Entergy Texas, Inc. v. Public Utility Commission of Texas, Office of Public Utility Counsel, and Texas Industrial Energy Consumers ( 2015 )


Menu:
  •                                                                                      ACCEPTED
    03-14-00709-CV
    4187470
    THIRD COURT OF APPEALS
    AUSTIN, TEXAS
    2/18/2015 9:33:00 AM
    JEFFREY D. KYLE
    CLERK
    NO. 03-14-00709-CV
    FILED IN
    3rd COURT OF APPEALS
    IN THE COURT OF APPEALS        AUSTIN, TEXAS
    FOR THE THIRD DISTRICT OF TEXAS2/18/2015 9:33:00 AM
    AUSTIN, TEXAS           JEFFREY D. KYLE
    Clerk
    ENTERGY TEXAS, INC.
    Appellants,
    v.
    PUBLIC UTILITY COMMISSION OF TEXAS
    Appellee.
    Appeal from the 53rd Judicial District Court, Travis County, Texas
    The Honorable Amy Clark Meachum, Judge Presiding
    APPELLEE TEXAS INDUSTRIAL ENERGY CONSUMERS’ BRIEF
    FEBRUARY 13, 2015
    Rex D. VanMiddlesworth
    rex.vanmiddlesworth@tklaw.com
    State Bar No. 20449400
    Benjamin Hallmark
    benjamin.hallmark@tklaw.com
    State Bar No. 24069865
    THOMPSON & KNIGHT LLP
    98 San Jacinto Blvd., Suite 1900
    Austin, TX 78701
    Telephone: (512) 469-6100
    Facsimile: (512) 469-6180
    ATTORNEYS FOR APPELLEE TEXAS
    INDUSTRIAL ENERGY CONSUMERS
    ORAL ARGUMENT REQUESTED
    TABLE OF CONTENTS
    PAGE
    TABLE OF AUTHORITIES .............................................................................................. iv
    STATUTORY AUTHORITIES .......................................................................................... v
    LEGISLATION ................................................................................................................... v
    STATEMENT OF THE CASE ......................................................................................... vii
    STATEMENT ON ORAL ARGUMENT ......................................................................... vii
    RESTATED ISSUES PRESENTED ................................................................................. vii
    STATEMENT OF FACTS .................................................................................................. 1
    I.        The legislature delayed deregulation in ETI’s service area, but took a
    small step towards competition by authorizing a CGS program................... 1
    II.       ETI proposed a CGS tariff in Commission Docket 37744. .......................... 3
    III.      The parties agreed on a different CGS program in Docket 38951, but
    could not agree on what costs would be unrecovered as a result of its
    implementation. ............................................................................................. 5
    IV.       The Commission found that the only costs that would be
    unrecovered as a result of implementation of the new CGS program
    were the costs to implement and administer it. ............................................. 6
    V.        The Commission rejected ETI’s proposal to surcharge pre-
    implementation CGS regulatory expenses and denied ETI’s request
    for interest on costs of implementing a CGS program. ............................... 10
    SUMMARY OF ARGUMENT ......................................................................................... 11
    ARGUMENT..................................................................................................................... 15
    I.        The Commission’s finding on ETI’s unrecovered costs is supported
    by substantial evidence and consistent with the CGS statute. .................... 15
    A.        Standard of Review .......................................................................... 15
    i
    B.        The evidence showed that ETI would not incur any costs to
    serve CGS customers that would be unrecovered, other than
    implementation and administration costs. ........................................ 16
    C.        ETI did not prove that it has unavoidable fixed generation
    costs that would be unrecovered as a result of the CGS
    program. ........................................................................................... 19
    D.        The Commission properly determined that the costs to
    implement and administer the CGS tariff would be
    unrecovered and included this finding in its order. .......................... 22
    E.        The Commission properly rejected ETI’s attempt to recast the
    statutory term “costs unrecovered” as lost revenues. ....................... 23
    1.        The Commission’s interpretation is consistent with the plain
    language of PURA § 39.452(b)............................................. 23
    2.        The Commission’s decision is consistent with the
    CenterPoint 2011 precedent.................................................. 25
    3.        ETI sought lost revenues at the Commission, not unrecovered
    costs. ...................................................................................... 30
    4.        The Commission’s rejection of ETI’s lost-revenues theory is
    consistent with the purposes of the CGS statute. .................. 33
    5.        High Plains is inapposite. ..................................................... 34
    F.        Contrary to ETI’s contentions, the Commission’s decision
    was based on a vast evidentiary record, not “solely upon its
    interpretation of the CGS statute” .................................................... 35
    II.    The Commission properly rejected ETI’s request to surcharge legal
    and regulatory costs incurred from 2010 to 2013 as costs of
    implementation. ........................................................................................... 38
    III.   The Commission properly rejected ETI’s request for interest on
    CGSC rider costs. ........................................................................................ 42
    A.        When the legislature intends to award carrying costs, it says
    so. ..................................................................................................... 42
    B.        The Commission has not allowed interest to be recovered on
    similar expenses. .............................................................................. 44
    ii
    PRAYER ........................................................................................................................... 46
    CERTIFICATE OF COMPLIANCE ................................................................................ 47
    CERTIFICATE OF SERVICE .......................................................................................... 48
    APPENDIX ....................................................................................................................... 49
    iii
    TABLE OF AUTHORITIES
    PAGE
    Cases
    CenterPoint Energy Houston Electric, LLC v. Public Util. Comm’n of Tex.
    
    354 S.W.3d 899
    (Tex. App. – Austin 2011, no pet.) ................................... passim
    CenterPoint Energy Houston Electric, LLC v. Public Util. Comm’n of Tex.,
    
    408 S.W.3d 910
    (Tex. App. – Austin 2013, pet. Denied .....................................41
    CenterPoint Energy, Inc. v. Public Util. Comm’n of Tex.
    
    143 S.W.3d 81
    (Tex. 2004) ..................................................................................46
    City of El Paso v. Pub. Util. Comm’n,
    
    883 S.W.2d 179
    (Tex. 1994) ................................................................................16
    In re Entergy Corp.,
    
    142 S.W.3d 316
    (Tex. 2004) .................................................................................1
    Laidlaw Waste Sys., Inc. v. City of Wilmer,
    
    904 S.W.2d 656
    (Tex. 1995) ......................................................................... 44, 45
    Moran Util. Co. v. R.R. Comm’n,
    
    697 S.W.2d 447
    , (Tex. App.—Austin 1985, pet. granted) (aff’d in
    relevant part, rev’d in part, 
    728 S.W.2d 764
    (Tex. 1987) ....................................46
    Office of Public Utility Counsel v. Texas-New Mexico Power Co.,
    
    344 S.W.3d 446
    (Tex. App.—Austin 2011, pet. denied)....................................38
    R.R. Comm’n v. High Plains Natural Gas Co.,
    
    628 S.W.2d 753
    (Tex. 1981) ................................................................................34
    R.R. Comm’n v. Texas Citizens for a Safe Future & Clean Water,
    
    336 S.W.3d 619
    (Tex. 2011) ......................................................................... 16, 24
    Reliant Energy, Inc. v. Pub. Util. Comm’n,
    
    153 S.W.3d 174
    (Tex. App.—Austin 2004, pet. denied).....................................16
    State Banking Board v. Allied Bank Marble Falls,
    
    748 S.W.2d 447
    (Tex. 1988) ...............................................................................38
    iv
    Texas Health Facilities Comm’n v. Charter Med.-Dallas, Inc.,
    
    665 S.W.2d 446
    (Tex. 1984) (citing Gerst v. Guardian Sav. & Loan
    Ass’n, 
    434 S.W.2d 113
    (Tex. 1968))............................................................. 15, 16
    STATUTORY AUTHORITIES
    Tex. Gov’t Code Ann. § 2001.174...........................................................................15
    Tex. Gov’t Code Ann. § 2001.175...........................................................................15
    Tex. Util. Code Ann. § 36.061 .................................................................... 43, 44, 45
    Tex. Util. Code Ann. §§ 36.402 ........................................................................ 43, 44
    Tex. Util. Code Ann. §§ 39.011-.359 ...................................................................... 1
    Tex. Util. Code Ann. § 39.452 ......................................................................... passim
    Tex. Util. Code Ann. § 39.4525 ........................................................................ 43, 44
    Tex. Util. Code Ann. § 39.454 .......................................................................... 43, 44
    Tex. Util. Code Ann. § 39.459 .......................................................................... 43, 44
    Tex. Util. Code Ann. § 39.905 ...................................................................... 26,27,28
    LEGISLATION
    Act of May 24, 2005, 79th Leg., R.S., ch. 1072, § 1, 2005 Tex. Sess. Law
    Serv. 3559, available at
    http://www.legis.state.tx.us/tlodocs/79R/billtext/pdf/HB01567F.pdf ........ 1, 2, 24
    Act of May 30, 2009, 81st Leg., R.S., ch. 1226, § 3, 2009 Tex. Sess. Law
    Serv. 3913, available at
    http://www.legis.state.tx.us/tlodocs/81R/billtext/pdf/SB01492F.pdf......................2, 24
    v
    COMMISSION PROCEEDINGS
    Application of CenterPoint Energy Houston Electric, LLC for a
    Competition Transition Charge, Docket No. 30706 ............................................45
    Application of Reliant Energy HL&P for Approval of Unbundled Cost of
    Service Rate Pursuant to PURA § 39.201 and Public Utility Commission
    Substantive Rule 25.344, Docket No. 22355................................................. 45, 46
    Complaint of the City of McKinney Against Southwestern Bell Telephone
    Company, Docket No. 11027 ...............................................................................45
    Petition of Texas Electric Service Co. for Authority to Change Rates,
    Docket 2606, 5 P.U.C. BULL. 109 .....................................................................45
    vi
    STATEMENT OF THE CASE
    This is an administrative appeal of an order of the Public Utility
    Commission of Texas (the Commission) in a contested-case proceeding. The order
    establishes a Competitive Generation Service (CGS) tariff, which would allow
    eligible customers to obtain their electricity from a supplier other than Entergy
    Texas, Inc. (ETI).
    STATEMENT ON ORAL ARGUMENT
    To the extent the Court grants any request for oral argument, TIEC requests
    the opportunity to be heard.
    RESTATED ISSUES PRESENTED
    (1) Whether the Commission’s findings of fact regarding the costs that
    would be unrecovered as a result of the implementation of the CGS program are
    supported by substantial evidence and consistent with PURA § 39.452(b);
    (2) Whether certain of ETI’s litigation and regulatory expenses, which
    would have been incurred whether or not the Commission implemented a CGS
    tariff, and which were already being recovered in ETI’s base rates, can be charged
    to ratepayers as CGS implementation costs through a special rider; and
    (3) Whether PURA mandates that ETI receive interest on the costs of CGS
    implementation in the absence of any statutory reference to interest.
    vii
    GLOSSARY OF ABBREVIATIONS
    AR, Supp.    Administrative Record and Supplemental Administrative Record,
    AR           organized by binders, exhibits, and transcripts
    CGS          Competitive Generation Service, created by PURA § 39.452(b)
    The Competitive Generation Service Costs Rider was designed to
    CGSC Rider   recover the costs of implementing and administering the program;
    approved by the PUC in Docket 39851 Order.
    The Competitive Generation Service Unrecovered Costs Rider
    CGSUSC
    was first proposed by ETI in Docket No. 37744, but was not
    Rider
    approved in either Docket 37744 or 38951.
    Commission   Public Utility Commission of Texas
    or PUC
    Entergy Operating Committee, the entity that conducts generation
    EOC
    planning on behalf of ETI and its sister companies in other states.
    ETI          Entergy Texas, Inc.
    “Large Industrial Power Service,” the tariff schedule under which
    LIPS
    most of ETI’s industrial customers take power.
    MW           Megawatt, a measure of energy (equal to 1000 kilowatts)
    PFD          Proposal for Decision
    PURA         Public Utility Regulatory Act, Tex. Util. Code §§ 11.001 et seq.
    TIEC         Texas Industrial Energy Consumers
    viii
    STATEMENT OF FACTS
    Appellee Texas Industrial Energy Consumers (TIEC) is an association of
    industrial consumers whose principal purpose is to address electricity matters at the
    Public Utility Commission (“the Commission”). 1 TIEC files this brief in support
    of the Commission’s order implementing a Competitive Generation Service
    (“CGS”) tariff for Entergy Texas, Inc. (“ETI”).
    I.     The legislature delayed deregulation in ETI’s service area, but took a
    small step towards competition by authorizing a CGS program.
    ETI is an investor-owned utility that provides bundled generation,
    transmission, distribution, and customer service to retail customers in Southeast
    Texas.2 In 1999, the legislature mandated that investor-owned utilities in Texas
    transition to competition. 3 The transition in ETI’s service area, however, was not
    smooth.4 Consequently, in 2005 the legislature enacted a special subchapter of
    PURA to specifically address ETI during the move to competition. 5                        This
    subchapter applies to no other utilities. 6 The legislation removed the mandate that
    1
    Supp. AR, Docket No. 37744, Item 2, Motion to Intervene of TIEC; AR Binder 1, Docket No.
    38951, Item 46, List of Participating Members of TIEC.
    2
    Supp. AR, Docket No. 37744, ETI Ex. 4, Domino Direct at 1.
    3
    Tex. Util. Code Ann. (“PURA”) §§ 39.011-.359.
    4
    See, e.g., In re Entergy Corp., 
    142 S.W.3d 316
    , 319-20 (Tex. 2004).
    5
    Act of May 24, 2005, 79th Leg., R.S., ch. 1072, § 1, 2005 Tex. Sess. Law Serv. 3559) (HB 1567)
    (codified at PURA subch. J, §§ 39.451-39.463). This legislation can be accessed at
    http://www.legis.state.tx.us/tlodocs/79R/billtext/pdf/HB01567F.pdf.
    6
    PURA § 39.451.
    1
    ETI proceed to a competitive market for generation, but still took a partial step
    toward competition by requiring ETI to propose a CGS tariff that would, if
    approved, allow eligible customers to obtain the generation of their electricity
    from another source.7
    In 2009, the legislature amended this provision to statutorily delay ETI’s
    transition to competition. 8 At the same time, however, the legislature reiterated the
    requirement that ETI propose a CGS tariff, adding additional instructions for
    implementation. The legislature also removed any requirement that the CGS tariff
    be proposed in a base rate case.9
    The 2009 legislation is codified in PURA § 39.452. Section 39.452(b)
    authorizes a CGS tariff that, if approved by the Commission, would allow certain
    customers to purchase their electricity from a third party. ETI would continue to
    provide transmission service and other services, but the electricity itself would be
    generated and provided from another source. 10 The same section states that “the
    utility’s rates shall be set, in the proceeding in which the tariff is adopted, to
    7
    Act of May 24, 2005, 79th Leg., R.S., ch. 1072, § 1, 2005 Tex. Sess. Law Serv. 3559) (HB
    1567).
    8
    Act of May 30, 2009, 81st Leg., R.S., ch. 1226, § 3, 2009 Tex. Sess. Law Serv. 3913, 3914 (SB
    1492) (codified at PURA § 39.452(i)).                 This legislation can be accessed at
    http://www.legis.state.tx.us/tlodocs/81R/billtext/pdf/SB01492F.pdf.
    9
    
