Archer Western Construction, LLC v. Beaird Drilling Services, Inc., and South Texas Innovations ( 2018 )


Menu:
  • REVERSE AND REMAND and Opinion Filed December 13, 2018
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-18-00140-CV
    ARCHER WESTERN CONSTRUCTION, LLC, Appellant
    V.
    BEAIRD DRILLING SERVICES, INC., AND SOUTH TEXAS INNOVATIONS,
    Appellees
    On Appeal from the 193rd Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-16-16390
    MEMORANDUM OPINION
    Before Justices Stoddart, Whitehill, and Boatright
    Opinion by Justice Whitehill
    This interlocutory appeal arises out of an arbitration clause in a construction contract and
    concerns whether Archer Western Construction, LLC (Archer) impliedly waived its right to
    arbitration. Archer argues that the trial court erred by denying its motion to compel arbitration
    because it did not waive its right to arbitration by substantially invoking the judicial process or
    causing South Texas Innovations (STI) to suffer prejudice.
    We conclude that even if Archer substantially invoked the judicial process, STI did not
    meet its burden to establish prejudice. Thus there was no implied waiver of Archer’s arbitration
    right, and the trial court abused its discretion in denying Archer’s motion to compel arbitration.
    Accordingly, we reverse the trial court’s order and remand for further proceedings consistent with
    this opinion.
    I. BACKGROUND
    Archer was the general contractor for the construction of a luxury high rise project and it
    hired STI to provide certain construction-related labor, materials and services for that project. The
    subcontract included the following arbitration provision:
    Arbitration. Any controversy or claim of Contractor against Subcontractor or
    Subcontractor against Contractor or its surety shall, at the option of Contractor or
    Contractor’s surety and at any time, be resolved by arbitration pursuant to rules
    determined by Contractor. The Contractor and Subcontractor agree to equally split
    the administrative costs, fees, and other similar expenses charged by the arbitrator
    or arbitration agency. Subcontractor irrevocably submits to the jurisdiction of the
    federal, state, or United States territory courts located in the state or United States
    territory of the Project for the purpose of proceedings with respect to the arbitration.
    At the Contractor’s or its surety's option, the arbitration may be consolidated with
    any arbitration between the Contractor and Owner or other entity associated with
    the Project. Subcontractor waives to the fullest extent permitted by law any
    objection that they may now or may hereafter have to having arbitration
    proceedings conducted in the state or United States territory in which the Project is
    located, including any claim that it is an inconvenient forum for such arbitration or
    court proceedings. The award rendered by the arbitrator(s) shall be conclusive and
    binding upon the parties and shall be enforceable in any court of competent
    jurisdiction of any Contracting State pursuant to the Convention on the Recognition
    and Enforcement of Foreign Arbitral Awards (330 UNTS 3; 9 U.S.C. 201, et seq.).
    Several lawsuits concerning disputed project payments were filed. The first lawsuit was
    filed by a drilling contractor, Beaird Drilling Services Inc., against Archer, STI, and other parties.
    (the Beaird suit).
    When a payment dispute arose between Archer and STI, STI filed a separate suit against
    Archer (the Archer suit). Archer answered, counterclaimed and filed a third-party petition in the
    Archer suit all subject to a motion to compel arbitration previously filed in that case.1
    By agreement, STI moved to consolidate the Beaird and Archer suits. The trial court
    consolidated the two suits into what is now this case.
    1
    The motion is not part of our record, but is referenced in the pleading. Neither party disputes that it was filed.
    –2–
    On January 9, 2018, Beaird’s claims were settled in mediation, leaving only the claims
    between STI and Archer.
    Shortly thereafter, Archer filed its “Motion to stay the proceeding and to compel
    arbitration, and, in the alternative, for continuance.” STI opposed Archer’s motion, arguing that
    Archer waived its right to compel arbitration by substantially participating in the judicial process
    and that it would cause STI “profound prejudice” to compel arbitration.
    The trial court denied the motion to compel arbitration, and Archer timely filed this
    interlocutory appeal.
    II. ANALYSIS
    A.     First Issue: Does the arbitration clause prohibit waiver?
    Archer initially argued that the arbitration clause’s language expressly prohibits waiver of
    arbitration. But Archer now withdraws that issue, and we do not consider it. See TEX. R. APP. P.
    47.1. Archer did not otherwise challenge the clause’s enforceability.
    B.     Second Issue: Did the trial court abuse its discretion by concluding that Archer
    waived its arbitration rights?
    Archer’s second issue argues that the trial court abused its discretion by denying its motion
    to compel arbitration because STI did not meet its burden to establish that Archer waived its
    arbitration rights. We agree because, assuming Archer substantially invoked the judicial process,
    STI failed to prove that it was thereby prejudiced.
    1.      Applicable Law
    Public policy strongly favors arbitration. Prudential Sec. Inc. v. Marshall, 
    909 S.W.2d 896
    , 898 (Tex. 1995). To compel arbitration, a party must show a valid agreement to arbitrate
    exists and the claims asserted are within the agreement’s scope. J.M. Davidson, Inc. v. Webster,
    
