Drexel Corporation v. Edgewood Development, Ltd , 2013 Tex. App. LEXIS 13784 ( 2013 )


Menu:
  • Affirmed and Opinion filed November 7, 2013.
    In The
    Fourteenth Court of Appeals
    NO. 14-13-00353-CV
    DREXEL CORPORATION, Appellant
    V.
    EDGEWOOD DEVELOPMENT, LTD, Appellee
    On Appeal from the 133rd District Court
    Harris County, Texas
    Trial Court Cause No. 2012-21997
    OPINION
    In this permissive interlocutory appeal, defendant Drexel Corporation argues
    that the trial court erred in denying its motion to dismiss the declaratory-judgment
    action against it for lack of subject-matter jurisdiction. Because plaintiff’s requests
    for declarations of contractual non-liability present a live controversy that is ripe
    for review, we affirm the trial court’s order.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    According to the pleadings in this case, Drexel Corporation brokered
    Edgewood Development, Ltd.’s purchase of an office building in 1995. The two
    companies disagreed about the payment due to Drexel, but resolved the dispute
    through a written contract in which Edgewood gave Drexel the rights to certain
    profits from the property and promised to pay Drexel a portion of the proceeds
    when the property is sold.      Approximately seventeen years later, Drexel sent
    Edgewood a demand letter in which it stated that the parties omitted to include in
    the contract a date by which the property would be sold and final payment made to
    Drexel. Drexel asserted that a reasonable time for the property’s sale had passed,
    and that a reasonable estimation of Drexel’s share of the proceeds from a
    hypothetical sale was $1.2 million. Drexel stated that if Edgewood did not pay
    $1.2 million within thirty days, Drexel would sue for “a declaratory judgment with
    respect to the missing term (i.e., the outside date for a sale of the Property), and a
    monetary judgment” for Drexel’s share of the sales proceeds, plus attorneys’ fees,
    costs, and interest.
    Edgewood did not wait for the thirty-day period mentioned in the demand
    letter to expire, but instead filed its own suit for declaratory judgment. Drexel
    moved to dismiss the suit for lack of subject-matter jurisdiction and argued that the
    controversy was not ripe. The trial court denied the motion to dismiss, but granted
    Drexel’s motion for a permissive appeal.            We likewise granted Drexel’s
    application for an interlocutory appeal.
    In the sole issue presented, Drexel challenges the trial court’s denial of its
    motion to dismiss the suit for lack of subject-matter jurisdiction.
    2
    II. STANDARD OF REVIEW
    The usual procedural vehicle used to challenge the sufficiency of the
    pleader’s jurisdictional allegations or the existence of jurisdictional facts is a plea
    to the jurisdiction. See Tex. Dep’t of Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 226–27 (Tex. 2004); Riner v. City of Hunters Creek, 
    403 S.W.3d 919
    , 921
    (Tex. App.—Houston [14th Dist.] 2012, no pet.). In substance, then, Drexel’s
    motion to dismiss was a plea to the jurisdiction. See Speer v. Stover, 
    685 S.W.2d 22
    , 23 (Tex. 1985) (per curiam).
    We review a trial court’s ruling on a plea to the jurisdiction de novo.
    