    Id. (codified at
    PURA § 39.452(b)), (removing “As part of a Subchapter C, Chapter 36, rate
    proceeding, the” from PURA § 39.452 (b)).
    10
    PURA § 39.452(b).
    2
    recover any costs unrecovered as a result of the implementation of the tariff.” 11
    The Commission’s application of this provision is at issue in this appeal.
    II.    ETI proposed a CGS tariff in Commission Docket 37744.
    ETI initially proposed a CGS program in Docket 37744, a base rate case, in
    2009. 12 The Commission referred the case to the State Office of Administrative
    Hearings (“SOAH”) to be tried by an administrative law judge (“ALJ”). 13 ETI
    raised a number of issues with the costs it claimed would be unrecovered under the
    CGS tariff it submitted. 14 One such issue was ETI’s witness’s assertion that ETI
    would still be required to provide capacity to a CGS customer even if that
    customer was purchasing its capacity elsewhere. 15 That was because the Entergy
    Operating Committee (“EOC”)—the entity that conducted generation planning on
    behalf of ETI and its sister companies in other states—would not recognize that a
    contract between the CGS customer and the CGS supplier would be a firm contract
    for ETI’s planning purposes. 16 According to ETI, this meant that, despite the fact
    11
    
    Id. 12 Supp.
    AR, Docket No. 37744, ETI Ex. 1, Entergy Texas, Inc.’s Statement of Intent and
    Application for Authority to Change Rates and Reconcile Fuel Costs.
    13
    Supp. AR, Docket No. 37744, Item 1, Order of Referral to State Office of Administrative
    Hearings (SOAH).
    14
    Supp. AR, Docket No. 37744, Item 37, Proposal for Decision (PFD) at 26, (“…ETI has given
    the Commission a worst-case scenario of 75 million dollars in unrecovered costs if every eligible
    customer participates.”).
    15
    Supp. AR, Docket No. 37744, Item 21, Initial Brief of Entergy Texas, Inc. on Proposed CGS
    at 20-21; Supp. AR, Docket No. 37744, Transcripts, HOM Vol. D at 51-52.
    16
    Supp. AR, Docket No. 37744, Item 37, PFD at 35-36.
    3
    that a CGS customer would be obtaining its electricity from an outside supplier,
    ETI would still be required to pay for generation capacity as if the CGS customer
    were actually buying its electricity from ETI. 17
    For whatever reason, ETI proposed no limits whatsoever on the number of
    customers or megawatts that could use CGS service, and then asserted that it could
    potentially lose all of the Large Industrial Power Service class (“LIPS”) to the CGS
    program. 18 At the time, these customers represented 651 megawatts of ETI’s total
    demand. 19
    The ALJ in Docket 37444 agreed with ETI that, under the CGS program ETI
    had proposed, ETI would still incur production costs to serve CGS customers
    despite the fact that these customers would obtain their electricity elsewhere,
    because the EOC would require ETI to buy capacity for these customers as if they
    were buying from ETI. 20 In light of this finding, and the fact that ETI’s proposal
    would save no capacity costs but merely shift these costs to ETI’s other
    customers, 21 the ALJ recommended that the CGS program ETI proposed in Docket
    17
    Supp. AR, Docket No. 37744, Item 21, Initial Brief of Entergy Texas, Inc. on Proposed CGS
    at 20.
    18
    Supp. AR, Docket No. 37744, ETI Ex. 9, May Direct at 13.
    19
    
    Id. 20 Supp.
    AR, Docket No. 37744, Item 37, PFD at 36, FoF 44.
    21
    
    Id. at FoF
    17.
    4
    37444 be rejected altogether.22 It was unsurprising that ETI did not object to this
    recommendation.23
    III.   The parties agreed on a different CGS program in Docket 38951, but
    could not agree on what costs would be unrecovered as a result of its
    implementation.
    ETI’s statement of facts describes in detail the CGS program it originally
    proposed in Docket 37444,24 but it fails to describe the key elements of the
    program the Commission actually approved in Docket 38951, from which this
    appeal lies. Because of this, one could be left with the impression that the program
    ETI proposed (and ultimately abandoned) in Docket 37444 is the CGS program at
    issue in this case.    However, the Commission did not approve that program.
    Instead, the Commission severed the CGS issues into Docket 38951 for further
    consideration.25 At the Commission’s urging, the parties began settlement talks on
    a revised CGS program and subsequently agreed on a new approach. The key
    element of this revised program was that the EOC would recognize that the CGS
    customer’s electricity was being provided by a third party, not ETI. 26 Thus, ETI
    22
    Supp. AR, Docket No. 37744, Item 37, PFD at 41.
    23
    Supp. AR, Docket No. 37744, Item 41, Exceptions of Entergy Texas, Inc. at 1.
    24
    ETI’s Appellant’s Brief at 9.
    25
    Supp. AR, Docket No. 37744, Item 53, PUC Order No. 14 – Memorializing Decision Granting
    Motion to Sever.
    26
    ETI’s agreement to do so was conditioned on certain conditions being met. AR Binder 2,
    Docket No. 38951, Item 119, Final Order at Finding of Fact (“FoF”) 41G.
    5
    would no longer have to incur any capacity costs to serve the CGS customer. 27
    The parties also agreed that only a small amount of ETI’s total load—a maximum
    of 115 megawatts—could participate in the CGS program. 28
    While the parties were able to agree on most of the previously contested
    issues surrounding the CGS program, they were not able to agree on what costs
    would be unrecovered as a result of its implementation. 29 Accordingly, the parties
    submitted additional testimony on the costs that would be unrecovered under the
    new program, and the Commission held an evidentiary hearing to decide the
    issue. 30
    IV.     The Commission found that the only costs that would be unrecovered as
    a result of implementation of the new CGS program were the costs to
    implement and administer it.
    ETI maintained in Docket 38951 that it was entitled to recover lost revenues
    for every kilowatt that a CGS customer purchased from a source other than ETI,
    even though ETI would no longer have any obligation to provide generation for the
    27
    Under the agreement, ETI would still provide back-up power when the CGS customer was
    unavailable. The CGS customer would pay for this power. AR Binder 4, Docket No. 38951,
    TIEC Ex. 15, Supplemental Direct Testimony and Exhibits of Jeffry Pollock at 15; AR Binder 2,
    Docket No. 38951, Item 119, Final Order at 19-20 (describing unserved energy rate and CGS
    cost distribution).
    28
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 36.
    29
    
    Id. at 3-4.
    30
    
    Id. 6 CGS
    customer. 31 Thus, despite the changes to the CGS program, ETI did not
    depart from the cost-recovery approach embodied in the rider it proposed in
    Docket 37744:
    This Competitive Generation Service Unrecovered Service Cost Rider
    (“Rider CGSUSC” or “Rider”) defines the procedure by which
    Entergy Texas, Inc. (“Company”) shall implement and adjust rates for
    recovery of lost base rate revenue resulting from customers
    participating in the Company’s Competitive Generation Service
    (“CGS Program”). The purpose of this Rider is to provide a
    mechanism for recovery of such lost base rate revenues that were
    included in the Company’s last general rate case proceeding before
    the Public Utility Commission of Texas (“PUCT”). 32
    In a nutshell, ETI contended that it was entitled to recover the hypothetical
    revenues (or “embedded generation costs” as ETI uses the term 33) that a CGS
    customer would have paid if it had purchased its electricity from ETI instead of
    from a third party. 34
    Other parties disagreed that ETI was entitled to lost revenues and submitted
    testimony that the revised CGS tariff would cost ETI nothing from a capacity
    31
    AR Binder 2, Docket No. 38951, Item 119, Final Order at 7; AR Binder 3, Docket No. 38951,
    ETI Ex. 91, May Supp. Direct at 5-8.
    32
    Supp. AR, Docket No. 37744, ETI Ex. 9, May Direct at Exhibit PRM-1 at 5 (emphasis added);
    see also AR Binder 5, Transcripts Vol. B, HOM Tr. At 72-73 (Apr. 19, 2012); AR Binder 3,
    Docket No. 38951, ETI Ex. 91, May Supp. Direct at 5-8.
    33
    ETI’s Appellant’s Brief at 8 (stating that the CGSUSC Rider would have recovered embedded
    generation costs that “migrating customers” would have paid but for CGS program).
    34
    Supp. AR, Docket No. 37744, Item 37, PFD at 22-13 and FoFs 14-18; Supp. AR, Docket No.
    37744, Transcripts, Vol. D at 165-166 (Jul. 16, 2010).
    7
    standpoint.35 The testimony submitted by intervenor witnesses was that, under the
    new framework, a CGS supplier would be required to enter into a purchase
    agreement directly with ETI (or on ETI’s behalf) under which the supplier would
    provide firm power to a CGS customer. 36 The CGS supplier’s charges to provide
    the power would be passed directly through to the CGS customer. 37 And ETI’s
    other costs of serving CGS customers, such as costs to provide transmission
    service and back-up power, would be charged to the very CGS customers who
    received those services.38     Thus, in addition to being presented with several
    stipulations regarding the structure of the agreed-to CGS program, 39 the
    Commission heard intervenor testimony that, under this framework, the CGS
    customer would pay ETI for the full cost of all of the service that ETI provides that
    customer, and the CGS customer would pay the CGS supplier for the cost of the
    power that the CGS supplier provides. 40
    Additionally, the stipulations presented to the Commission provided that the
    CGS customers would pay ETI’s incremental cost of implementing and
    35
    See, e.g., AR Binder 3, Docket No. 38951, Cities Ex. 6C, Nalepa Supp. Direct at 7-8; AR
    Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 14-21.
    36
    
    Id. 37 Id.
    38
    
    Id. 39 AR
    Binder 2, Docket No. 38951, Item 119, Final Order at FoF 12-18.
    40
    AR Binder 3, Docket No. 38951, Cities Ex. 6C, Nalepa Supp. Direct at 10; AR Binder 4,
    Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 16.
    8
    administering the CGS program. 41 Although those costs were unknown at the time
    of the hearing, the Commission (with ETI’s agreement) ordered that ETI could
    subsequently file an application to recover them. 42
    After considering the testimony, stipulated facts, agreements, and multiple
    rounds of briefing, the Commission made the following ultimate finding of fact as
    to unrecovered costs associated with the revised CGS program tariff then before it:
    The Commission finds that the costs that will be unrecovered as a
    result of the implementation of the CGS program tariff are the costs to
    implement and administer the CGS program tariff. 43
    The Commission also rejected ETI’s assertion that it was entitled to charge
    other ratepayers for the difference between what a CGS customer paid and what a
    full firm LIPS customer would have paid, 44 which ETI had characterized as “lost
    base rate revenues” in its proposed rider in Docket 37744.45 After this Court
    rejected a similar lost revenues argument in CenterPoint Energy Houston Electric,
    LLC v. Public Utility Commission (“CenterPoint 2011”),46 ETI downplayed the
    “lost revenues” language in its proposal, and instead used the terms “embedded
    41
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 35.
    42
    
    Id. 43 Supp.
    AR, Docket No. 37744, Item 27, SOAH Order No. 12 – Interim Order Approving
    Revised Interim Rates at FoF 40; AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF
    51.
    44
    AR Binder 2, Docket No. 38951, Item 119, Final Order at CoL 2.
    45
    Supp. AR, Docket No. 37744, ETI Ex. 9, May Direct at Exhibit PRM-1 at 5.
    46
    
    354 S.W.3d 899
    (Tex.App.—Austin 2011, no pet.).
    9
    generation costs” or “embedded production costs.” 47 But ETI’s witness made clear
    that they were the same thing. 48 Whatever the lexicon, the Commission rejected
    ETI’s argument that the statutory reference to unrecovered costs meant lost
    revenues. Specifically, the Commission made a conclusion of law that:
    PURA § 39.452(b) does not allow for the recovery of lost revenue or
    embedded generation costs.49
    The Commission’s order cited this Court’s decision in CenterPoint 2011 as
    precedent in support of its determination that PURA § 39.452(b)‘s reference to
    “costs unrecovered” did not mean “lost revenues.” 50
    V.    The Commission rejected ETI’s proposal to surcharge pre-
    implementation CGS regulatory expenses and denied ETI’s request for
    interest on costs of implementing a CGS program.
    ETI also proposed a “CGSC” rider that was to recover the company’s
    incremental development and ongoing CGS program operation costs, under the
    theory that these costs would otherwise be unrecovered as a result of the
    implementation of the CGS tariff. 51 ETI sought to surcharge ratepayers for its
    alleged historical CGS regulatory and litigation expenses dating back to November
    47
    AR Binder 3, Docket No. 38951, ETI Ex. 91, May Supp. Direct at 5-8; See, e.g., ETI’s
    Appellant’s Brief at 8, 15.
    48
    AR Binder 5, Transcripts, Vol. B, HOM Tr. At 72-73.
    49
    AR Binder 2, Docket No. 38951, Item 119, Final Order at CoL 2.
    50
    
