James Construction Group, LLC, Primoris Services Corporation v. Westlake Chemical Corporation ( 2019 )


Menu:
  • Affirmed as Modified, and Majority and Concurring and Dissenting Opinions
    filed December 17, 2019.
    In The
    Fourteenth Court of Appeals
    NO. 14-18-00083-CV
    JAMES CONSTRUCTION GROUP, LLC AND PRIMORIS SERVICES
    CORPORATION, Appellants/Cross-Appellees
    V.
    WESTLAKE CHEMICAL CORPORATION, Appellee/Cross-Appellant
    On Appeal from the 334th District Court
    Harris County, Texas
    Trial Court Cause No. 2014-72717
    MAJORITY OPINION
    James Construction Group, LLC (“James”), Primoris Services Corporation
    (“Primoris”), and Westlake Chemical Corporation (“Chemical”) appeal a judgment
    adjudicating their respective contract claims, which arose out of a construction
    agreement between Chemical and James. Following a jury trial, the trial court signed
    a judgment awarding Chemical $1,157,019.50 in breach-of-contract damages
    against James and Primoris, jointly and severally, and $2,923,600.50 in attorney’s
    fees against Primoris only. The judgment also awards James $1,270,962.89 in
    breach-of-contract damages against Chemical on James’s counterclaim. Each party
    raises multiple issues on appeal. For the reasons explained below, we modify the
    judgment and affirm the judgment as modified.
    General Background
    Chemical and James signed a construction contract providing for James to
    perform over $500 million in civil and mechanical construction work at a chlor-
    alkali chemical plant owned by Westlake Vinyls Company, L.P. (“Vinyls”).
    Although Chemical signed the contract in its own name, Vinyls authorized Chemical
    to sign it on Vinyls’s behalf, and the jury found that Chemical was acting as Vinyls’s
    agent in entering the contractual relationship.       In a separate agreement (the
    “Guaranty”), James’s parent company, Primoris, unconditionally guaranteed
    James’s performance under the construction contract.
    Following various disputes during the project Chemical filed this lawsuit, and
    the parties asserted breach-of-contract claims against each other.          We first
    summarize the general nature of the claims at issue and then detail additional
    pertinent facts in connection with their related issues.
    A.    Summary of Chemical’s claims
    Chemical’s claims against James mainly involve allegations that James
    breached contract provisions requiring it to perform work safely and to compensate
    Chemical for remedial or termination costs resulting from unsafe work. Chemical
    contends that due to James’s safety violations Chemical intervened and terminated
    some or all of James’s scope of work in accordance with Chemical’s contract rights.
    Chemical sought to recover damages allegedly incurred in exercising those rights
    and hiring others to complete the job.
    2
    Chemical’s claims are grounded on two key contract provisions.            First,
    paragraph 17.2, entitled “Inspection and Intervention,” provides that Chemical may
    “intervene in any appropriate way” if, in its reasonable opinion, James performs its
    contractual duties in an unsafe manner. In that instance, Chemical has the right to
    require James to take immediate remedial action to Chemical’s satisfaction. James
    is solely accountable for all costs associated with such intervention and remedial
    action, whether those costs are incurred by Chemical, James, or any third party.
    Another section, paragraph 21, applies to “Termination and Substitute
    Performance.”     Specifically, paragraph 21.3 enumerates Chemical’s right to
    terminate the contract for James’s default, including for serious safety violations.
    Paragraph 21.3 sets forth the relevant contractual sequence of events as follows: if
    Chemical determines in its reasonable opinion that James has “serious safety
    violations,” then Chemical may so notify James. Upon notification, James must
    begin to remedy the defect cited within a certain period. If Chemical is not
    reasonably satisfied with the pace or quality of the remediation effort, Chemical
    must notify James of that fact and may elect to terminate the contract or a portion of
    the work by providing notice to that effect. After providing notice, Chemical has
    the right to take unrestricted possession of the work or portion terminated and pay
    for its completion. Any extra cost in excess of the contract price incurred by
    Chemical in completing the terminated work is at James’s expense.
    Chemical also asserts a claim under the contract’s indemnity provision,
    paragraph 19.1. Chemical avers that James’s employee died while performing work
    under the contract, that Chemical incurred expenses in defending a wrongful-death
    claim asserted by the employee’s family, and that James breached paragraph 19.1
    by failing to indemnify Chemical for its costs resulting from the claim.
    3
    At trial, Chemical contended its damages resulting from James’s breaches
    exceeded $8.5 million.
    Finally, Chemical sued Primoris for breach of the Guaranty, contending that
    Primoris was liable for all contract damages owed by James.
    B.    Summary of James’s claims
    James’s counterclaims also rest in part on paragraph 21.3. James alleges that
    Chemical breached paragraph 21.3 by (1) improperly terminating James’s work
    because Chemical’s grounds for termination were unreasonable, and (2) failing to
    provide the notice paragraph 21.3 requires.
    James also contends that Chemical violated paragraph 26 of the contract,
    which is entitled “Waiver of Consequential Damages” and states among other things
    that neither party shall be liable to the other for any “consequential, incidental,
    indirect or punitive damages of any kind or character,” and “no claim shall be made”
    by either party against the other for such damages regardless of the legal theory
    supporting the claim. According to James, all of Chemical’s asserted contract
    damages are consequential in nature and barred by paragraph 26.
    C.    Summary of the jury findings and judgment
    Following a multi-week trial, a jury made the following relevant findings:
    1.    Chemical entered into the construction contract in its own name but
    with authority to act on behalf and for the benefit of Vinyls. The jury
    also found that James was estopped from denying that Chemical
    entered into the construction contract with Vinyls’s authority and on
    Vinyls’s behalf.
    2.    James failed to comply with paragraph 17.2, the “intervention”
    provision. The jury awarded Chemical $1,054,251.81 as a result of this
    breach.
    4
    3.       James failed to comply with paragraph 21.3, the “termination”
    provision; and Chemical substantially complied with that paragraph’s
    notice provisions. The jury awarded Chemical $1,054,251.81 as a
    result of this breach.1 Due to the jury’s findings in Chemical’s favor, it
    did not answer a series of questions on James’s counterclaims under
    paragraph 21.3.
    4.       James failed to comply with paragraph 19.1, the “indemnity” provision.
    The jury awarded Chemical $102,767.69 as a result of this breach.
    5.       Chemical incurred $2,923,600.50 in reasonable and necessary
    attorney’s fees through trial and would incur up to an additional
    $450,000 in attorney’s fees in the event of appeal.
    6.       Chemical failed to comply with paragraph 26, the waiver of
    consequential damages provision. The damages awarded for this
    breach were divided into two categories. The jury awarded James
    $238,778.26 for attorney’s fees incurred in defending against “chlorine
    costs” asserted by Chemical.2 Additionally, the jury awarded James a
    total of $1,032,184.63 for attorney’s fees incurred through trial (plus
    $62,500 in appellate fees) in defending against “consequential damages
    other than chlorine costs” asserted by Chemical.
    After several post-verdict motions, the trial court signed an amended
    judgment incorporating the above findings.                The judgment grants recovery to
    Chemical against James and Primoris, jointly and severally, for contract damages of
    $1,157,019.50, plus interest and taxable court costs. The judgment grants recovery
    to Chemical for its attorney’s fees of $2,923,600.50 against Primoris only, based on
    the Guaranty, plus conditional appellate attorney’s fees.3 The judgment grants
    1
    These were the same damages awarded in connection with James’s breach of paragraph
    17.2.
    2
    Prior to trial, the trial court granted James partial summary judgment on its consequential-
    damages counterclaim and determined that several million dollars in “chlorine costs” Chemical
    sought were barred by paragraph 26. Chemical agrees that the “chlorine costs” it asserted are
    barred, and Chemical does not challenge this summary-judgment ruling on appeal.
    3
    The trial court refused to enter judgment against James for Chemical’s attorney’s fees
    incurred in pursuing its contract claims because James is a limited liability company. See Tex.
    Civ. Prac. & Rem. Code § 38.001 (permitting recovery of attorney’s fees from an individual or
    5
    recovery to James against Chemical for contract damages of $1,270,962.89, plus
    conditional attorney’s fees on appeal. All parties timely appealed.
    Issues Presented
    James and Primoris present seven issues for review. Because many of their
    arguments overlap, we refer to James and Primoris collectively as “appellants” when
    discussing their joint contentions. In their first three issues, appellants argue that the
    trial court erred in rendering judgment for Chemical on Chemical’s claims under the
    contract’s termination (paragraph 21.3), intervention (paragraph 17.2), and
    indemnification (paragraph 19.1) provisions. In issues four and five, Primoris
    challenges the trial court’s award of attorney’s fees to Chemical. James urges in
    issue six that the trial court erred in refusing to award it prejudgment interest on its
    counterclaim for breach of paragraph 26. Finally, in issue seven James complains
    that the trial court erred in rendering a take-nothing judgment in Chemical’s favor
    on James’s counterclaim under paragraph 21.3.
    Chemical challenges the judgment in two cross-issues.                First, Chemical
    contends the trial court erred in rendering judgment for James on James’s
    counterclaim for breach of paragraph 26. Second, Chemical argues that the trial
    court erred in holding only Primoris liable for Chemical’s attorney’s fees, when
    James should be liable for the fees as well.
    We begin with appellants’ complaints.
    corporation for certain claims); Vast Constr., LLC v. CTC Contractors, LLC, 
    526 S.W.3d 709
    , 728
    (Tex. App.—Houston [14th Dist.] 2017, no pet.) (holding attorney’s fees may not be recovered
    from an LLC under chapter 38); Alta Mesa Holdings, L.P. v. Ives, 
    488 S.W.3d 438
    , 452-55 (Tex.
    App.—Houston [14th Dist.] 2016, pet. denied) (same).
    6
    Analysis
    Appellants’ Issues
    A.    Termination — Paragraph 21.3
    In issue one, appellants challenge the judgment against them on Chemical’s
    claim for breach of the contract’s termination provision. Appellants contend that:
    (1) no evidence supports the jury’s liability finding; (2) Chemical failed to comply
    with all conditions precedent to its right to terminate the contract for default and
    recover damages because it did not strictly comply with paragraph 21.3’s notice
    provisions, and alternatively the jury’s substantial compliance findings regarding
    notice are unsupported by evidence or pleading; and (3) the jury’s damage awards
    are either unsupported by evidence or barred by paragraph 26.
    1.     Standards of review
    When reviewing the legal sufficiency of the evidence, we view the evidence
    in the light most favorable to the judgment and indulge every reasonable inference
    that would support it. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 822 (Tex. 2005).
    We credit favorable evidence if a reasonable fact finder could and disregard contrary
    evidence unless a reasonable fact finder could not. 
    Id. at 807,
    827; Vast 
    Constr., 526 S.W.3d at 719
    . If there exists more than a scintilla of evidence to support the
    judgment, we must uphold it. Coffman v. Melton, 
    448 S.W.3d 68
    , 71 (Tex. App.—
    Houston [14th Dist.] 2014, pet. denied). More than a scintilla of evidence exists
    when the evidence supporting the finding rises to a level that would enable
    reasonable and fair-minded people to differ in their conclusions. 
    Id. We sustain
    a legal sufficiency or “no evidence” challenge only when: (1) the
    record discloses a complete absence of evidence of a vital fact; (2) the court is barred
    by rules of law or of evidence from giving weight to the only evidence offered to
    7
    prove a vital fact; (3) the evidence offered to prove a vital fact is no more than a
    mere scintilla; or (4) the evidence establishes conclusively the opposite of the vital
    fact. Regal Fin. Co. v. Tex Star Motors, Inc., 
    355 S.W.3d 595
    , 603 (Tex. 2010)
    (citing Merrell Dow Pharms., Inc. v. Havner, 
    953 S.W.2d 706
    , 711 (Tex. 1997)).
    We apply this standard mindful that the jury is the sole judge of the credibility of the
    witnesses and the weight to be given to their testimony. See City of 
    Keller, 168 S.W.3d at 819
    , 822.
    We construe contracts as a matter of law, absent ambiguity. Moayedi v.
    Interstate 35/Chisam Rd., L.P., 
    438 S.W.3d 1
    , 7 (Tex. 2014). Our primary concern
    is to ascertain and give effect to the parties’ true intentions as expressed in the
    agreement. El Paso Field Servs., L.P. v. MasTec N. Am., Inc., 
    389 S.W.3d 802
    , 805
    (Tex. 2012). We consider the entire writing and attempt to harmonize and give effect
    to all the provisions of the contract by analyzing them mindful of the whole
    agreement. See Frost Nat’l Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 311-12
    (Tex. 2005) (per curiam). “No single provision taken alone will be given controlling
    effect; rather, all the provisions must be considered with reference to the whole
    instrument.” J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex. 2003).
    2.     Legal sufficiency challenge to the liability finding
    In the first part of their first issue, appellants challenge the legal sufficiency
    of the evidence to support the jury’s liability finding in response to question 3D,
    which asked whether James breached paragraph 21.3. As relevant, paragraph 21.3
    provides:
    8
    21    TERMINATION AND SUBSTITUTE PERFORMANCE
    ...
    21.3 Right of Company to Terminate for Contractor Default. If
    [Chemical] discovers or determines, in its reasonable opinion
    that:
    ...
    21.3.2 [James] has serious safety violations; . . .
    then [Chemical] may so notify [James]. Upon receipt of any such
    notice, [James] shall begin to remedy the breach or defect cited
    within seventy-two (72) hours. If at any time, [Chemical] is not
    reasonably satisfied with the pace and the quality of the
    remediation effort, [Chemical] will so notify [James] and
    [Chemical] may thereafter, at its sole discretion, elect to either
    terminate this Contract or a portion of the Work by providing
    notice to that effect. After providing such notice, [Chemical]
    shall have the unrestricted right to take possession of the Work
    or the portion thereof terminated and to purchase and/or hire
    materials, tools, supervision, labor, and equipment for the
    completion of the Work or of the unremedied condition, as
    [Chemical] elects. Any extra costs in excess of the Contract
    Price incurred by [Chemical] in this regard shall be at the
    expense of [James]. This right is in addition to any other
    remedies [Chemical] may have hereunder.
    In question 3D, the jury was asked:
    Did James fail to comply with Section 21.3 of the Construction Contract?
    You are instructed that James failed to comply with Section 21.3 of the
    Construction Contract if all of the following circumstances occurred:
     Westlake Chemical discovered or determined in its reasonable
    opinion that James had serious safety violations, and
     Westlake Chemical was not reasonably satisfied with the pace and
    the quality of the remediation effort; and
     Westlake Chemical terminated the Construction Contract or a
    portion of the Work, and took possession of the Work or the portion
    9
    thereof terminated and purchased and/or hired materials, tools,
    supervision, labor, and equipment for the completion of the Work;
    and
     James has not paid Westlake Chemical for some or all of the extra
    costs in excess of the Contract Price incurred by Westlake Chemical
    in regards to taking possession of the Work or the portion thereof
    terminated and purchasing and/or hiring materials, tools,
    supervision, labor, and equipment for the completion of the Work.
    The jury found that James failed to comply with paragraph 21.3. In response
    to the next question, question 3E, the jury awarded Chemical $1,054,251.81 as fair
    and reasonable compensation for James’s failure to comply. The damages were
    divided into two categories:        (1) $211,836.81 in “safety training costs,” and
    (2) $842,415 in “increased foreman costs.”4
    To recover on a breach-of-contract claim, a party must prove: (1) the existence
    of a valid contract, (2) the party performed, tendered performance, or was excused
    from doing so, (3) the other party breached the contract, and (4) damages resulting
    from the breach. See Vast 
    Constr., 526 S.W.3d at 718
    n.6; Aguiar v. Segal, 
    167 S.W.3d 443
    , 450 (Tex. App.—Houston [14th Dist.] 2005, pet. denied).
    The essence of appellants’ point is that there is no evidence that Chemical
    incurred any termination costs.          Emphasizing the charge instruction that an
    affirmative answer to question 3D must be predicated on proof that the extra costs
    were “incurred by Westlake Chemical,” appellants say the jury finding is not
    supported by legally sufficient evidence because all the costs awarded were incurred
    by Vinyls, not Chemical. In response, Chemical argues that it is legally entitled to
    4
    Chemical separated its claimed damages into various categories, labelled in the jury
    charge as A-E and F1-F8. The jury awarded breach-of-contract damages in two categories, A
    (safety training costs) and D (increased foreman costs). The jury awarded no damages for the
    remaining categories.
    10
    recover damages incurred by Vinyls because Chemical is Vinyls’s agent with respect
    to the construction contract, as the jury found.5
    Appellants are correct that Vinyls incurred the termination costs underlying
    the jury’s award. Andrew Kenner, who served as vice-president of manufacturing
    for both Chemical and Vinyls, testified that Vinyls controlled the construction
    project on its property and “paid the bills.” Of the damages sought, Kenner stated
    that the only portion paid by Chemical was the cost related to the indemnification
    5
    In questions 1A and 1B, the jury was asked the following:
    Question No. 1A
    Did Westlake Chemical enter into the Construction Contract in its own
    name, to obtain construction services by James, on behalf and for the benefit of
    Westlake Vinyls, and with authority to act on behalf of Westlake Vinyls?
    Westlake Chemical had authority to act on behalf of Westlake Vinyls in
    entering into the Construction Contract with James if Westlake Chemical
    had actual authority to do so. Actual authority for Westlake Chemical to
    act for Westlake Vinyls must arise from Westlake Vinyls’ agreement that
    Westlake Chemical act on behalf and for the benefit of Westlake Vinyls.
    Question No. 1B
    Does James’s conduct preclude it from denying that Westlake Chemical
    entered into the Construction Contract in its own name, to obtain construction
    services by James, on behalf and for the benefit of Westlake Vinyls, and with
    authority to act on behalf of Westlake Vinyls?
    The law precludes James from asserting, to Westlake Chemical’s
    disadvantage, a right or position that is inconsistent with a position
    previously taken by James while it had knowledge of all material facts. This
    legal principle applies if it would be unconscionable to allow James to avoid
    corresponding obligations or effects by maintaining a position inconsistent
    with one to which it earlier acquiesced or from which it earlier accepted a
    benefit while having knowledge of all material facts.
    The jury answered “yes” to both questions. Chemical asserts without dispute that the jury’s
    affirmative answers to questions 1A and 1B establish a principal-agent relationship between
    Vinyls and Chemical with respect to the construction contract.
    11
    claim based on the death of James’s employee. He said all other damage elements
    were based on costs paid by Vinyls. Further, it is undisputed that Turner Industries,
    which replaced James as the mechanical contractor on the project, operated under a
    contract with Vinyls, not Chemical. Bryan Byrd, Chemical’s damage expert, stated
    that the payments to all major contractors, including Turner, came from Vinyls, even
    though other documents referenced Chemical. Byrd did not distinguish between
    Vinyls and Chemical for purposes of his review and considered both entities simply
    as “Westlake.”
    It is also true that Vinyls and Chemical are distinct corporate entities and they
    are correctly treated as such in the jury charge.6 But we ultimately conclude
    nonetheless that question 3D’s reference only to Chemical and not Vinyls does not
    permit us to sustain appellants’ legal sufficiency challenge under the present
    circumstances. We reach this conclusion for several reasons.
    First, appellants do not challenge the agency findings on appeal, so the
    relationship between Vinyls as principal and Chemical as agent is established
    conclusively, and we are bound by those findings. See, e.g., IKB Indus. v. Pro-Line
    Corp., 
    938 S.W.2d 440
    , 445 (Tex. 1997) (appellate courts are bound by
    unchallenged jury findings); Carbona v. CH Med., Inc., 
    266 S.W.3d 675
    , 687 (Tex.
    App.—Dallas 2008, no pet.); OXY USA, Inc. v. Cook, 
    127 S.W.3d 16
    , 21 (Tex.
    App.—Tyler 2003, pet. denied). We measure the sufficiency of the evidence by the
    charge as given. See Columbia Med. Ctr. of Las Colinas, Inc. v. Hogue, 
    271 S.W.3d 238
    , 254 (Tex. 2008); TecLogistics, Inc. v. Dresser-Rand Grp., Inc., 
    527 S.W.3d 589
    , 595 (Tex. App.—Houston [14th Dist.] 2017, no pet.). In doing so, we consider
    6
    The charge provides that “‘Westlake Chemical’ refers to Plaintiff Westlake Chemical
    Corporation.” Additionally, it defines “Westlake Vinyls” as “Westlake Chemical’s subsidiary,
    Westlake Vinyls Company, L.P.”
    12
    unchallenged and binding jury findings in one part of the charge to the extent they
    are relevant when we review the evidentiary sufficiency of other findings. See
    Venture v. UTSW DVA Healthcare, LLP, 
    559 S.W.3d 155
    , 160 (Tex. App.—Dallas
    2015) (noting unchallenged findings on prior material breach were binding and
    defeated appellant’s challenges to other findings), aff’d in part, rev’d in part on other
    grounds, 
    578 S.W.3d 469
    (Tex. 2019); see also Eagle Oil & Gas Co. v. TRO-X, L.P.,
    