    128 S.W.3d 223
    , 227 (Tex. 2003). Once that occurs, there is a strong presumption favoring
    –3–
    arbitration, and the burden then shifts to the party opposing arbitration to present an affirmative
    defense to enforcement. 
    Id.
    Waiver is a valid defense to arbitration. Perry Homes, 
    258 S.W.3d 580
    , 589–90 (Tex.
    2008).       Waiver is an intentional relinquishment of a known right, or intentional conduct
    inconsistent with asserting that right. Sun Exp. And Prod. Co. v. Benton, 
    728 S.W.2d 35
    , 37 (Tex.
    1987).
    Furthermore, waiver depends on the facts and the totality of the circumstances of each case.
    Perry Homes, 258 S.W.3d at 591. Although waiver can be implied from a party’s conduct, the
    “conduct must be unequivocal,” and the burden to prove waiver is a heavy one. See Richmont
    Holdings, Inc. v. Superior Recharge Sys., LLC, 
    455 S.W.3d 573
    ,575 (Tex. 2014) (per curiam).
    “[I]n close cases, the strong presumption against waiver should govern.” Perry Homes, 258
    S.W.3d at 591.
    Determining implied waiver involves a two-pronged test: (i) did the party seeking
    arbitration substantially invoke the judicial process, and (ii) did the opposing party prove that it
    suffered resulting prejudice. 2 Id. at 589–90, 593.
    Prejudice “refers to the inherent unfairness in terms of delay, expense, or damage to a
    party’s legal position that occurs when the party’s opponent forces it to litigate an issue and later
    seeks to arbitrate that same issue.” Id. at 597 (internal quotations omitted). “[A] party should not
    be allowed purposefully and unjustifiably to manipulate the exercise of its arbitral rights simply to
    gain an unfair tactical advantage over the opposing party.” Id. (internal quotations omitted). Thus,
    prejudice refers to “an inherent unfairness caused by a party’s attempt to have it both ways by
    2
    Although STI also argues express waiver, we do not consider that argument because STI did not raise it in the trial court. See TEX.
    R. APP. P.38.1.
    –4–
    switching between litigation and arbitration to its own advantage.” In re Citigroup Global Mkts.,
    Inc., 
    258 S.W.3d 623
    , 625 (Tex. 2008) (per curiam).
    We review a trial court’s denial of a motion to compel arbitration for an abuse of discretion.
    See In re D. Wilson Constr. Co., 
    196 S.W.3d 774
    , 780 (Tex. 2006) (orig. proceeding). Under this
    standard, we do not defer to the trial court on questions of law but do defer to a trial court’s fact
    findings if they are supported by evidence. Perry Homes, 258 S.W.3d at 598. But where the facts
    are undisputed, whether a party waived its right to arbitrate, including whether that party’s conduct
    caused prejudice, is a question of law that we review de novo. Id.
    2.     Implied Waiver
    Because the validity and scope of the arbitration agreement are not at issue here, we begin
    with STI’s implied waiver defense; specifically, whether STI met its burden to establish that
    Archer waived its right to arbitrate.
    Here, STI maintains that Archer substantially invoked the judicial process by engaging in
    numerous litigation activities. But even if Archer did so, STI cannot establish waiver unless it also
    establishes prejudice. See Perry Homes, 258 S.W.3d at 593. Thus, we begin with prejudice, and
    examine the record evidence of (i) delay; (ii) expense, and (iii) damage to STI’s legal position. Id.
    at 597.
    (a). Delay
    First, we consider delay. Although prejudice “is more easily shown when a party delays
    his request for arbitration and in the meantime engages in pretrial activity inconsistent with an
