Reytec Construction Resources, Inc. v. Baptist Hospitals of Southeast Texas ( 2016 )


Menu:
  •                                      In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    _________________
    NO. 09-15-00085-CV
    _________________
    REYTEC CONSTRUCTION RESOURCES, INC., Appellant
    V.
    BAPTIST HOSPITALS OF SOUTHEAST TEXAS, Appellee
    ________________________________________________________________________
    On Appeal from the 60th District Court
    Jefferson County, Texas
    Trial Cause No. B-193,365
    ________________________________________________________________________
    MEMORANDUM OPINION
    Reytec Construction Resources, Inc. (“Reytec”) appeals the trial court’s
    amended final judgment granting summary judgment in favor of Baptist Hospitals
    of Southeast Texas (the “Hospital”). Reytec presents four issues on appeal.
    Because we conclude that Reytec raised a genuine issue of material fact precluding
    summary judgment on the Hospital’s breach of contract claim, we reverse the trial
    court’s judgment and remand this cause for further proceedings.
    1
    I. Background
    Reytec is in the underground utility and road-construction business. The City
    of Beaumont hired Reytec to perform a road-construction project, which entailed
    excavation, removal, and replacement of an old roadway and everything beneath
    the roadway, including the storm drainage system and waterlines. In connection
    with this project, Reytec entered into a Lease Agreement (the “Lease”) with the
    Hospital, whereby Reytec leased property (the “Property”) from the Hospital that
    was located near Reytec’s construction site to serve as a location for it to store its
    construction equipment. The Lease provided that Reytec could use the Property
    “solely for the purpose of a construction equipment storage and material laydown
    yard.” Relevant to the issues on appeal, Paragraph 12 of the Lease provides:
    “SURRENDER OF PREMISES. Upon the expiration of the term hereof, Tenant
    shall surrender the Premises in as good a state and condition as they were at the
    commencement of this Lease Agreement, reasonable use and wear and tear thereof
    and damages by the elements excepted.” The Lease was executed by David
    Parmer, the CEO of the Hospital and by Greg Reyes, Reytec’s owner and
    President.
    In connection with the road-construction project, Reytec also required a
    place to deposit the materials it excavated, including concrete, dirt, and other
    2
    materials. During a preconstruction meeting with the Hospital, Reytec’s project
    manager and general superintendent, Thomas Gill, asked the Hospital if it wanted
    the dirt from the excavation of the road. At first the Hospital declined Gill’s offer,
    but later, Jessie Deville, the Administrative Director of Facilities for the Hospital,
    informed Gill that the Hospital did want the dirt to use in a future Hospital project.
    On March 22, 2010, Reytec and the Hospital entered into a “Dump Contract[.]”The
    relevant portion of the Dump Contract provides:
    I acknowledge by my signature below that I accept delivery,
    possession, and responsibility for excavated material as is delivered to
    [the Property] by [Reytec] for the sum of $00.00 per load for a total of
    $00.00. I further acknowledge that [Reytec] is only obligated to stock-
    pile material to allow for it to be mowed. Any surveying of property
    or land permits are the responsibility of the owner or representative of
    property where excavated material is to be delivered.
    Deville signed the Dump Contract in his official capacity as the Hospital’s
    Administrative Director of Facilities.
    There is evidence in the record to support that the Hospital gave Reytec
    access to the Property to start delivering excavated materials shortly after the
    Hospital entered into the Dump Contract with Reytec. But, approximately ten
    months later, on January 20, 2011, Deville asked Gill to remove the excavated
    materials from the Property. At that time, Gill reminded Deville that under the
    Dump Contract the excavated materials were the Hospital’s responsibility but gave
    3
    Deville an estimate on what Reytec would charge the Hospital to remove the
    materials.
    The Lease term was scheduled to end February 28, 2011. The Hospital
    decided not to renew the Lease but agreed to a short lease extension to allow
    Reytec time to procure a new property. After securing a new property to serve as
    its laydown yard, Reytec began removing its construction equipment from the
    Property. On March 7, 2011, the Hospital’s attorney sent Reytec a letter
    threatening to “take immediate steps to have [Reytec] evicted” unless Reytec
    removed its equipment and the excavated materials from the Property. Reytec
    eventually removed all of its equipment but did not remove the excavated
    materials. After Reytec left the Property, Deville obtained quotes from two other
    companies to have the excavated materials removed. The Hospital secured the
    services of AAA Floodmasters and paid $100,000 to remove the excavated
    materials from the Property.
    On October 17, 2012, the Hospital filed suit against Reytec, asserting claims
    for breach of contract based on the Lease. The Hospital amended its petition and
    asserted additional claims for breach of the Lease and also asserted an alternative
    claim for breach of contract based on the Dump Contract. The Hospital sought to
    recover the cost of removing the excavated materials from the Property, restoring
    4
    the Property to its pre-Lease condition, and claimed damages for diminished
    market value of the Property and the “loss of potential sale(s) of the [Property.]”
    The Hospital further sought attorney’s fees and its alleged costs associated with
    evicting Reytec from the Property.
    Reytec filed a general denial of the Hospital’s allegations and asserted
    various affirmative defenses. Relevant to the issues on appeal, Reytec alleged that
    (1) the Hospital waived its right to assert its claims regarding the excavated
    materials through execution of the Dump Contract, (2) the Hospital released
    Reytec from all obligations or responsibilities concerning the excavated materials,
    and (3) the Dump Contract served as a modification of the Lease thereby relieving
    Reytec of any obligations and duties under the Lease regarding the excavated
    materials.
    On November 14, 2014, the Hospital filed a second amended traditional and
    no-evidence motion for summary judgment. Therein, the Hospital sought summary
    judgment on its claims for breach of the Lease, breach of the Dump Contract, and
    Reytec’s affirmative defenses. On December 15, 2014, the trial court granted the
    Hospital’s motions for summary judgment in their entirety, and awarded the
    Hospital $100,000 in actual damages. The trial court also generally awarded the
    Hospital reasonable and necessary costs and attorney’s fees and pre-and post-
    5
    judgment interest. On February 19, 2015, the trial court amended its final judgment
    to include an award of $94,582.85 in attorney’s fees, $3,590.64 in taxable costs,
    and $10,833.33 in pre-judgment interest. The trial court also awarded the Hospital
    conditional appellate attorney’s fees, costs, and interest. Reytec appealed the trial
    court’s judgment.
    II. Standard of Review
    We review a trial court’s grant of a motion for summary judgment de novo.
    Buck v. Palmer, 
    381 S.W.3d 525
    , 527 (Tex. 2012); Travelers Ins. Co. v. Joachim,
    