    416 S.W.3d 137
    , 148-49 (Tex. App.—Eastland 2013, pet. denied) (reviewing legal
    sufficiency challenge, court examined instructions from charge as a whole, not only
    instructions in the question at issue; charge as a whole was pertinent to issue). We
    thus consider the jury’s agency findings and their legal consequences in our no-
    evidence review of question 3D, and appellants do not contend that we should do
    otherwise.
    As an agent, Chemical is Vinyls’s fiduciary. Johnson v. Brewer & Pritchard,
    P.C., 
    73 S.W.3d 193
    , 200 (Tex. 2002) (agency is special relationship that gives rise
    to a fiduciary duty); see Robles v. Consol. Graphics, Inc., 
    965 S.W.2d 552
    , 558 n.4
    (Tex. App.—Houston [14th Dist.] 1997, pet. denied); Rauscher Pierce Refsnes, Inc.
    v. Great Sw. Sav., F.A., 
    923 S.W.2d 112
    , 115-16 (Tex. App.—Houston [14th Dist.]
    1996, no writ); West v. Touchstone, 
    620 S.W.2d 687
    , 690 (Tex. App.—Dallas 1981,
    writ ref’d n.r.e.) (“the relationship between an agent and principal is a fiduciary
    one”); Restatement (Third) of Agency § 1.01 (2006). Once the principal-agent
    relationship is established, the agent’s acts are the principal’s acts for the limited
    purpose and scope of the agency relationship authorized by the principal. What a
    principal does through an agent it does itself. Shaw v. Kennedy, Ltd., 
    879 S.W.2d 240
    , 245 (Tex. App.—Amarillo 1994, no writ). Thus, agent and principal generally
    are considered one and the same with respect to acts within the relationship’s scope.
    See Holloway v. Skinner, 
    898 S.W.2d 793
    , 795 (Tex. 1995) (stating that agent cannot
    13
    tortiously interfere with principal’s contract because agent and principal are “one
    and the same”).
    As the jury found, Chemical signed the construction contract on behalf and
    for the benefit of Vinyls. Historically in Texas, agents cannot sue on contracts
    entered into on their principal’s behalf. See Tinsley v. Dowell, 
    26 S.W. 946
    , 948
    (Tex. 1894). But the Supreme Court of Texas has long recognized four exceptions
    to this rule: (1) when the agent contracts in his own name; (2) when the principal is
    undisclosed; (3) when the agent is authorized to act as owner of the property; and
    (4) when the agent has an interest in the contract’s subject matter. 
    Id. The first
    exception applies here because Chemical undisputedly signed the construction
    contract in its own name. An agent may sue in his own name when the agent
    contracts in his own name. See Perry v. Breland, 
    16 S.W.3d 182
    , 187 (Tex. App.—
    Eastland 2000, pet. denied).7 In Texas, a contracting agent’s right to enforce a
    contract on the principal’s behalf has arisen in the context of standing challenges,8
    and in response to arguments that the principal is an indispensable party.9 In each
    circumstance, courts have held that an agent who is a contracting party may sue in
    7
    See also Restatement (Second) of Agency §§ 363, 364 (1958) (“A person with whom an
    agent makes a contract on behalf of a principal is subject to liability in an action brought thereon
    by the agent in his own name on behalf of the principal if the agent is a party promisee.”). This is
    true not only in Texas but in other jurisdictions as well. E.g., Curo Enters. v. Dunes Residential
    Servs., Inc., 
    51 Kan. App. 2d 77
    , 
    342 P.3d 948
    (2015) (agent may sue in own name to enforce
    contract made on principal’s behalf); Barclae v. Zarb, 
    300 Mich. App. 455
    , 
    834 N.W.2d 100
    (2013) (same); Earl Fruit Co. v. Herman, 
    90 Cal. App. 640
    , 644-45 (1928) (“The right of an agent
    to sue on a contract which has been entered into in his own name has met with universal
    recognition.”).
    8
    See 
    Perry, 16 S.W.3d at 187-88
    ; see also Kakahadze v. M5 Int’l Co., No. H-12-3701,
    
    2014 WL 2547767
    , at *3-4 (S.D. Tex. June 5, 2014) (rejecting standing challenge based on agent’s
    right to assert contract claim under Texas law).
    9
    See Cleveland v. Heidenheimer, 
    46 S.W. 30
    , 32 (Tex. 1898); Tex. Gas Corp. v. Hankamer,
    
    326 S.W.2d 944
    , 958-59 (Tex. App.—Houston 1959, writ ref’d n.r.e.) (agent that “contracted in
    his own name” when selling gas and distillate of another company to defendants was entitled to
    “sue in his own name”).
    14
    the agent’s own name on the principal’s behalf. Thus, when, as here, the agent is a
    party to a contract for a disclosed principal, the agent may sue on the contract in the
    agent’s name, the principal’s name, or both. See Restatement (Third) of Agency
    § 6.01 cmt. e (2005). Chemical, the named plaintiff, pleaded that it brought suit as
    agent of Vinyls and on Vinyls’s behalf.
    More to the point, an agent’s right to enforce the contract by legal action on
    the principal’s behalf includes the right to recover damages suffered by the principal
    alone. See Restatement (Second) of Agency § 364 cmt. k (“If the agent brings an
    action in his own name but on account of the principal, he sues as a fiduciary and
    hence he recovers the full measure of damages although he is personally caused no
    pecuniary loss by the failure of the third person to perform.”); see also Brooks v.
    Hollaar, 
    297 P.3d 125
    , 129 (Alaska 2013) (agent may sue on contract in own name
    to recover principal’s damages) (citing Restatement (Second) of Agency § 364 cmt.
    k).10 In a non-precedential opinion, Texas Utilities Fuel Co. v. Marathon Oil Co.,
    No. 11-98-00079-CV, 
    2000 WL 34234653
    (Tex. App.—Eastland Mar. 9, 2000, no
    pet.) (not designated for publication),11 Texas Utilities Fuel Company (“TUFCO”)
    contracted to purchase gas from the defendant Marathon, but the gas was to benefit
    and be used by TUFCO’s sister company, Texas Utilities Electric Company (“TU
    Electric”). TUFCO sued on the contract, claiming Marathon breached. The trial
    court granted summary judgment for Marathon on the ground that TUFCO suffered
    no damages because TUFCO was reimbursed by TU Electric for its costs in
    supplying gas to TU Electric. 
    Id. at *9.
               Marathon argued that TU Electric was
    never mentioned in the pleadings, and that “the pleadings seek only damages
    10
    We are treating the cited Restatement section and comment as persuasive authority rather
    than controlling authority. Tex. Civ. Prac. & Rem. Code § 5.001(b).
    11
    See Tex. R. App. P. 47.7(b).
    15
    claimed to have been suffered directly by TUFCO, not TU Electric.” 
    Id. The court
    of appeals reversed the summary judgment. The court noted that although TUFCO
    sued in its own name, the record showed it was acting as the agent of TU Electric.
    
    Id. “At the
    very least,” the court said, “this summary judgment evidence creates a
    fact issue as to whether TUFCO purchased gas under the contract as TU Electric’s
    agent.” 
    Id. The court
    held that if TUFCO purchased the gas as an agent for TU
    Electric, TUFCO could still bring the lawsuit because “an agent who is a party
    promisee on a contract made by him on behalf of his principal may bring suit on that
    contract in his own name.” 
    Id. (citing Lubbock
    Feed Lots, Inc. v. Iowa Beef
    Processors, Inc., 
    630 F.2d 250
    , 258 (5th Cir. 1980)). We conclude that Chemical
    may sue on Vinyls’s behalf to recover contract damages even though Vinyls alone
    incurred them.
    Appellants neither present contrary authority nor dispute the legal effect of
    the jury’s agency findings. They characterize the agency findings as irrelevant, but
    we disagree. Chemical’s status as Vinyls’s agent, coupled with Chemical’s signing
    of the construction contract in its own name, means that Chemical is a party to the
    contract; that Vinyls is a party to the contract;12 that Chemical is entitled to sue on
    the contract in Vinyls’s name, in Chemical’s name, or both; and that Chemical may
    recover in its own name Vinyls’s damages.13 We have not located and the parties
    have not cited a case involving this issue that proceeded to jury verdict, so we have
    no guide against which to compare the present charge instructions when an agent
    sues to recover damages incurred only by the principal. But no party claims the
    12
    Latch v. Gratty, 
    107 S.W.3d 543
    , 546 (Tex. 2003) (citing Restatement (Second) of
    Agency § 186 cmt. c (“The principal becomes a party to the transaction only if it is proved that the
    agent intended to act upon his account.”)); see also Restatement (Third) of Agency § 6.01
    (disclosed principal is party to contract signed by principal’s agent with authority).
    13
    See Restatement (Second) of Agency § 364 cmt. k; Tex. Utils. Fuel Co., 
    2000 WL 34234653
    , at *9.
    16
    instruction accompanying question 3D is defective in wording, and it contains
    language consistent with the effect of the jury’s agency findings in questions 1A and
    1B. Based on those findings, Vinyls and Chemical are considered one and the same
    at least for the purpose of enforcing the contract rights at issue. See 
    Holloway, 898 S.W.2d at 795
    .14 If Chemical can sue in its own name to recover Vinyls’s damages,
    then it is entitled to a jury question in its own name to secure a judgment in its own
    name. Otherwise, there would be little point to recognizing a contracting agent’s
    right to sue in its own name to recover the principal’s contract damages. Chemical
    recovers as Vinyls’s fiduciary15 or trustee,16 and thus the recovery is rightfully
    Vinyls’s—a result not materially different than if question 3D had referred to costs
    “incurred by Westlake Vinyls” instead of “incurred by Westlake Chemical.”
    For these reasons, we overrule appellants’ legal-sufficiency challenge to the
    jury’s finding in response to question 3D.
    3.       Challenge to findings that Chemical substantially complied with notice
    conditions
    In the next part of their first issue, appellants contend that Chemical may not
    recover under paragraph 21.3 because it failed to strictly comply with that
    paragraph’s notice provisions, which they claim are conditions precedent to recovery
    14
    The jury heard Byrd explain that he did not distinguish between Vinyls and Chemical
    but considered them both as one entity, “Westlake.” Had the jury answered “no” to questions 1A
    and 1B, we would agree that appellants should prevail on their first issue because the instruction
    submitted with question 3D referred only to whether Chemical, not Vinyls, incurred damages.
    That Chemical incurred no damages generally would be fatal to recovery on this charge, but it is
    not so here because Chemical secured agency findings, which allow Chemical to recover Vinyls’s
    contract damages in Chemical’s name.
    15
    