    Id. at 7.
    51
    Supp. AR, Docket No. 37744, ETI Ex. 9, May Direct at Exhibit PRM-1 at 3; PURA §
    39.452(b).
    10
    10, 2010—years before any decision of whether there would even be a CGS tariff
    to implement. 52 These costs would have been incurred even if the Commission had
    denied the proposal to implement a CGS program in its July 2013 final order at
    issue in this appeal. The Commission denied ETI’s request and determined that
    the costs of implementing the CGS program tariff would begin if and when a CGS
    program was implemented.53 The Commission also determined that ETI was not
    entitled to interest on any costs of implementing a CGS program. 54
    ETI appealed the Commission’s order in Docket 38951 to district court.55
    Following full briefing and oral argument, the trial court, Judge Meachum
    presiding, affirmed the Commission’s order in all respects. 56 ETI then filed this
    appeal.
    SUMMARY OF ARGUMENT
    PURA § 39.452(b) states that a utility’s rates “shall be set . . . to recover any
    costs unrecovered as a result of the implementation of the tariff.” 57 The evidence
    showed that under the revised CGS tariff approved by the Commission, ETI would
    not incur any costs to serve CGS customers that would be unrecovered, other than
    52
    AR Binder 3, Docket No. 38951, ETI Ex. 103, Roach Supp. Reb. at 2:19-21.
    53
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 51.
    54
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 57.
    55
    CR4-19.
    56
    CR523-26.
    57
    Emphasis added.
    11
    as-yet unquantified implementation and administration costs. The revised program
    required that the CGS supplier, not ETI, would provide firm power to serve the
    CGS customer. Thus, unlike the program initially proposed in Docket 37744, ETI
    would not have any capacity costs associated with CGS customers. ETI would
    indisputably incur costs to provide back-up power, transmission, and other
    ancillary services to CGS customers. However, under the framework approved by
    the Commission, all of these costs would be charged to those CGS customers and
    would thus not be “unrecovered.”
    ETI contends that it has unavoidable fixed production costs, and asserts that
    these should be considered unrecovered costs.58 As an initial matter, ETI did not
    propose to measure and recover any fixed production costs that would somehow be
    unrecovered as a result of the CGS program. It simply sought revenues that it
    would have hypothetically charged if any future CGS customer had chosen to buy
    full firm power from ETI rather than from CGS suppliers. Further, the evidence
    contradicts ETI’s claim.        ETI purchases, rather than self-generates, the vast
    majority of the power it supplies to its retail customers, 59 and it is projecting
    substantial capacity shortfalls in the coming years. 60 ETI also projects steady
    58
    ETI Appellant’s Brief at 15-16.
    59
    Supp. AR, Docket No. 37744, Item 37, PFD at 31.
    60
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 42, 43.
    12
    growth in demand in its service area. 61 And, under the revised CGS framework
    approved by the Commission, the program was capped at 115 MW.                   Taken
    together, these facts mean that the implementation of the CGS program would not
    result in any load loss; it would merely slow ETI’s load growth and thus ameliorate
    ETI’s capacity shortfall.62 In other words, even if one assumes that all future CGS
    customers would have taken full firm power from ETI (rather than, for example,
    self-generating power or locating in another utility’s service territory), the CGS
    program would merely cause ETI to purchase less electricity than it otherwise
    would have.
    The Commission also properly rejected ETI’s position that by “costs
    unrecovered,” the legislature actually meant “lost revenues.” The plain language
    of the statute makes no reference to revenues, and this Court’s decision in
    CenterPoint 2011 confirms that a reference to “costs” in PURA does not mean
    “revenues.”
    ETI attempts to distinguish the CenterPoint 2011 holding by asserting that it
    sought to recover its “embedded production costs.” However, this contention is
    belied by the language of ETI’s proposed rider, in which ETI expressly sought
    recovery of “lost base rate revenues,” not unrecovered costs. It is also belied by
    61
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 22, JP-3 (citing
    Entergy’s Strategic Resource Plan).
    62
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 9.
    13
    the evidence, including testimony from an ETI witness that ETI sought to recover
    all revenues it would have received if a CGS customer that purchased power from
    a third party had instead purchased power under ETI’s full firm rates, even if that
    customer had never purchased power from ETI prior to signing up for the CGS
    program. The hypothetical revenue a new customer might have generated from
    ETI if it had chosen to purchase power from ETI under a firm rate cannot logically
    be considered an unrecovered cost to ETI. It is clear that ETI proposed a lost-
    revenues theory that is foreclosed by PURA and CenterPoint 2011.
    The Commission properly found that ETI will incur costs to implement and
    administer the CGS program, which will not be recovered by the CGS tariff itself.
    Accordingly, the Commission determined that these costs were unrecovered costs
    and provided a mechanism for their recovery. The Commission’s determination
    that these were the only costs that would be unrecovered is supported by the
    evidence, consistent with the plain language of the implementing statute, and
    faithful to this Court’s recent precedent in CenterPoint 2011.
    The Commission’s denial of ETI’s request to surcharge customers for
    regulatory costs incurred from November 2010 to July 2013 as costs of
    implementation should also be upheld. These costs would have been incurred
    regardless of whether the CGS program was ever implemented, and, under the
    14
    statute, ETI may only recover costs that are unrecovered as a result of
    implementation. Further, the record showed that ETI actually sought and was
    recovering pre-implementation costs related to the CGS program through its base
    rates.
    Finally, the Commission properly rejected ETI’s request to recover interest
    on the costs of CGS implementation. Contrary to ETI’s claim that it is statutorily
    entitled to interest, the statute makes no reference to carrying costs, and the
    Commission has long denied interest on similar regulatory expenses.
    ARGUMENT
    I.       The Commission’s finding on ETI’s unrecovered costs is supported by
    substantial evidence and consistent with the CGS statute.
    A.    Standard of Review
    Judicial review of the Commission’s findings of fact concerning
    unrecovered costs is under the substantial evidence rule. 63           The substantial
    evidence standard of review does not allow a court to substitute its judgment for
    that of the agency. 64 The scope of review under the substantial evidence rule is
    limited; the issue for the reviewing court is not whether the agency reached the
    correct conclusion, but whether there is “some reasonable basis in the record for
    63
    PURA § 15.001; Tex. Gov’t Code §§ 2001.174, 2001.175.
    64
    Texas Health Facilities Comm’n v. Charter Med.-Dallas, Inc., 
    665 S.W.2d 446
    , 452 (Tex.
    1984) (citing Gerst v. Guardian Sav. & Loan Ass’n, 
    434 S.W.2d 113
    , 115 (Tex. 1968)).
    15
    the action taken by the agency.” 65 Substantial evidence requires only more than a
    mere scintilla, and “the evidence in the record actually may preponderate against
    the decision of the agency and nonetheless amount to substantial evidence.” 66 A
    court must uphold an agency decision if a reasonable basis exists in the record for
    the decision.67
    ETI also argues that the Commission misconstrued the terms of § 39.452 of
    PURA. A reviewing court gives great weight to the agency’s interpretation of the
    statute it implements and enforces. 68 If a statute is subject to more than one
    interpretation, a court must uphold the agency’s interpretation if it is reasonable
    and in harmony with the statute. 69
    B.     The evidence showed that ETI would not incur any costs to serve
    CGS customers that would be unrecovered, other than
    implementation and administration costs.
    To understand the CGS program, it is helpful to draw an analogy. Consider
    a natural gas utility that provides service to an industrial consumer under a firm
    contract. Prior to deregulation, the gas utility would generally purchase or produce
    65
    See City of El Paso v. Pub. Util. Comm’n, 
    883 S.W.2d 179
    , 185 (Tex. 1994).
    66
    Charter 
    Med.-Dallas, 665 S.W.2d at 452
    (citing Lewis v. Metropolitan Sav. & Loan Ass’n, 
    550 S.W.2d 11
    , 13 (Tex. 1977)).
    67
    See City of El 
    Paso, 883 S.W.2d at 185
    .
    68
    Reliant Energy, Inc. v. Pub. Util. Comm’n, 
    153 S.W.3d 174
    , 187 (Tex. App.—Austin 2004,
    pet. denied).
    69
    R.R. Comm’n v. Texas Citizens for a Safe Future & Clean Water, 
    336 S.W.3d 619
    , 629 (Tex.
    2011).
    16
    the natural gas and then transport it to the customer on the utility-owned pipeline.
    However, if a CGS-style program were introduced, the customer could choose to
    purchase its natural gas from a third party, but it would still pay to have it shipped
    on the utility’s pipeline. Logically, this should result in the utility avoiding the
    costs necessary to either purchase or produce the gas that the customer was no
    longer buying from the utility.          However, if there were some overarching
    requirement that the utility was still responsible for buying natural gas for the
    customer even though the customer was obtaining it elsewhere, the utility might
    argue that it could not avoid its costs to provide gas to the customer. This is
    essentially what ETI argued in connection with the CGS program it initially
    proposed in Docket 37744.
    The key impediment to the CGS program proposed in that docket was the
    insistence by ETI and the Entergy Operating Committee that ETI would still have
    to incur production costs for a CGS customer even though that customer was not
    obtaining its electricity from ETI. 70 Critically, this impediment was resolved under
    the approach the Commission adopted in Docket 39851, because the revised
    program allowed the CGS customer to get its firm power from the CGS supplier
    without cost to ETI. The evidence established that this and other changes to the
    70
    Supp. AR, Docket No. 37744, Item 21, Initial Brief of Entergy Texas, Inc. on Proposed CGS
    at 20.
    17
    CGS program meant that ETI would not incur production costs to serve CGS
    customers.
    TIEC witness Jeffry Pollock 71 testified that, under the revised CGS program,
    the CGS customer would pay ETI for all costs associated with its service. 72 For
    example, even though the CGS customer would use an alternative source for its
    generation supply, it would still use the ETI transmission and distribution system
    to deliver the electricity. For this use, the CGS customer would pay ETI the full
    wires charges that any other electricity user in the ETI area would pay. 73 And,
    since there may be times when the CGS supplier experiences an outage, the CGS
    customer would pay ETI the full cost of back-up power, just as a customer that
    self-generates its own power would pay ETI for back-up power. 74 In short, ETI
    would not incur any production costs to serve the CGS customer that it would not
    recoup. As stated by Cities witness Karl Nalepa, “[t]he current CGS program has
    been designed such that no production costs need go unrecovered.” 75
    71
    Mr. Pollock’s pre-filed testimony on unrecovered costs under the revised CGS program in
    Docket No. 38951 is attached to this brief for the Court’s reference.
    72
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 15.
    73
    
    Id. 74 Id.
    See also AR Binder 2, Docket No. 38951, Item 119, Final Order at 19-20 (describing
    Unserved Energy rate and CGS Fixed Cost Contribution).
    75
    AR Binder 3, Docket No. 38951, Cities Ex. 6C, Nalepa Supp. Direct at 10.
    18
    C.       ETI did not prove that it has unavoidable fixed generation costs
    that would be unrecovered as a result of the CGS program.
    ETI argues in its brief that its costs of generation are fixed and do not change
    with changes in demand. 76 The crux of ETI’s argument is that implementing the
    CGS program will cost ETI money in the form of generation costs that neither the
    CGS customer nor any other customer will pay. 77 As an initial matter, ETI did not
    submit to the Commission a rider that would have measured any such
    “unrecovered” generation costs. The rider ETI submitted sought, by its own terms,
    “lost base rate revenue resulting from customers participating in the [CGS
    program].” 78     Further, the evidence showed that ETI would not have any
    unavoidable fixed production costs that would be unrecovered.
    ETI is a “short” utility—it has relatively little capacity in the form of ETI-
    owned power plants. 79         Accordingly, to satisfy its obligation to serve, ETI
    purchases the vast majority of its capacity in the wholesale market and resells that
    capacity to its retail customers. 80 In addition, ETI purchases capacity each month
    76
    See ETI’s Appellant’s Brief at 8, 15.
    77
    
    Id. 78 Supp.
    AR, Docket No. 37744, ETI Ex. 9, May Direct at Exhibit PRM-1 at 5 (emphasis added).
    79
    Supp. AR, Docket No. 37744, Item 37, PFD at 31.
    80
    See Docket No. 37744, Schedule P-6.1 and Schedule H-12.4a-g. ETI submitted that it had
    $124,341,000 in generated capacity cost and another 186,534,000 (IPCR - Capacity Rider of
    $25,769,780 + Other - Base Rate Costs of $160,764,523) in purchased capacity cost for a total of
    $310,875,000 in capacity costs.
    19
    from its affiliates based on ETI’s actual capacity shortfall in the month. 81 Thus,
    when ETI has additional demand from its customers, it must purchase additional
    power. Conversely, if an existing customer leaves the system or becomes a CGS
    customer, ETI would no longer need to purchase capacity for that customer. And
    if a customer new to ETI’s service area signed up for CGS service, ETI would not
    have to purchase any additional power whatsoever to serve that customer.
    The evidence also showed that ETI was experiencing considerable “load
    growth” (or increased demand for electricity). 82 Based on an assessment of both its
    load requirements and generating capability, ETI projected a capacity shortfall
    going forward.83 In fact, ETI stipulated that it would have a shortfall of 260 MW
    in 2012, which would grow to 506 MW by 2013.84 This evidence was significant
    given that the revised CGS program was limited to a maximum of 115 MW.85
    With the cap, the CGS program—even if fully subscribed—would do no more than
    slow ETI’s projected load growth and reduce ETI’s need to purchase additional
    81
    Supp. AR, Docket No. 37744, Item 37, PFD at 31.
    82
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 22, JP-3 (citing
    Entergy’s Strategic Resource Plan).
    83
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 42, 43.
    84
    
    Id. at FoF
    43.
    85
    
    Id. at FoF
    36.
    20
    capacity. 86 Because a CGS customer would obtain its own electricity supply, ETI
    could use its existing generation resources to serve existing and new non-CGS
    load.87 As Mr. Pollock testified, “ETI has been experiencing substantial load
    growth, and the addition of a CGS Program with a cap would only have the effect
    of slowing the load growth, not reducing ETI’s revenues.” 88
    In sum, the evidence showed that the CGS program, whether comprised of
    new load, existing LIPS customers, or some combination thereof, would do no
    more than to reduce the additional amount of power that ETI would have to
    purchase to serve its system in the future. ETI’s brief suggests that CGS customers
    would somehow get a “free lunch” at ETI’s expense. 89 As demonstrated by the
    foregoing, however, under the program adopted by the Commission, CGS
    customers would buy their lunch from the CGS suppliers and relieve ETI of the
    need to buy lunch on their behalf.
    86
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 21-23. The evidence
    in the underlying proceeding showed that ETI projected load growth of about 2 percent, or 80
    megawatts per year, through 2029.
    87
    
    Id. at 24.
    88
    
    Id. at 9.
    89
    ETI Appellant’s Brief at 19.
    21
    D.     The Commission properly determined that the costs to implement
    and administer the CGS tariff would be unrecovered and
    included this finding in its order.
    The evidence showed that the only costs that would be unrecovered as a
    result of the implementation of the program were implementation and
    administrative costs.90 Intervenor witnesses testified that ETI could recover these
    incremental CGS start-up and implementation costs, 91 and ETI agreed to seek these
    costs in an application in a subsequent proceeding. 92 Mr. Pollock’s testimony
    made clear that there would be no other unrecovered costs:
    Q     Would any unrecovered costs exist after start-up,
    on-going and backup power costs are paid by the CGS
    customer?
    A      No. Recall that, under the CGS Program described
    in the Stipulation, the CGS Customer would effectively
    buy its own capacity and energy from the CGS Supplier.
    With the exception of the capacity credit and fixed fuel
    factor, a CGS Customer will pay ETI a retail rate that
    includes all other charges the customer would pay as a
    firm customer, including a transmission and distribution
    rate and all other applicable tariffs (e.g., Rider TTC,
    HRC, SRC, SCO, AFC and FF charges, if applicable).
    There would be no other unrecovered costs. 93
    90
    AR Binder 2, Docket No. 38951, Item 119, Final Order at 8.
    91
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 15.
    92
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 54A.
    93
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 16.
    22
    ETI had the burden of proving that additional costs beyond those found by
    the Commission would be unrecovered.94 It failed to do so. The Commission’s
    finding that the only costs that would be unrecovered were those to implement and
    administer the tariff is supported by substantial evidence and should be upheld.
    E.     The Commission properly rejected ETI’s attempt to recast the
    statutory term “costs unrecovered” as lost revenues.
    While the Commission made a factual finding on the basis of extensive
    evidence, it also rejected ETI’s proposed interpretation of the statute that would
    equate “costs unrecovered” with the hypothetical lost revenues that a CGS
    customer would have paid had it chosen to purchase electricity under ETI’s LIPS
    rate instead. The Commission’s decision is consistent with the plain language of
    the statute, which provides that the utility’s rates will be set “to recover any costs
    unrecovered as a result of the implementation of the tariff. 95
    1.     The Commission’s interpretation is consistent with the
    plain language of PURA § 39.452(b).
    Common definitions of “cost” are “the amount of money that is needed to
    pay for or buy something” and “expenditure.” 96 As set out above, the Commission
    carefully examined the expenditures that ETI would incur as a result of the
    94
    PURA § 36.006.
    95
    PURA § 39.452(b) (emphasis added).
    96
    Definition of “cost”, Merriamwebster.com, http://www.merriam-webster.com/dictionary/cost
    (last visited Feb. 12, 2015).
    23
    program, but the record showed that ETI would not incur production expense or
    any other types of costs that would not be recovered (other than costs to implement
    and administer). Accordingly, the Commission’s decision is entirely consistent
    with the plain language of PURA § 39.452(b). Further, to the extent there is any
    ambiguity in the statute with respect to whether the statutory term “any costs
    unrecovered as a result of” includes lost revenues, the Commission’s determination
    is reasonable and is therefore entitled to deference. 97
    ETI argues that the framework of § 39.452(b) somehow plainly indicates
    that, because unrecovered costs must be ascertained in the same proceeding in
    which the CGS tariff is approved, these “costs” must be based on the test year used
    to set base rates.98 But ETI fails to point out that there is no requirement that the
    Commission implement the CGS program in a base rate case in which test year
    expenses and revenues are determined. The 2009 amendments to the CGS statute
    removed the requirement that the CGS tariff be set in a rate case. 99 As amended,
    the statute mandates that the Commission consider a CGS tariff by a date certain,
    97
    Texas Citizens for a Safe Future & Clean 
    Water, 336 S.W.3d at 629
    . Notably, the ALJ in
    Docket No. 37744 concluded that this term was vague. Supp. AR, Docket No. 37744, Item 37,
    PFD at 30.
    98
    ETI’s Appellant’s Brief at 17.
    99
    Compare Act of May 24, 2005, 79th Leg., R.S., ch. 1072, § 1, 2005 Tex. Sess. Law Serv. 3559)
    (HB 1567) with PURA § 39.452(b); see also Act of May 30, 2009, 81st Leg., R.S., ch. 1226, § 3,
    2009 Tex. Sess. Law Serv. 3913, 3914 (SB 1492) (codified at PURA § 39.452(i)).
    24
    whether or not ETI filed a rate case. 100 So any notion of a base rate test year is
    absent from § 39.452(b).
    Further, ETI fails to explain how a bare reference to “costs that would be
    unrecovered as a result of implementation of the tariff” correlates to a utility’s test
    year revenue requirement in some imagined rate case. ETI’s attempt to assert
    some statutory link between unrecovered costs and some unidentified rate case test
    year is without merit.
    2.      The Commission’s decision is consistent with the
    CenterPoint 2011 precedent.
    Had the legislature intended that ETI be permitted to charge customers for
    hypothetical lost revenues, it would have so stated. This is the crux of this Court’s
    decision in CenterPoint 2011. In that case, CenterPoint, ETI, and other utilities
    challenged one of the Commission’s energy efficiency rules, 101 which was intended
    to encourage residential and commercial customers to reduce their usage through
    energy efficiency measures.102 ETI and the other utilities argued that they should
    be allowed to charge customers for their lost revenues resulting from energy
    100
    PURA § 39.452(b).
    101
    Centerpoint Energy Houston Electric, LLC v. Pub. Util. Comm’n, 
    354 S.W.3d 899
    (Tex.
    App.—Austin 2011, no pet.).
    102
    Rulemaking Proceeding to Amend Energy Efficiency Rules, Project No. 37623, Order at 1
    (Aug. 9, 2010).
    25
    efficiency measures.103 The Court held, however, that in those rare instances in
    which the legislature intended to allow a utility to charge ratepayers for a loss in
    revenue, it has explicitly provided for recovery of a “loss of revenue” or a
    “decrease in revenue.” 104 The Court therefore upheld the Commission’s order
    denying a lost revenue adjustment mechanism very similar to the one proposed by
    ETI here, explaining:
    The legislature’s failure in PURA section 39.905 to specifically
    provide for recovery of “lost revenues,” in addition to “costs,”
    indicates that it intended for the EECRF [Energy Efficiency Cost
    Recovery Factor] to serve as a mechanism for a utility to recover out-
    of-pocket expenditures associated with its implementation of energy-
    efficiency programs, not to compensate a utility for any associated
    lost revenues attributable to those programs. 105
    As the Court observed, “[i]n at least two other provisions of PURA, the
    legislature expressly distinguishes ‘costs’ from ‘revenues,’ indicating that its use of
    the term ‘costs’ by itself does not encompass lost revenues.” 106 The Court noted
    that “PURA section 55.024(b) provides that a telecommunication utility may
    recover ‘all costs incurred and all loss of revenue’ resulting from imposition of
    charges for providing mandatory two-way extended area service to customers.” 107
    103
    AR Binder 4, Docket No. 38951, TIEC Ex. 24, Amicus Curiae Brief of Entergy Texas, Inc.,
    El Paso Electric Company and Southwestern Electric Power Company at 3.
    104
    CenterPoint 
    2011, 354 S.W.3d at 903-04
    .
    105
    
