bechtel-corporation-mastec-north-america-inc-dba-wilde-construction ( 2008 )


Menu:
  •       TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
    NO. 03-05-00430-CV
    Bechtel Corporation; MasTec North America, Inc., d/b/a Wilde Construction;
    C&S Network Construction and Bechtel Telecommunications, Appellants
    v.
    Citgo Products Pipeline Company, Appellee
    FROM THE DISTRICT COURT OF CALDWELL COUNTY, 22ND JUDICIAL DISTRICT
    NO. 01-0-213, HONORABLE TODD A. BLOMERTH, JUDGE PRESIDING
    OPINION
    A work crew employed by MasTec North America, Inc. d/b/a Wilde Construction
    (MasTec/Wilde) ruptured an underground gasoline pipeline owned and operated by CITGO Products
    Pipeline Company (CITGO) while excavating for an underground telecommunications line.
    Approximately 390 barrels of gasoline escaped into the surrounding area before the spill could be
    contained. CITGO incurred substantial expenses in responding to the spill and remediating
    contamination to soil and groundwater. CITGO sued MasTec/Wilde; C&S Network Construction,
    a MasTec/Wilde affiliate also involved in the project; and Bechtel Corporation and Bechtel
    Telecommunications (collectively, Bechtel), the construction manager on the project. CITGO’s
    claims were tried to a jury. Based on the verdict and evidence it subsequently heard on attorney’s
    fees, the district court awarded CITGO a total of $1,461,955.80 in actual damages from
    MasTec/Wilde (which had assumed C&S’s liabilities in addition to its own), $115,919.48 from
    Bechtel, prejudgment interest on these amounts, and $295,357.25 in attorney’s fees from
    MasTec/Wilde. MasTec/Wilde, C&S, and Bechtel have jointly appealed the judgment, bringing
    fifteen common issues. We will reverse and render judgment in part, and conditionally affirm the
    judgment in part.
    BACKGROUND
    The pipeline rupture occurred in May 1999, while appellants were laying an
    underground fiber-optic cable for Enron Broadband Services, Inc., as part of Enron Broadband’s
    “Texas Loop Project.” Enron Broadband hired MasTec/Wilde to lay the cable. MasTec/Wilde, in
    turn, subcontracted with C&S to work on the project. At all relevant times, MasTec/Wilde and C&S
    were each wholly-owned subsidiaries of MasTec, Inc. As their working arrangement was described
    at trial, MasTec/Wilde operated “rip crews” who would plow or “rip” trenches in the ground in
    which the cable would be placed, while C&S operated “bore crews” that would drill or bore holes
    underground as necessary to lay cable beneath obstacles. Enron Broadband also hired Bechtel as its
    construction manager for the Texas Loop Project. Bechtel’s job included supervising the progress
    of the cable-laying operations.
    The nature of the work to be performed on the Texas Loop Project implicated the
    Underground Facility Damage Prevention and Safety Act, commonly known as the Texas “one-call”
    statute. The current iteration of the one-call statute is codified in chapter 251 of the utilities code.
    See generally Tex. Util. Code Ann. §§ 251.001-.203 (West 2007).                At the time this case
    arose, however, the one-call statute was contained in article 9033 of the revised civil statutes,
    Act of Apr. 23, 1999, 76th Leg., R.S., ch. 62, § 18.17(a), 1999 Tex. Gen. Laws 392, 392-402
    2
    (“Former art. 9033”), and the case was tried, submitted, and briefed on appeal with extensive
    reference to that version of the statute. Although the two versions are largely identical in substantive
    respects material to this proceeding, we will refer to the former article 9033 version for clarity.
    The one-call statute generally requires that any person intending to “excavate”
    (as MasTec/Wilde and C&S undisputedly were1) to give notice to a “notification center” not earlier
    than the 14th day before the date excavation is to begin or later than the 48th hour before the time
    excavation is to begin. Former art. 9033, § 9(a). Such notice shall include (1) the name of the
    person serving the notice; (2) the “location of the proposed area of excavation,” including a street
    address, if available, or “an accurate description of the excavation area using any available
    designations such as the closest street, road, or intersection”; (3) the name, address, and telephone
    number of the excavator or excavator’s company; (4) the excavator’s “field telephone number,” if
    available; (5) “the starting date and time and the anticipated completion date of the excavation”; and
    (6) a statement as to whether explosives will be used. 
    Id. § 9(b).2
    A “notification center” under the one-call statute refers to an entity in which
    “operators” of “Class A underground facilities”—which include underground gasoline
    1
    The one-call statute defines “excavate” or “excavation” to mean “to use explosives or a
    motor, engine, hydraulic or pneumatically powered tool, or other mechanized equipment of any kind
    and includes auguring, backfilling, boring, compressing, digging, ditching, drilling, dragging,
    dredging, grading, mechanical probing, plowing-in, pulling-in, ripping, scraping, trenching, and
    tunneling to remove or otherwise disturb soil to a depth of 16 or more inches.” Act of Apr. 23, 1999,
    76th Leg., R.S., ch. 62, § 18.17(a), 1999 Tex. Gen. Laws 392, 393 (“Former art. 9033”).
    2
    A person may deliver this information “by any appropriate method, including the use of
    electronic means of data transfer,” and the notice is considered to have been provided when “the
    person delivers the required information and a notification center receives that information within
    the time limits prescribed by this Act.” 
    Id. § 11.
    3
    pipelines3—must “participate,” as a condition of doing business in Texas, by providing the
    notification center maps, grid locations, or other identifiers indicating the locations of the operator’s
    underground facilities; updates regarding any changes in such information; and the name and
    telephone number of a contact person or persons. 
    Id. § 7(a),
    (b). The notification center, in turn, is
    required, within two hours after receiving a notice of intent to excavate, to transmit the information
    received from the excavator to “each member operator that may have an underground facility in the
    vicinity of the proposed excavation operation.” 
    Id. § 8(b),
    (c).
    A C&S employee, Clint Ferguson, had the responsibility as “construction locator”
    to make the required “one-calls” for both the MasTec/Wilde rip crews and the C&S bore
    crews working on the Texas Loop Project. A portion of the project, approximately 8.5 miles
    in length, was to run through southern Caldwell County—the Luling area—along the north side of
    State Highway 90. Work on this portion of the project commenced in April 1999. Beginning as
    early as April 12, 1999, Ferguson made a series of one-calls to a notification center in advance of
    and during the crews’ work in Caldwell County. The notification center, in turn, generated
    notifications to operators of underground facilities in the area.
    East of Luling, the route of the planned Texas Loop Project excavation crossed a
    gasoline pipeline, known as the CASA Pipeline, that was owned and operated by CITGO. As one
    of the operators who had underground facilities in the area, CITGO received the notices transmitted
    by the notification center in response to Ferguson’s one-calls. The information transmitted by the
    notification center reflected that the work was to be performed by “C&S Construction” for “Enron,”
    3
    See 
    id. § 2(2).
    4
    and provided Clint Ferguson’s name and a phone number as the designated contact. The location
    of the proposed excavation was described in these notices as the entire right-of-way along the north
    side of Highway 90 running from the Caldwell-Guadalupe County line easterly to the
    Caldwell-Gonzalez County line.
    The one-call statute requires that an operator who receives a one-call notice
    must—generally within 48 hours after the time the excavator gave notice to the notification center
    of its intent to excavate, or “at a time agreed to by the operator and the excavator”—“mark the
    approximate location of its underground facilities at or near the site of the proposed excavation if
    the operator believes that marking the location is necessary.” Former art. 9033, § 14(a).4 The statute
    also affords an operator the right to be present at an excavation site if it meets certain conditions:
    To have a representative present during the excavation, the operator shall contact the
    excavator and advise the excavator of the operator’s intent to be present during
    excavation and confirm the start time of the excavation. If the excavator wants to
    change the start time, the excavator shall notify the operator to set a mutually
    agreed-to time to begin the excavation.
    