    Johnson, 73 S.W.3d at 200
    ; see 
    Robles, 965 S.W.2d at 558
    n.4.
    16
    See Small v. Ciao Stables, Inc., 
    289 Md. 554
    , 568, 
    425 A.2d 1030
    , 1038 (1981) (“The
    agent who is authorized to sue in his own name on behalf of his principal ‘recovers as trustee for
    his principal.’” (quoting U.S. Telegraph Co. v. Gildersleve, 
    29 Md. 232
    , 245, 246 (1868))).
    17
    for breach. Alternatively, appellants argue that to the extent Chemical may satisfy
    paragraph 21.3’s notice requirements by substantial compliance, the evidence is
    legally insufficient to support the jury’s findings that Chemical substantially
    complied.17
    a.     Strict compliance versus substantial compliance
    In questions 3A, 3B, and 3C, the jury found that Chemical substantially
    complied with each of the three notice provisions referenced in paragraph 21.3.18
    The jury instruction regarding substantial compliance was the same in each question,
    though tailored to the substance of each relevant notice:
    Answer “Yes” or “No” as to each of the following grounds on which
    you may find that Westlake Chemical provided notice regarding this
    notice provision of Section 21.3 of the Construction Contract:
    ...
    17
    Appellants also contend that the jury questions on substantial compliance are
    unsupported by Chemical’s pleading. Chemical pleaded that all conditions precedent to recovery
    had occurred or been performed. Appellants specifically denied this allegation, thus placing on
    Chemical the burden to prove that the conditions put into issue by appellants’ denial had in fact
    occurred. See U.S. Tire-Tech, Inc. v. Boeran, B.V., 
    110 S.W.3d 194
    , 200 (Tex. App.—Houston
    [1st Dist.] 2003, pet. denied) (when defendant specifically denied condition precedent of notice,
    plaintiff required to prove notice at trial). Substantial compliance with a contract requirement is
    the legal equivalent of full compliance. Telles v. Vasconcelos, 
    417 S.W.2d 491
    , 494 (Tex. App.—
    El Paso 1967, writ ref’d n.r.e.). As this court and others have stated, a party’s averment that all
    conditions precedent have occurred or have been performed will support the submission of a
    question or instruction on substantial performance. Geotech Energy Corp. v. Gulf States
    Telecomms. & Info. Sys., Inc., 
    788 S.W.2d 386
    , 390 (Tex. App.—Houston [14th Dist.] 1990, no
    writ); Zion Missionary Baptist Church v. Pearson, 
    695 S.W.2d 609
    , 611 (Tex. App.—Dallas 1985,
    writ ref’d n.r.e.); Del Monte Corp. v. Martin, 
    574 S.W.2d 597
    , 599 (Tex. App.—San Antonio 1978,
    no writ). We therefore reject appellants’ argument that the jury submissions regarding substantial
    compliance are not supported by Chemical’s petition.
    18
    The jury also found that Chemical did not strictly comply with the first two notice
    provisions, and that strict compliance with those provisions would not have been futile. Chemical
    does not challenge these findings. The jury was not asked whether Chemical strictly complied
    with the third notice provision.
    18
    Westlake Chemical notified James in “substantial compliance” with
    this notice provision?
    You are instructed that Westlake Chemical notified James in
    “substantial compliance” with this notice provision if all of the
    following circumstances occurred:
    • James received actual notice from Westlake Chemical that
    [Question 3A] Westlake Chemical had discovered or
    determined, in its reasonable opinion, that James had
    serious safety violations
    [Question 3B] Westlake Chemical was not reasonably
    satisfied with the pace and the quality of the remediation
    effort
    [Question 3C] Westlake Chemical had elected in its sole
    discretion to terminate the Construction Contract or a
    portion of the Work, and
    • the form of actual notice to James did not severely impair
    the purpose of this notice provision and caused no harm to
    James.
    Answer “Yes” or “No.”
    Answer:       Yes
    Appellants contend that Texas law mandates strict compliance with notice
    provisions in construction contracts. This contract requires notices to be written.19
    19
    Paragraph 9.1 provides:
    Notices. Any notice, approval or other communication given pursuant to
    this Contract shall be in writing and shall be deemed duly served and given (i) when
    received after being delivered by hand or overnight delivery service, (ii) when
    telecopied, with confirmation of receipt, to the facsimile number shown below,
    (iii) upon receipt when sent by certified or registered mail (return receipt
    requested), or (iv) by electronic mail to the Parties at their addresses as follows:
    [spaces for names, phone numbers, fax numbers, and email addresses are left blank]
    (emphasis added).
    19
    Because no notices were communicated in writing, appellants argue that Chemical
    did not strictly comply with the notice conditions, and consequently appellants
    cannot be liable for breach. Appellants do not contend that Chemical failed to
    strictly comply in any other respect. According to appellants, the jury’s substantial
    compliance findings are therefore immaterial. Appellants cite this court’s decisions
    in Arbor Windsor Court, Ltd. v. Weekley Homes, LP, 
    463 S.W.3d 131
    , 136-41 (Tex.
    App.—Houston [14th Dist.] 2015, pet. denied); Cajun Constructors, Inc. v. Velasco
    Drainage District, 
    380 S.W.3d 819
    , 825-26 (Tex. App.—Houston [14th Dist.] 2012,
    pet. denied); and Emerald Forest Utility District v. Simonsen Construction Co., 
    679 S.W.2d 51
    , 54 (Tex. App.—Houston [14th Dist.] 1984, writ ref’d n.r.e.). Appellants
    also cite Ogden v. Gibraltar Savings Association, 
    640 S.W.2d 232
    , 233-34 (Tex.
    1982), and Shumway v. Horizon Credit Corp., 
    801 S.W.2d 890
    , 893 (Tex. 1991), in
    support of the proposition that Texas courts consistently require strict compliance
    with written-notice requirements attendant to contractual forfeiture and termination
    provisions.
    In turn, Chemical insists that Texas law recognizes the doctrine of substantial
    compliance with respect to contractual notice provisions. Chemical cites three
    Dallas Court of Appeals opinions—Burlington Northern Railroad Co. v. General
    Projection Systems, Inc., No. 05-97-00425-CV, 
    2000 WL 1100874
    , at *5 (Tex.
    App.—Dallas Aug. 8, 2000, pet. denied) (not designated for publication); Texas
    Utilities Electric Co. v. Aetna Casualty & Surety Co., 
    786 S.W.2d 792
    , 793-94 (Tex.
    App.—Dallas 1990, writ denied); Barbier v. Barry, 
    345 S.W.2d 557
    , 562 (Tex.
    App.—Dallas 1961, no writ)—and the Fifth Circuit’s decision in South Texas
    Electric Co-op. v. Dresser-Rand Co., 
    575 F.3d 504
    , 507 (5th Cir. 2009).
    20
    All parties agree that paragraph 21.3’s notice provisions are conditions, not
    covenants.20 Paragraph 21.3 imposes two potential duties on James but only if
    certain events occur. The first duty is to begin remedying safety violations. If
    Chemical desired to trigger James’s remediation duty, the triggering conditions are
    that Chemical must have first discovered or determined in its reasonable opinion that
    James has serious safety violations, and it must have so notified James. James is
    then required to begin remediation of the defects cited within seventy-two hours after
    receiving Chemical’s notice.           The second potential duty is to pay for post-
    termination costs above the contract price. That duty is triggered if: (1) Chemical
    is not reasonably satisfied with the pace and quality of the remediation; (2) Chemical
    notifies James of its dissatisfaction; and (3) Chemical notifies James that it elects to
    terminate the contract or a portion of the work. The question we must decide is
    whether James’s duties to begin remediation and then pay for post-termination costs
    above the contract price are invoked if Chemical did not strictly comply with the
    conditions by providing notices in writing, as paragraph 9.1 requires, but instead
    substantially complied because James received non-written notice, the form of
    which did not severely impair the provision’s purpose and caused James no harm.
    20
    “A condition precedent may be either a condition to the formation of a contract or to an
    obligation to perform an existing agreement.” Hohenberg Bros. Co. v. George E. Gibbons & Co.,
    
    537 S.W.2d 1
    , 3 (Tex. 1976). A condition precedent to an obligation to perform is an act or event
    that “must occur before there is a right to immediate performance and before there is a breach of
    contractual duty.” Id.; see Solar Applications Eng’g, Inc. v. T.A. Oper. Corp., 
    327 S.W.3d 104
    ,
    108 (Tex. 2010). Stated differently, “a ‘triggering’ condition or event is one that brings something
    else into effect.” Greene v. Farmers Ins. Exch., 
    446 S.W.3d 761
    , 765 (Tex. 2014). A covenant,
    as distinguished from a condition, is an agreement to act or refrain from acting in a certain way.
    Solar 
    Applications, 327 S.W.3d at 108
    . “In short, when a party fails to fulfill a condition precedent
    to another party’s obligation, the other party has no duty under the contract to perform that
    obligation, regardless of whether the contract has been breached.” 
    Greene, 446 S.W.3d at 782
    n.25 (Tex. 2014) (Boyd, J., concurring); see Restatement (Second) of Contracts § 225(1), (2).
    21
    The Supreme Court of Texas has considered whether a failure to comply with
    certain notice conditions precedent excuses the other party’s performance or
    precludes liability for failure to perform. Most recently, the issue has arisen in the
    insurance context. E.g., Prodigy Commc’ns Corp. v. Agric. Excess & Surplus Ins.
    Co., 
    288 S.W.3d 374
    (Tex. 2009); PAJ, Inc. v. Hanover Ins. Co., 
    243 S.W.3d 630
    (Tex. 2008). In PAJ, the court considered the effect on commercial general liability
    coverage when an insured fails to timely notify the insurer of a claim but the insurer
    suffers no harm. 
    PAJ, 243 S.W.3d at 632
    . The court held that a failure to comply
    with a timely-notice provision does not excuse the insurer’s performance if the
    insurer is not prejudiced by the delay. 
    Id. at 636-37.
    The ruling rested in large part
    on fundamental contract law that material breaches excuse the other party’s
    performance, but immaterial breaches do not. 
    Id. at 633.
    In that case, the parties
    disputed whether the notice provisions were conditions precedent or covenants, but
    the court applied basic contract law of immateriality regardless of the character of
    the provision. 
    Id. at 636-37.
    Additionally, the court noted that the timely-notice
    provisions were not essential to the overall bargain, and that excusing performance
    altogether for de minimus deviations from notice requirements would be
    “draconian.” 
    Id. at 636.
    In Prodigy, the court considered whether PAJ’s holding would apply to a
    claims-made (as distinguished from an occurrence-based) insurance policy
    containing an “as soon as practicable” timely-notice provision. 
    Prodigy, 288 S.W.3d at 375
    . There the policy required that the insured give notice of a claim “as soon as
    practicable . . ., but in no event later than ninety (90) days after the expiration of the
    Policy Period or Discovery Period.” 
    Id. at 378.
    The contract clearly described the
    notice provision and reporting period provision as conditions precedent. 
    Id. The parties
    disputed whether notice of the claim was given “as soon as practicable,” but
    22
    the insurer admitted it suffered no prejudice. The court held that PAJ’s “notice-
    prejudice” rule also applied to the “as soon as practicable” notice provision in the
    claims-made policy at issue in Prodigy. 
    Id. at 382.
    The principal reason for the
    court’s holding was because the “as soon as practicable” notice clause was not
    essential to the bargain in that case. 
    Id. Thus, the
    insured’s failure to comply with
    the timely-notice condition did not excuse the insurer’s performance. 
    Id. In another
    insurance dispute pre-dating PAJ and Prodigy, the supreme court
    addressed an insured’s failure to comply with proof-of-loss conditions precedent in
    a policy providing disability benefits. See Am. Teachers Life Ins. Co. v. Brugette,
    
    728 S.W.2d 763
    (Tex. 1987). There the insured raised theories that he substantially
    complied with the conditions, or the insurer waived them. 
    Id. at 764.
    The court held
    that it was the insured’s burden to secure jury findings on substantial compliance,
    absent conclusive evidence in his favor, and because he failed to do so he was not
    entitled to prevail. 
    Id. Brugette recognizes
    that an insured may satisfy a proof-of-
    loss condition precedent by establishing he substantially complied with the
    condition. 
    Id. From these
    informative examples, we learn, in the insurance context at least,
    that a party will not lose the benefit of its bargain for immaterial or non-prejudicial
    non-compliance with timely-notice provisions, see 
    PAJ, 243 S.W.3d at 636-37
    ,
    including when those notice provisions are conditions precedent. See 
    Prodigy, 288 S.W.3d at 382
    . Under Prodigy’s reasoning, when a triggering condition is not
    essential to the overall bargain, a party’s failure to fully satisfy that condition does
    not necessarily excuse the other’s party’s obligation that would be triggered by the
    condition’s occurrence. See 
    id. This reasoning
    is consistent with other statements
    of a similar principle grounded in the Restatement: the non-performance of a
    condition precedent is excused if the condition’s requirement “(a) will involve
    23
    extreme forfeiture or penalty, and (b) its existence or occurrence forms no essential
    part of the exchange for the promisor’s performance.” Lesikar Constr. Co. v.
    Acoustex, Inc., 
    509 S.W.2d 877
    , 881 (Tex. App.—Fort Worth 1974, writ ref’d n.r.e.)
    (citing Restatement (First) of Contracts § 302). Brugette clearly acknowledges an
    insured’s right to recover on an insurance policy if the insured substantially complies
    with a proof-of-loss condition precedent.
    The supreme court also has considered the issue in the construction context,
    though not recently. Over a century ago, the high court upheld a contractor’s
    recovery for breach of contract despite the contractor’s failure to strictly comply
    with a contract condition requiring it to produce an architect’s certification that work
    performed complied with specifications. See Linch v. Paris Lumber & Grain Elev.
    Co., 
    80 Tex. 23
    , 
    15 S.W. 208
    (1891). In Linch, the contractor allegedly completed
    the first stage of construction but the owner refused full payment, contending that
    the work and materials did not strictly comply with the contract. The contractor sued
    for breach though it had not complied with the condition that it first secure an
    architect’s certification.21 The jury found for the contractor and the trial court
    rendered judgment in its favor. 
    Id. The owner
    complained on appeal about jury-
    charge instructions that permitted recovery upon substantial compliance with the
    contract’s terms. In particular, the owner argued that the contractor was not entitled
    to recover because the certificate condition had not been satisfied. 
    Id. at 213.
    The
    court rejected the argument and concluded that less than strict compliance with the
    21
    The contract provided that “no claim shall be made or suit brought for any sum due, or
    claimed to be due for said improvement, unless upon certificate of said superintendent or inspector
    that the improvement has been made in strict accordance with the contract and plans and
    specifications, or such alterations as may have been made therein in accordance with the
    stipulations of this contract.” 
    Id. at 208.
    The court viewed this provision as a condition, 
    id. at 213,
    and it contains the sort of conditional language typically signifying a condition precedent. See
    Solar 
    Applications, 327 S.W.3d at 109
    .
    24
    certificate condition did not defeat the contractor’s right of recovery. 
    Id. Not long
    after Linch, the supreme court stated in Perkins v. Locke, 
    88 Tex. 66
    , 
    29 S.W. 1048
    (1895), that substantial compliance with a contract’s certificate provision would
    suffice, though in Perkins the certificate did not substantially comply with the
    contract. 
    Id. at 1050.
    Appellants cite the supreme court’s decisions in Ogden and Shumway as
    supporting their contention that parties must strictly comply with written notice
    requirements attendant to contractual termination provisions.        But Ogden and
    Shumway discussed and applied equity and Uniform Commercial Code (UCC) rules
    uniquely applicable to acceleration and notice-of-acceleration provisions in
    promissory notes. 
    Shumway, 801 S.W.2d at 893-94
    ; 
    Ogden, 640 S.W.2d at 234-35
    .
    In Ogden, the court held that the note holder’s letter “gave no clear and unequivocal
    notice” that it would exercise its option to accelerate the note. 
    Ogden, 640 S.W.2d at 234
    . Thus, the notice of acceleration was insufficient and the maker could recover
    for wrongful foreclosure. Later, in Shumway, the court held that promissory note
    makers can waive presentment, notice of intent to accelerate, and notice of
    acceleration, which, to be effective, also must be expressed in clear and unequivocal
    language. 
    Shumway, 801 S.W.2d at 893
    . But the court later clarified Ogden in
    Jasper Federal Savings & Loan Association v. Reddell, 
    730 S.W.2d 672
    (Tex. 1987),
    in which the court held, in a deed-of-trust dispute, that actual knowledge of the right
    to reinstate after acceleration was sufficient despite a notice provision in the deed.
    
