City of Houston, Texas v. the Commons at Lake Houston, Ltd. ( 2019 )


Menu:
  • Reversed and Rendered and Opinion filed October 15, 2019.
    In The
    Fourteenth Court of Appeals
    NO. 14-18-00664-CV
    CITY OF HOUSTON, TEXAS, Appellant
    V.
    THE COMMONS AT LAKE HOUSTON, LTD., Appellee
    On Appeal from the County Civil Court at Law No. 1
    Harris County, Texas
    Trial Court Cause No. 1109638
    OPINION
    The Commons at Lake Houston, Ltd. sued the City of Houston for inverse
    condemnation and a declaratory judgment regarding a newly amended ordinance
    that regulates development in the 500-year floodplain. The City filed a plea to the
    jurisdiction, contending that The Commons’ claims were not ripe. The trial court
    denied the plea. We reverse the trial court’s order and render a judgment
    dismissing The Commons’ claims without prejudice.
    I.     STANDARD OF REVIEW
    Ripeness is a component of subject-matter jurisdiction, which may be
    challenged by a plea to the jurisdiction. See Riner v. City of Hunters Creek, 
    403 S.W.3d 919
    , 921–22 (Tex. App.—Houston [14th Dist.] 2013, no pet.). When a plea
    to the jurisdiction challenges the pleadings, we review de novo whether the pleader
    has alleged facts that affirmatively demonstrate the court’s jurisdiction. Tex. Dept.
    of Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 226 (Tex. 2004). When a plea to
    the jurisdiction challenges the existence of jurisdictional facts, we consider the
    relevant evidence submitted by the parties. 
    Id. at 227.
    If the evidence is undisputed
    or fails to raise a fact question on the jurisdictional issue, then the trial court rules
    on the plea as a matter of law, 
    id. at 228,
    and we review the ruling de novo, see 
    id. at 226.
    II.    BACKGROUND1
    The Commons owns a roughly 318-acre tract of land near Lake Houston.
    The Commons has begun development of the land into a master-planned
    community known as “The Crossing.” Significant portions of The Crossing are
    located within the 100-year or 500-year floodplains.
    The City has approved several general plans for The Crossing, and The
    Commons recorded subdivision plats consistent with the general plan and a final
    plat for part of The Crossing. The City approved a drainage plan and construction
    plans concerning water, sanitation, sewage, drainage facilities, and paving for part
    of The Crossing. The Commons began working on water, sewage, and drainage
    1
    We look to the The Commons’ live petition and the evidence submitted by the parties
    when reciting the relevant facts. Minor discrepancies between facts alleged in the petition and
    The Commons’ evidence, such as the acreage of land and number of homesites at issue, are
    irrelevant to the disposition of this appeal.
    2
    lines, investing millions of dollars towards amenities for the development of The
    Crossing.
    In the wake of Hurricane Harvey, the City passed Ordinance No. 2018-258
    to amend the existing floodplain development ordinance in Chapter 19 of the
    City’s Code of Ordinances. The old ordinance required that new residential
    structures within the 100-year floodplain had to be built at least one foot above the
    flood elevation. Among other changes, the new ordinance requires that new
    residential structures within the 500-year floodplain must be built at least two feet
    above the flood elevation. See Hous., Tex., Code of Ordinances §§ 19-2, 19-33,
    https://library.municode.com/tx/houston/codes/code_of_ordinances.
    The Commons sued the City before the effective date of the ordinance and
    ultimately asserted claims for inverse condemnation and a declaratory judgment.
    The Commons alleged that the application of the amended ordinance to its
    property would substantially damage the market value of the property, and the
    current development plan would be unfeasible.
    While the suit was pending, a person who worked on the The Crossing
    project for The Commons—Stephen Sheldon—emailed a managing engineer who
    worked for the City about what impact the “Vested Rights” statute2 might have if a
    general plan had been filed for a master-planned subdivision. In the email, Sheldon
    wrote, “I’m hoping you might be able to answer a question related to the ordinance
    that I’m having trouble tracking down.” Sheldon concluded:
    I realize you aren’t an attorney, but I was hoping either this had come
    up already in internal discussions (in which case you might know the
    answer as to whether [the statute] applies) or you might be able to
    forward this e-mail to an attorney who worked on this ordinance, who
    2
    See Tex. Loc. Gov’t Code ch. 245.