    315 S.W.3d 860
    , 862 (Tex. 2010). A no-evidence motion for summary judgment
    under Rule 166a(i) must challenge at least one specific element of the opponent’s
    claim or defense on which the opponent will have the burden of proof at trial. Tex.
    R. Civ. P. 166a(i). The opponent must then present summary judgment evidence
    raising a genuine issue of material fact to support the challenged elements. 
    Id. “The court
    must grant the motion unless the respondent produces summary judgment
    evidence raising a genuine issue of material fact” on the challenged elements. 
    Id. A genuine
    issue of material fact is raised when the nonmovant produces more than a
    scintilla of evidence establishing the existence of the challenged element. Fort
    Worth Osteopathic Hosp., Inc. v. Reese, 
    148 S.W.3d 94
    , 99 (Tex. 2004).
    6
    To prevail on a traditional motion for summary judgment, a movant must
    prove that there is no genuine issue regarding any material fact and that it is
    entitled to judgment as a matter of law. Tex. R. Civ. P. 166a(c); Little v. Tex. Dep’t
    of Criminal Justice, 
    148 S.W.3d 374
    , 381 (Tex. 2004). A matter is conclusively
    established if reasonable people could not differ as to the conclusion to be drawn
    from the evidence. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 816 (Tex. 2005).
    When a party moves for summary judgment on a claim for which it bears the
    burden of proof, the party must show it is entitled to prevail on each element of its
    cause of action. See Parker v. Dodge, 
    98 S.W.3d 297
    , 299 (Tex. App.—Houston
    [1st Dist.] 2003, no pet.). The party meets this burden if it produces evidence that
    would be sufficient to support an instructed verdict at trial. 
    Id. If the
    movant satisfies this burden, then the burden shifts to the nonmovant
    to raise a genuine issue of material fact precluding summary judgment. Centeq
    Realty, Inc. v. Siegler, 
    899 S.W.2d 195
    , 197 (Tex. 1995). To defeat a motion for
    summary judgment by raising an affirmative defense, the nonmovant must do more
    than just plead the affirmative defense. Lunsford Consulting Grp., Inc. v. Crescent
    Real Estate Funding VIII, L.P., 
    77 S.W.3d 473
    , 475 (Tex. App.—Houston [1st
    Dist.] 2002, no pet.). The nonmovant must come forward with evidence sufficient
    to raise a fact issue on each element of its affirmative defense. Brownlee v.
    7
    Brownlee, 
    665 S.W.2d 111
    , 112 (Tex. 1984); Anglo-Dutch Petrol. Int’l, Inc. v.
    Haskell, 
    193 S.W.3d 87
    , 95 (Tex. App.—Houston [1st Dist.] 2006, pet. denied).
    In reviewing both a traditional and no-evidence summary judgment, we
    consider the evidence in the light most favorable to the nonmovant. See Mann
    Frankfort Stein & Lipp Advisors, Inc. v. Fielding, 
    289 S.W.3d 844
    , 848 (Tex.
    2009); Smith v. O’Donnell, 
    288 S.W.3d 417
    , 424 (Tex. 2009). We credit evidence
    favorable to the nonmovant if a reasonable fact finder could, and we disregard
    contrary evidence unless a reasonable fact finder could not. See Mann 
    Frankfort, 289 S.W.3d at 848
    .
    Generally, when the trial court does not specify the grounds for its ruling, as
    is the case here, we will affirm the summary judgment if any of the theories
    advanced by the motion are meritorious. See State v. Ninety Thousand Two
    Hundred Thirty-Five Dollars & No Cents in U.S. Currency, 
    390 S.W.3d 289
    , 292
    (Tex. 2013); Provident Life & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 216
    (Tex. 2003). The Hospital advanced numerous grounds in its motions for summary
    judgment; however, the Hospital abandoned all but one of those grounds on
    appeal. In its brief, the Hospital argues: “[S]ummary judgment was proper, strictly
    based upon its claim of Reytec’s breach of section 12 of the Lease. In this appeal[,]
    8
    the Hospital does not claim that the summary judgment was based upon any other
    ground set forth in its Motions.” The Hospital further argues:
    Reytec devotes about one-half of its Brief to its defense of the
    Hospital’s claims in its motions for summary judgment for: (1)
    breaches of the Lease Agreement other than Reytec’s failure to return
    the premises to their pre-lease condition . . . and (2) breaches of the
    Dump [C]ontract . . . . The Hospital will not respond to those points
    because of its contention that the summary judgment was absolutely
    correct in sustaining the Hospital’s claim of breach of the Lease by
    reason of Reytec’s failure to return the premises to its pre-lease
    condition.
    Because the Hospital has abandoned these grounds on appeal, we do not address
    them or Reytec’s responses thereto in this appeal. See State Farm Fire & Cas. Co.
    v. S.S., 
    858 S.W.2d 374
    , 384 n.2 (Tex. 1993) (Gonzalez, J., dissenting) (stating that
    “if a [ground] was abandoned or otherwise withdrawn, it would be improper for
    the appellate court to render judgment upon it”); Wojcik v. Wesolick, 
    97 S.W.3d 335
    , 336–37 (Tex. App.—Houston [14th Dist.] 2003, no pet.) (holding that the
    court of appeals would not address summary judgment ground abandoned on
    appeal); Martin v. Martin, Martin & Richards, Inc., 
    991 S.W.2d 1
    , 4 n.1 (Tex.
    App.—Fort Worth 1997) (noting that appellees abandoned summary judgment
    ground of collateral estoppel by stating in their appellate brief that “they do not
    rely upon that doctrine”), rev’d on other grounds, 
    989 S.W.2d 357
    (Tex. 1998).
    9
    III. Breach of Contract
    To prevail on a breach of contract claim, a plaintiff must prove (1) the
    existence of a valid contract; (2) the plaintiff’s performance or tender of
    performance; (3) the defendant’s breach; and (4) the plaintiff’s damages resulting
    from the breach. See Bank of Tex. v. VR Elec., Inc., 
