Wesco Distribution, Inc. v. Westport Group, Inc. ( 2004 )


Menu:
  •       TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
    NO. 03-03-00438-CV
    Wesco Distribution, Inc., Appellant
    v.
    Westport Group, Inc., Appellee
    FROM THE DISTRICT COURT OF BASTROP COUNTY, 335TH JUDICIAL DISTRICT
    NO. 23,999, HONORABLE HAROLD R. TOWSLEE, JUDGE PRESIDING
    OPINION
    Appellant, Wesco Distribution, Inc., appeals the judgment of the district court of
    Bastrop County granting appellee Westport Group Inc.’s motion for summary judgment to remove
    a materialman’s lien and awarding Westport attorney’s fees in the amount of $16,140.77. Wesco
    raises two issues on appeal, asserting: (1) the district court misinterpreted the notice provisions of
    sections 53.003 and 53.056 of the property code, see Tex. Prop. Code Ann. §§ 53.003, .056 (West
    2002); and (2) the district court abused its discretion in awarding Westport attorney’s fees. We
    affirm the judgment of the district court.
    FACTUAL BACKGROUND
    Westport, a general contractor, agreed to build a dental office for E&M Properties and
    hired J&D Electric as its electrical subcontractor for the project. J&D Electric agreed to provide all
    the labor and materials necessary to perform the subcontract work. J&D Electric purchased some
    of the materials used in the dental office from Wesco, but failed to fully pay Wesco for these
    materials. On July 11, 2001, Wesco attempted to send notice by mail to Westport of J&D Electric’s
    outstanding bill for materials purchased between March 2001 and June 25, 2001, in order to notify
    Westport of Wesco’s claim for a materialman’s lien on the property. The post office returned this
    notice to Wesco because Wesco failed to attach sufficient postage. Wesco added postage and again
    mailed its notice to Westport on July 25, 2001. On July 19, Westport, having received no notice of
    lien, made a payment to J&D Electric. Although it is unclear when notice was actually received, it
    is clear that no payments were made by Westport after receipt of notice. By the time it received
    notice, Westport had paid J&D Electric almost everything it was owed. Wesco filed an affidavit
    claiming a lien on September 13, 2001.
    Westport filed suit to remove Wesco’s claimed lien, and Wesco filed suit for damages
    and foreclosure of its lien. The two lawsuits were consolidated. Westport filed a summary motion
    “to remove invalid or unenforceable lien” pursuant to section 53.160 of the property code, and
    Wesco opposed the motion. See 
    id. § 53.160.
    The trial court initially denied Westport’s summary
    motion, but when the parties filed cross-motions for summary judgment, the trial court granted
    Westport’s request for summary judgment made on the same grounds as its earlier motion. Wesco
    then brought this appeal.
    2
    STANDARD OF REVIEW
    Because the propriety of a summary judgment is a question of law, we review the trial
    court’s decision de novo. Natividad v. Alexsis, Inc., 
    875 S.W.2d 695
    , 699 (Tex. 1994); Texas Dep’t
    of Ins. v. American Home Assurance Co., 
    998 S.W.2d 344
    , 347 (Tex. App.—Austin 1999, no pet.).
    The standards for reviewing a motion for summary judgment are well established: (1) the movant
    for summary judgment has the burden of showing that no genuine issue of material fact exists and
    that it is entitled to judgment as a matter of law; (2) evidence favorable to the nonmovant will be
    taken as true in deciding whether there is a disputed material fact issue precluding summary
    judgment; and (3) every reasonable inference must be indulged in favor of the nonmovant and any
    doubts resolved in its favor. Nixon v. Mr. Prop. Mgmt. Co., 
    690 S.W.2d 546
    , 548-49 (Tex. 1985).
    DISCUSSION
    Construction of the Notice Provision
    In Wesco’s first issue, it argues that the trial court mistakenly interpreted the notice
    provisions contained in the materialman’s lien statute1 by finding that Wesco did not comply with
    its terms. The statute sets out deadlines for giving notice of unpaid balances owed by subcontractors
    to materialmen to the original contractor and the property owner and requires timely notice as a