    3
    might have this answer. Trying to do some advance planning for a
    couple of large tracts, and want to make sure I plan correctly!
    Sheldon did not mention The Commons, The Crossing, or any details related to
    The Crossing.
    The City’s engineer responded in relevant part:
    You are right, I’m not an attorney. What I can tell you is that while
    the plat would in fact be grandfathered and would not have to be re-
    platted due to the ordinance change, the particulars of the
    improvements (requirements for elevation of structures and mitigation
    requirements) are not part of the plat. The required elevation of
    structures and grading plans including required floodplain storage
    mitigation can only be grandfathered if that particular scope of work
    is part of the plans submitted for permit by the effective date of the
    ordinance (September 1, 2018).
    I hope this helps you. If not, let me know and I will get you more
    information.
    Sheldon responded, “I think so. . . really appreciate the thoughts, and needless to
    say, good luck with all the fun stuff coming your way with this new ordinance! ”
    (ellipsis in original).
    The City filed a plea to the jurisdiction, contending that The Commons’
    claims were not ripe because the City had not had an opportunity to make a final
    decision applying its floodplain regulations to The Crossing. The Commons
    responded with various items of evidence, including the emails discussed above
    and an affidavit from an employee of an entity related to The Commons. The
    employee testified that The Commons “conducted an analysis” and determined that
    the development of The Crossing would be “financially infeasible” under the
    amended ordinance. He testified that nearly 70% of the lots would be “unsaleable.”
    4
    The City filed an affidavit from the engineer who had answered the email.
    She testified that her email was not a final decision by the City approving or
    denying a permit, nor was her response a denial of a variance under the ordinance.
    The trial court denied the plea, and the City appealed. The ordinance became
    effective during the pendency of this appeal.
    III.   ANALYSIS
    In a single issue, the City contends that the trial court erred by denying the
    plea to the jurisdiction because The Commons’ claims are not ripe. Specifically,
    the City contends that the City has not made any final decision applying the
    ordinance to deny any permit application for The Commons’ property or otherwise
    decided whether the former or amended ordinance applies to The Crossing.
    A.    Legal Principles for Inverse Condemnation and Chapter 245 Claims
    When the government’s regulation of private property reaches a certain
    magnitude, there must be an exercise of eminent domain and compensation to the
    landowner. City of Houston v. Carlson, 
    451 S.W.3d 828
    , 831 (Tex. 2014). If a
    landowner believes compensation is due to them for a regulatory taking, the
    landowner may bring a claim for inverse condemnation. 
    Id. A regulatory
    taking
    can occur if a government agency imposes restrictions that unreasonably interfere
    with a landowner’s rights to use and enjoy the property. Mayhew v. Town of
    Sunnyvale, 
    964 S.W.2d 922
    , 935 (Tex. 1998).
    Chapter 245 of the Local Government Code creates a system by which
    property developers can rely on a municipality’s land-use regulations in effect at
    the time the original application for a permit had been filed. Vill. of Tiki Island v.
    Premier Tierra Holdings, Inc. (Tiki Island I), 
    464 S.W.3d 435
    , 439 (Tex. App.—
    Houston [14th Dist.] 2015, no pet.). Generally, Section 245.002 establishes that
    5
    municipal regulatory agencies must consider a permit application under the terms
    of the ordinances that were in effect at the time a permit, development plan, or plat
    application was filed. 
    Id. at 440
    (citing Tex. Loc. Gov’t Code § 245.002(a)). The
    rights accrue on the filing of an original application or plan for development or plat
    application that gives the regulatory agency fair notice of the project and the nature
    of the permit sought. 
    Id. These statutory
    rights are commonly referred to as “vested rights.” 
    Id. Vested rights
    attach to a project, not to a particular landowner. 
    Id. Thus, Chapter
    245 “freezes” the rules at the time the original application for a permit is filed and
    limits the rights of a municipality to change the rules in the middle of the game. 
    Id. Chapter 245
    authorizes enforcement of its provisions through a request for
    declaratory relief. 
    Id. (citing Tex.
    Loc. Gov’t Code § 245.006(a)).
    B.    Legal Principles for Ripeness Doctrine
    Justiciability doctrines, such as ripeness, are rooted in the prohibition against
    advisory opinions. 
    Id. at 439;
    see also Perry v. Del Rio, 
    66 S.W.3d 239
    , 249 (Tex.