    Id. at 675.
    In distinguishing Ogden, the court in Jasper observed that the bank never
    contended that Ogden had actual knowledge of its intent to accelerate. 
    Id. Jasper also
    relied on the court’s decision in University Savings Association v. Springwoods
    Shopping Center, 
    644 S.W.2d 705
    (Tex. 1982), upholding a foreclosure sale in
    which there had been no compliance with provisions relating to the recording of the
    25
    appointment of the substitute trustee before sale. See 
    Jasper, 730 S.W.2d at 675
    .
    The court held the borrower’s actions for wrongful foreclosure were barred by his
    actual notice of the substitution and identity of the substitute trustee, and the time
    and place of the sale, when no prejudice resulted from the failure to comply with the
    recordation provision in the deed of trust. 
    Id. (citing Univ.
    Savings, 644 S.W.2d at
    705
    ).
    In addition to the above authority, several Texas intermediate appellate courts
    have held, stated, or assumed that the substantial compliance doctrine applies to
    contract conditions precedent, including those containing notice provisions. In a
    notably comparable context, the Eastland Court of Appeals applied the substantial
    compliance doctrine to cancellation notice provisions in a construction contract and
    held that the terminating party substantially complied with the notice provision even
    though the notice was untimely. S. Mortg. Co. v. McGregor, 
    279 S.W. 860
    , 861
    (Tex. App.—Eastland 1926), aff’d, 
    286 S.W. 1086
    (Tex. Comm’n App. 1926,
    judgm’t adopted). Additionally and outside the construction context, the Dallas
    Court of Appeals has applied the substantial compliance doctrine to cancellation
    notice provisions in a contract to install audiovisual equipment,22 a licensing
    agreement,23 a contract to supply electrical power to a commercial business,24 and
    an employment contract.25 Our court and the San Antonio Court of Appeals have
    22
    Burlington N. R.R. Co., 
    2000 WL 1100874
    , at *5.
    23
    
    Barbier, 345 S.W.2d at 562
    (citing S. 
    Mortg., 279 S.W. at 860
    ). In Barbier, the court
    held that the party’s failure to send the notice by registered mail did not destroy its effectiveness
    as notice. 
    Id. 24 Tex.
    Util. Elec. Co. v. Aetna Cas. & Surety Co., 
    786 S.W.2d 792
    , 793-94 (Tex. App.—
    Dallas 1990, writ denied) (notice sent to and received at office location other than office location
    specified by contract substantially complied with contract terms).
    25
    Parking Co. of Am. v. Wilson, No. 05-99-00404-CV, 
    2002 WL 387180
    , at *3, (Tex.
    App.—Dallas Mar. 13, 2002, no pet.) (not designated for publication). In Wilson, the contract at
    issue required termination on thirty days’ written notice. The employee gave notice verbally. 
    Id. The court
    assumed that substantial compliance would suffice and further assumed that verbal
    26
    explicitly or implicitly applied the substantial compliance doctrine to notice
    provisions in lease agreements and in other contexts.26
    Appellants cite Texas intermediate appellate court decisions that are less clear,
    relying heavily on this court’s opinion in Emerald 
    Forest. 679 S.W.2d at 51
    . There,
    Emerald Forest Utility District sued an engineer and construction company after an
    underground sewer system built by the construction company failed. 
    Id. The jury
    found that the line failed because the engineer’s design was insufficient to deal with
    underground wet sand conditions discovered during construction. 
    Id. at 52.
    The
    jury also found that the utility district failed to provide sufficient plans to the
    construction company. 
    Id. We reversed
    and held that the construction company was
    liable for breach of its promise to deliver a working sewer system because the
    company was in a position to discover the insufficient soil conditions before it
    executed the contract, and it agreed to investigate and apply its independent
    judgment concerning worksite conditions. 
    Id. at 53.
    The company argued that it
    could not be liable on that ground because it notified the engineer and utility district
    of the wet sand conditions and requested a substitute design. 
    Id. at 54.
    This court
    said that the construction company could not avoid contract liability because the
    record did not show that the company gave written notice of the subsurface
    notice would be sufficient to substantially comply with the contract’s written notice provision, but
    held nonetheless that substantial compliance was not shown on that record. 
    Id. 26 MMM
    410 Bar & Grill, LLC v. Fong, No. 04-18-00156-CV, 
    2018 WL 5018767
    , at *3
    (Tex. App.—San Antonio Oct. 17, 2018, no pet.) (mem. op.); Am. Props. of Houston, LLC v.
    Detering Office Partners, Ltd., No. 14-10-00063-CV, 
    2011 WL 529711
    , at *3 (Tex. App.—
    Houston [14th Dist.] Feb. 15, 2011, no pet.) (mem. op.) (holding actual notice of landlord’s intent
    to repair the leased premises rendered the written notice requirement in the lease unnecessary); see
    also Comeaux v. Suderman, 
    93 S.W.3d 215
    , 219 (Tex. App.—Houston [14th Dist.] 2002, no pet.)
    (considering right of first refusal in option contract, stating party’s actual notice of proposed sale
    of premises and opportunity to purchase it rendered unnecessary for court to address whether
    notice was “technically insufficient”).
    27
    conditions varying from the original specifications, as the contract required.27 
    Id. As we
    stated, “[w]hen a contract provides for a particular form of notice, compliance
    with such provisions is a condition precedent to invoking the contract rights which
    are conditioned on the notice.” 
    Id. (citing Handelman
    v. Handelman, 
    608 S.W.2d 298
    (Tex. App.—Houston [14th Dist.] 1980, writ ref’d n.r.e.)).             We did not,
    however, discuss or mention the doctrine of substantial compliance as applied to the
    contract conditions, and it does not appear the construction company raised the issue.
    We will not construe Emerald Forest as holding that substantial compliance never
    applies to notice conditions precedent when it is not clear that the issue was raised,
    considered, and expressly rejected by our court in that case.
    We also disagree with appellants that our decisions in Arbor Windsor and
    Cajun Constructors compel us to deny Chemical’s recovery absent strict compliance
    with the contract’s notice provisions. In Arbor Windsor, we stated that Arbor
    Windsor had the burden to prove that it was excused from sending a notice of default
    to Weekley as a condition precedent to its right to invoke contractual remedies for
    default, and also had the burden to obtain a jury finding of excuse. Arbor 
    Windsor, 463 S.W.3d at 142
    . Arbor Windsor neither obtained a jury finding that it was
    excused nor argued that it conclusively established it was excused from sending
    notice of default.    
    Id. Here, in
    contrast, Chemical secured findings that it
    substantially complied with the notice provision. Indeed, by observing that Arbor
    Windsor could have proven it was excused from complying with the notice provision
    there at issue, our court necessarily recognized that a failure to strictly comply with
    the notice condition precedent would not always foreclose recovery, just that Arbor
    Windsor had not made the necessary showing in that case. In Cajun Constructors,
    27
    The contract stated: “[t]he CONTRACTOR will promptly notify the OWNER and
    ENGINEER in writing of any subsurface or latent physical conditions at the site differing
    materially from those indicated in the Contract Documents. . . .” 
    Id. (emphasis added).
    28
    we affirmed a summary judgment against a party seeking recovery for breach of
    contract because the plaintiff did not present evidence that it complied with the
    contract’s notice requirements, which we held to be conditions precedent to bringing
    suit. Cajun 
    Constructors, 380 S.W.3d at 825-26
    . As in Emerald Forest, however,
    the parties in Cajun Constructors did not raise the issue of substantial compliance
    and the court did not discuss it.
    We are not bound by the Fifth Circuit’s interpretation of state law, but we note
    that court has characterized as “well-established Texas law” the “applicability of the
    doctrine of substantial compliance to contractual notice provisions.” S. Tex. Elec.
    
    Co-op., 575 F.3d at 507
    (citing 
    Barbier, 345 S.W.2d at 562
    , and Tex. Utilities Elec.
    
    Co., 786 S.W.2d at 794
    ). No Texas state case is more factually on point than South
    Texas. In that case, which involved manufacture of a turbine, Dresser, like James,
    was required to correct defects after receiving written notice. 
    Id. at 506.
    Despite
    many problems, and Dresser’s awareness of them, Dresser did little to remedy the
    issues. South Texas employed others to perform repairs without providing Dresser
    written notice. 
    Id. South Texas
    sued for its repair costs; the jury found Dresser was
    liable for breach, and that South Texas substantially complied with the notice
    provision. 
    Id. On appeal,
    Dresser, again like James, argued that the court erred in
    submitting the substantial compliance issue to the jury because Texas law required
    strict compliance with the notice provision. 
    Id. at 507.
    The Fifth Circuit disagreed
    and reasoned that the notice provision’s purpose was served by Dresser’s actual
    knowledge of the problems and was not impaired by South Texas’s failure to strictly
    comply. See 
    id. at 508-09.
    In light of the above authority, we reject appellants’ argument that Texas law
    categorically requires strict compliance with written notice conditions precedent in
    construction contracts. We hold that Chemical’s failure to strictly comply with the
    29
    written notice provisions required by paragraphs 9.1 and 21.3 does not compel
    reversal, and that Chemical’s substantial compliance suffices to support recovery if
    the evidence shows that James received actual notice, and that the form of the notice
    did not severely impair the notice provision’s purpose and caused James no harm.
    We turn to whether the evidence in fact supports these findings.28
    b.      Legal sufficiency challenge to the jury’s substantial compliance
    findings
    Appellants contend that no legally sufficient evidence supports the jury’s
    substantial compliance findings in questions 3A, 3B, and 3C, and that those findings
    lack support because Chemical’s notices of default and termination were not clear
    and unequivocal. As to questions 3A and 3B, appellants argue more particularly that
    Chemical’s communications were insufficiently specific to constitute actual notice
    of any of the mentioned events. Appellants say there was no specific mention of any
    safety violations or that Chemical was unsatisfied with the pace or quality of James’s
    remedial efforts. Also, James could not determine from the communications when
    the seventy-two-hour period to institute remedial measures began after the first
    notice. Regarding question 3C, appellants argue that an April 2013 meeting about
    James’s deficient safety performance was vague, and that Chemical never actually
    informed James that it was being “terminated” for “default.”
    This issue requires us to examine whether the evidence supports the jury’s
    findings. As stated, we view the evidence in the light most favorable to the judgment
    and indulge every reasonable inference that would support it. City of 
    Keller, 168 S.W.3d at 822
    . We credit favorable evidence if a reasonable fact finder could and
    disregard contrary evidence unless a reasonable fact finder could not. 
    Id. at 807,
    28
    As no party complains of the language used in the instructions, we apply them as written
    and express no opinion whether they accurately or completely state Texas law.
    30
    827. If more than a scintilla of evidence supports the judgment, we must uphold it.
    