    Miranda, 133 S.W.3d at 226
    . In our review, we construe the pleadings liberally in
    favor of the pleader and look to the pleader’s intent to determine whether the facts
    alleged affirmatively demonstrate the trial court’s jurisdiction to hear the cause.
    See 
    id. If the
    pleadings affirmatively negate the existence of jurisdiction, then the
    trial court may grant the plea to the jurisdiction without allowing the plaintiffs an
    opportunity to amend. 
    Id. at 227.
    III. ANALYSIS
    Under the Uniform Declaratory Judgments Act (“the Act”), a person
    interested under a written contract or whose rights are affected by it “may have
    determined any question of construction or validity arising under the . . . contract.”
    TEX. CIV. PRAC. & REM. CODE ANN. § 37.004(a) (West 2008). “A contract may be
    construed either before or after there has been a breach,” 
    id. § 37.004(b),
    but the
    Act “gives the court no power to pass upon hypothetical or contingent situations,
    or determine questions not then essential to the decision of an actual controversy,
    although such questions may in the future require adjudication.” Firemen’s Ins.
    Co. of Newark, N.J. v. Burch, 
    442 S.W.2d 331
    , 333 (Tex. 1968), superseded by
    constitutional amendment on other grounds as stated in Farmers Tex. Cnty. Mut.
    3
    Ins. Co. v. Griffin, 
    955 S.W.2d 81
    (Tex. 1997) (per curiam) (sub. op.). Rather, an
    action for declaratory judgment is available “only where there is a ‘substantial
    controversy involving genuine conflict of tangible interests.’” City of Dallas v.
    VSC, LLC, 
    347 S.W.3d 231
    , 240 (Tex. 2011) (quoting Bonham State Bank v.
    Beadle, 
    907 S.W.2d 465
    , 467 (Tex. 1995) (internal quotations omitted)).            “A
    declaratory judgment is appropriate only if a justiciable controversy exists as to the
    rights and status of the parties and the controversy will be resolved by the
    declaration sought.” Bonham State 
    Bank, 907 S.W.2d at 467
    (citing Tex. Ass’n of
    Bus. v. Tex. Air Control Bd., 
    852 S.W.2d 440
    , 446 (Tex. 1993)).
    Here, there is such a justiciable controversy. Drexel has asserted that under
    the express and implied terms of the contract, Edgewood is obligated to pay it $1.2
    million. Drexel has demanded that Edgewood pay this amount, which it says is
    “now due and owing.” Edgewood, on the other hand, contends that Drexel’s
    interpretation contradicts the agreement’s unambiguous terms, and denies that it
    owes Drexel the payment demanded.          This is a live controversy that can be
    resolved by a judicial declaration of the parties’ rights and duties under the
    contract. See Stark v. Benckenstein, 
    156 S.W.3d 112
    , 117 (Tex. App.—Beaumont
    2004, pet. denied) (holding that the trial court had subject-matter jurisdiction over
    a request for declaration of non-liability under a release agreement); Mackie v.
    Guthrie, 
    78 S.W.3d 462
    , 467 (Tex. App.—Tyler 2001, pet. denied) (sub. op.)
    (holding that plaintiff had standing to maintain a declaratory-judgment action
    where plaintiff had received a demand letter from defendant and the declarations
    plaintiff sought would prevent defendant from recovering under the contract).
    Drexel argues that the trial court lacks subject-matter jurisdiction for two
    reasons. First, Drexel contends that the case is not ripe because Edgewood did not
    plead or prove that it would suffer any imminent injury or harm without the
    4
    judicial declaration it seeks. Second, Drexel asserts that Edgewood cannot use the
    Act to deprive the real plaintiff of the traditional right to choose the time and place
    of suit. We conclude that both arguments are without merit.
    A.     Edgewood pleaded and produced evidence of imminent harm.
    Ripeness is a component of subject-matter jurisdiction. Robinson v. Parker,
    
