Natgasoline LLC and Orascom E&C USA Inc. v. Refractory Construction Services, Co LLC , 566 S.W.3d 871 ( 2018 )


Menu:
  • Reversed and Remanded and Opinion filed December 18, 2018.
    In The
    Fourteenth Court of Appeals
    NO. 14-17-00503-CV
    NATGASOLINE LLC AND ORASCOM E&C USA INC., Appellants
    V.
    REFRACTORY CONSTRUCTION SERVICES, CO. LLC, Appellee
    On Appeal from the 122nd District Court
    Galveston County, Texas
    Trial Court Cause No. 17-CV-0149
    OPINION
    This appeal arises from competing motions to compel arbitration in a dispute
    involving the construction of a methanol plant.
    Refractory Construction Services, Co. LLC sued Crawford Industrial
    Services, LLC, Orascom E&C USA, Inc., and Natgasoline LLC to recover money
    allegedly owed to Refractory Construction under a construction contract. Crawford,
    a subcontractor, asserted cross-claims against contractor Orascom and plant owner
    Natgasoline.
    Orascom and Natgasoline filed a joint motion to compel a bilateral Orascom-
    Crawford arbitration.    Refractory Construction and Crawford jointly filed a
    competing motion to compel arbitration as to all parties and all claims.
    The trial court denied Orascom’s and Natgasoline’s motion to compel and
    ordered a single arbitration proceeding involving all parties and all claims. Orascom
    and Natgasoline appealed. For the reasons below, we reverse the trial court’s orders
    compelling a single arbitration proceeding and remand for further proceedings
    consistent with this opinion.
    BACKGROUND
    At issue are two construction contracts involving three signatories. One
    contract was between contractor Orascom and subcontractor Crawford (the
    “subcontract”). The second contract was between subcontractor Crawford and sub-
    subcontractor Refractory Construction (the “sub-subcontract”). The subcontract and
    sub-subcontract governed construction of Natgasoline’s methanol plant in
    Beaumont, Texas.
    2
    Orascom and Crawford are the only signatories to the subcontract; only Refractory
    Construction signed the sub-subcontract between Refractory Construction and
    Crawford.
    Both the subcontract and the sub-subcontract contain identical arbitration
    provisions:
    11.3.3 ARBITRATION
    If the matter is unresolved after submission of the matter to a mitigation
    procedure or mediation, a demand for arbitration may be served by
    either Party. Any arbitration shall be conducted in Harris County,
    Texas, United States of America in the English language. The
    arbitration shall be conducted in accordance with the Rules of
    Arbitration of the International Chamber of Commerce but excluding
    the emergency arbitrator appointment rules (“Rules”) in effect on the
    date of this Agreement. The arbitration shall be presided over by three
    (3) arbitrators appointed in accordance with the Rules. Each arbitrator
    shall be fluent in English. The arbitrators’ decision, which shall be in
    writing, shall be final, binding and conclusive upon the Parties and may
    be confirmed or embodied in any order or judgment of any court having
    jurisdiction. The foregoing agreement to arbitrate shall be specifically
    enforceable and the award rendered by the arbitrators shall be final and
    judgment may be entered upon it in accordance with applicable law in
    any court having jurisdiction thereof.
    The subcontract and the sub-subcontract also contain identical provisions addressing
    multi-party disputes:
    11.6 MULTI-PARTY PROCEEDING
    All parties necessary to resolve a matter agree to be parties to the same
    dispute resolution proceeding. To the extent disputes between the
    CONTRACTOR and SUBCONTRACTOR involve in whole or in part
    disputes between the CONTRACTOR and the OWNER, at the sole
    discretion of the CONTRACTOR disputes between the
    SUBCONTRACTOR and the CONTRACTOR shall be decided by the
    same tribunal and in the same forum as disputes between the
    CONTRACTOR and the OWNER.
    3
    Both documents define “OWNER” as Natgasoline, “CONTRACTOR” as Orascom,
    and “SUBCONTRACTOR” as Crawford.                  In the sub-subcontract, Refractory
    Construction is defined as the “SUPPLIER SUBCONTRACTOR.”
    Refractory Construction sued Crawford, Orascom, and Natgasoline in
    February 2017 and asserted claims for payment allegedly owed to Refractory
    Construction under the sub-subcontract. Crawford asserted cross-claims against
    Orascom and Natgasoline. Orascom and Natgasoline asserted affirmative defenses
    against Refractory Construction and Crawford.
    Orascom and Natgasoline filed a joint motion to compel bilateral arbitration
    between Orascom and Crawford under the subcontract.                 Orascom’s and
    Natgasoline’s motion also asked the trial court to stay trial court proceedings “in
    their entirety pending the completion of such mandatory alternative dispute
    resolution.”   While Orascom’s and Natgasoline’s motion to compel bilateral
    arbitration was pending, Refractory Construction and Crawford filed a joint motion
    to compel a single arbitration as to all parties and all claims.
    The trial court signed an order on May 24, 2017, stating in relevant part as
    follows:
    It is therefore, ORDERED, ADJUDGED, and DECREED that
    [Refractory Construction’s and Crawford’s] Motion to Compel
    Alternative Dispute Resolution as to All Claims and All Parties is in all
    things GRANTED.
    Or, in the alternative, it is therefore, ORDERED, ADJUGED, and
    DECREED that [Orascom’s and Natgasoline’s] Motion to Stay the
    Entire Case Pending Alternative Dispute Resolution between
    [Orascom] and Crawford is in all things DENIED.
    Orascom and Natgasoline filed a notice of appeal asserting that the trial court’s May
    2017 order “constitute[d] a final, appealable order.” Orascom and Natgasoline
    alternatively perfected the appeal as an interlocutory appeal.        In the further
    4
    alternative, Orascom and Natgasoline asked this court to treat their appellate brief as
    a petition for writ of mandamus. Refractory Construction is the only party to appear
    as appellee; Crawford did not file an appearance on appeal or an appellate brief.
    Upon receipt of the appeal, this court mailed a letter to the parties’ counsel
    addressing appellate jurisdiction and stating that the appeal would be dismissed
    unless a response was filed “showing meritorious grounds for continuing the
    appeal.”    Orascom and Natgasoline filed a response asserting that appellate
    jurisdiction exists because this case involves (1) an appeal from a final judgment; or
    (2) a statutorily authorized interlocutory appeal; or (3) a mandamus proceeding.
