at 312
    .
    Quantum Meruit
    In their first, second, and third issues, the Youngs challenge the trial court’s
    award of $146,000 in quantum meruit damages to Dimension. Specifically, the
    Youngs contend that (1) Dimension does not have a claim for quantum meruit
    because the materials and services it provided were covered by Contract; (2) there is
    legally and factually insufficient evidence to support the jury’s finding of $146,000
    in quantum meruit damages; and (3) the Youngs are entitled to a new trial because
    of procedural errors associated with the quantum meruit claim.
    A party generally cannot recover under quantum meruit when there is a valid
    contract covering the services or materials furnished. See In re Kellogg Brown &
    Root, Inc., 
    166 S.W.3d 732
    , 740 (Tex. 2005); Gulf Liquids New River Project, LLC
    v. Gulsby Eng’g, Inc., 
    356 S.W.3d 54
    , 69 (Tex. App.—Houston [1st Dist.] 2011, no
    pet.) (citing Truly v. Austin, 
    744 S.W.2d 934
    , 936 (Tex. 1988)). Whether an express
    contract covers the services at issue is a legal question for the court. Gulf Liquids
    New River 
    Project, 356 S.W.3d at 70
    . “When the evidence shows that no contract
    covers the service at issue, then the question of whether a party may recover in
    quantum meruit is for the trier of fact.” 
    Id. (emphasis in
    original) (citation omitted).
    8
    The Contract expressly obligates Dimension to “furnish all labor, services,
    equipment, materials, and all other facilities” for the construction of the Youngs’
    new home. The parties also attached an agreed Construction Loan Budget which
    contained detailed budgets itemizing the costs associated with the construction
    project, including the necessary labor and materials. The budget also contained two
    line items covering $20,000 in “construction extras.” The Youngs “acknowledge[d]
    and agree[d] that any overages in the budgets [were their] sole responsibility.”
    At trial, Dzuik testified that the Youngs made changes to the project after the
    parties February Amendment that resulted in “overages” with respect to the original
    budgets for several categories included in the Construction Loan Budget, including
    the inside door and trim, flatwork, the driveway, fencing, HVAC trim, the pool,
    landscaping/sprinkler/sod, wood floors, and lighting fixtures. Dzuik also testified
    that Larry Young added some other minor items.2
    After reviewing the Contract, we conclude that the Contract expressly covers
    the categories of items set forth in the detailed Construction Loan Budget attached
    to the Contract. See Frost Nat’l 
    Bank, 165 S.W.3d at 312
    (stating that interpretation
    of unambiguous contract is question of law for court). To the extent that the actual
    cost of providing one of these items exceeds the amount indicated by the
    2
    Such items included leaf guards for the gutters ($1,100) and log kits for the gas
    fireplaces ($2,500). Dzuik testified that the log kits were not included in the original
    budget.
    9
    Construction Loan Budget, the Youngs are solely responsible for that overage, based
    on the plain language of paragraph 4 of the contract—“Owner acknowledges and
    agrees that any overages in the budgets is the sole responsibility of the Owner.” See
    