    prerequisite for a valid lien claim.2 For Wesco’s lien claim to be valid, Wesco must have effectively
    1
    “If notice is sent by registered or certified mail, deposit or mailing of the notice in the
    United States mail in the form required constitutes compliance with the notice requirement.” Tex.
    Prop. Code Ann. § 53.003 (West 2002).
    2
    “A claimant other than an original contractor must give the notice prescribed by this
    section to be valid.” Tex. Prop. Code Ann. § 53.056(a) (West 2002).
    3
    notified Westport by July 15 of any unpaid balance for materials delivered in May.3 Because it
    attempted to send a notice on July 11, before the deadline, Wesco argues that it timely notified
    Westport under the statute. When that notice was returned to Wesco for insufficient postage, and the
    notice was re-sent on July 25, 2001, Westport argued that there was no timely notice of lien for
    nonpayment for supplies delivered to J&D Electric prior to the end of May.
    Wesco contends that its deposit of the notice with insufficient postage substantially
    complies with the statutory requirements of section 53.003 of the property code because Westport
    eventually received a notice. Despite the insufficient postage, it argues, Wesco deposited the notice
    within the statutory time period, and the statute requires nothing more. Westport responds that
    notice mailed with insufficient postage does not comply with statutory requirements because
    “sending” notice by mail necessarily includes attaching sufficient postage. Because Wesco failed
    to timely notify Westport of its lien claim, Westport argues, the lien it claims is invalid. We agree.
    This case calls for interpretation of the notice provisions of Texas’s mechanic’s and
    materialman’s lien statute. See Tex. Prop. Code Ann. §§ 53.003, .056. Statutory interpretation is
    a legal matter subject to de novo review. Bragg v. Edwards Aquifer Auth., 
    71 S.W.3d 729
    , 734 (Tex.
    2002); Pacesetter Pools, Inc. v. Pierce Homes, Inc., 
    86 S.W.3d 827
    , 831 (Tex. App.—Austin 2002,
    “If the lien claim arises from a debt incurred by a subcontractor, the claimant must give
    to the original contractor written notice of the unpaid balance. The claimant must give the notice
    not later than the 15th day of the second month following each month in which all or part of the
    claimant’s labor was performed or material delivered . . . .” 
    Id. § 53.056(b)
    (West 2002).
    3
    Although Wesco’s lien claim included unpaid balances for materials delivered in March
    and April, it is clear from the statute that no valid lien could attach for those balances, as their
    deadlines for notice, May 15 and June 15, respectively, had long since passed. Wesco advances no
    argument regarding those balances or deadlines.
    4
    no pet.) (citing Trinity Indus., Inc. v. Ashland, Inc., 
    53 S.W.3d 852
    , 868 (Tex. App. —Austin 2001,
    pet. denied)).
    “The primary rule of statutory interpretation is to ascertain and give effect to the
    intent of the legislature.” Southwestern Life Ins. Co. v. Montemayor, 
    24 S.W.3d 581
    , 583 (Tex.
    App.—Austin 2000, pet. denied) (citing Union Bankers Ins. Co. v. Shelton, 
    889 S.W.2d 278
    , 280
    (Tex. 1984)). If the legislature’s intent can be gathered from a reasonable interpretation of the statute
    as written, further implications are forbidden. 
    Id. A court
    may not add words to a statute unless
    necessary to give effect to clear legislative intent. See Jones v. Liberty Mut. Ins. Co., 
    745 S.W.2d 901
    , 902 (Tex. 1988); 
    Montemayor, 24 S.W.3d at 583
    . Courts should take into account the entire
    statute, not isolate disputed provisions. Texas Workers’ Compensation Commission v. Continental
    Casualty Company, 
    83 S.W.3d 901
    , 905 (Tex. App.—Austin 2002, no pet.). When the legislature
    employs a term in one section of a statute and excludes it in another, courts presume that the
    exclusion was intentional, and that the legislature had a reason for excluding it. Fireman’s Fund
    County Mut. Ins. Co. v. Hidi, 
    13 S.W.3d 767
    , 769 (Tex. 2000).
    Courts must also presume that the legislature intended a reasonable result.
    