    353 S.W.3d 753
    , 755 (Tex. 2011). To evaluate ripeness, courts consider “whether,
    at the time a lawsuit is filed, the facts are sufficiently developed ‘so that an injury
    has occurred or is likely to occur, rather than being contingent or remote.’” Waco
    Indep. Sch. Dist. v. Gibson, 
    22 S.W.3d 849
    , 851–52 (Tex. 2000) (quoting
    Patterson v. Planned Parenthood of Hous. & Se. Tex., Inc., 
    971 S.W.2d 439
    , 442
    (Tex. 1998)). Although a claim need not be fully ripened at the time suit is filed,
    the facts still must be developed sufficiently for the court to determine that an
    injury has occurred or is likely to occur. 
    Robinson, 353 S.W.3d at 755
    . “[I]f a
    party cannot demonstrate a reasonable likelihood that the claim will soon ripen, the
    case must be dismissed.” 
    Id. (citing Perry
    v. Del Rio, 
    66 S.W.3d 239
    , 251 (Tex.
    2001)). The ripeness requirement applies even if the party is seeking only a
    declaratory judgment. 
    Riner, 403 S.W.3d at 922
    . See also Bonham State 
    Bank, 907 S.W.2d at 468
    (“A trial court has discretion to enter a declaratory judgment so
    long as it will serve a useful purpose or will terminate the controversy between the
    parties.”).1
    In the ripeness inquiry, “the threat of harm can constitute a concrete injury,
    but the threat must be ‘direct and immediate’ rather than conjectural, hypothetical,
    or remote. To show that such injuries are likely to occur, for example, parties must
    1
    Drexel contends that the trial court lacks subject-matter jurisdiction over the case, but
    does not contend that if the trial court has jurisdiction, it would be an abuse of discretion for the
    trial court to render declaratory judgment.
    5
    demonstrate that the harm is imminent, but has not yet impacted them.” 
    Gibson, 22 S.W.3d at 852
    & n.23 (quoting Abbott Labs. v. Gardner, 
    387 U.S. 136
    , 152, 
    87 S. Ct. 1507
    , 1517, 
    18 L. Ed. 2d 681
    (1967)).
    As Edgewood’s pleadings demonstrate, the harm at issue is the wrongful
    retention or wrongful payment of $1.2 million.                 Edgewood filed this suit in
    response to Drexel’s letter insisting that Edgewood owed it this amount and
    demanding payment within thirty days.2 At the time the lawsuit was filed, just
    eleven days remained before the expiration of that deadline, but the parties had
    conflicting understandings of their rights and duties under the contract.                      If
    Edgewood truly owed Drexel this amount but did not pay it, then Drexel would be
    harmed; if Edgewood paid the money as Drexel demanded but did not owe it, then
    Edgewood would be harmed.                  Declaratory judgment accordingly was the
    appropriate vehicle to resolve the controversy. See Aetna Life Ins. Co. of Hartford,
    Conn. v. Haworth, 
    300 U.S. 227
    , 242, 
    57 S. Ct. 461
    , 465, 
    81 L. Ed. 617
    (1937)
    (holding that where one party asserts a present right to payment under a contract
    and the other party denies it, the “dispute is manifestly susceptible of judicial
    determination. It calls, not for an advisory opinion upon a hypothetical basis, but
    for an adjudication of present right upon established facts.”);3 MBM Fin. Corp. v.
    Woodlands Operating Co., L.P., 
    292 S.W.3d 660
    , 670 (Tex. 2009) (“The Act was
    originally ‘intended as a speedy and effective remedy’ for settling disputes before
    substantial damages were incurred. It is ‘intended to provide a remedy that is
    2
    Both the demand letter and the contract were attached to Edgewood’s pleadings.
    3
    Although Haworth was decided under the federal declaratory-judgment act, the Texas
    Act must be ‘so interpreted and construed as to effectuate its general purpose to make uniform
    the law of those states that enact it and to harmonize, as far as possible, with federal laws and
    regulations on the subject of declaratory judgments and decrees.” Man Indus. (India), Ltd. v.
    Midcontinent Exp. Pipeline, LLC, 
    407 S.W.3d 342
    , 354 (Tex. App.—Houston [14th Dist.] 2013,
    pet. filed) (quoting TEX. CIV. PRAC. & REM. CODE ANN. § 37.002 (West 2008)).
    6
    simpler and less harsh than coercive relief, if it appears that a declaration might
    terminate the potential controversy.’” (footnotes omitted) (quoting Cobb v.
    Harrington, 
    144 Tex. 360
    , 368, 
    190 S.W.2d 709
    , 713 (1945) and RESTATEMENT
    (SECOND) OF JUDGMENTS § 33 cmt. c (1982))).
    Drexel argues that harm is not imminent because it never filed a
    counterclaim and has indicated that it is not interested in pursuing the dispute at
    this time. In effect, Drexel argues that because it has not followed through on its
    demand, the issue is now moot. Drexel had the burden of proof on this point and
    failed to satisfy its burden. See Already, LLC v. Nike, Inc., 
    133 S. Ct. 721
    , 727,
    