    Coffman, 448 S.W.3d at 71
    . More than a scintilla of evidence exists when the
    evidence supporting the finding rises to a level that would enable reasonable and
    fair-minded people to differ in their conclusions. 
    Id. First Notice
    In question 3A, the jury found that Chemical provided notice to James that
    Chemical had discovered or determined, in its reasonable opinion, that James had
    serious safety violations, in that: (1) James received actual notice of that fact from
    Chemical; and (2) the form of actual notice did not severely impair the notice
    provision’s purpose and caused James no harm.
    James was responsible for performing its work safely. However, during the
    project, James incurred multiple OSHA-recordable safety incidents, as well as
    numerous documented “near miss” incidents. For example, on September 25, 2012,
    one of James’s workers broke his leg while on the jobsite. A root cause of this
    incident involved lack of communication between an operator and a flagger. Several
    other near-miss incidents occurred that also could be attributed to James’s failure to
    have appropriate flagging or spotting personnel.
    Three months after the worker injured his leg, another significant safety
    incident resulted in a fatality. In December 2012, one of James’s employees,
    Gregory Price, sustained a head injury from a fall on the job and later died. OSHA
    cited James for a “serious” safety violation for this fatality, which resulted from a
    lack of appropriate flagging personnel.
    Immediately following the Price incident, Chemical’s project manager,
    Abram Kuo, expressed Chemical’s displeasure over James’s safety performance to
    James’s site manager, Rusty DeBarge. Kuo copied DeBarge on an email in which
    31
    Kuo explained that the parties needed “to develop [a] preventive safety mind set with
    some extraordinary measure[s] on job safety.” Further, Kuo stated in the email that
    he would be on site January 2, 2013, to review the “safety performance and counter
    measures for safety prevention,” and that James’s management had been asked to
    attend that meeting. In a prior email in the chain on which DeBarge was copied,
    Kenner stated: “James Construction needs to show us how they will really prevent
    this and other types of incidents. [The Price fatality] was completely preventable.”
    In a separate email between Kuo and Kenner, Kuo confirmed that he had spoken
    with DeBarge and “expressed our displeasure over the incidents and safety
    performance of James.” According to Kuo, at the January 2 meeting, site teams from
    both James and Chemical sat down and discussed the safety incidents that had
    occurred, including the Price fatality, and Chemical stressed “how important [it was]
    to have [James] improve [its] safety performance on the job.” After that meeting,
    Chemical’s technology manager, Scott Campbell, met with DeBarge and asked
    James to document its safety procedures before and after the fatality, and told James
    that “we wanted to see their program improve greatly.” Chemical’s project team
    met and discussed how they could help James improve its safety performance. The
    team discussed whether the project was “too big for James” and talked about carving
    out portions of the work to help James improve its safety performance.
    In response to James’s actual knowledge that Chemical determined it had
    serious safety violations, James in fact began remedial measures, thus demonstrating
    that this knowledge satisfied the notice provision’s purpose. On January 9, DeBarge
    sent Chemical an email summarizing some of the post-accident measures
    implemented.29 DeBarge also stated subsequently in another email that because of
    29
    Appellants began remedial measures, and Chemical raised no complaint about their
    timeliness. Thus, it is immaterial whether James knew when its seventy-two-hour window
    commenced.
    32
    the Price fatality, James “would never consider ourselves successful in a general
    sense of safety on this project.”
    We conclude the above evidence is more than a scintilla that: (1) James
    received actual notice from Chemical that Chemical had discovered or determined,
    in its reasonable opinion, that James had serious safety violations; and (2) the form
    of actual notice (email and oral) did not severely impair the notice provision’s
    purpose and caused James no harm. We overrule appellants’ legal-sufficiency
    challenge to question 3A.
    Second and Third Notices
    In questions 3B and 3C, the jury found that Chemical provided notice to James
    that Chemical was not reasonably satisfied with the pace and the quality of the
    remediation effort, and that Chemical had elected to terminate the construction
    contract or a portion of the work, in that: (1) James received actual notice of those
    facts from Chemical; and (2) the form of actual notice did not severely impair the
    notice provision’s purpose and caused James no harm.
    James discovered that Chemical was considering making changes in the
    project going forward. Chemical had reached out to another construction company,
    Turner Industries, to discuss engaging Turner to work on the project. In response to
    this discovery, DeBarge emailed Kuo on January 18 regarding James’s ongoing
    safety improvement efforts. The content of this email both confirms James’s
    remediation efforts and shows that James was contemplating the possibility that it
    could be removed from the job or portions of its work could be re-assigned. Kuo
    responded to DeBarge’s email and confirmed that Chemical was considering
    transferring to Turner “independent jobs” such as ethylene dichloride distillation and
    pipeline work. In this email, Kuo explained that Chemical’s intent was to ensure
    success on the overall chlor-alkali project. Kuo emphasized that Chemical and
    33
    James had the responsibility to take “proactive action(s) deem[ed] necessary” to
    prevent any further safety incidents. On January 30, Vinyls entered into a general
    construction contract with Turner to take over ethylene dichloride distillation and
    pipeline work from James. Chemical re-assigned this work to reduce the load on
    James with the hope that James’s safety performance would improve.
    In late February, DeBarge sent an internal email to another James
    representative proposing, among other things, options for James to respond to “the
    situation.” Aware of the probability that James would lose further work to Turner,
    he suggested that James either accept a modified work scope as Chemical chose or
    take a firm stance and insist that Chemical quit holding issues like safety “over our
    heads.”
    According to Kuo, James’s safety record improved in January 2013, but by
    February safety incidents had ratcheted up. Campbell also testified about James’s
    typical response to safety incidents:
    After there would be an OSHA recordable there would be two weeks
    of really good performance, maybe a third week where there would be
    a little something. And then things start falling off again after three or
    four weeks, and we’d go back to Rusty [DeBarge] and try to get them
    back on track.
    Because James’s safety incidents continued after January and Chemical
    thought DeBarge had a “deaf ear” on safety concerns, Campbell and several other
    Chemical employees met with James’s vice president, Conrad Bourg, and asked
    Bourg to remove DeBarge.        James replaced DeBarge with Mark Lammon in
    February. Yet, internal emails between Chemical employees show that Chemical
    remained concerned about James’s safety performance. For example, in a March 6,
    2013 email, Kenner instructed Kuo to let James know that Chemical was considering
    removing it from the job and putting it “on notice.”           Additionally, internal
    34
    communications among James personnel show that James was aware of Chemical’s
    continued concerns with safety performance and intended to review its steps to
    improve its safety and productivity.
    Accidents continued to occur despite James’s downsized scope of work. An
    accident on April 1 resulted in a worker’s broken finger. On April 8, James’s
    workers damaged scaffolding over a chlorine line by striking it with a track hoe.
    According to Campbell, damage to the chlorine line could have been life-threatening
    to people in the area. The root cause of this near-miss incident was identified as a
    failure to effectively use spotting/flagging processes. Chemical then decided to
    remove all mechanical scope of work from James. Kuo told Campbell to meet with
    Turner immediately about its availability to assume James’s remaining mechanical
    work.
    Campbell scheduled an April 11 meeting with other Chemical and James
    personnel. During the meeting, Campbell told James’s representatives Lammon and
    Bourg that James’s safety record was “deplorable” or “terrible.” Campbell reiterated
    that despite Chemical’s attempts to help James improve its safety performance, and
    despite James’s replacement of its project manager, James was “falling back into the
    same pattern.”    Campbell informed them that James had five days to get its
    “remaining piping and mechanical people off the job.” Campbell explained that
    James would no longer be performing mechanical construction for the project
    because of James’s poor safety performance.       According to Campbell, Bourg
    responded with incredulity, exclaiming “everyone has fatalities.” Later that day,
    James terminated its subcontracts effective April 14. On May 8, DeBarge sent a
    letter to Chemical confirming that James had “discontinued mechanical work on the
    Chlor-Alkali project and we have completed the demobilization of the mechanical
    35
    forces.” James continued the civil construction portion of the job until it was
    completed, and Chemical paid James for its work on the project, including retainage.
    Citing Vinson Minerals, Ltd. v. XTO Energy, Inc., 
    335 S.W.3d 344
    , 356-58
    (Tex. App.—Fort Worth 2010, pet. denied), appellants say Chemical’s
    communications during the April 11 meeting were too vague and equivocal to
    constitute proper notice of termination. Vinson in some respects supports appellants’
    position that notice of termination must be clear and unequivocal, but Vinson does
    not say that only written notices can be clear and unequivocal. A reasonable juror
    could have found that Chemical’s statements during the meeting clearly informed
    James of its termination, and that James received the message. Otherwise, James
    would not have cancelled its subcontracts immediately or sent a letter to Chemical
    confirming its terminated scope of work.
    We conclude the above evidence is more than a scintilla that: (1) Chemical
    provided notice to James that Chemical was not reasonably satisfied with the pace
    and the quality of the remediation effort; (2) Chemical had elected to terminate the
    construction contract or a portion of the work; (3) James received actual notice of
    those facts from Chemical; and (4) the form of actual notice did not severely impair
    the notice provision’s purpose and caused James no harm. We overrule appellants’
    legal-sufficiency challenge to questions 3B and 3C.
    4.     Legal sufficiency challenge to damages
    Next, appellants challenge the legal sufficiency of the evidence to support the
    jury’s damages awards of $211,836.81 in safety training costs and $842,415 in
    increased foreman costs. In connection with the damages question, the trial court
    instructed the jury:
    To consider only the following elements of damage:
    36
    Any extra costs in excess of the Contract Price incurred by
    Westlake Chemical in regards to taking possession of the Work
    or the portion thereof terminated and purchasing and/or hiring
    materials, tools, supervision, labor, and equipment for the
    completion of the Work.
    If you answered “Yes” to Questions 1A or 1B, then you may
    include Westlake Vinyls’ damages, if any, in your answers
    below, otherwise, do not include Westlake Vinyls’ damages, if
    any, in your answers below.
    Appellants contend there is no evidence to support a finding in regard to either the
    “contract price” or the “extra costs in excess of the contract price.” We disagree.
    First, the contract does not define “Contract Price” as a fixed sum but rather
    as “the total compensation payable to the Contractor for the performance of the
    Work.” In turn, “Work” is defined as “certain services and/or equipment, materials,
    supplies, or other products.” The damages categories the jury awarded—“Safety
    Training Costs” and “Increased Foreman Costs”—were costs that were incurred only
    because of the transition from James to Turner, as explained by Chemical’s damages
    expert, Byrd. For example, Byrd testified that he “identified the extra piece of the
    cost that [was] uniquely caused by the removal and replacement of James.” Byrd
    also established that the damages incurred were associated with work scope that
    originally had been assigned to James but was reassigned to Turner after Chemical
    terminated James’s mechanical scope.30
    Turning to the specific categories of damages awarded, Byrd explained
    regarding the safety training costs:
    When James was on the project, James had a peak labor force of 732
    workers. So when Westlake had to replace James with Turner, they had
    30
    For example, Byrd explained, “Westlake actually removed work scope from James that
    was ongoing and active, at various states of progress throughout the entire facility, which was a
    massive scope removal, and then transferred that scope to Turner to complete.”
    37
    to pay Turner to reorient, basically, incur these costs uniquely as a
    result of the removal and replacement of [James], but only as to the
    732 people that had already been on site before.
    (Emphasis added). Accordingly, Byrd limited his damages calculation only to those
    732 workers, explaining that any workers provided by Turner in excess of that
    number were not part of his calculation because, had James hired additional workers,
    “those costs would have been incurred anyway.” Byrd testified that the total
    additional costs for safety training “attributable to Westlake Chemical’s removal of
    James’[s] mechanical scope” was $506,747. The jury’s $211,836.81 award for this
    damages category was well within the range to which Byrd testified. See, e.g., Gulf
    States Utils. Co. v. Low, 
    79 S.W.3d 561
    , 566 (Tex. 2002) (jury generally has
    discretion to award damages within the range of evidence presented at trial); Ho &
    Huang Props., L.P. v. Parkway Dental Assocs., P.A., 
    529 S.W.3d 102
    , 118 (Tex.
    App.—Houston [14th Dist.] 2017, pet. denied) (same).
    Byrd also explained how he calculated the “Extra Foreman Costs.” According
    to Byrd, replacing James on the project required Turner to “tighten up the foreman
    to crew ratio” because of the complex nature of the project and Turner’s “step[ping]
    in midstream.” Byrd stated that he examined James’s records before the termination,
    which indicated that James’s typical ratio between craft workers and foremen was
    one foreman for every ten workers. But after James’s termination, Turner reduced
    the foreman to craft worker ratio to one foreman for every five or six workers. Byrd
    explained that these extra costs arose “[b]ecause of the transition.” Byrd additionally
    stated that “tighten[ing] up the foreman to crew ratio . . . is a good management
    practice from the construction management standpoint.” He testified that the cost
    for these additional foremen—necessitated only by the removal of James’s scope of
    work and transition of that work to Turner—was $842,415, which is exactly the sum
    the jury awarded. Byrd unequivocally stated that these damages were “reasonable
    38
    and necessary costs that are attributable to Westlake Chemical’s removal of
    James’[s] mechanical scope.”
    In short, Byrd provided expert testimony summarizing the extra costs
    associated with the termination of James’s mechanical scope of work and transition
    of this work scope to Turner. The jury determined that some, but not all, of these
    extra costs should be borne by James. Considering the evidence in the light most
    favorable to the jury’s finding in response to Question 3E, indulging every
    reasonable inference that would support it, crediting favorable evidence if a
    reasonable fact finder could, and disregarding contrary evidence unless a reasonable
    fact finder could not, we conclude the trial evidence would enable reasonable and
    fair-minded people to find the damages as awarded by the jury. See, e.g., Ho &
    Huang 
    Props., 529 S.W.3d at 118
    .           Accordingly, we overrule James’s legal
    sufficiency challenge to the jury’s damage awards.
    5.     Argument that damages are barred by paragraph 26
    In a final point under issue one, and as an alternative to their legal sufficiency
    challenge, appellants assert that the damages awarded are consequential and barred
    by the contract’s consequential damages provision, paragraph 26, which provides
    that neither “shall be liable to the other” for “any consequential, incidental, indirect
    . . . damages of any kind or character.”
    Actual damages may be either direct or consequential. Arthur Andersen &
    Co. v. Perry Equip. Corp., 
    945 S.W.2d 812
    , 816 (Tex. 1997). “Direct damages are
    the necessary and usual result of the defendant’s wrongful act; they flow naturally
    and necessarily from the wrong. Direct damages compensate the plaintiff for the
    loss that is conclusively presumed to have been foreseen by the defendant from his
    wrongful act.” 
    Id. (citations omitted).
    In contrast, consequential damages are
    damages that result naturally, but not necessarily, from a breach. See 
    id. However, 39
    “if particular damages are specifically accounted for in the contract, they are direct,
    not consequential, in nature.” McKinney & Moore, Inc. v. City of Longview, No. 14-
    08-00628-CV, 
    2009 WL 4577348
    , at *5 (Tex. App.—Houston [14th Dist.] Dec. 8,
    2009, pet. denied) (mem. op.).
    Appellants claim the damages awarded by the jury are consequential because:
    (1) they were incurred by Vinyls, not Chemical; (2) they are not specifically
    accounted for in the construction contract and were not foreseeable by James; and
    (3) the increased foreman costs constitute “loss of productivity, loss of efficiency,
    or acceleration” type costs specifically foreclosed by paragraph 26.
    As to appellants’ first complaint, we have determined that Chemical, as
    Vinyls’s agent, was entitled to sue in its own name and recover damages on behalf
    of Vinyls.
    James’s complaints that the damages are consequential because they are not
    specifically accounted for in the contract or because the increased foreman costs
    constitute loss of productivity are unpersuasive. As noted above, the termination
    provision provides in pertinent part:
    [Chemical] shall have the unrestricted right to take possession of the
    Work or the portion thereof terminated and to purchase and/or hire
    materials, tools, supervision, labor, and equipment for the completion
    of the Work or of the unremedied condition, as [Chemical] elects. Any
    extra costs in excess of the Contract Price incurred by [Chemical] in
    this regard shall be at the expense of [James].
    Under this provision, James is responsible for Chemical’s costs in excess of
    the contract price for purchasing or hiring supervision (increased foreman costs) and
    labor (safety training costs) to complete the work. Because these categories of
    damages are specifically referenced in the construction contract, they are direct
    damages. See McKinney & Moore, 
    2009 WL 4577348
    , at *5 (holding that expenses
    40
    incurred under construction contract were direct damages because they were
    contemplated in contract provision that required defendant to reimburse plaintiff for
    damage occurring during work on project that were caused by negligence or fault of
    defendant or its agents); see also Tenn. Gas Pipeline Co. v. Technip USA Corp., No.
    01-06-00535-CV, 
    2008 WL 3876141
    , at *8-9 (Tex. App.—Houston [1st Dist.] Aug.
    21, 2008, pets. denied) (mem. op. on reh’g) (holding costs of providing power during
    construction delay were direct damages because contract provision specified that
    owner would provide electricity to construction site).
    In sum, we conclude that the damages awarded by the jury for safety training
    costs and increased foreman costs were direct damages, and we overrule this portion
    of appellants’ issue.
    *     *      *
    For the above reasons, we reject appellants’ challenges to the extent the
    judgment grants recovery to Chemical based on the jury’s findings that James
    breached paragraph 21.3. We affirm the portion of the judgment awarding to
    Chemical $1,054,251.81 in compensatory damages, together with all applicable pre-
    and post-judgment interest and taxable costs associated with that award. Due to our
    disposition of this issue, we need not address appellants’ alternative arguments in
    their second issue to the same damages awarded under paragraph 17.2. See Tex. R.
    App. P. 47.1 (“The court of appeals must hand down a written opinion that is as brief
    as practicable but that addresses every issue raised and necessary to final disposition
    of the appeal.”); see also Waite Hill Servs., Inc. v. World Class Metal Works, Inc.,
    
    959 S.W.2d 182
    , 184 (Tex. 1998) (explaining that a plaintiff is not entitled to
    recovery of the same damages for different theories of liability). Additionally, our
    holding necessarily defeats James’s requested relief in issue seven regarding its
    paragraph 21.3 counterclaim; and Primoris’s argument in issue five, in which
    41
    Primoris contends it cannot be liable on the Guaranty because James is not liable for
    breach of the construction contract. We overrule issues one, two, five, and seven.
    B.    Indemnification — Paragraph 19.1
    In their third issue, appellants contend that the trial court erred in rendering
    judgment for Chemical on Chemical’s indemnification claim under paragraph 19.1.
    That paragraph states:
    INDEMNIFICATION BY [JAMES]. [JAMES] SHALL DEFEND,
    INDEMNIFY AND HOLD HARMLESS [CHEMICAL], ITS
    AFFILIATES,      AGENTS,    DIRECTORS,     OFFICERS,
    SHAREHOLDERS, MEMBERS, REPRESENTATIVES, AGENTS,
    EMPLOYEES, SUCCESSORS, ASSIGNS AND INDEPENDENT
    CONTRACTORS (OTHER THAN [JAMES]) FROM AND
    AGAINST ANY AND ALL LIABILITIES, CLAIMS, LOSSES,
    DAMAGES, COSTS, PENALTIES, FINES, AND FEES, AS WELL
    AS COSTS OF DEFENSE, SETTLEMENT, AND REASONABLE
    ATTORNEY’S FEES (COLLECTIVELY, THE “LOSSES”)
    ARISING OUT OF SICKNESS, INJURY TO, OR DEATH OF ANY
    PERSON, OR DAMAGE TO OR DESTRUCTION OF REAL OR
    PERSONAL PROPERTY, INCUDING LOSS OF USE THEREOF,
    ARISING OUT OF, IN CONNECTION WITH, OR IN ANY WAY
    RELATED TO [JAMES]’S OR ITS SUBCONTRACTORS’
    PERFORMANCE OF THE WORK OR PRESENCE ON
    [CHEMICAL]’S PREMISES, BUT ONLY TO THE EXTENT OF
    [JAMES]’S OR ITS SUBCONTRACTORS’ NEGLIGENCE, STRICT
    LIABILTY OR OTHER LEGAL FAULT.
    As noted above, in December 2012, one of James’s employees, Gregory Price,
    sustained a head injury from a fall on the job. Price tragically died from his injuries
    shortly afterward. OSHA cited James for a “serious” safety violation because the
    fatality resulted from a lack of appropriate flagging personnel. Price’s family
    brought suit in Ascension Parish, Louisiana, against James and Chemical, among
    others, for wrongful death.
    42
    As part of the present action, Chemical alleged that James failed to indemnify
    it for the Price litigation in accordance with paragraph 19.1. Chemical presented
    evidence that it incurred over $205,000 in attorney’s fees defending the Price
    litigation. The jury found that James failed to comply with paragraph 19.1 and
    awarded Chemical $102,767.69 in reasonable and necessary attorney’s fees and
    costs.
    Appellants raise two arguments challenging this part of the judgment. First,
    appellants contend that Chemical’s prior material breach of paragraph 21.3—by
    wrongfully terminating James—bars recovery. Second, appellants say no evidence
    supports the damages.
    1.    No prior material breach
    Appellants argue that Chemical failed to properly terminate James’s
    performance under paragraph 21.3, which constitutes a prior material breach
    relieving it of any indemnification liability. See Pinnacle Anesthesia Consultants,
    P.A. v. Fisher, 
    309 S.W.3d 93
    , 99 (Tex. App.—Dallas 2009, pet. denied) (“A
    defendant’s improper termination of a contract is a breach of the contract as a matter
    of law.”) (citing Gunter Hotel of San Antonio Inc. v. Buck, 
    775 S.W.2d 689
    , 697
    (Tex. App.—San Antonio 1989, writ denied); Incorporated Carriers, Ltd. v.
    Crocker, 
    639 S.W.2d 338
    , 340 (Tex. App.—Texarkana 1982, no writ); Howell v.
    Kelly, 
    534 S.W.2d 737
    , 740 (Tex. App.—Houston [1st Dist.] 1976, no writ)). We
    disagree.
    Our disposition of appellants’ first issue forecloses this argument. As we have
    determined, legally sufficient evidence supports the jury’s findings that Chemical
    complied with the parts of paragraph 21.3 appellants say were violated, and that
    James breached paragraph 21.3. Moreover, if it were true that Chemical failed to
    fulfill paragraph 21.3’s default and notice provisions, as appellants contend, that
    43
    failure would not constitute a breach of contract giving rise to liability; it would
    merely amount to a failure to satisfy conditions precedent.            See, e.g., Solar
    