    Id. § 9(c).
    Importantly, if “[a]n excavator . . . has fully complied with the Act,” the statute further
    provides, the excavator “may not be liable for damage to an underground facility that was not
    marked in accordance with the Act.” 
    Id. § 14(c).
    4
    The one-call statute has since been amended to require an operator who does not
    deem marking its facilities “necessary” to give notice of such action to the excavator within
    48 hours. Act of May 22, 2001, 77th Leg., R.S., ch. 858, § 2, 2001 Tex. Gen. Laws 1707, 1707-08,
    codified at Tex. Util. Code Ann. § 251.157(d) (West 2007). No such provision was contained in the
    version of the one-call statute applicable to this case, however.
    5
    It is undisputed that, on May 7, 1999, a MasTec/Wilde rip crew struck the
    CASA Pipeline with a “rip cat,”a piece of machinery, weighing 70,000 to 80,000 pounds and having
    an 8 to 10 foot blade, used in trenching operations to “rip” or break up ground in advance of a
    bulldozer or plow. The impact ruptured the pipeline. Although there was fortunately no explosion,
    approximately 390 barrels of gasoline escaped before the spill could be contained. CITGO was able
    to recover only about 40 barrels of the gasoline. The escaped gasoline caused contamination to
    soil and groundwater. In addition to its lost product and pipeline repairs, CITGO incurred substantial
    expenses in responding to and remediating the spill.
    Trial centered largely on whether appellants or CITGO were responsible for the
    accident and the extent to which CITGO, C&S, and MasTec/Wilde had each complied with their
    respective obligations under the one-call statute. To summarize, CITGO maintained that its
    employees and agents had promptly responded to each one-call notification by contacting Ferguson
    to inquire about the details of his crews’ upcoming work. During these conversations, according to
    CITGO, Ferguson was informed that CITGO intended to have a representative present if his crews
    excavated near the CASA Pipeline and that Ferguson had agreed that no such work would occur
    without prior notice to CITGO. It further claimed that in response to a one-call notification it
    received on the morning of May 7, CITGO’s Sam Bentley called Ferguson and obtained assurances
    that Ferguson’s crews would be working several miles to the east of the CASA Pipeline area that
    day. Under CITGO’s theory, appellants breached these understandings or promises and violated the
    one-call statute when the MasTec/Wilde rip crew excavated in the area later that day without prior
    notice and without a CITGO representative present.
    6
    Appellants, by contrast, argued that CITGO was to blame for the accident because
    it had failed to locate and mark the CASA Pipeline in compliance with the one-call statute and had
    even placed stakes at the site that created the misleading impression regarding areas where the crews
    could safely work. According to appellants, Ferguson’s understanding with CITGO was that he
    would contact CITGO before his crews worked within the staked area. Appellants further contended
    that the MasTec/Wilde rip crew had hit the CASA Pipeline outside the staked area.
    A pivotal event in both side’s versions of the underlying facts was an April 22
    meeting between CITGO subcontractor Alton Schulle and Ferguson in the general area of the CASA
    Pipeline crossing. Schulle and Ferguson arranged the meeting to discuss excavation near the
    pipeline.   An understanding of the configuration of the Highway 90 right-of-way and the
    above-ground features signifying the presence of the pipeline is helpful in understanding the
    subsequent events. In this area, Highway 90 runs in roughly an east-west direction. A fenceline,
    located several feet north of the highway, ran roughly parallel to the highway. In the fenceline was
    a metal pipeline marker, and some fenceposts on either side were topped in white—an indication
    of a pipeline right-of-way. Near the metal pipeline marker was a vent pipe extending out of the
    ground. Another vent pipe appeared on the south side of Highway 90, at an angle southeast of the
    other vent pipe.
    During this meeting, Schulle attempted to locate the pipeline with an electronic
    “line finder.” He was unsuccessful. Schulle placed a wooden, flagged stake roughly eight feet south
    of the vent pipe on the north side of Highway 90 and, later, two additional stakes—one
    approximately 17 feet to the west of the first stake, and the other 15 and one half feet to the east of
    7
    the original stake. The parties gave competing accounts regarding what Schulle had intended the
    stakes to signify. According to Ferguson, after Schulle had attempted unsuccessfully to locate the
    pipeline with his line-finder, Schulle approximated the pipeline route by standing on the highway
    and “lining up” the vent pipe on each side of the highway with his arms. Based on this estimation,
    Ferguson recounted, Schulle placed the middle stake to indicate where he thought the pipeline ran.
    Ferguson further testified that he asked Schulle to mark a “safety zone” that his crews would know
    to avoid and outside of which they could work. The pair parted ways after their meeting, Ferguson
    claimed, with Schulle indicating he would return with a different line-finder and attempt again to
    locate the pipeline. Later that day, Ferguson recounted, the two additional stakes had appeared at
    the site. According to Ferguson, although he knew the precise location of the pipeline had not been
    located, he understood the three stakes to signify that the pipeline was located somewhere within that
    area and that his crews could work safely outside of it.
    Schulle, by contrast, denied that he had ever agreed or purported to mark a
    “safety zone” where the pipeline actually ran. He claimed that he had placed the stakes solely to call
    attention to the CASA Pipeline right-of-way because the metal pipeline marker in the fence, as well
    as the white-topped fenceposts, were obscured by brush.5 Schulle and other CITGO witnesses
    claimed that Ferguson had a clear understanding that the CASA Pipeline had not yet been located
    and that it would be necessary to find the line by carefully digging with a backhoe or by hand to
    unearth it before the cable project could cross it. Such efforts, CITGO claims it repeatedly
    5
    Schulle compared his use of the stakes to “the way you would use a highlighter on a piece
    of paper” and “was in no way to tell anyone where the pipeline was specifically located.”
    8
    emphasized to Ferguson, should occurr only when its representatives were present. According to
    CITGO, Ferguson shared that understanding and had agreed that his crews would not dig near the
    CASA Pipeline without prior notice to CITGO and its representative being present. It claims that,
    in reliance on this understanding, CITGO did not perceive a need to mark the precise route of the
    pipeline, as it anticipated that it would work with Ferguson’s crews to unearth the line at the
    appointed time. Ferguson, although not disputing that he had promised to give notice to CITGO
    before his crews excavated over the pipeline, claimed that this obligation applied only to work his
    crews would perform within the staked area.
    On May 6, Schulle and CITGO’s Sam Bennett arranged with Ferguson to meet with
    Chad Treadwell, the drilling superintendent of the C&S bore crews. Treadwell recounted that the
    purpose of the meeting was to discuss how the crew was to bore under or cross the CASA Pipeline.
    He acknowledged that Ferguson had told him that the precise location of the pipeline had not yet
    been located. During the meeting, Schulle and Bentley tried to find the pipeline with a line-finder,
    again without success. Ferguson, at Bentley’s request, dug a trench with a backhoe in front of the
    middle stake in an attempt to locate the pipeline. They did not find it. Based on this information,
    Bentley concluded that the pipeline was located somewhere to the east of the middle stake. He
    permitted the boring crew to dig in the west part of the staked area in order to bore under a TXDOT
    gravel or dirt pile to the immediate west. The CITGO agents did not adjust or move the stakes,
    however. Bentley explained that he did not believe it necessary to readjust the stakes because
    CITGO had been assured that no excavation would take place at the location without prior notice.
    9
    As it turned out, the portion of the CASA Pipeline north of Highway 90 ran
    mostly to the east of the staked area. From the south, the pipeline passes near the vent pipe south
    Highway 90 and crosses at a right angle to the roadway, continues running northward into the
    highway right-of-way for several feet, then veers at a sharp angle to the northwest. The pipeline
    continues in a northwesterly direction so as to cross the fenceline some distance to the west of the
    plane on which it had crossed Highway 90 and from which it bent northwestward.6 Because of the
    configuration of the pipeline, all or substantially all of the pipeline segments south of the stakes lay
    to the east of the staked area.
    CITGO presented evidence of how its employees and agents responded to the one-call
    notifications generated by Ferguson, including copies of the one-call notifications. On virtually all
    is a stamped form eliciting “Person Contacted,” “Date,” “By,” and “Remarks.” Each form is
    completed by hand. According to the handwritten notations, Ferguson assured CITGO on numerous
    occasions that his crews would be working in areas other than near the CASA Pipeline and that
    he would contact CITGO before his crews began work near the line. One notification, dated
    May 5, 1999, at 16:30 (4:30 p.m.), contained handwritten notations indicating that CITGO’s
    “Dennis Elly” contacted “Clint” and was advised that “they were about 1 mile west of line.”
    Another notification, dated May 7, at 10:15 a.m., contains handwritten notations indicating that
    CITGO’s Sam Bentley contacted Clint Ferguson that day and was advised: “This work is east of our
    line in Harwood area. Will not be working near our line today.” Harwood is a Caldwell County
    6
    Consequently, if, as Ferguson alleged, Schulle had estimated the pipeline route by lining
    up the two vent pipes, Schulle would have identified the long side of a triangle whose other two sides
    were formed by the pipeline’s actual route.
    10
    community located on Highway 90 several miles east of the CASA Pipeline area. Bentley testified
    that he obtained these assurances during the morning of May 7.              Ferguson denied giving
    such assurances.
    Later that same day, at approximately 3:00 p.m., the MasTec/Wilde crew hit the
    CASA Pipeline with its rip cat. The operator as well as his supervisor, testified that they had
    assumed the three wooden stakes at the site reflected the actual pipeline route, and that no one had
    informed them that the pipeline had, in fact, not yet been located. There was also evidence that,
    consistent with this belief, the operator had attempted to avoid the staked area and begun ripping at
    or near the eastern stake going eastward. Although the precise location where the rip cat struck the
    pipeline was disputed, there was evidence that the impact had occurred in an area of the pipeline east
    of the staked area.
    CITGO subsequently sued a number of parties for damages it incurred in connection
    with the pipeline rupture. It asserted causes of action for negligence, negligence per se, trespass,
    breach of contract, and promissory estoppel against MasTec/Wilde and C&S. In addition, CITGO
    asserted causes of action for negligent hiring, negligent retention, and negligent supervision
    against Bechtel. As to all defendants, CITGO alleged malice and sought exemplary damages.
    MasTec/Wilde, C&S, and Bechtel raised affirmative defenses, including immunity under the
    one-call statute.
    The district court submitted jury issues regarding negligence against C&S,
    MasTec/Wilde, Bechtel, and CITGO; promissory estoppel against C&S and MasTec/Wilde; trespass
    against C&S and MasTec/Wilde; and appellants’ affirmative defense of immunity under the one-call
    11
    statute. Predicated on affirmative findings as to either negligence or trespass as to one or more
    defendants, the court also submitted whether such conduct had been committed with malice. The
    jury found that the negligence of all parties had proximately caused the pipeline rupture, and
    apportioned responsibility 30 percent to MasTec/Wilde, 50 percent to C&S, 10 percent to Bechtel,
    and 10 percent to CITGO. The jury awarded $1,159,194.75 in past negligence damages and
    $668,250.00 in future negligence damages. The jury failed to find that either C&S or MasTec/Wilde
    had committed trespass or that any defendant had acted with malice in committing negligence. As
    for promissory estoppel, the jury found that CITGO had foreseeably relied to its detriment on a
    promise by both MasTec/Wilde and C&S and awarded $871,413.99 in past damages and
    $668,250.00 in future damages. CITGO had requested attorney’s fees under its promissory estoppel
    theory, and the parties subsequently tried the amount of such fees to the district court.
    Regarding appellants’ claims of immunity under the one-call statute, the district court
    instructed the jury by quoting pertinent portions of the statute and submitting, over objection, a
    series of three questions that followed a burden-shifting framework: (1) did MasTec/Wilde and
    C&S each “give the notice required by Section 9(a) and 9(b) of the Texas One-Call Statute?”
    (i.e., the one-call notice); (2) if so, “Did CITGO respond in accord with Section 9(c) [regarding the
    right to be present at the excavation] and 14 [regarding marking its facilities] of the Texas One-Call
    Statute?”; and (3) if so, did MasTec/Wilde and C&S each “then respond in accord with requirements
    for excavators as described in Section 9(c) of the Texas One-Call Statute.” In the first question, the
    jury found in the affirmative as to both MasTec/Wilde and C&S. In the second question, the jury
    12
    found in the affirmative. In the third question, the jury found that neither MasTec/Wilde nor C&S
    had responded in accord with section 9(c).
    The district court rendered judgment on the verdict. Because MasTec/Wilde had
    assumed all of C&S’s liabilities, the court imposed judgment against MasTec/Wilde for the damages
    the jury had awarded against both affiliates. Against MasTec/Wilde, the district court awarded
    CITGO $927,355.80 in past damages and $534,600.00 in future damages, amounts reflecting the
    total percentages of responsibility that the jury had imposed against MasTec/Wilde and C&S for
    negligence (30 percent + 50 percent = 80 percent) applied to the jury’s awards of past and future
    negligence damages. Similarly, the court awarded CITGO $115,919.48 in past damages and
    $66,825.00 in future damages from Bechtel, reflecting the 10 percent of negligence responsibility
    that the jury had apportioned to that party. Further, based on the jury’s promissory estoppel findings
    against MasTec/Wilde and C&S, the district court awarded CITGO $295,357.25 in trial-level
    attorney’s fees, plus a total of another $75,000 in conditional appellate attorney’s fees. Finally the
    court awarded prejudgment interest of $236,629.18 against MasTec/Wilde and $29,577.46 against
    Bechtel, and assessed court costs against MasTec/Wilde.
    MasTec, C&S, and Bechtel appealed.
    ANALYSIS
    Appellants bring a total of fifteen issues that can be categorized into four groups:
    (1) issues concerning the affirmative defense of immunity under the one-call statute; (2) an issue
    challenging the imposition of negligence liability against them; (3) issues contesting the amount of
    13
    past and future damages awarded in the judgment; and (4) issues attacking the attorney’s fee award
    and the underlying jury findings regarding promissory estoppel.
    One-call statute
    As noted, the one-call statute has provided at all relevant times that “[a]n excavator
    who has fully complied with this Act may not be liable for damage to an underground facility that
    was not marked in accordance with this Act.” Former art. 9033, § 14(c). The district court
    submitted the fact issues controlling the application of this defense in Question 12 of the charge. In
    Question 12, the court instructed the jury as follows:
    You are instructed that Texas Underground Damage Prevention and Safety Act,
    commonly known as the “Texas One-Call Statute,” states as follows:
    SECTION 9: DUTY OF AN EXCAVATOR.
    (a)     A person who intends to excavate shall notify a notification center not earlier
    than the 14th day before the date the excavation is to begin or later than the
    48th hour before the time the excavation is to begin, excluding Saturdays,
    Sundays, and legal holidays. Provided, however, if an excavator makes a
    Saturday notification, the excavator may begin the excavation the following
    Tuesday at 11:59 a.m. unless the intervening Monday is a holiday. If the
    intervening Monday is a holiday, the excavator may begin the excavation the
    following Wednesday at 11:59 a.m.
    (b)     The notice required under this section shall include:
    (1)     the name of the person serving the notice;
    (2)     the location of the proposed area of excavation, including;
    (A)     the street address, if available, and the location of the
    excavation at the street address; or
    (B)     if there is no street address, an accurate description using any
    available designations such as the closest street, road, or
    intersection;
    14
    (3)     the name, address, and telephone number of the excavator or the
    excavator’s company;
    (4)     the excavator’s field telephone number, if one is available;
    (5)     the starting date and time and the anticipated completion date of
    excavation; and
    (6)     a statement as to whether explosives will be used.
    (c)     To have a representative present during the excavation, the operator shall
    contact the excavator and advise the excavator of the operator’s intent to be
    present during excavation and confirm the start time of the excavation. If the
    excavator wants to change the start time, the excavator shall notify the
    operator to set a mutually agreed-to time to begin the excavation.
    SECTION 14. DUTY OF OPERATOR TO PERSON EXCAVATING.
    (a)     Not later that the 48th hour after the time the excavator give[s] to the
    notification system notice of intent to excavate, excluding Saturdays,
    Sundays, and legal holidays, 11:59 a.m. on the Tuesday following a Saturday
    notification unless the intervening Monday is a holiday, or at a time agreed
    to by the operator and the excavator, each Class A underground facility owner
    shall mark the approximate location of its underground facilities at or near the
    site of the proposed excavation if the operator believes that marking the
    location is necessary.
    (b)     An operator shall refer to the American Public Works Association color
    coding standards when marking.
    (c)     An excavator who has fully complied with this Act may not be liable for
    damage to an underground facility that was not marked in accordance with
    the Act.
    With the exception of two textual differences that are not material to this case, these
    instructions tracked verbatim sections 9 and 14 of former article 9033, the version of the
    one-call statute applicable to this case.7 See, e.g., Borneman v. Steak & Ale of Tex., 
    22 S.W.3d 7
              The first difference was that the first sentence of section 9(a) omitted a qualifier found in
    the statute, “Except as provided in sections 12 and 13 of this Act . . . .” Former art. 9033, § 9(a).
    The second was in section 14(a). The instruction omitted the statutory deadline for the operator to
    15
    411, 413 (Tex. 2000) (“As a general rule, when a statutory cause of action is submitted, the charge
    should ‘track the language of the provision as closely as possible.’”) (quoting Spencer v. Eagle Star
    Ins. Co. of Am., 
    876 S.W.2d 154
    , 157 (Tex. 1994)).
    Following these instructions, the district court submitted the following question:
    QUESTION NO. 12A
    Did the Defendants listed below give the notice required by Section 9(a) and 9(b) of
    the Texas One-Call Statute?
    Answer “Yes” or “No” as to each:
    MasTec/Wilde            _____
    C&S                     _____
    Predicated on an affirmative finding as to either defendant, the jury was instructed to answer the
    following:
    QUESTION NO. 12B
    Did CITGO respond in accord with Section 9(c) and 14 of the Texas One-Call
    Statute?
    Answer “Yes” or “No”:
    Predicated on an affirmative answer to 12B, the jury was instructed to answer the following:
    mark their facility applicable when an excavator makes a Saturday notification and the intervening
    Monday is a holiday––Wednesday at 11:59 a.m. 
    Id. § 14(a).
    It is undisputed that the excavation at
    issue here occurred on a Friday.
    16
    QUESTION NO. 12C
    Did the Defendants listed below then respond in accord with requirements for
    excavators as described in Section 9(c) of the Texas One-Call Statute?
    Answer “Yes” or “No” as to each:
    MasTec/Wilde           _____
    C&S                    _____
    The jury found in the affirmative as to both MasTec/Wilde and C&S in Question 12A—that
    each had “give[n] the notice required by Section 9(a) and 9(b) of the Texas One-Call Statute”—and
    found in Question 12B that CITGO had “then respond[ed] in accord with Section 9(c) and 14 of
    the Texas One-Call Statute,” but found in Question 12C that neither MasTec/Wilde nor C&S had
    “then respond[ed] in accord with requirements for excavators as described in Section 9(c) of the
    Texas One-Call Statute.” In light of these findings, the district court did not give effect to the
    affirmative defense of immunity under the one-call statute.
    At trial, appellants objected to Question 12A, 12B, and 12C on the ground that
    “the special interrogatory structure of the question does not comply with broad form requirements
    that are currently dictated by the Texas rules and courts.” They tendered what they regarded as a
    substantially correct version of the question containing the following interrogatories:
    Did the Defendants listed below fully comply with the Texas One-Call Statute?
    Answer “Yes” or “No” for each of the following:
    C&S                    _____
    MasTec/Wilde           _____
    17
    Predicated on an affirmative answer as to either defendant, the jury would then have answered the
    following question:
    Did CITGO mark its pipeline in accordance with the Texas One-Call Statute?
    Answer “Yes” or “No”
    ________8
    Appellants bring this complaint forward in their seventh issue on appeal, arguing that the district
    court abused its discretion in failing to submit the controlling issues regarding immunity under the
    one-call statute in broad form. They further contend on appeal that Question 12C “did not track the
    statutory language at all” or “implied to the jury that Defendants were obligated to respond under
    Section 9(c).” Even assuming that appellants preserved both complaints for appeal, we cannot
    conclude that the district court abused its discretion.
    Our analysis of appellants’ contentions relating to the one-call statute turn, in the first
    instance, on statutory construction. Statutory construction presents a question of law that we review
    de novo. See State v. Shumake, 
    199 S.W.3d 279
    , 284 (Tex. 2006). Our primary objective in
    statutory construction is to give effect to the legislature’s intent. 
    Id. We seek
    that intent “first and
    foremost” in the statutory text. Lexington Ins. Co. v. Strayhorn, 
    209 S.W.3d 83
    , 85 (Tex. 2006).
    We consider the words in context, not in isolation. State v. Gonzalez, 
    82 S.W.3d 322
    , 327
    8
    Appellants’ proposed submission also contained a “further instruction” that “a joint
    venture is a legal entity that meets the definition of a ‘person’ under the Texas One-Call Statute,”
    with a definition of the essential elements of “joint venture.” Because we conclude that the district
    court did not abuse its discretion in submitting Question 12, we need not address whether, as CITGO
    contends, the proposed “joint venture” instruction was not in substantially correct form.
    18
    (Tex. 2002). We rely on the plain meaning of the text, unless a different meaning is supplied by
    legislative definition or is apparent from context, or unless such a construction leads to absurd
    results. City of Rockwall v. Hughes, 
    246 S.W.3d 621
    , 625-26 (Tex. 2008) (citing Texas Dep’t of
    Transp. v. City of Sunset Valley, 
    146 S.W.3d 637
    , 642 (Tex. 2004); Taylor v. Firemen’s &
    Policemen’s Civil Serv. Comm’n of City of Lubbock, 
    616 S.W.2d 187
    , 189 (Tex. 1981); University
    of Tex. Sw. Med. Ctr. v. Loutzenhiser, 
    140 S.W.3d 351
    , 356 (Tex. 2004)); see Tex. Gov’t Code Ann.
    § 311.011 (West 2005) (“[w]ords and phrases shall be read in context and construed according to
    the rules of grammar and common usage”).
    Section 14(c) of the one-call statute states that “[a]n excavator who has fully complied
    with this Act may not be liable for damage to an underground facility that was not marked in
    accordance with this Act.” Former art. 9033, § 14(c). Section 14(c) thus provides immunity from
    “liability for damage to an underground facility” if an excavator can prove two elements: (1) the
    “excavator . . . has fully complied with this Act”; and (2) the underground facility “was not marked
    in accordance with this Act.” The term “fully complied” plainly denotes complete compliance with
    the one-call statute in all respects, as contrasted with partial compliance or substantial compliance.
    See United States v. Locke, 
    471 U.S. 84
    , 100-01 (1985) (discussing the concept of substantial
    versus full compliance in the context of statutory deadlines); CenterPoint Energy Houston Elec.,
    LLC v. Gulf Coast Coalition of Cities, 
    252 S.W.3d 1
    , 15 (Tex. App.—Austin 2008, pet. filed)
    (“We presume that every word was deliberately chosen and that excluded words were left out on
    purpose.”) (citing USA Waste Servs. of Houston, Inc. v. Strayhorn, 
    150 S.W.3d 491
    , 494
    (Tex. App.—Austin 2004, pet. denied)). Whether or how an excavator “fully complied” with the
    19
    one-call statute begins with section 9 of the statute, titled “Duty of an excavator.” Section 9(a), as
    discussed, requires an excavator to give at least 48 hours notice to a notification center of its intent
    to excavate, while section 9(b) specifies the content of such notifications. 
    Id. § 9(a),
    (b). Question
    12A appropriately inquired whether MasTec/Wilde and C&S each gave “the notice required by
    Section 9(a) and 9(b) of the Texas One-Call Statute?”
    A one-call notice in compliance with section 9(a) and (b), in turn, triggers an
    operator’s duty under section 14 to “mark the approximate locations of its underground facilities at
    or near the site of the proposed excavation.” 
    Id. § 14(a),
    (b). Section 9(c) also provides that an
    operator has a right “[t]o have a representative present during the excavation” if the
    operator—presumably in response to the one-call notification it received after the excavator
    complied with section 9(a) and (b)—“contact[s] the excavator” and (1) advises it of the operator’s
    “intent to be present during excavation” and (2) “confirm[s] the start time of the excavation.” 
    Id. § 9(c).
    Consistent with this statutory framework, Question 12B, conditioned upon an affirmative
    finding in Question 12A that one-call notification was given, inquired whether CITGO “respond[ed]
    in accord with Section 9(c) and 14 of the Texas One-Call Statute.” By answering “yes” to this
    conjunctive submission, the jury found that CITGO complied with both the marking requirements
    of section 14 and the conditions for invoking its right to be present at the excavation under
    section 9(c).
    If an operator invokes its right to be present during the excavation by meeting
    the conditions under section 9(c), as the jury found here, the excavator then has a mandatory duty
    not to “change the start time” without “notify[ing] the operator to set a mutually agreed to time.”
    20
    See 
    id. § 9(c).
    Whether MasTec/Wilde or C&S each complied with these duties was the focus of
    Question 12C. That question was conditioned upon an affirmative response in Question 12B—i.e.,
    that CITGO had invoked the duties under section 9(c)—and inquired whether each
    “then respond[ed] in accord with requirements for excavators as described in Section 9(c) of the
    Texas One-Call Statute.”
    In sum, the burden-shifting, conditioned sequence that the district court employed in
    Question 12 tracked the statutory framework and properly submitted the fact issues whose resolution
    controlled whether MasTec/Wilde and C&S were entitled to immunity from liability under the
    one-call statute in this case. We disagree with appellants that the district court abused its
    discretion in declining to submit the parties’ compliance with the one-call statute in the broad-form
    manner they proposed. Although trial courts must submit fact issues to the jury in broad form
    “whenever feasible,” Tex. R. Civ. P. 277, “‘it is not always practicable to submit every issue in a
    case broadly,’ and broad-form submissions cannot be used to broaden the harmless error rule to deny
    a party the correct charge for which it otherwise would be entitled.” Romero v. KPH Consolidation,
    Inc., 
    166 S.W.3d 212
    , 230 (Tex. 2005) (quoting Harris Co. v. Smith, 
    96 S.W.3d 230
    , 235
    (Tex. 2002)). Here, broad-form submission as proposed by appellants was not practicable for at least
    two related reasons. First, appellants’ proposal omitted any issue or instruction regarding whether
    CITGO had complied with its duties under section 9(c) to notify appellants that it desired to be
    present during the excavation. CITGO was entitled to obtain a finding on that question as a basis
    for imposing duties on appellants under section 9(c). Second, appellants’ proposed issue as to
    whether C&S and MasTec/Wilde “fully complied” with the one-call statute would have subsumed
    21
    whether appellants (1) made the one-calls required under sections 9(a) and (b), and (2) complied
    with any duties under section 9(c). An affirmative finding on such an issue would leave an appellate
    court unable to determine whether the jury found that (1) appellants complied with sections 9(a) and
    (b) and CITGO did not comply with section 9(c) so as to give rise to appellants’ duties under that
    provision, or (2) appellants complied with sections 9(a) and (b), CITGO complied with section 9(c),
    and appellants complied with section 9(c). As CITGO contends, “[t]he questions as requested by
    Appellants would not have permitted proper review of the case on appeal.” We overrule appellants’
    seventh issue.
    In their fifth issue, appellants argue that the district court erred in failing to disregard
    the jury’s answers to Questions 12B and 12C and render judgment that CITGO take nothing.
    Appellants argue principally that the evidence conclusively establishes that they complied with
    the notification requirements of section 9(a) and (b) and that CITGO failed to comply with
    section 14 by failing to mark the CASA Pipeline. However, it not clear that appellants are
    challenging the jury’s other finding in Question 12B that CITGO complied with section 9(c) so as
    to give rise to MasTec/Wilde and C&S’s duties under that provision. As for whether MasTec/Wilde
    and C&S complied with those duties, appellants contend only that “the jury’s answer to 12C should
    be disregarded” because “[t]hough the jury found that Defendants failed to notify the pipeline
    operator of the excavation start time, the record shows Defendants gave numerous notifications
    within the time frame required by statute.” In support, appellants cite to the copies of the one-call
    notifications in evidence, which, it emphasizes, “Citgo conceded that it received.” Although copies
    of the one-call notifications may be probative of whether MasTec/Wilde or C&S complied with the
    22
    notification requirements of section 9(a) or (b), so as to support the jury’s findings in Question 12A,
    the jury’s finding in 12C instead turned on the nature of the communications between CITGO and
    Ferguson after CITGO’s receipt of Ferguson’s one-call notifications.
    In any event, we conclude that the evidence was legally and factually sufficient to
    support the jury’s findings in 12B that CITGO “respond[ed] in accord with Section 9(c)” and in 12C
    that neither MasTec/Wilde nor C&S “respond[ed] in accord with requirements for excavators as
    described in Section 9(c).”
    When a party challenges the legal sufficiency of the evidence supporting an adverse
    finding on an issue on which it has the burden of proof, that party must demonstrate on appeal
    that the evidence conclusively established, as a matter of law, all vital facts in support of the issue.
    Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 241 (Tex. 2001). In conducting a legal sufficiency
    review of the evidence, a court must consider all of the evidence in the light most favorable to the
    fact finding and indulge every reasonable inference that would support it. City of Keller v. Wilson,
    