    276 S.W.3d 671
    , 677 (Tex.
    App.—Houston [1st Dist.] 2008, pet. denied); Sullivan v. Smith, 
    110 S.W.3d 545
    ,
    546 (Tex. App.—Beaumont 2003, no pet.). “A breach of contract occurs when a
    party fails to perform an act that it has expressly or impliedly promised to
    perform.” Case Corp. v. Hi-Class Bus. Sys. of Am., Inc., 
    184 S.W.3d 760
    , 769–70
    (Tex. App.—Dallas 2005, pet. denied).
    The Hospital contends that it conclusively established its claim that Reytec
    breached Paragraph 12 of the Lease when Reytec “admitted failure to ‘surrender
    the Premises in as good a state and condition as they were at the commencement of
    this Lease Agreement, reasonable wear and tear thereof and damages by the
    elements except.” Reytec does not dispute that it left the excavated materials on the
    Property at the end of the Lease. Rather, Reytec contends that it was no longer
    obligated under the Lease or was otherwise excused from removing the excavated
    materials because the parties had entered into the Dump Contract, which altered
    10
    Reytec’s obligations under the Lease. Thus, the real point of contention between
    the parties is how, if at all, the Dump Contract affects the terms of the Lease.
    According to the Hospital, the Dump Contract did not modify the Lease, but
    rather the Dump Contract was abrogated by Paragraph 24 of the Lease. Paragraph
    24 provides that the Lease “contains the entire agreement between the parties” and
    that it can only be modified “through a written amendment signed by all of the
    parties hereto.” The Hospital contends that the Dump Contract could not have
    modified the Lease because it was entered into before the Lease was formally
    executed by the parties. The Hospital argues that instead, the Dump Contract
    “merged into the [Lease] and was of no further force and effect when the [Lease]
    was signed.”
    According to Reytec, the Dump Contract relieved Reytec of the obligation to
    remove the excavated materials from the Property by modifying the terms of the
    Lease, and that by entering into the Dump Contract, the Hospital waived its right to
    complain about the excavated materials and released Reytec of any obligations
    regarding the materials left on the Property. Reytec argues that the trial court erred
    in granting summary judgment because there remain material fact issues regarding
    its affirmative defenses of modification, release, and waiver. Reytec contends that
    the Dump Contract modified the Lease by expressly allowing Reytec to stockpile
    11
    excavated materials on the Property during the Lease term and in relieving Reytec
    of any obligation to remove the materials at the end of the Lease. To properly
    analyze this dispute, we must first examine the terms of the Lease and the Dump
    Contract. Then, we must consider all of the summary judgment evidence in a light
    most favorable to the nonmovant Reytec to determine whether there is a genuine
    issue of material fact regarding the parties’ intent to modify or otherwise alter their
    respective obligations under the Lease.
    A. Contract Interpretation
    Our primary concern in construing a lease contract is to ascertain the true
    intent of the parties. See Italian Cowboy Partners, Ltd. v. Prudential Ins. Co. of
    Am., 
    341 S.W.3d 323
    , 333 (Tex. 2011). In so doing, “‘we must examine and
    consider the entire writing in an effort to harmonize and give effect to all the
    provisions of the contract so that none will be rendered meaningless.’” 
    Id. (quoting J.M.
    Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex. 2003)). To understand
    the parties’ intent, we must examine the agreement as a whole in light of the
    circumstances present at the time when the parties entered into the agreement.
    Anglo-Dutch Petroleum Int’l, Inc. v. Greenberg Peden, P.C., 
    352 S.W.3d 445
    ,
    449–51 (Tex. 2011). “Facts and circumstances that may be considered include the
    commercial or other setting in which the contract was negotiated and other
    12
    objectively determinable factors that give context to the parties’ transaction.”
    Americo Life, Inc. v. Myer, 
    440 S.W.3d 18
    , 22 (Tex. 2014). The parol-evidence
    rule does not prohibit considering surrounding “facts and circumstances that
    inform the contract text and render it capable of only one meaning.” 
    Id. No single
    provision taken alone should control—instead, we must consider all provisions
    with reference to the entire agreement. J.M. 
    Davidson, 128 S.W.3d at 229
    . We also
    consider the particular business activity to be served, and when possible and
    proper, we avoid a construction that is unreasonable, inequitable, and oppressive.
    Frost Nat’l Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 312 (Tex. 2005)
    (quoting Reilly v. Rangers Mgmt., Inc., 
    727 S.W.2d 527
    , 530 (Tex. 1987)). We
    begin our analysis with the Lease’s express language. See Italian 
    Cowboy, 341 S.W.3d at 333
    .
    The   opening    statement   of   the   Lease   provides,   “THIS   LEASE
    AGREEMENT . . . made and entered into this ______________ day of
    _______________, 2010, by and between . . . .” The parties never filled in the
    blanks to reflect the date in which the Lease was “entered into[.]” The plain
    language of the Lease reflects that it is for a term of one year—to begin February
    28, 2010 and terminate February 28, 2011. The Lease specifies that it “shall
    commence on February 28, 2010” and then defines the term “Commencement
    13
    Date” as used in the Lease to mean “February 28, 2010.” The Lease provides that
    rather than making rent payments to the Hospital, Reytec would “furnish all labor,
    materials, supplies, tools, equipment, supervision, utilities and all else necessary”
