City of Alton, Carter & Burgess, Inc., Turner, Collie & Braden, Inc., and Cris Equipment Company, Inc. v. Sharyland Water Supply Corporation ( 2008 )


Menu:
  •                              NUMBER 13-06-00038-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    CITY OF ALTON, CARTER & BURGESS, INC.,
    TURNER, COLLIE & BRADEN, INC., AND CRIS
    EQUIPMENT COMPANY, INC.,                                                     Appellants,
    v.
    SHARYLAND WATER SUPPLY CORPORATION,                                          Appellee.
    On appeal from the 206th District Court of Hidalgo County, Texas.
    OPINION
    Before Justices Yañez, Rodriguez, and Garza
    Opinion by Justice Rodriguez
    This case arises from the installation of a sanitary sewer system. By four issues,
    appellant/cross-appellee, the City of Alton (Alton), contends the following: (1) it is immune
    from suit;1 (2) in the alternative, the trial court should not have submitted breach of contract
    issues; (3) there were no compensable damages and there was no evidence of damages
    caused by Alton; and (4) appellee/cross-appellant, Sharyland Water Supply Corporation
    (Sharyland), cannot recover attorney's fees against Alton. Appellants, Carter and Burgess,
    Inc. (C&B), Turner, Collie & Braden, Inc. (TCB), and Cris Equipment Company, Inc. (Cris),
    challenge, among other things, the status of Sharyland as a third-party beneficiary to their
    respective contracts with Alton. They also contend that the trial court erred in submitting
    a negligence question because that claim is barred by the economic loss rule.
    Furthermore, C&B, TCB, and Cris complain of the trial court's imposition of joint liability and
    attorney's fees against all defendants. Finally, cross-appellant, Sharyland, asserts that the
    trial court erred in refusing to grant equitable relief in lieu of the monetary damages
    awarded by the jury. We affirm in part, reverse and render in part, and reverse and
    remand in part, as to appellant Alton; we reverse and render as to appellants C&B, TCB,
    and Cris; and we affirm as to cross-appellant Sharyland.
    I. Factual Background
    In the early 1980s, Alton, a Class A municipality located in Hidalgo County, Texas,
    installed a water distribution system to provide potable water to its residents.2 Beginning
    1 Alton claim s governm ental im m unity. See Tooke v. City of Mexia, 197 S.W .3d 325, 331 n.11 (Tex.
    2006) (citing W ichita Falls State Hosp. v. Taylor, 106 S.W . 3d 692, 694 n.3 (Tex. 2003) ("Courts often use the
    term s sovereign im m unity and governm ental im m unity interchangeably. However, they involve two distinct
    concepts. Sovereign im m unity refers to the State's im m unity from suit and liability. In addition to protecting
    the State from liability, it also protects the various divisions of state governm ent, including agencies, boards,
    hospitals, and universities. Governm ental im m unity, on the other hand, protects political subdivisions of the
    State, including counties, cities, and school districts.")); Harris County v. Sykes, 136 S.W .3d 635, 638 (Tex.
    2004) (concluding that governm ental im m unity operates like sovereign im m unity and affords a sim ilar
    protection to political subdivisions of the State, including counties and cities).
    2 Potable water is water that is suitable for drinking. See M ERR IAM -W EBSTER O NLINE D IC TIO NAR Y ,
    available at http://www.m erriam -webster.com /dictionary/potable (last visited Nov. 24, 2008).
    2
    in 1981, Alton and Sharyland entered into numerous water service agreements (collectively
    referred to as the Water Service Agreement). By the Water Service Agreement, Sharyland
    agreed to sell and deliver water and/or sewer service to Alton, and Alton agreed to
    purchase and receive water and/or sewer service from Sharyland. In order to obtain water
    for its new system, Alton entered into a Water Supply Agreement with Sharyland, a non-
    profit rural water supply corporation, on August 12, 1982. Under the 1982 agreement,
    Alton conveyed its new water distribution system to Sharyland, and Sharyland agreed to
    provide Alton with water.
    During the 1990's, the citizens of Alton relied on septic systems and outhouses for
    sewage disposal. In 1994, Alton obtained development grants for the installation of a
    sanitary sewer system. Part of the septic system was built in the public right-of-way and
    another part connected the septic system from the public right-of-way to individual houses.
    For the public right-of-way phase, Alton entered into contracts with L.L. Rodriguez and
    Associates to design a sanitary sewer system; C&B to manage the project; and TCB to
    provide inspection services for the construction phase. Alton also contracted with Cris for
    installation of the sewer main and the residential service connections within the public right-
    of-way. Cris subcontracted with Grab Pipeline Services, Inc., to assist in the installation.3
    The construction of the sewer system was completed in 1999.
    Alton's sewer system consists of main sewer lines, residential service connections,
    and yard lines. The residential service connections join perpendicular to the main sewer
    line and run horizontally from the main sewer line to the residential property line where they
    3 The jury found no liability on the part of L.L. Rodriguez and Associates or Grab Pipeline Services,
    Inc., and those entities are not parties to this appeal.
    3
    connect with the yard line. The yard line runs from the property line to the individual home
    to complete each residential connection. In certain locations, Alton's sewer main and
    Sharyland's water main run parallel to each other in a public right-of-way, resulting in some
    of Alton's residential service connections crossing Sharyland's water main in order to
    connect to the yard lines. The residential service connections are the only portions of
    Alton's sewer system at issue in this case.4
    II. Procedural Background
    A. Pleadings
    On March 3, 2000, Sharyland sued Alton for breach of the Water Supply Agreement
    and the Water Service Agreement.5 Sharyland also sued C&B, TCB, and Cris, all
    engineering firms, for negligence and breach of contract. In addition, Sharyland asked the
    trial court to enjoin Alton from operating sewer lines across Sharyland's waterlines in a
    wrongful manner and to compel Alton to reconstruct the sewer lines in a manner consistent
    with the parties' agreements, state law, and proper engineering practice.
    Sharyland alleged that the sanitary sewer residential service connections were
    installed in violation of state regulations and industry standards and represented a threat
    to Sharyland's potable water system. Sharyland sought a declaration of the parties' rights
    4 Sascon Construction C o. (Sascon) installed the yard lines on private property. Sascon is not a
    party to the lawsuit.
    5 Sharyland also alleged negligence and nuisance claim s against Alton. At the close of the evidence
    at trial, however, Sharyland dropped its claim for negligence. It had earlier dropped its nuisance claim . The
    issue of breach of contract, as against Alton, was subm itted to the jury.
    In addition, an issue on unconstitutional taking was subm itted; however, the jury found that Alton did
    not com m it an unconstitutional taking of Sharyland's property. It also found that Sharyland was not estopped
    from com plaining about the m anner in which the sewer system was installed. These findings are not
    challenged on appeal.
    4
    and obligations under section 317.13 of the Texas Commission on Environmental Quality
    Design Criteria for Sewerage Systems (the Commission) as it related to the construction
    of the sewer system in proximity to its waterlines.6                       See 30 TEX . ADMIN . CODE §
    317.13(1)(B) (2008) (33 TEX . REG . 2126, 2234, adopted 33 TEX . REG . 6928 (2008) (codified
    at 30 Tex. Admin. Code. Ann. §§217.1-.33).
    Alton counterclaimed, asking the trial court to declare its August 12, 1982 Water
    Supply Agreement with Sharyland null and void. In response, Sharyland asserted that
    Alton's counterclaim was preempted and/or barred by, among other things, the provisions
    of section 1926(b) of title 7 of the United States Code, which limits a government's
    authority to curtail the service provided by a utility during the term of repayment of a federal
    loan. See 7 U.S.C.A. § 1926(b) (1999).7
    B. Motions for Summary Judgment
    6 Section 317.13, a regulation prom ulgated by the Texas Com m ission on Environm ental Quality (the
    Com m ission), provides as follows:
    W here a sanitary sewer crosses a waterline and the sewer is constructed of cast iron, ductile
    iron, or PVC with a m inim um pressure rating of 150 psi, an absolute m inim um distance of six
    inches between outside diam eters shall be m aintained. In addition, the sewer shall be
    located below the waterline where possible, and one length of the sewer pipe m ust be
    centered on the waterline.
    30 T EX . A D M IN . C O DE § 317.13(1)(B) (2008) (33 T EX . R EG . 2126, 2234, adopted 33 T EX . R EG . 6928 (2008)
    (codified at 30 T EX . A D M IN . C OD E A N N . §§217.1-.33).
    7 Providing for water and waste facility loans and grants, section 1926(b) sets out the following:
    The service provided or m ade available through any such association shall not be curtailed
    or lim ited by inclusion of the area served by such association within the boundaries of any
    m unicipal corporation or other public body, or by the granting of any private franchise for
    sim ilar service within such area during the term of such loan; nor shall the happening of any
    such event be the basis of requiring such association to secure any franchise, license, or
    perm it as a condition to continuing to serve the area served by the association at the tim e of
    the occurrence of such event.
    7 U.S.C.A. § 1926(b) (1999).
    5
    Sharyland filed two motions for summary judgment.                        In its motion for partial
    summary judgment Sharyland asked the trial court to grant its request for declaratory
