Contemporary Contractors, Inc. v. WILC/MVL, LLP and Settlement Investments Management Corp. ( 2015 )


Menu:
  • Affirmed and Opinion Filed May 28, 2015
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-14-00411-CV
    CONTEMPORARY CONTRACTORS, INC., Appellant
    V.
    WILC/MVL, LLP AND SETTLEMENT INVESTMENTS MANAGEMENT CORP.,
    Appellees
    On Appeal from the 68th Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-12-14470-C
    MEMORANDUM OPINION
    Before Justices Francis, Lang-Miers, and Whitehill
    Opinion by Justice Whitehill
    This appeal from a bench trial on a breach of express warranty claim arises out of a
    contract to paint an apartment complex. The trial court found that Contemporary Contractors,
    Inc. (“Contractor”) breached the express warranty in its contract with WILC/MVL, LLP and
    Settlement Investment Management Corp. (“WILC”).              The Contractor brings six issues
    challenging the legal and factual sufficiency of the evidence to support the trial court’s findings
    concerning liability and reasonable repair costs. Concluding that the Contractor’s arguments
    lack merit, we affirm the trial court’s judgment.
    I. Background
    On January 19, 2009, the parties entered into a contract for the Contractor to replace and
    repair exterior wood on and to paint the exterior of the Marina Del Ray apartment complex in
    Grapevine, Texas. The contract warranted that the work would be free of defects and would
    perform as intended for five years after completion.
    WILC began to notice issues with the exterior paint about a year after the work was
    completed, and asked the Contractor to repaint the property. When the Contractor refused,
    WILC sued the Contractor for breach of the express warranty.
    The trial court found that the Contractor breached the contract’s express warranty and
    entered judgment in WILC’s favor for $92,000 and attorney’s fees.                                                The trial court made
    findings of fact and conclusions of law to support the judgment. This appeal followed.
    II. Issues on Appeal and Standard of Review
    In its first, second, third, and fourth issues, the Contractor challenges the legal and factual
    sufficiency of the evidence to support the trial court’s findings that (i) the paint job failed, (ii) the
    Contractor is liable to WILC for breach of the contract’s express warranty and (iii) the
    reasonable and necessary cost of repair is $92,000.1 In its fifth and sixth issues, the Contractor
    globally asserts that “the trial court’s findings are so contrary to the evidence as to be clearly
    wrong and unjust” and “there are no findings of fact or evidence to support the Trial Court’s
    judgment.”
    Because, as discussed below, the evidence is factually sufficient to support the trial
    court’s findings that the warranty was breached and that $92,000 was a reasonable and necessary
    repair cost, we need not and do not discuss the legal sufficiency issues. See British Am. Ins. Co.
    v. Howarton, 
    877 S.W.2d 347
    , 352 (Tex. App.—Houston [1st Dist.] 1994, writ dism’d by agmt.).
    In an appeal from a bench trial, we review a trial court’s fact findings under the same
    sufficiency of the evidence standards used regarding jury findings. Ortiz v. Jones, 
    917 S.W.2d 770
    , 772 (Tex. 1996). When a party attacks the factual sufficiency of an adverse finding on an
    1
    These issues challenge the trial court’s conclusions of law numbered 2 and 3 and the court’s findings of fact numbered 10 and 11.
    –2–
    issue on which it did not have the burden of proof at trial, it must show that there is factually
    insufficient evidence to support the adverse finding. Vongontard v. Tippit, 
    137 S.W.3d 109
    , 112
    (Tex. App.—Houston [1st Dist.] 2004, no pet.). To conduct this review, we examine the entire
    record and consider and weigh all the evidence, both in support of, and contrary to, the
    challenged finding. See Plas–Tex, Inc. v. U.S. Steel Corp., 
    772 S.W.2d 442
    , 445 (Tex. 1989).
    We must uphold the finding unless the evidence that supports it is so weak as to be clearly wrong
    or manifestly unjust. 