    intent to arbitrate,” Ideal Roofing, Inc. v. Ambruster, No. 05-13-00446-CV, 
    2013 WL 6063724
    , at
    *8 (Tex. App.—Dallas Nov. 18, 2013, no pet.), delay alone generally cannot establish waiver. See
    In re Vesta Ins. Group, Inc., 192 S.W.3d at 763.
    –5–
    STI sued Archer on July 7, 2017, and Archer moved to compel arbitration approximately
    five and a half months later, on January 22, 2018. STI argues that, while the length of delay is not
    particularly problematic, the timing of the motion to compel arbitration shows Archer’s intent to
    delay the proceedings.
    Specifically, trial was set for February 27, 2018. Archer, however, sought to continue the
    case “for at least six months” to conduct discovery on the consolidated claims. The court denied
    the continuance motion, and shortly thereafter Archer moved to compel arbitration. In that motion,
    Archer alternatively requested that the court delay the trial setting for at least four months.
    There is no dispute but that Archer knew of the arbitration clause early on. When STI sued
    Archer in July 2017, Archer moved to compel arbitration when it filed its answer and counterclaim
    and made those pleadings subject to the arbitration demand. STI argues that Archer did not seek
    arbitration in the consolidated suit until after the denial of its continuance motion despite Archer’s
    prior awareness of its arbitration right. However, STI’s argument ignores the fact that Archer’s
    timing followed the Beaird claims settlement—when all that remained in the suit were arbitrable
    claims between STI and Archer.
    Moreover, the timing is significant only if the delay actually caused prejudice. To this end,
    STI maintains that it has been prejudiced by the delay because “Archer continues to withhold funds
    in excess of $5 million owed to STI.” There is, however, no evidence to support this assertion.
    Notwithstanding Archer’s awareness of the arbitration provision, the litigation activity, and
    the timing of its motion, the record does not establish that Archer’s delay was an attempt to move
    the litigation forward for its own benefit and to STI’s detriment. See, e.g., Sipriano, 
    2016 WL 2905553
    , at *6.
    –6–
    (b). Expense
    Next, we consider expense. Archer also engaged in discovery (in the Beaird case and in
    this case) including: (i) propounding four requests for production and one set of interrogatories to
    STI, and (ii) a deposition on written questions and request for documents to a third party. Archer
    also filed: (i) a motion to consolidate, (ii) a motion for continuance, (iii) a counterclaim and
    amended counterclaim, (iv) a third party petition against STI’s surety, (v) a motion for summary
    judgment, and (vi) a temporary restraining order, and participated in mediation and designated
    experts.
    STI’s evidence included an affidavit from its president, Gary Haymond, who stated that
    STI “has incurred $101,703.52 in attorney’s fees and expenses” in this litigation. Haymond also
    says that STI “sustained the majority of the ongoing significant attorney’s fees and expenses” after
    the cases were consolidated. Haymond claims that “STI would suffer significant prejudice in the
    form of financial harm . . . after having engaged in substantial litigation efforts and agreeing to
    consolidate the case . . . .”
    But there have been multiple suits involving multiple parties and STI does not quantify
    which portion of the fees and expenses are specifically attributable to Archer’s litigation activities.
    It also does not quantify the “majority” amount of those fees it claims occurred after consolidation.
    Moreover, the record contains no evidence that the trial preparation and “litigation efforts”