    judgment relief and declare that section 317.13 applied to all sewers located in proximity
    with waterlines in this case. See 30 TEX . ADMIN . CODE ANN . § 317.13(1)(B). In its motion
    for summary judgment, Sharyland urged that section 1926(b) barred Alton's counterclaim.
    See 7 U.S.C.A. § 1926(b). The trial court granted Sharyland's motion for partial summary
    judgment on its declaratory judgment claim finding that section 317.13 "applies to the
    situation presented in this case" and that "[t]he term 'sewer' in the context of . . . [c]hapter
    317 refers to 'a conduit which carries off water or waste matter' and includes sanitary sewer
    residential service connections." See 30 TEX . ADMIN . CODE § 317.13. The trial court also
    granted Sharyland's motion for summary judgment, concluding that section 1926(b) barred
    Alton's counterclaim and ordering that Alton take nothing by its counterclaim against
    Sharyland. See 7 U.S.C. § 1926(b).
    C. Jury Trial
    Sharyland's breach of contract claim against Alton and its breach of contract and
    negligence claims against C&B, TCB, and Cris were tried to a jury. The jury found that
    Alton breached its Water Supply Agreement with Sharyland by failing to maintain required
    separation distance between sewer lines and that it breached the Water Service
    Agreement by failing to comply with Sharyland's rules and regulations.8 The jury also
    8 The jury found that Alton failed to com ply with the following provision— paragraph 6— of the W ater
    Supply Agreem ent:
    In the event of the installation of a sewer system , such sewer lines and system s shall rem ain
    a required distance from the water lines and all septic tank drain fields shall be at least ten
    (10) feet from the water lines, or as otherwise prescribed by the rules and regulations of the
    Texas State Departm ent of Health.
    6
    found that C&B, TCB, and Cris each breached their respective contracts with Alton and
    that Sharyland was a third-party beneficiary of those contracts. Finally, the jury found that:
    (1) C&B, TCB, and Chris were negligent; (2) such negligence was the proximate cause of
    damages to Sharyland; and (3) liability should be apportioned jointly and severally, at 20%
    for C&B, 40% for TCB, and 40% for Cris. The jury assessed damages at $1,139,000 and
    awarded Sharyland attorney's fees in the amount of $510,221.68 through trial, with
    additional awards of $125,000 should appeals be filed in the court of appeals and the
    Texas Supreme Court.
    D. Post-Trial Hearings and Entry of Judgment
    The trial court conducted post-trial hearings. After hearing arguments of counsel
    and receiving evidence regarding equitable relief and attorney's fees, the trial court entered
    final judgment awarding Sharyland monetary damages and attorney's fees against Alton,
    C&B, TCB, and Cris, but denying Sharyland's claims for injunctive relief and specific
    performance. All motions for new trial were heard and overruled. All parties appealed from
    the judgment.
    III. Sharyland's Breach of Contract Claim Against Alton
    A. Governmental Immunity
    By its first issue, Alton contends that the court has no jurisdiction over Sharyland's
    breach of contract claims because it has not waived its governmental immunity. In
    The jury also found that Alton failed to com ply with the following provision— paragraph 5— of the W ater Service
    Agreem ent:
    The Corporation [Sharyland] agrees to sell and deliver water and/or sewer service to the
    Mem ber [Alton] and Mem ber agrees to purchase and receive water and/or sewer service
    from the Corporation, in accordance with the bylaws and rules and regulations of the
    Corporation as am ended from tim e to tim e by the Corporation.
    7
    response, Sharyland argues Alton's immunity has been waived by an equitable waiver of
    immunity, by Alton's counterclaim asking the court to declare the contracts between
    Sharyland and Alton void, and by sections 271.151-.160 of the Texas Local Government
    Code. See TEX . LOCAL GOV'T CODE ANN . §§ 271.151-.160 (Vernon 2005).
    1. Standard of Review and Applicable Law
    Governmental immunity deprives a trial court of subject-matter jurisdiction for
    lawsuits in which certain governmental units have been sued, unless the governmental unit
    consents to suit. See Harris County v. Sykes, 
    136 S.W.3d 635
    , 638 (Tex. 2004); Tex.
    Dep't of Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 224 (Tex. 2004). Whether a trial
    court has subject-matter jurisdiction is a question of law. 
    Miranda, 133 S.W.3d at 226
    .
    In Texas, governmental immunity has two components: (1) immunity from liability,
    which bars enforcement of a judgment against a governmental entity, and (2) immunity
    from suit, which bars suit against the entity altogether. Tooke v. City of Mexia, 
    197 S.W.3d 325
    , 332 (Tex. 2006). By entering into a contract, a governmental entity necessarily
    waives immunity from liability, voluntarily binding itself like any other party to the terms of
    the agreement, but it does not waive immunity from suit. 
    Id. Texas courts
    consistently
    defer to the legislature to waive immunity from suit because this allows the legislature to
    protect its policymaking function. 
    Id. This is
    particularly true in the context of contract
    claims, where "legislative control over [governmental] immunity allows the legislature to
    respond to changing conditions and revise existing agreements if doing so would benefit
    the public." 
    Id. (quoting Tex.
    Natural Res. Conservation Comm'n v. IT-Davy, 
    74 S.W.3d 849
    , 854 (Tex. 2002)); see Catalina Dev. Inc. v. County of El Paso, 
    121 S.W.3d 704
    , 705-
    8
    06 (Tex. 2003). To ensure that legislative control is not lightly disturbed, a waiver of
    immunity must be "clear and unambiguous." 
    Tooke, 197 S.W.3d at 332-33
    .
    2. Equitable Waiver of Immunity by Conduct
    Sharyland first asserts that Alton's conduct constitutes an equitable basis on which
    this Court should hold Alton waived its governmental immunity from suit. Among other
    things, Sharyland argues that Alton did not simply breach its contractual duties, but through
    an intentional course of conduct chose to leave leaking sewer lines installed over
    Sharyland's waterlines in violation of state law and contrary to industry standards and
    engineering specifications. Sharyland contends that Alton's conduct threatens the safety
    of the public's water supply and is "a gross and reprehensible dereliction of its duties to its
    citizens." While Sharyland recognizes that the supreme court has never articulated a
    circumstance where an equitable waiver of immunity might be appropriate, it urges this
    Court to fashion a waiver-by-conduct exception in this case.
    In Federal Sign v. Texas Southern University, the supreme court recognized that
    "[t]here may be other circumstances where the State may waive its immunity by conduct
    other than simply executing a contract so that it is not always immune from suit when it
    contracts." 
    951 S.W.2d 401
    , 408 n.1 (Tex. 1997), superseded by statute on other grounds
    as stated in Gen. Servs. Comm'n v. Little-Tex Insulation Co., 
    39 S.W.3d 591
    , 593 (Tex.
    2001). A year later, while noting that several appellate courts have relied on that language
    to create a "judicially-imposed, equitable waiver of immunity from suit by conduct," the
    supreme court reaffirmed "that it is the legislature's sole province to waive or abrogate
    sovereign immunity." 
    IT-Davy, 74 S.W.3d at 856-57
    ("Creating a waiver-by-conduct
    exception would force the State to expend its resources to litigate the waiver-by-conduct
    9
    issue before enjoying sovereign immunity's protections and this would defeat many of the
    doctrine's underlying policies."). The supreme court has not provided for the exception
    urged by Sharyland, and we decline to create one in this case. "We instead follow the
    supreme court preceden[t] that it is the legislature's sole province to waive sovereign
    immunity." My-Tech, Inc. v. Univ. of N. Tex. Health Sci. Ctr., 
    166 S.W.3d 880
    , 884 (Tex.
    App.–Dallas 2005, pet. denied) (citing, e.g., Lubbock County v. Trammel's Lubbock Bail
    Bonds, 
    80 S.W.3d 580
    , 585 (Tex. 2002) ("It is not the function of a court of appeals to
    abrogate or modify established precedent.")). Thus, we conclude that Alton's conduct in
    this case does not constitute an equitable basis upon which this Court could hold that Alton
    waived its governmental immunity from suit.
    3. Waiver of Immunity by Filing a Counterclaim
    Relying on Reata Construction Corporation v. City of Dallas, Sharyland also argues
    that Alton waived its immunity when it filed its counterclaim for a declaratory judgment.
    See 
    197 S.W.3d 371
    , 376-77 (Tex. 2004). In Reata, the supreme court held that if a city
    interjects itself in litigation asserting an affirmative claim for monetary damages, immunity
    may be partially waived. 
    Id. Here, Alton's
    counterclaim asked that the trial court declare
    the Water Supply Agreement between Sharyland and Alton void under a variety of
    theories. Alton made no claim for monetary damages; thus, it did not waive, even partially,
    its immunity by its counterclaim. See 
    id. 4. Waiver
    of Immunity Under Section 271.152
    Finally, Sharyland argues Alton's immunity from suit has been waived by the Texas
    Local Government Code. See TEX . LOCAL GOV'T CODE ANN . §§ 271.151-.160. In this case,
    we agree.
    10
    The Texas Local Government Code waives a local government's immunity from suit
    for certain contractual claims. Section 271.152 provides that
    [a] local governmental entity that is authorized by statute or the constitution
    to enter into a contract and that enters into a contract subject to this
    subchapter waives sovereign immunity to suit for the purpose of adjudicating
    a claim for breach of the contract, subject to the terms and conditions of this
    subchapter.
    