    id. Thus, any
    “overages” testified to by Dzuik are covered by the Contract. The
    minor items requested by the Youngs during construction are also covered by the
    $20,000 budgeted to cover any “construction extras.” Because the items and
    overages are covered by the Contract, the trial court erred in awarding Dimension
    damages based on quantum meruit. See In re Kellogg Brown & 
    Root, 166 S.W.3d at 740
    ; Gulf Liquids New River 
    Project, 356 S.W.3d at 69
    .
    We sustain the Youngs’ first issue and reverse the award of $146,000 in
    quantum meruit damages to Dimension.3
    Breach of Contract
    In their fourth and fifth issues, the Youngs argue that the trial court erred by
    awarding Dimension damages on its breach of contract claim because: (1)
    Dimension failed to get a jury finding that the Youngs breached the contract; (2) the
    undisputed evidence demonstrates that Dimension failed to provide the Affidavit of
    Completion and the lien-releases which are conditions precedent to obtaining
    payment of the contractual retainage; (3) there is legally insufficient evidence to
    3
    As a result of our disposition of this issue, we need not address the Youngs’ second
    and third issues.
    10
    support the jury’s findings that Dimension’s failure to provide them with an
    Affidavit of Completion (Question 4) and obtain Change Orders (Question 5) were
    excused because the Youngs waived these requirements; and (4) Dimension’s failure
    to provide them with an Affidavit of Completion and obtain Change Orders
    constitute prior material breaches of the contract.
    A.    Applicable Law
    The elements of a breach-of-contract claim are (1) the existence of a valid
    contract; (2) performance or tendered performance by the plaintiff; (3) breach by the
    defendant; and (4) damages as a result of breach. Bank of Tex. v. VR Elec., Inc., 
    276 S.W.3d 671
    , 677 (Tex. App.—Houston [1st Dist.] 2008, pet. denied).
    “Whether a party has breached a contract is a question of law for the court,
    not a question of fact for the jury, when the facts of the parties’ conduct are
    undisputed or conclusively established.” Grohman v. Kahlig, 
    318 S.W.3d 882
    , 887
    (Tex. 2010) (citing Sullivan v. Barnett, 
    471 S.W.2d 39
    , 44 (Tex. 1971)). “The judge
    determines what conduct is required of the parties and, insofar as a dispute exists
    concerning the failure of a party to perform the contract, the judge submits the
    disputed fact questions to the jury.” Lafarge Corp. v. Wolff Inc., 
    977 S.W.2d 181
    ,
    186 (Tex. App.—Austin 1998, pet. denied) (citing ITT Commercial Fin. Corp. v.
    Riehn, 
    796 S.W.2d 248
    , 253 n.3 (Tex. App.—Dallas 1990, no writ)).
    11
    B.    Dimension’s Failure to Obtain a Jury Finding
    The Youngs argue that Dimension did not meet its burden of proof with
    respect to its breach of contract claim because Dimension failed to get a jury finding
    that the Youngs breached the contract.
    At trial, Dimension argued that the Youngs breached the Contract by: (1)
    failing to pay for all of the extras and upgrades that were added to the Contract after
    February 2008, and (2) failing to pay the $103,317.71 retainage (five percent of
    $2,066,354.57). Dimension also argued that if the post-February 2008 items were
    not covered by the Contract, then those costs were recoverable under quantum
    meruit. Dimension submitted jury questions on the issue of whether the Youngs’
    failure to pay for all of the extras and upgrades that were added after February 2008
    breached the Contract (Questions 1 and 2). Because the jury found that the Youngs
    only agreed to pay $2,066,354.57 for the construction of the home, the jury did not
    answer Question 2. The jury’s responses to these questions, however, are not
    dispositive of the issue of whether Dimension needed to get a jury finding that the
    Youngs breached the contract by failing to pay the retainage. See Hous. Med. Testing
    Servs., Inc. v. Mintzer, 
    417 S.W.3d 691
    , 696 (Tex. App.—Houston [14th Dist.] 2013,
    no pet.) (stating that appellate courts must interpret jury findings in manner that
    supports judgment).
    12
    It is undisputed that the Youngs agreed to pay Dimension a minimum of
    $2,066,354.57 under the Contract and that this sum included the $103,317.71
    contractual retainage. Both parties agreed that the Youngs never paid Dimension the
    $103,317.71 retainage. Since this fact was established without dispute, Dimension
    was not required to submit a jury question on the issue. See City of Keller v. Wilson,
    