    168 S.W.3d 802
    , 822 (Tex. 2005).
    When a party attacks the factual sufficiency of an adverse finding on an issue on
    which he has the burden of proof, he must demonstrate on appeal that the adverse finding is against
    the great weight and preponderance of the evidence. Dow Chem. 
    Co., 46 S.W.3d at 241
    . The court
    of appeals must consider and weigh all of the evidence, and can set aside a finding only if the
    evidence is so weak or if the finding is so against the great weight and preponderance of the evidence
    that it is clearly wrong and unjust. 
    Id. 23 As
    previously described, CITGO presented evidence that, in response to one-call
    notifications and in a face-to-face meeting, it had repeatedly informed Clint Ferguson of its intent
    to be present at any excavation near the CASA Pipeline and that Ferguson and CITGO had an
    ongoing understanding that his crews would not excavate near the CASA Pipeline without prior
    notice and a CITGO representative present. Further, in the context of this alleged understanding,
    CITGO’s Sam Bennet testified that he responded to a one-call notification during the morning of the
    accident by calling Ferguson and obtaining Ferguson’s assurances that his crews would be working
    several miles away from the pipeline that day. In terms of section 9(c), CITGO had contacted
    Ferguson, informed Ferguson of its intent to be present when his crews were excavating near the
    CASA Pipeline, and confirmed that there would be no “start time” for such excavation that day.9
    9
    In an amicus curiae brief, the National Utility Contractor’s Association argues that
    “in order to establish compliance with the statute, Citgo had to prove that it advised Appellants of
    its intent to be present during the excavation that actually occurred and that Citgo confirmed the start
    time of that excavation” and that “[o]nly if Citgo complied with these requirements and there was
    a confirmed start time, would Appellants have had a duty to notify Citgo that they wanted to change
    the start time and reach an agreement as to when to begin excavation.” We generally agree that the
    burden is initially upon the operator to comply with the requirements of section 9(c) before any
    duties arise under it on the part of the excavator. As we have explained, the district court correctly
    placed this burden in the jury charge. The Association further urges that “there is no evidence or
    insufficient evidence that Citgo ever made a request to be present during the excavation that actually
    took place near the Luling site or that Citgo complied with its obligation to ‘confirm the start time
    of the excavation.’” (Emphasis added). The Association’s apparent premise is that an operator’s
    confirmation that no excavation will be occurring at a location on a particular day does not suffice
    to “confirm the start time” of an excavation. Similarly, it suggests that if the excavator subsequently
    reneges and excavates there anyway without informing the operator, the operator will have failed to
    advise the excavator of its intent to be present “during the excavation that actually took place”
    despite having been assured that the excavation would not be occurring at all. To the contrary, we
    conclude from the text and structure of section 9(c) that an operator would necessarily “confirm the
    start time” of an excavation if it confirmed that the excavator would start no excavation at a
    particular location on a particular day, to the same extent as if the excavator provided a time at which
    it actually would start excavating. In either case, if the excavator subsequently decided to deviate
    from that understanding, section 9(c) would require it to “notify the operator to set a mutually
    agreed-to time.”
    24
    Although Ferguson disputed Bennett’s version of this conversation, the jury could have reasonably
    credited Bennett’s account, and it was the jury’s province to resolve the conflict in the manner it did.
    See City of 
    Keller, 168 S.W.3d at 819
    , 822 (we may not substitute our judgment for the jury’s, and
    we must defer to the jury’s determinations of the credibility of the witnesses, the weight to be
    given the testimony, and the resolution of evidentiary conflicts.) The evidence was sufficient
    to support the jury’s finding in Question 12B that CITGO had complied with section 9(c). As
    for Question 12C, the evidence is sufficient, if not undisputed, that CITGO was never notified
    that a MasTec/Wilde rip crew would, contrary to Ferguson’s statements, be excavating near the
    pipeline after all.
    Because MasTec/Wilde and C&S could not have “fully complied with the Act”—the
    first element of immunity under the one-call statute—if they failed to comply with duties under
    section 9(c), the jury’s findings regarding section 9(c) in Questions 12B and 12C support the district
    court’s judgment in which it refused to give effect to appellants’ immunity defense. This is true
    regardless of whether the evidence also supports the jury’s additional finding in Question 12B that
    CITGO complied with section 14. Although that finding would go to the second element of
    immunity—whether the CASA Pipeline was “marked in accordance with the Act,” see former art.
    9033, § 14(c)—it has no bearing on an excavator’s duties under section 9(c). The legislature, again,
    made those duties contingent upon an operator’s compliance with the conditions in section 9(c), not
    section 14. We overrule appellants’ fifth issue.10
    10
    CITGO brings a cross-point in which it contends the evidence is legally and factually
    sufficient to support the jury’s findings in Question 12A that both MasTec/Wilde and C&S gave
    “the notice required by Section 9(a) and 9(b) of the Texas One-Call Statute.” Specifically, CITGO
    25
    Finally, in their sixth issue, appellants urge that CITGO’s recovery should be barred
    as a matter of “public policy” because, they again urge, CITCO failed to mark the CASA Pipeline
    in compliance with section 14 of the one-call statute. We observe that the legislature—the principal
    arbiter of public policy under our tripartite system of government—has not seen fit to provide
    excavators immunity based solely on the failure of an operator to mark its underground facilities.
    Instead, the excavator must “fully comply” with the statute. See former art. 9033, § 14(c). This
    includes section 9(c). The gravamen of appellants’ argument is that we should judicially eliminate
    or ignore one of the two statutory elements of one-call statute immunity.
    Appellants attempt to justify such a holding by invoking common-law concepts that
    have been applied to bar recovery under an insurance policy where the covered loss was caused by
    the policy beneficiary’s own intentional conduct. See Norman v. State Farm Fire & Cas. Co.,
    