    Refractory Construction filed a motion to dismiss Orascom’s and
    Natgasoline’s appeal for lack of jurisdiction.      After receiving Orascom’s and
    Natgasoline’s response, this court denied Refractory Construction’s motion to
    dismiss.
    The case was orally argued on May 7, 2018. After arguments were heard, this
    court issued an order abating the appeal to allow the trial court to clarify its intent
    with respect to the May 2017 order. The trial court signed a second order on June
    6, 2018, stating that “it was the intent of the [trial court] to grant [Refractory
    Construction’s and Crawford’s] Motion to Compel Alternative Dispute Resolution
    as to All Claims and All Parties and that a single arbitration proceeding occur
    involving All Claims and all Parties . . .” (emphasis in original). Orascom’s and
    Natgasoline’s appeal was reinstated upon receipt of the trial court’s June 2018 order.
    After the appeal was reinstated, the parties filed supplemental briefs addressing
    jurisdictional issues.
    GOVERNING LAW
    We must determine as a threshold matter whether the Federal Arbitration Act
    5
    (the “FAA”) or the Texas Arbitration Act (the “TAA”) applies to this dispute. See
    generally 
    9 U.S.C.A. §§ 1-16
     (West 2009); 
    Tex. Civ. Prac. & Rem. Code Ann. §§ 171.001
    -.098 (Vernon 2011). The arbitration provisions at issue do not refer to
    the FAA or the TAA. The subcontract and sub-subcontract state that they “shall be
    governed by the Law in effect at the location of the Project.” The project is located
    in Beaumont, Texas.
    “If an arbitration agreement does not specify whether the FAA or the TAA
    applies, but states that it is governed by the laws of Texas, both the FAA and the
    TAA apply unless the agreement specifically excludes federal law.” In re Devon
    Energy Corp., 
    332 S.W.3d 543
    , 547 (Tex. App.—Houston [1st Dist.] 2009, orig.
    proceeding); see also Roehrs v. FSI Holdings, Inc., 
    246 S.W.3d 796
    , 803 (Tex.
    App.—Dallas 2008, pet. denied). We apply this precept here. See In re Devon
    Energy Corp., 
    332 S.W.3d at 547
    ; Roehrs, 
    246 S.W.3d at 803
    .
    ANALYSIS
    We initially address whether we have appellate jurisdiction to review
    Orascom’s and Natgasoline’s appeal. We conclude that (1) Orascom’s appeal can
    be heard under our interlocutory appellate jurisdiction; and (2) we lack appellate
    jurisdiction over Natgasoline’s appeal.
    The second part of our analysis examines whether the trial court’s orders
    compelling a single arbitration proceeding comport with the subcontract’s and sub-
    subcontract’s arbitration provisions. We conclude that they do not.
    I.     Appellate Jurisdiction
    Orascom and Natgasoline assert that appellate jurisdiction exists here because
    this proceeding is (1) an appeal from a final judgment; or (2) a statutorily authorized
    interlocutory appeal; or (3) a mandamus proceeding. We address these jurisdictional
    6
    bases under Texas procedural law. See Bison Bldg. Materials, Ltd. v. Aldridge, 
    422 S.W.3d 582
    , 585 (Tex. 2012) (Texas courts apply Texas procedural law when the
    FAA governs the underlying dispute).
    A.     Final Judgment
    An appeal generally may be taken only from a final judgment. Lehmann v.
    Har-Con Corp., 
    39 S.W.3d 191
    , 195 (Tex. 2001); Futch v. Reliant Sources, Inc., 
    351 S.W.3d 929
    , 931 (Tex. App.—Houston [14th Dist.] 2011, no pet.).                 When a
    conventional trial on the merits has not occurred, “an order or judgment is not final
    for purposes of appeal unless it actually disposes of all parties and all claims, or
    unless the order clearly and unequivocally states that it finally disposes of all parties
    and all claims.” Gutierrez v. Stewart Title Co., 
    550 S.W.3d 304
    , 309 (Tex. App.—
    Houston [14th Dist.] 2018, no pet.). To determine whether an order constitutes a
    final judgment, we look at the language of the order and the record in the case.
    Futch, 
    351 S.W.3d at 931
    .
    Orders compelling arbitration generally do not dispose of all parties and
    issues; instead, they “contemplate continuing resolution through the arbitration
    process.” Brooks v. Pep Boys Auto. Supercenters, 
    104 S.W.3d 656
    , 660 (Tex.
    App.—Houston [1st Dist.] 2003, no pet.); see also John M. O’Quinn, P.C. v. Wood,
    Nos. 12-06-00151-CV, 12-06-00188-CV, 
    2006 WL 3735617
    , at *3 (Tex. App.—
    Tyler Dec. 20, 2006, orig. proceeding) (mem. op.) (when a trial court “compels
    arbitration without dismissing the case,” it “retains continuing jurisdiction of the
    case until a final judgment or order is entered”). An order compelling arbitration is
    interlocutory unless it clearly states that it dismisses the entire case and therefore is
    final. See Brooks, 
    104 S.W.3d at 660
    ; see also Small v. Specialty Contractors, Inc.,
    
    310 S.W.3d 639
    , 642 (Tex. App.—Dallas 2010, no pet.).
    In the context of a motion to compel arbitration, a “dismissal would usually
    7
    be inappropriate because the trial court cannot dispose of all claims and all parties
    until arbitration is completed.” In re Gulf Expl., LLC, 
    289 S.W.3d 836
    , 841 (Tex.
    2009) (orig. proceeding). Retaining jurisdiction over the case permits the trial court
    to take any action necessary to facilitate the arbitration’s completion. See 
    id.
    (“During arbitration, a court order may be needed to replace an arbitrator, compel
    attendance of witnesses, or direct arbitrators to proceed promptly.” (internal citations
    omitted)). Incorporating this reasoning, the TAA requires that an order compelling
    arbitration “include a stay of any proceeding.” See 
    Tex. Civ. Prac. & Rem. Code Ann. § 171.021
    (c).