    Id. at 904.
    106
    
    Id. at 903-04.
    107
    
    Id. at 904
    (emphasis in original).
    26
    Similarly, “in PURA section 56.025(e), the legislature directed the Commission to
    ‘implement a mechanism to replace the reasonably projected increase in costs or
    decrease in revenue’ caused by a governmental agency’s order, rule, or policy.”108
    The Court concluded that, since the legislature expressly provided for recovery of
    lost revenue when that was the intent, the absence of such language in the energy
    efficiency provisions compelled the conclusion that such intent was absent.109
    The Commission reasonably relied on this precedent. The Commission
    found that, like the statutory language regarding energy efficiency cost recovery in
    PURA § 39.905, “PURA § 39.452(b) only provides for ‘costs unrecovered as a
    result of implementation of the tariff’ and does not specifically provide for the
    utility to recover lost revenues or any other types of costs.” 110 The Commission’s
    interpretation of the statute was consistent with the statutory language, reasonably
    based on the evidence, and consistent with the CenterPoint 2011 precedent.
    ETI’s attempts to distinguish the CenterPoint 2011 decision are unavailing.
    ETI first tries to diminish the Third Court’s precedent by distinguishing the energy
    efficiency statute, PURA § 39.905, from PURA § 39.452(b) on the basis that the
    EECRF statute, PURA § 39.905, authorizes “cost recovery for utility expenditures
    108
    
    Id. at 904
    (emphasis in original).
    109
    
    Id. at 903-04.
    110
    AR Binder 2, Docket No. 38951, Item 119, Final Order at 8.
    27
    made to satisfy the goal of this section . . .,” whereas the CGS statute, PURA
    § 39.452(b), requires that “rates shall be set . . . to recover any costs unrecovered as
    a result of the implementation of the tariff.” 111 ETI ignores that the words costs
    and expenditures are synonyms. 112 It also ignores the simple point of the
    CenterPoint 2011 decision: when the legislature has intended to allow recovery for
    lost revenues, it has expressly stated as much.
    Indeed, the arguments that ETI unsuccessfully made in CenterPoint 2011
    bear a striking resemblance to its contentions here. ETI’s chief point in both cases
    was that the legislature created a program that will (i) cause ETI implementation
    costs and (ii) allegedly result in lost revenues because of reduced demand caused
    by the program. In CenterPoint 2011, ETI argued:
    PURA section 39.905 requires electric utilities to incur two kinds of
    costs: the cost of the utilities’ expenditures on energy efficiency
    programs implemented under the statute, and the value of lost revenue
    recovery due to depressed revenues that result from energy efficiency
    measures. 113
    Here, ETI asserts:
    This new “competitive generation service” or “CGS” program costs
    ETI money to develop and administer. It also costs ETI money in that
    the CGS program permits eligible customers to contract for electric
    111
    ETI’s Appellant’s Brief at 22, 23 (emphases added).
    112
    Definition      of        “cost”,     Merriam-Webster.com,    http://www.merriam-
    webster.com/dictionary/cost (last visited Feb. 12, 2015).
    113
    AR Binder 4, Docket No. 38951, TIEC Ex. 24, Amicus Curiae Brief of Entergy Texas, Inc.,
    El Paso Electric Company and Southwestern Electric Power Company at 2.
    28
    generation resources from alternative suppliers, which allows them to
    avoid paying some of ETI’s costs that would otherwise be allocated to
    them under ETI’s base rates. 114
    In both cases, ETI argued that it should not only be entitled to the costs to
    implement and administer the program at issue, but also to the revenues it would
    have received in its absence.         And in both cases, ETI argued that if the
    Commission does not allow it to recover its lost revenues, it will be deprived of the
    opportunity to recover its reasonable and necessary expenses. 115 The only real
    difference between ETI’s approach in the two cases is its choice of nomenclature.
    In CenterPoint 2011, ETI openly referred to its desire to recover “lost
    revenues,” whereas in this case ETI frames the issue as one of “fixed production
    costs,” 116 “embedded generation costs,”117 or “embedded production costs.”118 It is
    abundantly clear, however, that ETI is still referring to lost revenues. The Court
    properly rejected ETI’s claim for lost revenues in CenterPoint 2011, and it should
    do the same here.
    114
    ETI Appellant’s Brief at 6.
    115
    AR Binder 4, Docket No. 38951, TIEC Ex. 24, Amicus Curiae Brief of Entergy Texas, Inc.,
    El Paso Electric Company and Southwestern Electric Power Company at 4; ETI Appellant’s
    Brief at 28.
    116
    ETI Appellant’s Brief at 23.
    117
    
    Id. at 9.
    118
    
    Id. at 15.
                                                29
    3.      ETI sought lost revenues at the Commission, not
    unrecovered costs.
    Relatedly, ETI tries to distinguish the CenterPoint 2011 case with its claim
    that it “indisputably” sought only “costs” here, 119 when in fact that very claim was
    hotly contested and ultimately rejected by the Commission.120                   What ETI
    characterized as costs, were, according to multiple witnesses, simply its lost
    revenues.121 Relying on the PFD from Docket 37744, ETI states that “[n]one of
    the experts in this case disputed that the CGS program could lead to unrecovered
    ‘costs’ of the type claimed by ETI.”122 Notably, ETI’s citation is to testimony
    concerning the program initially proposed by ETI in Docket 37744 under which
    the EOC required ETI to provide capacity for CGS customers even though they
    were buying their electricity elsewhere. 123 Multiple witnesses testified that the
    revised CGS program in Docket 38951—the program that was actually
    approved—would not result in any costs that would be unrecovered as a result of
    the program. 124 Mr. Pollock, for example, testified that under the CGS program
    119
    ETI’s Appellant’s Brief at 24.
    120
    AR Binder 2, Docket No. 38951, Item 119, Final Order at 7-8.
    121
    AR Binder 3, Docket No. 38951, Cities Ex. 6C, Nalepa Supp. Direct at 3, 7-8; AR Binder 4,
    Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 14-15.
    122
    ETI’s Appellant’s Brief at 25 .
    123
    
    Id. at n.
    35.
    124
    AR Binder 3, Docket No. 38951, Cities Ex. 6C, Nalepa Supp. Direct 3, 7-8; AR Binder 4,
    Docket No. 38951, TIEC Ex. 27, Pollock Second Supp. Direct at 14-15.
    30
    adopted by the Commission, “no unrecovered costs would exist that need to be
    allocated to other customers and customer classes.” 125
    Indeed, ETI’s claim that it sought “costs” is based on its post-CenterPoint
    2011 attempt to frame the relief it sought at the Commission as its “embedded
    production costs” rather than its lost revenues. The term “embedded generation
    costs” does not appear anywhere in PURA or the Commission’s Rules. 126 By
    “embedded,” ETI means the “costs” that are contained in its rates. And when ETI
    refers to “embedded generation costs,” it is not referring to costs that it incurs
    because of the CGS program, but instead to the hypothetical revenues it will lose if
    new customers buy CGS power instead of ETI’s power, or if existing customers
    stop buying electricity from ETI. ETI essentially concedes as much in its brief. 127
    That ETI sought lost revenues is also evident from the CGSUSC rider ETI
    proposed in Docket 37744.         As noted, ETI’s stated purpose for its proposed
    CGSUSC rider was to “adjust rates for recovery of lost base rate revenue resulting
    from customers participating in the [CGS progam].” 128 If that were not clear
    enough, ETI’s witness Phillip May testified that ETI considered itself entitled to
    125
    AR Binder 4, Docket No. 38951, TIEC Ex. 15, Pollock Supp. Direct at 8.
    126
    Nor does “embedded production costs.”
    127
    ETI’s Appellant’s Brief at 24-26 (stating, for example: “What would have been billed may
    logically be termed ‘revenues’”).
    128
    Supp. AR, Docket No. 37744, ETI Ex. 9, May Direct at Exhibit PRM-1 at 5.
    31
    lost revenues from CGS sales whether or not the utility had ever incurred
    production costs to serve a CGS customer:
    Q Okay. So your proposal for the CGSUSC Rider is to
    calculate the difference between what would have billed -
    - been billed under traditional LIPS service and the
    amounts collected under the CGS service?
    A That’s a fair characterization.
    Q Okay. So let me get this straight. Under the
    company’s proposal, if a brand-new industrial customer
    came to you that had never received service from ETI
    and they said, "We want to sign up for CGS," ETI would
    still seek to recover lost revenues based on LIPS from
    that customer?
    A Yeah, I believe that is consistent with the
    program . . . . 129
    Mr. May’s testimony lays bare that ETI is attempting to recover revenues
    regardless of whether it has ever incurred any cost to serve or even planned to
    serve a customer. The Commission saw ETI’s use of “embedded generation costs”
    for what it was—an attempt to repackage a lost revenue-theory that is foreclosed
    by the plain language of PURA § 39.452(b) and CenterPoint 2011.
    129
    Supp. AR, Docket No. 37744, Transcripts, Vol. D, HOM Tr. at 165:23-166:11 (Jul. 16, 2010).
    Mr. May confirmed at the Commission’s April 19, 2012 evidentiary hearing that ETI sought the
    same lost-revenues relief in Docket No. 38951 that it sought in Docket No. 37744. Tr. At 72-73;
    see also AR Binder 3, Docket No. 38951, ETI Ex. 91, May Supp. Direct at 5-8.
    32
    4.     The Commission’s rejection of ETI’s lost-revenues
    theory is consistent with the purposes of the CGS statute.
    ETI’s proposal is also inconsistent with the purposes of the CGS program.
    Two of the legislative purposes for the program were to provide the industrial base
    in ETI’s region with some opportunity to shop for more competitive power, and to
    ensure that residential customers were well served. 130 ETI’s proposal that it be
    permitted to recover hypothetical lost revenues detached from any cost it actually
    incurs as result of the CGS program serves neither purpose. As ETI is at pains to
    point out in its brief, if it is entitled to recover these revenues, someone will have
    to pay for them. If it is all customers other than the CGS participants that must
    pay, this will harm the legislative goal that residential consumers be served well.
    If the CGS participants themselves were charged for the very revenues that ETI
    would have collected but for their decision to take CGS service, there would,
    needless to say, be no incentive to sign up.
    As the Commission recognized, ETI’s interpretation of the statute is
    unreasonable and would only serve to torpedo the entire program. For example, at
    the evidentiary hearing on the revised CGS program in Docket 38951, Chairman
    Donna Nelson stated:
    130
    Supp. AR, Docket No. 37744, Item 19, Initial Brief of TIEC, Attachment 1, Transcript of
    Proceedings before the Texas State Senate 81st Legislature, Senate Committee on Business and
    Commerce, at 9-10 (Apr. 14, 2009).           Video of the proceedings can be found at
    http://www.senate.state.tx.us/75r/senate/commit/c510/c510.htm.
    33
    Well, and I guess I would say I’m not going to say this is my final
    conclusion, but I would say it would seem to me that if you follow
    Entergy’s logic in this case, you would end up with an absurd result
    and a program that doesn’t work. So I’m not going to say one way or
    the other because I’m certainly going to review everything, but I can’t
    see how you arrive at any other conclusion. 131
    Chairman Nelson’s concerns with ETI’s lost-revenues proposal were well placed.
    The Commission properly rejected it.
    5.     High Plains is inapposite.
    ETI’s reliance on the High Plains Natural Gas case to justify its position is
    misplaced.132 High Plains Natural Gas, which was decided more than thirty years
    ago, did not fundamentally alter PURA Chapter 36’s ratemaking framework. The
    case does not stand for the proposition that utilities may recover lost revenues or
    costs they do not incur. Rather, in High Plains Natural Gas, the Texas Supreme
    Court examined the issue of whether PURA allowed the Railroad Commission to
    utilize a purchase gas adjustment to compensate for increased fuel costs after a
    base rate case had concluded. Examining a PURA article that stated “[i]n fixing
    the rates of a public utility the regulatory authority shall fix its overall revenues at a
    level which will permit such utility to recover its operating expenses together with
    a reasonable return on its invested capital,” the court held that this “mandates that
    131
    AR Binder 5, Docket No. 38951, Transcripts, Vol. B, HOM Transcript at 207-208 (Apr. 19,
    2012).
    132
    ETI Initial Brief at 18-19 (discussing R.R. Comm’n v. High Plains Natural Gas Co., 
    628 S.W.2d 753
    (Tex. 1981) (per curiam)).
    34
    the Commission structure a system that will permit the utility to recover all of its
    operating expenses.”133 The Public Utility Commission has done this through its
    Chapter 36 ratemaking process, which has been in place for many years.
    F.     Contrary to ETI’s contentions, the Commission’s decision was
    based on a vast evidentiary record, not “solely upon its
    interpretation of the CGS statute”
    ETI argues that “the Commission did not reach the issue of how much of
    ETI’s costs will be unrecovered as a result of implementing the CGS program,
    because the Commission defined the term “unrecovered costs” in a way that
    precludes the issue from arising. This is simply incorrect. It is true that the
    Commission concluded as a matter of law that PURA § 39.452(b)‘s reference to
    “costs unrecovered” does not encompass ETI’s recovery theory because, regardless
    of whether ETI called them “lost base rate revenues” or “embedded production
    costs,” ETI was seeking to charge for lost revenues, not costs. However, the
    Commission also embarked on a factual inquiry into what costs actually would be
    unrecovered. Indeed, before the Commission issued its order regarding ETI’s
    unrecovered costs in Docket 38951, it considered extensive supplemental
    testimony on the revised CGS framework, including testimony regarding the
    definition, existence, and calculation of any costs that would be unrecovered as a
    133
    High Plains Natural Gas, 
    628 S.W.2d 753
    , 753 (construing Tex. Rev. Civ. Stat. Ann. art.
    1446c).
    35
    result of the new proposal. The Commission then held an additional evidentiary
    hearing on the revised program and the issue of unrecovered costs.            The
    commissioners even took the unusual step of conducting this hearing personally
    rather than referring the case to SOAH.
    Having considered the evidence on the new CGS proposal, the Commission
    made detailed findings on its mechanics. 134 As discussed above, the Commission
    also made detailed findings on ETI’s resource position and its projected future
    capacity shortfall.135    These latter findings in particular would be completely
    superfluous if the Commission’s order was based purely on statutory construction.
    Based on all of its subsidiary findings, the Commission made its ultimate finding
    (Finding of Fact 51) that “the costs that will be unrecovered as a result of the
    implementation of the CGS program tariff are the costs to implement and
    administer the CGS program tariff.” 136
    Unable to contest this finding on the evidence, ETI resorts to distraction.
    Specifically, ETI plucks words like “defined,” and “interpretation” out of context
    in an attempt to show that the Commission’s decision was based on the statute
    134
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 32.
    135
    