    Id. § 271.152.
    The statute defines a "contract subject to this subchapter" as "a written
    contract stating the essential terms of the agreement for providing goods or services to the
    local governmental entity that is properly executed on behalf of the local governmental
    entity." 
    Id. § 271.151(2).
    Sharyland asserts, and Alton concedes, that the agreements in
    this case involve services. Thus, pursuant to sections 271.151(2) and 271.152, we
    conclude that the agreements at issue in this case fall within the provisions of the statute
    because they involve services.                 See 
    id. §§ 271.151(2),
    271.152.                  Thus, Alton's
    governmental immunity to suit for purposes of adjudicating Sharyland's breach of contract
    claim has been waived, and we overrule Alton's first issue on this basis.9
    B. Submission of Jury Issue on
    Breach of Paragraph 6 of the Water Supply Agreement
    By its second issue, Alton contends that the trial court should not have submitted
    a jury question based on the alleged breach of paragraph 6 of the Water Supply
    Agreement.
    9 Relying on section 271.153, Alton also argues that because it did not purchase the services from
    Sharyland and because it was not required to pay any m onies to Sharyland, the contracts are not of the type
    contem plated by the Legislature. See T EX . L O C AL G O V 'T C OD E A N N . § 271.153(a) (Vernon 2005) (lim iting
    dam ages to "the balance due and owed by the local governm ental entity under the contract," "the am ount
    owed for change orders or additional work the contractor is directed to perform by a local governm ental entity
    in connection with the contract," and "interest as allowed by law"); see also § 271.153(b) (excluding
    "consequential dam ages," "exem plary dam ages," or "dam ages for unabsorbed hom e office overhead"). W e
    address this argum ent in our discussion of Alton's third issue.
    11
    1. Standard of Review
    We review alleged jury charge error under an abuse of discretion standard. Shupe
    v. Lingafelter, 
    192 S.W.3d 577
    , 579 (Tex. 2006) (per curiam); Toles v. Toles, 
    45 S.W.3d 252
    , 263 (Tex. App.–Dallas 2001, pet. denied). The trial court has broad discretion in
    submitting jury questions as long as the questions submitted fairly place the disputed
    issues before the jury, see 
    Toles, 45 S.W.3d at 263
    , and the charge is legally correct. See
    Hyundai Motor Co. v. Rodriguez, 
    995 S.W.2d 661
    , 664 (Tex. 1999). "A trial court abuses
    its discretion when it acts arbitrarily and unreasonably, without reference to guiding rules
    or principles, or misapplies the law to the established facts of the case." Downer v.
    Aquamarine Operators, Inc., 
    701 S.W.2d 238
    , 241-42 (Tex. 1985). This Court will not
    reverse a judgment based on charge error in the absence of harm, which results if the error
    "probably caused the rendition of an improper judgment" or "probably prevented the
    appellant from properly presenting the case to the court of appeals." TEX . R. APP. P.
    44.1(a); see Bed, Bath & Beyond, Inc. v. Urista, 
    211 S.W.3d 753
    , 757 (Tex. 2006); Harris
    County v. Smith, 
    96 S.W.3d 230
    , 234-35 (Tex. 2002).
    2. Allegation that Agreement is Void
    Alton first complains that the Water Supply Agreement is void because: (1) it has
    no term of duration; (2) it abdicates a governmental function; (3) it is unconstitutional; and
    (4) it lacks consideration. Sharyland argues that Alton has waived this argument. We
    agree.
    Alton filed a declaratory-judgment counterclaim against Sharyland requesting that
    the trial court declare the Water Supply Agreement void and return the water system and
    its easements to Alton. Sharyland answered by asserting, among other things, that section
    12
    1926(b) barred Alton's counterclaim. See 7 U.S.C.A. § 1926(b).10 Sharyland filed a
    summary judgment motion urging that its affirmative defense barred Alton's counterclaim.
    See 
    id. The trial
    court agreed and granted Sharyland summary judgment on Alton's
    counterclaim.
    Alton has raised no issue related to the trial court's granting of Sharyland's motion
    for summary judgment on its counterclaim.                 See TEX . R. APP. P. 38.1(i); Jacobs v.
    Satterwhite, 
    65 S.W.3d 653
    , 655-56 (Tex. 2001) (per curiam) (citing San Jacinto River
    Auth. v. Duke, 
    783 S.W.2d 209
    , 209-10 (Tex. 1990) (per curiam) (stating that it is a
    "well-established rule that grounds of error not asserted by points of error or argument in
    the court of appeals are waived")). Alton has not challenged Sharyland's section 1926(b)
    affirmative defense, the basis on which the summary judgment was granted. Moreover,
    Alton acknowledges that it is not appealing its counterclaim. Thus, we conclude that Alton
    has waived this argument.
    3. Allegation of Lack of Fair Notice
    Alton also contends that a question regarding its alleged failure to comply with
    paragraph 6 of the Water Supply Agreement should not have been submitted to the jury
    because Alton did not have fair notice that Sharyland intended to complain about this
    paragraph until trial and that the error is not harmless. We disagree.
    In its pleadings and through its written discovery, Sharyland alleged breach of
    paragraph 5 of the Water Supply Agreement, which addresses easements "providing for
    the rights to use, operate, inspect, repair, maintain, replace, remove, enlarge, reconstruct
    10 Alton does not dispute that Sharyland financed the construction and operation of its retail water
    and wastewater system s through loans and grants secured through the Farm er's Hom e Adm inistration and
    that Sharyland continues to be obligated to repay the federal governm ent.
    13
    and service the water supply system . . . ." Over Alton's objection, the trial court submitted
    an issue on breach of paragraph 6, which addresses the separation distance between the
    waterlines and the sewer system. Alton contends that it had been given no notice of
    Sharyland's intention to submit such an issue and had not been given an opportunity to
    perform any discovery on the issue. However, four years before the case was tried, Tim
    Nicolls, Sharyland's General Manager, testified at his deposition that Sharyland was
    complaining of a breach of both paragraphs 5 and 6 of the Water Supply Agreement, as
    well as a breach of the Water Service Agreement. It is not necessary to supplement
    responses to written discovery requests if the additional or corrective information is made
    known to the other party on the record at a deposition. See TEX . R. CIV. P. 193.5(a)(2).
    Thus, we conclude that Alton had fair notice and that the trial court did not abuse its
    discretion in submitting this issue to the jury.
    Because the jury's finding that Alton breached paragraph 6 of the Water Supply
    Agreement supports the jury's verdict and the trial court's judgment against Alton, we need
    not address Alton's remaining argument that a breach of the Water Service Agreement
    cannot support the damages sought by Sharyland. See TEX . R. APP. P. 47.1. We overrule
    Alton's second issue.
    C. Damages Sought by Sharyland
    In its third issue, Alton contends that Sharyland had no compensable damages and
    produced no evidence of damages. Alton also asserts that, if this Court should find that
    Sharyland has compensable damages, they are not recoverable from Alton because its
    damages are limited under section 271.153(a). See TEX . LOCAL GOV 'T CODE ANN . §
    271.153(a). We agree with this last assertion.
    14
    Sharyland sought money damages for, among other things, alleged increased costs
    in operation of its water distribution system, costs to place barriers to mitigate the hazard
    caused by the defendants, costs associated with increased safety precaution and
    maintenance measures it takes when repairing its lines, and lost interest on these sums.
    The charge instructed the jury to consider only "[t]he reasonable cost of the repairs
    necessary to restore the property to its condition immediately before the injury." On
    appeal, Sharyland argues that it is being compelled by Alton to perform work to safeguard
    the water system because Alton refused to install the sewer lines as agreed in the Water
    Supply Agreement. Based on this argument, Sharyland maintains that section 271.153,
    as written, allows the damages that the jury awarded. See 
    id. The total
    amount of money awarded in an adjudication brought against a local
    governmental entity for breach of a contract subject to chapter 271 is limited to the
    following:
    (1) the balance due and owed by the local governmental entity under the
    contract as it may have been amended, including any amount owed as
    compensation for the increased cost to perform the work as a direct result of
    owner-caused delays or acceleration;
    (2) the amount owed for change orders or additional work the contractor is
    directed to perform by a local governmental entity in connection with the
    contract; and
    (3) interest as allowed by law.
    