    Applications, 327 S.W.3d at 108
    . Failure to satisfy a condition precedent generally
    results in no liability, but failure to perform a contractual covenant may create
    liability. See Centex Corp. v. Dalton, 
    840 S.W.2d 952
    , 956 (Tex. 1992). If Chemical
    erred in determining an event of default occurred or failed to provide proper notice
    under section 21.3, then, at most, James would be excused from the obligations
    conditioned on those events. See, e.g., Solar 
    Applications, 327 S.W.3d at 108
    ;
    McMahan v. Greenwood, 
    108 S.W.3d 467
    , 484 (Tex. App.—Houston [14th Dist.]
    2003, pet. denied); Restatement (Second) of Contracts § 225. The failure would not
    constitute a prior material breach that would excuse James’s obligations under the
    indemnification provision.
    2.     Legal sufficiency challenge to damages
    As fair and reasonable compensation for James’s breach of the indemnity
    provision, the jury awarded to Chemical $102,767.69, which consisted of reasonable
    and necessary attorney’s fees and costs incurred by Chemical in defending the Price
    litigation. Appellants argue that the award is unsupported by legally sufficient
    evidence because Chemical failed to prove the fees are reasonable. There are two
    parts to their argument: (1) the sponsoring expert witness was not qualified to opine
    as to reasonableness of attorney’s fees in a Louisiana wrongful-death case; and
    (2) the expert’s opinions are conclusory and speculative.
    “‘If scientific, technical, or other specialized knowledge will assist the trier of
    fact to understand the evidence or to determine a fact in issue, a witness qualified as
    an expert by knowledge, skill, experience, training or education may testify thereto
    in the form of an opinion or otherwise.’” Cooper Tire & Rubber Co. v. Mendez, 
    204 S.W.3d 797
    , 800 (Tex. 2006) (quoting Tex. R. Evid. 702). Expert testimony is
    44
    admissible when (1) the expert is qualified, and (2) the testimony is relevant and
    based on a reliable foundation. 
    Id. We review
    the trial court’s determination that
    an expert is qualified for abuse of discretion. 
    Id. The test
    for abuse of discretion is
    whether the trial court acted without reference to guiding rules or principles. 
    Id. Whether a
    proffered expert is qualified is not subject to rigid formula. Mega
    Child Care, Inc. v. Tex. Dept. of Protective & Regulatory Servs., 
    29 S.W.3d 303
    ,
    310 (Tex. App.—Houston [14th Dist.] 2000, no pet.). There must be, however, a
    “fit” between the subject matter and the expert’s familiarity with that subject matter.
    See Broders v. Heise, 
    924 S.W.2d 148
    , 153 (Tex. 1996). “The proponent must
    establish that the expert has knowledge, skill, experience, training, or education
    regarding the specific issue before the trial court which would qualify the expert to
    give an opinion on that particular subject.” Mega Child 
    Care, 29 S.W.3d at 310
    .
    Chemical presented Texas attorney Lee Kaplan to testify about the
    reasonableness and necessity of the attorney’s fees Chemical incurred in defending
    the Price litigation. Appellants assert that Kaplan was not qualified because he is
    not licensed to practice law in Louisiana, is not familiar with Louisiana law or
    procedure, is not familiar with practices in Ascension Parish or the fees customarily
    charged for legal services in that locality, and is not familiar with wrongful-death
    lawsuits.
    An appellate challenge to an expert’s qualifications must be preserved by
    timely objection in the trial court. See, e.g., Nissan Motor Co. v. Armstrong, 
    145 S.W.3d 131
    , 143-44 (Tex. 2004). At trial, James objected to Kaplan’s qualifications,
    but only on the grounds that, “[a]lthough the witness did testify he did have litigation
    in Louisiana, he’s not licensed in Louisiana, and doesn’t practice in Louisiana, and
    doesn’t qualify for providing an opinion on that.” Thus, we limit our review to
    45
    whether the trial court abused its discretion in determining that Kaplan was qualified
    to opine about the reasonableness of attorney’s fees in Louisiana.
    We conclude Chemical met its burden. Kaplan testified that he has litigated
    cases in Louisiana, has been admitted pro hac vice there, and his firm frequently
    litigates or quotes fees to potential clients there. He stated that the fee structure in
    Louisiana is generally about fifteen to twenty percent lower than in Houston, Texas.
    Kaplan explained that he has law partners who are licensed in Louisiana, and he is
    familiar with the hourly rates these partners charge in Louisiana. Kaplan also
    testified that he is familiar with the law firm that represented Chemical in the Price
    litigation, which was a Houston firm with a New Orleans office. He stated that he
    is familiar with litigating wrongful-death cases in small counties, and he additionally
    explained that he examined the pleadings in the wrongful-death suit. On balance,
    we conclude that the trial court did not abuse its discretion, and there exists a
    sufficient “fit between the subject matter and [Kaplan]’s familiarity with that subject
    matter.” See 
    Mendez, 204 S.W.3d at 800
    ; 
    Broders, 924 S.W.2d at 153
    .
    Finally, appellants contend that Kaplan’s testimony amounted to no evidence
    of Chemical’s damages because it is conclusory and speculative. “An expert’s
    testimony is conclusory when the expert asserts a conclusion with no basis.”
    Bombardier Aerospace Corp. v. SPEP Aircraft Holdings, LLC, 
    572 S.W.3d 213
    , 223
    (Tex. 2019). Such a no-evidence complaint may be raised for the first time on
    appeal. See 
    id. As always,
    when considering a no-evidence point, we view the
    evidence in the light most favorable to the verdict, including every reasonable
    inference to support it. See 
    id. The jury
    was instructed that the only element of damages it could consider
    was “the costs of defense and reasonable attorney’s fees incurred by Westlake
    Chemical in defending” the wrongful-death suit. The jury was further instructed on
    46
    the Arthur Andersen31 factors:
    Factors to consider in determining a reasonable fee include—
    1. The time and labor required, the novelty and difficulty of the
    questions involved and the skill required to perform the legal
    services properly.
    2. The likelihood that the acceptance of the particular employment will
    preclude other employment by the lawyer.
    3. The fee customarily charged in the locality for similar legal services.
    4. The amount involved and the results obtained.
    5. The time limitations imposed by the client or by the circumstances.
    6. The nature and length of the professional relationship with the
    client.
    7. The experience, reputation, and ability of the lawyer or lawyers
    performing these services.
    8. Whether the fee is fixed or contingent on results obtained or
    uncertainty of collection before the legal services have been
    rendered.
    While these factors generally guide the fact finder on determining
    reasonableness of attorney’s fees, the proponent need not present evidence on all of
    them. See Messier v. Messier, 
    458 S.W.3d 155
    , 166-67 (Tex. App.—Houston [14th
    Dist.] 2015, no pet.); Arthur J. Gallagher & Co. v. Dieterich, 270 S.W3d 695, 706
    (Tex. App.—Dallas 2008, no pet.). Kaplan testified that he considered only four of
    these factors—1, 3, 4, and 7—relevant to the Price litigation.
    As to the first factor, Kaplan testified that the fees incurred were reasonable
    because the plaintiff demanded and obtained discovery, requiring Chemical to
    participate in motion practice over the course of nine months. Kaplan additionally
    explained that, in a wrongful-death case, the use of more experienced lawyers, such
    31
    Arthur 
    Andersen, 945 S.W.2d at 818
    .
    47
    as those Chemical engaged, is appropriate due to the dispute’s gravity. As to factor
    three, Kaplan testified that, although he personally “didn’t live that case,” the fees
    involved were “in line with what you customarily charge to handle the case.”
    Turning to the fourth factor, Kaplan explained that the Price litigation likely
    involved “a lot of money” because Price had a family and survivors. He also pointed
    out that Chemical’s lawyers prevailed on summary judgment, thus sparing Chemical
    from a wrongful-death trial. Finally, as to the seventh factor, Kaplan testified that
    the lawyers involved were capable, senior lawyers; the firm enjoys a “very good
    reputation;” and the lawyers “handled the case the way you’re supposed to.”
    After presenting this evidence, Chemical requested $205,533.39, and the jury
    awarded approximately half of that amount. Kaplan’s opinion that the fees involved
    in the wrongful-death suit were reasonable is supported by consideration of several
    of the Arthur Andersen factors. Accordingly, Chemical presented a factual basis for
    Kaplan’s opinions, and his testimony is not conclusory. See, e.g., Bombardier
    Aerospace 
    Corp., 572 S.W.3d at 227-28
    .
    We conclude that legally sufficient evidence supports the jury’s damage
    award on Chemical’s indemnification claim and therefore we affirm that portion of
    the amended judgment awarding Chemical recovery for $102,767.69, together with
    all applicable pre- and post-judgment interest and taxable costs associated with that
    award. We overrule appellants’ third issue.
    C.    Attorney’s Fees
    In issue four, Primoris challenges Chemical’s recovery of $2,923,600.50 trial
    and conditional appellate attorney’s fees. Primoris requests a rendition of judgment
    because no evidence supports the award. Alternatively, Primoris seeks a remand
    because Chemical failed to segregate recoverable fees from non-recoverable fees,
    and because the award is excessive.
    48
    1.        No-evidence challenge
    Chemical pleaded a breach of contract claim against James based on the
    construction contract and against Primoris based on the Guaranty. Chemical also
    requested reasonable and necessary attorney’s fees. Texas follows the “American
    rule” that attorney’s fees paid to prosecute or defend a lawsuit cannot be recovered
    in that suit absent a statute or contract that allows for their recovery. See Alyeska
    Pipeline Serv. Co. v. Wilderness Society, 
    421 U.S. 240
    , 247 (1975); Akin, Gump,
    Strauss, Hauer & Feld, L.L.P. v. Nat’l Dev. & Research Corp., 
    299 S.W.3d 106
    , 120
    (Tex. 2009). Neither the construction contract nor the Guaranty provide for an award
    of attorney’s fees to a prevailing party. Thus, the only potential basis for recovery
    of attorney’s fees is Texas Civil Practice and Remedies Code chapter 38. See Tex.
    Civ. Prac. & Rem. Code § 38.001(8). When a party prevails and is awarded damages
    on a breach-of-contract claim, it is entitled to attorney’s fees under section 38.001.
    Horizon Health Corp. v. Acadia Healthcare Co., 
    520 S.W.3d 848
    , 883 (Tex. 2017)
    (citing Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 201 (Tex.
    2004)).
    Chemical secured findings that James breached the construction contract. We
    have upheld James’s liability under paragraph 21.3 for breach of contract and
    compensatory damages. However, the court did not submit a jury question on
    Chemical’s breach-of-contract claim against Primoris. According to the record, the
    parties stipulated that if the jury found that James breached the construction contract,
    and if the jury awarded damages resulting from the breach, then Primoris is jointly
    and severally liable for the amounts James owes to Chemical because Primoris
    would have breached the Guaranty.32
    32
    Counsel stated the following on the record:
    [Chemical’s counsel:] I understand that the Court ruled that if the jury finds that
    49
    The Guaranty itself states in relevant part:
    For good and valuable consideration, the sufficiency of which is
    hereby acknowledged, [Primoris] hereby unconditionally and
    irrevocably guarantees to [Chemical] . . . the due and punctual
    performance of, and compliance with, all obligations, covenants,
    terms and conditions to be performed or complied with by
    [James] pursuant to that certain Contract Agreement dated as of
    May 18 2012 between [James] and [Chemical] (the
    “Agreement”) (all obligations of [James] under the Agreement
    being referred to collectively herein as the “Obligations”). Such
    Guarantee will not terminate until:
    a. the Obligations have been performed in full by [James]; or
    b. performance has been waived in writing by [Chemical].
    Based on the jury’s breach-of-contract findings against James, the parties’
    stipulation, and authority holding that chapter 38 does not permit recovery of
    attorney’s fees from a limited liability company, the trial court rendered judgment
    for Chemical’s attorney’s fees against Primoris only.
    James failed to comply with any provision of the Construction Contract with
    Westlake Chemical, either Section 17.2, 21.3, or 19.1, and if the jury finds that
    there are damages greater than zero resulting from the failures to comply with any
    of these provisions, then Primoris is jointly and severally liable . . . with James to
    Westlake Chemical under the parent guarantee for the same amount that James is
    liable for to Westlake Chemical under the Construction Contract, because it would
    then have failed to comply with the Primoris parent guarantee, and would owe the
    same amount of damages under the guarantee.
    Based on that ruling, we are not submitting jury questions on liability or damages
    for our claim under the guarantee; but by doing so, want to make it clear on the
    record that we are doing it based on the Court’s ruling, and we’re not waiving our
    right to recover against Primoris under the guarantee. And we expect that the Court
    will render judgment on [Chemical’s] claim against Primoris under the guarantee,
    as appropriate, based on that ruling after the jury’s verdict.
    THE COURT: [Counsel?]
    [James’s counsel:] Yes, sir. We understand and agree to that.
    50
    In its no-evidence challenge, Primoris contends that it is not liable for
    attorney’s fees under the Guaranty because James, the principal obligor, is not liable
    for attorney’s fees for breaching the construction contract. Primoris relies on the
    Guaranty language and case law holding that a guarantor’s liability is measured by,
    and limited to, the principal obligor’s liability unless a more extensive or more
    limited liability is expressly set forth in the guaranty agreement. See Material
    P’ships, Inc. v. Ventura, 
    102 S.W.3d 252
    , 265 (Tex. App.—Houston [14th Dist.]
    2003, pet. denied); W. Bank-Downtown v. Carline, 
    757 S.W.2d 111
    , 113 (Tex.
    App.—Houston [1st Dist.] 1988, writ denied).
    If the only contractual breach at issue were James’s breach of the construction
    contract, we would agree with Primoris that the Guaranty does not support the
    judgment because the Guaranty does not impose on Primoris any duty to pay sums
    that James does not owe under the construction contract. See Material 
    P’ships, 102 S.W.3d at 265
    . In signing the Guaranty, Primoris unconditionally and irrevocably
    guaranteed James’s “due and punctual performance of, and compliance with” the
    construction contract. James has no obligation to pay the attorney’s fees Chemical
    incurred to prove James breached the construction contract; thus, Primoris generally
    has no obligation to pay those attorney’s fees either.
    However, Chemical’s claim for attorney’s fees is based on Primoris’s alleged
    breach of the Guaranty, not on James’s liability for fees. Chemical argues that
    Primoris breached the separate Guaranty, and that it is entitled to fees as a result of
    that breach regardless whether chapter 38 permits a fee award against James for its
    breach of the construction contract.
    To recover attorney’s fees from Primoris under section 38.001, Chemical had
    to prevail on its breach-of-contract claim on the Guaranty against Primoris and
    51
    recover damages.33 See Ventling v. Johnson, 
    466 S.W.3d 143
    , 154 (Tex. 2015);
    Green Int’l v. Solis, 
    951 S.W.2d 384
    , 390 (Tex. 1997). To succeed on its claim for
    breach of the Guaranty, Chemical had to establish: (1) the existence and ownership
    of the guaranty; (2) the terms of the underlying contract by the holder; (3) the
    occurrence of the condition on which liability is based; and (4) the guarantor’s failure
    or refusal to perform the promise. See Wasserberg v. RES-TX One, LLC, No. 14-
    13-00674-CV, 
    2014 WL 6922545
    , at *6 (Tex. App.—Houston [14th Dist.] Dec. 9,
    2014, pet. denied) (mem. op.) (citing Wasserberg v. Flooring Servs. of Tex., LLC,
    
    376 S.W.3d 202
    , 205 (Tex. App.—Houston [14th Dist.] 2012, no pet.)). The
    Guaranty and the construction contract are included in the record and their existence
    and terms are not disputed. In a March 30, 2016 letter, Chemical demanded that
    James and Primoris pay damages resulting from James’s breaches of the
    construction contract within thirty days. Primoris did not tender payment within
    thirty days. By stipulation read into the record, the parties agreed that if the jury
    found that James failed to comply with the construction contract and caused damages
    greater than zero, then Primoris is jointly and severally liable to Chemical under the
    Guaranty for the same amount James owes because Primoris would then have failed
    to comply with the Guaranty. James, Primoris, and Chemical thus acknowledged
    that if James breached the construction contract then Primoris was in breach of the
    Guaranty.
    The parties’ stipulation accords with Texas guaranty law, which recognizes
    two distinct types of guaranty: a guaranty of collection (or conditional guaranty)
    and a guaranty of payment (or unconditional guaranty). See Universal Metals &
    Mach., Inc. v. Bohart, 
    539 S.W.2d 874
    , 877 (Tex. 1976); Ford v. Darwin, 767
    33
    Chemical also had to present its claim to Primoris, and payment for the just amount owed
    must not have been tendered within thirty days after the claim was presented. Tex. Civ. Prac. &
    Rem. Code § 38.002. Chemical presented its demand to Primoris on March 30, 2016.
    