    The trial court’s May 2017 order grants Refractory Construction’s and
    Crawford’s motion to compel arbitration; in the alternative, that order denies
    Orascom’s and Natgasoline’s “Motion to Stay the Entire Case Pending Alternative
    Dispute Resolution between [Orascom] and Crawford.” The trial court’s June 2018
    order states that its May 2017 order was intended “to grant [Refractory
    Construction’s and Crawford’s] Motion to Compel Alternative Dispute Resolution
    as to All Claims and All Parties and that a single arbitration proceeding occur
    involving All Claims and all Parties . . . ” (emphasis in original). Arguing that these
    two orders constitute a final judgment, Orascom and Natgasoline contend that the
    orders “unequivocally dispose[] of all claims and all parties” and are “clearly
    intended to dispose of the entire case and all pending motions.”
    We reject this contention.      The orders do not state that they are final
    judgments, do not dismiss the case, and do not include language suggesting finality.
    The trial court’s orders do not “clearly and unequivocally state[]” that they “finally
    dispose[] of all parties and all claims” in the proceeding. See Gutierrez, 
    550 S.W.3d at 309
    ; Small, 
    310 S.W.3d at 642
    .
    Instead of disposing of all parties and all claims, the trial court’s orders direct
    8
    the parties to participate in a single arbitration proceeding.       By compelling
    arbitration, the trial court reasonably could have “contemplate[d] continuing
    resolution” as necessary to facilitate the arbitration’s completion. See Brooks, 
    104 S.W.3d at 660
    ; see also In re Gulf Expl., LLC, 289 S.W.3d at 841. Moreover, under
    the TAA, the trial court was required to stay the underlying proceeding in
    conjunction with the orders compelling arbitration. See 
    Tex. Civ. Prac. & Rem. Code Ann. § 171.021
    (c). In the absence of any language indicating finality, the trial
    court’s orders compelling arbitration do not constitute final judgments.         See
    Gutierrez, 
    550 S.W.3d at 309
    ; Small, 
    310 S.W.3d at 642
    .
    Orascom’s and Natgasoline’s appeal was not properly perfected as an appeal
    from a final judgment.
    B.     Interlocutory Appeal
    Orascom and Natgasoline assert that their appeal properly was perfected as an
    interlocutory appeal because the trial court’s orders effected an unequivocal denial
    of Orascom’s and Natgasoline’s motion to compel a bilateral arbitration between
    Orascom and Crawford under the subcontract.
    Appellate courts may consider appeals from interlocutory orders when a
    statute explicitly authorizes an appeal. Tex. A & M Univ. Sys. v. Koseoglu, 
    233 S.W.3d 835
    , 840 (Tex. 2007). The FAA and TAA permit an interlocutory appeal
    from an order denying a motion to compel arbitration. See 
    9 U.S.C.A. § 16
    ; 
    Tex. Civ. Prac. & Rem. Code Ann. § 51.016
     (Vernon 2015), § 171.098(a)(1); see also In
    re Helix Energy Sols. Group, Inc., 
    303 S.W.3d 386
    , 395 n.7 (Tex. App.—Houston
    [14th Dist.] 2010, orig. proceeding).
    When determining whether an order denies a motion to compel arbitration,
    “[t]he substance and function of the order viewed in the context of the record
    9
    controls our interlocutory jurisdiction.” McReynolds v. Elston, 
    222 S.W.3d 731
    , 738
    (Tex. App.—Houston [14th Dist.] 2007, no pet.); see also Tex. La Fiesta Auto Sales,
    LLC v. Belk, 
    349 S.W.3d 872
    , 878 (Tex. App.—Houston [14th Dist.] 2011, no pet.).
    The FAA and TAA permit interlocutory appellate review of an order that denies a
    party’s right to arbitrate in a specific manner under a specific contract. See Tex. La
    Fiesta Auto Sales, LLC, 
    349 S.W.3d at 878
     (analyzing the FAA); McReynolds, 
    222 S.W.3d at 738
     (analyzing the TAA). McReynolds and Texas La Fiesta guide our
    analysis here.
    The parties in McReynolds were engaged in arbitration proceedings pursuant
    to their partnership agreement when the plaintiff sued to compel arbitration under a
    separate settlement agreement. 
    222 S.W.3d at 736-37
    . The trial court denied the
    plaintiff’s motion to compel and the plaintiff appealed. 
    Id. at 737
    . Asserting that
    the court lacked interlocutory appellate jurisdiction under the TAA, the defendant
    asserted that “the court’s order did not deny the [plaintiff’s] ‘right to arbitration’ but
    merely allowed pending arbitration to continue.” 
    Id. at 738
    .
    Rejecting the defendant’s argument, McReynolds noted that the plaintiff’s
    motion to compel sought “to enforce his express contractual right of arbitration
    under the Settlement Agreement,” which included arbitrating before a different
    arbitrator. 
    Id.
     Concluding that the trial court’s order “denied [the plaintiff’s]
    potential contractual right to arbitration under the Settlement Agreement,” the court
    determined that the TAA granted interlocutory jurisdiction to review the trial court’s
    order. 
    Id. at 738-39
    .
    The parties in Texas La Fiesta similarly signed two agreements that included
    separate arbitration provisions:     an arbitration agreement and an employment
    contract. 
    349 S.W.3d at 875-76
    . After the plaintiff sued the defendants, the
    defendants moved to compel arbitration under the arbitration agreement. 
    Id. at 876
    .
    10
    The trial court denied in part the defendants’ motion to compel, concluding that the
    arbitration agreement was superseded by the employment contract. 
    Id. at 876-77
    .
    The trial court ordered the parties to arbitrate under the employment contract. 
    Id. at 877
    .
    The defendants appealed and the plaintiff challenged the court’s appellate
    jurisdiction. 
    Id.
     Noting that “the trial court’s order did not compel arbitration under
    the arbitration agreement as the [defendants] requested,” the court “conclude[d] that
    the trial court’s order denied the [defendants’] their potential contractual right to
    arbitration . . . as provided in the arbitration agreement.” 
    Id. at 879
    . The appellate
    court therefore could review the defendants’ appeal under the FAA’s interlocutory
    jurisdiction provision. 
    Id.