    Montemayor, 24 S.W.3d at 585
    ; Enochs v. Brown, 
    872 S.W.2d 312
    , 318 (Tex. App.—Austin 1994,
    no writ). We must be mindful of the consequences of possible constructions when interpreting a
    statute, Continental Casualty 
    Co., 83 S.W.3d at 905
    , because courts should not construe statutes in
    a way that leads to foolish or absurd consequences. 
    Montemayor, 24 S.W.3d at 584-85
    (citing Meno
    v. Kitchens, 
    873 S.W.2d 789
    , 792 (Tex. App.—Austin 1994, writ denied)).
    5
    The materialman’s lien statute is liberally construed for the purpose of protecting
    laborers and materialmen. Industrial Indem. Co. v. Zack Burkett Co., 
    677 S.W.2d 493
    , 495 (Tex.
    1984) (per curiam); Hayek v. Western Steel Co., 
    478 S.W.2d 786
    , 795 (Tex. 1972). Giving “‘liberal
    construction’ means to give the language of a statutory provision, freely and consciously, its
    commonly, generally accepted meaning, to the end that the most comprehensive application thereof
    may be accorded, without doing violence to any of its terms.” Maryland Cas. Co. v. Smith, 
    40 S.W.2d 913
    , 914 (Tex. Civ. App.—Dallas 1931, no writ). Liberal interpretation of a statute does
    not permit doing violence to the language in the statute. Deep E. Tex. Reg’l Mental Health & Mental
    Retardation Svcs. v. Kinnear, 
    877 S.W.2d 550
    , 563 (Tex. App.—Beaumont 1994, no writ).
    Wesco argues first that the statute does not require postage to be affixed in order for
    notice to be effective, and that the absence of the word “postage” in the statute indicates a legislative
    intent that postage not be required for mailed notice to be considered effective. It offers two other
    provisions of the property code for comparison. The first allows notice to debtors by certified mail
    to be considered complete when that notice is deposited with the United States post office, “postage
    prepaid and addressed to the debtor” at its last known address. Tex. Prop. Code Ann. § 51.002(e)
    (West 2002). The second considers notice by lessors to tenants delivered when deposited with the
    United States post office, “properly addressed with postage prepaid.” 
    Id. § 59.043(b)
    (West 2002).
    Section 53.003, in contrast, is silent on the proper address or prepayment of postage.
    It allows notice by certified or registered mail to be considered effective upon “deposit or mailing
    of the notice in the United States mail in the form required.” The previous two provisions do not
    include the phrase “in the form required,” perhaps because they specify the form required: correctly
    6
    addressed and with postage prepaid. Section 53.003 permits use of certified or registered mail and
    recognizes compliance with whatever form the U.S. Postal Service requires. The Postal Service
    requires postage. 39 C.F.R. § 3030 (2003).4
    Construing the statute to not require postage at all would produce absurd results.
    Here, the first attempt at notice would have been effective; there would be no need for Wesco to re-
    send the returned correspondence because the statute’s requirements for constructive notice would
    have already been met. According to that construction, “notice” that would never and could never
    arrive would nonetheless be considered effective against Westport.
    In an attempt to temper this extreme result, Wesco asserts that its interpretation would
    indeed require some kind of notice. Because the statute should be liberally interpreted for the benefit
    of materialmen, Wesco argues, its timely but postage-deficient notice should, combined with its
    postage-prepaid but untimely notice, qualify as substantial compliance with the statute. Wesco
    characterizes the return of its notice for insufficient postage as a delay in delivery by the Postal
    Service and argues that it substantially complied with the requirement that it mail its notice within
    the statutory time period because the initial mailing occurred on July 11, and the general purpose of