    2001). Ripeness is a question of timing. 
    Perry, 66 S.W.3d at 249
    . It is invoked to
    determine whether a dispute has matured to the point that warrants a decision. 
    Id. The central
    concern is whether the case involves uncertain or contingent future
    events that may not occur as anticipated or may not occur at all. 
    Id. Ripeness requires
    a concrete injury. Waco Indep. Sch. Dist. v. Gibson, 
    22 S.W.3d 849
    , 851 (Tex. 2000). A case is not ripe if determining whether the
    plaintiff has a concrete injury depends on contingent or hypothetical facts, or upon
    events that have not yet come to pass. 
    Id. at 852.
    The facts must be sufficiently
    developed so that an injury has occurred or is imminent. See 
    id. at 851–52.
    A case
    that was unripe when initially filed can be become ripe by subsequent events. See
    
    Perry, 66 S.W.3d at 251
    –52.
    6
    C.    Ripeness Doctrine Applied to Regulatory Taking and Chapter 245
    Claims
    A court cannot determine if a regulation has gone “too far” unless it knows
    how far the regulation goes. Mayhew v. Town of Sunnyvale, 
    964 S.W.2d 922
    , 929
    (Tex. 1998). In other words, a court cannot determine whether a taking has
    occurred until the court can compare the uses prohibited by the regulation to any
    permissible uses that may be made of the affected property. 
    Id. Accordingly, for
    a
    regulatory taking claim to be ripe, there must be a “final decision regarding the
    application of the regulations to the property at issue.” 
    Id. A final
    decision usually requires both a rejected development plan and the
    denial of a variance from the controlling regulations. 
    Id. The variance
    requirement
    is applied flexibly to serve its purpose of giving the government an opportunity to
    grant different forms of relief or make policy decisions which might abate the
    alleged taking. 
    Id. at 930.
    Thus, a landowner is not required to make futile variance
    requests or permit applications. See 
    id. at 929.
    The ripeness doctrine does not
    require a landowner to seek permits for development that the landowner does not
    deem economically viable or to make development proposals that the landowner
    would never actually develop. 
    Id. at 932
    (holding that the landowner who had
    requested development of 3,600 units was not required to make a subsequent
    request for a variance to develop 3,600 units when the town “clearly” was not
    going to approve a development proposal for 3,600 units).
    Furthermore, a taking claim may be ripe regardless of whether a party has
    had a development plan rejected and a variance denied if (1) a party has alleged or
    demonstrated a concrete injury and (2) the regulation does not allow for the
    exercise of discretion or the application of a variance. See City of Houston v. HS
    Tejas, Ltd., No. 01-11-00431-CV, 
    2012 WL 682298
    , at *4 (Tex. App.—Houston
    7
    [1st Dist.] Mar. 1, 2012, no pet.) (mem. op.); City of Houston v. Norcini, 
    317 S.W.3d 287
    , 293–95 (Tex. App.—Houston [1st Dist.] 2009, pet. denied); see also
    Palazzolo v. Rhode Island, 
    533 U.S. 606
    , 620 (2001) (“While a landowner must
    give a land-use authority an opportunity to exercise its discretion, once it becomes
    clear that the agency lacks the discretion to permit any development, or the
    permissible uses of the property are known to a reasonable degree of certainty, a
    taking claim is likely to have ripened.”).
    This court has held that for a declaratory judgment claim under Chapter 245
    to be ripe, the plaintiff must allege or demonstrate that an “official action” of the
    government has caused the injuries. See Tiki Island 
    I, 464 S.W.3d at 442
    . This
    court held that a claim was not ripe when the plaintiff filed a plat application and
    the municipality denied it, but (1) the record did not disclose the reasons why the
    municipality denied the application; (2) the plaintiff never asked the municipality
    to certify the reasons for the denial; (3) no plat or permit applications had since
    been denied for any specified reason; and (4) the plaintiff had not challenged the
    denial of the plat application in any proceeding. 
    Id. A plaintiff
    may have vested
    rights in a project, but there must be some context within which to declare what the
    rights are. See 
    id. at 443.