    Here, as in McReynolds and Texas La Fiesta, the parties sought different
    arbitrations. Orascom and Natgasoline moved to compel arbitration under the
    subcontract only as between Orascom and Crawford.                    In contrast, Refractory
    Construction and Crawford moved to compel arbitration under the subcontract and
    sub-subcontract in a single proceeding encompassing all claims and all parties. The
    trial court ordered a single arbitration proceeding encompassing all claims and all
    parties; it denied Orascom’s and Natgasoline’s “Motion to Stay the Entire Case
    Pending Alternative Dispute Resolution between [Orascom] and Crawford.”
    The subcontract authorizes arbitration only between the “Parties” to the
    subcontract — namely, Orascom and Crawford. The subcontract does not permit
    Refractory Construction to inject itself into the arbitration proceeding between
    Orascom and Crawford.1 By requiring all parties to arbitrate all claims in a single
    1
    The subcontract’s “Multi-Party Proceeding” provision grants limited discretion to involve
    other parties in an arbitration proceeding, but this discretion is vested solely in Orascom and
    extends only to disputes between Orascom and Natgasoline. Orascom and Natgasoline do not
    assert any claims against each other in the underlying proceeding. Therefore, this provision does
    11
    arbitration proceeding, the trial court effectively denied to Orascom its right under
    the subcontract to arbitrate only with Crawford. See Tex. La Fiesta Auto Sales, LLC,
    
    349 S.W.3d at 879
    ; McReynolds, 
    222 S.W.3d at 738-39
    . We therefore have
    jurisdiction over Orascom’s interlocutory appeal. See 
    9 U.S.C.A. § 16
    ; 
    Tex. Civ. Prac. & Rem. Code Ann. §§ 51.016
    , 171.098(a)(1).
    Although the denial of Orascom’s bilateral arbitration right under the
    subcontract authorizes an exercise of interlocutory jurisdiction, the same logic does
    not extend to Natgasoline. Unlike Orascom, Natgasoline is not a party to the
    subcontract or the sub-subcontract and is not entitled to enforce the arbitration
    provisions under the particular circumstances present here. See G.T. Leach Builders,
    LLC v. Sapphire V.P., LP, 
    458 S.W.3d 502
    , 524 (Tex. 2015) (“As a general rule, an
    arbitration clause cannot be invoked by a non-party to the arbitration contract.”
    (internal quotation omitted)). Natgasoline does not seek to invoke its own asserted
    right to participate in arbitration — rather, it seeks only to compel arbitration
    between two other parties under contracts it did not sign. Natgasoline has not
    presented any argument or authority that would support recognizing interlocutory
    appellate jurisdiction in these circumstances.          Because the trial court’s orders
    compelling arbitration do not deny to Natgasoline any contractual rights with respect
    to arbitration, we lack jurisdiction over Natgasoline’s attempted interlocutory
    appeal. See 
    9 U.S.C.A. § 16
    ; 
    Tex. Civ. Prac. & Rem. Code Ann. §§ 51.016
    ,
    171.098(a)(1); see also Tex. La Fiesta Auto Sales, LLC, 
    349 S.W.3d at 879
    ;
    McReynolds, 
    222 S.W.3d at 738-39
    .
    We turn now to Refractory Construction’s arguments challenging our
    interlocutory appellate jurisdiction.
    not authorize Refractory Construction to join an arbitration between Orascom and Crawford.
    12
    Asserting that the trial court did not deny Orascom’s and Natgasoline’s
    motion to compel arbitration, Refractory Construction points out that the trial court’s
    May 2017 order denies only Orascom’s and Natgasoline’s “Motion to Stay the Entire
    Case Pending Alternative Dispute Resolution between [Orascom] and Crawford.”
    But our jurisdictional analysis is not limited to the express language of the trial
    court’s order. We instead examine “[t]he substance and function of the order viewed
    in the context of the record.” McReynolds, 
    222 S.W.3d at 738
    ; see also Tex. La
    Fiesta Auto Sales, LLC, 
    349 S.W.3d at 878
    . We also consider the trial court’s June
    2018 order signed in response to this court’s request for clarification as to whether a
    single arbitration proceeding was contemplated. By ordering a single arbitration
    proceeding involving all claims and all parties, the trial court denied Orascom its
    right under the subcontract to arbitrate only with Crawford. See Tex. La Fiesta Auto
    Sales, LLC, 
    349 S.W.3d at 879
    ; McReynolds, 
    222 S.W.3d at 738-39
    . This denial
    gives rise to interlocutory jurisdiction. See 
    9 U.S.C.A. § 16
    ; 
    Tex. Civ. Prac. & Rem. Code Ann. §§ 51.016
    , 171.098(a)(1).
    Refractory Construction asserts that, even if Orascom’s appeal can be
    construed as an interlocutory appeal from an order denying a motion to compel
    arbitration, Orascom nonetheless (1) failed to appeal within 20 days after the trial
    court’s May 2017 order was signed; and (2) is not entitled to an extension of time
    for filing a notice of appeal.
    We conclude that Orascom properly perfected its appeal from an interlocutory
    order. An appeal from an interlocutory order is accelerated. Tex. R. App. P. 28.1(a).
    “[I]n an accelerated appeal, the notice of appeal must be filed within 20 days after
    the judgment or order is signed[.]” 
    Id. at 26
    .1(b). The time to file the notice of
    appeal may be extended if, within 15 days after the deadline for filing the notice of
    appeal, the appealing party files in the trial court a notice of appeal and files in the
    13
    appellate court a motion to extend time for filing a notice of appeal. 
    Id. at 10
    .5(b)(2),
    26.3. A motion to extend time for filing a notice of appeal must state (1) the deadline
    for filing the item in question; (2) the facts relied on to reasonably explain the need
    for an extension; (3) the trial court; (4) the date of the trial court’s judgment or
    appealable order; and (5) the case number or style of the case in the trial court. 
    Id. at 10
    .5(b)(2).
    Here, the trial court signed its order on May 24, 2017. Treating this as an
    appealable interlocutory order, Orascom’s notice of appeal was due no later than 20
    days later on June 13, 2017. Orascom filed its notice of appeal on June 23, 2017.
    Orascom’s notice of appeal included a request for an extension of time:
    [T]o the extent that a court may determine that the Judgment is not a
    final judgment, [Orascom and Natgasoline] alternatively notice this
    appeal as an interlocutory appeal under Texas Civil Practice &
    Remedies Code §§ 51.016 and/or 171.098(a)(1) and request an
    extension of time based on the good cause of the legal uncertainty, if
    any, as to whether the Judgment is not actually a final judgment.