    168 S.W.3d 802
    , 814–15 (Tex. 2005) (“[U]ncontroverted issues need not be
    submitted to a jury at all.”).
    However, the Youngs’ failure to pay the retainage would not constitute a
    breach of the contract if the obligation never accrued because Dimension failed to
    satisfy two conditions precedent to payment—Dimension’s obligations to provide
    the Youngs with lien-releases and an executed Affidavit of Completion—or if
    Dimension committed a prior breach when it failed to comply with the Change Order
    provision.
    Because Dimension asserted in its pleading that all conditions precedent were
    satisfied, the Youngs were required to specifically deny each condition precedent.
    See TEX. R. CIV. P. 54. The Youngs failed to do so. Further, evidence regarding
    whether Dimension satisfied its obligations to provide the Youngs with lien-releases
    and an Affidavit of Completion was admitted without objection and therefore these
    issues were tried by consent. See Cunningham v. Zurich Am. Ins. Co., 
    352 S.W.3d 519
    , 533 & n.61 (Tex. App.—Fort Worth 2011, pet. denied) (holding that even if
    13
    certain requirement was condition precedent that was not specifically denied, it was
    tried by consent).
    Dimension argued that, even if the Affidavit of Completion requirement was
    a condition precedent, its failure to provide the Affidavit of Completion, and its
    failure to comply with the Change Order provision, were excused by the Youngs’
    waiver of these requirements. Questions about these potential contract breaches were
    submitted to the jury and the jury found they were excused (Questions 4 and 5).
    The payment of the retainage was required by the Contract on completion of
    the project. The fact of nonpayment was established by agreement between the
    parties. The Youngs’ argument that payment was not due because of a failure of
    condition precedent was negated by a jury finding that Dimension’s failure to
    provide the Youngs with an Affidavit of Completion was excused. Likewise, the
    Youngs’ argument that payment was not due because of a prior material breach was
    negated by the jury’s finding that Dimension’s failure to obtain Change Orders was
    excused. As discussed below, the jury’s findings on these issues are supported by
    sufficient evidence. As further discussed, neither the Contract nor the Property Code
    required Dimension to provide the Youngs with lien releases from all of the
    subcontractors, and the affidavit that Dimension gave to the Youngs at closing
    satisfies the Probate Code’s Final Bills-Paid Affidavit requirement. Thus, the failure
    to pay the retainage is established by the record as a breach of contract.
    14
    C.    Delivery of Lien Releases
    The Youngs argue that the evidence conclusively establishes that Dimension
    did not provide them with lien releases from all of the subcontractors, as required by
    the Contract and under Property Code section 53.259.
    The Contract does not require Dimension to provide lien releases from all of
    the various subcontractors in order to receive the retainage. Paragraph 14 of the
    contract specifically grants Dimension a mechanic’s and materialman’s lien on the
    property in order to secure the Youngs’ payment of the Contract. The only liens
    referred to by the Contract are the liens granted to Dimension by paragraph 14. Thus,
    paragraph 8(c)’s reference to Dimension’s contractual obligation to “deliver[] lien
    releases to [the Youngs] in form and substance as may be reasonably required by
    [the Youngs],” refers to Dimension’s liens on the property. See Frost Nat’l 
    Bank, 165 S.W.3d at 312
    (stating that interpretation of unambiguous contract is question
    of law for court).
    The Youngs further contend that Dimension was required to provide them
    with lien releases from all of the subcontractors as a condition precedent to payment
    of the retainage pursuant to Property Code section 53.259. See TEX. PROP. CODE
    ANN. § 53.259 (West 2014). Property Code section 53.259, which is entitled “Final
    Bills-Paid Affidavit Required,” provides:
    As a condition of final payment under a residential construction
    contract, the original contractor shall, at the time the final payment is
    15
    tendered, execute and deliver to the owner, or the owner’s agent, an
    affidavit stating that the original contractor has paid each person in full
    for all labor and materials used in the construction of improvements on
    the real property. If the original contractor has not paid each person in
    full, the original contractor shall state in the affidavit the amount owed
    and the name and, if known, the address and telephone number of each
    person to whom a payment is owed.
    TEX. PROP. CODE ANN. § 53.259(a). Contrary to the Youngs’ position, section 53.259
    does not require Dimension to provide the Youngs with any lien releases; the plain
    language of the statute only requires Dimension to provide them with an affidavit
    stating that all of the subcontractors have been paid in full. See id.; see also Valdez
    v. Hollenbeck, 
    465 S.W.3d 217
    , 227 (Tex. 2015) (stating courts construe statutes in
    accordance with plain meaning of statutory text).
    In this case, the evidence conclusively demonstrates that Dzuik, acting in his
    capacity as president of Dimension, signed an “Owner’s and Contractor’s Affidavit”
    on April 8, 2008 in which he averred that “all sub-contractors . . . have been paid in
    full, [and] that there are no mechanics’ or materialmen’s liens against [the Youngs’]
    property . . . .” The evidence also conclusively demonstrates that Dimension released
    its mechanic’s and materialman’s liens on the property in April 2008, as evidenced
    by that same affidavit executed at closing. Neither section 53.259 nor the Contract
    requires a final all-bills paid affidavit to be in a particular form or a form approved
    by the owner. Section 53.259 only requires that Dimension provide the Youngs with
    an “affidavit stating that the original contractor has paid each person in full for all
    16
    labor and materials used in the construction of improvements on the real property.”
