Mega Builders, Inc., D/B/A Mega & Associates v. Bell Tech Enterprises, Inc. and Trimcos LLC ( 2018 )


Menu:
  • Affirmed and Memorandum Opinion filed August 2, 2018.
    In The
    Fourteenth Court of Appeals
    NO. 14-17-00642-CV
    MEGA BUILDERS, INC., D/B/A MEGA & ASSOCIATES, Appellant
    V.
    BELL TECH ENTERPRISES, INC. AND TRIMCOS LLC, Appellees
    On Appeal from the 215th District Court
    Harris County, Texas
    Trial Court Cause No. 2014-47565
    MEMORANDUM OPINION
    In this construction dispute, appellant Mega Builders, Inc., d/b/a Mega &
    Associates, appeals the trial court’s judgment in favor of appellees Bell Tech
    Enterprises, Inc. and Trimcos LLC. Bell Tech entered into a contract with Trimcos
    to construct an office building. By a separate contract, Trimcos engaged Mega to
    provide labor and materials for construction. After a payment dispute, Mega left the
    project and sued Trimcos and Bell Tech for, among other things, breach of contract.
    Trimcos counterclaimed, contending it overpaid Mega. A jury found that Mega
    breached the contract and that Trimcos did not breach the contract, and awarded
    Trimcos damages. Consistent with the verdict, the trial court signed a judgment
    awarding Trimcos damages against Mega.
    On appeal, Mega argues that the trial court’s exclusion of two exhibits was
    error and led to the rendition of an improper judgment. Concluding that the trial
    court either did not abuse its discretion or that any error in excluding the evidence
    was harmless, we affirm.
    Background
    This dispute stems from construction of an office building in Houston. Bell
    Tech is the building owner. At trial, the parties introduced two contracts into
    evidence. The first contract was between Bell Tech and Trimcos. That contract was
    signed April 25, 2013. The second contract was between Trimcos and Mega and is
    dated May 1, 2013. The price of both contracts was the same: $3.7 million. Under
    both contracts, work was to begin in May 2013 and be substantially completed by
    mid-March 2014.
    According to Mega, Trimcos received periodic payments from Bell Tech for
    Mega’s work but withheld portions of those payments from Mega. D.J. Mody,
    Mega’s owner, testified that he was “consistently starving for funds.” In January
    2014, Mody learned that the bank had distributed more money to Trimcos than
    Trimcos had paid Mega. Mody felt “cheated,” and Mega demanded an accounting
    and supplemental payment from Trimcos.
    Trimcos provided an accounting of amounts invoiced and paid as of February
    2014 under the May 1, 2013 contract. The accounting is a three-page spreadsheet
    reflecting billing details, payment and adjustment details, retention amounts,
    2
    discounts, and a balance due. The balance owed to Mega as of February 2014 is
    stated to be $23,551.28.
    Mega contends it agreed with Trimcos in March 2014 to a final settlement
    sum Trimcos was to pay to Mega. Under the alleged agreement, (1) Mega received
    an immediate payment of $23,551.28 (per the accounting), and (2) Trimcos would
    pay a previously withheld “retainage” of $75,622.98.1 The document stated:
    Received $23,551.28 from TRIMCOS, LLC as full and final settlement
    subject to retention amount ($75,622.95) for Belltech Office Building.
    Project address 14602 Presidio Sqr., Houston.
    The document was signed by representatives of Mega and Trimcos and dated
    March 3, 2014. The document included a photocopy of a check issued by Trimcos
    to Mega in the amount of $23,551.28. The February 2014 accounting and the alleged
    March 3, 2014 settlement agreement are the important documents for purposes of
    this appeal.      They are identified in our record as Mega Exhibits 9 and 10,
    respectively.
    Mega left the project in March 2014. According to Raffy Bell, Bell Tech’s
    owner, the only completed work at that point was the building’s foundation.
    Trimcos completed construction of the building.
    A few months after Mega left the project, it filed a mechanic’s and
    materialman’s lien against the building project, claiming it had not been paid
    1
    Retainage means “an amount representing part of a [construction or repair] contract
    payment that is not required to be paid to the claimant within the month following the month in
    which labor is performed, material is furnished, or specially fabricated material is delivered.” Tex.