    Citing Texas Rule of Appellate Procedure 10.5(b)(2), Refractory Construction
    asserts that Orascom’s request is “devoid of any reference to the deadline for its
    filing.” Refractory Construction also asserts that “[t]here is no reasonable legal
    uncertainty” warranting an extension.
    The notice’s failure to reference the deadline for its filing does not defeat
    Orascom’s request for an extension of time, and Refractory Construction cites no
    authority holding otherwise. Even an implied motion for an extension of time is
    effective so long as the appellant “come[s] forward with a reasonable explanation to
    support the late filing.” Hykonnen v. Baker Hughes Bus. Support Servs., 
    93 S.W.3d 562
    , 563 (Tex. App.—Houston [14th Dist.] 2002, no pet.); see also Jones v. Funk,
    No. 14-16-00577-CV, 
    2016 WL 5400217
    , at *1 (Tex. App.—Houston [14th Dist.]
    14
    Sept. 27, 2016, no pet.) (per curiam) (mem. op.). A reasonable explanation includes
    any plausible statement of circumstances that shows the failure to file within the
    required time period was not deliberate or intentional, but was the result of
    inadvertence, mistake, or mischance. Hykonnen, 
    93 S.W.3d at 563
    . “Any conduct
    short of deliberate or intentional noncompliance qualifies as inadvertence, mistake,
    or mischance — even if that conduct can be characterized as professional
    negligence.” 
    Id.
    Orascom’s notice provides a “reasonable explanation” for its untimely filing:
    uncertainty with respect to the finality of the trial court’s May 24, 2017 order. This
    explanation suffices to show that Orascom’s failure to file within the required time
    period was not deliberate or intentional. See id.; see also Jones, 
    2016 WL 5400217
    ,
    at *1. Orascom’s motion for an extension of time was effective and makes its notice
    of appeal timely. See Tex. R. App. P. 10.5(b)(2), 26.1(b), 26.3; see also Hykonnen,
    
    93 S.W.3d at 563
    . We reject Refractory Construction’s arguments challenging our
    interlocutory jurisdiction.
    By ordering all parties to arbitrate all claims in a single proceeding, the trial
    court denied to Orascom its right under the subcontract to arbitrate only with
    Crawford. See Tex. La Fiesta Auto Sales, LLC, 
    349 S.W.3d at 879
    ; McReynolds,
    
    222 S.W.3d at 738-39
    . But the same is not true for Natgasoline — the trial court’s
    orders compelling arbitration do not divest any contractual arbitration rights
    belonging to Natgasoline. Therefore, under the FAA and TAA, we have jurisdiction
    to consider Orascom’s interlocutory appeal.       We lack jurisdiction to consider
    Natgasoline’s attempted appeal. See 
    9 U.S.C.A. § 16
    ; 
    Tex. Civ. Prac. & Rem. Code Ann. §§ 51.016
    , 171.098(a)(1); see also Tex. La Fiesta Auto Sales, LLC, 
    349 S.W.3d at 879
    ; McReynolds, 
    222 S.W.3d at 738-39
    .
    The final section of this jurisdictional analysis examines whether mandamus
    15
    relief is available to Natgasoline. See CMH Homes v. Perez, 
    340 S.W.3d 444
    , 453
    (Tex. 2011) (in an “uncertain legal environment,” an appellant may in the alternative
    “request mandamus treatment of its appeal”).
    C.     Mandamus
    Insofar as Natgasoline seeks to undo the trial court’s orders compelling a
    single arbitration proceeding by pursuing a petition for writ of mandamus, we
    conclude that any mandamus relief sought by Natgasoline would be moot. This is
    so because, as discussed more fully below, we reverse the trial court’s orders
    compelling arbitration in an interlocutory appeal properly pursued by Orascom.
    Therefore, we decline to address Natgasoline’s arguments with respect to its
    entitlement to mandamus relief.
    II.     Review of the Trial Court’s Orders Compelling a Single Arbitration
    Proceeding
    We now turn to the merits of Orascom’s authorized interlocutory appeal from
    the denial of its motion to compel a bilateral Orascom-Crawford arbitration under
    the subcontract.
    We review the trial court’s denial of a motion to compel arbitration under an
    abuse of discretion standard. In re Labatt Food Serv., L.P., 
    279 S.W.3d 640
    , 643
    (Tex. 2009) (orig. proceeding); Branch Law Firm L.L.P. v. Osborn, 
    532 S.W.3d 1
    ,
    12 (Tex. App.—Houston [14th Dist.] 2016, pet. denied). We defer to the trial court’s
    factual determinations if they are supported by the record; we review the trial court’s
    legal determinations de novo. In re Labatt Food Serv., L.P., 279 S.W.3d at 643;
    Branch Law Firm L.L.P., 
    532 S.W.3d at 12
    .
    Under the FAA and TAA, a party seeking to compel arbitration must establish
    that (1) there is a valid arbitration agreement; and (2) the claims in dispute fall within
    the scope of that agreement. In re Rubiola, 
    334 S.W.3d 220
    , 223 (Tex. 2011) (orig.
    16
    proceeding) (FAA); McReynolds, 
    222 S.W.3d at 739
     (TAA).
    The parties do not dispute that (1) a valid arbitration agreement exists between
    Orascom and Crawford under the subcontract; and (2) Crawford’s claims against
    Orascom fall within the scope of the subcontract’s arbitration provision. The parties
    dispute whether the subcontract or the sub-subcontract authorizes the trial court to
    deny a bilateral Orascom-Crawford arbitration in favor of a single arbitration
    proceeding involving all parties and all claims. Refractory Construction asserts three
    arguments to support a single arbitration proceeding.
    1.       Under the sub-subcontract and Texas Rule of Civil Procedure 39(a),
    Refractory Construction is a necessary party to an Orascom-Crawford
    arbitration proceeding.
    2.       Estoppel permits Refractory Construction to join a bilateral Orascom-
    Crawford arbitration proceeding under the subcontract.
    3.       Permitting Orascom and Crawford to arbitrate without Refractory
    Construction is contrary to public policy.
    We conclude that these arguments do not authorize a single arbitration proceeding
    involving all parties and all claims. Therefore, the trial court erred in denying
    Orascom’s motion to compel a bilateral Orascom-Crawford arbitration under the
    subcontract.