    Similarly, the Third Court of Appeals has held that, because of the statute’s
    focus on zoning rights, a plaintiff “must allege some facts to show that the city has
    applied its regulations to a particular case.” Save Our Springs All. v. City of Austin,
    
    149 S.W.3d 674
    , 683–84 (Tex. App.—Austin 2004, no pet.). “A regulatory agency
    ought to have the opportunity to make a final determination as to which set of land-
    use regulations apply to a specific plat before a court intervenes.” 
    Id. at 684.
    8
    D.      Unripe Inverse Condemnation Claim
    It is undisputed that The Commons has not had any permit or plat
    applications, or requests for variances, denied as a result of the amended ordinance.
    Indeed, the ordinance did not become effective until after the trial court denied the
    plea.
    The Commons contends that its inverse condemnation claim was “ripe upon
    enactment” because the ordinance prohibits precisely the use intended for the
    property.3 The Commons contends further that the futility exception applies for
    two reasons. First, The Commons contends that its financial hardship alone cannot
    justify a variance under the ordinance. Second, The Commons contends that it
    cannot comply with particular requirements for the application for a floodplain
    development permit because it is a developer and not a builder.
    The ordinance expressly allows for variances. See Hous., Tex., Code of
    Ordinances § 19-20. Thus, the ordinance is not like the one faced in Norcini, HS
    Tejas, and similar cases. The ordinance in those cases prohibited construction in
    the floodway and left no room for discretion by the City. See, e.g., 
    Norcini, 317 S.W.3d at 295
    . Accordingly, those cases are inapplicable to the facts here.
    The ordinance provides that “a variance may be sought only on the basis that
    the imposition of the requirements of this chapter for the issuance of a permit to the
    applicant constitutes an exceptional hardship.” Hous., Tex., Code of Ordinances
    § 19-20(a). The ordinance does not prohibit the granting of a variance based on
    financial hardship. The ordinance asks an applicant to describe the “estimated cost
    in dollars of complying with the requirement,” and the “estimated cost in dollars of
    construction by the proposed alternative.” See 
    id. § 19-20(b)(5)(6).
    Thus, financial
    3
    See Hallco Tex. Inc. v. McMullen Cty., 
    221 S.W.3d 50
    , 60 (Tex. 2006) (plurality op.).
    9
    considerations of the landowner are factors that the City may consider. The
    Commons’ reliance on cases addressing what is an “unnecessary” hardship to
    avoid zoning regulations are inapplicable. See Bd. of Adjustments of City of Piney
    Point Vill. v. Solar, 
    171 S.W.3d 251
    , 255 (Tex. App.—Houston [14th Dist.] 2005,
    pet. denied); see also Tex. Loc. Gov’t Code § 211.009(a)(3).
    The Commons suggests that it cannot comply with the requirements of
    applying for a floodplain development permit because such applications require
    The Commons to show the “proposed structures . . . drawn to scale.” See Hous.,
    Tex., Code of Ordinances § 19-18(a)(2). The Commons contends that the nature of
    its business—development rather than building—means any application for a
    permit would be “purely hypothetical.”
    Nothing prevents The Commons from seeking—and the City from
    granting—a variance notwithstanding The Commons’ failure to show on the
    application residential buildings drawn to scale. The Commons would not need to
    submit detailed plans for structures, i.e., residential buildings, if The Commons
    does not intend to build them. See 
    Mayhew, 964 S.W.2d at 932
    (holding that a
    taking claim was ripe after it was clear the municipality would not approve
    development at the level requested by the landowner; reasoning that a landowner is
    not required to seek permits that the landowner does not deem economically
    viable, nor is a landowner required to expend time and resources pursuing a
    development proposal that the landowner will “never actually develop”).
    The purpose of the “final decision” requirement, usually evidenced through
    the denial of a permit, is to determine the “application of the regulations to the
    property at issue.” 
    Id. at 929.
    The Commons’ application must be sufficient for the
    City to make the determination of whether the regulations will bar residential
    construction below two feet above the 500-year flood elevation. The Commons
    10
    need only follow “reasonable and necessary” steps to allow the City to exercise its
    discretion. See 
    Palazzolo, 533 U.S. at 620
    –21. If the City were to unreasonably
    withhold a final decision from The Commons regarding minimum elevation, the
    claim could ripen because subsequent applications or variance requests might be
    futile. See 
    Mayhew, 964 S.W.2d at 932
    ; see also 
    Palazzolo, 533 U.S. at 621
    (“Government authorities, of course, may not burden property by imposition of
    repetitive or unfair land-use procedures in order to avoid a final decision.”).