    804 F.2d 1365
    , 1366 (5th Cir. 1986). Equating CITGO’s alleged failure to mark the CASA Pipeline
    as required by section 14 to such conduct as arson, appellants reason that CITGO should similarly
    be barred from “benefitting from its own wrongdoing” by recovering damages from the pipeline
    rupture under negligence and promissory estoppel theories. Appellants cite no authority for
    extending the concept of Norman in this manner, and we are aware of none. We also observe
    that Texas law already accounts for the type of “wrongdoing” of which appellants complain
    through proportionate responsibility. Here, the jury attributed ten percent of the negligence
    argues that there is no evidence that anyone other than Clint Ferguson, a C&S employee, made
    one-call notifications in connection with the Texas Loop Project work and that these calls by C&S
    did not suffice when the “excavator” who damaged its pipeline was MasTec/Wilde. Because we
    have overruled appellants’ challenge to the jury’s findings in Question 12B and 12C, we need not
    reach CITGO’s cross-point.
    26
    that proximately caused the pipeline rupture to CITGO, and reduced its recovery accordingly. In
    sum, appellants urge us to adopt a form of immunity or absolute statutory defense that heretofore has
    been recognized by neither the legislature nor Texas common law. We reject that invitation, and
    overrule appellants’ sixth issue.
    Negligence liability
    In their fourth issue, appellants contend that the jury’s apportionment of fault under
    the negligence findings was against the great weight and preponderance of the evidence and
    was manifestly unjust. As discussed, the jury apportioned responsibility 50 percent to C&S,
    30 percent to MasTec/Wilde, 10 percent to Bechtel, and 10 percent to CITGO. Appellants urge that
    “the great weight and preponderance of the evidence establishes that CITGO was at least 51% at
    fault,” a percentage that would bar CITGO from recovering in negligence. See Tex. Civ. Prac. &
    Rem. Code Ann. § 33.001 (West 2008).
    If a jury’s verdict is so against the great weight and preponderance of the evidence
    as to be manifestly unjust, we must reverse the judgment. See In re King’s Estate, 
    244 S.W.2d 660
    ,
    661 (Tex. 1951). In determining whether a finding was against the great weight and preponderance
    of the evidence, the court of appeals must consider and weigh all of the evidence, and can set
    aside a finding only if the evidence is so weak that it is clearly wrong and unjust. Dow Chem. 
    Co., 46 S.W.3d at 241
    . Appellants emphasize evidence that CITGO received one-call notifications
    regarding the ongoing Texas Loop Project excavation, that CITGO never located or marked the
    actual location of the CASA Pipeline, that Schulle placed and left in place stakes that
    created a misleading impression regarding the pipeline’s location, and that CITGO and not
    27
    appellants had access to the maps and other information from which the pipeline’s actual location
    could have been determined. Indeed, CITGO does not challenge the jury’s finding that its was
    contributorily negligent.
    However, the jury also heard evidence CITGO and Ferguson had an understanding
    that Ferguson’s crews would not excavate near the CASA Pipeline without prior notice to CITGO
    and CITGO’s representatives being present, a factor that the jury reasonably could have considered
    in drawing inferences from the acts or alleged omissions of CITGO personnel that appellants
    attack.11 There was also evidence that both Ferguson and Bechtel employees had been informed that
    CITGO had not yet located the pipeline’s precise location. Nonetheless, both the rip cat operator and
    his supervisor testified that they had not been informed the pipeline had not been located. The jury
    also heard evidence of a near-miss with another underground facility on May 6 that the jury could
    reasonably have concluded was caused by similar communication breakdowns between Ferguson
    and his crews. We cannot conclude that the jury’s failure to allocate at least 51 percent of fault to
    CITGO is against the great weight and preponderance of the evidence and is manifestly unjust. See
    Rosell v. Central W. Motor Stages, Inc., 
    89 S.W.3d 643
    , 659-60 (Tex. App.—Dallas 2002,
    pet. denied) (the determination of negligent parties’ proportionate responsibility is a matter within
    the jury’s sound discretion).
    11
    For example, Bentley testified that he did not believe it necessary to readjust the stakes
    after determining on May 6 that pipeline lay to the east of the middle stake because CITGO had been
    assured that no excavation would take place at the location without prior notice.
    28
    Negligence damages
    “Tulsa overhead”
    In their third issue, appellants attack the jury’s award of past negligence damages on
    the basis that there is legally and factually insufficient evidence to support the full amount of that
    award. At trial, CITGO presented spreadsheets, backup documentation, and testimony from a safety
    environmental manager, Kenny Holtgreve, indicating that CITGO had incurred a total of $1,159,194
    in expenses from the pipeline rupture and gasoline spill until date of trial. The jury ultimately
    awarded this entire amount as past negligence damages.
    CITGO’s calculations presented to the jury included roughly $80,000 it claimed in
    emergency response costs, $766,000 in remediation costs, $10,000 in lost product, and $15,000
    in payments to the adjoining landowner to gain access to the property.               The remaining
    amount—$287,780.76—was a figure intended to reflect the value of employee time, equipment,
    materials, and other overhead that CITGO had to divert from normal business operations
    when responding to the large gasoline spill.           It is only the latter component of past
    negligence damages—which the parties respectively term “project management expenses” or
    “Tulsa overhead”12—that appellants challenge.
    Holtgreve testified regarding the bases for CITGO’s claim for $287,780.76 in
    “Tulsa overhead.” He testified that CITGO incurred significant additional internal costs when
    having to divert employees and company resources from normal business operations to respond to
    the spill. Holtgreve, for example, observed that “[o]ne hundred percent of my time” was devoted
    12
    This is the term CITGO uses in its spreadsheet to identify this category of expenses.
    29
    to the project in the spill’s immediate aftermath. He added that “people in the operations area in
    the field,” such as “Sam Bentley and his people” were involved in the project, as well as
    “accounting people who would have to keep track of the invoices,” “administrative people who
    would get the invoices to process them,” and “other managers who would manage, oversee what we
    did.” As Holtgreve put it, “[i]f the person’s time is allocated to do this project instead of his normal
    job, this is time lost by Citgo. Therefore, that is money that Citgo has lost because of the event.”
    Holtgreve further noted that the work required increased use of CITGO telephones and other
    equipment. To reflect the value of these lost company resources, Holtgreve explained, CITGO
    imposed a percentage surcharge or mark-up in the same manner that it did when performing projects,
    such as relocating pipelines, for a third party.
    Holtgreve explained that on such projects, CITGO would ordinarily charge a
    management fee of 34 percent that “covers the staff type of functions, the accounting functions, the
    legal functions, the human resource functions, management functions that are not directly associated
    to Citgo, because Citgo works for Citgo and we are not in the business of doing projects for other
    companies.” Holtgreve opined that such fees were “a common practice in the industry.” To
    approximate the value of its employees’ time and overhead expended in the spill response and
    remediation, CITGO, essentially treating the gasoline spill as if it was a project being performed for
    a third party, multiplied those costs by 34 percent, yielding the $287,780.76 figure.
    Appellants argue that there is legally and factually insufficient evidence that CITGO
    incurred $287,780.76 in lost employee time and resources. They point out that CITGO did not
    attempt to quantify or prove the actual amount or value of its lost overhead even though Holtgreve
    30
    acknowledged that CITGO’s accounting department could have tracked those figures. As for the
    basis of the 34 percent mark-up, Holtgreve conceded that he had no personal knowledge regarding
    how that percentage figure had been derived, explaining only that “[i]t’s a number that [CITGO]
    had generated in the past based off of some study that [it] had done somewhere in the past” and
    “was associated with the projects when I started dealing with them.” CITGO did not elaborate
    further regarding the origins of the “Tulsa overhead.”
    CITGO responds that there was sufficient evidence that CITGO incurred substantial
    lost employee time and resources when responding to the pipeline rupture. It also suggests that
    appellants waived any complaint regarding the origins of the “Tulsa overhead” because they did not
    preserve objections to the admission of Holtgreve’s testimony or the submission of a broad-form
    question on negligence damages. Question 3 of the charge asked: “What sum of money, if paid not
    in cash, would fairly and reasonably compensate CITGO for the damages incurred in the past
    resulting from the rupture of the CASA Pipeline.” The jury was instructed to consider the reasonable
    costs in Caldwell County, Texas (1) “to restore the CASA Pipeline to the condition it was in
    immediately before the occurrence in question” and (2) “to respond to and remediate the spill,”
    including “reasonable and necessary clean-up costs and monitoring expenses.” Because Holtgreve’s
    testimony regarding lost employee time and the 34 percent mark-up was in evidence and the
    charge permitted the jury to consider it, CITGO reasons, appellants cannot now complain that
    the jury did so.
    In this regard, both parties emphasize that appellants objected to and obtained an
    instruction in the past promissory estoppel damages question, “Do not include Tulsa overhead.” In
    31
    response to appellants’ objection, the district court stated that it “didn’t hear any evidence” of “what
    the 34 percent was” or how this fee CITGO charged to third parties was probative of damages
    CITGO incurred in connection with the spill. However, appellants did not request a similar
    instruction in the otherwise-parallel question for past negligence damages. As it turned out, the jury,
    while awarding $1,159,194.75 in past negligence damages, awarded only $871,413.99 in past
    promissory estoppel damages—a difference of $287,780.76, corresponding precisely to the amount
    of “Tulsa overhead.”
    On this record, sufficient evidence would support the jury’s award of $1,159,194.75
    in past negligence damages only if there was sufficient evidence that CITGO incurred at least
    $287,780.76 in “Tulsa overhead.” The evidence supports no more than speculation as to that fact.
    Although Holtgreve did allude generally to “people in the operations area in the field,”
    “accounting people,” “administrative people,” and “other managers” having to devote all of their
    time to the project for some unspecified period after the accident, he provided no basis to quantify
    the value of that time, such as salaries and the like, other than the 34 percent mark-up that CITGO
    used on third-party projects. CITGO’s methodology in determining that percentage was never
    explained. Nor does CITGO refer us to any other evidence in the record from which the
    jury reasonably could have inferred that the company had incurred at least $287,780.76 in
    lost employee time or overhead in connection with the pipeline rupture. Consequently, the evidence
    is legally insufficient to support the jury’s award of the full amount of $1,159,194.75 in past
    negligence damages.
    32
    Appellants do not dispute, however, that legally and factually sufficient evidence
    supports the award of the other components of past negligence damages, which total $871,413.99.
    Where, as here, we conclude that there is insufficient evidence to support the full amount of a
    damages award but sufficient evidence to support a lesser award, we may suggest a remittitur
    See Spring Windows Fashions Div., Inc. v. The Blind Maker, 
    184 S.W.3d 840
    , 889-90
    (Tex. App.—Austin 2006, pet. granted, remanded by agr.); Tex. R. App. P. 46.3. The party
    prevailing in the trial court must be given the option of accepting the remittitur or having the case
    remanded for a new trial. Spring 
    Windows, 184 S.W.3d at 889-90
    . Accordingly, we will suggest
    a remittitur of $287,780.76, the difference between the jury’s award of $1,159,194.75 in past
    negligence damages and the amount of such damages that the evidence supports.
    Future damages
    In their second issue, appellants argue that CITGO cannot recover future damages
    because the testimony of CITGO’s damages expert, David Sweeten, was unreliable and should have
    been excluded.13 Appellants brought a pretrial motion to exclude Sweeten’s testimony as unreliable
    on grounds that there was no basis for an assumption that the “plume” of benzene and MTBE14
    contamination from the gasoline that had escaped the ruptured CASA Pipeline had extended into the
    surrounding area beyond Plum Creek, an area waterway. If Sweeten’s testimony had been properly
    excluded, appellants contend, there is no evidence of future damages.
    13
    Appellants asserted this challenge against the jury’s findings regarding both
    future negligence and future promissory estoppel damages. As to each, the jury awarded the
    sum of $668,250.00.
    14
    MTBE stands for methyl-tertiary-butyl-ether, a common additive to gasoline.
    33
    A trial court’s decision to admit or exclude expert testimony is reviewed for an abuse
    of discretion. Helena Chem. Co. v. Wilkins, 
    47 S.W.3d 486
    , 499 (Tex. 2001). “The test for abuse
    of discretion is whether the trial court acted without reference to any guiding rules or principles.”
    E.I. du Pont de Nemours & Co. v. Robinson, 
    923 S.W.2d 549
    , 558 (Tex. 1995). If a party opposes
    and objects to the admission of expert testimony, the proponent bears the burden of demonstrating
    its admissibility. 
    Robinson, 923 S.W.2d at 557
    .
    Expert testimony is admissible if (1) the expert is qualified, and (2) the testimony is
    relevant and based on a reliable foundation. 
    Wilkins, 47 S.W.3d at 499
    ; 
    Robinson, 923 S.W.2d at 556
    . Scientific testimony is unreliable if it is not grounded “in the methods and procedures of
    science,” and amounts to no more than a “subjective belief or unsupported speculation.” 
    Robinson, 923 S.W.2d at 557
    (quoting Daubert v. Merrell Dow Pharm., Inc., 
    509 U.S. 579
    , 590 (1993)).
    Expert testimony is also unreliable if “there is simply too great an analytical gap between the data
    and the opinion proffered.” Gammill v. Jack Williams Chevrolet, 
    972 S.W.2d 713
    , 727 (Tex. 1998)
    (quoting General Elec. Co. v. Joiner, 
    522 U.S. 136
    , 146 (1997)).
    Factors used by courts to determine whether expert testimony is reliable include:
    1.      the extent to which the theory has been or can be tested;
    2.      the extent to which the technique relies upon the subjective interpretation of
    the expert;
    3.      whether the theory has been subjected to peer review and/or publication;
    4.      the technique’s potential rate of error;
    5.      whether the underlying theory or technique has been generally accepted as
    valid by the relevant scientific community; and
    34
    6.      the non-judicial uses which have been made of the theory or technique.
    