    Prop. Code § 53.001(11). To benefit potential lien claimants, the Property Code requires an owner
    of a construction or repair project to retain 10% of either the contract price of the work or the value
    of the work if there is no contract price. See 
    id. §§ 53.101(a),
    53.102.
    3
    $107,973.30. Mega also claimed it held a constitutional lien as an original contractor
    on the Bell Tech project.
    Mega then sued Bell Tech and Trimcos, asserting breach of the April 25, 2013,
    and May 1, 2013 contracts. Mega did not allege that Trimcos breached the purported
    March 2014 settlement agreement. Mega also asserted a fraud claim against Bell
    Tech and Trimcos in the alternative, and asserted a claim for unjust enrichment and
    quantum meruit against Bell Tech. Mega alleged that it substantially performed the
    work contemplated by the May 1, 2013 contract, but had not been paid all amounts
    due for its labor or materials. Mega sought $128,321.37 in liquidated damages,
    unliquidated damages for its non-contract claims, and foreclosure on the statutory
    and constitutional liens on Bell Tech’s building.
    Trimcos filed a breach of contract counterclaim, asserting that Trimcos was
    entitled to a refund of money it allegedly overpaid Mega. Alternatively, Trimcos
    asserted a claim for money had and received. Bell Tech answered Mega’s petition
    but asserted no counterclaims.
    Before trial, defendants Bell Tech and Trimcos filed a motion in limine,
    seeking to exclude mention of any agreements that did not form a basis of Mega’s
    claims. In particular, the defendants claimed Mega’s Exhibits 9 and 10 were
    irrelevant because Mega had not pled breach of any purported settlement agreement.
    Further, Mega argued that the exhibits were inadmissible under Texas Rule of
    Evidence 408.2 The trial court granted the motion in limine. The next day, the trial
    2
    Rule 408, governing “Compromise Offers and Negotiations,” provides:
    (a) Prohibited Uses. Evidence of the following is not admissible either to prove or
    disprove the validity or amount of a disputed claim:
    (1) furnishing, promising, or offering—or accepting, promising to accept, or
    offering to accept—a valuable consideration in compromising or attempting to
    compromise the claim; and
    4
    court ruled that it was excluding the exhibits on grounds that they constituted
    evidence of a settlement agreement.3 Mega presented the exhibits as an offer of
    proof, and the court accepted them.
    After a three-day trial, the jury found:
    (a)    Mega entered into the May 1, 2013 contract with Trimcos to construct
    the office building;
    (b)    Mega did not enter into the May 1, 2013 contract with Bell Tech to
    construct the office building;
    (c)    Mega failed to comply with the May 1, 2013 contract;
    (d)    Bell Tech and Trimcos did not fail to comply with the May 1, 2013
    contract;
    (e)    Mega’s failure to comply was not excused;
    (f)    Mega was an original contractor on the project;
    (g)    Trimcos did not underpay Mega;
    (h)    Trimcos overpaid Mega $23,159.53;
    (i)    neither Trimcos nor Bell Tech failed to promptly pay any money due
    to Mega; and
    (j)    Mega did not perform any compensable work for Bell Tech for which
    Mega was not paid.
    Trimcos and Bell Tech moved to enter judgment on the jury verdict and
    Trimcos also moved for partial judgment notwithstanding the verdict (“JNOV”).
    The defendants asked the court to render judgment ordering that Mega take nothing
    on its claims, that Mega’s liens be dissolved, that Trimcos be awarded $23,159.53
    (2) conduct or statements made during compromise negotiations about the claim.
    Tex. R. Evid. 408(a).
    3
    The copy of the check included in Exhibit 10 was admitted into evidence separately as
    part of Trimcos’s Exhibit 3, which contained copies of all checks remitted by Trimcos to Mega.
    Thus, the only part of Exhibit 10 excluded from evidence is the handwritten portion documenting
    the purported settlement agreement.
    5
    in actual damages, and that the defendants be awarded costs of court, pre-judgment
    interest, and post-judgment interest. Trimcos also requested additional damages in
    the amount of $196,303. Trimcos argued that the evidence conclusively established
    that it overpaid Mega by $219,462.53, and that the jury erroneously offset that
    amount by the profit that Mega would have realized upon completion of the contract.
    Because the jury found Mega breached the contract, Trimcos argued that Mega was
    not entitled to a credit for any contractual profit.