    A.       Refractory Construction is Not a Necessary Party to a Bilateral
    Orascom-Crawford Arbitration
    Relying heavily on the sub-subcontract’s “Multi-Party Proceeding” provision,
    Refractory Construction asserts that “all parties in the instant litigation should be
    and were properly ordered to arbitrate together.” Orascom argues that the sub-
    subcontract does not support an interpretation that authorizes a single arbitration
    proceeding for all parties and all claims.
    “Arbitration agreements are interpreted under traditional contract principles.”
    17
    J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 227 (Tex. 2003). If we can give
    the agreement’s language a certain and definite meaning, the agreement is
    unambiguous and we construe it as a matter of law. Milner v. Milner, 
    361 S.W.3d 615
    , 619 (Tex. 2012). Our primary concern in construing an agreement is to
    ascertain the intent of the parties as expressed in the instrument. Valence Operating
    Co. v. Dorsett, 
    164 S.W.3d 656
    , 662 (Tex. 2005).
    An agreement’s terms are accorded their “plain and ordinary meaning” unless
    the agreement indicates that the parties intended a different meaning. Dynegy
    Midstream Servs., Ltd. P’ship v. Apache Corp., 
    294 S.W.3d 164
    , 168 (Tex. 2009).
    We presume that the parties intended each contract provision to have effect. Va.
    Power Energy Mktg., Inc. v. Apache Corp., 
    297 S.W.3d 397
    , 403 (Tex. App.—
    Houston [14th Dist.] 2009, pet. denied).
    We examine and consider the agreement as a whole in an effort to harmonize
    and give effect to all provisions so that none are rendered meaningless. Branch Law
    Firm L.L.P., 
    532 S.W.3d at 12
    . “No single provision taken alone will be given
    controlling effect; rather, all the provisions must be considered with reference to the
    whole instrument.” J.M. Davidson, Inc., 128 S.W.3d at 229.
    Refractory Construction focuses its arguments in particular on the sub-
    subcontract’s “Multi-Party Proceeding” provision.         The first sentence of this
    provision states as follows: “All parties necessary to resolve a matter agree to be
    parties to the same dispute resolution proceeding.”
    This first sentence does not exist in isolation. To the contrary, it is followed
    immediately by another sentence applying this “Multi-Party Proceeding” provision
    “[t]o the extent disputes between [Orascom] . . . and [Crawford] . . . involve in whole
    or in part disputes between [Orascom] . . . and [Natgasoline] . . . .”
    18
    If a dispute between Orascom and Crawford also involves a dispute between
    Orascom and Natgasoline, then “at the sole discretion of [Orascom] . . . disputes
    between [Crawford] . . . and [Orascom] . . . shall be decided by the same tribunal
    and in the same forum as disputes between [Crawford] . . . and [Natgasoline] . . . .”
    Arguing in favor of a single arbitration proceeding encompassing all parties
    and all claims, Refractory Construction first points to the sub-subcontract’s
    definition of “Parties:”
    The “Parties” are collectively the CONTRACTOR and the
    SUBCONTRACTOR including their SubSubcontractors.
    Refractory Construction contends that this definition of “Parties,” when read in
    conjunction with the first sentence of the sub-subcontract’s “Multi-Party
    Proceeding” provision, supports the denial of a bilateral Orascom-Crawford
    arbitration in favor of a single arbitration proceeding involving all parties and all
    claims.
    The sub-subcontract is unambiguous and we ascertain its meaning as a matter
    of law. See Milner, 361 S.W.3d at 619. Under these unambiguous terms we reject
    Refractory Construction’s interpretation of the sub-subcontract — and with it,
    Refractory Construction’s reliance upon the sub-subcontract to override the bilateral
    Orascom-Crawford arbitration mandated under the subcontract. We do so for two
    reasons.
    First, the sub-subcontract defines “Parties” as a capitalized term that includes,
    collectively, contractor Orascom, subcontractor Crawford, and Orascom’s and
    Crawford’s sub-subcontractors. “Parties” as a capitalized term is employed in
    multiple sub-subcontract provisions, including those addressing the scope of the
    work, the progress schedule, indemnity, insurance, and bonds.
    The sub-subcontract’s “Multi-Party Proceeding” provision, in contrast,
    19
    utilizes the word “parties” in its uncapitalized form. Ignoring the uncapitalized use
    of “parties” in favor of applying the defined, capitalized term would vitiate the sub-
    subcontract’s distinction between “Parties” and “parties.” We decline to apply an
    interpretation of the sub-subcontract that would render these distinctions
    meaningless. See Branch Law Firm L.L.P., 
    532 S.W.3d at 12
    ; Va. Power Energy
    Mktg., Inc., 
    297 S.W.3d at 403
    ; see also PopCap Games, Inc. v. MumboJumbo, LLC,
    
    350 S.W.3d 699
    , 708 (Tex. App.—Dallas 2011, pet. denied) (“The use of different
    language in different parts of a contract generally means that the parties intended
    different things.”).
    Second, even if we were to apply the defined term “Parties” to the sub-
    subcontract’s “Multi-Party Proceeding” provision, this provision still would not
    authorize Refractory Construction to compel a single arbitration proceeding
    encompassing all parties (including Refractory Construction) and all claims.
    The subcontract and sub-subcontract contain identical “Multi-Party
    Proceeding” provisions, and we consider these contracts together to ascertain the
    “Multi-Party Proceeding” provisions’ intended effect. See DeWitt Cty. Elec. Coop.,
    Inc. v. Parks, 
    1 S.W.3d 96
    , 102 (Tex. 1999) (“Under generally accepted principles
    of contract interpretation, all writings that pertain to the same transaction will be
    considered together, even if they were executed at different times and do not
    expressly refer to one another.”); Cleveland Constr., Inc. v. Levco Constr., Inc., 
    359 S.W.3d 843
    , 852-53 (Tex. App.—Houston [1st Dist.] 2012, pet. dism’d) (same).