    Robinson, 923 S.W.2d at 557
    . These factors are non-exclusive and flexible. 
    Id. Sweeten testified
    concerning two estimates of future clean-up costs that he had
    prepared. In his first estimate, which he had prepared in early 2004, Sweeten calculated total future
    costs as $668,250.00. In his second estimate, which he prepared in November 2004, Sweeten revised
    these calculations in light of intervening developments to yield at total of $1,270,000.00 in estimated
    future clean-up costs. The focus of appellants’ challenge is Sweeten’s assumption in his second cost
    estimate that contamination had extended from the rupture site beyond Plum Creek. Appellants
    attack this assumption in light of Sweeten’s admission that he had not completed a delineation of
    the plume beyond the creek.
    The jury ultimately awarded $668,250.00 in future damages under both CITGO’s
    negligence and promissory estoppel theories, an amount corresponding precisely to Sweeten’s
    first cost estimate. Consequently, if Sweeten’s testimony regarding his first cost estimate is relevant,
    is reliable, and was properly admitted, that evidence alone could support the jury’s future damages
    award. It is debatable whether appellants have preserved any complaint regarding this aspect of
    Sweeten’s testimony, as their challenge has been focused entirely on Sweeten’s assumptions
    underlying his second cost estimate. Nonetheless, even assuming that appellants preserved this
    challenge, we conclude that the district court did not abuse its discretion in admitting Sweeten’s
    testimony regarding his first cost estimate.
    Sweeten’s first cost estimate was based on an area on the spill side of Plum Creek,
    on which well testing had shown that MTBE and benzene were above acceptable TCEQ-approved
    35
    levels. The data retrieved from these temporary wells included points within a specific area between
    the release site and Plum Creek and exhibited levels of both MTBE and benzene that exceeded the
    TCEQ acceptable levels. These data points created a circular area of contamination from which
    Sweeten calculated the estimated clean-up costs. Applying his experience to these data points,
    Sweeten testified to future environmental clean-up costs totaling $668,250.00.
    According to the report prepared by Sweeten as well as his accompanying testimony,
    some of the factors he considered in arriving at the $668,250.00 estimate were:
    •       Groundwater monitoring and reporting: collecting semi-annual groundwater
    samples from the permanent monitoring wells, as required by TCEQ for the
    life of the clean-up project;
    •       Laboratory costs: costs incurred from submission of the gathered samples to
    a lab for analysis;
    •       Pilot testing, aquifer pump test, and remedial design: tests to determine
    methods of running short-scale or short-duration tests to determine the
    appropriate technology for interim corrective action, as required by TCEQ;
    •       Submission of APAR (Affected Property Assessment Report) or risk
    assessment: compilation of all collected data;
    •       Prepare response action plan (RAP): preparation of a report, as required by
    the TCEQ;
    •       Prepare site-specific discharge permit: costs incurred in obtaining a permit
    to pump the water out so that contaminated water does not reach Plum Creek;
    •       Remedial system design, capital equipment and construction: based on the
    data gathered, a report setting out the response action plan, including capital
    costs for equipment to be used; and
    •       General project management regulatory interface: managing the tasks and
    coordinating the people and equipment, including communications with
    TCEQ.
    36
    Sweeten testified that he then took the above line items and projected them out over the next
    few years, to the extent that they were ongoing events. Sweeten also testified that he had prepared
    similar cost estimates for CITGO on another pipeline project and on other projects for other clients
    and that, based on this experience, he was generally familiar with how much these clean-up
    procedures cost.
    Although there had not yet been a “complete delineation” such that CITGO did not
    yet know the “full extent” of the problem, some testing and delineation activities had been
    completed—notably, those in the area of the concentration circles on which Sweeten’s first cost
    estimate was based. Even assuming that appellants are correct in their assertion that there was no
    evidence how far the contamination extended, there was at least evidence that the area contained in
    the concentration circles—and the area on which Sweeten’s first cost estimate was based—was
    contaminated according to TCEQ standards. Contrary to appellants’ assertion, Sweeten agreed that
    he needed more information to determine a final remedial technology, not that he needed more
    information to create a reliable cost estimate as to the designated area. With the data points available
    to Sweeten, he was able to create a reliable initial cost estimate, which projected clean-up costs to
    be $668,250.00. Although the full extent of the contamination may have been unknown at the time,
    the figure of $668,250.00 was based on known, objective data points. We, therefore, conclude that,
    based on Sweeten’s experience and the known data points, his testimony with respect to the initial
    cost estimate was reliable, and the district court acted within its discretion in admitting it. See
    