    The trial court signed a judgment, which (1) ordered that Mega take nothing
    on its claims, (2) invalidated Mega’s lien and ordered it removed from the real
    property records, (3) awarded Trimcos actual damages from Mega of $23,159.53,4
    and (4) awarded Trimcos pre-judgment interest, court costs, and post-judgment
    interest.
    Mega appeals.
    Analysis
    Mega presents four issues, all centering on the trial court’s exclusion of
    Exhibits 9 and 10. Mega argues that the exhibits were improperly excluded under
    Rule 408 because they did not constitute a settlement offer or agreement. Further,
    Mega contends the trial court’s erroneous ruling probably resulted in rendition of an
    improper judgment because it led to the jury’s adverse findings in response to the
    breach and damage questions.
    A.     Error Preservation
    Appellees argue that Mega did not preserve error. Appellees contend that the
    trial court did not exclude Exhibit 9 and therefore Mega failed to preserve any issue
    4
    The trial court struck out a line that would have awarded Trimcos an additional $196,303,
    effectively denying Trimcos’s motion for JNOV.
    6
    for our review as to Exhibit 9. Appellees also argue that Mega “failed to present to
    the trial court the same theory of admissibility that it is now making on appeal” as
    to both exhibits. The record does not support appellees’ assertions.
    During a pre-trial hearing, the trial court stated that “[i]n regards to Plaintiff’s
    Exhibit 10 and 11, the Court is going to exclude those because they are discussing,
    per [Exhibit] 11, this was a settlement agreement.” The defendants’ attorney then
    asked, “[A]nd you’re also excluding Exhibit No. 9 and 11? Nine is the discussion
    regarding the numbers. . . . So that needs to be excluded as well.” The court stated,
    “So Plaintiff’s 1, 10 and 11.” The reference to Exhibit 1 appears to be either a
    misstatement or a mistranscription, as the record makes clear that the parties and the
    court were discussing only Exhibits 9, 10, and 11. Mega’s attorney clarified that
    “Your Honor has excluded Exhibits 9, 10 and 11,” and then requested that the court
    accept Exhibits 9, 10, and 11 as an offer of proof, which the trial court accepted.
    Thus, the record shows that the trial court excluded Exhibits 9 and 10. Tex. R. Evid.
    103(a).
    Stating the grounds for the offer of proof, Mega’s attorney indicated that
    Exhibits 9 and 10 represented “balances presented to [Mega’s owner Mody] by the
    Defendant Trimcos” and “a memorandum signed by Trimcos . . . by which Trimcos
    recognized that it was a sum further due to Mega in the amount of $75,622.95.” See
    Tex. R. Evid. 103(c). These arguments align with Mega’s contentions on appeal.
    See Tex. R. Evid. 103(a)(2) (to preserve error regarding a ruling excluding evidence,
    the substance of the evidence must be made known to the trial court by offer or
    apparent from the context of the questioning).
    We conclude that Mega preserved its complaint regarding the exclusion of
    Exhibits 9 and 10.
    7
    B.    Exclusion of Exhibits 9 and 10
    1.     Standard of review
    We review a trial court’s ruling on the admission or exclusion of evidence for
    abuse of discretion. See Brookshire Bros., Ltd. v. Aldridge, 
    438 S.W.3d 9
    , 27 (Tex.
    2014). Even if the trial court abuses its discretion in admitting or excluding
    evidence, a party seeking to reverse a judgment based on evidentiary error must
    demonstrate harm by proving that the error probably resulted in rendition of an
    improper judgment. Neely v. Comm’n for Lawyer Discipline, 
    302 S.W.3d 331
    , 339
    (Tex. App.—Houston [14th Dist.] 2009, pet. denied).           To determine whether
    evidentiary error probably resulted in the rendition of an improper judgment, an
    appellate court reviews the entire record. Barnhart v. Morales, 
    459 S.W.3d 733
    , 742
    (Tex. App.—Houston [14th Dist.] 2015, no pet.). The complaining party must
    demonstrate that the judgment turns on the particular evidence that was excluded or
    admitted. Hooper v. Chittaluru, 
    222 S.W.3d 103
    , 107 (Tex. App.—Houston [14th
    Dist.] 2006, pet. denied) (op. on reh’g). A reviewing court ordinarily will not reverse
    a judgment based on an erroneous exclusionary ruling when the excluded evidence
    is cumulative or not controlling on a material issue dispositive to the case. 