    would not also be useful in arbitrating STI’s claims. See In re Vesta Ins. Group, Inc., 192 S.W.3d
    at 763 (attorney affidavit that plaintiff incurred more than $200,000 in discovery-related expenses
    and fees did not establish prejudice without evidence of the extent and substance of the discovery
    and that the discovery would not be useful in arbitration); Practicehwy.com, Inc. v. Albany IVF
    Fertility & Gynecology, PLLC, Np. 05-06-00222-CV, 
    2006 WL 2960838
    , *3 (Tex. App.—Dallas
    Oct. 18, 2006, no pet.) (no prejudice where there was no evidence that time and funds expended
    –7–
    would not have been expended or inure to appellee’s benefit in his arbitration); Tex. Residential
    Mortgage, L.P. v. Portman, 
    152 S.W.3d 861
    , 864 (Tex. App.—Dallas 2005, no pet.) (plaintiff’s
    trial preparation expense resulting from ten-month delay did not establish prejudice). Nor is there
    any evidence that participating in arbitration would result in economic hardship to STI. See
    Sipriano v. Regional Fin. Corp. of Tx., No. 05-15-00397-CV, 
    2016 WL 2905553
    , at *5, n.6 (Tex.
    App.—Dallas May 16, 2016, no pet.).
    (c). Damage to Legal Position
    Finally, we examine whether STI’s legal position was damaged by Archer’s delay in
    asserting its arbitration right. STI has not argued, and we see no evidence in the record, that the
    delay or other activity harmed its legal position. See, e.g., Pilot Travel Ctrs., LLC v. McCray, 
    416 S.W.3d 168
    , 186 (Tex. App.—Dallas 2013, no pet.). While there is no dispute that Archer engaged
    in discovery and other litigation activities, the record does not show that it obtained any
    information that could not be obtained in arbitration.
    Given the totality of the circumstances and the strong presumption against waiver, we
    conclude that STI did not establish it was prejudiced by Archer’s actions. Absent prejudice, we
    need not address whether Archer’s conduct substantially invoked the judicial process. See TEX.
    R. APP. P. 47.1; Texas Residential Mortgage, L.P., 
    152 S.W.3d at
    863–64. Because the trial court
    abused its discretion in denying Archer’s motion to compel arbitration, we resolve Archer’s second
    issue in its favor.
    –8–
    III.   CONCLUSION
    We reverse the trial court’s order denying Archer’s motion to compel arbitration and
    remand to the trial court for entry of an order compelling the parties’ dispute to arbitration and
    granting an appropriate stay.
    /Bill Whitehill/
    BILL WHITEHILL
    JUSTICE
    180140F.P05
    –9–
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    ARCHER WESTERN CONSTRUCTION,                        On Appeal from the 193rd Judicial District
    LLC, Appellant                                      Court, Dallas County, Texas
    Trial Court Cause No. DC-16-16390.
    No. 05-18-00140-CV          V.                      Opinion delivered by Justice Whitehill.
    Justices Stoddart and Boatright
    BEAIRD DRILLING SERVICES, INC.,                     participating.
    AND SOUTH TEXAS INNOVATIONS,
    Appellee
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    REVERSED and this cause is REMANDED to the trial court for entry of an order compelling
    the parties’ dispute to arbitration and granting an appropriate stay.
    It is ORDERED that appellant ARCHER WESTERN CONSTRUCTION, LLC recover
    its costs of this appeal from appellee BEAIRD DRILLING SERVICES, INC., AND SOUTH
    TEXAS INNOVATIONS.
    Judgment entered December 13, 2018.
    –10–
    

Document Info

Docket Number: 05-18-00140-CV

Filed Date: 12/13/2018

Precedential Status: Precedential

Modified Date: 12/17/2018