    Id. The trier
    of fact is the sole judge of the witnesses’ credibility and the
    weight given to their testimony. Helping Hands Home Care, Inc. v. Home Health of Tarrant
    County, Inc., 
    393 S.W.3d 492
    , 505–06 (Tex. App.—Dallas 2013, pet. denied). As such, the trial
    court may choose to believe one witness and disbelieve another. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 819 (Tex. 2005). We will not substitute our judgment for the trial court’s merely
    because we might reach a different conclusion. Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 407 (Tex. 1998).
    We review the trial court’s conclusions of law de novo. Fulgham v. Fischer, 
    349 S.W.3d 153
    , 157 (Tex. App.—Dallas 2011, no pet.).
    III. Analysis
    A. Is the Evidence Factually Sufficient to Support Contractor’s Liability?
    The Liability Dispute
    The Contractor’s liability depends on whether the evidence was sufficient to establish a
    breach of the express warranty included in the parties’ contract. To recover for breach of an
    express warranty, a plaintiff must prove: (1) an express affirmation of fact or promise by the
    seller relating to the goods; (2) that such affirmation of fact or promise became a part of the basis
    of the bargain; (3) that the plaintiff relied upon said affirmation of fact or promise; (4) that the
    goods failed to comply with the affirmation of fact or promise; (5) that the plaintiff was injured
    –3–
    by such failure of the product to comply with the express warranty; and (6) that such failure was
    the proximate cause of the plaintiff’s injury. Am. Eurocopter Corp. v. CJ Sys. Aviation Grp., 
    407 S.W.3d 274
    , 292 (Tex. App.—Dallas 2013, pet. denied); see also Paragon Contractors, Inc. v.
    Larco Const., Inc., 
    227 S.W.3d 876
    , 886 (Tex. App.—Dallas 2007, no pet.) (breach of express
    services warranty).
    Here, the first three elements are undisputed. The Contractor’s liability issues instead
    challenge the court’s determination that the paint job failed, that is, that the five year
    performance warranty failed. Specifically, the Contractor challenges the court’s findings and
    conclusions that (i) by early spring 2012, the exterior areas of the apartments showed evidence
    that the painting had failed and that the paint job had faded and was peeling throughout the entire
    exterior of the complex, and (ii) the Contractor is liable to WILC for breaching the parties’
    express warranty. We examine these findings given the express warranty and the evidence
    adduced at trial. As discussed below, the primary liability dispute turns on the nature of the
    warranty at issue.
    The Warranty
    The express warranty provides:
    All work described herein shall be warranted and guaranteed to be free of
    defects and failure and to perform as intended for a period of five years
    from completion.
    This warranty has two parts: (i) to be free from defects and failure and (ii) to perform as
    intended for five years. A breach of either part breaches the warranty.
    The Contractor, however, relies on Melody Home Mfg. Co. v. Barnes, 
    741 S.W.2d 349
    ,
    351 (Tex. 1987), to argue that in a breach of warranty case, the only requirement is that the work
    be performed in a good and workmanlike manner. According to the Contractor, the trial court
    “only found that the paint had failed,” not that the Contractor failed to perform the work in a
    –4–
    good and workmanlike manner. The Contractor argues that the evidence is uncontroverted that
    the work was performed in accordance with the specifications (and that the paint used was equal
    to or better than the specified paint). It is thus presumed that the work was done in a good and
    workmanlike manner.
    The Contractor’s reliance on Melody Homes is misplaced. Melody Homes involved an
    implied warranty under the Deceptive Trade Practices Act, but the warranty here is a contractual
    express warranty. Whether the work was performed in a good and workmanlike manner is not at
    issue here. We instead consider whether the Contractor met the express warranty terms.
    Generally, a warranty describes the character, quality, or title of the thing being sold.
    See Chilton Ins. Co. v. Pate & Pate Enters, Inc., 
    930 S.W.2d 877
    , 890–91 (Tex. App.—San
    Antonio 1996, writ denied). An express warranty is a definitive affirmation of fact or a promise
    that becomes part of the basis of the bargain and on which the parties rely. 
    Id. at 891.
    Express
    warranties arise out of the parties’ agreed terms and result from a negotiated exchange. See Med.