    to construct a sidewalk for the Hospital. According to the terms of the Lease,
    Reytec would complete this work by May 3, 2010. The Lease was executed by
    both parties; however, the execution paragraphs of the Lease are not dated.
    Our review of the Lease reflects that it does not provide that the
    commencement date is determined or otherwise affected by the date the Lease was
    actually executed by the parties. The Lease uses the commencement date as the
    relevant date for the parties’ obligation in Paragraph 12, which specifies that
    Reytec is to return “the Premises in as good a state and condition as they were at
    the commencement of this Lease[.]”
    The summary judgment record includes the deposition transcripts of Thomas
    Gill and Thomas “Rusty” Pena. As explained above, Gill was Reytec’s project
    manager and general superintendent for the road-construction project. Pena is
    Reytec’s Vice President. Neither Pena nor Gill could testify as to when the Lease
    was formally executed by the parties. In response to requests for admission, Reytec
    responded that it could not admit or deny the date the lease was signed because it
    did not have sufficient information or knowledge to do so truthfully.
    14
    There is evidence in the record that the Lease was not formally executed by
    the Hospital until May 4, 2010. Jessie Deville, whose deposition transcript is also
    included in the summary judgment record, testified that the Hospital’s CEO,
    Parmer, is in charge of executing contracts on behalf of the Hospital. It is
    undisputed that Parmer executed the Lease on behalf of the Hospital. The Lease
    was initialed by Bryan Chandler, another employee with the Hospital that helped
    negotiate the Lease. Deville testified that he did not know the specific date that the
    Lease was signed by Parmer or Chandler. However, Deville explained that the
    Hospital has a formal contract procedure in place, which culminates with the
    CEO’s signature. He testified that a contract is required to have approval from a
    senior manager, the CFO, and the CEO. The Hospital produced its “Contract
    Approval Form” for the lease agreement between the Hospital and Reytec. The
    form is blank where it requests the “Initial Review Date[.]” The form states that the
    “Effective Date” is “2-28-10” and is for a term of twelve months to end “2-28-
    11[.]” The form has a place for various people in management to sign and date
    acknowledging their review and approval of the contract at issue. The form was
    signed by the Senior Manager of Department Review on April 9, 2010, and by the
    CEO on May 4, 2010. The form was also signed by the CFO, but there is no date
    for his signature. The Hospital also produced a form from its Risk Management
    15
    Department wherein the Vice President of Business Development signed on April
    9, 2010 indicating he had reviewed the Lease. The Hospital’s general counsel also
    signed a form on April 15, 2010, indicating he had reviewed the Lease. The form
    signed by the Hospital’s general counsel reflects that the effective date of the lease
    is “2-28-10[.]” Therefore, even though there is some evidence that suggests the
    Lease was not formally executed by the Hospital until May 4, 2010, the Hospital’s
    own internal documents at the time reflect that the Hospital intended the Lease to
    take effect February 28, 2010, as evidenced in the language of the Lease.
    While the Hospital produced some evidence that the Lease was formally
    executed after its express commencement date, Deville testified that it was
    “feasible and doable” for the Hospital to have started performance under a contract
    before the contract approval procedures were complete. In fact, he testified that
    this was a practice that the Hospital engaged in. He explained, “We work out an
    agreement and the paperwork follows.” Deville admitted that Reytec occupied the
    Property around February 28, 2010, before the Hospital formally executed the
    Lease. Additionally, there is evidence that Reytec had begun constructing the
    sidewalk contemplated under the Lease during the months of March, April, and
    May of 2010. Under the terms of the Lease, Reytec was required to complete the
    sidewalk by May 3, 2010. In Pena’s affidavit, also included in the record, he stated
    16
    that it was always the intention of the parties that the Lease would start on
    February 28, 2010 and terminate one year later. He stated that the Hospital never
    informed Reytec that it intended the Lease to become effective on any other day.
    We note that while the Hospital seeks an interpretation of the Lease that
    would have us ignore the express commencement date in the Lease’s language, the
    Hospital has consistently sought to enforce the express termination date of the
    Lease, which was February 28, 2011. The Hospital also sought to hold Reytec to
    the May 3, 2010 deadline for completion of the sidewalk, which under the
    Hospital’s interpretation of the Lease’s effective date, would have required Reytec
    to complete the sidewalk before the Lease had commenced.
    The plain language of the Lease is consistent with an interpretation that the
    parties’ mutual intention regarding the Lease was that the effective start date was
    to be February 28, 2010, rather than the date the Lease was formally executed by
    the parties. The Hospital’s merger argument is based on its contention that the
    Dump Contract was entered into before the Lease. In viewing the evidence in the
    light most favorable to the nonmovant Reytec, we conclude that Reytec has raised
    a genuine issue of material fact concerning the parties’ intention to be bound by the
    Lease on its defined commencement date even though they anticipated the Lease
    would be formally executed in the future. See Murphy v. Seabarge, Ltd., 868
    