    Id. In this
    case, section 271.153(a) does not provide Sharyland an avenue for recovery.
    See 
    id. There is
    neither a balance due and owed by Alton under the agreements, nor is
    there any amount due from change orders, additional work, or interest. See 
    id. Thus, Sharyland's
    damages, if any, fall outside the limited damages recoverable under section
    271.153(a). 
    Id. In addition,
    to the extent the damages could be considered consequential
    15
    damages, they are expressly excluded from damages that can be recovered under chapter
    271.    See 
    id. § 271.153(b)(1)
    (providing that "this subchapter may not include
    consequential damages"); see also 
    Tooke, 197 S.W.3d at 346
    (concluding that
    consequential damages of lost profits were excluded by the statute). Therefore, we sustain
    Alton's third issue on this basis.
    D. Attorney's Fees
    By its fourth issue, Alton contends that Sharyland cannot recover attorney's fees
    under section 271.159 of the local government code because there was no written
    agreement between Sharyland and Alton that expressly contracted for such fees. See
    TEX . LOCAL GOV'T CODE ANN . § 271.159 (providing that no attorney's fees shall be awarded
    to any party unless the local governmental entity has entered into a written agreement that
    expressly authorizes the prevailing party to recover attorney's fees). Sharyland argues that
    section 271.159 does not apply retroactively and that under prior law pursuant to Texas
    Civil Practice and Remedies Code section 38.001 for its breach of contract claim, the
    award was appropriate. See TEX . CIV. PRAC . & REM . CODE ANN . § 38.001 (Vernon 2008).
    Sharyland also asserts that it was entitled to attorney's fees under the Declaratory
    Judgment Act (the Act). See 
    id. §§ 37.001-.011
    (Vernon 2008).
    1. Attorney's Fees Under Section 38.001
    We need not determine the applicability of section 271.159 to Sharyland's breach
    of contract claim because, even pursuant to section 38.001, Sharyland cannot recover
    attorney's fees against Alton. Section 38.001(8) permits an award of attorney's fees for a
    suit based on a written contract. See TEX . CIV. PRAC . & REM . CODE ANN . 38.001(8).
    However, "[t]o recover attorney's fees under [section] 38.001, a party must (1) prevail on
    16
    a cause of action for which attorney's fees are recoverable, and (2) recover damages. . .
    ." Green Int'l v. Solis, 
    951 S.W.2d 384
    , 390 (Tex. 1997). Because of the section 271.153
    limitation on damages, Sharyland has recovered no damages in this case. See TEX . LOCAL
    GOV'T CODE ANN . § 271.153. Moreover, to recover attorney's fees under chapter 38, the
    plaintiff must sue an individual or a corporation. See TEX . CIV. PRAC . & REM . CODE ANN .
    § 38.001. Alton, a municipality, is not considered a corporation even when it is acting in
    its proprietary function. See TEX . LOC . GOV'T CODE ANN . § 5.904(b) (Vernon 2008).
    Therefore, we conclude the trial court erred in awarding attorney's fees pursuant to section
    38.001(8).
    2. Attorney's Fees Under the Act
    Sharyland also contends that the award of attorney's fees was proper under the Act.
    In a declaratory judgment action, the decision to grant or deny attorney's fees is solely
    within the discretion of the trial court. See TEX . CIV. PRAC . & REM . CODE ANN . § 37.009;
    Neeley v. W. Orange-Cove Consol. Indep. Sch. Dist., 
    176 S.W.3d 746
    , 799 (Tex. 2005);
    Wilson v. Chazanow, 
    105 S.W.3d 21
    , 26 (Tex. App.–Corpus Christi 2002, no pet.). The
    court may award costs and reasonable and necessary attorney's fees as are equitable and
    just. See TEX . CIV. PRAC . & REM . CODE ANN . § 37.009. This Court should not reverse the
    trial court's decision regarding attorney's fees absent a clear showing that the trial court
    abused its discretion. Texstar N. Am. Inc. v. Ladd Petroleum Corp., 
    809 S.W.2d 672
    , 679
    (Tex. App.–Corpus Christi 1991, writ denied).
    Sharyland sought a declaration from the trial court that section 1926(b) barred
    Alton's counterclaim. In its motion for summary judgment, however, Sharyland presented
    its argument under section 1926(b) as an affirmative defense to Alton's counterclaim, not
    17
    as a request for declaratory judgment, and we construe it as such on appeal. Therefore,
    Sharyland's contention that it pleaded and prevailed on this alleged declaratory judgment
    action does not support an award of attorney's fees.
    Sharyland also asserts that the award of attorney's fees is supported by its
    declaratory judgment action seeking a declaration from the trial court that the provisions
    of section 317.13 of the Texas Administrative Code applied to the sewer crossings at issue.
    See 30 TEX . ADMIN . CODE ANN . § 317.13(1)(B). In its summary judgment order, the trial
    court granted Sharyland declaratory judgment that section 317.13 applied and that the
    definition of "sewer" included sanitary sewer residential service connections. On appeal,
    Alton asserts only that the issue of Sharyland's fees in its declaratory judgment hearing is
    completely irrelevant to the issues in this appeal. Alton does not challenge the declaratory
    nature of the section 317.13 ruling, and we cannot conclude that there is a clear showing
    that the trial court abused its discretion in awarding attorney's fees on the basis of this
    declaratory judgment action. See 
    Texstar, 809 S.W.2d at 679
    .
    Sharyland presented testimony of counsel regarding attorney's fees incurred. It did
    not, however, segregate the fees. Therefore, remand for a determination of the amount
    of the award properly attributable to the declaratory judgment action is the appropriate
    remedy. See First Nat'l Bank v. Anderson Ford-Lincoln-Mercury, 
    704 S.W.2d 83
    , 85 (Tex.
    App.–Dallas 1985, ref. n.r.e.) (op. on rehr'g) (determining that when it was unclear whether
    an award of attorney's fees was attributable to a declaratory judgment claim or to an
    unsuccessful breach of contract claim, remand is required). We sustain Alton's fourth
    issue as to the fees attributable to the breach of contract claim and overrule it as to the
    attorney's fees attributable to the declaratory judgment.
    18
    IV. Sharyland's Claims Against C&B, TCB, and Cris
    A. Third-Party Beneficiary Status on Breach of Contract Claim
    C&B and TCB, by their first issues, and Cris, by its second issue, complain of
    charge error related to Alton's breach of contract claim against them. Over objection, the
    trial court submitted the following question to the jury:
    Was Sharyland Water Supply Corporation a third party beneficiary of
    any of the following contracts:
    A party is a third party beneficiary of a contract if:
    (1)     the contracting party intended to secure some benefit to that
    third party; and
    (2)     the contracting parties entered into the contract directly for the
    third party's benefit.
    To qualify as a third party beneficiary a third party must show that it
    is either a creditor beneficiary or a donee beneficiary. A third party is a
    creditor beneficiary if performance under a contract made between others
    will come to the third party in satisfaction of a legal duty owed the third party
    by the promisee. This duty may be a contractual obligation, or other legally
    enforceable commitment owed to the third party. A third party is a donee
    beneficiary if the performance promised under the contract will, when
    rendered, come to the third party as a pure donation.
    You are instructed that in order to claim third party beneficiary status
    to any contract, the Plaintiff must show that the subject contract contains a
    clear and apparent intent of the contracting parties to confer third-party
    beneficiary status upon the Plaintiff, and that the parties entered into the
    contract directly and primarily for the third party's benefit.
    The jury found that Sharyland was a third-party beneficiary of the contracts between Alton
    and C&B, Alton and TCB, and Alton and Cris.
    C&B, TCB, and Cris contend that Sharyland lacks standing to claim under, or to
    enforce, their respective contracts with Alton because the contracts contain no provisions
    that the contracting parties intended to confer a direct benefit on Sharyland or any other
    19
    third party.   They also assert that, in this case, Sharyland's status as a third-party
    beneficiary to the contracts was a question of law for the trial court to determine, not a
    question of fact for the jury; therefore, the trial court erred in submitting a question on
    Sharyland's status as a third-party beneficiary of their respective contracts with Alton.
    In response, Sharyland asserts that it was a third-party beneficiary of the contracts,
    and by submitting the issue to the jury, the trial court impliedly found that the matter of
    third-party beneficiary status was controverted—that the language of the contract was
    susceptible to more than one reasonable interpretation regarding the intent of the parties.
    Based on this alleged ambiguity, Sharyland claims the trial court did not err in submitting
    a jury question on the issue of Sharyland's status as a third-party beneficiary.
    1. Standard of Review and Applicable Law
    As set out above, "[w]e review the trial court's submission of . . . jury questions
    under an abuse of discretion standard." Toles, 
    45 S.W.3d 263
    . We will not reverse a
    judgment based on charge error in the absence of harm. See TEX . R. APP. P. 44.1(a); Bed,
    Bath & 
    Beyond, 211 S.W.3d at 757
    .
    There is a presumption against conferring third-party-beneficiary status on
    noncontracting parties. S. Tex. Water Auth. v. Lomas, 
    223 S.W.3d 304
    , 306 (Tex. 2007)
    (per curiam); MCI Telecomms. Corp. v. Tex. Utils. Elec. Co., 
    995 S.W.2d 647
    , 652 (Tex.
    1999); Ortega v. City Nat'l Bank, 
    97 S.W.3d 765
    , 773 (Tex. App.–Corpus Christi 2003, no
    pet.) (op. on rehr'g). In deciding whether a third party may enforce or challenge a contract
    between others, it is the contracting parties' intent that controls. 
    Lomas, 223 S.W.3d at 306
    . The intent to confer a direct benefit upon a third party must be clearly and fully
    spelled out or enforcement by the third party must be denied. Id.; Stine v. Steward, 80
    