    Gammill, 972 S.W.2d at 726
    (“Experience alone may provide a sufficient basis for an expert’s
    testimony”). Accordingly, we overrule appellants’ second issue.
    37
    Attorney’s fees
    In their remaining nine issues, appellants challenge the district court’s award of
    $295,357.25 in trial-level attorney’s fees and another $75,000 in conditional appellate attorney’s
    fees. This award was based on the jury’s favorable findings regarding CITGO’s promissory
    estoppel theory of recovery under 38.001(8) of the civil practice and remedies code, see
    Tex. Civ. Prac. & Rem. Code Ann. § 38.001(8) (West 2008) (authorizing attorney’s fees for claims
    for “an oral or written contract”), and the evidence that the district court heard regarding the amount
    of such fees. Appellants assert essentially four types of challenges to the attorney’s fee award.
    First, appellants bring a number of issues attacking CITGO’s right to recover under
    a promissory estoppel theory. Appellants argue that CITGO presented no evidence of any damages
    compensable under a promissory estoppel theory,15 that the evidence is legally and factually
    insufficient to support the jury’s finding that CITGO reasonably relied on any promise to its
    detriment,16 that CITGO’s “promissory estoppel” claim “sounded in tort,”17 and that CITGO’s
    recovery in negligence eliminates any “injustice” that would justify the application of the promissory
    estoppel doctrine.18    See, e.g., Trammel Crow Co. No. 60 v. William Jefferson Harkinson
    and Jeff Harkinson Investments, Inc., 
    944 S.W.2d 631
    , 636 (Tex. 1997) (promissory estoppel
    15
    Appellants’ thirteenth issue.
    16
    Issue twelve.
    17
    Issue nine. In fact, CITGO had sought submission of a negligent misrepresentation theory,
    to which appellants objected on the ground that it had not been pled. The district court refused the
    submission, and CITGO does not complain of that ruling on appeal.
    18
    Issue eleven.
    38
    “may apply . . . if injustice can be avoided only by enforcement of the promise”). Appellants also
    urge that the jury’s contributory negligence finding against CITGO bars its recovery under
    promissory estoppel as a matter of law19 and, relatedly, that the district court abused its discretion
    in refusing to submit an “unclean hands” instruction to the jury.20
    In the alternative, in their eighth issue, appellants argue that a promissory estoppel
    claim is not a claim for “an oral or written contract” that can support an award of attorney’s fees
    under section 38.001(8) of the civil practice and remedies code.21 In the further alternative, in their
    first issue, appellants urge that CITGO cannot “mix and match” recovery of actual damages based
    on its negligence theory and attorney’s fees under its promissory estoppel theory, but must be
    required to elect to recover under only one of the theories. See JHC Ventures, L.P. v. Fast Trucking,
    Inc., 
    94 S.W.3d 762
    , 774 (Tex. App.—San Antonio 2002, no pet.).22 Finally, in their fifteenth issue,
    19
    Issue ten.
    20
    Issue fourteen.
    21
    As appellants emphasize, Texas courts currently are split on that question.
    Compare Doctors Hosp. 1997, L.P. v. Sambuca Houston, L.P., 
    154 S.W.3d 634
    , 635-38
    (Tex. App.—Houston [14th Dist.] 2004, pet. abated) (holding that attorney’s fees are not recoverable
    under section 38.001(8) for a promissory estoppel claim because such claims presuppose no
    “oral or written contract”) (quoting Subaru of Am., Inc. v. David McDavid Nissan, Inc., 
    84 S.W.3d 212
    , 226 (Tex. 2002) (“promissory estoppel doctrine presumes no contract exists”)), with Preload
    Tech., Inc. v. A.B. & J. Constr. Co., 
    696 F.2d 1080
    , 1094-95 (5th Cir. 1983) (Texas law) (upholding
    award of attorney’s fees for promissory estoppel claim enforcing a promise that the court compared
    to an option contract). In unpublished opinions, this Court had upheld attorney’s fee awards on
    promissory estoppel claims. See Safe Env’t v. Pelzel & Assocs., Inc., No. 03-98-00721-CV, 1999
    Tex. App. LEXIS 7628 (Tex. App.—Austin 1999, no pet.) (mem. op.).
    22
    CITGO disputes this conclusion, but maintains that if it must elect between the two
    theories, it would recover against MasTec/Wilde and C&S under promissory estoppel (including
    attorney’s fees) and against Bechtel in negligence.
    39
    appellants complain that CITGO failed to segregate its attorney’s fees among valid and invalid
    grounds of recovery.
    We agree with appellants that CITGO cannot recover under a promissory estoppel
    theory because CITGO presented no evidence of the types of damages that are compensable under
    such a theory. As it has been recognized by the Texas Supreme Court, “[t]he function of the
    doctrine of promissory estoppel is . . . defensive in that it estops a promisor from denying the
    enforceability of the promise.”       See Wheeler v. White, 
    398 S.W.2d 93
    , 96 (Tex. 1965)
    (citing Restatement (Second) of Contracts § 90 (1981)); see also In re Weekley Homes, L.P.,
    