    17 S.W.2d 929
    , 933 (Tex. App.—Houston [14th Dist.] 1994, writ denied) (“Actions
    may manifest an intent to be bound to an agreement, even though the parties may
    expressly provide a formal contract will be executed in the future.”); see also
    Foreca, S.A. v. GRD Dev. Co., 
    758 S.W.2d 744
    , 745 (Tex. 1988) (quoting A.
    Corbin, Corbin on Contracts § 30 at 97 (1963)) (explaining that the question of the
    parties’ intent to be bound with or without the execution of a final written contract
    is a question of fact for the jury). For all these reasons, we conclude the Hospital
    did not conclusively establish that the Dump Contract was entered into before the
    Lease, and therefore, has not shown as a matter of law that the Dump Contract was
    abrogated by the Lease under its merger provision. See Pitman v. Lightfoot, 
    937 S.W.2d 496
    , 529 (Tex. App.—San Antonio 1996, writ denied) (explaining that the
    merger doctrine “refers to the extinguishment of one contract by its absorption into
    another subsequent contract and is largely a matter of [the] intention of the
    parties”).
    B. Contract Modification
    Reytec contends that it is not liable for breach of contract because the Dump
    Contract modified its obligations under the Lease. Contract modification is an
    affirmative defense that Reytec had the burden to prove. See Intec Sys., Inc. v.
    Lowrey, 
    230 S.W.3d 913
    , 918 (Tex. App.—Dallas 2007, no pet.). The
    18
    determination of whether a contract has been modified depends on the parties’
    intentions and is a question of fact. Arthur J. Gallagher & Co. v. Dieterich, 
    270 S.W.3d 695
    , 702 (Tex. App.—Dallas 2008, no pet.). A valid contract modification
    must include a meeting of the minds supported by consideration. Id.; see Dupree v.
    Boniuk Interests, Ltd., 
    472 S.W.3d 355
    , 367–68 (Tex. App.—Houston [1st Dist.]
    2015, no pet.) (explaining that a modification to a lease agreement must be
    supported by consideration independent of the consideration provided in the
    original lease). “In determining whether the parties had a meeting of the minds
    concerning a modification of a contract, the focus is on what the parties did and
    said, not their subjective states of mind.” 
    Dieterich, 270 S.W.3d at 702
    .
    Consideration may consist of a benefit that accrues to one party or a detriment that
    is incurred by the other party. 
    Dupree, 472 S.W.3d at 368
    . However, a promise to
    fulfill an obligation in which the party was already bound cannot serve as new
    consideration for the modification. 
    Id. The Dump
    Contract is essentially a letter agreement written on Reytec
    letterhead and is dated, March 22, 2010. In the Dump Contract, the Hospital agreed
    to "accept delivery, possession, and responsibility for excavated material as is
    delivered to [the Property] by [Reytec] for the sum of $00.00 per load for a total of
    $00.00.” The Hospital further agreed Reytec was “only obligated to stock-pile
    19
    material to allow for it to be mowed.” Deville signed the Dump Contract on behalf
    of the Hospital. Deville testified that he signed the Dump Contract and has no
    reason to believe that he did not sign it on March 22, 2010. Guy Giesecke, the
    former chief operating officer for the Hospital, initialed the Dump Contract.
    The plain language of the Dump Contract supports that the parties had a
    meeting of the minds that Reytec, at the very least, was permitted to stockpile
    excavated materials on the Property. The plain language also supports that the
    parties had a meeting of the minds that the Hospital would not only take delivery
    and possession of the excavated materials, but that the Hospital would also become
    responsible for the materials delivered to the Property by Reytec.
    Contrary to the Hospital’s contention, there is nothing in the plain language
    of the Dump Contract itself to suggest that the Hospital was only agreeing to
    temporarily take possession of and responsibility for the materials. Moreover, there
    is evidence in the record that conflicts with this contention. Deville testified that
    when he executed the Dump Contract, he was considering the Hospital’s ability to
    use the excavated dirt “to fill a hole that would be created from destruction of
    another building.” He testified that early during the term of the Lease, he realized
    that the Hospital could not use the dirt as he had anticipated, so he informed
    Reytec that the Hospital no longer wanted to accept delivery, possession, and
    20
    responsibility for the excavated materials. It is undisputed that, at least at some
    point during the Lease term, the Hospital intended to use the excavated materials
    for its own benefit. This evidence is inconsistent with the Hospital’s argument that
    Reytec owned the dirt and was only allowed to store it on the Property temporarily.
    Reytec also argues that the Lease modification was supported by new
    consideration. Reytec agreed to deliver and stockpile the excavated materials on
    the Property free of charge to the Hospital. And, in return, the Hospital gave up its
    right to enforce Paragraphs 10 and 12 of the Lease. The Hospital does not
    challenge Reytec’s contention that the modification was supported by new
    consideration.
    We conclude that Reytec has presented more than a scintilla of evidence that
    a fact issue remains as to whether the parties’ intended to modify the Lease with
    the Dump Contract. Further, we conclude that Reytec produced summary judgment
    evidence sufficient to raise a fact issue on each element of its defense of
    modification.
    C. Waiver
    Reytec also alleged that through the Dump Contract, the Hospital waived its
    right to assert its claims regarding the excavated materials. The Hospital’s only
    argument on appeal regarding Reytec’s waiver defense is that the Dump Contract
    21
    was abrogated by the Lease’s merger clause. However, as discussed above, Reytec
    has raised a genuine issue of material fact regarding the merger argument.
    Waiver is the intentional relinquishment of a known right and is either made
    expressly or indicated by conduct that is inconsistent with an intent to claim the
    right. See Jernigan v. Langley, 
    111 S.W.3d 153
    , 156 (Tex. 2003). “The elements of
    waiver include (1) an existing right, benefit, or advantage held by a party; (2) the
    party’s actual knowledge of its existence; and (3) the party’s actual intent to
    relinquish the right, or intentional conduct inconsistent with the right.” Ulico Cas.
    Co. v. Allied Pilots Ass’n, 
    262 S.W.3d 773
    , 778 (Tex. 2008). “Waiver is largely a
    matter of intent, and for implied waiver to be found through a party’s actions,
    intent must be clearly demonstrated by the surrounding facts and circumstances.”
    