    We conclude that the April 2008 affidavit executed by Dzuik on behalf of Dimension
    satisfies this statutory obligation.
    D.     Sufficiency of Evidence Supporting Jury Findings on Waiver
    1.     Standard of Review and Applicable Law
    When addressing a challenge to the legal sufficiency of the evidence to
    support the jury’s findings, we review the entire record, credit favorable evidence if
    reasonable jurors could, and disregard contrary evidence unless reasonable jurors
    could not. See City of 
    Keller, 168 S.W.3d at 822
    , 827. We may not sustain a legal
    sufficiency, or “no evidence,” point unless the record demonstrates: (1) a complete
    absence of a vital fact; (2) the court is barred by rules of law or of evidence from
    giving weight to the only evidence offered to prove a vital fact; (3) the evidence
    offered to prove a vital fact is no more than a mere scintilla; or (4) the evidence
    conclusively establishes the opposite of the vital fact. 
    Id. at 810;
    Merrell Dow
    Pharms., Inc. v. Havner, 
    953 S.W.2d 706
    , 711 (Tex. 1997). If more than a scintilla
    of evidence exists to support the finding, the legal sufficiency challenge fails.
    Haggar Clothing Co. v. Hernandez, 
    164 S.W.3d 386
    , 388 (Tex. 2005). Evidence
    does not exceed a scintilla if jurors “would have to guess whether a vital fact exists.”
    City of 
    Keller, 168 S.W.3d at 813
    .
    17
    The jury is the sole judge of the weight and credibility of the evidence, and is
    entitled to resolve any conflicts in the evidence and to choose which testimony to
    believe. See 
    id. at 819.
    We therefore assume that jurors decided questions of
    credibility or conflicting evidence in favor of the verdict if they reasonably could do
    so. 
    Id. at 820.
    We do not substitute our judgment for that of the jurors if the evidence
    falls within this zone of reasonable disagreement. 
    Id. at 822.
    Waiver is primarily a function of intent and requires either the intentional
    relinquishment of a known right or intentional conduct inconsistent with claiming
    that right. Crosstex Energy Servs., L.P. v. Pro Plus, Inc., 
    430 S.W.3d 384
    , 391, 393–
    94 (Tex. 2014) (citations omitted). To establish waiver, a party must prove that the
    other party had (1) an existing right, benefit, or advantage, (2) actual or constructive
    knowledge of its existence, and (3) an actual intent to relinquish the right. ASI Techs.,
    Inc. v. Johnson Equip. Co., 
    75 S.W.3d 545
    , 548 (Tex. App.—San Antonio 2002, pet.
    denied). To find waiver through conduct, such intent “must be clearly demonstrated
    by the surrounding facts and circumstances.” Crosstex Energy 
    Servs., 430 S.W.3d at 393
    –94 (quoting Jernigan v. Langley, 
    111 S.W.3d 153
    , 156 (Tex. 2003)). For
    example, an implied waiver may be established by showing a party’s prolonged
    silence or inaction in asserting a known right. See Motor Vehicle Bd. v. El Paso
    Indep. Auto. Dealers Ass’n, 
    1 S.W.3d 108
    , 111 (Tex. 1999).
    18
    2.     Affidavit of Completion
    The Youngs further argue that the evidence conclusively establishes that
    Dimension did not provide them with an Affidavit of Completion, as required by
    paragraph 8(c) of the Contract and there is legally insufficient evidence to support
    the jury’s finding that Dimension’s failure to comply with this contractual obligation
    was excused because the Youngs waived this requirement (Question 4). Dimension
    acknowledges that it did not provide the Youngs with an Affidavit of Completion,
    but argues that the jury’s finding that its failure to provide the affidavit was excused
    by the Youngs’ waiver of that right is supported by sufficient evidence.
    Although “Affidavit of Completion” is not defined in the Contract, it has a
    technical meaning under the Property Code. Property Code section 53.106, which is
    entitled “Affidavit of Completion,” states that the owner of a given property may
    file an affidavit of completion with the county clerk of the county in which the
    property is located and that any such affidavit must contain, among other things, “a
    conspicuous statement that a claimant may not have a lien on retained funds unless
    the claimant files an affidavit claiming a lien not later than the 40th day after the
    date the work under the original contract is completed.” TEX. PROP. CODE ANN.
    § 53.106(a)(6) (West 2014).
    The Youngs argue that the record not only discloses no clear intent by them
    to waive their right to obtain an affidavit of completion, but it also reflects that they
    19
    insisted on the affidavit of completion and the appropriate lien releases, as
    demonstrated by e-mail correspondence with Dzuik that was admitted into evidence
    as defendants’ exhibits 29 and 35, and plaintiff’s exhibit 172. Dziuk, however,
    testified that, prior to the lawsuit being filed, no one from the Youngs’ side asked
    him for an affidavit of completion.
    Defendants’ exhibit 29 is a September 2008 e-mail from the Youngs’ attorney
    to Dzuik asking Dzuik to provide lien releases from several subcontractors. The
    Youngs’ attorney also attached a copy of the “Final Bills-Paid Affidavit, Pursuant
    to Texas Property Code § 53.259” and instructed Dzuik to sign and notarize the
    affidavit and “hand deliver the original to Larry when he gives you his check
    tomorrow.” Defendants’ exhibit 35 is a March 2, 2009 e-mail from the Youngs’
    attorney to Dzuik, attaching another copy of the same proposed affidavit, and stating:
    “If you could sign and email or fax the affidavit to me, I’ll call the bank and let them
    know to have the check ready for you.” Plaintiff’s exhibit 172 is a March 15, 2011
    e-mail from Larry Young to Dzuik attaching a copy of the same proposed affidavit
    and stating, “This is what [my attorney] suggested you sign when I pay you.” We
    have not found—and the Youngs have not directed us to—any correspondence in
    which the Youngs or their counsel requested an “Affidavit of Completion” prior to
    the filing of the lawsuit in 2012.
    20
    These three exhibits never mention an Affidavit of Completion and do not