    Id. at 42-43.
    136
    AR Binder 2, Docket No. 38951, Item 119, Final Order at FoF 51.
    36
    alone.137 Notably, in making this argument, ETI quotes several passages from the
    Commission’s order, but is careful not to quote the operative finding, Finding of
    Fact 51. Further, the passages relied upon by ETI do not prove its point. For
    example, ETI cites a passage in which the Commission used the word
    “interpretation.” However, the cited sentence is explicit that the Commission’s
    decision was “Based on the evidence and testimony.” 138 How this sentence could
    possibly indicate that the Commission based its decision purely on statutory
    construction is a mystery.
    ETI’s contention that the Commission defined unrecovered costs in a
    manner that would categorically exclude the recovery of its production costs is also
    belied by the order. The Commission never stated that ETI’s only costs eligible for
    consideration under the statute are CGS implementation and administration costs.
    It determined that these were the only costs that actually would be unrecovered.
    Indeed, there is no dispute that ETI will incur production costs to provide back-up
    power to a CGS customer. However, the parties stipulated that the CGS customer
    would pay for that power under the program, which stipulation the Commission
    expressly noted in its finding of facts.139 If there were no provision for ETI
    recovering its back-up power production costs, the Commission would have
    137
    ETI Appellant’s Brief at 29.
    138
    AR Binder 2, Docket No. 38951, Item 119, Final Order at 8.
    139
    
    Id. at FoF
    41E&F.
    37
    properly found that they were unrecovered costs under the statute. But this was
    simply not the case with the program the Commission evaluated.
    Agency orders are construed as a whole to ascertain the intent of the
    administrative body. 140 As the Texas Supreme Court has put it, “[t]here is no
    precise form for an agency’s articulation of underlying facts, and courts will not
    subject an agency’s order to some “hypertechnical standard of review.” 141 In this
    case, the order makes clear that the Commission made a factual finding as to what
    actual costs would be unrecovered.          That finding is supported by substantial
    evidence and should be upheld.
    II.    The Commission properly rejected ETI’s request to surcharge legal and
    regulatory costs incurred from 2010 to 2013 as costs of implementation.
    ETI’s argument in its second issue is that the Commission is required to
    adopt a special rider for costs related to the CGS program that were incurred prior
    to any determination that there would even be a CGS program. ETI’s argument
    fails for two principal reasons.
    First, the costs of which ETI complains would have been incurred whether
    or not a CGS tariff was implemented. Had the Commission decided to reject a
    140
    Office of Pub. Util. Counsel v. Texas-New Mexico Power Co., 
    344 S.W.3d 446
    , 450-51 (Tex.
    App.—Austin 2011, pet. denied) (citations omitted).
    141
    State Banking Bd. v. Allied Bank Marble Falls, 
    748 S.W.2d 447
    , 449 (Tex. 1988).
    38
    CGS tariff, as many parties repeatedly invited it to do, 142 there would have been no
    implementation of a CGS tariff whatsoever, and accordingly, there could have
    been no costs unrecovered as a result of the implementation of the tariff.143 Any
    costs incurred in the regulatory process leading up to a decision of whether to
    implement a tariff are subject to the Commission’s standard ratemaking
    procedures.
    Costs prior to the Commission’s decision to implement a tariff were not
    caused by the “implementation of the tariff,” they were caused by the statutory
    mandate to delay competition and for ETI to propose a competitive generation
    tariff, which the Commission was authorized to implement or not. They are among
    the many regulatory costs that utilities incur to comply with statutory mandates,
    and they would have been incurred whether or not a CGS tariff was actually
    implemented by the Commission. The Commission’s decision that costs incurred
    before any decision to implement a CGS tariff cannot be deemed to be “as a result
    of the implementation of the tariff” within the meaning of PURA § 39.45(b) was
    correct.
    Second, the record before the Commission showed that ETI had actually
    sought and was recovering pre-implementation costs related to the CGS program
    142
    Supp. AR, Docket No. 37744, State Ex. 2, Pevoto Direct at 38; Supp. AR, Docket No. 37744,
    Cities Ex. 6, Nalepa Direct at 60; AR Binder 4, Docket No. 38951, Kroger Ex. 2, Townsend
    Direct at 7.
    143
    PURA § 39.452(b) (emphasis added).
    39
    through its base rates. At the time of the final hearing in Docket 38951, ETI had
    already been allowed to include $310,746 per year in CGS-related costs in its base
    rates. 144 The record in this case does not reflect how long those base rates have
    been in effect, how much ETI has recovered in CGS-related regulatory costs
    through those base rates, or how much of CGS-related costs continue to be
    included in base rates. Accordingly, there is no evidence in the record to indicate
    whether ETI has over-collected or under-collected its actual pre-implementation
    CGS-related costs.
    In any case, there is no basis for requiring the Commission to ensure that the
    previously approved base rates recovered exactly the amount of ETI’s pre-
    implementation CGS costs. It is fundamental to ratemaking that the level of the
    utility’s actual costs are constantly changing. Indeed, before the ink is dry on a
    final order, a utility will be experiencing higher costs in some categories and lower
    costs in other categories. Nothing in PURA requires the PUC to allow ETI to take
    one shot at recovering pre-implementation CGS costs through base rates and
    another shot through a special CGS rider.
    144
    AR Binder 3, Docket No. 38951, ETI Ex. 103, Roach Supp. Rebuttal at 3 n.2 (recognizing
    that ETI’s current retail base rates include $299,372 in costs related to the CGS program for
    Total Retail, $11,374 for Wholesale, for a Total Company amount of $ 310,746).
    40
    ETI’s reliance on CenterPoint Energy Houston Electric, LLC v. Public
    Utility Commission (“CenterPoint 2013”) 145 is also misplaced. In CenterPoint
    2013, the Third Court of Appeals held that the Commission misapplied an energy
    efficiency rule by excluding from the calculation of a utility’s performance bonus a
    portion of the money that the utility had spent administering energy efficiency
    programs. 146 The Commission did not award CenterPoint the full amount of the
    performance bonus it had sought, arguing that because a portion of the money
    spent on the programs had been spent under a settlement agreement, and not
    specifically pursuant to the Commission’s rule, that portion was not considered
    eligible for the bonus program outlined in the rule.147         Importantly, it was
    undisputed that the utility had administered various energy efficiency programs for
    which it had actually incurred costs.148 The appellate court held that because
    CenterPoint had spent money on energy efficiency programs that surpassed their
    goal of consumption reduction, the costs that CenterPoint had actually incurred
    should be considered when calculating the utility’s bonus.149
    CenterPoint 2013 is inapposite because, unlike ETI, CenterPoint did not
    seek to recover the money it spent prior to implementing the energy efficiency
    145
    
    408 S.W.3d 910
    (Tex. App.—Austin 2013, pet. denied).
    146
    CenterPoint 
    2013, 408 S.W.3d at 922
    .
    147
    
    Id. at 917.
    148
    
    Id. at 918.
    149
    
    Id. at 921.
                                                41
    programs. Rather, the utility sought to include the costs that it had actually incurred
    to administer its energy efficiency programs in the calculation of its performance
    bonus.         These costs related to the actual administration of energy efficiency
    programs, whereas the costs that ETI seeks to recover here do not relate to
    administration of a CGS program, but rather to regulatory proceedings that were
    required whether or not a CGS program would be implemented.                         The
    Commission’s decision to deny a surcharge for ETI’s pre-implementation costs
    should be affirmed.
    III.      The Commission properly rejected ETI’s request for interest on CGSC
    rider costs.
    ETI can point to no statutory requirement that the Commission allow interest
    on the costs of CGS implementation, and utilities are not typically entitled to
    interest on expenses. The Commission’s decision should be upheld.
    A.       When the legislature intends to award carrying costs, it says so.
    ETI argues that it is entitled to recover its interest on implementation costs
    because it believes PURA § 39.452(b) gives it a right to recover “all costs”
    associated with the program, including interest. 150 ETI overstates what it claims to
    be its CGS entitlement. 151 Notably, where PURA has mandated carrying costs, it
    has specifically stated. There are provisions that expressly provide for recovery of
    150
    ETI’s Appellant’s Brief at 34.
    151
    See 
    id. at 36
    (“ETI is statutorily entitled to recover . . . interest.”).
    42
    carrying costs in PURA, but PURA § 39.452(b) is not one of them. For example,
    PURA § 36.402(b) provides that system restoration costs for a hurricane “shall
    include carrying costs at the utility’s weighted average cost of capital.” PURA
    § 39.4525(d), which authorizes special hiring assistance for federal proceedings,
    provides: “the commission shall allow the electric utility to recover both the total
    costs the electric utility paid under Subsection (c) and the carrying charges for
    those costs through a rider established annually to recover the costs paid and
    carrying charges incurred during the preceding calendar year.” PURA § 39.454,
    which authorizes recovery for ETI’s transition to competition charges, provides
    that “[a] rate rider implemented to recover approved transition to competition costs
    shall provide for recovery of those costs over a period not to exceed 15 years, with
    appropriate carrying costs.”       PURA § 39.459, which relates to hurricane
    reconstruction costs, provides: “[i]f the commission determines it to be
    appropriate, hurricane reconstruction costs may include carrying costs from the
    date on which the hurricane reconstruction costs were incurred until the date that
    transition bonds are issued.” PURA § 36.061, which authorizes bill payment
    assistance costs for military veterans, provides that the electric utility is entitled to
    “apply carrying charges at the utility’s weighted average cost of capital to the
    extent related to the bill payment assistance program.” The legislature knows how
    43
    to specify the recovery of interest on program costs, and it chose not to do so with
    the CGS program.
    These provisions in PURA indicate that the legislature did not intend for the
    recovery of carrying costs on CGS costs; otherwise, the CGS statute would include
    an explicit provision allowing it. A cardinal principle of statutory construction is
    that if items are listed specifically, items not mentioned are excluded, unless
    otherwise stated.152 Similarly, if a term such as “carrying costs” is specified in one
    section of a statute (PURA §§ 36.402(b), 36.061(c)(3), 39.4525(d), 39.454, and
    39.459(b)), but omitted in another section, it is presumed that the legislature did
    not intend to include it in the latter section. 153      Applying these principles of
    statutory construction, it is clear that the legislature did not require interest on CGS
    costs.
    B.    The Commission has not allowed interest to be recovered on
    similar expenses.
    In reaching its determination that there was no need for interest on CGSC
    rider costs, the Commission analogized these costs to rate case expenses. The
    Commission does not allow interest to accrue on the unamortized balance of rate
    152
    Laidlaw Waste Sys., Inc. v. City of Wilmer, 
    904 S.W.2d 656
    , 659 (Tex. 1995).
    153
    