    The identical “Multi-Party Proceeding” provisions in both the subcontract and
    the sub-subcontract provide that Orascom has sole discretion to add a party to an
    arbitration proceeding between Orascom and Crawford. That additional party is
    Natgasoline. Neither the subcontract nor the sub-subcontract grants Refractory
    Construction a parallel right to add itself or another party to an arbitration proceeding
    20
    between Orascom and Crawford, or to inject itself into the bilateral Orascom-
    Crawford arbitration mandated by the subcontract.          Refractory Construction’s
    overbroad interpretation of the provisions’ first sentence cannot be harmonized with
    the second sentence’s limited allocation of sole discretion to Orascom to add
    Natgasoline to an Orascom-Crawford arbitration. See J.M. Davidson, Inc., 128
    S.W.3d at 229; Branch Law Firm L.L.P., 
    532 S.W.3d at 12
    . Therefore, we reject
    Refractory Construction’s interpretation of the sub-subcontract’s “Multi-Party
    Proceeding” provision.
    Refractory Construction also relies on Texas Rule of Civil Procedure 39 to
    support its contention that it is a necessary party to an Orascom-Crawford
    arbitration. But “absent a specific agreement[,] the rules of civil procedure and
    joinder of claims and parties do not apply in arbitration.” Crossmark, Inc. v. Hazar,
    
    124 S.W.3d 422
    , 434 (Tex. App.—Dallas 2004, pet. denied); see also In re F.C.
    Holdings, Inc., 
    349 S.W.3d 811
    , 816 (Tex. App.—Tyler 2011, orig. proceeding
    [mand. denied]).
    The subcontract’s and sub-subcontract’s arbitration provisions do not invoke
    the Texas Rules of Civil Procedure; the provisions state that they are governed by
    the arbitration rules promulgated by the International Chamber of Commerce. Texas
    Rule of Civil Procedure 39 therefore does not provide a basis to compel a
    consolidated arbitration involving all parties and all claims.
    B.     Estoppel
    Refractory Construction asserts that “equitable estoppel operates to estop
    [Orascom and Crawford], signatories to the subcontract, from arbitrating in
    [Refractory Construction’s] absence.”
    The parties encompassed by an arbitration agreement generally are
    21
    determined with reference to the parties’ intent as expressed by the agreement’s
    terms. Jody James Farms, JV v. Altman Group, Inc., 
    547 S.W.3d 624
    , 633 (Tex.
    2018). Arbitration with a non-signatory may be required in several circumstances,
    including (1) incorporation by reference, (2) assumption, (3) agency, (4) alter ego,
    (5) estoppel, and (6) third-party beneficiary. Id.; see also Cotton Commercial USA,
    Inc. v. Clear Creek Ind. Sch. Dist., 
    387 S.W.3d 99
    , 104-04 & n.4 (Tex. App.—
    Houston [14th Dist.] 2012, no pet.). “Estoppel” encompasses two distinct bases for
    compelling arbitration with respect to non-signatories: direct benefits estoppel and
    intertwined claims estoppel. See Jody James Farms, JV, 547 S.W.3d at 637-40.
    Despite its status as a non-signatory to the subcontract, Refractory
    Construction contends that it can join an Orascom-Crawford bilateral arbitration
    under the subcontract pursuant to the direct benefits and intertwined claims bases
    for estoppel. We examine each theory in turn.
    1.     Direct benefits estoppel
    Under principles of direct benefits estoppel, “‘a litigant who sues based on a
    contract subjects him or herself to the contract’s terms . . . including the Arbitration
    Addendum.” G.T. Leach Builders, LLC, 458 S.W.3d at 527 (quoting In re FirstMerit
    Bank, N.A., 
    52 S.W.3d 749
    , 755-56 (Tex. 2001) (orig. proceeding)). Direct benefits
    estoppel prevents a claimant from seeking benefits under a contract while
    simultaneously attempting to avoid the contract’s obligations, such as an obligation
    to arbitrate disputes. In re Kellogg Brown & Root, Inc., 
    166 S.W.3d 732
    , 739 (Tex.
    2005) (orig. proceeding). “Thus, a non-signatory plaintiff may be compelled to
    arbitrate if it seeks to enforce terms of a contract containing an arbitration provision.”
    
    Id.
    Direct benefits estoppel does not apply merely because a non-signatory’s
    claim “relates to” a contract containing an arbitration agreement. G.T. Leach
    22
    Builders, LLC, 458 S.W.3d at 527. Rather, the non-signatory must “seek to derive
    a direct benefit” from the agreement such that its claim “depend[s] on the existence
    of the contract and [would] be unable to stand independently without the contract.”
    Id. at 527-28 (internal quotations omitted); see, e.g., Rachal v. Reitz, 
    403 S.W.3d 840
    , 847-48 (Tex. 2013) (by pursuing a suit based on a trust’s terms and validity, the
    non-signatory beneficiary was barred by direct benefits estoppel from avoiding a
    trust’s arbitration provision); In re FirstMerit Bank, N.A., 52 S.W.3d at 752-53, 755-
    56 (by suing based on the contract, the plaintiffs sought benefits that stemmed
    directly from the contract; the plaintiffs therefore were subject to the contract’s
    arbitration provision). If a non-signatory’s claims can stand independently of the
    underlying contract, then arbitration generally should not be compelled under a
    theory of direct benefits estoppel. In re Kellogg Brown & Root, Inc., 166 S.W.3d at
    739-40.
    To support its invocation of direct benefits estoppel as a basis for joining the
    bilateral Orascom-Crawford arbitration, Refractory Construction asserts that
    Orascom “call[s] for an interpretation of the sub-subcontract . . . which would
    provide Orascom with the sole discretion to join parties to an arbitration under the
    sub-subcontract” (emphasis in original). When Orascom asserts its interpretation of
    the sub-subcontract, Refractory Construction argues that Orascom “clearly seek[s]
    to derive direct benefits” from the sub-subcontract — benefits that in turn permit
    Refractory Construction to join a bilateral Orascom-Crawford arbitration under the
    subcontract.
    We reject Refractory Construction’s contention. Direct benefits estoppel
    prevents a party from asserting a claim under a contract and simultaneously avoiding
    the contract’s obligations, such as an arbitration provision. See G.T. Leach Builders,
    LLC, 458 S.W.3d at 527; In re Kellogg Brown & Root, Inc., 166 S.W.3d at 739.