    demonstrate that the Youngs insisted that Dimension provide an Affidavit of
    Completion before they would pay the $103,000 retainage. On the contrary, these
    exhibits indicate that the Youngs were willing to pay Dimension the retainage if
    Dzuik signed the “Final Bills-Paid Affidavit, Pursuant to Texas Property Code
    § 53.259” and provided the lien releases they were requesting. Although it can serve
    some of the same purposes, an “Affidavit of Completion” as described by section
    53.106(a), is not a final-bills-paid affidavit as required by section 53.259, or a lien
    release. Compare TEX. PROP. CODE ANN. § 53.106(a) with TEX. PROP. CODE ANN.
    § 53.259. Moreover, the Youngs’ attorney testified that he never requested an
    Affidavit of Completion from Dimension. He also testified that the Youngs were
    willing to waive the Affidavit of Completion requirement in September 2008 if they
    received the lien releases they were requesting.
    Based on this evidence and the record as whole, we conclude that there is
    more than a scintilla of evidence demonstrating that although the Youngs knew
    about the Affidavit of Completion requirement in September 2008, they did not
    request an Affidavit of Completion from Dimension until after the lawsuit was filed
    in 2012. Accordingly, we hold that there is legally sufficient evidence supporting the
    jury’s finding that the Youngs waived the Affidavit of Completion requirement in
    response to Question 4. See El Paso Indep. Auto. 
    Dealers, 1 S.W.3d at 111
    (stating
    21
    that implied waiver may be established by showing party’s prolonged silence or
    inaction in asserting known right).
    3.     Change Orders
    The Youngs argue that the evidence conclusively establishes that Dimension
    breached the Contract by failing to provide them with written change orders, as
    required by paragraph 5 of the Contract, Dimension’s breach constitutes a prior
    material breach of the Contract which relieved the Youngs of any further
    performance, and that there is legally insufficient evidence to support the jury’s
    finding that Dimension’s breach was excused because the Youngs waived this
    requirement (Question 5).
    Paragraph 5 states: “Change Orders. If Owner desires changes or alteration to
    the Work, and subject to the approval of the requested change or alteration by
    Contractor, a Change Order shall be completed for same, and executed by both
    Owner and Contractor as an Amendment to this Contract.”
    Unless excused, a prior material breach of the contract by one party relieves
    the other contracting party of any further performance. See Mustang Pipeline Co. v.
    Driver Pipeline Co., 
    134 S.W.3d 195
    , 196 (Tex. 2004); see also Tex. Standard Oil
    & Gas, L.P. v. Frankel Offshore Energy, Inc., 
    394 S.W.3d 753
    , 779–80 (Tex. App.—
    Houston [14th Dist.] 2012, no pet.) (affirming take-nothing judgment based in part
    on jury finding that party’s material breach was excused).
    22
    The Contract containing the Change Order provision was executed on January
    15, 2007. There is evidence that the Youngs made a series of changes to the work
    being performed under the Contract after that date and no Change Order was ever
    completed. In fact, Larry Young testified that he “never told [Dzuik] he needed a
    change order,” and that on some occasions Young himself assumed “that a change
    order wasn’t necessary.” Similarly, Dzuik testified that no one asked him to provide
    a Change Order while the house was under construction and that no one suggested
    that he should have prepared Change Orders until after the lawsuit was filed in
    March 2012.
    Based on this evidence and the record as a whole, we conclude that there is
    more than a scintilla of evidence supporting the jury’s finding that the Youngs
    waived compliance with the Change Order provision because they knew about the
    provision and did not insist on compliance until years after the project was
    completed. See El Paso Indep. Auto. 
    Dealers, 1 S.W.3d at 111
    (stating implied
    waiver may be established by showing party’s prolonged silence or inaction in
    asserting known right). Accordingly, we hold that there is legally sufficient evidence
    supporting the jury’s answer to Question 5.4
    4
    In light of our disposition, we need not address whether the Change Order is a
    condition precedent, as opposed to a covenant.
    23
    E.    Conclusion
    We overrule the Youngs’ fourth and fifth issues.
    Attorney’s Fees
    In their sixth issue, the Youngs argue that the trial court abused its discretion
    in awarding $260,417.70 in attorney’s fees, plus over $140,000 in contingent
    appellate fees, to Dimension because no viable legal theory supports the award,
    Dimension did not offer any proof of segregation, and the amount of fees awarded
    was unreasonable, excessive, and disproportionate to the damages recovered.
    We review a trial court’s award of attorney’s fees under an abuse of discretion
    standard. See Ridge Oil Co., Inc. v. Guinn Invs., Inc., 
    148 S.W.3d 143
    , 163 (Tex.
    2004). A party may not recover attorney’s fees unless authorized by statute or
    contract. Tony Gullo Motors I, L.P. v. Chapa, 
    212 S.W.3d 299
    , 310–11 (Tex. 2006).
    The Youngs argue that no viable legal theory supports the award of attorney’s
    fees to Dimension. Texas Civil Practice and Remedies Code section 38.001(8)
    provides for the recovery of attorney’s fees in a suit on a contract. To recover
    attorney’s fees under section 38.001, a party must prevail on the underlying claim
    and recover damages. Intercontinental Grp. P’ship v. KB Home Lone Star L.P., 
    295 S.W.3d 650
    , 653 (Tex. 2009). Under section 38.001, the trial court has no discretion
    to deny attorney’s fees when presented with evidence of the same. Bocquet v.
    Herring, 
    972 S.W.2d 19
    , 20 (Tex. 1998) (noting that statutes providing that party
    24
    “may recover” attorney’s fees are not discretionary). If trial attorney’s fees are
    mandatory under section 38.001, then appellate attorney’s fees are also mandatory
    when proof of reasonable fees is presented. See Gill Sav. Ass’n v. Chair King, Inc.,
    