    Id. 2. Exhibit
    9
    We presume without deciding that the trial court abused its discretion by
    excluding Exhibit 9, and we proceed to a determination of whether the exclusion
    caused Mega harm—i.e., whether the exclusion probably resulted in the rendition of
    an improper judgment. See Tex. R. App. P. 44.1(a)(1). Mega alleges that the
    exclusion led the jury to answer a number of questions erroneously.
    Exhibit 9, which is a summary of the invoices submitted by Mega and the
    amounts paid by Trimcos, is cumulative of other evidence properly admitted and
    8
    considered by the jury. Exhibit 9 identifies Invoices #1-3, 5-12, 14 (though the
    amount of Invoice #9 is left blank). Trimcos introduced copies of each of these
    invoices, as well as other invoices not included in Exhibit 9. Trimcos also introduced
    copies of checks issued to Mega, as referenced in Exhibit 9. Finally, the amount
    “due after adjustment,” per Exhibit 9, is $23,551. Trimcos introduced independent
    evidence that it paid Mega this amount. Exhibit 9 also listed the retainage amount
    of $75,622.98 Mega claimed it was owed. But Mega introduced other evidence
    supporting its allegation that Trimcos owed it retained funds. In fact, Mega argued
    and presented evidence that the amount of retainage Trimcos owed was $196,000, a
    far greater sum than the $75,622.98 amount noted on Exhibit 9.
    Viewing the other evidence in the record, we cannot say that the exclusion of
    Exhibit 9 caused Mega any harm. See Garden Ridge, L.P. v. Clear Lake Ctr., L.P.,
    
    504 S.W.3d 428
    , 441 (Tex. App.—Houston [14th Dist.] 2016, no pet.); Mancorp,
    Inc. v. Culpepper, 
    802 S.W.2d 226
    , 230 (Tex. 1990) (evidence not harmful when it
    was “entirely cumulative” of other testimony).
    3.     Exhibit 10
    We next turn to the trial court’s exclusion of Exhibit 10. Exhibit 10 states that
    Mega received $23,551.28 from Trimcos on March 3, 2014, “as full and final
    settlement subject to retention amount ($75,622.95) for Belltech Office Building.”
    The trial court excluded the exhibit as evidence of a settlement agreement. See Tex.
    R. Evid. 408(a) (evidence of compromise offers or agreements “is not admissible
    either to prove or disprove the validity or amount of a disputed claim”).
    Mega argues that Exhibit 10 is not evidence of compromise and settlement,
    but rather an acknowledgement by Trimcos of the total amount due for Mega’s work,
    including payment of retained funds, as of February 2014.               Mega’s own
    characterization of events belies its argument. A few months before Mega left the
    9
    project, Mody demanded that Trimcos’s owner “make [a] payment to avoid
    problems on the project.” After Trimcos allegedly failed to make timely periodic
    payments, Mega “demanded an accounting,” and the parties eventually “reached an
    accord” that Mega would receive an immediate payment of $23,551.28 and a future
    payment of withheld retainage. Mega admits to leaving the project, due to the
    ongoing payment disputes. The plain text of Exhibit 10—that the consideration
    mentioned was in “full and final settlement” of Mega’s work on the building—
    supports a reasonable conclusion that Exhibit 10 is evidence of a compromise or
    settlement and was properly excluded. See, e.g., Ford Motor Co. v. Leggat, 
    904 S.W.2d 643
    , 649 (Tex. 1995) (“Settlement agreements . . . , of course, are not
    admissible at trial to prove liability.”); Vinson Minerals, Ltd. v. XTO Energy, Inc.,
    
    335 S.W.3d 344
    , 354 (Tex. App.—Fort Worth 2010, pet. denied) (holding text of
    letter supported reasonable conclusion that letter constituted settlement offer). In its
    reply brief, Mega admits that Exhibit 10 “was, at one time, a putative settlement
    agreement.” Additionally, the trial court’s ruling was consistent with Mega’s
    Exhibit 11, also excluded, which consisted of an email exchange between the parties
    and referred to the March 3, 2014 agreement as a settlement.