    20 S.W.3d 586
    , 589 (Tex. 2002) (per curiam); MCI Telecomms. 
    Corp., 995 S.W.2d at 651
    ;
    
    Ortega, 97 S.W.3d at 773
    . If there is any reasonable doubt as to the contracting parties'
    intent to confer a direct benefit on the third party by way of the specific contract, the third-
    party beneficiary claim fails. 
    Ortega, 97 S.W.3d at 773
    .
    To qualify as one for whose benefit a contract was made, the third party must be
    either a donee beneficiary or a creditor beneficiary. MCI Telecomms. 
    Corp., 995 S.W.2d at 651
    ; 
    Ortega, 97 S.W.3d at 773
    . A person is a donee beneficiary if the performance
    promised will come to him as a pure donation. MCI Telecomms. 
    Corp., 995 S.W.2d at 651
    .
    If performance will come to satisfy a duty or legally enforceable commitment owed by the
    promisee, then the third party is considered a creditor beneficiary.11 Id.; 
    Ortega, 97 S.W.3d at 774
    . A third party is not a creditor beneficiary, however, unless the contract shows both
    the intent to confer a benefit on the third party and the intent that the third party has the
    right to enforce the contact. 
    Ortega, 97 S.W.3d at 774
    ; MJR Corp. v. B & B Vending Co.,
    
    760 S.W.2d 4
    , 16 (Tex. App.–Dallas 1988, writ denied). "Unless both intents were
    exhibited on his behalf, the third party remains no more than an incidental beneficiary."
    MJR 
    Corp., 760 S.W.2d at 16
    . And, incidental benefits that may flow from a contract to a
    third party do not confer the right to enforce the contract. Lomas, 
    223 S.W.3d 306
    .
    Furthermore, "the fact that a person is directly affected by the [contracting] parties'
    conduct, or that he 'may have a substantial interest' in a contract's enforcement, does not
    11 A creditor beneficiary m ay be defined as a third person to whom the bargain-seeking party (the
    "prom isee" or contract party exacting the particular stipulation) has an indebtedness, contractual obligation,
    or other legally enforceable com m itm ent to the third party which com m itm ent the bargain-seeker wishes to
    discharge or protect by stipulating that the bargain-giver (the opposing contract party or "prom isor" concerning
    the particular stipulation) shall deliver a contract perform ance to the third party. MJR Corp. v. B & B Vending
    Co., 760 S.W .2d 4, 11 (Tex. App.–Dallas 1988, writ denied).
    21
    make him a third party beneficiary." Loyd v. ECO Res., Inc., 
    956 S.W.2d 110
    , 134 (Tex.
    App.–Houston [14th Dist.] 1997, no writ) (quoting Merrimack Mut. Fire Ins. Co. v. Allied
    Fairbanks Bank, 
    678 S.W.2d 574
    , 577 (Tex. App.–Houston [14th Dist.] 1984, writ ref'd
    n.r.e.) ("The fact that the mortgagor's liability for attorney's fees was directly affected by the
    attorney's fee contract had no effect on the court's holding that the mortgagor had no
    standing to contest the attorney's fee contract.")). Finally, "general beneficence does not
    create third-party rights." 
    Lomas, 223 S.W.3d at 307
    ; 
    Ortega, 97 S.W.3d at 773
    ("the
    contracting parties must intend to secure a benefit for the specific third party bringing the
    action; it is not enough that the contract is designed to benefit a broad class of people, of
    whom the third-party might be a member"); see 
    Stine, 80 S.W.3d at 589
    ("A third party may
    recover on a contract made between other parties only if the parties intended to secure a
    benefit to that third party . . . ." (emphasis added)).
    "Our analysis of the third-party beneficiary issue requires us to interpret the contract
    . . . ." MCI Telecomms. 
    Corp., 995 S.W.2d at 651
    . If a contract can be given a certain or
    definite legal meaning, then it is not ambiguous. 
    Coker, 650 S.W.2d at 393
    . "When a
    contract is not ambiguous, the construction of the written instrument is a question of law
    for the court." MCI Telecomms. 
    Corp., 995 S.W.2d at 651
    (citing 
    Coker, 650 S.W.2d at 393
    ); see J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex. 2003). If a contact
    is susceptible to more than one reasonable interpretation, it is ambiguous. Frost Nat'l Bank
    v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 312 (Tex. 2005) (per curiam). Lack of clarity,
    however, does not create an ambiguity, and not every difference in the interpretation of a
    contract amounts to an ambiguity. Universal Health Serv., Inc. v. Renaissance Women's
    Group, P.A., 
    121 S.W.3d 742
    , 746 (Tex. 2003) (quoting Forbau v. Aetna Life Ins. Co., 876
    
    22 S.W.2d 132
    , 134 (Tex. 1994)). "A court may conclude that a contract is ambiguous in the
    absence of such a pleading by either party." Sage St. Assocs. v. Northdale Constr. Co.,
    
    863 S.W.2d 438
    , 445 (Tex. 1993); see Royal Maccabees Life Ins. Co. v. James, 
    146 S.W.3d 340
    , 347 (Tex. App.–Dallas 2004, pet. denied) (op. on rehr'g) (explaining that a
    court may determine ambiguity as a matter of law for the first time on appeal).
    2. Third-Party Beneficiary Analysis
    Sharyland argues that by undertaking their contractual obligations with Alton, C&B,
    TCB, and Cris expressly agreed, as their core obligations, to protect Sharyland's waterlines
    as required under the contract documents, including certain plans and specifications.
    Sharyland argues that these plans and specifications were developed for its "sole benefit"
    and that the only "person" to be benefitted from these particular plans and specifications
    detailing the manner of installing the sewer lines in proximity to the waterline was
    Sharyland. It claims that the contracts were intended to protect Sharyland's waterlines
    from being contaminated by sewage.
    Alton engaged the services of C&B for the construction management of Alton's
    waste water collection system, TCB for the project's engineering and inspection, and Cris
    for the construction of the project. The contracts, executed only by representatives of Alton
    and C&B, TCB, or Cris, do not reference any third parties and do not indicate any intent
    to discharge any obligation owed to Sharyland, specifically, or to any other third party. The
    contracts do not clearly and fully spell out the contracting parties' intent to confer a direct
    benefit specifically on Sharyland or on any other third party and do not name or generally
    reference Sharyland as part of a group. The contracts describe only the duties and
    obligations agreed to between the contracting parties. They are devoid of any third-party
    23
    benefit language. They lack language specifically naming Sharyland as a beneficiary or
    providing Sharyland with the right to sue to enforce the contract.12
    Without more in the contracts specifically showing both the intent to confer a benefit
    on Sharyland and the intent that Sharyland has the right to enforce the contact,
    Sharyland's argument only implies third-party beneficiary status. And, Texas law as
    articulated by the Texas Supreme Court and by this Court is clear: a stranger to a contract
    cannot become a third-party beneficiary by implication. See MCI Telecomms. 
    Corp., 995 S.W.2d at 651
    ; 
    Ortega, 97 S.W.3d at 773
    . Moreover, the fact that Sharyland may have
    been directly affected by the contracting parties' conduct or may have a substantial interest
    in the contract's enforcement does not make Sharyland a third-party beneficiary. See
    