    the statute’s notice provision was achieved.
    4
    “Postage must be fully prepaid on all mail at the time of mailing, except as authorized by
    law or this Schedule. Except as authorized by law or this Schedule, mail deposited without
    prepayment of sufficient postage shall be delivered to the addressee subject to payment of deficient
    postage, returned to the sender, or otherwise disposed of as specified by the Postal Service. Mail
    deposited without any postage affixed will be returned to the sender without any attempt at delivery.”
    39 C.F.R. § 3030 (2003).
    7
    The liberal construction for which Wesco argues does not excuse failure to comply
    with the statutory requirement that the materialman provide “timely written notice.” See Texas
    Constr. Assocs., Inc., v. Balli, 
    558 S.W.2d 513
    , 518-19 (Tex. Civ. App.—Corpus Christi 1977, no
    writ). In Balli, the materialman failed to provide timely written notice of part of its claim to the
    owner and contractor. 
    Id. Even though
    the contractor and the owner already had actual notice of
    the debt, liberal construction did not save the materialman’s lien from his failure to provide timely
    written notice. 
    Id. Where, as
    here, the party entitled to notice does not have actual notice, the
    requirement should apply with as much or more force. Liberal construction cannot read the timing
    requirements out of the statute. 
    Id. at 518.
    Because Wesco tried to mail its notice, it claims its efforts constitute substantial
    compliance with the statute. It is true that substantial compliance is sufficient to perfect a
    materialman’s lien. First Nat’l Bank in Graham v. Sledge, 
    653 S.W.2d 283
    , 285 (Tex. 1983). In
    Sledge, the court held that notice sent by regular instead of certified mail substantially complied with
    the notice requirements where it was undisputed that notice was actually received timely. 
    Id. at 287;
    see also Occidental Neb. Fed. Sav. Bank v. East End Glass Co., 
    773 S.W.2d 687
    , 689 (Tex.
    App.—San Antonio 1989, no writ) ( “If in fact a written notice is received, the method by which the
    notice was delivered is immaterial.”). Substantial compliance excuses deficiencies in materialman’s
    lien notices such as addressing the notice to the wrong entity where it was sent to and received by
    the right person in a “system of interlocking corporate shells,” 
    Occidental, 773 S.W.2d at 688
    , or
    failure to write the statement or bill in the usual or customary manner, where notice was timely.
    8
    Hunt Developers, Inc. v. Western Steel Co., 
    409 S.W.2d 443
    , 449 (Tex. Civ. App.—Corpus Christi
    1966, no writ).
    However, “substantial compliance” is not a license to ignore statutory requirements.
    See Conn, Sherrod, & Co. Inc. v. Tri-Electric Supply Co., 
    535 S.W.2d 31
    , 34-35 (Tex. Civ.
    App.—Tyler 1976, writ ref’d n.r.e.) (holding that liberal interpretation and substantial compliance
    did not allow courts to alter meaning of statutory language, and that timely filing of affidavit without
    correct jurat was not substantial compliance as required to perfect materialman’s lien). In Sledge,
    for instance, the court was careful to note that, in looking for substantial compliance, it determined
    whether the liens at issue were valid by comparing the steps taken to perfect them with the statutory
    requirements. 
    Sledge, 653 S.W.2d at 286
    . Failure to satisfy the notice provisions of the statute was
    fatal to the lien claim in Sledge; the court examined the only notices sent within the statutory time
    limit and decided that, because they did not contain the proper information, they did not substantially
    comply with the statute. 
    Id. at 287.
    The notice requirement, unlike the technical defects excused by substantial
    compliance, plays a critical role in achieving the purposes of this statute. The materialman’s lien
    statute is designed to protect contractors, subcontractors, and owners. Cabintree, Inc. v. Schneider,
    