    Based on this record, however, the futility exception does not apply. The
    permissible uses of The Commons’ property is not known to a reasonable degree
    of certainty. The Commons must give the City an opportunity to exercise its
    discretion. See 
    Palazzolo, 533 U.S. at 620
    . Because The Commons has not yet
    done so, the inverse condemnation claim is not ripe.
    E.    Unripe Chapter 245 Claim
    Similar concerns compel a holding that The Commons’ request for a
    declaratory judgment under Chapter 245 is unripe. The Commons contends,
    however, that the email exchange with one of the City’s engineers shows that the
    City has finally decided that Chapter 245 is inapplicable. We disagree with The
    Commons.
    The email exchange is not the type of “official action” contemplated in the
    Village of Tiki Island cases. Compare Tiki Island 
    I, 464 S.W.3d at 442
    (holding
    that the Chapter 245 claim was not ripe because the landowner failed to
    demonstrate that an official action of the municipality caused injuries when the
    record failed to show why the municipality denied an earlier plat application; the
    landowner did not request certified reasons for the denial; no plat or permit
    applications had since been denied for any specified reasons; and the landowner
    had not challenged the denial of the plat application in any proceeding), with Vill.
    11
    of Tiki Island v. Premier Tierra Holdings, Inc. (Tiki Island II), 
    555 S.W.3d 738
    ,
    749 (Tex. App.—Houston [14th Dist.] 2018, no pet.) (holding that the claim was
    ripe when the municipality denied the landowner’s plat applications three times
    based on substantially the same reasons, and the record showed that the parties
    engaged in extensive negotiations and that the municipality had multiple
    opportunities to determine the existence and extent of the landowner’s vested
    rights).
    In the email, The Commons asked a general question about unspecified
    tracts of land without providing any details about the prior plan, plat, or permit
    applications that had been filed for The Crossing. The City’s employee clarified
    that she was “not an attorney” and gave a general answer. She offered to follow-up
    and get more information if the answer did not help. But The Commons did not
    respond with a request for more information or make any specific request to have
    Chapter 245 applied to The Crossing. We conclude that the email exchange is no
    evidence that the City has made a final decision to apply the new ordinance to The
    Commons’ property. See Tiki Island 
    I, 464 S.W.3d at 442
    ; Save Our Springs
    
    Alliance, 149 S.W.3d at 683
    –84. Under these circumstances, the Chapter 245 claim
    is not ripe. 4
    4
    We need not reach the question of whether a claim for a declaratory judgment under
    Chapter 245 is only ripe if a permit application has been denied. Compare City of Glenn Heights
    v. Sheffield Dev. Co., 
    55 S.W.3d 158
    , 166 (Tex. App.—Dallas 2001, pet. denied) (“It is clear
    from the correspondence in the record that a controversy existed over which ordinance should
    apply to the development of the subject property, and there is no indication chapter 245 requires
    a plat application formally be denied before a court can determine the parties’ zoning rights.”),
    with Save Our Springs 
    All., 149 S.W.3d at 683
    –84 (disagreeing with Sheffield; “The individual
    and particular nature of this statutory scheme requires that individual permits be issued or denied
    for a controversy to be ripe for adjudication.”). That is, we do not hold in this case that the sole
    method of ripening a claim under Chapter 245 is to have a permit denied. The Commons has
    neither had a permit denied nor obtained any other official decision from the City regarding the
    application of Chapter 245 to The Crossing. Thus, under the particular facts of this case, the City
    has not had any opportunity to determine the existence or extent of The Commons’ vested rights.
    12
    IV.    CONCLUSION
    Considering the pleadings and undisputed facts, we hold that The Commons’
    claims are not ripe. Thus, the trial court erred by denying the City’s plea to the
    jurisdiction. We sustain the City’s issue, reverse the trial court’s order, and render
    a judgment that The Commons’ claims are dismissed without prejudice. See Tiki
    Island 
    I, 464 S.W.3d at 243
    –44.
    /s/    Ken Wise
    Justice
    Panel consists of Chief Justice Frost and Justices Wise and Hassan.
    Cf. Tiki Island 
    II, 555 S.W.3d at 749
    (ripe claim when the municipality had the opportunity to
    determine the existence and extent of the landowner’s vested rights).
    13