    Loyd, 956 S.W.2d at 134
    . Finally, although Sharyland and others may benefit generally
    from aspects of the contracts, including compliance with all federal, state, and local laws,
    ordinances, regulations, professional guidelines, and the parties' plans and specifications,
    "general beneficence does not create third-party rights." 
    Lomas, 223 S.W.3d at 307
    . If it
    did, "every Texan could challenge or seek to enforce any government contract and the
    presumption against third-party-beneficiary agreements would disappear." 
    Id. 12 For
    exam ple, the agreem ent between Alton and TCB includes a rem edies section that
    contem plates disputes between Alton and TCB only. The rem edies section does not address enforcem ent
    of disputes by Sharyland or by any other third party. Paragraph 16 of the agreem ent provides the following:
    Unless otherwise provided in this Agreem ent, all claim s, counterclaim s, disputes, and other
    m atters in question between [Alton] and [TCB] arising out of or relating to this Agreem ent or
    the breach of it will be decided by arbitration if the parties m utually agree, or in a court of
    com petent jurisdiction within . . . Texas. Venue . . . shall be in Hidalgo County, Texas.
    Sharyland argues that the rem edies section referred to by TCB does not foreclose Sharyland from enforcing
    the contract as a third-party beneficiary because it is prefaced by the phrase "unless otherwise provided in
    this Agreem ent." However, Sharyland does not refer this Court to contractual language that provides
    otherwise.
    24
    Sharyland does not contend that it could recover as a donee beneficiary; rather it
    appears to argue that it is a creditor beneficiary based on the contractual obligations owed
    to Sharyland by Alton as set out in the Water Supply Agreement and the Water Service
    Agreement. Sharyland asserts that "[i]t is clear that the [contracts], including the plans and
    specifications, for the project, fulfilled a legal obligation by Alton to Sharyland to construct
    the sewer line crossings in the manner required by law, with the sewer lines, wherever
    possible, crossing underneath the waterlines."
    This argument fails because a third party is not a creditor beneficiary unless the
    contracts at issue show both the intent to confer a benefit on the third party and the intent
    that the third party has the right to enforce the contact. See 
    Ortega, 97 S.W.3d at 774
    ;
    MJR 
    Corp., 760 S.W.2d at 16
    .           As noted above, neither intent was exhibited on
    Sharyland's behalf. Moreover, the contractual documents do not acknowledge a debt or
    legal obligation owed by Alton to Sharyland. The agreements do not say directly or
    indirectly that C&B, TCB, or Cris would pay a debt or assume a legal obligation owed by
    Alton to Sharyland. See MJR 
    Corp., 760 S.W.2d at 11
    . Therefore, we find Sharyland's
    argument unpersuasive and conclude that Sharyland remains no more than an incidental
    beneficiary. See 
    id. at 16.
    The contracts at issue in this case can be given a certain legal meaning—that
    Sharyland is not a third-party beneficiary—and are not susceptible to more than one
    reasonable interpretation. Therefore, they are not ambiguous. See MCI Telecomms.
    
    Corp., 995 S.W.2d at 651
    ; 
    Coker, 650 S.W.2d at 393
    . Because the construction of an
    unambiguous contract is a question of law for the court, see MCI Telecomms. Corp., 
    995 25 S.W.2d at 651
    , we conclude the trial court abused its discretion and erred when it
    submitted the third-party beneficiary question to the jury as a fact issue.
    3. Harm Analysis
    Having concluded the trial court erred, we will reverse only if the error "was
    reasonably calculated to and probably did cause the rendition of an improper judgment."
    Bed, Bath & 
    Beyond, 211 S.W.3d at 757
    . Sharyland argues that the error, if any, was
    harmless. It reasons that, had the question not been submitted to the jury, the trial court
    would have necessarily decided as a matter of law that Sharyland was a third-party
    beneficiary. The jury would have been so instructed and would have been asked to
    answer the questions on breach and damages. Based on the analysis above, we disagree
    with this reasoning.
    In this case, submission of the third-party beneficiary question allowed the jury to
    incorrectly find that Sharyland was a third-party beneficiary. This, in turn, allowed the jury
    to reach the question of breach and resulting damages. If the third-party beneficiary
    question had not been posed, and had been decided correctly by the trial court, the jury
    would not have found C&B, TCB, or Cris liable for breach of contract. We conclude,
    therefore, that the error was reasonably calculated to and probably did cause the rendition
    of an improper judgment. See 
    id. We sustain
    C&B's and TCB's first issues and Cris's second issue. Having so
    concluded, we need not address appellants' claims that the evidence is legally and
    factually insufficient to support the jury's finding that Sharyland was a third-party beneficiary
    or that C&B, TCB, and Cris breached their respective contracts with Alton as they are not
    dispositive to this appeal. See TEX . R. APP. P. 47.1.
    26
    B. Negligence Claim
    C&B's and TCB's third issues and Cris's fifth issue assert that the economic loss rule
    bars Sharyland's negligence claim because Sharyland claimed economic damages but
    failed to claim and prove property (water main) damages. Because this issue is dispositive
    of Sharyland's negligence claim, we address it first.
    "Texas courts have applied the economic loss rule to preclude tort claims between
    parties who are not in contractual privity." Sterling Chems., Inc. v. Texaco Inc., 
    259 S.W.3d 793
    , 797 (Tex. App.–Houston [1st Dist.] 2007, pet. denied). "'Economic loss' has
    been defined as 'damages for inadequate value, costs of repair and replacement of the
    defective product, or consequent loss of profits—without any claim of personal injury or
    damage to other property. . . .'" Thomson v. Espey Huston & Assocs., 
    899 S.W.2d 415
    ,
    421 (Tex. App.–Austin 1995, no writ) (quoting 2314 Lincoln Park West Condo. Ass'n v.
    Mann, Gin, Ebel & Frazier, Ltd., 
    555 N.E.2d 346
    , 385 (Ill. 1990)). In tort cases where there
    is an absence of privity of contract or, as in this case, an absence of third-party beneficiary
    status, economic damages are not recoverable unless they are accompanied by actual
    physical injury or property damage.13 See Express One Int'l, Inc. v. Steinbeck, 
    53 S.W.3d 895
    , 899 (Tex. App.–Dallas 2001, no pet.); Coastal Conduit & Ditching, Inc. v. Noram
    Energy Corp., 
    29 S.W.3d 282
    , 288-89 (Tex. App.–Houston [14th Dist.] 2000, no pet.); Hou-
    Tex, Inc. v. Landmark Graphics, 
    26 S.W.3d 103
    , 107 (Tex. App.–Houston [14th Dist.] 2000,
    13 In its cross-issue on equitable relief, Sharyland speculates, without citation to the record or
    authority, that raw sewage leaks from Alton's sewer lines would subject Sharyland's em ployees to increased
    risk of harm when repairing broken water lines and subject Sharyland's m em bers to physical injury and death
    due to water borne contam ination originating and em anating from Alton's sewer lines. See T EX . R. A PP . P.
    38.1(i). In this issue regarding econom ic dam ages, however, Sharyland m akes no claim of personal injury;
    therefore, the issue of whether a personal injury has occurred, either to em ployees or custom ers, is not before
    us.
    27
    no pet.). Thus, the threshold issue in this case is whether Sharyland suffered property
    damage, such that the economic loss rule will not bar its recovery. See Hou-Tex, 
    Inc., 26 S.W.3d at 107
    .
    In its live pleading, Sharyland sought damages for "increased costs in operation and
    costs to place barriers to mitigate the hazard caused by Defendants" and for "costs
    associated with increased safety precaution and maintenance measures it takes when
    repairing its lines." In determining the amount of damages that were proximately caused
    by the parties' negligence, the jury was instructed to consider only "[t]he reasonable cost
    of the repairs necessary to restore the property to its condition immediately before the
    injury." On appeal, Sharyland asserts that contamination of the waterline is not a remote
    theoretical injury and the damages required to protect the waterlines are not remote,
    contingent, speculative, or conjectural as argued by TCB.
    Sharyland contends that economic loss is not sought in this case. It alleges that the
    parties' negligence in improperly installing the sewer system has caused property damage
    to its waterlines. Specifically, Sharyland claims that its waterlines have been subjected to
    raw sewage leaking from the sewer lines.14 Sharyland argues that because it must take
    action to protect its waterlines from the sewage flowing in the sewer lines placed above the
    waterlines, its property has been damaged. It asserts that the continued and repeated
    threat of leaks occurring imposes a continuous and unabated risk to Sharyland's system.
    It argues that because of the close proximity of Alton's sewer lines to Sharyland's
    waterlines, Sharyland must take steps to prevent contamination both before and after a
    14 As a result of investigative excavations, one leak was found in one of the excavated sewer lines.
    The leak was caused by a rolled gasket in the coupling.
    28
    break or leak is found in the waterlines and must repair its waterlines to bring them back
    into compliance with state laws and regulations. According to Sharyland, based on the
    excavations of various areas of its waterlines to determine the impact of the sewer lines
    on the waterlines, the evidence shows that approximately sixty of the sixty-six excavated
    sewer service connections inappropriately cross Sharyland's waterlines. It argues that the
    jury properly awarded Sharyland past damages for previous diagnostic activities and future
    damages for a remedial course of action to encase and protect the waterlines from
    contamination. Essentially, Sharyland argues there is property damage because the
    leaking sewage has or will damage the waterlines necessitating remedial actions; C&B,
    TCB and Cris assert that this is not property damage.
    Neither party has provided this Court with any authority for the definition of property
    damage in the context of the economic-loss rule, and we find none. In determining
    whether Sharyland's claimed costs associated with increased safety precautions,
    maintenance measures, and repairs to its waterlines to bring them into compliance with
    state laws and regulations constitute property damage, we have considered the following
    case law defining property damage in other contexts: (1) Trans-Gulf Corp. v. Performance
    Aircraft Servs., Inc., 
    82 S.W.3d 691
    , 695 (Tex. App.–Eastland 2002, no pet.) (holding that
    the economic loss rule barred a claim by an aircraft purchaser against a repair company
    for additional costs incurred because of a faulty fuel tank repair); (2) Blanche v. First
    Nationwide Mortgage Corp., 
    74 S.W.3d 444
    , 453 (Tex. App.–Dallas 2002, no pet.)
    (concluding that the denial of a loan causing credit damage and the payment of higher
    interest rates are "economic damages not recoverable in a simple negligence action"); (3)
    Express One Int'l, 
    Inc., 53 S.W.3d at 898-99
    (holding that the economic loss rule barred
    29
    a negligence claim by an employer against a former employee for litigation-related costs
    it incurred because of a statement posted by the former employee on an internet bulletin
    board); (4) Coastal Conduit & 
    Ditching, 29 S.W.3d at 385-90
    (concluding that a contractor's
    claim for increased location costs because of a gas company's failure to properly lay or
    mark pipelines was barred by the economic loss rule); and (5) Amarillo Nat'l Bank v. Terry,
    