    728 S.W.2d 395
    , 396 (Tex. App.—Houston [1st Dist.] 1986, writ ref’d). The purposes of notice are:
    (1) to give those parties entitled to notice an opportunity to protect their interests, and (2) to prevent
    surprise. Philbrook v. Berry, 
    679 S.W.2d 651
    , 653 (Tex. App.—Houston [1st Dist.] 1984, orig.
    proceeding). There are many examples of courts applying the notice provision to protect the interests
    of the parties entitled to notice. In disputes between the materialman and the property owner, the
    9
    owner is the party entitled to notice, and Texas courts apply the statute’s protections to the owner.
    In Raymond v. Rahme, 
    78 S.W.3d 552
    , 560 (Tex. App.—Austin 2002, no pet.), for example, the
    court required timely notice to the property owner in order for substantial compliance to make the
    lien valid. The court examined the only notice that arrived timely and found it inadequate because
    it did not contain a required warning to the owner that personal liability might attach if the debt
    remained unpaid. 
    Id. at 561.
    Similarly, the Occidental court explains the object of the statute’s
    notice provision: “[t]he common sense reason for requiring a materialman to give notice to the
    owner is to let the owner know that the contractor has not paid the materialman . . . and give[] the
    owner an opportunity to retain funds still under [the] owner’s control and to avoid the imposition
    of a statutory lien.” 
    Occidental, 773 S.W.2d at 688
    . Wesco reads these cases to hold that only the
    owner may claim protections from the notice provision. Wesco quotes Hunt Developers, which says,
    “[t]he Legislature did not intend that the materialman should lose his lien through the technicalities
    of a warning, where the owner was not misled to his prejudice,” to support the proposition that
    prejudice to the general contractor does not justify holding the materialman to the statutory notice
    requirements of the 
    statute.5 409 S.W.2d at 449
    (emphasis added). Because E&M Properties, the
    owner, received sufficient notice, Wesco argues, the lien can be valid as to Westport without timely
    notice to Westport. Under Wesco’s interpretation, the statute is not intended to protect the interests
    5
    Here Wesco uses “notice” and “warning” interchangeably, but the warning is a portion of
    the notice to the owner that explains that personal liability might attach if the bill remains unpaid.
    See Hunt Developers, Inc. v. Western Steel Co., 
    409 S.W.2d 443
    , 446-47 (Tex. Civ. App.—Corpus
    Christi 1996, no writ).
    10
    of general contractors. This reading would nullify the requirement that notice be provided to the
    general contractor.
    Neither the principles of statutory construction nor case law permit this interpretation
    because it does violence to the terms of the materialman’s lien statute by reading the notice
    provision6 completely out of the statute. See 
    Kinnear, 877 S.W.2d at 563
    ; Maryland Cas. 
    Co., 40 S.W.2d at 914
    . Furthermore, Wesco is mistaken in its assumption that the statute is not intended to
    protect the interests of general contractors. Hunt Developers itself holds substantial compliance
    “especially sufficient where no one has been misled to his prejudice.” Hunt 
    Developers, 409 S.W.2d at 449
    (emphasis added). Other cases indicate that where the materialman does not timely notify the
    general contractor entitled to notice under the materialman’s statute, the materialman has not
    substantially complied. See, e.g., Stone Fort Nat’l Bank v. Elliot Elec. Supply Co., 
    548 S.W.2d 441
    ,
    445 (Tex. Civ. App.—Tyler 1977, writ ref’d n.r.e.). In Stone Fort, the materialman claimed a lien
    because it “substantially complied” with the statute by properly and timely filing its affidavit and
    notifying the owner of the outstanding bill and of the affidavit. 
    Id. The court
    disagreed with this
    contention of substantial compliance because it ignored notice to the original contractor. 
    Id. The notice
    to the original contractor “is for the benefit of the original contractor. It is the only notice that
    the original contractor personally receives.” 
    Id. at 445-46.
    Because the materialman failed to
    6
    “If the lien claim arises from a debt incurred by a subcontractor, the claimant must give to
    the original contractor written notice of the unpaid balance. The claimant must give the notice not
    later than the 15th day of the second month following each month in which all or part of the
    claimant’s labor was performed or material delivered . . . .” Tex. Prop. Code Ann. § 53.056(b).
    11
    provide that notice, it had not complied with the requirements of the materialman’s lien statute. 