    Jernigan, 111 S.W.3d at 156
    . Ordinarily, waiver is a question of fact, but if the
    surrounding circumstances and facts are undisputed, the question becomes one of
    law. 
    Id. at 156–57.
    The Hospital does not dispute the first two elements of Reytec’s waiver
    defense. The summary judgment record supports that the Hospital held rights
    under the Lease and that it had knowledge of those rights. As explained above,
    Reytec has presented more than a scintilla of evidence to support that the Dump
    Contract was not abrogated by the Lease, but rather was intended by the parties to
    22
    alter their various obligations under the Lease. There is evidence in the record that
    the Hospital allowed Reytec to continue to stockpile excavated materials on the
    Property several months after the time the Hospital claims that the Dump Contract
    was abrogated. There is also evidence in the record that even though the Hospital
    had a representative observe the Property on a weekly basis, the Hospital did not
    complain about the continued stockpiling of excavated materials until months after
    the Dump Contract was allegedly abrogated. In viewing the evidence in the light
    most favorable to Reytec, we conclude that Reytec has raised a genuine issue of
    material fact concerning each element of its affirmative defense of waiver
    sufficient to preclude summary judgment.
    D. Release
    Reytec also alleged that through the Dump Contract, the Hospital released
    Reytec from all obligations or responsibilities concerning the excavated materials.
    “A release is an agreement or contract in which one party agrees that a legal right
    or obligation owed by the other party is surrendered.” D.R. Horton–Tex., Ltd. v.
    Savannah Props. Assocs., L.P., 
    416 S.W.3d 217
    , 226 (Tex. App.—Fort Worth
    2013, no pet.). Because a release is essentially a contract, a defendant must prove
    the elements of a contract to establish the affirmative defense of release of liability.
    Vera v. North Star Dodge Sales, Inc., 
    989 S.W.2d 13
    , 17 (Tex. App.—San Antonio
    23
    1998, no pet.). We construe a release primarily “to ascertain and give effect to the
    intention of the parties to the release, considering the instrument as a whole.” D.R.
    