    184 L. Ed. 2d 553
    (2013) (explaining that under the voluntary-cessation doctrine,
    the party who contends that its failure to pursue the claim renders the case moot
    bears the “formidable burden” to establish that it “could not reasonably be
    expected to resume” the same conduct). Drexel has retained an “unfettered ability”
    to insist that Edgewood make payments that Edgewood denies it owes. Cf. 
    id. The case
    is not moot because there is still a live controversy and the trial court’s
    judgment on the merits can still affect the parties’ rights or interests. Cf. Heckman
    v. Williamson County, 
    369 S.W.3d 137
    , 162 (Tex. 2012) (describing the conditions
    that render a case moot); Robinson v. Alief Indep. Sch. Dist., 
    298 S.W.3d 321
    , 325
    (Tex. App.—Houston [14th Dist.] 2009, pet. denied) (same).
    B.    The argument that the Act should not be used “to deprive the real
    plaintiff of the traditional right to choose the time and place of suit”
    does not apply to a plaintiff’s request for a declaration of contractual
    non-liability.
    Drexel’s remaining argument is inapplicable to a plaintiff suing for
    declaration of non-liability under a contract. In Abor v. Black, the Texas Supreme
    Court held that under the Act, a trial court has “jurisdiction over declarations of
    non-liability of a potential defendant in a tort action,” but that “the trial court
    7
    should have declined to exercise such jurisdiction because it deprived the real
    plaintiff of the traditional right to choose the time and place of suit.” 
    695 S.W.2d 564
    , 566 (Tex. 1985) (orig. proceeding) (emphasis added). This is so because, as
    our sister court has explained, “only a plaintiff may seek redress for a tort. But in a
    contract case, either party may breach the agreement and either party may sue for a
    breach or a judicial determination of rights under the contract.” Hartman v. Sirgo
    Operating, Inc., 
    863 S.W.2d 764
    , 767 (Tex. App.—El Paso 1993, writ denied).
    Thus, the rule announced in Abor does not apply to a suit in which the plaintiff
    seeks a declaration of non-liability under a contract. See, e.g., MBM Fin. 
    Corp., 292 S.W.3d at 668
    (“Extending the bar against declarations of non-liability from
    tort to contract cases would drastically handicap declaratory-judgment practice in
    Texas.”); Transp. Ins. Co. v. WH Cleaners, Inc., 
    372 S.W.3d 223
    , 231 (Tex.
    App.—Dallas 2012, no pet.) (“Under the Texas Act, either party may seek
    declaratory relief if there is a question regarding rights, status, or other legal
    relations arising under a written contract.”); Beard v. Endeavor Natural Gas, L.P.,
    No. 01-08-00180-CV, 
    2008 WL 5392026
    , at *5 (Tex. App.—Houston [1st Dist.]
    Dec. 19, 2008, pet. denied) (mem. op.) (rejecting argument that “preemptive” suit
    for declaration of non-liability under a contract is an improper use of the Act);
    Trinity Universal Ins. Co. v. Sweatt, 
    978 S.W.2d 267
    , 271 (Tex. App.—Fort Worth
    1998, no pet.) (declining to extend the rule announced in Abor to contract actions
    and noting that “[c]onstruction and validity of contracts are the most obvious and
    common uses of the declaratory[-]judgment action”). See also 
    Haworth, 300 U.S. at 244
    , 57 S. Ct. at 465, 
    81 L. Ed. 617
    (“[T]he character of the controversy and of
    the issue to be determined is essentially the same whether it is presented by [either
    party to the contract]. . . . It is the nature of the controversy, not the method of its
    presentation or the particular party who presents it, that is determinative.”).
    8
    In making the contrary argument, Drexel relies on a case in which a plaintiff
    who asserted both contract and tort claims moved to nonsuit a case after the
    defendant asserted a counterclaim for declaratory judgment. See In re Hanby, No.
    14-09-00896-CV, 
    2010 WL 1492863
    (Tex. App.—Houston [14th Dist.] Apr. 15,
    2010, orig. proceeding) (per curiam) (sub. mem. op.). The case is distinguishable.
    In Hanby, we did not address questions of justiciability, ripeness, or even the
    prevention of forum-shopping in contract cases as Drexel seems to argue. We
    instead addressed the narrower question of whether a defendant’s request for a
    purely defensive declaratory judgment on contract issues could prevent a plaintiff
    who had asserted both contract and tort claims from taking a non-suit of the entire
    case. See id., 
    2010 WL 1492863
    , at *1–3. In so doing, we followed the Texas
    Supreme Court’s opinion in BHP Petroleum Co. v. Millard, 
    800 S.W.2d 838
    , 840
    (Tex. 1990) (orig. proceeding).      Under BHP Petroleum, a counterclaim for
    declaratory relief that simply raises defenses to the claims pleaded by the plaintiff
    does not impair the plaintiff’s right to a nonsuit, whereas a counterclaim that
    requests affirmative relief—that is, one that goes beyond a defense to the claims
    raised in the plaintiff’s live pleading—survives a nonsuit of the plaintiff’s claim.
    See 
    id. at 841
    & n.8 However, in certain instances a “defensive” declaratory
    judgment will survive a nonsuit when there are continuing obligations between the
    parties. See 
    id. In Hanby,
    we concluded that the counterclaim did not seek a
    declaration concerning an ongoing obligation. Hanby, 
    2010 WL 1492863
    , at *3.
    Here, however, Edgewood has an ongoing obligation to pay Drexel upon the sale
    of the building; the issue in controversy is whether Edgewood must sell the
    building at a particular time or must pay Drexel a portion of some hypothetical
    sales proceeds if it fails to sell the building within that time. Hanby therefore does
    not control.
    9
    We accordingly overrule the sole issue presented for our review.
    IV. CONCLUSION
    Because the trial court did not err in denying Drexel’s motion to dismiss
    Edgewood’s suit for lack of subject-matter jurisdiction, we affirm the trial court’s
    order.
    /s/     Tracy Christopher
    Justice
    Panel consists of Justices Christopher, Donovan, and Brown.
    10
    