    Id. (“When the
    Legislature employs a term in one section of a statute and excludes it in
    another section, the term should not be implied where excluded.”).
    44
    case expenses. 154 The Commission has a precedent of disallowing the recovery of
    interest in such instances. 155 For example, in Docket 30706, CenterPoint Energy
    sought to recover its rate case expenses over three years with a return on the unpaid
    balance. The Commission rejected CenterPoint’s request for interest, explicitly
    noting its “practice of not permitting utilities to receive interest on unpaid rate-case
    expenses.”156
    Not allowing interest on CGS implementation costs is consistent with the
    treatment of rate case expenses, which are typically amortized over a three-year
    period without a return on the unamortized balance.157 ETI cites no Commission
    precedent allowing a return on the unamortized amount of rate-case expenses.
    There is ample and longstanding Commission precedent, however, that denies the
    154
    AR Binder 2, Docket No. 38951, Item 119, Final Order at 10. Utilities and municipalities are
    reimbursed for legal expenses incurred during rate cases. PURA §§ 36.061(b)(2), 33.023.
    155
    Application of Reliant Energy HL&P for Approval of Unbundled Cost of Service Rate
    Pursuant to PURA § 39.201 and Public Utility Commission Substantive Rule 25.344, Docket
    22355, Order at FoF 98G (Oct. 4, 2001) (“The Commission finds that Reliant should not earn a
    return on the outstanding balance of its rate case expenses.”). See also Petition of Texas Electric
    Service Co. for Authority to Change Rates, Docket 2606, 5 P.U.C. BULL. 109 (Oct. 16, 1979)
    (finding that in amortizing legal expenses arising from previous Commission investigation and
    prior rate case, Commission refused to include requested carrying charge in utility’s cost of
    service as an allowance for the time value of money); Complaint of the City of McKinney
    Against Southwestern Bell Telephone Company, Docket 11027, Final Order at CoL 9 (May 17,
    1995) (noting that nothing “in PURA authorizes McKinney to recover interest on its rate case
    expenses.”).
    156
    Application of CenterPoint Energy Houston Electric, LLC for a Competition Transition
    Charge, Docket 30706, Order at 32 (Jul. 14, 2005).
    157
    AR Binder 4, Docket No. 38951, TIEC Ex. 27, Pollock Second Supp. Direct at 27.
    45
    recovery of interest on these types of costs. 158 Further, this Court has affirmed the
    Railroad Commission’s refusal under PURA to allow a utility to recover interest
    on its rate-case expenses.159
    Lastly, ETI mistakenly relies on CenterPoint Energy, Inc. v. Public Utility
    Commission (“CenterPoint 2004”).160 That case dealt with the unique situation of
    the calculation of stranded costs for utilities that were subject to deregulation. ETI
    continues to be subject to traditional cost-of-service regulation.              Nothing in
    CenterPoint 2004 suggests that the Commission’s longstanding practice of not
    allowing interest on expenses is unlawful.
    Contrary to ETI’s assertion, utilities have no general right to charge interest
    on expenses. The Commission’s denial of interest is consistent with PURA and
    should be upheld.
    PRAYER
    For all the foregoing reasons, TIEC prays that the Court affirm the district
    court’s judgment in all respects and grant TIEC all other such relief to which it
    may show itself justly entitled.
    158
    Application of Reliant Energy HL&P for Approval of Unbundled Cost of Service Rate
    Pursuant to PURA § 39.201 and Public Utility Commission Substantive Rule 25.344, Docket
    22355, Order at 61 n.130 (Oct. 4, 2001).
    159
    Moran Util. Co. v. R.R. Comm’n, 
    697 S.W.2d 447
    , 452 (Tex. App.—Austin 1985, pet.
    granted) (aff’d in relevant part, rev’d in part, 
    728 S.W.2d 764
    (Tex. 1987)).
    160
    ETI Appellant’s Brief at 35-36 (citing CenterPoint Energy, Inc. v. Pub. Util. Comm’n, 
    143 S.W.3d 81
    , 83 (Tex. 2004)).
    46
    Respectfully submitted,
    /s/ Rex D. VanMiddlesworth
    Rex D. VanMiddlesworth
    State Bar No. 20449400
    Benjamin Hallmark
    State Bar No. 24069865
    THOMPSON & KNIGHT LLP
    98 San Jacinto Blvd., Suite 1900
    Austin, TX 78701
    Telephone: (512) 469-6100
    Facsimile: (512) 469-6180
    ATTORNEYS FOR APPELLEE TEXAS
    INDUSTRIAL ENERGY CONSUMERS
    CERTIFICATE OF COMPLIANCE
    I certify that this document contains 11,437 words in the portions of the
    document that are subject to the word limits of Texas Rule of Appellate Procedure
    9.4(i), including the Glossary of Abbreviations, as measured by the undersigned’s
    word-processing software.
    /s/ Benjamin Hallmark
    47
    CERTIFICATE OF SERVICE
    As required by Texas Rule of Appellate Procedure 9.5, I certify that on the
    13th day of February, 2015, the foregoing document was electronically filed with
    the Clerk of the Court using the electronic case filing system of the Court, and that
    a true and correct copy was served on the following lead counsel for all parties
    listed below via electronic service:
    Counsel for Entergy Texas, Inc.               David C. Duggins
    John F. Williams
    Marnie A. McCormick
    Duggins Wren Mann & Romero, LLP
    600 Congress Ave., Ste. 1900
    Austin, Texas 78701
    Counsel for the Public Utility Commission     Elizabeth R. B. Sterling
    of Texas                                      Megan M. Neal
    Environmental Protection Division
    Office of the Attorney General
    P.O. Box 12548
    Austin, Texas 78711-2548
    Counsel for Office of Public Utility          Sara J. Ferris
    Counsel                                       Office of Public Utility Counsel
    1701 N. Congress Ave., Ste. 9-180
    P.O. Box 12397
    Austin, Texas 78711-2397
    /s/ Benjamin Hallmark
    48
    APPENDIX
    D. 38951 – Excerpt from Supplemental Direct Testimony
    and Exhibits of Jeffry Pollock
    49
    PUC DOCKET NO. 38951
    §
    APPLICATION OF ENTERGY              §
    TEXAS, INC. FOR APPROVAL OF         §           PUBLIC UTILITY
    COMPETITIVE GENERATION              §
    SERVICE TARIFF (ISSUES              §        COMMISSION OF TEXAS
    SEVERED FROM DOCKET NO.             §
    ~
    37744)
    Supplemental Direct Testimony and Exhibits
    of
    JEFFRY POLLOCK
    On Behalf of
    Texas Industrial Energy Consumers                 ..,...., (
    ...,
    N
    !"1"1   ~TJ
    c·-                          CD      i   '11
    C)
    X~-
    ..:.-). ··'
    (")-<:
    0       rrt
    t("}                         -o      <
    rtft··--.                   :X      rn
    ;,:() .'``:
    ::X __\..
    :r-
    (/l
    N ..
    .&:"
    0
    {./)
    0
    ....-........
    February, 2012
    }.POLLOCK
    1
    Jeffry Pollock
    Supplemental Direct
    Page 14
    3. UNRECOVERED COSTS FROM THE CGS PROGRAM
    1    Q        WHY IS THE ISSUE OF THE DEFINITION OF "UNRECOVERED COSTS" BEING
    2             ADDRESSED IN THIS PROCEEDING?
    3    A         PURA § 39.452(b) provides that Ell's rates "shall be set, in the proceeding in which
    4              the tariff is adopted, to recover any costs unrecovered as a result of the
    5             implementation of the tariff." ETI and TIEC do not agree about what "costs" this
    6             refers to. Just as ETI and other utilities unsuccessfully argued with respect to energy
    7             efficiency program costs, ETI claims the reference to "costs" would allow it to recover
    8             not just its actual expenditures in implementing a CGS Program but also hypothetical
    9             lost revenues ETI may have received if all CGS Customers paid Ell's full firm rate
    10             instead. ETI's proposed Rider CGSUSC clearly states that it "defines the procedure
    11             by which Entergy Texas, Inc. ('Company') shall implement and adjust rates for
    12             recovery of lost base rate revenue resulting from customers participating in the
    13             Company's Competitive Generation Service ('CGS Program')." 1 (emphasis added)
    14   Definition of Unrecovered Costs
    15   Q         HOW SHOULD UNRECOVERED COSTS BE DEFINED?
    16   A         Unrecovered costs should not include ETI's hypothetical lost revenues. If a CGS
    17             tariff is adopted, the costs that could be unrecovered as a result of implementation of
    18             the tariff should include the expenditures actually incurred by ETI to implement and
    1
    Docket No. 37744, ETI Ex. 9 at Exhibit PRM-1.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    15
    Jeffry Pollock
    Supplemental Direct
    Page 15
    1              maintain a CGS Program, as well as the cost of providing backup power to CGS
    2              Customers. All of those costs should be fully paid by the CGS Customers.
    3    Q         WHAT EXPENDITURES WOULD ETI INCUR TO IMPLEMENT AND MAINTAIN
    4              THE CGS PROGRAM ONCE THE PROGRAM IS ADOPTED?
    5    A         ETI witness, Mr. Phillip R. May, has stated that ETI will incur both start-up and on-
    6              going costs associated with the CGS Program. This will include costs related to
    7              incremental implementation and ongoing operating costs incurred to support the
    8              CGS Program. 2 According to Mr. May:
    9                     ETI must modify its Customer Information System ("CIS") and Large
    10                     Power Billing Systems ("LPBS") within its Major Account Billing
    11                     function to support the CGS Program as it is currently designed.
    12                     In addition to the initial implementation costs explained above, the
    13                     CGSC Rider will also recover incremental on-going costs incurred to
    14                     support the CGS Program. These incremental costs are primarily
    15                     focused around the Major Accounts Billing and its systems support. 3
    16   Q         HOW SHOULD THESE COSTS BE RECOVERED?
    17   A         As I discussed in my testimony in Docket No. 37744, these costs should be
    18             recovered from CGS Customers based on a fixed monthly charge. ETI's program
    19             development and ongoing costs will depend on the scope of the program that is
    20             ultimately approved.
    21   Q         WHAT COSTS WILL ETI INCUR TO PROVIDE BACKUP POWER?
    22   A         ETI will provide generation services when a CGS Supplier cannot provide the CGS
    23             Contract Capacity in any given hour (provided that the CGS Customer has not
    2
    Docket No. 37744, Direct Testimony of Phillip R. May at 14.
    3
    /dat 19.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    16
    ----------------------------------------------------                                                           --
    Jeffry Pollock
    Supplemental Direct
    Page 16
    1           simultaneously curtailed its CGS load). Thus, ETI will incur additional fuel and other
    2          variable costs as well capacity costs to stand ready to provide backup service.
    3    Q      HOW WILL THE COSTS OF BACKUP POWER BE RECOVERED?
    4    A      The costs of backup power will be paid for by CGS Customers through the Unserved
    5           Energy Rate and a Fixed Cost Contribution Fee referenced in the Stipulation.
    6          Unserved Energy will be priced at 105% of avoided energy cost plus an O&M Adder.
    7           This is similar to how ETI currently prices backup power in Schedule SMS. 4         In
    8          addition, the CGS Customer will be required to pay a Fixed Cost Contribution Fee of
    9          $1.10 per kW-Month of CGS Contract Capacity.          The Unserved Energy pricing
    10          mechanism ensures that CGS Customers pay all of the incremental variable costs
    11          associated with back-up power plus a contribution to generation fixed costs.
    12   Q      WOULD ANY UNRECOVERED COSTS EXIST AFTER START-UP, ON-GOING
    13          AND BACKUP POWER COSTS ARE PAID BY THE CGS CUSTOMER?
    14   A      No.   Recall that, under the CGS Program described in the Stipulation, the CGS
    15          Customer would effectively buy its own capacity and energy from the CGS Supplier.
    16          With the exception of the capacity credit and fixed fuel factor, a CGS Customer will
    17          pay ETI a retail rate that includes all other charges the customer would pay as a firm
    18          customer, including a transmission and distribution rate and all other applicable
    19          tariffs (e.g., Rider TTC, HRC, SRC, SCO, AFC and FF charges, if applicable). There
    20          would be no other unrecovered costs.
    4
    The same O&M Adder is also used in Schedule SMS. In addition, Schedule SMS customers pay for
    energy at 100% of avoided cost rather than 105%.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    17
    Jeffry Pollock
    Supplemental Direct
    Page 17
    1    Hypothetical Lost Revenues Are Not Unrecovered Costs
    2    Q        WHAT IS ETI'S DEFINITION OF UNRECOVERED COSTS?
    3    A        In addition to start-up, on-going, and backup power costs, ETI defines its
    4             unrecovered costs as lost base rate revenue from CGS Customers. As described in
    5              its proposed Rider CGSUSC tariff in Docket No. 37744, the purpose of its Rider
    6              CGSUSC is as follows:
    7                    This Competitive Generation Service Unrecovered Service Cost
    8                    Rider ("Rider CGSUSC" or "Rider") defines the procedure by
    9                    which Entergy Texas, Inc. ("Company") shall implement and adjust
    10                    rates for recovery of lost base rate revenue resulting from
    11                    customers participating in the Company's Competitive Generation
    12                    Service ("CGS Program"). The purpose of this Rider is to provide
    13                    a mechanism for recovery of such lost base rate revenues that
    14                    were included in the Company's last general rate case proceeding
    15                    before the Public Utility Commission of Texas ("PUCT").
    16                    (emphasis added)5
    17             Thus, ETI asserts that lost revenues and unrecovered costs are the same.
    18   Q         HOW DOES ETI CALCULATE UNRECOVERED COSTS FROM LOST BASE
    19             RATE REVENUES?
    20   A         ETI is proposing to calculate unrecovered costs based on the revenues associated
    21             with the generation cost components reflected in the ETI firm rate that would
    22             otherwise apply to the CGS Customer. Lost revenues are the product of generation-
    23             related charges (e.g., $6.84 per kW-Month for the current LIPS rate based on the
    24             rates established in Docket No. 37744) and the amount of CGS load, less certain
    25             offsets.
    5
    Docket No. 37744, ETI Ex. 9 at Exhibit PRM-1.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    18
    Jeffry Pollock
    Supplemental Direct
    Page 18
    1   Q   WHAT ARE THOSE OFFSETS?
    2    A   ETI proposes to reduce lost revenues to reflect the following off-setting revenue
    3        contributions/cost reductions:
    4              1. The Fixed Cost Contribution Fee of $1.10 per kW-Month;
    5             2. Revenues from the Variable O&M Adder when Unserved Energy is
    6                 provided; and
    7             3. A reduction in Schedule MSS-1 payments to the other Entergy
    8                operating companies as a result of treating CGS as firm capacity,
    9                which ETI calculates as $3.10 per kW-Month.
    10       These offsets are shown in ETI's Exhibit PRM-4. ETI calculates net unrecovered
    11       costs at current rates of $2.64 kW-Month, less whatever offset would result from the
    12       O&M Adder.
    13   Q   ARE LOST REVENUES AND COSTS THE SAME THING?
    14   A   No.     Costs are ETI's actual expenditures to serve a CGS Customer, not its
    15       anticipated revenues from hypothetical lost sales to customers.
    16   Q   ARE YOU FAMILIAR WITH ANY COMMISSION PRECEDENT REGARDING THE
    17       ISSUE OF WHETHER A UTILITY'S COSTS MAY INCLUDE LOST REVENUES?
    18   A   Yes. I am aware that the Commission in Project No. 37623 and Docket No. 38213
    19       rejected a lost revenues approach to determining costs associated with energy
    20       efficiency programs and that the Commission's decision has been upheld by the
    21       courts, most recently in a 2011 Court of Appeals decision.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    19
    Jeffry Pollock
    Supplemental Direct
    Page 19
    1    Q     DID THE COURT OF APPEALS DISCUSS THE DISTINCTION BETWEEN
    2          "COSTS" AND "LOST REVENUES"?
    3    A     Yes. The court specifically found that the term "costs" in PURA is not intended to
    4          include lost revenues, stating as follows:
    5                            In at least two other provisions of PURA, the legislature
    6                  expressly distinguishes "costs" from "revenues," indicating that its use
    7                  of the term "costs" by itself does not encompass lost revenues. For
    8                  example, PURA section 55.042(b) provides that a telecommunications
    9                  utility may recover "all costs incurred and all loss of revenue" resulting
    10                  from imposition of charges for providing mandatory two-way extended
    11                  area service to customers. See Tex. Util. Code Ann. § 55.042(b)
    12                  (West 2007) (emphasis added). In PURA section 56.025(e), the
    13                  legislature directed the Commission to "implement a mechanism to
    14                  replace the reasonably projected increase in costs or decrease in
    15                  revenue" caused by a governmental agency's order, rule, or policy.
    16                  See 
    id. § 56.025(e)
    (West 2007) (emphasis added).                  These
    17                  provisions further support our conclusion that the term "costs,"
    18                  as used by the legislature in PURA, is not intended to include