    797 S.W.2d 31
    , 32 (Tex. 1990) (remanding for retrial on appellate attorney’s fees
    under section 38.001 when there was some evidence to support award). Because
    Dimension pleaded for attorney’s fees based on Chapter 38, prevailed on its breach
    of contract claim for the retainage, and recovered damages for that claim, Dimension
    is entitled to recover some amount of attorney’s fees under Chapter 38. See KB
    
    Home, 295 S.W.3d at 653
    ; 
    Bocquet, 972 S.W.2d at 20
    .
    The Youngs argue that that attorney’s fee award must be reversed because
    Dimension did not offer any proof that it segregated its fees. Where, as here, a party
    seeks attorney’s fees in a case where some claims permit the recovery of fees and
    others do not, the party must segregate and exclude the fees for services related to
    the claims for which fees are not recoverable unless the “discrete legal services
    advance[d] both [the] recoverable claim and the unrecoverable claim.” Tony 
    Gullo, 212 S.W.3d at 13
    –14. When a party does not segregate attorney’s fees between
    recoverable and unrecoverable claims in the court below and we determine
    segregation is required, the fee award must be reversed and the case must be
    remanded to the trial court to determine which fees are recoverable. See 
    id. at 314.
    It is not necessary for an attorney to keep separate records documenting the exact
    25
    amount of time spent pursuing one claim versus another to prove that the amount of
    attorney’s fees sought is sufficiently segregated. See 
    id. Rather, an
    attorney can
    satisfy his evidentiary burden by presenting evidence of unsegregated attorney’s fees
    and a rough percentage of the amount attributable to the claims for which fees are
    not recoverable. See 
    id. at 314
    & n.83. Although the need to segregate fees is a
    question of law, the extent to which certain claims can be segregated is a mixed
    question of law and fact. Penhollow Custom Homes, L.L.C. v. Kim, 
    320 S.W.3d 366
    ,
    374 (Tex. App.—El Paso 2010, no pet.).
    At the bench trial on attorney’s fees, Dimension’s expert offered
    uncontradicted testimony that he reviewed the time sheets for Dimension’s attorneys
    and found no discrete entries attributable to Dimension’s tort claims for fraud and
    negligent misrepresentation. Dimension’s expert also testified that he had
    determined that 95% of the time spent in this case would have been necessary even
    if there had been no tort claims. The expert did not, however, attempt to segregate
    the fees attributable to Dimension’s breach of contract claim from its quantum
    meriut claim. Although Dimension originally prevailed on its quantum meriut claim,
    we have since reversed that portion of the trial court’s judgment, and, as such,
    Dimension is no longer entitled to attorney’s fees on that claim. Because
    Dimension’s evidence of fees expended is some evidence of what the segregated
    amount should be for its breach of contract claim, we will remand the issue to the
    26
    trial court for further consideration of the correct amount. See Tex. Ear Nose &
    Throat Consultants, PLLC v. Jones, 
    470 S.W.3d 67
    , 91 (Tex. App.—Houston [14th
    Dist.] 2015, no pet.) (reversing award of attorney’s fees where party failed to present
    evidence of segregation or intertwining, and remanding for new assessment of
    amount of fees).
    Conclusion
    We affirm the breach of contract award, reverse the quantum meriut award,
    and remand for further proceedings with respect to the award of attorney’s fees.
    Russell Lloyd
    Justice
    Panel consists of Justices Keyes, Massengale, and Lloyd.
    27
    