    Id. at 446.
    Wesco draws comparisons between this case and Don Hill Construction Company
    v. Dealers Electrical Supply Company, 
    790 S.W.2d 805
    (Tex. App.—Beaumont 1990, no writ). In
    Don Hill, the materialman properly notified the property owner, but failed to timely notify the
    general contractor of part of its claim. 
    Id. at 809-10.
    The owner, despite acknowledging it had
    received notice of the nonpayment, did not retain funds for the materialman, but paid the general
    contractor instead. 
    Id. at 810.
    The court held that the properly notified owner could not escape its
    own liability because notice to the general contractor was untimely. 
    Id. at 809.
    In this case, the
    owner, E&M Properties, has not escaped liability. E&M Properties properly withheld funds and
    eventually surrendered them. Don Hill does not stand for the proposition that the general contractor
    can be held liable under the materialman’s lien statute without proper notice because the
    materialman notified others; the general contractor in Don Hill argued that, because its notice was
    untimely, it could not be held liable for nonpayment under the materialman’s lien statute in the
    property code. 
    Id. at 811.
    The court held the general contractor liable under a different theory not
    presented here.7 In other words, the court found the owner liable under the materialman’s lien
    statute, but the court did not find the general contractor liable under the materialman’s lien statute.
    7
    The Don Hill court held that, because the owner paid the general contractor after receiving
    the materialman’s notice of lien, the funds it paid were trust funds held for the benefit of the
    materialman, and transfer of those funds did not change their character. Don Hill Constr. Co. v.
    Dealers Elec. Supply Co., 
    790 S.W.2d 805
    , 811-12 (Tex. App.—Beaumont 1990, no writ). Westport
    did not receive the contested amount in trust funds from E&M Properties, and neither party raises
    the issue of trust funds here. Accordingly, we do not reach it.
    12
    Texas’s materialman’s lien statute strikes a balance between interests of materialmen
    and general contractors by imputing notice to contractors to whom notice has been properly mailed.
    This scheme mirrors the evidentiary presumption that a properly mailed notice is received at its
    destination. When a sender has done everything necessary for notice to arrive, notice is considered
    effective as to the intended recipient. See Mosser v. Plano Three Venture, 
    893 S.W.2d 8
    , 11 (Tex.
    App.—Dallas 1994, no writ) (holding service by mail complete upon deposit of properly addressed
    envelope, postage prepaid, with Postal Service); Mobile Am. Sales Corp. v. Gradley, 
    612 S.W.2d 625
    , 628 (Tex. Civ. App.—Beaumont 1980, no writ) (reciting rule that presumption that mailed
    letter was received only arises upon proof of proper address, stamp, and mailing); Employers’ Nat’l
    Life Ins. Co. of Dallas, Tex. v. Willits, 
    436 S.W.2d 918
    , 921 (Tex. Civ. App.—Amarillo 1968, writ
    ref’d n.r.e.) (noting that letters properly addressed, stamped, and mailed are sufficient to raise
    presumption that they were received). This presumption relieves the sender of the difficult burden
    of showing that the recipient actually received notice. So does Texas’s materialman’s lien statute.
    See Buckner v. Anderson-Dunham, Inc., 
    482 S.W.2d 350
    , 351-52 (Tex. Civ. App.—Eastland 1972,
    no writ) (holding notice properly addressed and marked as postage paid certified mail was effective
    when mailed, not when received). Neither encompasses the absurd result that receipt of notice is
    imputed to a party to whom notice was never properly sent. The statute and case law treat certain
    parties as entitled to notice. Correspondence without postage will not and cannot ever reach the
    party entitled to notice. Imputing notice to the intended recipient when the sender had not done
    everything necessary for notice to arrive would be nonsensical and unfair, and would render the
    notice provisions of the statute a meaningless ritual.
    13
    In other contexts, Texas courts hold that mailing a notice requires proper postage.
    There has been a longstanding general rule that a mailed notice is only effective if it has been
    properly mailed, meaning properly addressed and bearing the correct amount of postage. Johnson
    Serv. Co. v. Climate Control Contractors, Inc., 
    478 S.W.2d 643
    , 645-46 (Tex. Civ. App.—Austin
    1972, no writ). Notice that is required by statute before suspending a real estate license is effective
    when it is properly stamped, addressed, certified, and mailed. Tunnell v. Texas Real Estate Comm’n,
    