    23
    Here, Orascom asserts no claims against Refractory Construction under the sub-
    subcontract to which Orascom is not a signatory. Orascom therefore does not seek
    to derive a “direct benefit” from the sub-subcontract as necessary to invoke direct
    benefits estoppel. See G.T. Leach Builders, LLC, 458 S.W.3d at 527 (direct benefits
    estoppel prevents a plaintiff from asserting a claim that “depend[s] on the existence”
    of the contract but simultaneously avoiding the contract’s arbitration provision); In
    re Kellogg Brown & Root, Inc., 166 S.W.3d at 739 (“a non-signatory plaintiff may
    be compelled to arbitrate if its claims are ‘based on a contract’ containing an
    agreement to arbitrate”).
    Under these circumstances, Refractory Construction cannot invoke the sub-
    subcontract and direct benefits estoppel to justify a single arbitration proceeding
    involving all parties and all claims in place of the bilateral Orascom-Crawford
    arbitration specified under the subcontract.
    2.    Intertwined claims estoppel
    Refractory Construction asserts that the theory of intertwined claims estoppel
    prevents Orascom and Crawford from arbitrating without Refractory Construction
    because Refractory Construction’s “claims are so intertwined with the subcontract.”
    In Merrill Lynch Investment Managers v. Optibase, Ltd., 
    337 F.3d 125
     (2nd
    Cir. 2003), the Second Circuit discussed an “alternative estoppel theory,” also called
    “intertwined-claims theory.” 
    Id. at 131
    . Intertwined claims estoppel may permit a
    non-signatory to compel arbitration when (1) the non-signatory has a close
    relationship with a signatory to a contract with an arbitration agreement, and (2) the
    non-signatory’s claims are “intimately founded in and intertwined with the
    underlying contract obligations.” See In re Merrill Lynch Trust Co. FSB, 
    235 S.W.3d 185
    , 193 (Tex. 2007) (orig. proceeding); see also Jody James Farms, JV,
    547 S.W.3d at 639. This estoppel formulation has not been adopted by the Supreme
    24
    Court of Texas. See Jody James Farms, JV, 547 S.W.3d at 639; In re Merrill Lynch
    Trust Co. FSB, 235 S.W.3d at 193.
    Limiting the application of intertwined claims estoppel, the Second Circuit
    has clarified that the theory does not apply “whenever a relationship of any kind may
    be found among the parties to a dispute and their dispute deals with the subject matter
    of an arbitration contract made by one of them.” Sokol Holdings, Inc. v. BMB Munai,
    Inc., 
    542 F.3d 354
    , 359 (2nd Cir. 2008). Instead, the Second Circuit decisions that
    compel arbitration on the basis of intertwined claims “typically involve some
    corporate affiliation between a signatory and non-signatory, not just a working
    relationship.” Jody James Farms, JV, 547 S.W.3d at 640 (citing Sokol Holdings,
    Inc., 
    542 F.3d at 359-61
    ).
    Declining to adopt intertwined claims estoppel in Jody James Farm, JV, the
    Supreme Court of Texas noted that the defendants “may have an entangled business
    relationship” with respect to the transaction at issue, but no evidence “show[ed] them
    to be anything other than independent and distinct entities.”        
    Id.
     To compel
    arbitration based on intertwined claims estoppel, “the relationship must be closer
    than merely independent participants in a business transaction.” 
    Id.
    Here, too, the evidence does not show that Orascom, Crawford, and
    Refractory Construction are “anything other than independent and distinct entities”
    that contracted to participate in a construction project. See 
    id.
     Intertwined claims
    estoppel cannot arise solely from this working relationship. See id.; see also Merrill
    Lynch Investment Managers, 
    337 F.3d at 131
    ; In re Merrill Lynch Trust Co. FSB,
    235 S.W.3d at 193. Because the parties are “merely independent participants in a
    business transaction,” intertwined claims estoppel does not authorize a single
    arbitration proceeding involving all parties and all claims. See Merrill Lynch Inv.
    Managers, 
    337 F.3d at 131
    ; Jody James Farms, JV, 547 S.W.3d at 639; In re Merrill
    25
    Lynch Trust Co. FSB, 235 S.W.3d at 193.
    C.     Public Policy
    Refractory Construction asserts that an arbitration between Orascom and
    Crawford without Refractory Construction’s participation would permit its “rights
    to be adjudicated in its absence” and would leave Refractory Construction “with
    effectively no remedy.”
    Although arbitration is favored under public policy, it also is a creature of
    contract and “cannot be ordered in the absence of an agreement to arbitrate.” Cedillo
    v. Immobiliere Jeuness Establissement, 
    476 S.W.3d 557
    , 564 (Tex. App.—Houston
    [14th Dist.] 2015, pet. denied); see also In re Kellogg Brown & Root, Inc., 166
    S.W.3d at 738.
    Here, the subcontract mandates a bilateral Orascom-Crawford arbitration
    proceeding. Neither the subcontract nor the sub-subcontract permits Refractory
    Construction to override this mandate in favor of a single arbitration proceeding
    involving all parties and all claims. Refractory Construction’s estoppel arguments
    also do not provide a basis to compel a consolidated arbitration proceeding.
    Standing alone, Refractory Construction’s policy arguments do not support denying
    a bilateral Orascom-Crawford arbitration under the subcontract in favor of a single
    proceeding involving all parties and all claims. See In re Kellogg Brown & Root,
    Inc., 166 S.W.3d at 738; Cedillo, 476 S.W.3d at 564.          We reject Refractory
    Construction’s public policy arguments.
    CONCLUSION
    In their notice of appeal and before this court, Orascom and Natgasoline assert
    that appellate jurisdiction exists here because this proceeding is (1) an appeal from
    a final judgment; or (2) a statutorily authorized interlocutory appeal; or (3) a
    26
    mandamus proceeding.       We conclude that we have jurisdiction to consider
    Orascom’s interlocutory appeal and lack appellate jurisdiction over Natgasoline’s
    appeal.
    Considering the merits of Orascom’s authorized interlocutory appeal, we
    conclude that the trial court erred in denying Orascom’s motion to compel a bilateral
    Orascom-Crawford arbitration under the subcontract, and in ordering instead a
    single arbitration proceeding involving all parties and all claims. We reverse the
    trial court’s May 24, 2017 and June 6, 2018 orders and remand for further
    proceedings consistent with this opinion.
    /s/    William J. Boyce
    Justice
    Panel consists of Justices Boyce, Christopher, and Busby.
    27