    19                  lost revenues. The legislature's failure in PURA section 39.905 to
    20                  specifically provide for recovery of "lost revenues," in addition to
    21                  "costs," indicates that it intended for EECRF to serve as a mechanism
    22                  for a utility to recovery out-of-pocket expenditures associated with its
    23                  implementation of energy-efficiency programs, not to compensate a
    24                  utility for any associated lost revenues attributable to those programs.
    6
    25                    (emphasis added)
    26   Q      ARE THERE ANY POLICY REASONS TO ALLOW ETI TO RECOVER LOST
    27          REVENUES THAT IT ATTRIBUTES TO THE CGS PROGRAM?
    28   A      No. As previously discussed, the CGS Program would allow a retail customer to
    29          replace ETI generation service with electricity provided from a QF in Ell's service
    30          area.   This is no different than a customer that chooses to install generation or
    31          energy efficiency to displace the service that would otherwise be provided by ETI.
    6
    CenterPoint Energy Houston Elec., LLC v. Public Utility Com'n, 
    354 S.W.3d 899
    (Tex.App.-
    Austin, 2011).
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    20
    -------------------------------``-
    Jeffry Pollock
    Supplemental Direct
    Page 20
    1    Q        IS ETI ALLOWED TO RECOVER LOST REVENUES FROM A CUSTOMER THAT
    2             INSTALLS EITHER SELF-GENERATION OR ENERGY EFFICIENCY?
    3    A         No. Given that there is no difference between CGS, installing self-generation, and
    4             energy-efficiency in terms of its impact on the regulated utility, it would not be good
    5              public policy to treat the CGS Program differently from either self-generation or
    6              energy efficiency. The utility should not be allowed to recover more than the actual
    7              costs of providing the service associated with a particular program.
    8   Q         ARE THERE OTHER POLICY REASONS TO REJECT ETI'S LOST REVENUE
    9             APPROACH?
    10   A         Yes. ETI's lost revenue approach assumes that it would have provided generation
    11             services to all loads that opt to participate in the CGS Program. 7 This is not a valid
    12             assumption. For example:
    13                 •   An existing self-generation customer could choose to replace its
    14                     existing generation with CGS power because CGS power is more
    15                     economical than generation services purchased from ETI;
    16                 •   A customer could restart an idled facility because the CGS Program
    17                     makes the restart economically viable;
    18                 •   An existing ETI customer could decide to add facilities, or;
    19                 •   A new customer could locate in ETI's service area because electricity
    20                     is less expensive under the CGS Program than under ETI's other
    21                     ~ri~.
    22             In each of these scenarios, the customer would not have purchased generation
    23             services from ETI under a firm rate.       ETI clearly cannot claim that it lost any
    24             revenues as a result of the CGS Program in these instances.            In fact, ETI would
    7
    ETI's Response to TIEC 1-9.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    21
    Jeffry Pollock
    Supplemental Direct
    Page 21
    1         enjoy higher revenues.         Yet, all of these scenarios would be counted in ETI's
    2         definition of lost revenues.
    3    There are No Lost Revenues
    4    Q    IF THE COMMISSION ADOPTS ETI'S LOST REVENUES APPROACH TO
    5         CALCULATING COSTS, WOULD ETI EXPERIENCE ANY UNRECOVERED
    6         COSTS AS A RESULT OF THE IMPLEMENTATION OF THE PROGRAM?
    7    A    No.
    8   Q    PLEASE EXPLAIN.
    9   A    ETI's lost revenues approach is flawed because it has failed to recognize the impact
    10        of its increased revenues from load growth.        With the proposed cap, the CGS
    11         Program would at most have the effect of slowing ETI's load growth, not reducing its
    12         load. As load grows, each additional kW and kWh sold will provide a contribution to
    13         all fixed costs, including embedded generation capacity costs.     Any reduction in
    14         embedded generation cost recovery that may be attributable to the CGS Program
    15         may be more than offset by the increased revenues resulting from load growth.
    16         Stated differently, as long as ETI continues to collect the same amount of revenue or
    17         more as its embedded generation costs established for a test-year, it cannot claim
    18         that any costs are unrecovered, irrespective of how it defines unrecovered costs.
    19         Instead, those costs are simply being recovered from new customers or through
    20         growth in the demand of existing customers.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    22
    Jeffry Pollock
    Supplemental Direct
    Page 22
    1    Q   CAN YOU PLEASE PROVIDE AN EXAMPLE OF HOW LOAD GROWTH WOULD
    2        OFFSET Ell'S LOST REVENUES FROM A CUSTOMER THAT GOES ON THE
    3        CGS PROGRAM?
    4    A   Yes. Assume a hypothetical utility's base rates are set based on test year sales of
    5        1,000 MW. Then assume in a subsequent year the utility has 1,000 MW of firm load
    6        plus 100 MW of load associated with a CGS Customer that provides its own
    7        generation.   In this simplified example, the utility has clearly experienced no
    8       unrecovered capacity costs associated with the 100 MW CGS Customer. It is still
    9       responsible for providing capacity for 1000 MW of firm load, and it receives revenues
    10       from 1,000 MW of firm load.
    11   Q   IS ETI CONTINUING TO EXPERIENCE LOAD GROWTH?
    12   A   Yes. Exhibit JP-2 quantifies the growth in sales experienced by ETI since its last
    13       rate case. As can be seen, ETI is serving 10,515 (2.6%) more customers, selling
    14       887 million (5.9%) more kWh, and the billing demand for the demand metered
    15       classes has increased by 1. 7 million kW (7 .2%) since the last rate case.
    16   Q   IS ETI PROJECTING LOAD GROWTH OVER ITS PLANNING HORIZON?
    17   A   Yes.   Exhibit JP-3 is an excerpt from Entergy's Strategic Resource Plan (SRP)
    18       Refresh. It shows the projected long-term load growth for each operating company,
    19       including ETI. As can be seen, ETI is projecting load growth through the year 2029.
    20       On average, ETI's projected annual growth is about 2%, which translates into about
    21       80 MW per year. Over the next five years, projected load growth will average nearly
    22       74 MW per year.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    23
    Jeffry Pollock
    Supplemental Direct
    Page 23
    1    Q        WOULD THE ADDITIONAL REVENUES DERIVED FROM ETI'S PROJECTED
    2              LOAD GROWTH MORE THAN OFFSET ETI'S CLAIMED LOST REVENUES?
    3    A         Yes. This is shown in Exhibit JP-4. The starting point for the analysis is the lost
    4              revenues per kW calculated in ETI's Exhibit PRM-4, line 6.         Assuming that the
    5              maximum 150 MW of load were to subscribe to CGS service, ETI would calculate
    6              annual lost revenues at $4.8 million at current rates {line 2).       However, each
    7              additional kilowatt of load would generate $6.84 per kW of additional capacity-related
    8             revenue (line 3). At this rate, ETI would have to experience only 58 MW of load
    9             growth to fully offset the lost revenues (line 4 ).
    10   Q         WOULD THE RESULTS CHANGE MATERIALLY IF THE RATES THAT ETI IS
    11             PROPOSING TO IMPLEMENT IN ITS PENDING RATE CASE WERE ADOPTED?
    12   A         No. For illustration only, I have also analyzed the impact if the rates proposed in
    13             ETI's pending rate case (Docket No. 39896) were adopted.            As can be seen,
    14             revenues from projected annual load growth would exceed the projected loss of
    15             revenues from 150 MW of CGS service.
    16   Q         WHAT REASON DID ETI GIVE FOR NOT OFFSETTING ITS LOST REVENUES
    17             WITH REVENUES FROM LOAD GROWTH?
    18   A         Mr. May asserts that "Load growth is not a concept that can be appropriately applied
    19             within the context that rates are set in Texas based upon an historical test year with
    20             known and measureable costs.'.s However, Mr. May's assertion is inconsistent with
    21             ETI's lost revenue approach, which would make an out-of-test-year adjustment by
    8
    Supplemental Testimony of Phillip R. May at 12.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    24
    -------------------------------------------------
    Jeffry Pollock
    Supplemental Direct
    Page 24
    1        quantifying its change in revenues resulting from loads that convert to CGS.
    2        Equating lost revenues with unrecovered costs is wrong in the first place, but even if
    3        one accepted that hypothetical, ETI's approach fails to recognize offsetting changes,
    4         such as load growth.
    5   Q     DO YOU AGREE WITH MR. MAY THAT LOAD GROWTH IS ONLY OFFSETTING
    6         INCREMENTALCOSTS?
    7   A     Yes.   However, that is exactly what .a load growth offset to lost revenues would
    8         accomplish. As shown by Exhibit PRM-4, ETI is asserting that CGS is creating a net
    9         incremental cost of between $2.64 and $3.54        per kW month.      It is, therefore,
    10         appropriate to recognize how load growth can offset this incremental cost.
    11   Other Offsetting Cost Savings
    12   Q     ARE THERE ANY OTHER OFFSETTING COST SAVINGS FROM THE CGS
    13         PROGRAM?
    14   A     Yes.   Because a CGS Customer is effectively self-supplying generation that ETI
    15         does not have to procure, operate and maintain, ETI can utilize existing generation
    16         resources to serve both existing and new non-CGS loads. This, in turn, would allow
    17         ETI to defer or displace additional generation capacity that would be needed to
    18         maintain reliable service. As discussed later, ETI is short of capacity; specifically
    19         base-load capacity. The CGS Program can provide the needed base-load capacity
    20         at a lower cost than the alternatives.
    3. Unrecovered Costs From the CGS Program
    J. POLLOCK
    INCORPORATED
    25
    Jeffry Pollock
    Supplemental Direct
    Page 25
    1    Q      DOES ETI'S LOST REVENUE APPROACH RECOGNIZE HOW THE CGS
    2           PROGRAM COULD POTENTIALLY OFFSET THE NEED FOR NEW BASE-LOAD
    3           CAPACITY AND PRODUCE OPERATING SAVINGS?
    4    A      No, it does not. ETI has a significant supply deficit. This is shown in Exhibit JP-5,
    5           which is an excerpt from Entergy's 2009 Strategic Resource Plan (SRP).                  The
    6           supply deficit is shown for each different capacity supply role; that is, Base Load,
    7          Core Load Following, Seasonal Load Following, and Peaking Plus Reserves.                  As
    8          can be seen, ETI's total deficit is about 978 MW. However, its total deficit of base-
    9          load supply is 969 MW.         Thus, ETI's supply deficit is almost entirely base-load
    10          capacity. If CGS can be counted as firm capacity, it can reduce ETI's base-load
    11           capacity deficit.
    12   Q      WHAT CONDITIONS MUST CGS SUPPLY MEET IN ORDER TO BE COUNTED
    13           AS FIRM CAPACITY?
    14   A       At a minimum, a CGS Supplier must enter into a contract with ETI to provide CGS
    15           capacity on a 24x7 basis, except when the supplier's resource is not physically
    16           available. Further, the CGS Supplier must obtain the status of a network resource
    17           under Entergy's OATT. And finally, the CGS Supplier must make the necessary
    18           arrangements to ensure that there is adequate transmission to support any CGS
    19           contract for the duration of the proposed contract. 9 Assuming all of these minimum
    20           conditions are met, there is no legitimate reason for not treating the CGS Supply as
    21           firm capacity.
    9
    I have observed that several of ETI's Purchased Power Agreements obligate ETI (and not the seller)
    to obtain network transmission service.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    26
    Jeffry Pollock
    Supplemental Direct
    Page 26
    1    Q         WHY DO YOU ASSERT THAT CGS SUPPLY IS A MORE ECONOMICAL
    2              RESOURCE THAN BASE-LOAD CAPACITY THAT ETI WOULD OTHERWISE
    3              NEED IN THE ABSENCE OF CGS?
    4    A         The SRP identifies a combined cycle gas turbine (CCGT) as the best option for
    5              meeting the Entergy system's base-load capacity deficit. 10 The estimated installed
    6              cost and levelized fixed cost of new CCGT capacity is provided in Exhibit JP-6.
    7                     The information was obtained from a variety of different sources, including
    8             the Entergy SRP, Ninemile Unit 6 (a capacity addition planned by Entergy Louisiana,
    9             LLC), and the Energy Information Administration (EIA). As can be seen, the installed
    10             costs range from $1 ,235 to $1 ,280 per kW. Using the same levelized fixed charge
    11             rate that Entergy uses in evaluating self-build generation options, the range of
    12             levelized annual fixed cost would be $168 to $177 per kW-Year ($13.99 to $14.74
    13             per kW-Month). The embedded generation capacity cost reflected in current rates is
    14             $82 per kW-Year ($6.84 per kW-Month). Thus, adding self-build base-load capacity
    15             will drive rates up for all ETI customers.
    16   Q         HAS THE COMMISSION EMPLOYED A SIMILAR GENERATION PROXY IN
    17             DETERMINING        THE    COST     EFFECTIVENESS          OF   ENERGY    EFFICIENCY
    18             PROGRAMS?
    19   A         Yes. In Subst. R. 25.183(b)(2) the Commission has established a capacity benefit of
    20             energy efficiency programs of $80 per kW-Year or $6.66 per kW-Month. Although
    21             this proxy is based on the cost of typically lower-cost peaking capacity (and is
    10
    Entergy System Planning & Operations, 2009 Strategic Resource Plan at 1-10.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    27
    Jeffry Pollock
    Supplemental Direct
    Page 27
    1        therefore not directly comparable to CGS Supply, which is base-load capacity), it is
    2        clearly comparable to the generation capacity charges included currently in base
    3        rates that ETI uses as the starting point for its lost revenue calculations.
    4    Q   YOU PREVIOUSLY MENTIONED THAT ETI TREATS THE LOWER PAYMENTS
    5        UNDER SCHEDULE MSS-1 AS AN OFFSET TO LOST REVENUES. WHAT IS
    6        SCHEDULE MSS-1?
    7    A   Schedule MSS-1 is a FERC approved tariff that "equalizes" reserve capacity
    8        throughout the Entergy system.         Each operating company is required to have
    9       sufficient capacity to meet its firm load obligation. An operating company that does
    10       not have sufficient capacity to meet its firm load obligation is said to have a "deficit,"
    11       while an operating company with more capacity than is needed to meet its firm load
    12       obligation is said to have a "surplus." Under Schedule MSS-1, the deficit companies
    13       make a reserve equalization payment to the surplus companies.                  The reserve
    14       equalization payment is based on the embedded cost of the older steam units on the
    15       Entergy System that are designated as reserve capacity. The sum of the payments
    16       by the deficit companies equals the sum of the receipts by the surplus companies.
    17       Thus, Schedule MSS-1 is a transfer payment between the Entergy operating
    18       companies.
    19   Q   DOES ENTERGY TEXAS HAVE A SURPLUS OR A DEFICIT OF RESERVE
    20       CAPACITY?
    21   A   ETI is a deficit company.      Thus, it makes reserve equalization payments to the
    22       surplus operating companies.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    28
    Jeffry Pollock
    Supplemental Direct
    Page 28
    1   Q         HOW WOULD THE CGS PROGRAM AFFECT THE AMOUNT OF RESERVE
    2              EQUALIZATION PAYMENTS THAT ETI MAKES UNDER SCHEDULE MSS-1?
    3   A         If the CGS Suppliers are counted as firm resources, it will decrease ETI's reserve
    4              capacity deficit, which in turn will reduce the amount of reserve equalization
    5             payments.     For this reason, ETI recognizes this reduction as an offset to lost
    6             revenues.
    7   Q         DOES THAT MAKE SCHEDULE MSS-1 A PROXY FOR THE VALUE OF CGS
    8             CAPACITY?
    9   A         No.   As previously stated, the Schedule MSS-1 charges are a transfer payment
    10             between the Entergy operating companies for existing generation capacity
    11             resources. CGS, by contrast, would be a new system resource. Further, CGS would
    12             be a 24x7 base-load resource, while Schedule MSS-1 is based on the cost of
    13             existing reserve capacity, which is comprised of peaking resources that are used
    14             infrequently. Thus, it would be incorrect to use the Schedule MSS-1 rate (which
    15             reflects the cost of existing peaking capacity resources) to value CGS Power (which
    16             is an incremental base-load resource).
    17                     Further, Entergy does not take its MSS-1 costs into account for resource
    18             planning purposes. That is, when planning to meet ETI's resource needs through
    19             either a purchase power agreement (PPA) or other resource, MSS-1 costs are not