    180 S.W.3d 127
    , 133 (Tex. 2005) (“we have long recognized . . . the defensive theory of promissory
    estoppel.”). That is, promissory estoppel prevents a promisor who has induced substantial action
    or forebearance by another from denying that promise if “injustice can be avoided only by
    enforcement,” 
    id. (citing Harkinson,
    944 S.W.2d at 636), but “it does not create a contract right that
    does not otherwise exist,” Sun Oil Co. (Delaware) v. Madeley, 
    626 S.W.2d 726
    , 734 (Tex. 1981);
    see Hruska v. First State Bank of Deanville, 
    747 S.W.2d 783
    , 785 (Tex. 1988). Rather, it merely
    “prevents a party from insisting upon his strict legal rights”—i.e., the right to avoid his promise as
    not contractually binding—“when it would be unjust to allow him to enforce them.” In re Weekley
    Homes, 
    L.P., 180 S.W.3d at 133
    (quoting 
    Wheeler, 398 S.W.2d at 96
    ).
    Although promissory estoppel may be the basis for an affirmative claim, 
    Wheeler, 398 S.W.2d at 96
    , the supreme court has restricted the types of damages a promissory estoppel
    plaintiff can recover to “enforce” a promise: “the promisee is to be allowed to recover no more than
    reliance damages measured by the detriment sustained.” 
    Wheeler, 398 S.W.2d at 97
    . “Reliance
    40
    damages, similar to out-of-pocket recovery, reimburse one for expenditures made toward the
    execution of the contract in order to restore the status quo before the contract.” Hart v. Moore,
    