    761 S.W.2d 123
    , 124 (Tex. App.—Dallas 1988, no writ); Texas Real Estate Comm’n v. Howard, 
    538 S.W.2d 429
    , 433 (Tex. Civ. App.—Houston [1st Dist.] 1976, writ ref’d n.r.e.). A lessor’s
    contractual duty to notify by mail that did not specify that proper postage be affixed was not satisfied
    by a letter that actually arrived at the correct address, but with postage due of $0.50. Rosenthal v.
    Executive Car Leasing Co. of Houston, 
    435 S.W.2d 168
    , 169-70 (Tex. Civ. App.—Houston [1st
    Dist.] 1968, no writ.) In these cases, insufficient postage meant ineffective notice.
    The district court’s decision that Wesco’s lien is invalid because its attempt to timely
    notify Westport failed for lack of sufficient postage is consistent with the statute. The effort Wesco
    made did not satisfy the notice requirements mandated by the materialman’s lien statute. We
    overrule the first issue.
    Attorney’s Fees
    In Wesco’s second issue, it argues that the district court abused its discretion in
    awarding Westport the full amount of its attorney’s fees under section 53.156 of the property code.
    The award of attorney’s fees rests in the sound discretion of the district court and will not be reversed
    absent a clear showing of abuse of discretion. Oake v. Collin County, 
    692 S.W.2d 454
    , 455 (Tex.
    14
    1985); West Tex. Rehab. Ctr. v. Allen, 
    810 S.W.2d 870
    , 874 (Tex. App.—Austin 1991, no writ). A
    trial court abuses its discretion when it acts unreasonably and arbitrarily or without reference to
    guiding principles. Beaumont Bank, N.A. v. Buller, 
    806 S.W.2d 223
    , 226 (Tex. 1991); Downer v.
    Aquamarine Operators, Inc., 
    701 S.W.2d 238
    , 241-42 (Tex. 1985). In a proceeding to foreclose a
    materialman’s lien or declare such a lien or claim invalid, the court may award costs and reasonable
    attorney’s fees that are equitable and just. Tex. Prop. Code Ann. § 53.156 (West 2002).
    Wesco argues that the district court improperly awarded attorney’s fees because
    Westport incurred the majority of those fees after and because of the court’s error. The district court
    initially denied Westport’s summary motion to remove an invalid or unenforceable lien, but later
    granted Westport’s motion for partial summary judgment made on the same grounds: untimely
    notice because of insufficient postage.        At the attorney’s fees hearing, the district court
    acknowledged that granting the first motion would have resulted in lower attorney’s fees. Wesco
    puts great emphasis on the court’s comment: “Some of this burden might need to be mine.”
    Westport responds by identifying a variety of factors the district judge should consider
    in determining attorney’s fees, including the quality of legal work, the time and effort required, the
    nature and intricacies of the case, the extent and type of the attorney’s responsibilities, and any
    benefits from the litigation. See Del Valle Indep. Sch. Dist. v. Lopez, 
    863 S.W.2d 507
    , 513 (Tex.
    App.—Austin 1997, pet. denied). Consideration of such factors is important in determining
    attorney’s fees. Arthur Anderson & Co. v. Perry Equip. Corp., 
    945 S.W.2d 812
    , 818 (Tex. 1997);
    Lubbock County v. Strube, 
    953 S.W.2d 847
    , 858 (Tex. App.—Austin 1997, pet. denied). Where,
    as here, the court took evidence and considered such factors, it did not act without reference to
    guiding principles.
    15
    Obviously, disposing of any case earlier would result in lower attorney’s fees for all
    involved. Not all cases are resolved as efficiently as, in hindsight, they could have been. However,
    the touchstone of whether attorney’s fees can be awarded is whether they were reasonable and
    necessary at the time the party incurred them. See Stewart Title Guar. Co. v. Sterling, 
    822 S.W.2d 1
    , 10 (Tex. 1991). This determination of reasonableness is a question for the trier of fact. 
    Id. at 12.
    The district court found that the fees were reasonable and necessary, including those incurred
    between the initial summary motion and the motion for partial summary judgment. Wesco continued
    to pursue its lien. Westport had no choice but to continue to incur attorney’s fees in defending its
    position. We cannot say that the district court acted unreasonably, arbitrarily, or without reference
    to guiding principles in so finding. We leave the award of attorney’s fees undisturbed.
    CONCLUSION
    We hold that the district court did not err in granting summary judgment invalidating
    Wesco’s lien because Wesco failed to provide timely notice. The grant of attorney’s fees to
    Westport was not unreasonable, arbitrary, or made without reference to guiding principles.
    Accordingly, we affirm the district court on both points.
    David Puryear, Justice
    Before Chief Justice Law, Justices Kidd and Puryear
    Affirmed
    Filed: April 8, 2004
    16
    