    City Dallas, Ltd. v. Carlisle Corp., 
    251 S.W.3d 55
    , 60 (Tex. 2008) (citations omitted). Here, the
    Contractor expressly promised that, at a minimum, the paint job would perform as intended for
    five years. That was an allocated risk that became part of the parties’ bargain.
    Breach
    George Martin, WILC’s president, identified the January 19, 2009 contract between
    WILC and the Contractor for repainting and repairing the apartment complex. The contract
    required the Contractor to replace exterior wood, make repairs, and paint the entire complex
    exterior for $87,899. It completed the work about two to three months later.
    Martin began to notice issues with the apartments’ exterior paint in one particular area on
    the back side of the property about a year after the Contractor finished the work. The issues
    continued in that area, and then Martin began to notice other areas where the paint appeared to be
    –5–
    “sloughing off or sagging,” and other areas where it was peeling badly. Martin identified these
    issues, as well as fading paint, in photographs that were admitted into evidence.           Martin
    explained that he considered 100% of the property to be affected because the peeling, fading, and
    sloughing off was throughout the property.
    In 2012, Martin hired architect Shannon Pearcey to review the contract and inspect the
    premises to determine whether the Contractor complied with the contract. Pearcey photographed
    the property and testified that the paint conditions shown in the photographs affected every
    building on the property except the new leasing office. Pearcey prepared a property condition
    report that was admitted into evidence without objection. That report included the site visit
    pictures, which she said show “failing paint on the siding, trim, fascia, etc.” Pearcey opined that
    the paint was failing throughout the entire apartment complex.
    The Contractor, however, argues the evidence is uncontroverted that “the paint itself did
    not fail.” In this regard, the Contractor relies on the testimony of Christopher Heath. Heath, an
    employee of the paint supplier, testified that, although the paint used for the project was not the
    paint specified in the contract, the paint used was of equal or better quality. The company
    checked its retained paint sample and determined that it was manufactured within specifications.
    After WILC complained, the Contractor asked Heath to inspect the property to evaluate
    what areas were affected by white staining on the siding. He determined that twenty to twenty-
    five percent of the property was affected. The white substance was a white cellulose-based
    material that was on top of the paint film. Heath opined that the white stains resulted from
    deteriorating siding. A report discussing Heath’s evaluation was admitted into evidence. Heath
    acknowledged that one of the photographs of the property showed peeling paint, but he could not
    state whether that was caused by the siding. At one point, Heath said that “the paint didn’t fail,”
    but he also said “it [the paint job] didn’t last five years. It just didn’t.”
    –6–
    Marion Whittington, a paint company sales representative, also testified for the
    Contractor. At the Contractor’s request, Whittington inspected the property to “see if there [was]
    something going on with the paint.” Whittington determined that wax was leaching out and off
    of the masonite material to the siding below, and “it was not a matter of the paint.” Whittington
    said that, although the area could be repainted, the issue would just occur again because of the
    siding. On cross-examination, Whittington acknowledged that the “wax bleed” he described
    could come through the primer. When asked if the wax bleed would occur faster with a weaker
    primer, Whittington replied, “perhaps so.”
    The Contractor’s president admitted that there were defects and that the paint was peeling
    and sloughing as shown on the photographs admitted into evidence.                 The Contractor’s
    superintendent testified that he never checked to determine whether the paint and primer that
    were used complied with the contract specifications.
    That the Contractor offered evidence suggesting that the paint itself was not defective and
    that the issues were caused by the siding does not mean WILC’s evidence was insufficient.
    Instead, given the warranty requirement that the work would last for at least five years, we
    conclude that the trial court’s determination that the warranty was breached is not so against the
    great weight of the evidence as to be manifestly unjust and to warrant a new trial. See Cain v.
    Bain, 
    709 S.W.2d 175
    , 176 (Tex. 1986).
    For the above reasons, we decide the Contractor’s first, second, fifth, and sixth issue
    liability challenges against it. We consequently also decide the Contractor’s legal sufficiency
    liability challenges in issues three, four, and six against it.
    B. Is the Evidence Factually Sufficient to Support the Damages?
    Part of the Contractor’s second issue challenges the factual sufficiency of the trial court’s
    damages findings. In particular, the Contractor contends that the evidence is insufficient to
    –7–
    support the trial court’s findings that $92,000 is the reasonable and necessary cost to replace the
    defective, peeling, and faded paint work.