    Horton, 416 S.W.3d at 226
    . Here, again, the Hospital’s only challenge to this
    defense is to the continued enforceability of the Dump Contract. As we have
    explained above, Reytec has presented evidence to raise a genuine issue of material
    fact as to the parties’ intentions regarding the Lease and the Dump Contract. For
    the same reasons as identified above, viewing the evidence most favorably to the
    nonmovant Reytec, we conclude that Reytec has presented sufficient summary
    judgment evidence to raise a genuine issue of material fact concerning each
    element of its release defense to preclude summary judgment.
    The only summary judgment ground asserted by the Hospital on appeal is
    that Reytec is liable for breach of contract for not fulfilling its obligations under
    Paragraph 12 of the Lease. We have concluded that Reytec has raised genuine
    issues of material fact regarding its affirmative defenses of modification, waiver,
    and release sufficient to preclude summary judgment on the breach of contract
    issue. Because the Hospital has abandoned its other summary judgment grounds,
    we need not address those issues. Therefore, the trial court erred in granting
    summary judgment, and we reverse the trial court’s judgment and remand this
    cause for further proceedings.
    24
    REVERSED AND REMANDED.
    ______________________________
    CHARLES KREGER
    Justice
    Submitted on November 30, 2015
    Opinion Delivered November 23, 2016
    Before McKeithen, C.J., Kreger and Johnson, JJ.
    25
    