    52 S.W.2d 851
    , 854 (Tex. App.—Dallas 1989, writ denied). A guaranty of payment,
    such as the unconditional Guaranty in today’s case, is an obligation to pay the debt
    when due if the debtor does not. Cox v. Lerman, 
    949 S.W.2d 527
    , 530 (Tex. App.—
    Houston [14th Dist.] 1997, no writ).               It requires no condition precedent to
    enforcement against the guarantor other than a default by the principal debtor. 
    Id. Primoris bound
    itself to James’s obligations under the construction contract by the
    unambiguous language of the Guaranty. As acknowledged by the stipulation,
    Primoris had a payment obligation immediately upon James’s breach, and it
    remained in breach of the Guaranty as long as it failed to perform. See Mid-S.
    Telecomms. Co. v. Best, 
    184 S.W.3d 386
    , 391 (Tex. App.—Austin 2006, no pet.).
    Citing Colonial American Casualty & Surety Co. v. Scherer, 
    214 S.W.3d 725
    ,
    735 (Tex. App.—Austin 2007, no pet.), Primoris argues that a surety’s liability for
    attorney’s fees under section 38.001 cannot extend beyond the liability of its
    principal. Scherer is distinguishable, however, because the claimant in that case
    neither pleaded a breach-of-contract claim against the surety nor sought attorney’s
    fees under section 38.001. 
    Id. at 734-35.
    Chemical did both.
    Additionally, Primoris disputes its liability for attorney’s fees because the
    Guaranty is governed by Louisiana law,34 which, according to Primoris, states that a
    guarantor is not liable for attorney’s fees incurred in enforcing a guaranty unless the
    guaranty agreement or the underlying contract provides for their recovery. Primoris,
    however, does not direct us to where in the record it urged the trial court to apply
    Louisiana law and proved the content and applicability of that law. We presume that
    Texas and Louisiana law agree in any relevant respects. See Lujan v. Navistar Fin.
    Corp., 
    433 S.W.3d 699
    , 706 n.1 (Tex. App.—Houston [1st Dist.] 2014, no pet.);
    34
    Paragraph 5 of the Guaranty states: “This Guarantee shall be governed by and construed
    in accordance with the laws of Louisiana.”
    53
    Collins v. Tex. Mall, L.P., 
    297 S.W.3d 409
    , 414-15 (Tex. App.—Fort Worth 2009,
    no pet.); see also Tex. R. Evid. 202 (providing that a party may compel a trial court
    to take judicial notice of another state’s law by filing a motion, giving notice to the
    other parties, and furnishing the court with sufficient information to enable it to
    properly comply with the request).
    Primoris cannot be made to pay Chemical’s attorney’s fees based solely on
    James’s breach of the construction contract; but Primoris can be made to pay
    Chemical’s attorney’s fees based on its breach of the Guaranty—which was shown
    once the jury found James breached the construction contract and found damages.
    Based on the jury findings and the stipulation, Chemical established (1) that Primoris
    failed to comply with the Guaranty and (2) damages. See Wasserberg, 
    2014 WL 6922545
    , at *7 (upholding summary judgment for breach of guaranty agreement).
    Therefore, attorney’s fees are recoverable against Primoris under section 38.001. As
    Primoris raises no other legal sufficiency challenges to the attorney’s fees, we
    overrule the legal sufficiency portion of issue four.
    2.     Primoris’s request for remand
    Next, we consider Primoris’s request for a new trial on attorney’s fees.
    Primoris argues first that Chemical failed to segregate fees incurred in pursuing
    direct damages from those incurred in pursuing consequential damages. Primoris
    states that because consequential damages are not recoverable under paragraph 26
    of the construction contract, Chemical may not recover attorney’s fees incurred in
    pursuing those types of damages. Chemical responds that no such segregation duty
    is required because: (1) the law mandates fee segregation only as to “claims,” not
    damage categories; and (2) the fees incurred in pursuing all contract damages were
    “intertwined.”
    54
    Fee claimants must segregate fees between claims for which they are
    recoverable and claims for which they are not. Tony Gullo Motors I, L.P. v. Chapa,
    
    212 S.W.3d 299
    , 311 (Tex. 2006). “[I]f any attorney’s fees relate solely to a claim
    for which such fees are unrecoverable, a claimant must segregate recoverable from
    unrecoverable fees.” 
    Id. at 313.
    “[I]t is only when discrete legal services advance
    both a recoverable and unrecoverable claim that they are so intertwined that they
    need not be segregated.” 
    Id. at 313-14.
    At the time of trial, Chemical’s only pleaded claim was a breach-of-contract
    claim against two defendants, James and Primoris. Breach of contract is a claim for
    which attorney’s fees are recoverable. Though other claims and parties were
    involved previously, Chemical segregated and excluded fees incurred in pursuing
    claims against James or others that ultimately settled. Chemical also excluded fees
    incurred solely in defense of James’s counterclaim.35
    Primoris argues nonetheless that Chemical was required to segregate fees for
    work developing and supporting requested damages that Primoris characterizes as
    consequential from those it characterizes as direct. For example, the trial court
    determined as a matter of law that certain “chlorine costs” Chemical sought were
    consequential damages and therefore were barred by the construction contract’s
    consequential damage provision—a ruling Chemical does not contest. According to
    Primoris, all other categories of damage Chemical sought in its damage model
    (except for the two categories awarded by the jury) similarly are barred because they
    too are consequential.36 Primoris asserts that Chemical should not recover fees
    incurred in pursuing the “chlorine costs” (which was not submitted to the jury), or
    35
    Chemical then reduced its requested fee by an additional ten percent to adjust for any
    record-keeping or duplication errors.
    36
    Specifically, Primoris contends that the requested damages in categories B, C, E, and
    F1-F8—which the jury did not award—are consequential.
    55
    in pursuing damage categories B, C, E, and F1-F8, because Chemical is
    “contractually barred from asserting those claims against James” under paragraph
    26. Primoris reasons that the attorney’s fee award is error because it includes fees
    incurred in seeking all of Chemical’s damages although most of them are
    unrecoverable under paragraph 26.
    Primoris describes a breach of contract claimant’s purported duty to segregate
    between services performed to advance distinct categories of damages when some
    damages may or may not ultimately be barred by an affirmative defense, such as in
    this case a consequential damages provision.        We have found no Texas case
    imposing such a segregation duty, and Primoris cites none. Texas law so far has
    required segregation of attorney’s fees only among those incurred in advancing
    “claims” for which fees are recoverable and those for which they are unrecoverable.
    See Tony 
    Gullo, 212 S.W.3d at 313-14
    ; In re Lesikar, 
    285 S.W.3d 577
    , 585 (Tex.
    App.—Houston [14th Dist.] 2009, no pet.); see also 7979 Airport Garage, L.L.C. v.
    Dollar Rent A Car Sys., Inc., 
    245 S.W.3d 488
    , 507 (Tex. App.—Houston [14th Dist.]
    2007, pet. denied) (“[W]hen a defendant asserts a counterclaim that the plaintiff must
    overcome in order to fully recover on its contract claim, the attorney’s fees necessary
    to defeat that counterclaim are likewise recoverable.”) (citing Varner v. Cardenas,
    
    218 S.W.3d 68
    , 70 (Tex. 2007)). Here, Chemical’s requested fees relate only to
    breach-of-contract claims for which fees are recoverable.         Segregation is not
    required when attorney’s fees are recoverable for all claims. Land v. Land, 
    561 S.W.3d 624
    , 640 (Tex. App.—Houston [14th Dist.] 2018, pet. denied). Accordingly,
    this portion of Primoris’s argument lacks merit.
    Next, Primoris contends that Chemical failed to segregate the fees incurred in
    prosecuting its claim against Primoris for breach of the Guaranty from those incurred
    in prosecuting its claim against James for breach of the construction contract. But,
    56
    as explained, Chemical could not prove that Primoris breached the Guaranty and
    recover on that claim without also proving that James breached the construction
    contract. A guaranty of payment cannot be enforced against the guarantor until the
    principal debtor defaults on the underlying obligation. See 
    Cox, 949 S.W.2d at 530
    .
    All of Chemical’s attorney’s fees incurred in pursuing its breach-of-contract claim
    against James were necessary to establish a right of recovery on its breach-of-
    contract claim against Primoris. Thus, these services were intertwined and no
    segregation was required. See Tony 
    Gullo, 212 S.W.3d at 313-14
    .
    Finally, Primoris argues that the attorney’s fees are excessive. Its argument
    is premised, however, on the assumption that we have reversed Chemical’s recovery
    of contract damages under paragraphs 17.2 and 21.3, thus leaving intact at most
    Chemical’s indemnity damages of $102,767.69 for breach of paragraph 19.1.
    Because we have affirmed the judgment awarding Chemical its actual damages
    resulting from James’s breach of paragraph 21.3, Primoris’s excessiveness argument
    fails and we thus overrule Primoris’s fourth issue in its entirety.
    Chemical’s Cross-Issues
    A.    Waiver of Consequential Damages
    Chemical’s first cross-issue concerns the meaning and effect of paragraph 26
    of the construction contract, entitled “Waiver of Consequential Damages.”
    According to James, paragraph 26 is a covenant not to sue for the damages described
    therein. James alleged in a counterclaim that Chemical breached paragraph 26 by
    affirmatively seeking damages that James contends are consequential. Agreeing
    with James, the jury found that Chemical breached paragraph 26 and awarded
    damages in the form of reasonable and necessary attorney’s fees that James incurred
    in defending against Chemical’s attempts to recover consequential damages. The
    57
    trial court rendered judgment in James’s favor for $1,270,962.89, plus conditional
    appellate fees based on the jury verdict.
    Chemical contends that the judgment against it on James’s counterclaim is
    error for a number of reasons, but we address only the first one because we find it
    dispositive. According to Chemical, paragraph 26 is a waiver of consequential
    damages—an affirmative defense—not a covenant not to sue, and thus cannot
    support a breach of contract claim or an award of attorney’s fees. James responds
    that paragraph 26 includes both a waiver of consequential damages and a covenant
    not to sue. Resolving this issue requires us to determine the meaning of paragraph
    26.
    1.     Standard of review
    Interpretation of an unambiguous contract is a question of law for the court to
    decide de novo. URI, Inc. v. Kleberg County, 
    543 S.W.3d 755
    , 763 (Tex. 2018).
    Again, when a contract’s meaning is disputed, our primary objective is to ascertain
    and give effect to the parties’ intent as expressed in the instrument. Id.; Italian
    Cowboy Partners, Ltd. v. Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 333 (Tex.
    2011). Objective manifestations of intent control, not what one side or the other
    alleges they intended to say but did not. 
    URI, 543 S.W.3d at 763-64
    . We therefore
    “presume parties intend what the words of their contract say” and interpret contract
    language according to its “plain, ordinary, and generally accepted meaning” unless
    the instrument directs otherwise. 
    Id. at 764.
    We also examine and consider the
    entire contract in an effort to harmonize and give effect to all provisions of the
    contract so that none are rendered meaningless. Italian Cowboy 
    Partners, 341 S.W.3d at 333
    .
    58
    2.     Application
    We begin by quoting paragraph 26 in its entirety:
    26     WAIVER OF CONSEQUENTIAL DAMAGES
    Neither [Chemical] nor [James] shall be liable to the other for any
    consequential, incidental, indirect or punitive damages of any kind or
    character, including, but not limited to, loss of use, loss of profit, loss
    of revenue, loss of productivity, loss of efficiency, or acceleration costs
    whenever arising under this Contract or as a result of, relating to or in
    connection with the Work and no claim shall be made by either
    [Chemical] or [James] against the other for such damages
    REGARDLESS WHETHER SUCH CLAIM IS BASED OR
    CLAIMED TO BE BASED ON NEGLIGENCE OR STRICT
    LIABILITY (INCLUDING SOLE, JOINT, ACTIVE, PASSIVE,
    CONCURRENT NEGLIGENCE OR GROSS NEGLIGENCE) OR
    ANY OTHER THEORY OF LEGAL LIABILITY, AND
    INCLUDING PRE-EXISTING CONDITIONS BUT EXCLUDING
    GROSS NEGLIGENCE AND WILLFUL MISCONDUCT.
    (Italics added for emphasis; capitalization and bold in original). James emphasizes
    the italicized language that “no claim shall be made” for the described damages as
    support for its argument that paragraph 26 is a covenant not to sue. Chemical
    counters that James ignores the rest of the paragraph, including particularly the first
    clause and the capitalized language, which show that the parties intended this section
    merely to prevent either party from recovering on a claim for “consequential,
    incidental, indirect or punitive” damages regardless of the legal theory of liability
    asserted.
    Chemical relies on National Property Holdings, L.P. v. Westergren, 
    453 S.W.3d 419
    , 428-29 (Tex. 2015) (per curiam), a case that examined among other
    issues whether a party who releases a claim and later files suit on that claim
    necessarily breaches the release agreement, and whether the release and other
    agreements there at issue included a covenant not to sue. In that case, the parties
    59
    disputed the meaning of a mediated settlement agreement, an oral side agreement,
    and a subsequent written release. 
    Id. at 421.
    After disputes arose over the scope and
    meaning of the settlement agreements and the release, Westergren claimed the
    settlement had not been fully performed and sued the other parties for breach of
    contract and other claims. The other parties filed a counterclaim, asserting that
    Westergren breached the settlement agreement and the release by filing suit against
    them.        
    Id. at 422.
      The trial court rendered a take-nothing judgment on the
    counterclaim, and the court of appeals affirmed. In the supreme court, the counter-
    claimants argued that a party who releases a claim and later files suit on that claim
    breaches the release agreement. 
    Id. at 428.
    The court rejected this argument based
    on the release language contained in both the settlement agreement and the
    subsequent release document. Neither instrument, the court held, contained an
    express or implied covenant not to sue. 
    Id. Rather, the
    language in those documents
    indicated an intent to establish an affirmative defense to any future suit. 
    Id. As the
    court stated, “[a]lthough the release provides an affirmative defense to future suits,
    we cannot construe it as including a covenant not to sue where, in fact, the plain
    language does not bar future suits.” 
    Id. at 428-29.
    The court affirmed the judgment
    that Westergren did not breach the settlement agreement and release by filing the
    later suit. Chemical argues that paragraph 26, like the contract language examined
    in Westergren, functions as a defense to a claim of consequential damages, not as a
    basis for a breach-of-contract claim.
    James, on the other hand, likens the present text to language it says several
    courts have construed or characterized as a covenant not to sue.37 Among these, the
    37
    James cites Palestine Contractors, Inc. v. Perkins, 
    386 S.W.2d 764
    , 765 n.1 (Tex. 1964)
    (reciting the parties’ agreement “not to sue, make claim, or institute any action or proceeding
    directly or indirectly against” the other “to recover damages of any kind or character”); Felix v.
    Prosperity Bank, No. 01-14-00997-CV, 
    2015 WL 9242048
    , at *1 (Tex. App.—Houston [1st Dist.]
    Dec. 17, 2015, no pet.) (mem. op.) (bank agreement with depositor provided that, if depositor
    60
    most comparable contract text appears in the First Court of Appeals’s opinion in
    Felix. See 
    2015 WL 9242048
    , at *1. There, fraudulent wire transfers allegedly were
    made from Felix’s deposit account with Prosperity Bank. The account was governed
    by a written deposit agreement, which required Felix to examine his statements and
    comply with specified procedures for reporting unauthorized transactions. 
    Id. at *1.
    The agreement spelled out certain consequences for the failure to timely report
    disputed transactions, including that “you cannot assert a claim against us” as to any
    challenged items in a particular statement not timely reported. 
    Id. Felix sued
    the
    bank for unauthorized transfers. The bank moved for summary judgment based on
    the agreement and Felix’s failure to timely notify the bank of the subject
    transactions. 
    Id. The trial
    court granted summary judgment to the bank but awarded
    no attorney’s fees. On appeal, the bank argued that it was entitled to fees under Civil
    Practice and Remedies Code chapter 38 because Felix breached the contract by suing
    the bank despite his agreement that he could not assert a claim if he failed to report
    unauthorized transactions timely. 
    Id. at *2.
    The court of appeals agreed with the
    bank, concluding that the bank had enforced a material contract right and thus was
    entitled to fees. 
    Id. at *3.
    As James notes, the Felix court referred to the deposit
    agreement’s relevant language as a “covenant not to sue.” But the court did not
    discuss whether that was an appropriate characterization and it does not appear the
    failed to meet certain conditions, depositor “cannot assert a claim against us on any items in that
    statement, and the loss will be entirely yours”); Caspary v. Woodruff, No. 13-98-00106-CV, 
    2000 WL 35729203
    , at *11 (Tex. App.—Corpus Christi Aug. 31, 2000, pet. denied) (not designated for
    publication) (stock repurchase agreement provided, “sellers covenant . . . to neither institute nor
    participate in any arbitration or legal action” against other party); Pape Equip. Co. v. I.C.S., Inc.,
    