    Martin testified he has been in the multifamily property management business for more
    than thirty years, he was currently managing nine multifamily properties, and from that
    experience he is familiar with the cost of repair and repainting multifamily projects. He also said
    that it is something he does on a monthly and annual basis.
    Martin asked the Contractor and its paint supplier to repaint the property. When they did
    not do so, he hired Five Star Contractors to repaint the property. After the Five Star contract was
    admitted into evidence over the Contractor’s hearsay objection, Martin testified that (i) the paint
    cost needed to repaint the property was $26,000, (ii) the labor cost was $66,200, and (iii) based
    on his experience, these costs were reasonable and were paid.
    The Contractor argues that the Five Star contract should not have been admitted into
    evidence and without that contract there is no evidence of the cost of labor for repainting.
    Contractor further asserts that Martin was not qualified to testify about the cost of repair, and his
    lay testimony contrasts with the Contractor’s experts’ testimony that the problem areas alone
    could have been repainted.
    The Five Star contract was properly admitted into evidence. The Contractor argues that
    the estimate was hearsay because Five Star was not present to authenticate it. Hearsay and
    authenticity are distinct objections and the Contractor’s argument in substance challenges only
    the exhibit’s authenticity. Authenticity is a condition precedent to its admissibility. TEX. R.
    EVID. 901(a). Evidence sufficient to support a finding that the matter in question is what its
    proponent claims satisfies this requirement. 
    Id. The testimony
    of a witness with knowledge of
    the relevant facts is one way to authenticate evidence. 
    Id. 901(b)(1). Martin
    , who had such
    knowledge, authenticated the contract which bears his signature. The trial court did not abuse its
    –8–
    discretion by overruling the Contractor’s objection. See Bay Area Healthcare Grp, Ltd. v.
    McShane, 
    239 S.W.3d 231
    , 234 (Tex. 2007) (stating evidentiary rulings committed to trial
    court’s sound discretion).
    Although the Contractor also complains that Martin was not qualified to testify about
    reasonable repair costs, this objection was not asserted at trial. Moreover, even had the issue
    been preserved, his testimony together with the Five Star contract were sufficient to support the
    damages. See Bernstein v. Thomas, 
    298 S.W.3d 817
    , 826 (Tex. App.—Dallas 2009, no pet.).
    Contractor’s argument about conflicting testimony regarding damages is similarly
    unpersuasive. Such conflicts involve weight and credibility determinations. An appellate court
    cannot pass upon a witness’s credibility or substitute its judgment for the fact-finder’s, even if
    there is conflicting evidence that would support a different conclusion. See Cain v. Bain 
    709 S.W.2d 175
    , 176 (Tex. 1986). The trial court, as the factfinder, was free to believe Martin and
    Pearcey’s testimony that the entire property needed to be repainted, and Martin’s testimony that
    the reasonable cost to do so was $92,000. We thus overrule the Contractor’s third issue. See
    British Am. Ins. 
    Co., 877 S.W.2d at 352
    .
    IV. Conclusion
    Having resolved all of the Contractor’s issues against it, we affirm the trial court’s
    judgment.
    140411F.P05
    /Bill Whitehill/
    BILL WHITEHILL
    JUSTICE
    –9–
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    CONTEMPORARY CONTRACTORS,                            On Appeal from the 68th Judicial District
    INC., Appellant                                      Court, Dallas County, Texas
    Trial Court Cause No. DC-12-14470-C.
    No. 05-14-00411-CV         V.                        Opinion delivered by Justice Whitehill.
    Justices Francis and Lang-Miers
    WILC/MVL, LLP AND SETTLEMENT                         participating.
    INVESTMENTS MANAGEMENT CORP.,
    Appellees
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    AFFIRMED.
    It is ORDERED that appellees WILC/MVL, LLP AND SETTLEMENT
    INVESTMENTS MANAGEMENT CORP. recover their costs of this appeal from appellant
    CONTEMPORARY CONTRACTORS, INC..
    Judgment entered May 28, 2015.
    –10–