    Mega argues alternatively that even if Exhibit 10 constitutes a settlement
    agreement, the trial court nevertheless should have admitted it as impeachment
    evidence, which Mega contends is a “permissible use” under Rule 408(b). Rule
    408(b) provides that the trial court may admit evidence of a compromise offer or
    agreement for other purposes, “such as proving a party’s or witness’s bias, prejudice,
    or interest, negating a contention of undue delay, or proving an effort to obstruct a
    criminal investigation or prosecution.” Tex. R. Evid. 408(b).
    Mega’s argument misses the mark. Trimcos’s claim was that Mega breached
    the contract, and that Trimcos was entitled to a refund of overpayments. Mega
    10
    insists that Exhibit 10 was crucial in “negat[ing] Trimcos’ claim of overpayment.”
    That is, Mega sought to admit Exhibit 10 to “prove or disprove the validity or amount
    of a disputed claim.” Tex. R. Evid. 408(a). This is a prohibited use of the document;
    Mega’s stated purpose does not fall within Rule 408(b)’s exception. Regardless
    whether Exhibit 10 was offered as direct or impeachment evidence, Mega sought its
    introduction to disprove Trimcos’s claim of overpayment. Mega does not claim that
    Exhibit 10 was relevant to bias, prejudice, interest, or any other permitted use stated
    in the rule.
    Whether evidence is impermissibly offered as evidence of liability or for some
    other valid reason is a matter within the trial court’s discretion. See Tatum v.
    Progressive Polymers, Inc., 
    881 S.W.2d 835
    , 837 (Tex. App.—Tyler 1994, no writ).
    For the reasons stated, we hold that the trial court did not abuse its discretion in
    excluding Exhibit 10 on Rule 408 grounds.
    Even if the court erred, however, we conclude that Mega suffered no harm.
    Exhibit 10 is not controlling on a material issue because Mega did not sue for breach
    of any alleged settlement agreement.       See Bartosh v Gulf Health Care Ctr.-
    Galveston, 
    178 S.W.3d 434
    , 439 (Tex. App.—Houston [14th Dist.] 2005, no pet.)
    (to establish harm, appellant must demonstrate that the excluded evidence was
    controlling on a material issue).
    Further, Mega fails to explain how the admission of Exhibit 10 would have
    led the jury to reach a verdict more favorable to Mega. Mega’s theory at trial—both
    in support of its affirmative claim for damages and in opposition to Trimcos’s
    overpayment claim—was that Trimcos did not pay Mega what Mega was owed.
    According to Mody, Mega’s owner, Trimcos received money from either Bell Tech
    or the bank that should have been disbursed to Mega. In support, Mega relied on a
    bank loan document, showing that Bell Tech had retained $196,303, which
    11
    represented 10% of the completed work as of mid-March 2014. Mody testified that
    he expected to be paid his profit and overhead from the retainage at the end of the
    project. At the end of the trial, Mega argued to the jury that it was owed at least
    $196,000.
    Trimcos, on the other hand, argued that it had overpaid Mega by $219,462.55,
    the difference between the total invoiced by Mega for its labor costs and the total
    paid by Trimcos before Mega left the project.             The jury awarded Trimcos
    $23,159.53, which is the difference (less two cents) between what Trimcos and
    Mega, respectively, requested.      Accordingly, the jury likely credited Mega’s
    argument that it was entitled to $196,303 in retainage, an amount substantially
    greater than the $75,622.98 amount referenced in Exhibit 10. Thus, we are not
    persuaded that the exclusion of Exhibit 10 led to the rendition of an improper verdict.
    See, e.g., Castillo v. Am. Garment Finishers Corp., 
    965 S.W.2d 646
    , 653 (Tex.
    App.—El Paso 1998, no pet.) (erroneous exclusion of testimony regarding doctor’s
    bill was harmless, when plaintiff presented other evidence to establish the same fact
    and the jury awarded him the full amount of the bill).
    *         *     *
    Based on the above, we conclude that any error in the trial court’s exclusion
    of Exhibits 9 and 10 probably did not lead to the rendition of an improper judgment.
    Accordingly, we overrule all of Mega’s issues on appeal.
    Conclusion
    We affirm the trial court’s judgment.
    /s/       Kevin Jewell
    Justice
    Panel consists of Justices Busby, Brown, and Jewell.
    12