    952 S.W.2d 90
    , 97 (Tex. App.—Amarillo 1997, pet. denied); see Restatement (Second) of Contracts
    § 349 (reliance damages “includ[e] expenditures made in preparation for performance or in
    performance, less any loss that the party in breach can prove with reasonable certainty the injured
    party would have suffered had the contract been performed”); see also Quigley v. Bennett,
    
    227 S.W.3d 51
    , 56 (Brister, J., concurring and dissenting) (“reliance damages” for fraud
    “compensate for the plaintiff’s out-of-pocket expenditures”). In this way, reliance damages protect
    a promisee’s “reliance interest” in a contract or promise, or his interest in being reimbursed for loss
    caused by reliance on the promise by being put in as good a position as he would have been had the
    contract not been formed or promise relied upon. Restatement (Second) of Contracts §§ 344, 349;
    see 
    Quigley, 227 S.W.3d at 56
    (Brister, J., concurring and dissenting); O’Farrill Avila v. Gonzalez,
    
    974 S.W.2d 237
    , 247 (Tex. App.—San Antonio 1998, pet. denied).
    Reliance damages are distinguished from expectancy or “benefit-of-the-bargain”
    damages, which serve to protect the promisee’s “expectation interest,” or his interest in having
    the benefit of his bargain by being put in as good a position as he would have been had the
    contract or promise been performed. Restatement (Second) of Contracts § 344. Consequently,
    expectancy damages like lost profits, for example, are not recoverable based on promissory estoppel.
    See Sun Oil 
    Co., 626 S.W.2d at 734
    (“The damages recoverable by a party claiming estoppel are not
    measured by the profits that such party’s reliance led him to expect, but instead are limited to
    the amount necessary to compensate that party for a loss already suffered.”); Fretz Constr. Co.
    v. Southern Nat’l Bank of Houston, 
    626 S.W.2d 478
    , 483 (Tex. 1981) (“Damages recoverable in a
    41
    case of promissory estoppel are not the profit that the promisee expected, but only the amount
    necessary to restore him to the position he would have been in had he not acted in reliance on the
    promise.”). Similarly, consequential damages resulting from the failure to perform the promise are
    likewise not recoverable. 
    Id. The limitation
    of promissory estoppel damages solely to reliance
    damages, rather than compensating for the loss of the full benefit of the breached or unperformed
    contract or promise, reflects the view that “[s]ince the promisee in such cases is partly responsible
    for his failure to bind the promisor to a legally sufficient contract, it is reasonable to conclude that
    all that is required to achieve justice is to put the promisee in the position he would have been in had
    he not acted in reliance upon the promise.” 
    Wheeler, 398 S.W.2d at 97
    .
    As its promissory estoppel “reliance damages,” CITGO obtained jury awards for its
    damages resulting from the pipeline rupture. Question 10 asked the jury to determine the sum of
    money that “would fairly and reasonably compensate CITGO for the damages incurred in the past
    resulting from the detrimental reliance found in Question 9” (the promissory estoppel liability issue),
    including “the reasonable cost in Caldwell County, Texas to restore the CASA Pipeline to the
    condition it was in immediately before the occurrence” and “to respond to and remediate the spill.”
    With the exception of the “Tulsa overhead” instruction, previously discussed, Question 10
    paralleled the question on past negligence damages, and the jury awarded damages that differed
    only with respect to the “Tulsa overhead” amount. Similarly, Question 11 asked the jury to
    determine the sum of money that “would fairly and reasonably compensate CITGO for the
    damages which in reasonable probability will be incurred in the future resulting from the rupture of
    the CASA Pipeline found in Question 9.” The jury awarded identical future damages for both
    negligence and promissory estoppel.
    42
    CITGO did not present evidence of “reliance damages” apart from the damages it
    attributes to the pipeline rupture. In CITGO’s view, the pipeline rupture was “a direct result of its
    reliance on Clint Ferguson’s statement that Appellants’ crews would not be working near CITGO’s
    pipeline that day” because it “acted in reliance on Clint Ferguson’s promise and did not send out a
    representative to demand and supervise the uncovering of the pipeline prior to excavation.” In turn,
    it contends that “[t]he environmental damages found by the jury were a direct result of the line
    rupture from responding to the emergency, repairing the line, remediation of the soil, bioremediation
    of the groundwater, testing and monitoring, to future monitoring and remediation to remove the
    contamination.” We cannot agree that the damages from the pipeline rupture are reliance damages
    that CITGO can recover under its promissory estoppel theory.
    CITGO’s promissory estoppel damages theory is that it should recover its costs of
    repairing the pipeline and cleaning up the spill because (1) if Ferguson had kept his promise to give
    CITGO prior notice before it excavated near the CASA Pipeline, (2) CITGO would have sent a
    representative to the site, (3) who, in turn, would have located and uncovered the pipeline, and
    (4) ensured that any excavation on the site would not have ruptured the pipeline. CITGO’s damages
    are not reimbursement for any amounts it expended in reliance on the promises, but compensation
    for consequential losses CITGO claimed it incurred when appellants failed to perform their promises.
    Such damages are in the nature of expectancy damages: they place CITGO in the position it claims
    it would have been had the promises been kept. Such damages are not recoverable through
    promissory estoppel. See Sun Oil 
    Co., 626 S.W.2d at 734
    ; Fretz Constr. 
    Co., 626 S.W.2d at 483
    .
    Because there was no evidence that CITGO incurred reliance damages that can
    support recovery under its promissory estoppel theory, we sustain appellants’ thirteenth issue.
    43
    Consequently, the district court erred in awarding CITGO attorney’s fees. We do not reach and
    express no opinion regarding appellants’ other challenges to the attorney’s fees award.
    CONCLUSION
    We reverse the portion of the district court’s judgment awarding CITGO attorney’s
    fees on its promissory estoppel theory and render judgment that CITGO take nothing on that theory.
    As for CITGO’s negligence claim, we hold that the evidence is legally insufficient to support the
    jury’s award of $1,159,194.75 in past damages, but there is sufficient evidence that CITGO incurred
    $871,413.99 in such damages—a difference of $287,780.76. Accordingly, we suggest a remittitur
    in the amount of $287,780.76. See Tex. R. App. P. 46.3. If CITGO files a remittitur in this amount
    with the district clerk within thirty days of the date of this opinion and so notifies the Court, we will,
    having overruled appellants’ other issues challenging CITGO’s negligence recovery, reform the
    district court’s judgment to award $871,413.99 in past negligence damages and, as modified, affirm.
    If the sum is not remitted, the judgment will be reversed, and the cause will be remanded to the
    district court for a new trial on CITGO’s negligence claims.
    ____________________________________________
    Bob Pemberton, Justice
    Before Justices Pemberton, Waldrop and Smith;
    (Justice B.A. Smith Not Participating)
    Reversed and Rendered in part, and Conditionally Affirmed in part
    Filed: October 3, 2008
    44
    

Document Info

Docket Number: 03-05-00430-CV

Filed Date: 10/3/2008

Precedential Status: Precedential

Modified Date: 2/1/2016

Authorities (31)

Daubert v. Merrell Dow Pharmaceuticals, Inc. , 113 S. Ct. 2786 ( 1993 )

Taylor v. Firemen's & Policemen's Civil Service Commission , 24 Tex. Sup. Ct. J. 421 ( 1981 )

Preload Technology, Inc. v. A.B. & J. Construction Company, ... , 696 F.2d 1080 ( 1983 )

Harris County v. Smith , 46 Tex. Sup. Ct. J. 263 ( 2002 )

Texas Department of Transportation v. City of Sunset Valley , 47 Tex. Sup. Ct. J. 1252 ( 2004 )

General Electric Co. v. Joiner , 118 S. Ct. 512 ( 1997 )

In Re King's Estate , 150 Tex. 662 ( 1951 )

Claude Norman, Eloise Norman v. State Farm Fire & Casualty ... , 804 F.2d 1365 ( 1986 )

USA Waste Services of Houston, Inc. v. Strayhorn , 2004 Tex. App. LEXIS 2427 ( 2004 )

Lexington Insurance Co. v. Strayhorn , 50 Tex. Sup. Ct. J. 181 ( 2006 )

JHC Ventures, L.P. v. Fast Trucking, Inc. , 2002 Tex. App. LEXIS 8407 ( 2002 )

In Re Weekley Homes, L.P. , 49 Tex. Sup. Ct. J. 55 ( 2005 )

Spencer v. Eagle Star Insurance Co. of America , 37 Tex. Sup. Ct. J. 519 ( 1994 )

Romero v. KPH Consolidation, Inc. , 48 Tex. Sup. Ct. J. 752 ( 2005 )

Dow Chemical Co. v. Francis , 44 Tex. Sup. Ct. J. 664 ( 2001 )

Rosell v. Central West Motor Stages, Inc. , 89 S.W.3d 643 ( 2002 )

Wheeler v. White , 9 Tex. Sup. Ct. J. 105 ( 1965 )

Hart v. Moore , 952 S.W.2d 90 ( 1997 )

O'Farrill Avila v. Gonzalez , 974 S.W.2d 237 ( 1998 )

Hruska v. First State Bank of Deanville , 31 Tex. Sup. Ct. J. 292 ( 1988 )

View All Authorities »