    737 S.W.2d 397
    , 400-01 (Tex. App.—Houston [14th Dist.] 1987, writ ref’d n.r.e.) (agreement “not
    to sue, claim or make claims or institute any action or proceeding directly or indirectly against”
    other “to recover damages of any kind or character”); see also Knutson v. Morton Foods, Inc., 
    603 S.W.2d 805
    , 811 (Tex. 1980) (Denton, J., concurring) (stating that “a covenant not to sue is merely
    a promise not to pursue a claim or cause of action.”) (citing Robertson v. Trammell, 
    98 Tex. 364
    ,
    
    83 S.W. 1098
    (1904)).
    61
    parties disputed the issue. Moreover, the complete contract provision at issue in
    Felix is not substantively similar to paragraph 26 in the construction contract before
    us. 
    Id. at *1.
    None of the cases cited by Chemical or James examines a waiver or considers
    whether contract language purporting to be a waiver, as we have here, is a covenant
    not to sue. Black’s defines “waiver” as: “the intentional or voluntary relinquishment
    of a known right” or the “renunciation, repudiation, abandonment, or surrender of
    some claim, right, privilege, or of the opportunity to take advantage of some
    . . . wrong.” Black’s Law Dictionary 1580 (2d ed. 1990). Generally, the elements
    of waiver include (1) an existing right, benefit, or advantage held by a party, (2) the
    party’s actual knowledge of its existence, and (3) the party’s actual intent to
    relinquish the right, or intentional conduct inconsistent with the right. Ulico Cas.
    Co. v. Allied Pilots Ass’n, 
    262 S.W.3d 773
    , 778 (Tex. 2008); Trelltex, Inc. v. Intecx,
    L.L.C., 
    494 S.W.3d 781
    , 790 (Tex. App.—Houston [14th Dist.] 2016, no pet.).
    Parties can waive common law rights by agreement,38 and we respect their freedom
    of contract to do so.39 Typical examples include consequential damage waivers or
    limitation-of-damage clauses, which generally are valid.40
    38
    See In re H.E. Butt Grocery Co., 
    17 S.W.3d 360
    , 374 (Tex. App.—Houston [14th Dist.]
    2000, orig. proceeding); Sedona Contracting, Inc. v. Ford, Powell & Carson, Inc., 
    995 S.W.2d 192
    , 196 (Tex. App.—San Antonio 1999, pet. denied) (discussing waiver of claims in bid form);
    Martin v. Lou Poliquin Enters., Inc., 
    696 S.W.2d 180
    , 186 (Tex. App.—Houston [14th Dist.] 1985,
    writ ref’d n.r.e.) (contractual damage limitation may waive damage rights under common law
    breach of contract theory).
    39
    See Bombardier Aerospace Corp. v. SPEP Aircraft Holdings, LLC, 
    572 S.W.3d 213
    , 230
    (Tex. 2019); Fortis Benefits v. Cantu, 
    234 S.W.3d 642
    , 649 (Tex. 2007) (Texas has “long
    recognized a strong public policy in favor of preserving the freedom of contract”). Absent a
    compelling reason, courts must respect and enforce the terms of a contract that the parties have
    freely and voluntarily made. 
    Bombardier, 572 S.W.3d at 230
    ; Shields Ltd. P’ship v. Bradberry,
    
    526 S.W.3d 471
    , 482 (Tex. 2017).
    40
    See El Paso Mktg., L.P. v. Wolf Hollow I, L.P., 
    383 S.W.3d 138
    , 143-44 (Tex. 2012);
    Sw. Bell Tel. 
    Co., 811 S.W.2d at 577
    (limitation-of-liability clauses are generally valid and
    62
    Construing its plain language, paragraph 26 simply is not a categorical
    covenant not to sue. The provision does not say that the parties agree not to sue each
    other. See 
    Westergren, 453 S.W.3d at 428-29
    ; Guggenheim Corp. Funding, LLC v.
    Valerus Compression Servs., L.P., 
    465 S.W.3d 673
    , 692-93 (Tex. App.—Houston
    [14th Dist.] 2015, pet. denied) (declining to interpret contractual provision as
    covenant not to sue in the absence of explicit language preventing party from filing
    suit). For example, a lawsuit for direct damages is not prohibited. In contrast, the
    principal cases upon which James relies are materially different from today’s case
    because the parties in Perkins, Caspary, and Pape Equipment, unlike Chemical,
    agreed not to sue, or to institute, or to participate in, any legal action. Cf. 
    Perkins, 386 S.W.2d at 765
    n.1; Caspary, 
    2000 WL 35729203
    , at *11; Pape 
    Equip., 737 S.W.2d at 400-01
    . Though the agreement in Felix did not contain that critical
    language, Felix is distinguishable for the reasons stated above. So, Chemical has
    not breached paragraph 26 by filing a lawsuit.
    Paragraph 26 says that the parties will not be liable to each other for certain
    types of damages and will make no claims against the other for the proscribed
    damages regardless of the legal theory offered in support of them. Persuasively,
    courts in Texas and elsewhere have characterized contract language to the effect that
    no party “shall be liable to the other,” and parties shall “make no claim” or “no claim
    shall be made,” as a waiver. See Le Norman Operating LLC v. Chalker Energy
    Partners III, LLC, 
    547 S.W.3d 27
    , 32 (Tex. App.—Houston [1st Dist.] 2017, pet.
    granted) (contract providing “neither party shall be liable to the other party” for
    consequential damages was waiver); MEMC Pasadena, Inc. v. Riddle Power, LLC,
    enforceable); DaimlerChrysler Motors Co. v. Manuel, 
    362 S.W.3d 160
    , 183 (Tex. App.—Fort
    Worth 2012, no pet.); Tenn. Gas Pipeline, 
    2008 WL 3876141
    , at *6-8; see also Vallance & Co. v.
    De Anda, 
    595 S.W.2d 587
    , 589-90 (Tex. App.—San Antonio 1980, no writ) (discussing liquidated
    damages provision; contracting parties can limit their liability in damages to a specified amount).
    63
    
    472 S.W.3d 379
    , 385 (Tex. App.—Houston [14th Dist.] 2015, no pet.) (same);
    Perez-Gurri Corp. v. McLeod, 
    238 So. 3d 347
    , 351 (Fla. Dist. Ct. App. 2017)
    (contract language stating “no claim . . . shall be made” for delay damages was part
    of waiver provision); Barhorst v. Thatcher, 
    144 N.E.2d 272
    , 274 (Ohio Ct. App.
    1956).
    We conclude that paragraph 26, read as a whole—including the “no claim
    shall be made” clause—evinces the parties’ intent to relinquish any claim they may
    ever have for consequential damages arising under the construction contract.41 The
    parties used language one would reasonably expect to be used in drafting a waiver
    of damages clause42 and indeed entitled paragraph 26 “Waiver of Consequential
    Damages.” See RSUI Indemnity 
    Co., 466 S.W.3d at 121
    (“Generally, courts should
    construe contractual provisions in a manner that is consistent with the labels the
    parties give them.”). Relinquishing a claim is the essence of a waiver, which can be
    accomplished by written agreement pre-dispute and pre-injury. See 
    Tenneco, 925 S.W.2d at 643
    (a party’s express renunciation of a known right can establish waiver);
    
    Sedona, 995 S.W.2d at 196
    (discussing waiver of claims in a bid form). Applying
    the traditional elements of waiver, (1) the parties waived a right existing at the time
    of contracting because they understood they had right to complain and seek damages
    in the event of a breach of contract; (2) the contract shows the parties’ constructive
    knowledge of rights to sue for damages in the event of breach;43 and (3) the language
    is clear that the parties intend to relinquish a right to claim certain types of damages
    41
    The provision limits liability on other types of damages as well, but only consequential
    damages are at issue here.
    42
    Le Norman 
    Operating, 547 S.W.3d at 32
    ; MEMC Pasadena, 
    Inc., 472 S.W.3d at 385
    ;
    Perez-Gurri 
    Corp., 238 So. 3d at 351
    ; 
    Barhorst, 144 N.E.2d at 274
    .
    43
    This is evident from at least paragraphs 9, 17, 19, and 21, already discussed at length.
    Also, paragraph 27 assigns Texas law as governing any “disputes” arising from the contract.
    64
    for breach. See 
    Sedona, 995 S.W.2d at 196
    . We disagree with appellants that one
    small clause, excised from the whole paragraph, also constitutes a covenant not to
    sue when that intent is not plainly expressed. The part of paragraph 26 stating that
    “no claim shall be made” for the described damages regardless of the theory offered
    to support them merely defines the extent of the waiver.
    We therefore agree with Chemical that paragraph 26 is a waiver of certain
    damages; it is not also a covenant not to sue. The difference between agreeing not
    to sue each other and agreeing to narrow the scope of recoverable damages in the
    event of suit is subtle but consequential.44 Paragraph 26 is the latter agreement, not
    the former. James may (and did) assert paragraph 26 as an affirmative defense to
    Chemical’s claims. But James is not entitled to recover attorney’s fees under chapter
    38 to the extent it prevailed on that defense. See N. Star Water Logic, LLC v.
    Ecolotron, Inc., 
    486 S.W.3d 102
    , 107 (Tex. App.—Houston [14th Dist.] 2016, no
    pet.) (party cannot recover fees for successfully defending breach of contract claim);
    see also Green 
    Int’l, 951 S.W.2d at 390
    (“To recover attorney’s fees under Section
    38.001, a party must (1) prevail on a cause of action for which attorney’s fees are
    recoverable, and (2) recover damages.”). In short, paragraph 26 means that James
    is not liable for any consequential damages, not that James may recover its attorney’s
    fees for defending against Chemical’s claims for consequential damages. We reject
    appellants’ argument that paragraph 26 constitutes both a consequential damages
    waiver and a covenant not to sue.
    We sustain Chemical’s first cross-issue, which requires rendition of a take-
    nothing judgment on James’s counterclaim for breach of paragraph 26.
    Accordingly, we need not reach appellants’ sixth issue.
    44
    Parties are presumed to know and understand the legal effect of their contracts and
    waivers. 
    Trelltex, 494 S.W.3d at 792
    .
    65
    B.    Attorney’s Fees Against James
    In Chemical’s second cross-issue, it contends that the trial court erred in
    denying Chemical recovery of attorney’s fees against James. The judgment does not
    grant Chemical recovery of fees under section 38.001 against James because James
    is a limited liability company. This court and others have held that chapter 38 does
    not permit recovery of attorney’s fees from a limited liability company. Vast
    
    Constr., 526 S.W.3d at 728
    ; Alta 
    Mesa, 488 S.W.3d at 452-55
    . Chemical invites us
    to overrule our precedent in its second cross-issue.       We decline Chemical’s
    invitation, and in any event only an en banc majority can overrule this court’s
    precedent. See Tex. R. App. P. 41.2(c). We overrule Chemical’s second cross-issue.
    Conclusion
    In sum, we hold the following.
    We overrule appellants’ first issue because the evidence is legally sufficient
    to support the jury’s liability and damages findings regarding James’s breach of
    paragraph 21.3, the termination provision. Due to our resolution of appellants’ first
    issue, we do not reach their second and seventh issues, and we overrule their fifth
    issue. We overrule appellants’ third issue because the evidence is legally sufficient
    to support the jury’s liability and damages findings regarding James’s breach of
    paragraph 19.1, the indemnity provision. We affirm the portion of the judgment
    awarding Chemical its breach-of-contract damages in the amount of $1,157,019.50,
    plus pre-judgment and post-judgment interest and taxable costs related to that sum
    as set forth in the judgment.
    We overrule appellants’ fourth issue because Chemical established that
    Primoris breached the Guaranty, and legally sufficient evidence supports the amount
    awarded. We affirm the portion of the judgment awarding to Chemical from
    66
    Primoris $2,923,600.50 in attorney’s fees for representation through trial and the
    completion of proceedings in the trial court, plus post-judgment interest on that
    amount as set forth in the judgment.
    We sustain Chemical’s first cross-issue because paragraph 26 is not a
    covenant not to sue but is only a waiver of certain damages. Therefore, it cannot
    support a judgment for breach of contract. Due to our resolution, we do not reach
    appellants’ sixth issue. We delete that portion of the judgment awarding damages
    to James on its counterclaim, and we render a take-nothing judgment in Chemical’s
    favor as to that claim. We overrule Chemical’s second cross-issue because chapter
    38 does not permit recovery of attorney’s fees against a limited liability company.
    We affirm the trial court’s judgment as so modified.
    /s/    Kevin Jewell
    Justice
    Panel consists of Chief Justice Frost and Justices Jewell and Bourliot. (Frost, C.J.,
    concurring and dissenting).
    67
    

Document Info

Docket Number: 14-18-00083-CV

Filed Date: 12/17/2019

Precedential Status: Precedential

Modified Date: 12/17/2019

Authorities (79)

Southern Mortgage Co. v. McGregor , 279 S.W. 860 ( 1926 )

Tinsley v. Dowell , 87 Tex. 23 ( 1894 )

Mega Child Care, Inc. v. Texas Department of Protective & ... , 2000 Tex. App. LEXIS 6517 ( 2000 )

Texas Gas Corporation v. Hankamer , 1959 Tex. App. LEXIS 2055 ( 1959 )

Handelman v. Handelman , 1980 Tex. App. LEXIS 4052 ( 1980 )

Cleveland & Cameron v. Heidenheimer , 92 Tex. 108 ( 1898 )

Varner v. Cardenas , 50 Tex. Sup. Ct. J. 525 ( 2007 )

Prodigy Communications Corp. v. Agricultural Excess & ... , 52 Tex. Sup. Ct. J. 475 ( 2009 )

Regal Finance Co. v. Tex Star Motors, Inc. , 53 Tex. Sup. Ct. J. 1034 ( 2010 )

Ulico Casualty Co. v. Allied Pilots Ass'n , 51 Tex. Sup. Ct. J. 1320 ( 2008 )

Broders v. Heise , 39 Tex. Sup. Ct. J. 752 ( 1996 )

DaimlerChrysler Motors Co., LLC v. Manuel , 2012 Tex. App. LEXIS 1489 ( 2012 )

Palestine Contractors, Inc. v. Perkins , 386 S.W.2d 764 ( 1964 )

McMahan v. Greenwood , 2003 Tex. App. LEXIS 4662 ( 2003 )

Cox v. Lerman , 1997 Tex. App. LEXIS 3807 ( 1997 )

OXY USA, INC. v. Cook , 127 S.W.3d 16 ( 2003 )

Jasper Federal Savings & Loan Ass'n v. Reddell , 30 Tex. Sup. Ct. J. 461 ( 1987 )

Small v. Ciao Stables, Inc. , 289 Md. 554 ( 1981 )

Kansas City, El Paso & Mexican Railway Co. v. Perkins , 88 Tex. 66 ( 1895 )

Linch v. Paris Lumber and Grain Elevator Co. , 80 Tex. 23 ( 1891 )

View All Authorities »