    658 S.W.2d 702
    , 704 (Tex. App.–Amarillo 1983, no writ) (concluding that the bank's loss
    caused by minor's unauthorized withdrawals constitutes economic loss and not property
    damage). See also Zurich Am. Ins. Co. v. Hughes, No. 11-05-00044-CV, 2006 Tex. App.
    LEXIS 6037, **4-10 (Tex. App.–Eastland July 13, 2006, pet. denied) (mem. op.) (examining
    case law defining property damage in other contexts and determining, in a summary
    judgment proceeding, that there was no actual property damage and that the economic
    loss rule barred a subrogation claim).
    Appellate courts have also held that property damage ordinarily entails physical
    destruction of property. See Murray v. Ford Motor Co., 
    97 S.W.3d 888
    , 892 (Tex.
    App.–Dallas 2003, no pet.) ("A plaintiff could recover in tort . . . for physical damage the
    defective product causes to 'other property.'"); 
    Thomson, 899 S.W.2d at 422
    (concluding,
    to the extent the alleged inadequacies in the engineering services caused property damage
    to other parts of the apartment complex beyond the subject of the contract itself, Thomson
    also had a tort claim). Other courts have held that property damage requires actual
    damage to tangible property and not mere economic loss or loss of economic opportunity.
    See, e.g., Mfrs. Auto Leasing, Inc. v. Autoflex Leasing, Inc., 
    139 S.W.3d 342
    , 348 (Tex.
    App.–Fort Worth 2004, pet. denied); Spangler v. Jones, 
    861 S.W.2d 392
    , 398 (Tex.
    App.–Dallas 1993, writ denied) (en banc).
    30
    From these cases it is clear that property damage cannot consist merely of damage
    to an intangible asset or increased operational costs. Instead, some physical destruction
    of tangible property must occur. Based on this determination, we conclude that Sharyland
    has not suffered property damage. The sewer service lines have not corroded the
    waterlines. There is no evidence of physical damage to the waterlines, nor is there
    evidence that the water flowing through the water mains has been contaminated because
    of sewage leaks. Thus, Sharyland neither pleaded nor offered evidence of an actual injury
    or property damage to its waterlines or to the water that flows through the waterlines.
    Sharyland seeks compensation only for economic damages including the cost associated
    with protecting, maintaining, and repairing its waterlines. Because Sharyland has not
    identified any property damage that it has sustained as a result of the sewer line being laid
    above its waterlines, we conclude that the economic loss rule bars Sharyland's negligence
    claim against C&B, TCB, and Cris, parties with which it is not in contractual privity. We
    sustain C&B's and TCB's third issues and Cris's fifth issue.
    C. Joint and Several Liability and Attorney's Fees
    By C&B's ninth and tenth issues, TCB's seventh and eighth issues, and Cris's first
    and sixth issues, the parties contend that the trial court erred in imposing joint and several
    liability and awarding attorney's fees against them. We agree. Having concluded that
    Sharyland is not a third-party beneficiary of the respective contracts between Alton and
    C&B, TCB, and Cris, and that the economic loss rule bars Sharyland's negligence claim,
    we conclude that the trial court erred in rendering a judgment which imposed joint and
    several liability against C&B, TCB, and Cris for damages and in awarding attorney's fees
    against C&B, TCB, and Cris. We sustain C&B's ninth and tenth issues, TCB's seventh and
    31
    eighth issues, and Cris's first and sixth issues. Because a professional negligence claim
    requires privity of contract, see Ervin v. Mann Frankfort Stein & Lipp CPAS, LLP, 
    234 S.W.3d 172
    , 182-83 (Tex. App.–San Antonio 2007, no pet.), we also sustain C&B's
    seventh issue urging that the trial court erred by entering judgment against it based upon
    a claim of professional negligence.
    Finally, the remaining issues brought by C&B, TCB, and Cris are not dispositive of
    this appeal, and we need not address them. See TEX . R. APP. P. 47.1.
    V. Sharyland's Claim for Equitable Relief Against Alton
    By a single issue, cross-appellant Sharyland contends that the trial court erred in
    failing to grant equitable relief, in lieu of the monetary damages awarded by the jury against
    Alton.15 Sharyland asserts that the equities weigh heavily in favor of the granting of a
    15 The judgm ent sought by Sharyland included the following equitable relief:
    IT IS FURTHER ORDERED, ADJUDGED AND DECREED that specific perform ance
    of the W ater Supply Agreem ent and W ater Service Agreem ent be granted and . . . Alton . .
    . [is] ordered to excavate each sewer pipe lateral constructed in the C ity of Alton/City of
    McAllen W astewater Im provem ents Project where it crosses [Sharyland's] waterline and
    install the sewer pipe lateral in the following m anner:
    A.      W ith an absolute m inim um distance of six (6) inches between
    outside diam eters of the crossing sewer pipe lateral and the
    [Sharyland's] waterline; and
    B.      W ith the sewer pipe lateral being located below the waterline where
    possible; and
    C.      W ith the sewer pipe lateral being constructed of a continuance
    section of pipe, without joints or couplings, from a point beginning
    nine (9) feet from the [Sharyland's] waterline on one side to a point
    being nine (9) feet from the [Sharyland's] waterline on the opposite
    side of the waterline; or
    D.      In lieu of conform ing with paragraph C, im m ediately above, the
    crossing sewer pipe m ay be encased in a joint of 150 psi pressure
    class pipe at least eighteen (18) feet long and two (2) nom inal sizes
    larger than the crossing sewer pipe lateral, and in such case the
    space around the carrier pipe shall be supported at m inim um five
    (5) feet intervals with spacers or be filled to the spring line with
    washed sand and this encasem ent pipe shall be centered on the
    32
    permanent injunction preventing Alton from operating the sewer lines as constructed and
    the ordering of specific performance of the Water Service Agreement and the Water
    Supply Agreement in the form of remediation—that is, reconstruction or relocation of the
    residential service connections such that they cross under Sharyland's water lines or are
    otherwise in accordance with section 317.13. Sharyland contends that remediation would
    have been: (1) less disruptive to the potable water supply; (2) more protective of human
    health because there would have been essentially no risk of contamination of water
    delivery to customers in the area; and (3) more economical because the cost of specific
    performance would be less than the monetary damages awarded to Sharyland by the jury.
    A. Standard of Review
    "Specific performance is an equitable remedy that rests in the sound discretion of
    the trial court." Am. Apparel Prod., Inc. v. Brabs, Inc., 
    880 S.W.2d 267
    , 269 (Tex.
    App.–Houston [14th Dist.] 1994, no writ). The issuance or denial of a permanent injunction
    is also reviewed for abuse of discretion. Operation Rescue - Nat'l v. Planned Parenthood
    of Houston and S.E. Tex., Inc., 
    975 S.W.2d 546
    , 560 (Tex. 1998). The trial court abuses
    its discretion when it acts arbitrarily and unreasonably, without reference to guiding rules
    crossed waterline and both ends sealed with cem ent grout or a
    m anufactured seal;
    within sixty (60) days of the date of the judgm ent, and to continue such actions diligently until
    achieving com plete com pliance with this order, but in no event shall such actions take m ore
    than one hundred eighty (180) days to achieve com plete com pliance with this order.
    IT IS FURTHER ORDERED, ADJUDGED AND DECREED that . . . Alton [is]
    com m anded, beginning no later than one hundred eighty (180) days from the date of this
    judgm ent, to desist and refrain from allowing sewage to pass through all sewer pipe laterals
    where they cross over [Sharyland's] waterline until the sewer lines are excavated and unless
    the sewage pipe laterals are constructed as ordered in subparagraphs A, B, C and D above.
    33
    or principles, or misapplies the law to the established facts of the case. 
    Downer, 701 S.W.2d at 241-42
    .
    B. Analysis
    1. Unauthorized Action
    Sharyland's claims for injunctive relief and for remediation to bring the sewer lines
    into compliance with bylaws and rules and regulations of the corporation and with state
    regulations arguably fit within the scope of suits to remedy an unlawful or unauthorized
    action—relief that is not subject to governmental immunity. See Dir. of the Dep't of Agric.
    and Env't v. Printing Indus. Ass'n., 
    600 S.W.2d 264
    , 265-66 (Tex. 1980). However, the
    unlawful or unauthorized action for which immunity does not apply is an action performed
    by a state official, not the State. See id.; cf. City of Elsa v. M.A.L., 
    226 S.W.3d 390
    , 392
    (Tex. 2007) (quoting City of Beaumont v. Bouillion, 
    896 S.W.2d 143
    , 144, 149 (Tex. 1995)
    (holding that "suits for injunctive relief" may be maintained against governmental entities
    to remedy violations of the Texas Constitution)). "This is because suits to compel state
    officers to act within their official capacity do not attempt to subject the State to liability."
    