Document Info

Docket Number: 14-13-00353-CV

Citation Numbers: 417 S.W.3d 672, 2013 Tex. App. LEXIS 13784, 2013 WL 5947007

Judges: Christopher, Donovan, Brown

Filed Date: 11/7/2013

Precedential Status: Precedential

Modified Date: 11/14/2024

Authorities (19)

Stark v. Benckenstein , 2004 Tex. App. LEXIS 11842 ( 2004 )

Bonham State Bank v. Beadle , 38 Tex. Sup. Ct. J. 768 ( 1995 )

Patterson v. Planned Parenthood of Houston and Southeast ... , 41 Tex. Sup. Ct. J. 1001 ( 1998 )

Abor v. Black , 28 Tex. Sup. Ct. J. 581 ( 1985 )

Robinson v. Alief Independent School District , 2009 Tex. App. LEXIS 6621 ( 2009 )

MacKie v. Guthrie , 78 S.W.3d 462 ( 2002 )

Texas Ass'n of Business v. Texas Air Control Board , 852 S.W.2d 440 ( 1993 )

Texas Department of Parks & Wildlife v. Miranda , 47 Tex. Sup. Ct. J. 386 ( 2004 )

Aetna Life Insurance v. Haworth , 57 S. Ct. 461 ( 1937 )

Trinity Universal Insurance v. Sweatt , 1998 Tex. App. LEXIS 6741 ( 1998 )

Firemen's Ins. Co. of Newark, New Jersey v. Burch , 12 Tex. Sup. Ct. J. 49 ( 1968 )

Speer v. Stover , 28 Tex. Sup. Ct. J. 235 ( 1985 )

Abbott Laboratories v. Gardner , 87 S. Ct. 1507 ( 1967 )

Already, LLC v. Nike, Inc. , 133 S. Ct. 721 ( 2013 )

MBM Financial Corp. v. Woodlands Operating Co. , 52 Tex. Sup. Ct. J. 1221 ( 2009 )

City of Dallas v. VSC, LLC , 54 Tex. Sup. Ct. J. 1319 ( 2011 )

Hartman v. Sirgo Operating, Inc. , 863 S.W.2d 764 ( 1993 )

Cobb v. Harrington , 144 Tex. 360 ( 1945 )

Farmers Texas County Mutual Insurance v. Griffin , 1997 Tex. LEXIS 116 ( 1997 )

View All Authorities »