Document Info

Docket Number: 03-03-00438-CV

Filed Date: 4/8/2004

Precedential Status: Precedential

Modified Date: 9/6/2015

Authorities (37)

Philbrook v. Berry , 1984 Tex. App. LEXIS 6211 ( 1984 )

Mobile America Sales Corp. v. Gradley , 1980 Tex. App. LEXIS 4320 ( 1980 )

Pacesetter Pools, Inc. v. Pierce Homes, Inc. , 86 S.W.3d 827 ( 2002 )

Meno v. Kitchens , 873 S.W.2d 789 ( 1994 )

Jones v. Liberty Mutual Insurance Co. , 31 Tex. Sup. Ct. J. 257 ( 1988 )

Hayek v. Western Steel Company , 15 Tex. Sup. Ct. J. 232 ( 1972 )

WORKERS'COMP. COM'N v. Continental Cas. , 83 S.W.3d 901 ( 2002 )

Oake v. Collin County , 28 Tex. Sup. Ct. J. 492 ( 1985 )

Stone Fort National Bank v. Elliott Electric Supply Co. , 1977 Tex. App. LEXIS 2699 ( 1977 )

Texas Construction Associates, Inc. v. Balli , 1977 Tex. App. LEXIS 3645 ( 1977 )

Southwestern Life Insurance Co. v. Montemayor , 24 S.W.3d 581 ( 2000 )

Occidental Nebraska Federal Savings Bank v. East End Glass ... , 773 S.W.2d 687 ( 1989 )

Industrial Indemnity Co. v. Zack Burkett Co. , 27 Tex. Sup. Ct. J. 451 ( 1984 )

Trinity Industries, Inc. v. Ashland, Inc. , 2001 Tex. App. LEXIS 5357 ( 2001 )

Enochs v. Brown , 1994 Tex. App. LEXIS 565 ( 1994 )

Conn, Sherrod & Co. v. Tri-Electric Supply Co. , 1976 Tex. App. LEXIS 2584 ( 1976 )

LUBBOCK COUNTY, TEX. v. Strube , 1997 Tex. App. LEXIS 6745 ( 1997 )

Buckner v. Anderson-Dunham, Inc. , 1972 Tex. App. LEXIS 3019 ( 1972 )

Hunt Developers, Inc. v. Western Steel Company , 1966 Tex. App. LEXIS 2158 ( 1966 )

DEL VALLE INDEP. SCHOOL DIST. v. Lopez , 863 S.W.2d 507 ( 1993 )

View All Authorities »