    IT-Davy, 74 S.W.3d at 855
    . "In contrast, . . . suits . . . seeking to establish a contract's
    validity, to enforce performance under a contract, or to impose contractual liabilities are
    suits against the State." 
    Id. "That is
    because such suits attempt to control state action by
    imposing liability on the State. Consequently, such suits cannot be maintained without
    legislative permission." 
    Id. at 856.
    In this instance, Sharyland's claim for specific performance and injunctive relief
    under a contract is not against a state officer. Sharyland seeks, through its equitable claim,
    to enforce performance under a contract against Alton and thus "control state action" by
    34
    imposing liability on Alton. See 
    id. Sharyland cannot
    pursue an equitable claim regarding
    an unauthorized act against Alton without legislative permission. Because no such
    permission has been given, governmental immunity precludes Sharyland's claim. See 
    id. (citations omitted).
    Therefore, we conclude that the trial court did not abuse its discretion
    in denying Sharyland equitable relief on this basis.
    2. Adequate Remedy
    "It is a fundamental rule of equity that a court will not grant specific performance
    unless it is shown that an adequate remedy does not exist at law." American Housing
    Res., Inc. v. Slaughter, 
    597 S.W.2d 13
    , 15 (Tex. Civ. App.–Dallas 1980, writ ref'd n.r.e.);
    see Cardinal Health Staffing Network v. Bowen, 
    106 S.W.3d 230
    , 235 (Tex. App.–Houston
    [1st Dist.] 2003, no pet.) (en banc) ("An adequate remedy at law is one that is as complete,
    practical, and efficient to the prompt administration of justice as is equitable relief.").
    Cross-appellant Sharyland claims that the legal remedy of damages for breach of contract
    is not as complete, practical, prompt, and efficient as the requested equitable remedies.
    Cross-appellee Alton asserts that Sharyland had an adequate remedy in its breach of
    contract action tried to a jury. We agree.
    Sharyland does not dispute that Alton completed the construction of the sewer
    lines—that Alton performed the contract. Rather, the dispute is over how Alton constructed
    the sewer lines—how Alton performed the contract. Sharyland is asking that Alton "fix" its
    breach through remediation. It is not clear to this Court how Sharyland's equitable claim
    for relief is different, except in the language used, from the breach of contract claim
    Sharyland asserted at trial against Alton. We see no distinction between Sharyland's claim
    in equity for remediation of the sewer lines and its claim for breach of contract. Even when
    35
    couched as equitable relief, Sharyland's request is for the expenditure of money—money
    Alton would spend in the remediation process, and we have already concluded, under its
    breach of contract action, that Sharyland's compensable damages are not recoverable
    from Alton because its damages are limited under section 271.153(a). See TEX . LOCAL
    GOV'T CODE ANN . § 271.153(a); cf. Tex. S. Univ. v. Araserve Campus Dining Servs., 
    981 S.W.2d 929
    , 935 (Tex. App.–Houston [1st Dist.] 1998, pet. denied) ("And since appellants
    requested equitable relief in the form of an order reinstating them to their jobs, rather than
    monetary damages, the remedy sought was a permissible one."); Alcorn v. Vaksman, 
    877 S.W.2d 390
    , 404 (Tex. App.–Houston [1st Dist.] 1994, writ denied) (en banc) (providing
    that unlike suits for monetary damages, suits against the State seeking equitable remedies
    for constitutional violations are allowed without the State's consent).
    While Sharyland has argued that the comparative advantages of the equitable
    remedy outweigh those of the legal remedy and while it may now argue that the remedy
    is not adequate because its damages were limited by the legislature, we conclude that
    Sharyland had an adequate legal avenue through which to pursue its breach of contract
    claims, an adequate remedy provided for by the legislature "that is as complete, practical,
    and efficient to the prompt administration of justice as is equitable relief." See 
    Bowen, 106 S.W.3d at 235
    . Therefore, under the facts of this case, we further conclude that the trial
    court did not abuse its discretion in denying Sharyland's claims for equitable relief on this
    basis.
    Accordingly, we overrule cross-appellant Sharyland's sole issue.
    36
    VI. Conclusion
    We affirm the judgment of the trial court on Sharyland's breach of contract claim
    against Alton; however, we reverse and render judgment that damages and attorney's fees
    awarded against Alton on this breach of contract claim are not recoverable. We also
    reverse and remand to the trial court the award of attorney's fees for a determination of the
    amount of the award properly attributable to Sharyland's declaratory judgment action
    against Alton. We reverse and render judgment that Sharyland take nothing for damages
    and attorney's fees on its contract claims and its negligence claims against C&B, TCB, and
    Cris. Finally, we affirm the trial court's denial of Sharyland's request for equitable relief as
    against Alton.
    NELDA V. RODRIGUEZ
    Justice
    Opinion delivered and filed this
    25th day of November, 2008.
    37
    

Document Info

Docket Number: 13-06-00038-CV

Filed Date: 11/25/2008

Precedential Status: Precedential

Modified Date: 9/11/2015

Authorities (50)

Harris County v. Sykes , 47 Tex. Sup. Ct. J. 618 ( 2004 )

Ortega v. City National Bank , 2003 Tex. App. LEXIS 677 ( 2003 )

Harris County v. Smith , 46 Tex. Sup. Ct. J. 263 ( 2002 )

Murray v. Ford Motor Co. , 2003 Tex. App. LEXIS 1480 ( 2003 )

American Housing Resources, Inc. v. Slaughter , 597 S.W.2d 13 ( 1980 )

Universal Health Services, Inc. v. Renaissance Women's ... , 47 Tex. Sup. Ct. J. 20 ( 2003 )

Shupe v. Lingafelter , 49 Tex. Sup. Ct. J. 604 ( 2006 )

Thomson v. Espey Huston & Associates, Inc. , 1995 Tex. App. LEXIS 1173 ( 1995 )

Jacobs v. Satterwhite , 45 Tex. Sup. Ct. J. 217 ( 2001 )

Wilson v. Chazanow , 2002 Tex. App. LEXIS 3360 ( 2002 )

Loyd v. ECO Resources, Inc. , 1997 Tex. App. LEXIS 5008 ( 1997 )

Operation Rescue-National v. Planned Parenthood of Houston ... , 975 S.W.2d 546 ( 1998 )

Hyundai Motor Co. v. Rodriguez Ex Rel. Rodriguez , 42 Tex. Sup. Ct. J. 738 ( 1999 )

Tooke v. City of Mexia , 49 Tex. Sup. Ct. J. 819 ( 2006 )

Coastal Conduit & Ditching, Inc. v. Noram Energy Corp. , 2000 Tex. App. LEXIS 6202 ( 2000 )

Texas Department of Parks & Wildlife v. Miranda , 47 Tex. Sup. Ct. J. 386 ( 2004 )

Ervin v. Mann Frankfort Stein & Lipp CPAs, L.L.P. , 2007 Tex. App. LEXIS 6247 ( 2007 )

Amarillo National Bank v. Terry , 1983 Tex. App. LEXIS 4944 ( 1983 )

Director of the Department of Agriculture & Environment v. ... , 23 Tex. Sup. Ct. J. 397 ( 1980 )

Merrimack Mutual Fire Insurance Co. v. Allied Fairbanks Bank , 1984 Tex. App. LEXIS 5767 ( 1984 )

View All Authorities »