Document Info

Docket Number: 09-15-00085-CV

Filed Date: 11/23/2016

Precedential Status: Precedential

Modified Date: 11/23/2016

Authorities (24)

Case Corp. v. Hi-Class Business Systems of America, Inc. , 184 S.W.3d 760 ( 2006 )

Provident Life & Accident Insurance Co. v. Knott , 47 Tex. Sup. Ct. J. 174 ( 2003 )

Sullivan v. Smith , 2003 Tex. App. LEXIS 4796 ( 2003 )

Wojcik v. Wesolick , 2003 Tex. App. LEXIS 302 ( 2003 )

Intec Systems, Inc. v. Lowrey , 230 S.W.3d 913 ( 2007 )

Ulico Casualty Co. v. Allied Pilots Ass'n , 51 Tex. Sup. Ct. J. 1320 ( 2008 )

Parker v. Dodge , 2003 Tex. App. LEXIS 488 ( 2003 )

Fort Worth Osteopathic Hospital, Inc. v. Reese , 47 Tex. Sup. Ct. J. 999 ( 2004 )

Martin v. Martin, Martin & Richards, Inc. , 1997 Tex. App. LEXIS 6742 ( 1997 )

Pitman v. Lightfoot , 1996 Tex. App. LEXIS 3531 ( 1996 )

Bank of Texas v. VR Electric, Inc. , 2008 Tex. App. LEXIS 9745 ( 2008 )

Travelers Insurance Co. v. Joachim , 53 Tex. Sup. Ct. J. 745 ( 2010 )

Lunsford Consulting Group, Inc. v. Crescent Real Estate ... , 2002 Tex. App. LEXIS 3728 ( 2002 )

Brownlee v. Brownlee , 27 Tex. Sup. Ct. J. 259 ( 1984 )

Reilly v. Rangers Management, Inc. , 30 Tex. Sup. Ct. J. 333 ( 1987 )

Vera v. North Star Dodge Sales, Inc. , 989 S.W.2d 13 ( 1999 )

Little v. Texas Department of Criminal Justice , 48 Tex. Sup. Ct. J. 56 ( 2004 )

Frost National Bank v. L & F Distributors, Ltd. , 48 Tex. Sup. Ct. J. 803 ( 2005 )

City of Keller v. Wilson , 48 Tex. Sup. Ct. J. 848 ( 2005 )

Arthur J. Gallagher & Co. v. Dieterich , 270 S.W.3d 695 ( 2008 )

View All Authorities »