Document Info

Docket Number: 01-14-00331-CV

Filed Date: 8/30/2016

Precedential Status: Precedential

Modified Date: 8/31/2016

Authorities (23)

ASI Technologies, Inc. v. Johnson Equipment Co. , 75 S.W.3d 545 ( 2002 )

ITT Commercial Finance Corp. v. Riehn , 1990 Tex. App. LEXIS 2546 ( 1990 )

Ridge Oil Co., Inc. v. Guinn Investments, Inc. , 47 Tex. Sup. Ct. J. 1080 ( 2004 )

Valence Operating Co. v. Dorsett , 48 Tex. Sup. Ct. J. 671 ( 2005 )

Intercontinental Group Partnership v. KB Home Lone Star L.P. , 52 Tex. Sup. Ct. J. 1204 ( 2009 )

Bank of Texas v. VR Electric, Inc. , 2008 Tex. App. LEXIS 9745 ( 2008 )

Truly v. Austin , 31 Tex. Sup. Ct. J. 228 ( 1988 )

In Re Kellogg Brown & Root, Inc. , 48 Tex. Sup. Ct. J. 678 ( 2005 )

Gulf Liquids New River Project, LLC v. Gulsby Engineering, ... , 356 S.W.3d 54 ( 2011 )

Bocquet v. Herring , 972 S.W.2d 19 ( 1998 )

Lafarge Corp. v. Wolff, Inc. , 1998 Tex. App. LEXIS 6017 ( 1998 )

Sullivan v. Barnett , 14 Tex. Sup. Ct. J. 416 ( 1971 )

Gill Savings Ass'n v. Chair King, Inc. , 34 Tex. Sup. Ct. J. 42 ( 1990 )

Merrell Dow Pharmaceuticals, Inc. v. Havner , 40 Tex. Sup. Ct. J. 846 ( 1997 )

Motor Vehicle Board v. El Paso Independent Automobile ... , 42 Tex. Sup. Ct. J. 1128 ( 1999 )

Mustang Pipeline Co. v. Driver Pipeline Co. , 47 Tex. Sup. Ct. J. 461 ( 2004 )

Haggar Clothing Co. v. Hernandez , 48 Tex. Sup. Ct. J. 639 ( 2005 )

Frost National Bank v. L & F Distributors, Ltd. , 48 Tex. Sup. Ct. J. 803 ( 2005 )

City of Keller v. Wilson , 48 Tex. Sup. Ct. J. 848 ( 2005 )

Grohman v. Kahlig , 53 Tex. Sup. Ct. J. 964 ( 2010 )

View All Authorities »