    20             considered. 11
    11
    Docket No. 37744, Deposition of Robert Cooper at 24-25.
    3. Unrecovered Costs From the CGS Program
    J. POLLOCK
    INCORPORATED
    29
    Jeffry Pollock
    Supplemental Direct
    Page 29
    1    Q   IF SCHEDULE MSS-1 IS A PROXY FOR THE INCREMENTAL COST OF
    2        CAPACITY, WOULD IT EVER MAKE ECONOMIC SENSE FOR ETI TO ENTER
    3        INTO PURCHASED POWER AGREEMENTS THAT WERE MORE EXPENSIVE
    4        THAN THE MSS-1 RATE?
    5    A   No, because this presumes Ell's incremental cost of capacity is the MSS-1 rate. In
    6        fact, ETI is paying higher demand charges (substantially higher in some PPAs) than
    7        $3.73 per kW-Month, which is the current Schedule MSS-1 rate as shown in Exhibit
    8       PRM-3. If the value of capacity was only $3.73 per kW, it is unlikely that these PPAs
    9       would be considered prudent.
    10   Q   PLEASE SUMMARIZE YOUR ANALYSIS OF THE COST OF CGS SUPPLY
    11       RELATIVE TO THE ALTERNATIVES.
    12   A   ETI's lost revenues approach assumes that the cost of CGS Supply would be equal
    13       to ETI's embedded generation capacity costs or $82 per kW-Year ($6.84 per kW-
    14       Month x 12). Put another way, it is ETI's position that even though the parties have
    15       agreed that the CGS Customer will pay for its own capacity pursuant to the CGS
    16       Customer-Supplier Agreement, ETI's capacity costs for the CGS Program will be at
    17       least equal to $6.84 per kW-Month (before offsets).       However, as demonstrated
    18       above, the cost of alternative capacity resources that would offset its projected base-
    19       load capacity deficit would be $14 or more per kW-Month, which is substantially
    20       above ETI's embedded generation capacity costs.              Thus, from a capacity
    21       perspective, CGS power can be a lower cost option for ETI than the base-load
    22       resources ETI would otherwise need to meet its projected capacity.
    3. Unrecovered Costs From the CGS Program
    J. POLLOCK
    INCORPORATED
    30
    Jeffry Pollock
    Supplemental Direct
    Page 30
    1    Q         HAVE YOU REVIEWED THE TESTIMONY OF ANDREW J. O'BRIEN ON BEHALF
    2              OF ETI?
    3    A         Yes.    Mr. O'Brien contends (on pages 7-8) that CGS Supply will have little or no
    4              capacity value.
    5    Q         DO YOU AGREE WITH MR. O'BRIEN'S ANALYSIS?
    'I
    6    A         No. Mr. O'Brien has clearly 'undervalued the capacity benefits of CGS power. First,
    7              it should be noted that Mr. O'Brien makes this claim with respect to CGS power, but
    8             ETI admits that it has done no comparison of the value of CGS power to its existing
    9             purchase power contracts. 12      Mr. O'Brien's testimony should be given very little
    10             weight for this reason. Second, Mr. O'Brien's analysis ignores the specific supply
    11             role that a particular resource (such as CGS) may be selected to provide.              As
    12             previously stated, Entergy defines four major supply roles:
    13                 •    Base Load;
    14                 •    Core Load Following;
    15                 •    Seasonal Load Following; and
    16                 •    Peaking Plus Reserves.
    17             It is reasonable to expect that each different type of resource will possess the
    18             characteristics required to meet its specific supply role. In other words, a particular
    19             resource need not possess every attribute identified in Mr. O'Brien's testimony to be
    20             of value.
    21                      For example, with regard to flexibility, Mr. O'Brien asserts that CGS capacity
    22             has no flexibility, it cannot be cycled or used to follow load variations or controlled by
    12
    ETI's Response to TIEC 1-2.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    31
    Jeffry Pollock
    Supplemental Direct
    Page 31
    1              the Entergy System Operator. 13 These limitations would be of concern if CGS power
    2              was intended to be a load following product.      It is not a concern for a base-load
    3              product. As such, CGS power is similar to a nuclear plant. A nuclear plant will either
    4              be totally on or totally off. As long as a nuclear plant is capable of operating at full
    5              output, there would never be a reason for the System Operator to change the
    6              dispatch of the plant. Further, it is unclear how Mr. O'Brien accounts for the fact that
    7              the Entergy System Operator will be able to order the CGS Supplier to curtail or not
    8              operate during system emergencies, the same as other network resources.
    9    Q         WOULD THE UNIT CONTINGENT NATURE OF CGS CAPACITY MAKE IT LESS
    10             VALUABLE THAN OTHER ETI RESOURCES?
    11   A         No, not necessarily. Mr. O'Brien asserts that CGS would be less firm than other
    12             resources. However, he has provided no analysis to support his assertion. Further,
    13             his concern about the "priority" of the host loads behind all QFs (including the QFs
    14             that sell unit contingent power to ETI) is misplaced. This is because the failure to
    15             achieve the required performance can be costly.        The CGS Supplier will not be
    16             immune from performance risk.
    17                     The 24x7 nature of the CGS product will require the CGS Supplier to commit
    18             only the amount of capacity that can meet a high level of performance. Further, as
    19             previously stated, the CGS Supplier is obligated to achieve an 80% capacity factor
    20             during on-peak hours.      Failure to do so would subject the CGS Customer to
    21             additional costs and potentially trigger liquidated damage charges.
    13
    ETI's Response to TIEC 1-1.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    32
    Jeffry Pollock
    Supplemental Direct
    Page 32
    1    Q   HAS ENTERGY ENTERED INTO SHORT-TERM UNIT CONTRACTS?
    2    A   Yes.    ETI has entered into numerous unit contingent contracts, including both
    3        affiliates and third party contracts. Exhibit JP-7 is a list of the currently effective unit
    4        contingent contracts and the term of each separate transaction. As can be seen,
    5        most of these unit contingent transactions have terms as short as one to three years.
    6    Q   DO MR. O'BRIEN'S CONCERNS ABOUT THE MINIMUM SIZE OF A CGS
    7        CONTRACT HAVE MERIT?
    8    A   No.     The CGS Program is essentially being offered as a pilot.              Accordingly,
    9        limitations have been placed on the scope of the program, including the eligible
    10        suppliers and the maximum amount of CGS load.                 It is unclear that potential
    11        customers would want to risk a significant amount of load without first gaining more
    12        experience.
    13                 However, the initial offering could result in up to 150 MW of firm base-load
    14        capacity. This is comparable in size to the majority of ETI's unit contingent contracts,
    ·15       as shown in Exhibit JP-7.
    16                 If the pilot is a success, there is no reason not to expect customers to commit
    17        more of their load to CGS and potentially enter into longer term contracts.
    18    Q   DO YOU AGREE WITH MR. O'BRIEN'S RANKING OF CGS RELATIVE TO
    19        ENERGY COST?
    20    A   No. The moderate ranking is based on the fact that CGS energy is priced at avoided
    21        cost.   However, Mr. O'Brien ignores that the CGS Customer will be paying ETI
    22        avoided cost for every kWh purchased by ETI from the CGS Supplier and resold to
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    33
    Jeffry Pollock
    Supplemental Direct
    Page 33
    1          the customer. Thus, the CGS Program will have a "zero" net energy cost to ETI's
    2           customers. Even base-load units have some positive energy cost. For this reason,
    3           CGS should be ranked as "highly valuable" with respect to energy cost.
    4    Q      DOES THE LOCATION OF CGS SUPPLY DIMINISH ITS VALUE?
    5   A      No. Ideally, resources should be located close to the loads they serve. The CGS
    6           Supply will be located in ETI's service area. This service area is within the WOTAB
    7           planning region, which is considered a capacity-constrained region. 14
    8   Q       DOES ETI PURCHASE CAPACITY THAT IS LOCATED OUTSIDE OF WOTAB?
    9   A      Yes. For example, the resources supporting the EAI-WBL are located outside of
    10           WOTAB. This fact has not diminished ETI's willingness to pay a high price for this
    11           capacity.
    12   Q       DOES MR. O'BRIEN'S TESTIMONY PLACE A HIGH VALUE ON ANY ASPECT
    13           OF CGS SUPPLY?
    14   A       Yes. His testimony ascribes a high value on firming up QF Puts. As discussed
    15           below, firming up the QF Puts would reduce the need for flexible capacity and lower
    16           operating costs.
    14
    Entergy System Planning & Operations, 2009 Strategic Resource Plan at 2-10. The WOTAB
    planning region is the area generally west of the Baton Rouge, Louisiana metropolitan area, to the
    westernmost portion of Entergy's service territory in Texas. The westernmost portion ofWOTAB is
    the Western area (a sub-area), which encompasses the westernmost part of ETI's service territory,
    generally west of the Trinity River.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    34
    Jeffry Pollock
    Supplemental Direct
    Page 34
    1    Q          WHAT IS A QF PUT?
    2    A          A QF Put is when a Qualifying Facility generates excess energy that cannot be
    3               otherwise used by the OF's host load. This excess energy is "put" to the Entergy
    4               system. QF Puts are unscheduled, and they are also highly variable. According to
    5               Entergy, in 2008 QF Puts change an average of 182 MW or more during a one hour
    6               period and 891 MW in a 24-hour period.          Five percent of the time, the QF Put
    7               changed by 1,674 MW or more during a 24-hour period. 15
    8    Q          IS THERE A COST INCURRED BY ENTERGY TO MANAGE QF PUTS?
    9    A          Yes. Entergy says it incurs significant costs to manage QF Puts. For example:
    10                       The amount of energy put to the System by Qualifying Facilities (QFs)
    11                       varies significantly from minute-to-minute and hour-to-hour.
    12                       Changes in the injection or retraction of QF Put energy require
    13                       the System to have a substantial amount of flexible load
    14                       following capacity ready and available to the System Dispatcher
    15                       to increase or decrease System generation so that changes in
    16                       QF puts can be managed without compromising reliability. 16
    17                       (emphasis added)
    18   Q          HOW MUCH FLEXIBLE CAPACITY DOES ENTERGY SAY IT REQUIRES?
    19   A          According to Entergy:
    20                       The amount of flexible capacity that must be operating in any
    21                       particular time is typically on the order of 4,000 to 6,000 MWs. At
    22                       times during the year, the amount of flexible capacity that must be
    23                       committed can be as much as 9,000 MWs. 17
    15
    /d. at 7-13.
    16   /d.
    17
    /d. at 8-8.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    35
    Jeffry Pollock
    Supplemental Direct
    Page 35
    1   Q   WOULD CGS FIRM-UP THE QF PUTS?
    2    A   Yes. CGS could eliminate up to 150 MW of QF Puts. By reducing the QF Puts, the
    3       system should require less flexible capacity and incur lower operating costs.
    4   Q   HAS THE ENTERGY SYSTEM HAD EXPERIENCE WITH FIRMING-UP QF
    5       CAPACITY?
    6   A   Yes.   In November 2008 Entergy Gulf States Louisiana, LLC (EGSL) sought
    7       approval of a three-year contract with Calpine for the purchase of 485 MW of
    8       capacity.   The generation facility was part of a QF.     In supporting the proposed
    9       contract, EGSL cited a number of benefits:
    10              Q.    DOES THE ECONOMIC ANALYSIS INCLUDE ANY BENEFITS
    11              ASSOCIATED WITH FIRMING UP THE QF PUT CURRENTLY
    12              ASSOCIATED WITH THE CARVILLE FACILITY AND REDUCING
    13              THE OPERATIONAL FLEXIBILITY REQUIREMENTS?
    14              A.   No. As a QF, the Carville Facility otherwise has the right to "put"
    15              non-firm, as-available energy to the Company and be paid the
    16              Company's avoided cost for that energy, subject to certain limitations
    17              provided for in PURPA and the Federal Energy Regulatory
    18              Commission's ("FERC") implementing regulations and incorporated
    19              into the LPSC's Avoided Cost General Order. However, under the
    20              Calpine Contract, Calpine will not put unscheduled energy to
    21              the Company, but rather will allow the Company to "firm up" the
    22              delivery of energy associated with the capacity under contract
    23              from Calpine's generating units at the Carville Facility.           The
    24              Carville Contract provides the System dispatcher certainty
    25              about the output from the capacity under contract from the
    26              Carville Facility and effectively reduces            the    operational
    27              flexibility requirements for the System.          However, the exact
    3. Unrecovered Costs From the CGS Program
    J. POLLOCK
    INCORPORATED
    36
    Jeffry Pollock
    Supplemental Direct
    Page 36
    1                    economic value of this benefit is difficult to estimate. ESI took the
    2                     conservative approach and chose not to calculate any specific
    3                     savings associated with this benefit. It should be noted that the
    4                     benefits of firming up QF put exist during each year of the
    5                     contract term. 18 (emphasis added)
    6   Q         HAS ENTERGY QUANTIFIED THE VALUE OF FLEXIBLE CAPACITY?
    7   A
    8   Q         CAN THE CGS PROGRAM OFFSET SOME OF THE COSTS INCURRED TO
    9             PROVIDE FLEXIBLE CAPACITY?
    10   A         Yes. Firming up 150 MW of OF Puts will reduce the costs associated with flexible
    11             capacity. Based on a review of various studies presented in recent filings, I believe
    12             $2 million per year would be a conservative estimate of the lower operating costs.
    13   Q         PLEASE SUMMARIZE THE BENEFITS OF CGS SUPPLY.
    14   A         CGS can provide the needed base-load supply at a lower capacity cost than ETI's
    15             alternatives. Replacing the QF Puts with CGS will reduce the Entergy System's (and
    16             ETI's) requirements for flexible capacity, thereby resulting in lower operating costs.
    17             In summary, CGS Supply will provide significant economic benefits to all ETI
    18             customers. These economic benefits are ignored in ETI's lost revenue analysis.
    18
    LPSC Docket No. U-28805 Subdocket B: In Re: Application of Entergy Gulf States Louisiana,
    L.L.C. for Authorization to Participate in a Contract for the Purchase of Capacity and Electric Power
    from Calpine Energy Services, L.P. and Carville Energy Center, LLC; November 25, 2008,
    Application at 17-18.
    19
    ETI's Response to TIEC 1-3.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    37
    Jeffry Pollock
    Supplemental Direct
    Page 37
    1   Q   SHOULD LOST REVENUES BE INCLUDED AS UNRECOVERED COSTS?
    2    A   No. For all of the reasons cited, including Commission and court precedent rejecting
    3        lost revenues as a "cost," the similar impacts between CGS Program, self-
    4        generation, and energy efficiency, and Ell's failure to recognize load growth and the
    5       potential economic benefits of the CGS Program, the Commission should reject
    6       ETI's definition of unrecovered costs.   The only legitimate unrecovered costs are
    7       those associated with start-up, on-going implementation, and backup power. As
    8       these costs will be paid by the CGS Customers, there would be no unrecovered
    9       costs associated with the CGS Program.
    10   Q   IF THE COMMISSION DECIDES THAT Ell'S UNRECOVERED COSTS SHOULD
    11       INCLUDE      LOST     REVENUES,      HOW       SHOULD     LOST     REVENUES       BE
    12       QUANTIFIED?
    13   A   I would recommend modifying ETI's lost revenue analysis as follows:
    14          •   Lost revenues shown in Exhibit PRM-4 should only be calculated for
    15              loads that actually purchased generation services from ETI. This
    16              excludes new customers, new loads of existing customers, self-
    17              generation displacement, and inactive loads that are brought back on
    18              line that would otherwise not have purchased electricity from ETI
    19              absent the CGS Program. This would recognize that ETI did not
    20              provide generation services under each of these scenarios.
    21          •   Lost revenues should be further offset by load growth and any other
    22              quantifiable benefits of CGS (e.g., capacity deferral, lower operating
    23              costs).
    24       As previously stated, ETI is projecting sufficient load growth to more than offset any
    25       lost revenues even before consideration of any other quantifiable benefits.
    26       Recognizing these other benefits clearly demonstrates the overall benefits of the
    27       CGS Program and that ETI would have zero unrecovered costs.
    3. Unrecovered Costs From the CGS Program
    J.POLLOCK
    INCORPORATED
    38